Escolar Documentos
Profissional Documentos
Cultura Documentos
CONTRACT
PARTICULARS LEVEL AMOUNT
TOTAL
TOTAL AMOUNT COLLECTED AMOUNT 6/6/2019
AS OF APRIL 15 COLLECTED
122,000.00
59,500.00
31,000.00
44,800.00 ₱ 257,300.00 17,000.00
175,000.00 175,000.00 6,000.00
37,000.00 37,000.00 2,000.00
NO BILLING
- 4,000.00
- 9,000.00
11,000.00
₱ 469,300.00 ₱ 49,000.00 ₱ - ₱ - ₱ -
₱ - ₱ - ₱ - ₱ - ₱ - ₱ -
TOTAL BALANCE
PAYMENT
396,300.00 (241,550.00)
59,500.00 18,850.00
31,000.00 24,000.00
44,800.00 24,761.00
356,000.00 (106,000.00)
76,000.00 (31,000.00)
₱ - ₱ 963,600.00 -₱ 310,939.00
Project: CONSTURCTION OF 4 STOREY EIGHT CLASSROOM BUILDING AT LUMAMPONG NAT
Location : INDANG, CAVITE
Contractor: Emman Ondoy
CONTRACT AGREEMENT
WATER PROOFING (CR)
PERCENTAGE
UNIT TOTAL
Item QTY. UNIT THIS
COST AMOUNT PREVIOUS
PERIOD
A. WATER PROOFING WORKS -
Second Floor CR (2 units) 25.00 m2 150.00 3,750.00 95%
Third Floor CR (2 units) 25.00 m2 150.00 3,750.00 95%
Fourth Floor CR (2 units) 25.00 m2 150.00 3,750.00 90%
ROOFDECK 9.00 m2 150.00 1,350.00 90%
- m2 - -
CONTRACT AMOUNT 12,600.00 0.00% 92.98%
92.98%
REEMENT
FING (CR)
RCENTAGE AMOUNT
TO THIS APPROVED
PREVIOUS TO DATE
DATE PERIOD AMOUNT
Total 11,715.00
Less: 5 % Retention 585.75
UNIT
Item QTY. UNIT
COST
A. GROUND FLOOR
B. SECOND FLOOR
FLOOR TOPPING 151.21 m2 100.00
PLASTERING 15.12 m2 100.00
INSTALLATION OF DOORS 6.00 PCS 700.00
INSTALLATION OF CUBICLE DOORS 3.00 PCS 400.00
INSTALLATION OF FLOOR AND WALL TILES 56.50 m2 150.00
INSTALLATION OF CEILING @ CR 11.50 m2 160.00
CONST. OF COUNTER SINK WITH TILES 2.00 UNITS 750.00
CONST. OF URINAL WITH TILES 1.00 UNITS 400.00
C. THIRD FLOOR
FLOOR TOPPING 209.00 m2 100.00
PLASTERING 15.12 m2 100.00
INSTALLATION OF DOORS 6.00 PCS 700.00
INSTALLATION OF CUBICLE DOORS 3.00 PCS 400.00
INSTALLATION OF FLOOR AND WALL TILES 56.50 m2 160.00
INSTALLATION OF CEILING @ CR 11.50 m2 160.00
CONST. OF COUNTER SINK WITH TILES 2.00 UNITS 750.00
CONST. OF URINAL WITH TILES 1.00 UNITS 400.00
D. FOURTH FLOOR
FLOOR TOPPING 214.21 m2 100.00
STAIR TOPPING TO ROOF DECK 9.00 m2 100.00
INSTALLATION OF DOORS 7.00 PCS 700.00
INSTALLATION OF CUBICLE DOORS 3.00 PCS 400.00
INSTALLATION OF FLOOR AND WALL TILES 56.50 m2 150.00
CEILING WORKS 94.38 m2 160.00
TILING OF COUNTER SINK 2.00 UNITS 750.00
TILING OF URINAL 1.00 UNIT 750.00
PLASTERING
4TH FLOOR 26.60 m2 100.00
ROOF BEAM LEVEL 27.80 m2 100.00
WALL @ SIDE OF STAIRS TO RD 4.80 m2 100.00
CHB LAYING 8.85 m2 90.00
E. ADDITIONAL WORKS
RAMP RAILING 1.00 UNITS 5,390.00
INSTALLATION OF ZOCALO 1.00 UNIT 10,000.00
CONTRACT AMOUNT
Checked by:
CONTRACT AGREEMENT
FINISHING WORKS
As of June 06,2019
PERCENTAGE AMOUNT
QUOTATION THIS TO THIS APPROVED
PREVIOUS PREVIOUS TO DATE
PERIOD DATE PERIOD AMOUNT
Total 150,551.98
Less: 5 % Retention 7,527.60
PERCENTAGE
UNIT TOTAL
Item QTY. UNIT THIS
