Doha Petroleum Construction Co.

Ltd
Post Box 1744, Doha - Qatar. Tel: 4600350 - Fax: 4601066
Project EPIC FOR UPGRADATION OF AC UPS UNITS IN NGL3,
INSPECTION & TEST PLAN Job No, J 24555

MESAIEED ELECTRICAL Ref. No.


Revision
3513-M3GE-2-25-0019
A
Contract No. GC12105200 Date 13-08-2013
Page 2 of 29
Project No. 3513
Item Process Quality Control QC Procedure/ Acceptance Criteria Verifying Inspection Points
No. Description Activity Spec. Reference Value Code/Standard Documents Responsibility DOPET QP Remarks

1 Material Receiving
Receiving
Receiving inspection Visual inspection for any
Procedure for Inspection Material
of all electrical physical damage /defect Compliance with
material control Request Cum Controller,
1.1 equipments including & verification against Specifications/ H W
3513-M3GE-0- Report Material QC Inspector
UPS, DB’s, Panels and delivery note/contract Datasheets
25-0005 and Equipment (E&I)
all accessories requirements/ certification
Certificates

Receiving inspection Receiving


Visual inspection for any
of Power & Control Procedure for Inspection Material
physical damage /defect 19200-01-16-13 R3
Cables, Grounding material control Request Cum Controller,
1.2 & verification against Electrical bulk H W
Cables & materials, 3513-M3GE-0- Report Material QC Inspector
delivery note/contract materials
Glands, Connectors 25-0005 and Equipment (E&I)
requirements/ certification
and accessories Certificates

Receiving
Visual inspection for any
Procedure for Inspection Material
Receiving inspection physical damage /defect 19200-01-16-13 R3
material control Request Cum Controller,
1.3 of Lighting Fixtures & verification against Electrical bulk H W
3513-M3GE-0- Report Material QC Inspector
and Accessories delivery note/contract materials
25-0005 and Equipment (E&I)
requirements/ certification
Certificates

Visual inspection for any


Procedure for Receiving Material
Receiving inspection physical damage /defect & 19200-01-16-13 R3
material control Inspection Controller,
1.4 of Cable Tray and verification against delivery Electrical bulk H W
3513-M3GE-0- Request Cum QC Inspector
Conduits note/contract requirements/ materials
25-0005 Report (E&I)
certification
2 Pre-Installation

DOC NO : 3513-M3GE-2-25-0019 REV. A PAGE 2 OF 29