Escolar Documentos
Profissional Documentos
Cultura Documentos
To cite this article: Gian Michele Calvi, Matteo Moratti, Gerard J. O'Reilly, Nicola Scattarreggia,
Ricardo Monteiro, Daniele Malomo, Paolo Martino Calvi & Rui Pinho (2018): Once upon
a Time in Italy: The Tale of the Morandi Bridge, Structural Engineering International, DOI:
10.1080/10168664.2018.1558033
Article views: 92
Fig.1: Schematic of the piers and distances between each support of the Morandi Bridge, with the three balanced systems shown to pass over
residential areas, numerous transportation lines and the Polcevera river (although not shown, the area between piers 1 and 8 is also heavily
industrialised) (Units: m)
Fig. 2: Longitudinal and transversal section of one of the “balanced systems” that constituted the large span portions of the viaduct (Units: m)
compression, while still not bonded to configuration upon mounting the 36 m responded elastically to any action
the stays, and the final “usual injec- simply supported Gerber beams and (traffic, temperature and wind,
tion” of all ducts with the definitive completing the dead weight on the whereas no mention is made to earth-
connection between cable stays and entire deck. It is evident from descrip- quakes). In addition, the stays con-
deck.22 tion and construction photos that this crete would have always been in
phase followed the casting of the con- compression (therefore not suscep-
The deck extremities were deformed crete stays and the cable injection. tible to cracking and consequent cor-
upwards by appropriately tensioning According to Morandi, in its final con- rosion potential) and stiffer (thus less
the cable stays, to obtain a straight figuration the bridge would have sensitive to fatigue problems and less
Fig. 4: Geometry and reinforcement (top) in addition to three cross-sections (bottom) of the main deck (Units: m)
Gerber beam. Fig. 10 shows this demand for the various load cases in be seen that there is a significant
demand, together with the capacity, Fig. 11. As in the case of flexure, the reserve of capacity in each loading
and it can again be seen that there is shear capacity of the main deck is well scenario investigated.
a good degree of reserve capacity in above the maximum anticipated
each loading scenario investigated. demands from both the static loading For what concerns the possible acci-
and also the seismic loading, indicating dental point load, mentioned at the
that it had sufficient reserve capacity. beginning of this Section, a preliminary
Shear Capacity of Main Deck and assessment, described in the paragraph
Supported Spans Furthermore, for the case of removal
of the stay on the left-hand side, it can below, has been carried out, leaving a
The shear capacity estimates are based be seen that the shear demand in the more refined analysis to future detailed
on a simplified version of the Modified deck over the left pier does not exceed studies, given that not only is an impact
Compression Field Theory (MCFT), the capacity, indicating that should a analysis of such a complex system and
formulated by Vecchio and Collins.33 stay be removed from the system, no the evidence very complex and time-
The MCFT represents a generalised problems would be expected as a consuming, but also because, as dis-
approach for modelling the behaviour result of the increased shear demand. cussed later, even a complete collapse
of reinforced concrete elements sub- of the supported span would hardly
jected to multi-axial loading conditions. With respect to the simply-supported
result in the global collapse of the
It consists of a smeared, rotating crack Gerber beam, the corresponding
system
model that treats stresses and strains shear force capacity profile was also
in a localised average sense, and estimated for different cross sections, Assuming a weight W tumbling on the
allows their reorientation as a result of located at 2, 9 and 18 m distance deck from a height h, the equivalent
changing load and/or material response. from the support ledge, connecting force can be estimated equating the
Similar to the case of the flexural the main deck and the simply-sup- potential energy at the beginning of
capacity, the shear resistance of the ported Gerber beam. The shear the event and at maximum displace-
main deck was computed at various capacity is depicted, together with ment (d) of the impacted section,
points and is compared with the the demand, in Fig. 12. Again, it can obtaining, assuming perfectly elastic
Fig. 10: Comparison of the flexural capacity of the simply-supported deck computed from moment-curvature analysis with the static loading
and seismic demands
response, Pe = W·h/d. In case of an capacity (in the range of hundreds of shear capacity of the ledge estimated as
elastic response and of a falling height mm). The only possible events are a 3805 kN, which corresponds to a safety
of the order of 1 m, this equivalent complete punching of the upper and factor of 4.6, when considering the
force can be in the order of ten times lower slabs, of little interest here, and shear demand due permanent loads
the tumbling weight and should be a collapse of the cantilever part of the (820 kN), but may again imply a local
further amplified to consider the deck, in proximity of the Gerber failure when considering the aforemen-
dynamic response of the structure, as saddle, which will produce similar tioned hypothetical accidental point
a function of the ratio of the duration effects to the saddle collapse itself, dis- load acting, in addition to the permanent
of the impulse and the structure cussed later. It is noted, however, that loads, at the most unfavourable location.
