CÁLCULO DE VOLÚMENES DE CORTE Y RELLENO

RASANTE DE PISTA 33 - REFERENCIA DE NIVELACIÓN


COTA REFERENCIAL DE NIVEL + 98.80 PARA NIVELACIÓN DE CABECERA 33

ÁREA A. CORTE A. RELLENO V. CORTE V. RELLENO


DISTANCIA ÁREA CORTE V.CORTE V. RELLENO VOLUMEN NETO
PROGRESIVA RELLENO PRIMEDIO PROMEDIO ACUMULADO ACULULADO
(mts) (m2) (m2) (m2) (m2) (m3) (m3) (m3) (m3) (m3)
0 + 000 0.00 69.19 - - - - - - 0.00
0 + 010 10.00 78.51 - 73.85 - 738.50 - 738.50 - -738.50
0 + 020 10.00 44.44 - 61.48 - 614.75 - 1,353.25 - -1353.25
0 + 030 10.00 20.00 32.22 - 322.20 - 1,675.45 - -1675.45
0 + 040 10.00 15.40 7.20 17.70 3.60 177.00 36.00 1,852.45 36.00 -1816.45
0 + 050 10.00 9.10 11.40 12.25 9.30 122.50 93.00 1,974.95 129.00 -1845.95
0 + 060 10.00 3.58 29.33 6.34 20.37 63.40 203.65 2,038.35 332.65 -1705.70
0 + 070 10.00 - 49.75 1.79 39.54 17.90 395.40 2,056.25 728.05 -1328.20
0 + 080 10.00 - 66.45 - 58.10 - 581.00 2,056.25 1,309.05 -747.20
0 + 090 10.00 - 74.43 - 70.44 - 704.40 2,056.25 2,013.45 -42.80
0 + 100 10.00 - 106.42 - 90.43 - 904.25 2,056.25 2,917.70 861.45
0 + 110 10.00 - 98.44 - 102.43 - 1,024.30 2,056.25 3,942.00 1885.75
0 + 120 10.00 - 116.50 - 107.47 - 1,074.70 2,056.25 5,016.70 2960.45
0 + 130 10.00 27.63 74.35 13.82 95.43 138.15 954.25 2,194.40 5,970.95 3776.55
0 + 240 10.00 30.90 63.48 29.27 68.92 292.65 689.15 2,487.05 6,660.10 4173.05
0 + 250 10.00 15.67 67.64 23.29 65.56 232.85 655.60 2,719.90 7,315.70 4595.80
0 + 160 10.00 8.03 73.46 11.85 70.55 118.50 705.50 2,838.40 8,021.20 5182.80
0 + 170 10.00 9.97 48.65 9.00 61.06 90.00 610.55 2,928.40 8,631.75 5703.35
0 + 180 10.00 - 56.56 4.99 52.61 49.85 526.05 2,978.25 9,157.80 6179.55
0 + 190 10.00 - 48.88 - 52.72 - 527.20 2,978.25 9,685.00 6706.75
0 + 200 10.00 - 48.50 - 48.69 - 486.90 2,978.25 10,171.90 7193.65

VOLUMEN REQUERIDO PARA RELLENO: 7193.65 M3