WORK METHOD STAEMENT FOR HANDRAIL

SCOPE OF WORK
This procedure covers the methodology to be followed for carrying out Handrail in line with the
approved technical specifications.

MATERIALS
MS pipe, MS Bends, Anchor fastener, MS Base plate,

EQUPIMENTS AND TOOLS


Welding machine, cutting machine, SS buffing machine.

PREPARTORY WORKS
 Check the civil plastering works are completed.
 Check the open well width by drop the plumb from the top floor to check the center of stairs it
should be equally divided.
 All the welding joints are checked properly for any excess welding flux deposits. Grinding is done
so as to give such junction uniform appearance.
 Staircase marking should be done with respect to the meter marking.

WORK METHODOLOGY

 Mark the location of MS base plate and drill the holes for anchor bolts.
 Now the threaded anchor bolts are driven into the holes, ensure that they firmly fixed.
 Base plate is fixed on to the anchor bolts using nuts.
 The number of anchor bolts to be used for fastening and the size of base plate is as per drawing
and requirements.
 A button mark of thickness equal to FFL level is made on the 1st and last step on the each flight so
as to check the height of the staircase railing with respect to the FFL.
 Once the FFL is fixed. The staircase railing of the first flight of the staircase is held it place.
 Then the railing for the flight is placed on position and the bottoms of the balusters are welded to
the center of the fixed base plate.
 Sufficient gap should be provide for the railings from the edges of the staircase, consider the offset
of stone finishing.
 Check the top rail from FFL should be as per drawing.
 All the bends should be smooth without any welding flux.
 Apply red-oxide primer and apply approved colour of two coats enamel spray painting.