Escolar Documentos
Profissional Documentos
Cultura Documentos
Need
Field Sales Lead
Keyspan Energy needs to install four 69kV
Joe Fani - Burgoyne
substations allowing local gas generation to
Dick Molnar-ABB Field
be on line before the summer peak of 2002.
Sales
In-house resources not available.
Solution
ABB’s MODULA concept allows delivery of
permit-drawings in 5 weeks!
Compact footprint allows flexibility in site
selection
First units scheduled for delivered to site in 4
months!
Benefits
Keyspan able to meet deadline and satisfy
local customers
ABB Modular design is more cost efficient
than traditional internal solution
Customer Resource and Time Constraint Solution at
Grand Bahama Power
Need
Shipcare facility required power in 8
months
GBP desired ease of expansion
with minimum energization outages
Solution
Modular approach met all of GBP’s
desired objectives
Tesco’s relationship achieved a sole
sourced negotiation
Benefits
Grand Bahama met the Shipcare
power delivery requirement
Training of new GBP personnel
Standardization for future Subs
10 MVA 69/12kV Modular Substation
Status
Phase II being installed
Time and Resource Constraint Solution-Walgreens
Need
Central Warehouse Facility operating
by March 2002
115/12.5kv Substation in service
within 6 months
Solution
ABB’s pre-designed substation PS-1
concept met budget and saved 6
months off utilities completion time
Benefit
PS1 Modular design will allow Facility
operation on schedule
Cost savings from better terms
Status
Commissioned 1/30/02
Energization: 2/10/02
Transmission Constraint Solution - Georgia Pacific
Need
Georgia Pacific needed additional electrical
capacity when expanding the paper mill in
Virginia
Transmission Line, S/S, Distribution Line
Solution
ABB built short power line to connect to 69kV
network instead of 13.8kV
ABB’s modular substation concept PS-1 met
the budget and improved the completion time
by 3 months
Benefits
GP’s received lower rates when buying
energy @ 69kV
The 69kV connection allowed
higher capacity and reliability
115/15kV Substation Solution-Borg Warner
Need
10MVA Power at 115/15kv
Energize in 6 months
Meet Budget Price
Solution
ABB delivered a complete
modular turnkey substation in
6 months and at budget price
Benefits
Speed: 6 month to Energize
Cost: Minimum Labor on Site
Price: Competitive
Lower energy cost at 115kv
results in substation cost
recovered after 5 years
Case Study -Multiple Wind Parks in Texas
Need
Energize 3- 115/34.5kv
substations in 6 months, 3 more
in another 6 months
Solution
ABB’s pre-designed modular
substation concept met the
budget and schedule
Benefit
RES completed the wind farms
in time to energize on schedule
and receive tax credits
Case Studies Tractebel - Hot Spring
Need
Small Site Footprint
Difficult Interconnecting
Schedule
Solution
ABB GIS to Minimize Space
Trained Preferred
Subcontractor on GIS
Installation Techniques
Worked with Customer and
Interconnecting Utility to
Develop Optimal Approach
Benefits
Project Completed On
Schedule
Interconnecting Utility Buy-in
on Interconnect
Case Studies Tractebel - Choctaw
Need
High Site Land Prep Costs
High Reliability
Project Budgets
Solution
ABB AIS vs GIS Reliability
Analysis
ABB AIS vs. GIS Total Life
Cycle Cost Analysis
CGIT to Eliminate all AIS and
Minimize Footprint
Benefits
Lower LCC Than AIS
Project Completed on Time
Major Land Development
Costs Saved
Case Studies TVA - Pinhook
Need
High Site Land Prep Costs
due to Extremely Rocky Soil
Desire to Avoid Leakage
Problems of Previous
Generations of GIS
Desire to Buy from a Familiar
Source
Solution
Reduced Substation Footprint
via GIS
Cost Effective Indoor
Substation Proposed to
Address Leakage Issue
Benefits
Major Land Development Cost
Savings
Leakage Issues Addressed
Case Studies TVA - Maury
Need
Replace Aging GIS Substation
Aggressive Cut In Schedule
Improved Substation
Functionality
Solution
ABB GIS to Upgrade Existing
ITE Substation
Creative Layout Changes to
Facilitate Cut In Schedule and
Improve Substation
Expandability
Benefits
New, Improved GIS
Improved Functionality
Met Cut In Schedule
Case Studies Austin Energy - Harris
Need
Very Small Site Footprint
Aesthetically pleasing due
University concerns
Single source of responsibility
Flexibility with design
Solution
ABB GIS in small bldg.
Coordination with Univ. and
AE with multiple equipment
Extensive civil works under
ABB control
Met AE equipment stds.
Benefits
Met small footprint needs
Competitive turnkey pricing
Met AE equipment stds.
Interface directly to ABB
Ranger system for AE
Univ. has single point of
control
Case Studies City of Burbank - Capon
Need
Difficult Customer (Warner Bros.)
Aesthetics, Space, Time, Quality
Project Execution a Key
Solution
ABB Optimized Spec
Strong Project Manager
Previous Successes with MV GIS
Benefits
No Complaints from Warner Bros.
No Scope Changes
Project Completed One Month
Early
Case Studies City of Burbank – Hollywood Way
Need
Downtown Location
Critical Schedule
Freeway Off Ramp
Solution
Negotiated Project
Off Ramp Added to Scope
“No Scope Change”
Commitment
Same Team as Capon
Benefits
Substation Project Completed
On Time
In Spite of Surprises from
CalTrans and PacBell
Case Studies Commonwealth Edison
Need
Small downtown site
Architecturally pleasing to
neighborhood
Site coordination/permits
Reliability/quality/safety
Short timeframe
Solution
GIS w/ small footprints
Upgradeable from 69 to
138kV
Capture Team approach
Project schedule management
for cutover
Benefits
Substations built ahead of
schedule
Control/power cable interfaces
coordinated thru one
High safety/quality
Bristol-Myers Squibb
Need
Customers largest R&D facility
needed better reliability in their
electrical supply
Three previous outages cost
customer $7 billion dollars (Lost 3
FDA approvals)
Solution
ABB designed a highly reliable and
redundant 7 breaker 69 kV ring
bus Modular substation with 3-25
MVA transformers
Benefit
Meet customer time frame ( 8
months) and budget
No outages during the cut over
Status
Commissioned: Sept 2003
69/13 kV Modula Substation Energization: Oct 2003
San Isabel Electric Association
Need
Pueblo West load growth required
new substation to meet summer
load
115/12.47kV substation required in
service within 7 months
Project is RUS financed
Solution
ABB’s pre-designed Modular
substation met budget and saved
4 months off Coops completion
time
Benefit
Modular design allows flexibility
and future growth
Status
Commissioned: August 2003
Energization: 2 QTR 2004
115kV/12.47, 12/20/25 MVA
TXU Energy Services, Baylor
Need
138 kV to 12.47 kV 16/22.5
MVA dual transformer
installation needed in 6 months
Compact design due to limited
site space
Flexibility to add for future
Solution
ABB substation based upon
standardized PS -1 design
Total turnkey, flexible design
and short installation time frame
Benefit
Completely designed, installed,
and commissioned in 6 months
Status
Commissioned: Nov 2003
138kV to 12.47kV, 16/22.5 MVA Energization: Dec 2003
Modular Cap Bank Projects
Montana-Dakota Utilities
Hettinger Substation:
115kV, 15 MVAR two step bank
Baker Substation:
115kV, 15MVAR two step bank