proper period; as well known, the if such impulsive action would
maximum amplification factor is equal damage the transverse link, it could Torsion Capacity of Main Deck
to 2. It is noted, however, that consider- have an impact in the stay-deck con-
Considering the large in-plane bending
ing the shear and flexural capacities nection, something that would instead
be of relevance, as shown later in this and torsion resulting from a potential
depicted above (Figs. 10 and 12), it
paper. stay release, the strength of the deck
results evident that a nonlinear
was also evaluated considering the sim-
response is to be expected, implying A shear verification of the support ledge, ultaneous presence of torsional, shear
damage, larger displacements and connecting the main deck and the and flexural actions. To this end, the
added energy dissipation, implying simply-supported Gerber beam, was “Variable-Angle Truss Model” pro-
that a correct estimate of the impulsive also carried out. The shear strength of posed by Rabbat and Collins34
load cannot be obtained by the simple the ledge was estimated using two implemented in the CSA A23.3-1435
use of the equation described above, approaches: i) strut-and-tie method, to was employed. In this model, the cross
valid only in the elastic domain. ensure that no crushing of the diagonal section is idealised using four parallel
A collapse induced by an impulsive struts or failure of the ties (in this case longitudinal chords, made of longitudi-
load on the main deck has to be represented by the cables) would occur; nal pre-stressing steel, reinforcing bars
excluded, considering its large shear and ii) interface shear transfer equations, and concrete. The chords are connected
strength (in the range of 50 MN, Fig. to ensure that no interface failure would by four “walls”, consisting of diagonally
11) and considerable displacement occur. These calculations resulted in a cracked concrete and transverse
Fig. 12: Comparison of the shear capacity of the simply-supported deck computed using MCFT with the static loading and seismic demands
reinforcement. Moment and axial forces compression forces resulting from the maximum value of ν=0.11. These
acting on the cross section are resisted by in-plane bending moment. Therefore, values suggest that for both normal
axial stresses that arise in the chords, a torsional failure of the deck following and seismic loading conditions,
while shears and torsions acting on the the rupture of the stays on one side rep- neither the pier nor the antenna
cross section are resisted by shear flows resents a plausible sequence of events. exhibit any cases of relatively large
that develop in the walls. In performing loading nor would they have presented
the calculations, a simplifying assump- Seismic Capacity of Pier and any alarming results had a seismic ver-
tion was made that is the shear flow gen- Antenna ification been examined.
erated by an applied torque was In addition to the deck elements, the
assumed to distribute only along the per- Summary and Preliminary
forces acting in the antenna were also
imeter of the cross section, thus weight- Conclusions
checked to ensure that it too possessed
ing only on the flanges and on the two sufficient reserve capacity for the situ- An examination of the outcomes of the
most outer webs. ations examined here. For the static analyses and verifications described
loading with the self-weight and above already allows one to derive a
As before, the torsional capacity was
live loads, the vertical force acting number of preliminary considerations.
computed for a number of sections
through each antenna leg is found to In general, the “balanced system”, as
along the main deck, as shown in
be 27 100 kN, which when considering conceived and designed, appears to
Fig. 13. For what concerns the torsional
the cross section to be 4.5 × 0.9 m, have had significant capacity reserves,
demand, Section 4.1.1 reported that
gives an axial load ratio of ν≈0.18, com- as demonstrated by the large force/
upon the removal of one of the stays,
puted as the axial load normalised by moment capacity-demand ratios in
the forces increased from a balanced
the product of the gross cross-sectional flexure, shear and torsion mechanisms.