COST AMOUNT PREVIOUS
PERIOD
A. TILING WORKS -
Ground Floor Classrooms (2 units) 121.25 m2 160.00 19,400.00
Ground Floor Hallway 65.00 m3 160.00 10,400.00
Second Floor Classrooms (1 units) 60.63 m2 160.00 9,700.80
Third Floor Classrooms - m2 160.00 -
Fourth Floor - m2 - -
Water tank Deck - m2 - -
CONTRACT AMOUNT 39,500.80 0.00% 0.00%
0.00%
GREEMENT
CLASSROOM)
ERCENTAGE AMOUNT
TO THIS
PREVIOUS TO DATE
DATE PERIOD APPROVED AMOUNT
0% - - -
0% - - -
0% - - -
0% - - -
0% - - -
0% - - -
0.00% - - -
Total 0.00
Less: 5 % Retention 0.00
A. WALLS
Exterior Walls
Ground Floor 102.00 m2 75.00 7,650.00 0.02 5,799.01
Second Floor 84.00 m2 75.00 6,300.00 0.02 4,775.66
Third Floor 84.00 m2 75.00 6,300.00 0.02 4,775.66
Fourth Floor 86.00 m2 75.00 6,450.00 0.02 4,889.36
Roof beam level- A frame 49.00 m2 75.00 3,675.00 0.01 2,785.80
Interior Walls
Ground Floor 282.00 m2 75.00 21,150.00 0.06 16,032.57
Second Floor 278.00 m2 75.00 20,850.00 0.06 15,805.15
Third Floor 278.00 m2 75.00 20,850.00 0.06 15,805.15
Fourth Floor 280.00 m2 75.00 21,000.00 0.06 15,918.86
Drywall Partition included m2 75.00 - -
Blackboard 76.00 m2 75.00 5,700.00 0.02 4,320.83
B. FLOOR COLUMNS - - -
Exterior Columns - - -
Ground Floor 72.00 m2 75.00 5,400.00 0.02 4,093.42
Second Floor 65.00 m2 75.00 4,875.00 0.01 3,695.45
Third Floor 65.00 m2 75.00 4,875.00 0.01 3,695.45
Fourth Floor 65.00 m2 75.00 4,875.00 0.01 3,695.45
Interior Columns - - -
Ground Floor 44.00 m2 75.00 3,300.00 0.01 2,501.54
Second Floor 40.00 m2 75.00 3,000.00 0.01 2,274.12
Third Floor 40.00 m2 75.00 3,000.00 0.01 2,274.12
Fourth Floor 40.00 m2 75.00 3,000.00 0.01 2,274.12
C. BEAMS - - -
Exterior Beams - - -
Second Floor 28.00 m2 75.00 2,100.00 0.01 1,591.89
Third Floor 28.00 m2 75.00 2,100.00 0.01 1,591.89
Fourth Floor 28.00 m2 75.00 2,100.00 0.01 1,591.89
Roof beam level 28.00 m2 75.00 2,100.00 0.01 1,591.89
Interior Beams - - -
Second Floor 104.00 m2 75.00 7,800.00 0.02 5,912.72
Third Floor 104.00 m2 75.00 7,800.00 0.02 5,912.72
Fourth Floor 104.00 m2 75.00 7,800.00 0.02 5,912.72
Roof beam level n/a m2 75.00 - -
D. CEILING - - -
Concrete Slab soffit - -
Ground Floor 199.00 m2 75.00 14,925.00 0.05 11,313.76
Second Floor 199.00 m2 75.00 14,925.00 0.05 11,313.76
Third Floor 199.00 m2 75.00 14,925.00 0.05 11,313.76
Stair soffit 27.00 m2 75.00 2,025.00 0.01 1,535.03
Sunbreaker/wdo canopy 58.00 m2 75.00 4,350.00 0.01 3,297.48
Hardiflex Ceiling Board - - -
Ground Floor-cr 12.00 m2 75.00 900.00 0.00 682.24
Second Floor-cr 11.50 m2 75.00 862.50 0.00 653.81
Third Floor-cr 11.50 m2 75.00 862.50 0.00 653.81
Fourth Floor -cr,room and 218.50 m2 75.00 16,387.50 0.05 12,422.40
Ceiling eaves 85.00 m2 75.00 6,375.00 0.02 4,832.51
Ceiling vent n/a pcs 75.00 - -
E. DOORS AND WINDOWS - - -
Panel and flush Doors - - -
D-1 90 X 210cm-rooms 64.00 m2 75.00 4,800.00 0.01 3,638.60
