Você está na página 1de 21

ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month

ecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
1 LOTE 4 CUADRANTE "D" ALOJAMIENTO 177 days Mon 2/4/19 Wed 10/9/19

2 PARTIDAS GENERALES 4 days Mon 2/4/19 Fri 2/8/19

3 PRELIMINARES: 4 days Mon 2/4/19 Fri 2/8/19

4 Campamento 4 days Mon 2/4/19 Fri 2/8/19

5 Replanteo continuo 0 mons Fri 2/8/19 Fri 2/8/19 4 2/8

6 EDIFICIOS DE ALOJAMIENTO (8 EDIFICIOS) 101 days Thu 2/7/19 Fri 6/28/19

7 PRELIMINARES: Fumigación área de Construcción 6 days Thu 2/7/19 Fri 2/15/19 5SS-1 day

8 MOVIMIMIENTO DE TIERRA 20 days Fri 2/8/19 Fri 3/8/19

9 EDIFICIO 1 10 days Fri 2/8/19 Fri 2/22/19 7SS+1 day

10 EDIFICIO 2 10 days Fri 2/8/19 Fri 2/22/19 9SS

11 EDIFICIO 3 10 days Fri 2/8/19 Fri 2/22/19 10SS

12 EDIFICIO 4 10 days Fri 2/8/19 Fri 2/22/19 11SS

13 EDIFICIO 5 10 days Fri 2/22/19 Fri 3/8/19 12

14 EDIFICIO 6 10 days Fri 2/22/19 Fri 3/8/19 13SS

15 EDIFICIO 7 10 days Fri 2/22/19 Fri 3/8/19 14SS

16 EDIFICIO 8 10 days Fri 2/22/19 Fri 3/8/19 15SS

17 HORMIGON ARMADO 68 days Fri 2/22/19 Wed 5/29/19

18 EDIFICIO 1 36 days Fri 2/22/19 Mon 4/15/19

19 1ER NIVEL 16 days Fri 2/22/19 Mon 3/18/19 9

20 2DO NIVEL 16 days Fri 3/1/19 Mon 3/25/19 19SS+5 days

21 3ER NIVEL 16 days Fri 3/8/19 Mon 4/1/19 20SS+5 days

22 4TO NIVEL 16 days Fri 3/15/19 Mon 4/8/19 21SS+5 days

23 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 16 days Fri 3/22/19 Mon 4/15/19 22SS+5 days

24 EDIFICIO 2 36 days Fri 2/22/19 Mon 4/15/19

25 1ER NIVEL 16 days Fri 2/22/19 Mon 3/18/19 19SS

26 2DO NIVEL 16 days Fri 3/1/19 Mon 3/25/19 25SS+5 days

27 3ER NIVEL 16 days Fri 3/8/19 Mon 4/1/19 26SS+5 days

28 4TO NIVEL 16 days Fri 3/15/19 Mon 4/8/19 27SS+5 days

29 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 16 days Fri 3/22/19 Mon 4/15/19 28SS+5 days

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 1
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
30 EDIFICIO 3 36 days Wed 3/6/19 Thu 4/25/19

31 1ER NIVEL 16 days Wed 3/6/19 Thu 3/28/19 19SS+8 days

32 2DO NIVEL 16 days Wed 3/13/19 Thu 4/4/19 31SS+5 days

33 3ER NIVEL 16 days Wed 3/20/19 Thu 4/11/19 32SS+5 days

34 4TO NIVEL 16 days Wed 3/27/19 Thu 4/18/19 33SS+5 days

35 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 16 days Wed 4/3/19 Thu 4/25/19 34SS+5 days

36 EDIFICIO 4 36 days Wed 3/6/19 Thu 4/25/19

37 1ER NIVEL 16 days Wed 3/6/19 Thu 3/28/19 31SS

38 2DO NIVEL 16 days Wed 3/13/19 Thu 4/4/19 37SS+5 days

39 3ER NIVEL 16 days Wed 3/20/19 Thu 4/11/19 38SS+5 days

40 4TO NIVEL 16 days Wed 3/27/19 Thu 4/18/19 39SS+5 days

41 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 16 days Wed 4/3/19 Thu 4/25/19 40SS+5 days

42 EDIFICIO 5 36 days Thu 3/28/19 Fri 5/17/19

43 1ER NIVEL 16 days Thu 3/28/19 Fri 4/19/19 31

44 2DO NIVEL 16 days Thu 4/4/19 Fri 4/26/19 43SS+5 days

45 3ER NIVEL 16 days Thu 4/11/19 Fri 5/3/19 44SS+5 days

46 4TO NIVEL 16 days Thu 4/18/19 Fri 5/10/19 45SS+5 days

47 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 16 days Thu 4/25/19 Fri 5/17/19 46SS+5 days

48 EDIFICIO 6 36 days Thu 3/28/19 Fri 5/17/19

49 1ER NIVEL 16 days Thu 3/28/19 Fri 4/19/19 43SS

50 2DO NIVEL 16 days Thu 4/4/19 Fri 4/26/19 49SS+5 days

51 3ER NIVEL 16 days Thu 4/11/19 Fri 5/3/19 50SS+5 days

52 4TO NIVEL 16 days Thu 4/18/19 Fri 5/10/19 51SS+5 days

53 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 16 days Thu 4/25/19 Fri 5/17/19 52SS+5 days

54 EDIFICIO 7 36 days Tue 4/9/19 Wed 5/29/19

55 1ER NIVEL 16 days Tue 4/9/19 Wed 5/1/19 43SS+8 days

56 2DO NIVEL 16 days Tue 4/16/19 Wed 5/8/19 55SS+5 days

57 3ER NIVEL 16 days Tue 4/23/19 Wed 5/15/19 56SS+5 days

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 2
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
58 4TO NIVEL 16 days Tue 4/30/19 Wed 5/22/19 57SS+5 days

59 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 16 days Tue 5/7/19 Wed 5/29/19 58SS+5 days

60 EDIFICIO 8 36 days Tue 4/9/19 Wed 5/29/19

61 1ER NIVEL 16 days Tue 4/9/19 Wed 5/1/19 55SS

62 2DO NIVEL 16 days Tue 4/16/19 Wed 5/8/19 61SS+5 days

63 3ER NIVEL 16 days Tue 4/23/19 Wed 5/15/19 62SS+5 days

64 4TO NIVEL 16 days Tue 4/30/19 Wed 5/22/19 63SS+5 days

65 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 16 days Tue 5/7/19 Wed 5/29/19 64SS+5 days

66 MUROS DE: Bloques de 6" BNP y SNP y Bloques de 4" 54 days Mon 3/18/19 Fri 5/31/19
SNP

67 EDIFICIO 1 22 days Mon 3/18/19 Wed 4/17/19 19

68 EDIFICIO 2 22 days Mon 3/18/19 Wed 4/17/19 25

69 EDIFICIO 3 22 days Thu 3/28/19 Mon 4/29/19 31

70 EDIFICIO 4 22 days Thu 3/28/19 Mon 4/29/19 37

71 EDIFICIO 5 22 days Fri 4/19/19 Tue 5/21/19 43

72 EDIFICIO 6 22 days Fri 4/19/19 Tue 5/21/19 49

73 EDIFICIO 7 22 days Wed 5/1/19 Fri 5/31/19 55

74 EDIFICIO 8 22 days Wed 5/1/19 Fri 5/31/19 61

75 TERMINACION DE SUPERFICIE: Fraguache, Pañete y 53 days Fri 3/22/19 Wed 6/5/19


Cantos

76 EDIFICIO 1 20 days Fri 3/22/19 Fri 4/19/19 67SS+4 days

77 EDIFICIO 2 20 days Fri 3/22/19 Fri 4/19/19 68SS+4 days

78 EDIFICIO 3 20 days Thu 4/4/19 Thu 5/2/19 69SS+5 days

79 EDIFICIO 4 20 days Thu 4/4/19 Thu 5/2/19 70SS+5 days

80 EDIFICIO 5 20 days Fri 4/26/19 Fri 5/24/19 71SS+5 days

81 EDIFICIO 6 20 days Fri 4/26/19 Fri 5/24/19 72SS+5 days

82 EDIFICIO 7 20 days Wed 5/8/19 Wed 6/5/19 73SS+5 days

83 EDIFICIO 8 20 days Wed 5/8/19 Wed 6/5/19 74SS+5 days

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 3
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
84 TERMINACION DE PISOS: Torta de hormigón de base 43 days Fri 4/5/19 Wed 6/5/19
e=0.10mt con fIbra y Piso cemento pulido con intralok
bonding agent terminado con helicoptero