22 600 kN in each stay to about
area and concrete compressive strength,
39 000 kN in a single stay. Considering Indeed, and more specifically, it seems
taken as 37 MPa. For the case when the
that the upward force in the remaining that the complete loss of a stay could
whole stay is removed on the south side,
stay is now unbalanced, this would be have resulted in the type of complete
the forces acting through on the
anticipated to translate as a torsional collapse that was observed, given that:
antenna legs on the same side reduce,
force in the main deck. Taking the verti-
with the opposite legs being compressed
cal component of this 39 000 kN axial . The flexural and shear capacities of
further. The maximum compressive
force as half, given the stays are inclined the deck are in the range of two or
load through the antenna legs on the
at approximately 30°, and multiplying more times the demand under
north side increases to 32 300 kN,
by the lever arm of half the deck normal loading conditions and may
which gives ν=0.22 and the maximum
width, taken as 18 m, the estimated even sustain the impact of a stay
load on the side with the stay removed
torsion induced along the main deck is removal;
reduces to 17 400 kN, giving ν=0.12, .
about 175.5 MNm, which was reported However, a stay removal will induce
which confirms that the legs of the
by the numerical model and shown in a bending moment in the plane of
antenna would be expected to remain
Fig. 13. In addition, the eccentricity of the deck and a torque that will be
in compression despite losing a stay.
the axial force in the plane of the deck above the capacity (Fig. 13);
will produce an in plane bending In the case of the seismic loading, the . The live loads are only a small frac-
moment, which can be estimated in axial load ratio in each antenna leg tion of the permanent loads and
the range of 250 MNm, with simple for the collapse prevention limit state cannot change significantly the
equilibrium consideration similar to intensity increased from the ν=0.18 stress and strain demand.
those applied for the torque. The tor- reported above to a value of ν=0.21.
sional demand alone, following the For the case of the pier legs, under However, it cannot be excluded that an
stay removal, is far in excess of the tor- normal loading conditions the axial impact on the deck induces local
sional capacity computed under normal load ratio is computed as ν=0.05 in damage and possibly attains the
loading conditions (Fig. 13), and will be each leg, but when examined under capacity of one or more of the beams
worsen by the additional tensile and seismic loading increases to a of the simply supported span, though
modelled assuming cross-section area structural distress would have had to It is therefore concluded that no
reduction also for the 352 pre-tensioned appear well in advance. reasonable level of impulsive loading
cables, both in the S-W stay alone, as could cause the collapse of the bridge,
before, as well as in the other three unless in combination with other pro-
stays. Even if significant vertical displa- Scenario 2—Collapse Induced by blems, for example, a concurrent loss
cements (up to −800 mm) were an Impulsive Load Acting on in the stay capacity.
obtained (which would have induced Critical Sections
noticeable progressive structural
This modelling scenario explores the
damage), in most of the cases the Scenario 3—Failure of the Deck-
possibility of a collapse induced by
bridge seems to be able to cope with stay or Antenna-stay Connections
the previously introduced hypothetical
them, thanks to its good capacity of
case of an impulsive load acting on As depicted in Fig. 18, two scenarios are
accommodating relative displacements
critical sections, possibly weakened by herein considered; either a failure at the
and to find different equilibrium con-
some loss of post-tensioning. The interface between the S-W stay and the
figurations through the exploitation of
aforementioned local impulsive load antenna (possibly related to fatigue in
the large over-strength present in
was thus considered acting in the vicin- the tendons), or the sudden loss of con-
many elements and sections, discussed
ity of the support ledge, with an ulti- nection between the same S-W stay and
in the previous section of this paper.