D-2 80 x 210cm - cr door 4.00 m2 75.00 300.00 0.00 227.41
D-3 70 x 210cm - storage 32.00 m2 75.00 2,400.00 0.01 1,819.30
D-4 60 x 120cm - cr cubicl 16.00 m2 75.00 1,200.00 0.00 909.65
D-5 90 x 210cm - pwd 4.00 m2 75.00 300.00 0.00 227.41
Door jamb - - -
D-1 90 X 240cm-rooms 106.00 l.m. 40.00 4,240.00 0.01 3,214.09
D-2 80 x 210cm - cr door 5.00 l.m. 40.00 200.00 0.00 151.61
D-3 70 x 210cm - storage 40.00 l.m. 40.00 1,600.00 0.00 1,212.87
D-4 60 x 120cm - cr cubicl 26.00 l.m. 40.00 1,040.00 0.00 788.36
D-5 90 x 210cm - pwd 5.00 l.m. 40.00 200.00 0.00 151.61
Window wooden jamb - -
W2-140 x 150cm-rooms 16.00 pcs 200.00 3,200.00 0.01 2,425.73
W3-635 x 180cm- cr n/a pcs 160.00 - -
W4-635 x 60cm- cr 12.00 pcs 100.00 1,200.00 0.00 909.65
F. STEEL - - -
Stair and railing - - -
Ground Floor 39.00 m2 75.00 2,925.00 0.01 2,217.27
Second Floor 39.00 m2 75.00 2,925.00 0.01 2,217.27
Third Floor 41.00 m2 75.00 3,075.00 0.01 2,330.98
Steel wdo & wdo grilles - - -
W1-170 X 360cm-rooms St 196.00 m2 75.00 14,700.00 0.04 11,143.20
W2-170 x 160cm-rooms-gri 16.00 pcs 100.00 1,600.00 0.00 1,212.87
PAGE 2/2 (LUMAMPONG-FINISHING-PAINTING)
Hallway Pipe Railing -
Ground Floor 6.00 pcs 150.00 900.00 0.003 682.24
Second Floor 6.00 pcs 150.00 900.00 0.003 682.24
Third Floor 6.00 pcs 150.00 900.00 0.003 682.24
Fourth Floor 5.00 pcs 150.00 750.00 0.002 568.53
Flourescent hanger 24.00 pcs 40.00 960.00 0.003 727.72
Down spout pvc 135.00 l.m. 40.00 5,400.00 0.016 4,093.42
Fire pro b.i. pipe riser 13.00 l.m. 40.00 520.00 0.002 394.18
Water tank stair 1.00 units 1,200.00 1,200.00 0.004 909.65
Ramp Railing 2.00 units 1,200.00 2,400.00 0.007 1,819.30
Fire Exit Stair 125.00 m2 75.00 9,375.00 0.028 7,106.63
CONTRACT AMOUNT 250,000.00 250,000.00
32979750
Checked by:
GREEMENT # 5
G WORKS
As of June 06,2019
PERCENTAGE AMOUNT
APPROVE
THIS TO THIS D
PREVIOUS PREVIOUS TO DATE
PERIOD DATE PERIOD AMOUNT
0% - - -
0% - - -
0% - - -
0% - - -
0% - - -
60% 60% 2,456.05 - 2,456.05
0% - - -
75% 75% 682.24 - 682.24
80% 80% 1,455.44 - 1,455.44
50% 45% 95% 3,553.32 3,197.99 6,751.30 17,666.14
80.78% 2.44% 84.65% 201,959.16 6,106.02 211,618.49
Total 211,618.49
Less: 5 % Retention 10,580.92
AÑO
PROJECT: CONSTURCTION OF 4 STOREY EIGHT CLASSROOM BUILDING AT LUMAMPONG NATIONAL HIGH SCHOOL
LOCATION: CALUMPANG CERCA, INDANG, CAVITE
CONTRACTOR: RONALD ALENABO
PERCENTAGE %
TOTAL
Item AMOUNT PREVIOUS
Noted by:
0.00% - - -
0.00% - - -
Total 9,500.00
5% RETENTION 475.00
Net Amount: 9,025.00
Less: Previous Collection -
Billable Amount 9,025.00
PERCENTAGE %
TOTAL
Item THIS
AMOUNT PREVIOUS PERIOD
Noted by:
- - -
100.00% 11,900.00 2,100.00 14,000.00
100.00% 15,300.00 2,700.00 18,000.00
100.00% 11,700.00 6,300.00 18,000.00
Total 70,000.00
10% RETENTION 7,000.00
Net Amount: 63,000.00
Less: Previous Collection 61,000.00
Billable Amount 2,000.00