85 EDIFICIO 1 10 days Fri 4/5/19 Fri 4/19/19 76FF

86 EDIFICIO 2 10 days Fri 4/5/19 Fri 4/19/19 77FF

87 EDIFICIO 3 10 days Thu 4/18/19 Thu 5/2/19 78FF

88 EDIFICIO 4 10 days Thu 4/18/19 Thu 5/2/19 79FF

89 EDIFICIO 5 10 days Fri 5/10/19 Fri 5/24/19 80FF

90 EDIFICIO 6 10 days Fri 5/10/19 Fri 5/24/19 81FF

91 EDIFICIO 7 10 days Wed 5/22/19 Wed 6/5/19 82FF

92 EDIFICIO 8 10 days Wed 5/22/19 Wed 6/5/19 82FF

93 TERMINACION DE ESCALERA: Escalones y descanso 37 days Mon 4/15/19 Wed 6/5/19


es de cemento pulido con intralok bonding agent
terminado con helicoptero

94 EDIFICIO 1 4 days Mon 4/15/19 Fri 4/19/19 85FF

95 EDIFICIO 2 4 days Mon 4/15/19 Fri 4/19/19 86FF

96 EDIFICIO 3 4 days Fri 4/26/19 Thu 5/2/19 87FF

97 EDIFICIO 4 4 days Fri 4/26/19 Thu 5/2/19 88FF

98 EDIFICIO 5 4 days Mon 5/20/19 Fri 5/24/19 89FF

99 EDIFICIO 6 4 days Mon 5/20/19 Fri 5/24/19 90FF

100 EDIFICIO 7 4 days Thu 5/30/19 Wed 6/5/19 91FF

101 EDIFICIO 8 4 days Thu 5/30/19 Wed 6/5/19 92FF

102 PROTECCION DE HIERROS EN PUERTAS Y VENTANAS 36 days Fri 4/19/19 Mon 6/10/19

103 EDIFICIO 1 3 days Fri 4/19/19 Wed 4/24/19 85

104 EDIFICIO 2 3 days Fri 4/19/19 Wed 4/24/19 86

105 EDIFICIO 3 3 days Thu 5/2/19 Tue 5/7/19 87

106 EDIFICIO 4 3 days Thu 5/2/19 Tue 5/7/19 88

107 EDIFICIO 5 3 days Fri 5/24/19 Wed 5/29/19 89

108 EDIFICIO 6 3 days Fri 5/24/19 Wed 5/29/19 90

109 EDIFICIO 7 3 days Wed 6/5/19 Mon 6/10/19 91

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 4
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
110 EDIFICIO 8 3 days Wed 6/5/19 Mon 6/10/19 92

111 PUERTAS: Polimetal y Puerta Multilock 36 days Fri 4/19/19 Mon 6/10/19

112 EDIFICIO 1 3 days Fri 4/19/19 Wed 4/24/19 85

113 EDIFICIO 2 3 days Fri 4/19/19 Wed 4/24/19 86

114 EDIFICIO 3 3 days Thu 5/2/19 Tue 5/7/19 87

115 EDIFICIO 4 3 days Thu 5/2/19 Tue 5/7/19 88

116 EDIFICIO 5 3 days Fri 5/24/19 Wed 5/29/19 89

117 EDIFICIO 6 3 days Fri 5/24/19 Wed 5/29/19 90

118 EDIFICIO 7 3 days Wed 6/5/19 Mon 6/10/19 91

119 EDIFICIO 8 3 days Wed 6/5/19 Mon 6/10/19 92

120 VENTANAS : Ventanas Corredizas Policarbonato 37 days Fri 4/19/19 Tue 6/11/19
anti-golpes con marco de Aluminio y Policarbonato
antigolpes resistente a la tensión y rotura transparente
en control

121 EDIFICIO 1 4 days Fri 4/19/19 Thu 4/25/19 85

122 EDIFICIO 2 4 days Fri 4/19/19 Thu 4/25/19 86

123 EDIFICIO 3 4 days Thu 5/2/19 Wed 5/8/19 87

124 EDIFICIO 4 4 days Thu 5/2/19 Wed 5/8/19 88

125 EDIFICIO 5 4 days Fri 5/24/19 Thu 5/30/19 89

126 EDIFICIO 6 4 days Fri 5/24/19 Thu 5/30/19 90

127 EDIFICIO 7 4 days Wed 6/5/19 Tue 6/11/19 91

128 EDIFICIO 8 4 days Wed 6/5/19 Tue 6/11/19 92

129 PINTURAS ( 2 MANOS) 43 days Fri 4/19/19 Wed 6/19/19

130 EDIFICIO 1 10 days Fri 4/19/19 Fri 5/3/19 85

131 EDIFICIO 2 10 days Fri 4/19/19 Fri 5/3/19 86

132 EDIFICIO 3 10 days Thu 5/2/19 Thu 5/16/19 87

133 EDIFICIO 4 10 days Thu 5/2/19 Thu 5/16/19 88

134 EDIFICIO 5 10 days Fri 5/24/19 Fri 6/7/19 89

135 EDIFICIO 6 10 days Fri 5/24/19 Fri 6/7/19 90

136 EDIFICIO 7 10 days Wed 6/5/19 Wed 6/19/19 91

137 EDIFICIO 8 10 days Wed 6/5/19 Wed 6/19/19 92

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 5
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
138 VARIOS: Tope de granito, Fascias para tapar tuberias, 53 days Fri 4/5/19 Wed 6/19/19
Plafon, Poliuretano en juntas, Bancos, Escalones de
entrada, Barandas en aluminio para escaleras

139 EDIFICIO 1 20 days Fri 4/5/19 Fri 5/3/19 130FF

140 EDIFICIO 2 20 days Fri 4/5/19 Fri 5/3/19 131FF

141 EDIFICIO 3 20 days Thu 4/18/19 Thu 5/16/19 132FF

142 EDIFICIO 4 20 days Thu 4/18/19 Thu 5/16/19 133FF

143 EDIFICIO 5 20 days Fri 5/10/19 Fri 6/7/19 134FF

144 EDIFICIO 6 20 days Fri 5/10/19 Fri 6/7/19 135FF

145 EDIFICIO 7 20 days Wed 5/22/19 Wed 6/19/19 136FF

146 EDIFICIO 8 20 days Wed 5/22/19 Wed 6/19/19 137FF

147 RAMPAS DE ACCESO ENTRADA 16 days Tue 5/14/19 Wed 6/5/19 93FF

148 TERMINACION DE TECHO: Blocks de antepecho, Fino 52 days Wed 4/17/19 Fri 6/28/19
de mezcla, Zabaleta e Impermeabilizante acrilico

149 EDIFICIO 1 20 days Wed 4/17/19 Wed 5/15/19 67

150 EDIFICIO 2 20 days Wed 4/17/19 Wed 5/15/19 68

151 EDIFICIO 3 20 days Mon 4/29/19 Mon 5/27/19 69

152 EDIFICIO 4 20 days Mon 4/29/19 Mon 5/27/19 70

153 EDIFICIO 5 20 days Tue 5/21/19 Tue 6/18/19 71

154 EDIFICIO 6 20 days Tue 5/21/19 Tue 6/18/19 72

155 EDIFICIO 7 20 days Fri 5/31/19 Fri 6/28/19 73

156 EDIFICIO 8 20 days Fri 5/31/19 Fri 6/28/19 74

157 INSTALACIONES SANITARIAS : 62 days Mon 3/18/19 Wed 6/12/19

158 EDIFICIO 1 30 days Mon 3/18/19 Mon 4/29/19 67SS

159 EDIFICIO 2 30 days Mon 3/18/19 Mon 4/29/19 68SS

160 EDIFICIO 3 30 days Thu 3/28/19 Thu 5/9/19 69SS

161 EDIFICIO 4 30 days Thu 3/28/19 Thu 5/9/19 70SS

162 EDIFICIO 5 30 days Fri 4/19/19 Fri 5/31/19 71SS

163 EDIFICIO 6 30 days Fri 4/19/19 Fri 5/31/19 72SS

164 EDIFICIO 7 30 days Wed 5/1/19 Wed 6/12/19 73SS

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 6
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
165 EDIFICIO 8 30 days Wed 5/1/19 Wed 6/12/19 74SS