mate capacity of 3400 kN being the main deck (as previously discussed,
As an example, considering a cross- obtained, when local shear failure of the limited knowledge about the trans-
section area reduction of 50% of both the occurs, albeit not leading to the col- verse link details cannot exclude this
the S-W and S-E steel cables, in lapse of the entire supported span, as possibility). The collapse sequence (as
addition to a deterioration of 70% of illustrated in Fig. 16. induced by the antenna-to-stay inter-
the cross-section of the S-W 112 post- face failure) is depicted in Fig. 19; (i) a
Finally, and although the simply-sup-
compression tendons, leads to a S-W torsional collapse of the deck in a
ported Gerber span appears to
vertical displacement of −480 mm, section next to the west side of the
possess sufficient strength to withstand
whilst on the S-E, N-W and N-E, pier strut and the subsequent falling to
the considered hypothetical accidental
−240, −250 and −140 mm were the ground of the west supported
impulsive load, the effect of its poten-
respectively predicted. Although this span, (ii) the consequent release of the
tial failure on the global dynamic
case was specifically selected for maxi- S-W stay and flat collapse to the
response of the bridge was nonetheless
mising the deck torsional response and ground of the west deck and supported
investigated, through the sudden
a considerable relative vertical displa- span, (iii) the collapse of the south
removal (after the application of the
cement between the S-W and the N- antenna, followed by the north one,
static loads) of one, and then two of
W side of the bridge was observed, (iv) the collapse of the central span
its six constitutive Gerber beams. In
no collapse occurred. Indeed, in order when hit by the falling antenna debris.
the first case, no explicit collapse of
to be able to obtain an explicit collapse A very similar collapse sequence was
the supported span was obtained. On
of the structure, an area reduction in obtained for the case of deck-to-stay
the contrary, the simultaneous
the range of 60–70% of both the 112 interface failure.
removal of two of the Gerber beams
post-compression tendons (S-W stay)
did lead to a collapse of the supported The progressive collapse sequence
and the 352 pre-tensioned cables (S-
span, which induced on the main described above seems to be remark-
W and S-E stays) would need to be
bridge system a flexural deformation ably consistent with the actual evi-
introduced. It is thus concluded that
producing vertical displacements at dence, as may be gathered also from
whilst a progressive reduction of
the connection between the S-W stay Fig. 20, where observed and predicted
tendons cross-section area and related
and the deck of + 160 and + 170 mm debris are compared. Such a good
post-tensioning force might have been
towards N-W and S-W respectively, agreement seems to lend further
a con-cause of the observed collapse,
whilst on the N-E and S-E sides −135 weight to the possibility that the col-
it could not by itself alone be the
and −145 mm. As also gathered from lapse of the bridge was indeed trig-
cause of the collapse of the bridge,
Fig. 17, however, such scenario does gered by a failure of the deck/antenna
since conspicuous signs of significant
not lead to the collapse of the bridge. interfaces of the S-W stay.
Fig. 17: Bridge response when one of the simply-supported Gerber spans is taken to collapse
Fig. 18: Failure of the S-W stay at the interface with antenna (left) and deck (right)
Fig. 19: Predicted collapse mechanism associated to a sudden failure of the connection between antenna and S-W stay
Concluding Remarks: What term effects of time dependent safety margins of different sections
Might Have Happened phenomena (such as creep and relax- and elements. From these verifications,
ation) and the actual injection of it can be concluded that:
The introductory part of this paper tendons ducts and the potential conse-
. All elements, with no exception, had
tries to outline the exciting time of quences in terms of corrosion; Morandi
freeways booming construction in the himself raised these issues in the year ample margins of safety towards
1950s and 1960s, with the rapid intro- following the construction of the failure, considering the structure as
duction of new, advanced construction bridge.44 With specific reference to described at the time of construction.
. The addition of variable live loads
technology and namely of large span the case under scrutiny, it appears
pre-stressed bridge structures. In this that the tendon ducts were certainly seems to have little influence on the
daring context, the Morandi Bridge poorly injected and possibly not assessed demands, thus being an
stands out as one of the most original injected at all in most cases, however, unlikely trigger of failure.
and well-devised structures. However, this regrettable situation does not . An “exceptional” point load, acting
it appears that some relevant aspects appear to have had a serious impact on a critical section of the
had not been properly considered, on the collapse, unless in favouring supported span may induce local
because of an insufficient level of the progression of corrosion. element collapse, particularly in pres-
knowledge, or because they were ence of relevant progress of corrosion.
In the main part of this study, well- . A local failure such as those men-
deliberately considered minor and not known structural analysis codes were
relevant, or simply because they were tioned in the previous point will not
employed to model the structural extend into a global collapse (e.g. a
overlooked and taken for granted. system and equally well-established
Two typical examples are the long- shear failure of at least two Gerber
theories were used to calculate the beams of the supported span may