Escolar Documentos
Profissional Documentos
Cultura Documentos
CONSTRUCTION TECHNOLOGY 1
BASEMENT
CONSTRUCTION
WHAT IS BASEMENT…
A basement is a storey or several stories
of a building that are either completely or
partially below the ground floor.
Not all buildings have basements.
For buildings with basements, the furnace,
water heater, car park and air-conditioning
system of a house or building are typically
located in the basement; so also are
amenities such as the electrical
distribution system, and cable television
distribution point.
Basement Grades (BS 8102)
Grade Possible Use Conditions Required Moisture Exclusion
Grade 1: Car parking, >65% relative humidity Minor wet seepage and
Basic Utility Mechanical plant 15-32oC temperature visible damp patches
rooms may be acceptable.
laboratory testing
Evaluation of foundation of adjacent
OPEN-CUT CONSTRUCTION
CUT AND COVER
CONSTRUCTION
BOTTOM UP
TOP DOWN CONSTRUCTION
OPEN-CUT
CONSTRUCTION
For all excavations, operators must know:
the line;
the final depth of the excavation;
the approximate width of the excavation
Open excavation
with sloping sides
(if constraints of
space on the site
permits)
Angle of slope
nature of soil +
moisture content
Construction Method for Deep
Basement
Open excavation is not suitable:
Extent of excavation required around the
Use:
excavation with temporary support
Excavation supported by permanent retaining
36
Overall construction method: typically top
down, bottom upwards or semi top-down.
Wall method. (temporary, permanent or
both)
king post walls
steel sheet piling
soil mix columns
r.c. contiguous piles
r.c. secant piles (hard/hard, hard/soft)
diaphragm walls
Wall selection
King post walls. Timber laggings allowed to slide
downwards between king posts. Poor
tolerances, loss of ground.
Sheet piling. poor tolerances, Split clutches due
to obstructions.
Contiguous piles, secant piles. wasting of pile
shafts. Overbreak.
Diaphragm walls. Slurry inclusions, poor joints,
poor cover to steel,bleed, poor tolerances,
inclusions at toe of walls.
Contiguous Piled Wall - 750mm diameter at 900mm Centres
Plunge Columns - Sequence
rig boring wall piles Secant Walls and Columns
Diaphragm Wall Excavation
Reinforcing Cage Installation
Guide wall Construction for piling
The hard / hard secant piled wall,
consisted of 304 piles, 1180mm
diameter at 1950mm spacing up to
31m long. The secant piling formed the
lower part of the wall, with a new in-situ
concrete retaining wall up to 1m thick
built over the top. A steel beam was
cast into every third pile designed to
extend 7m above the pile cut off level
into the existing basement. Short flat
jack props were placed horizontally in
the narrow gap between the beams and
the existing wall, to aid the eventual
demolition of the old wall. During the
development of the site, six existing
piles from the previous structure to
occupy the site were incorporated into
the wall. Water tightness was ensured
between these and the new piles by
injection grouting.
Schematic of Construction Sequence
for hard secant piled wall
Completed Hard / Hard Secant Piled Wall
Top-Down Construction
1. Formation of permanent retaining
walls to the perimeter of
basement area.
2. Form internal foundation and
column support by using plunge
method.
3. Create the uppermost floor slab
(with temporary base)
4. Excavate downwards tru
openings on slab or service
shafts
5. Remove temp. base, excavate
until the depth of next floor level.
6. Cast the next floor level, repeat
the process.
7. Can use non-suspended slab for
the basement slab.
Typical sequence of top down
construction
2) Install bearing piles with plunge columns
3) Cast ground floor slab
4) Excavate and cast upper
basement floor slab.