166 INSTALACIONES ELECTRICAS 62 days Mon 3/18/19 Wed 6/12/19

167 EDIFICIO 1 30 days Mon 3/18/19 Mon 4/29/19 67SS

168 EDIFICIO 2 30 days Mon 3/18/19 Mon 4/29/19 68SS

169 EDIFICIO 3 30 days Thu 3/28/19 Thu 5/9/19 69SS

170 EDIFICIO 4 30 days Thu 3/28/19 Thu 5/9/19 70SS

171 EDIFICIO 5 30 days Fri 4/19/19 Fri 5/31/19 71SS

172 EDIFICIO 6 30 days Fri 4/19/19 Fri 5/31/19 72SS

173 EDIFICIO 7 30 days Wed 5/1/19 Wed 6/12/19 73SS

174 EDIFICIO 8 30 days Wed 5/1/19 Wed 6/12/19 74SS

175 EDIFICIO DE OBSERVACIÓN 58 days Tue 5/14/19 Fri 8/2/19

176 PRELIMINARES: Fumigación área de Construcción 1 day Tue 5/14/19 Wed 5/15/19 177SS-1 day

177 MOVIMIENTO DE TIERRA 10 days Wed 5/15/19 Wed 5/29/19 179SS-5 days

178 HORMIGÓN ARMADO 35 days Wed 5/22/19 Wed 7/10/19

179 1ER NIVEL 19 days Wed 5/22/19 Tue 6/18/19 64

180 2DO NIVEL 17 days Thu 5/30/19 Mon 6/24/19 179SS+6 days

181 3ER NIVEL 17 days Fri 6/7/19 Tue 7/2/19 180SS+6 days

182 4TO NIVEL 17 days Mon 6/17/19 Wed 7/10/19 181SS+6 days

183 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 10 days Tue 6/25/19 Tue 7/9/19 182SS+6 days

184 MUROS DE: Bloques de 6" BNP y SNP 21 days Tue 6/18/19 Wed 7/17/19

185 1ER NIVEL 5 days Tue 6/18/19 Tue 6/25/19 179

186 2DO NIVEL 5 days Mon 6/24/19 Mon 7/1/19 180

187 3ER NIVEL 5 days Tue 7/2/19 Tue 7/9/19 181

188 4TO NIVEL 5 days Wed 7/10/19 Wed 7/17/19 182

189 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 3 days Tue 7/9/19 Fri 7/12/19 183

190 TERMINACION DE SUPERFICIE: Careteo, Pañete, 21 days Thu 6/20/19 Fri 7/19/19
Cantos y Violinado en Superficie Exterior

191 1ER NIVEL 5 days Thu 6/20/19 Thu 6/27/19 185SS+2 days

192 2DO NIVEL 5 days Wed 6/26/19 Wed 7/3/19 186SS+2 days

193 3ER NIVEL 5 days Thu 7/4/19 Thu 7/11/19 187SS+2 days

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 7
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
194 4TO NIVEL 5 days Fri 7/12/19 Fri 7/19/19 188SS+2 days

195 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 3 days Thu 7/11/19 Tue 7/16/19 189SS+2 days

196 TERMINACIÓN DE PISOS: Torta de Hormigón de base, 19 days Tue 6/25/19 Mon 7/22/19
Piso cemento pulido con intralok bonding agent

197 1ER NIVEL 3 days Tue 6/25/19 Fri 6/28/19 191SS+3 days

198 2DO NIVEL 3 days Mon 7/1/19 Thu 7/4/19 192SS+3 days

199 3ER NIVEL 3 days Tue 7/9/19 Fri 7/12/19 193SS+3 days

200 4TO NIVEL 3 days Wed 7/17/19 Mon 7/22/19 194SS+3 days

201 TERMINACION DE ESCALERA: Escalones y descanso es 4 days Tue 7/16/19 Mon 7/22/19 196FF
de cemento pulido con intralok bonding agent terminado
con helicoptero

202 PROTECCIÓN DE HIERROS 3 days Thu 7/4/19 Tue 7/9/19 190SS+10 days

203 PUERTAS: Puertas en hierro, Puerta multilock, Puertas 4 days Fri 7/19/19 Thu 7/25/19 190
polimetal

204 VENTANAS: Policarbonato fijo Anti-golpe, Ventana 4 days Fri 7/19/19 Thu 7/25/19 203SS
Corrediza con marco de Aluminio

205 PINTURAS ( 2 MANOS) 10 days Fri 7/19/19 Fri 8/2/19

206 1ER NIVEL 7 days Fri 7/19/19 Tue 7/30/19 190

207 2DO NIVEL 7 days Mon 7/22/19 Wed 7/31/19 206SS+1 day

208 3ER NIVEL 7 days Tue 7/23/19 Thu 8/1/19 207SS+1 day

209 4TO NIVEL 7 days Wed 7/24/19 Fri 8/2/19 208SS+1 day

210 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 3 days Thu 7/25/19 Tue 7/30/19 209SS+1 day

211 VARIOS: Tope de granito, Fascias para tapar tuberias, 20 days Fri 7/5/19 Fri 8/2/19 205FF
Plafon, Poliuretano en juntas, Escalones de entrada,
Barandas en aluminio para escaleras, Perfil metálico en
Fachada de Escalera, Malla soldada y plastificada en
huecos de ventana en Huecos de Escalera

212 RAMPA DE ACCESO ENTRADA: 4 days Tue 7/16/19 Mon 7/22/19 201FF

213 TERMINACION DE TECHO: Blocks de antepecho, Fino de 10 days Fri 7/12/19 Fri 7/26/19 189
mezcla, Zabaleta

214 Impermeabilizante, Lona Asfáltica Granulada en poliester 2 days Fri 7/26/19 Tue 7/30/19 213

215 INSTALACION SANITARIA 18 days Fri 7/5/19 Wed 7/31/19

216 Suministro e instalacion de quipos lavamanos, inodoros, 4 days Thu 7/25/19 Wed 7/31/19 203
duchas y mezcladoras

217 Suministro e instalacion de salidas de agua potable y residual


8 days Fri 7/5/19 Wed 7/17/19 184FF

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 8
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
218 Conexión a red de agua potable, drenaje residual y accesorios
3 days Tue 7/16/19 Fri 7/19/19 190FF

219 Sistema contra incendio 4 days Mon 7/15/19 Fri 7/19/19 190FF

220 INSTALACION ELECTRICA 43 days Wed 5/22/19 Mon 7/22/19

221 Panel board monofasico 6 espacios 1 day Fri 7/19/19 Mon 7/22/19 190

222 Panel breaker 1 day Fri 7/19/19 Mon 7/22/19 221SS

223 Salida Abanico de techo 4 days Tue 6/18/19 Wed 7/17/19 184SS

224 Salida Lamparas 5 days Tue 6/18/19 Thu 7/18/19 223SS

225 Salida para Motores de puertas en cendas y areas 1 day Tue 6/18/19 Thu 7/18/19 224SS
comunes utilizadas por internos

226 Salidas para Interruptores y Tomacorrientes 5 days Tue 6/18/19 Tue 7/16/19 225SS

227 Salida para camara de seguridad, telefonos, data, cable 3 days Tue 6/18/19 Thu 7/18/19 226SS
TV

228 Malla de aterrizaje 1 day Wed 5/22/19 Thu 5/23/19 179SS

229 EDIFICIO DE CELDAS CONYUGALES 58 days Tue 5/14/19 Fri 8/2/19

230 PRELIMINARES: Fumigación área de Construcción 1 day Tue 5/14/19 Wed 5/15/19 231SS-1 day

231 MOVIMIENTO DE TIERRA 10 days Wed 5/15/19 Wed 5/29/19 233SS-5 days

232 HORMIGÓN ARMADO 35 days Wed 5/22/19 Wed 7/10/19

233 1ER NIVEL 19 days Wed 5/22/19 Tue 6/18/19 179SS

234 2DO NIVEL 17 days Thu 5/30/19 Mon 6/24/19 233SS+6 days

235 3ER NIVEL 17 days Fri 6/7/19 Tue 7/2/19 234SS+6 days

236 4TO NIVEL 17 days Mon 6/17/19 Wed 7/10/19 235SS+6 days

237 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 10 days Tue 6/25/19 Tue 7/9/19 236SS+6 days

238 MUROS DE: Bloques de 6" BNP y SNP 21 days Tue 6/18/19 Wed 7/17/19

239 1ER NIVEL 5 days Tue 6/18/19 Tue 6/25/19 233

240 2DO NIVEL 5 days Mon 6/24/19 Mon 7/1/19 234

241 3ER NIVEL 5 days Tue 7/2/19 Tue 7/9/19 235

242 4TO NIVEL 5 days Wed 7/10/19 Wed 7/17/19 236

243 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 3 days Tue 7/9/19 Fri 7/12/19 237

244 TERMINACION DE SUPERFICIE: Careteo, Pañete, 21 days Thu 6/20/19 Fri 7/19/19
Cantos y Violinado en Superficie Exterior

245 1ER NIVEL 5 days Thu 6/20/19 Thu 6/27/19 239SS+2 days

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 9
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
246 2DO NIVEL 5 days Wed 6/26/19 Wed 7/3/19 240SS+2 days

247 3ER NIVEL 5 days Thu 7/4/19 Thu 7/11/19 241SS+2 days

248 4TO NIVEL 5 days Fri 7/12/19 Fri 7/19/19 242SS+2 days

249 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 3 days Thu 7/11/19 Tue 7/16/19 243SS+2 days

250 TERMINACIÓN DE PISOS: Torta de Hormigón de base, 19 days Tue 6/25/19 Mon 7/22/19
Piso cemento pulido con intralok bonding agent

251 1ER NIVEL 3 days Tue 6/25/19 Fri 6/28/19 245SS+3 days

252 2DO NIVEL 3 days Mon 7/1/19 Thu 7/4/19 246SS+3 days

253 3ER NIVEL 3 days Tue 7/9/19 Fri 7/12/19 247SS+3 days

254 4TO NIVEL 3 days Wed 7/17/19 Mon 7/22/19 248SS+3 days

255 TERMINACION DE ESCALERA: Escalones y descanso es 4 days Tue 7/16/19 Mon 7/22/19 250FF
de cemento pulido con intralok bonding agent terminado
con helicoptero

256 PROTECCIÓN DE HIERROS 3 days Thu 7/4/19 Tue 7/9/19 244SS+10 days

257 PUERTAS: Puerta multilock, Puertas polimetal 4 days Fri 7/19/19 Thu 7/25/19 244

258 VENTANAS: Policarbonato fijo Anti-golpe, Ventana 4 days Fri 7/19/19 Thu 7/25/19 257SS
Corrediza con marco de Aluminio

259 PINTURAS ( 2 MANOS) 10 days Fri 7/19/19 Fri 8/2/19

260 1ER NIVEL 7 days Fri 7/19/19 Tue 7/30/19 244

261 2DO NIVEL 7 days Mon 7/22/19 Wed 7/31/19 260SS+1 day

262 3ER NIVEL 7 days Tue 7/23/19 Thu 8/1/19 261SS+1 day

263 4TO NIVEL 7 days Wed 7/24/19 Fri 8/2/19 262SS+1 day

264 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 3 days Thu 7/25/19 Tue 7/30/19 263SS+1 day

265 VARIOS: Tope de granito, Fascias para tapar tuberias, 20 days Fri 7/5/19 Fri 8/2/19 259FF
Plafon, Poliuretano en juntas, Escalones de entrada,
Barandas en aluminio para escaleras, Perfil metálico en
Fachada de Escalera, Malla soldada y plastificada en
huecos de ventanas

266 RAMPA DE ACCESO ENTRADA: 4 days Tue 7/16/19 Mon 7/22/19 255FF

267 TERMINACION DE TECHO: Blocks de antepecho, Fino de 10 days Fri 7/12/19 Fri 7/26/19 243
mezcla, Zabaleta

268 Impermeabilizante, Lona Asfáltica Granulada en poliester 2 days Fri 7/26/19 Tue 7/30/19 267

269 INSTALACION SANITARIA 18 days Fri 7/5/19 Wed 7/31/19

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 10
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
270 Suministro e instalacion de quipos lavamanos, inodoros, 4 days Thu 7/25/19 Wed 7/31/19 257
duchas y mezcladoras

271 Suministro e instalacion de salidas de agua potable y residual


8 days Fri 7/5/19 Wed 7/17/19 238FF

272 Conexión a red de agua potable, drenaje residual y accesorios


3 days Tue 7/16/19 Fri 7/19/19 244FF

273 Sistema contra incendio 4 days Mon 7/15/19 Fri 7/19/19 244FF

274 INSTALACION ELECTRICA 43 days Wed 5/22/19 Mon 7/22/19

275 Panel board monofasico 6 espacios 1 day Fri 7/19/19 Mon 7/22/19 244

276 Panel breaker 1 day Fri 7/19/19 Mon 7/22/19 275SS

277 Salida Abanico de techo 4 days Tue 6/18/19 Wed 7/17/19 238SS

278 Salida Lamparas 5 days Tue 6/18/19 Thu 7/18/19 277SS

279 Salida para Motores de puertas en cendas y areas 1 day Tue 6/18/19 Thu 7/18/19 278SS
comunes utilizadas por internos

280 Salidas para Interruptores y Tomacorrientes 5 days Tue 6/18/19 Tue 7/16/19 279SS

281 Salida para camara de seguridad, telefonos, data, cable 3 days Tue 6/18/19 Thu 7/18/19 280SS
TV

282 Malla de aterrizaje 1 day Wed 5/22/19 Thu 5/23/19 233SS

283 EDIFICIO DE REFLEXIÓN 58 days Mon 6/10/19 Thu 8/29/19

284 PRELIMINARES: Fumigación área de Construcción 1 day Mon 6/10/19 Tue 6/11/19 285SS-1 day

285 MOVIMIENTO DE TIERRA 10 days Tue 6/11/19 Tue 6/25/19 287SS-5 days

286 HORMIGÓN ARMADO 35 days Tue 6/18/19 Tue 8/6/19

287 1ER NIVEL 19 days Tue 6/18/19 Mon 7/15/19 233

288 2DO NIVEL 17 days Wed 6/26/19 Fri 7/19/19 287SS+6 days

289 3ER NIVEL 17 days Thu 7/4/19 Mon 7/29/19 288SS+6 days

290 4TO NIVEL 17 days Fri 7/12/19 Tue 8/6/19 289SS+6 days

291 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 10 days Mon 7/22/19 Mon 8/5/19 290SS+6 days

292 MUROS DE: Bloques de 6" BNP y SNP 21 days Mon 7/15/19 Tue 8/13/19

293 1ER NIVEL 5 days Mon 7/15/19 Mon 7/22/19 287

294 2DO NIVEL 5 days Fri 7/19/19 Fri 7/26/19 288

295 3ER NIVEL 5 days Mon 7/29/19 Mon 8/5/19 289

296 4TO NIVEL 5 days Tue 8/6/19 Tue 8/13/19 290

297 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 3 days Mon 8/5/19 Thu 8/8/19 291

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 11
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
298 TERMINACION DE SUPERFICIE: Careteo, Pañete, 21 days Wed 7/17/19 Thu 8/15/19
Cantos y Violinado en Superficie Exterior

299 1ER NIVEL 5 days Wed 7/17/19 Wed 7/24/19 293SS+2 days

300 2DO NIVEL 5 days Tue 7/23/19 Tue 7/30/19 294SS+2 days

301 3ER NIVEL 5 days Wed 7/31/19 Wed 8/7/19 295SS+2 days

302 4TO NIVEL 5 days Thu 8/8/19 Thu 8/15/19 296SS+2 days

303 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 3 days Wed 8/7/19 Mon 8/12/19 297SS+2 days

304 TERMINACIÓN DE PISOS: Torta de Hormigón de base, 19 days Mon 7/22/19 Fri 8/16/19
Piso cemento pulido con intralok bonding agent

305 1ER NIVEL 3 days Mon 7/22/19 Thu 7/25/19 299SS+3 days

306 2DO NIVEL 3 days Fri 7/26/19 Wed 7/31/19 300SS+3 days

307 3ER NIVEL 3 days Mon 8/5/19 Thu 8/8/19 301SS+3 days

308 4TO NIVEL 3 days Tue 8/13/19 Fri 8/16/19 302SS+3 days

309 TERMINACION DE TECHO: Blocks de antepecho, Fino de 10 days Thu 8/8/19 Thu 8/22/19 297
mezcla, Zabaleta

310 Impermeabilizante, Lona Asfáltica Granulada en poliester 2 days Thu 8/22/19 Mon 8/26/19 309

311 TERMINACION DE ESCALERA: Escalones y descanso es 4 days Mon 8/12/19 Fri 8/16/19 304FF
de cemento pulido con intralok bonding agent terminado
con helicoptero

312 PROTECCIÓN DE HIERROS 3 days Wed 7/31/19 Mon 8/5/19 298SS+10 days

313 PUERTAS: Puertas en hierro, Puerta multilock, Puertas 4 days Thu 8/15/19 Wed 8/21/19 298
polimetal

314 VENTANAS: Policarbonato fijo Anti-golpe, Ventana 4 days Thu 8/15/19 Wed 8/21/19 313SS
Corrediza con marco de Aluminio

315 PINTURAS ( 2 MANOS) 10 days Thu 8/15/19 Thu 8/29/19

316 1ER NIVEL 7 days Thu 8/15/19 Mon 8/26/19 298

317 2DO NIVEL 7 days Fri 8/16/19 Tue 8/27/19 316SS+1 day

318 3ER NIVEL 7 days Mon 8/19/19 Wed 8/28/19 317SS+1 day

319 4TO NIVEL 7 days Tue 8/20/19 Thu 8/29/19 318SS+1 day

320 5TO NIVEL (CAJA ESCALERA Y TERM. TECHOS) 3 days Wed 8/21/19 Mon 8/26/19 319SS+1 day

321 VARIOS: Tope de granito, Fascias tapar tuberias, Plafon, 20 days Thu 8/1/19 Thu 8/29/19 315FF
Poliuretano en juntas, Escalones de entrada, Barandas en
aluminio escaleras, Perfil metálico en Fachada, Malla
soldada huecos de ventana, Bancos horm, Proteccion
techo patio

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 12
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
322 RAMPA DE ACCESO ENTRADA: 4 days Mon 8/12/19 Fri 8/16/19 311FF

323 INSTALACION SANITARIA 18 days Thu 8/1/19 Tue 8/27/19

324 Suministro e instalacion de quipos lavamanos, inodoros, 4 days Wed 8/21/19 Tue 8/27/19 313
duchas y mezcladoras

325 Suministro e instalacion de salidas de agua potable y residual


8 days Thu 8/1/19 Tue 8/13/19 292FF

326 Conexión a red de agua potable, drenaje residual y accesorios


3 days Mon 8/12/19 Thu 8/15/19 298FF

327 Sistema contra incendio 4 days Fri 8/9/19 Thu 8/15/19 298FF

328 INSTALACION ELECTRICA 43 days Tue 6/18/19 Fri 8/16/19

329 Panel board monofasico 6 espacios 1 day Thu 8/15/19 Fri 8/16/19 298

330 Panel breaker 1 day Thu 8/15/19 Fri 8/16/19 329SS

331 Salida Abanico de techo 4 days Mon 7/15/19 Tue 8/13/19 292SS

332 Salida Lamparas 5 days Mon 7/15/19 Wed 8/14/19 331SS

333 Salida para Motores de puertas en cendas y areas 1 day Mon 7/15/19 Wed 8/14/19 332SS
comunes utilizadas por internos

334 Salidas para Interruptores y Tomacorrientes 5 days Mon 7/15/19 Mon 8/12/19 333SS

335 Salida para camara de seguridad, telefonos, data, cable 3 days Mon 7/15/19 Wed 8/14/19 334SS
TV

336 Malla de aterrizaje 1 day Tue 6/18/19 Wed 6/19/19 287SS

337 EDIFICIO DE MAXIMA SEGURIDAD 44 days Mon 6/10/19 Fri 8/9/19

338 PRELIMINARES: Fumigación área de Construcción 1 day Mon 6/10/19 Tue 6/11/19 339SS-1 day

339 MOVIMIENTO DE TIERRA 10 days Tue 6/11/19 Tue 6/25/19 340SS-5 days

340 HORMIGÓN ARMADO 15 days Tue 6/18/19 Tue 7/9/19 287SS

341 MUROS DE: Bloques de 6" BNP y SNP 15 days Fri 6/28/19 Fri 7/19/19 340SS+8 days

342 TERMINACION DE SUPERFICIE: Careteo, Pañete, Cantos 15 days Fri 7/5/19 Fri 7/26/19 341SS+5 days

343 TERMINACIÓN DE PISOS: Torta de Hormigón de base, 8 days Fri 7/19/19 Wed 7/31/19 342SS+10 days
Piso cemento pulido con intralok bonding agent, Piso
Hormigon frotado

344 TERMINACION DE ESCALERA EN ENTRADA: Escalones 2 days Mon 7/29/19 Wed 7/31/19 343FF
y descanso es de cemento pulido con intralok bonding
agent terminado con helicoptero

345 PROTECCIÓN DE HIERROS 4 days Fri 7/26/19 Thu 8/1/19 342

346 PUERTAS: Puertas corrediza de barrotes, Puertas de 4 days Fri 7/26/19 Thu 8/1/19 345SS
hierro dobles, Puerta multilock, Puertas polimetal

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 13
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
347 VENTANAS: Policarbonato fijo Anti-golpe, Laminado de 4 days Fri 7/26/19 Thu 8/1/19 346SS
visión unilateral en área de control y monitoreo, ,
Policarbonato antigolpes y seguridad transparente

348 PINTURAS ( 2 MANOS) 15 days Fri 7/19/19 Fri 8/9/19 342SS+10 days

349 TERMINACION DE TECHO: Blocks de antepecho, Fino de 8 days Tue 7/9/19 Fri 7/19/19 340
mezcla, Zabaleta

350 Impermeabilizante, Lona Asfáltica Granulada en poliester 5 days Fri 7/19/19 Fri 7/26/19 349

351 VARIOS: Tope de granito, Poliuretano en juntas, Bancos 20 days Fri 7/12/19 Fri 8/9/19 348FF
de hormigon, Puerta y escalera cisterna, Jardineras,
Aceras

352 VERJA PATIO INTERIOR 12 days Fri 7/19/19 Tue 8/6/19 341

353 RAMPA ACCESO ENTRADA 3 days Fri 7/26/19 Wed 7/31/19 344FF

354 INSTALACION SANITARIA 15 days Mon 7/15/19 Mon 8/5/19

355 Suministro e instalacion de quipos lavamanos, inodoros, 2 days Thu 8/1/19 Mon 8/5/19 346
duchas y mezcladoras

356 Suministro e instalacion de salidas de agua potable y residual


4 days Mon 7/15/19 Fri 7/19/19 341FF

357 Conexión a red de agua potable, drenaje residual y accesorios


1 day Thu 7/25/19 Fri 7/26/19 342FF

358 Sistema contra incendio 4 days Mon 7/22/19 Fri 7/26/19 342FF

359 INSTALACION ELECTRICA 38 days Tue 6/18/19 Fri 8/9/19

360 Panel board monofasico 6 espacios 1 day Fri 7/26/19 Mon 7/29/19 342

361 Panel breaker 1 day Fri 7/26/19 Mon 7/29/19 360SS

362 Salida Lamparas 5 days Fri 7/26/19 Fri 8/9/19 361SS

363 Salida para Motores de puertas en cendas y areas 1 day Fri 7/26/19 Fri 8/9/19 362SS
comunes utilizadas por internos

364 Salidas para Interruptores y Tomacorrientes 5 days Fri 7/26/19 Fri 8/9/19 363SS

365 Salida para camara de seguridad, telefonos, data, cable 3 days Fri 7/26/19 Thu 8/8/19 364SS
TV

366 Malla de aterrizaje 1 day Tue 6/18/19 Wed 6/19/19 340SS

367 COMEDOR 59 days Mon 7/1/19 Fri 9/20/19

368 PRELIMINARES: Fumigación área de Construcción 1 day Mon 7/1/19 Tue 7/2/19 369SS-1 day

369 MOVIMIENTO DE TIERRA 20 days Tue 7/2/19 Tue 7/30/19 370SS-5 days

370 HORMIGÓN ARMADO 30 days Tue 7/9/19 Tue 8/20/19 340

371 MUROS DE: Bloques de 6" y 4" BNP y SNP 20 days Fri 7/19/19 Fri 8/16/19 370SS+8 days

372 TERMINACION DE SUPERFICIE: Careteo, Pañete, Cantos 20 days Fri 7/26/19 Fri 8/23/19 371SS+5 days

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 14
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
373 TERMINACIÓN DE PISOS: Torta de Hormigón de base, 12 days Fri 8/9/19 Tue 8/27/19 372SS+10 days
Piso cemento pulido, Piso Hormigon frotado

374 PROTECCIÓN DE HIERROS 5 days Fri 8/23/19 Fri 8/30/19 372

375 PUERTAS: Puertas polimetal, Puertas enrrollables, Puertas 8 days Fri 8/23/19 Wed 9/4/19 374SS
de hierro

376 VENTANAS: Ventana de corrediza de policarbonato, 8 days Fri 8/23/19 Wed 9/4/19 375SS
Policarbonato fijo antigolpe, Malla electrosoldada en marco,
louvers

377 PINTURAS ( 2 MANOS) 20 days Fri 8/23/19 Fri 9/20/19 372SS+20 days

378 VARIOS: Tope de granito, Poliuretano en juntas, Columnas 20 days Fri 8/23/19 Fri 9/20/19 377FF
revestidas en aluminio

379 RAMPA CARGA Y DESCARGA 5 days Fri 8/16/19 Fri 8/23/19 371

380 TERMINACION DE TECHO: Blocks de antepecho, Fino de 8 days Tue 8/20/19 Fri 8/30/19 370
mezcla, Zabaleta

381 Impermeabilizante, Lona Asfáltica Granulada en poliester 10 days Fri 8/30/19 Fri 9/13/19 380

382 INSTALACION SANITARIA 23 days Mon 8/12/19 Thu 9/12/19

383 Suministro e instalacion de quipos lavamanos, inodoros, 10 days Thu 8/29/19 Thu 9/12/19 375SS+4 days
orinales, fregaderos y mezcladoras

384 Suministro e instalacion de salidas de agua potable y residual


4 days Mon 8/12/19 Fri 8/16/19 371FF

385 Conexión a red de agua potable, drenaje residual y accesorios


2 days Wed 8/21/19 Fri 8/23/19 372FF

386 Sistema contra incendio 5 days Fri 8/16/19 Fri 8/23/19 372FF

387 INSTALACION ELECTRICA 45 days Tue 7/9/19 Tue 9/10/19

388 Panel board monofasico 6 espacios 1 day Fri 8/23/19 Mon 8/26/19 372

389 Panel breaker 1 day Fri 8/23/19 Mon 8/26/19 388SS

390 Salida Abanico de techo 4 days Fri 8/23/19 Tue 9/10/19 389SS

391 Salida Lamparas 5 days Fri 8/23/19 Mon 9/9/19 390SS

392 Salidas para Interruptores y Tomacorrientes 5 days Fri 8/23/19 Mon 9/9/19 391SS

393 Salida para camara de seguridad, telefonos, data, cable 3 days Fri 8/23/19 Tue 9/10/19 392SS
TV

394 Malla de aterrizaje 1 day Tue 7/9/19 Wed 7/10/19 370SS

395 EDIFICIO DE ECONOMATO (2 EDIFICIOS) 32 days Mon 8/12/19 Wed 9/25/19

396 PRELIMINARES: Fumigación área de Construcción 1 day Mon 8/12/19 Tue 8/13/19 397SS-1 day

397 MOVIMIENTO DE TIERRA 5 days Tue 8/13/19 Tue 8/20/19 398SS-5 days

398 HORMIGÓN ARMADO 14 days Tue 8/20/19 Mon 9/9/19 370

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 15
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
399 MUROS DE: Bloques de 8", 6" y 4" BNP y SNP 5 days Fri 8/30/19 Fri 9/6/19 398SS+8 days

400 TERMINACION DE SUPERFICIE: Fraguache, Pañete, 5 days Fri 9/6/19 Fri 9/13/19 399SS+5 days
Cantos

401 TERMINACIÓN DE PISOS: Torta de Hormigón de base, 5 days Fri 9/13/19 Fri 9/20/19 400
Piso cemento pulido con intralok bonding agent

402 PROTECCIÓN DE HIERROS 2 days Fri 9/13/19 Tue 9/17/19 400

403 VENTANAS: Policarbonato corrediza 2 days Tue 9/17/19 Thu 9/19/19 402

404 PUERTAS: Puertas polimetal 2 days Tue 9/17/19 Thu 9/19/19 403SS

405 TERMINACION DE TECHO: Blocks de antepecho, Fino de 6 days Mon 9/9/19 Tue 9/17/19 398
mezcla, Zabaleta, impermeabilizante acrilico

406 PINTURAS ( 2 MANOS) 5 days Wed 9/18/19 Wed 9/25/19 407

407 TERMINACION EXTERIOR 3 days Fri 9/13/19 Wed 9/18/19 400

408 VARIOS: Tope de granito, Vertedero, Poliuretano en juntas, 4 days Thu 9/19/19 Wed 9/25/19 406FF
Barandas minusbalidos

409 INSTALACION SANITARIA 12 days Thu 9/5/19 Mon 9/23/19

410 Suministro e instalacion de quipos lavamanos, inodoros, 2 days Thu 9/19/19 Mon 9/23/19 404
duchas y mezcladoras

411 Suministro e instalacion de salidas de agua potable y residual


1 day Thu 9/5/19 Fri 9/6/19 399FF

412 Conexión a red de agua potable, drenaje residual y accesorios


1 day Thu 9/12/19 Fri 9/13/19 400FF

413 INSTALACION ELECTRICA 22 days Tue 8/20/19 Thu 9/19/19

414 Panel board monofasico 6 espacios 1 day Fri 9/13/19 Mon 9/16/19 400

415 Panel breaker 1 day Fri 9/13/19 Mon 9/16/19 414SS

416 Salida Lamparas 1 day Fri 9/13/19 Thu 9/19/19 415SS

417 Salidas para Interruptores y Tomacorrientes 1 day Fri 9/13/19 Thu 9/19/19 416SS

418 Malla de aterrizaje 1 day Tue 8/20/19 Wed 8/21/19 398SS

419 EDIFICIO ACCESO A CUADRANTES 44 days Mon 7/22/19 Fri 9/20/19

420 PRELIMINARES: Fumigación área de Construcción 1 day Mon 7/22/19 Tue 7/23/19 421SS-1 day

421 MOVIMIENTO DE TIERRA 10 days Tue 7/23/19 Tue 8/6/19 422SS-5 days

422 HORMIGÓN ARMADO 15 days Tue 7/30/19 Tue 8/20/19 370SS+15 days

423 MUROS DE: Bloques de 6" y 4" BNP y SNP 15 days Fri 8/9/19 Fri 8/30/19 422SS+8 days

424 TERMINACION DE SUPERFICIE: Careteo, Pañete, Cantos 15 days Fri 8/16/19 Fri 9/6/19 423SS+5 days

425 TERMINACIÓN DE PISOS: Torta de Hormigón de base, 6 days Fri 8/30/19 Mon 9/9/19 424SS+10 days
Piso cemento pulido con intralok bonding agent

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 16
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
426 PROTECCIÓN DE HIERROS 5 days Fri 9/6/19 Fri 9/13/19 424

427 ESTRUCTURA METÁLICA: Techo de aluzinc sobre 6 days Tue 8/20/19 Wed 8/28/19 422
correas

428 PUERTAS: Puertas polimetal, batientes tola, de sistema 6 days Fri 9/6/19 Mon 9/16/19 426SS
plegadizo

429 VENTANAS: Proyectadas 4 days Fri 9/6/19 Thu 9/12/19 428SS

430 PINTURAS ( 2 MANOS) 15 days Fri 8/30/19 Fri 9/20/19 424SS+10 days

431 VARIOS: Tope de granito, Poliuretano en juntas 5 days Fri 9/13/19 Fri 9/20/19 430FF

432 TERMINACION DE TECHO: Blocks de antepecho, Fino de 10 days Tue 8/20/19 Tue 9/3/19 422
mezcla, Zabaleta, Impermeabilizante acrilico

433 INSTALACION SANITARIA 17 days Mon 8/26/19 Wed 9/18/19

434 Suministro e instalacion de quipos lavamanos, inodoros, 2 days Mon 9/16/19 Wed 9/18/19 428
orinales y mezcladoras

435 Suministro e instalacion de salidas de agua potable y residual


4 days Mon 8/26/19 Fri 8/30/19 423FF

436 Conexión a red de agua potable, drenaje residual y accesorios


1 day Thu 9/5/19 Fri 9/6/19 424FF

437 Sistema contra incendio 4 days Mon 9/2/19 Fri 9/6/19 424FF

438 INSTALACION ELECTRICA 38 days Tue 7/30/19 Fri 9/20/19

439 Panel board monofasico 6 espacios 1 day Fri 9/6/19 Mon 9/9/19 424

440 Panel breaker 1 day Fri 9/6/19 Mon 9/9/19 439SS

441 Salida Lamparas 5 days Fri 9/6/19 Fri 9/20/19 440SS

442 Salida para Motores de puertas en cendas y areas 1 day Fri 9/6/19 Fri 9/20/19 441SS
comunes utilizadas por internos

443 Salidas para Interruptores y Tomacorrientes 5 days Fri 9/6/19 Fri 9/20/19 442SS

444 Salida para camara de seguridad, telefonos, data, cable 3 days Fri 9/6/19 Thu 9/19/19 443SS
TV

445 Malla de aterrizaje 1 day Tue 7/30/19 Wed 7/31/19 422SS

446 TEMPLO (IGLESIA) 41 days Mon 8/12/19 Tue 10/8/19

447 PRELIMINARES: Fumigación área de Construcción 1 day Mon 8/12/19 Tue 8/13/19 448SS-1 day

448 MOVIMIENTO DE TIERRA 10 days Tue 8/13/19 Tue 8/27/19 449SS-5 days

449 HORMIGÓN ARMADO 15 days Tue 8/20/19 Tue 9/10/19 422

450 MUROS DE: Bloques de 6" y 4" BNP y SNP 15 days Fri 8/30/19 Fri 9/20/19 449SS+8 days

451 TERMINACION DE SUPERFICIE: Careteo, Pañete, Cantos 15 days Fri 9/6/19 Fri 9/27/19 450SS+5 days

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 17
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
452 TERMINACIÓN DE PISOS: Torta de Hormigón de base, 6 days Fri 9/20/19 Mon 9/30/19 451SS+10 days
Piso cemento pulido, Piso violinado, Piso hormigon
estampado

453 TERMINACION DE ESCALERA 3 days Fri 9/6/19 Wed 9/11/19 451SS

454 PUERTAS: Puertas policarbonato, Polimetal, Doble de 4 days Fri 9/27/19 Thu 10/3/19 451
hierro

455 VENTANAS: Paño fijo, Ventanas corredizas, Ventanas 4 days Fri 9/27/19 Thu 10/3/19 454SS
proyectadas

456 PINTURAS ( 2 MANOS) 15 days Tue 9/17/19 Tue 10/8/19 451SS+7 days

457 RAMPA DE ACCESO ENTRADA: Baranda en perfiles de 2 days Fri 9/27/19 Tue 10/1/19 454SS
aluminio en rampa de entrada

458 TERMINACION DE TECHO: Blocks de antepecho, Fino de 10 days Tue 9/10/19 Tue 9/24/19 449
mezcla, Zabaleta, Impermeabilizante acrilico

459 ESTRUCTURA METÁLICA: Techo de aluzinc sobre 18 days Tue 9/10/19 Fri 10/4/19 449
correas

460 VARIOS: Tope de granito, Escalera caracol, Jardinera 5 days Tue 10/1/19 Tue 10/8/19 456FF

461 INSTALACION SANITARIA 15 days Mon 9/16/19 Mon 10/7/19

462 Suministro e instalacion de quipos lavamanos, inodoros, 2 days Thu 10/3/19 Mon 10/7/19 454
orinales, fregadero y mezcladoras

463 Suministro e instalacion de salidas de agua potable y residual


4 days Mon 9/16/19 Fri 9/20/19 450FF

464 Conexión a red de agua potable, drenaje residual y accesorios


1 day Thu 9/26/19 Fri 9/27/19 451FF

465 Sistema contra incendio 4 days Mon 9/23/19 Fri 9/27/19 451FF

466 INSTALACION ELECTRICA 34 days Tue 8/20/19 Mon 10/7/19

467 Panel board monofasico 6 espacios 1 day Fri 9/27/19 Mon 9/30/19 451

468 Panel breaker 1 day Fri 9/27/19 Mon 9/30/19 467SS

469 Salida Lamparas 5 days Fri 9/27/19 Mon 10/7/19 468SS

470 Salida Abanico de techo 3 days Fri 9/27/19 Mon 10/7/19 469SS

471 Salidas para Interruptores y Tomacorrientes 5 days Fri 9/27/19 Mon 10/7/19 470SS

472 Salida para camara de seguridad, telefonos, data, cable 3 days Fri 9/27/19 Mon 10/7/19 471SS
TV

473 Malla de aterrizaje 1 day Tue 8/20/19 Wed 8/21/19 449SS

474 EXTERIORES 173 days Fri 2/8/19 Wed 10/9/19

475 CONSTRUCCION CAMPO DE SOFT BALL (1 und) 50 days Fri 2/8/19 Fri 4/19/19

476 PRELIMINARES:Topografía, Limpieza inicial y 5 days Fri 2/8/19 Fri 2/15/19 5SS
acondicionamiento del área

477 MOVIMIENTO DE TIERRA : 20 days Fri 2/15/19 Fri 3/15/19 476

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 18
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
478 GRAMA 15 days Fri 3/15/19 Fri 4/5/19 477

479 DRENAJE (BÁSICO) 5 days Fri 3/15/19 Fri 3/22/19 477

480 CONSTRUCCIÓN BACKSTOPS 25 days Fri 3/15/19 Fri 4/19/19 477

481 MISCELÁNEOS:Almohadillas (bases), Torres de foull 3 days Fri 4/5/19 Wed 4/10/19 478

482 GARITAS (8 EDIFICIOS) 36 days Tue 8/20/19 Wed 10/9/19

483 MOVIMIENTO DE TIERRA 6 days Tue 8/20/19 Wed 8/28/19 397

484 HORMIGON ARMADO 16 days Wed 8/28/19 Thu 9/19/19 483

485 MUROS DE BLOQUES 5 days Thu 9/19/19 Thu 9/26/19 484

486 TERMINACION DE SUPERFICIE: 5 days Thu 9/26/19 Thu 10/3/19 485

487 TERMINACION DE PISOS 3 days Tue 10/1/19 Fri 10/4/19 486SS+3 days

488 TERMINACION DE TECHO: Fino de mezcla, Zabaleta, 8 days Thu 9/26/19 Tue 10/8/19 485
Impermeabilizante acrilico

489 PINTURA :(dos manos) 4 days Thu 10/3/19 Wed 10/9/19 486

490 PUERTA Y VENTANAS 2 days Thu 10/3/19 Mon 10/7/19 486

491 Acera Perimetral, ancho = 0.20m 3 days Thu 9/26/19 Tue 10/1/19 485

492 Perfiles Metalicos Hierro Negro HSS 2''x2'' W=6 mm 1 day Thu 10/3/19 Fri 10/4/19 486

493 CONSTRUCCION CANCHA MIXTA (6 UDS): 58 days Fri 3/29/19 Wed 6/19/19

494 PRELIMINARES: Limpieza inicial y acondicionamiento 5 days Fri 3/29/19 Fri 4/5/19 495SS-5 days
del área

495 MOVIMIENTO DE TIERRA 20 days Fri 4/5/19 Fri 5/3/19 478

496 HORMIGON ARMADO 10 days Fri 5/3/19 Fri 5/17/19 495

497 MUROS DE BLOQUES 10 days Fri 5/17/19 Fri 5/31/19 496

498 TERMINACION DE SUPERFICIE 8 days Fri 5/31/19 Wed 6/12/19 497

499 PINTURA ( 2 MANOS) 5 days Wed 6/12/19 Wed 6/19/19 498

500 MISCELÁNEOS: Tablero de fibra de vidrio incl. Aro y 5 days Wed 6/12/19 Wed 6/19/19 499FF
malla, Tubos HG

501 CONSTRUCCION PLATAFORMA DE GIMNASIO (8 UDS): 65 days Fri 5/3/19 Fri 8/2/19

502 MOVIMIENTO DE TIERRA 15 days Fri 5/3/19 Fri 5/24/19 495

503 HORMIGON ARMADO 15 days Fri 5/24/19 Fri 6/14/19 502

504 MUROS DE BLOQUES 20 days Fri 6/14/19 Fri 7/12/19 503

505 TERMINACION DE SUPERFICIE 15 days Fri 7/12/19 Fri 8/2/19 504

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 19
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
506 EDIFICIO CASETA PLANTA 27 days Mon 8/26/19 Wed 10/2/19

507 PRELIMINARES: Fumigación área de Construcción 2 days Mon 8/26/19 Wed 8/28/19 508SS-2 days

508 MOVIMIENTO DE TIERRA 5 days Wed 8/28/19 Wed 9/4/19 483

509 HORMIGON ARMADO 5 days Wed 9/4/19 Wed 9/11/19 508

510 MUROS DE BLOQUES 5 days Wed 9/11/19 Wed 9/18/19 509

511 TERMINACION DE SUPERFICIE 5 days Wed 9/18/19 Wed 9/25/19 510

512 TERMINACIONES DE PISOS: Torta de Hormigón 3 days Wed 9/11/19 Mon 9/16/19 509
fc=210 k/c2 Ø⅜@0.25, Frotado para planta de
emergencia

513 PUERTAS Y VENTANAS 2 days Mon 9/16/19 Wed 9/18/19 512

514 TERMINACIONES DE TECHOS: Antepecho, Fino, 8 days Wed 9/18/19 Mon 9/30/19 513
Zabaleta, Impermeabilitante

515 PINTURA 2 days Mon 9/30/19 Wed 10/2/19 514

516 Acera Perimetral 5 days Wed 9/18/19 Wed 9/25/19 511SS

517 VERJA PERIMETRAL INTERIOR 55 days Mon 7/1/19 Mon 9/16/19

518 MOVIMIENTO DE TIERRA 30 days Mon 7/1/19 Mon 8/12/19 367SS

519 HORMIGON ARMADO 35 days Mon 7/8/19 Mon 8/26/19 518SS+5 days

520 MUROS DE BLOQUES 35 days Mon 7/15/19 Mon 9/2/19 519SS+5 days

521 TERMINACION DE SUPERFICIE 35 days Mon 7/22/19 Mon 9/9/19 520SS+5 days

522 MALLA CICLONICA 35 days Mon 7/29/19 Mon 9/16/19 521SS+5 days

523 VERJA PERIMETRAL EXTERIOR DEL CUADRANTE 45 days Mon 7/15/19 Mon 9/16/19

524 MOVIMIENTO DE TIERRA 20 days Mon 7/15/19 Mon 8/12/19 518SS+10 days

525 HORMIGON ARMADO 25 days Mon 7/22/19 Mon 8/26/19 524SS+5 days

526 MUROS DE BLOQUES 25 days Mon 7/29/19 Mon 9/2/19 525SS+5 days

527 TERMINACION DE SUPERFICIE 25 days Mon 8/5/19 Mon 9/9/19 526SS+5 days

528 MALLA CICLONICA 25 days Mon 8/12/19 Mon 9/16/19 527SS+5 days

529 ACERAS EXTERIORES 45 days Mon 7/15/19 Mon 9/16/19

530 Aceras exteriores. Piso hormigón rayado con color. 45 days Mon 7/15/19 Mon 9/16/19 523SS

531 PUNTO DE ENCUENTRO SEGURIDAD 16 days Tue 9/3/19 Wed 9/25/19

532 MOVIMIENTO DE TIERRA 4 days Tue 9/3/19 Mon 9/9/19 482SS+10 days

533 HORMIGON ARMADO 4 days Mon 9/9/19 Fri 9/13/19 532

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 20
ID Task Nombre de tarea Duration Start Finish Predecessors Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Mode 27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15
534 MUROS DE BLOQUES 4 days Fri 9/13/19 Thu 9/19/19 533

535 TERMINACION DE SUPERFICIE 3 days Thu 9/19/19 Tue 9/24/19 534

536 PINTURA: Señalización punto de encuentro 1 day Tue 9/24/19 Wed 9/25/19 535

537 ESTRUCTURA DE PAVIMENTO 60 days Mon 7/1/19 Mon 9/23/19

538 Escarificacion de superfice 10 days Mon 7/1/19 Mon 7/15/19 518SS

539 Terminación de sub-rasante 10 days Mon 7/15/19 Mon 7/29/19 538

540 Sub-base granular natural, e=0.28 mts. 15 days Mon 7/29/19 Mon 8/19/19 539

541 Base granular natural, estabilizada con cemento gris a un10


3%days Mon 8/19/19 Mon 9/2/19 540

542 Carpeta en Hormrigón hidraulico con microfibras, e= 0.145mts


days Mon 9/2/19 Mon 9/9/19 541

543 Para gomas en parqueos 5 days Mon 9/9/19 Mon 9/16/19 542

544 Pintura para señalización parqueo discapacitados 5 days Mon 9/16/19 Mon 9/23/19 543

545 INSTALACIONES SANITARIAS EXTERIORES 73 days Wed 6/5/19 Mon 9/16/19

546 Registro Residual 0.60x0.60x1.00 m 50 days Wed 6/5/19 Wed 8/14/19 84

547 Trampa de grasa 0.80x1.00x1.00 m 45 days Wed 6/5/19 Wed 8/7/19 546SS

548 Registros de Ladrillos In Situ o prefabricados 0.80x1.50m20 days Mon 7/22/19 Mon 8/19/19 540FF

549 Conexion de Acometidas a Alcantarilla 20 days Mon 7/22/19 Mon 8/19/19 548SS

550 Tubería de arrastre drenaje sanitario 20 days Mon 7/22/19 Mon 8/19/19 549SS

551 Tubería del alcantarillado colector sanitario 20 days Mon 7/22/19 Mon 8/19/19 550SS

552 Tubería de arrastre agua potable 20 days Mon 7/22/19 Mon 8/19/19 551SS

553 Tubería del acueducto 20 days Mon 7/22/19 Mon 8/19/19 552SS

554 Válvulas, Medidores 20 days Mon 7/22/19 Mon 8/19/19 553SS

555 Hidrantes 10 days Mon 9/2/19 Mon 9/16/19 529FF

556 Imbornal de dos rejillas 12 days Mon 7/15/19 Wed 7/31/19 529SS

557 Tubería alcantarilla agua pluvial 20 days Mon 7/22/19 Mon 8/19/19 552SS

558 INSTALACIONES ELECTRICAS EXTERIORES 25 days Fri 8/2/19 Fri 9/6/19

559 Alimentadores sistema soterrado 25 days Fri 8/2/19 Fri 9/6/19 229

560 Panel Board 15 days Fri 8/16/19 Fri 9/6/19 559FF

561 PAISAJISMO 30 days Wed 8/14/19 Wed 9/25/19

562 PAISAJISMO: 30 days Wed 8/14/19 Wed 9/25/19 474FF-10 days

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite Progreso manual

Proyecto: LOTE 4 CRONOGRAM División Tarea inactiva solo duración solo fin Tareas críticas
Fecha: Fri 1/25/19 Hito Hito inactivo Informe de resumen manual Tareas externas División crítica

Resumen Resumen inactivo Resumen manual Hito externo Progreso

Página 21

Você também pode gostar