Escolar Documentos
Profissional Documentos
Cultura Documentos
Ref: SS/QA-4
Daily Inspection Report
Date 01/11/13
QA/QC Inspection of prestressed sleepers for track work for DTL1, DTL2 and NSLE at For LTA C9309
ACPM Factory, Pontian, Johor Contract
Production
OBSERVATION (S) Action
Area
Setsco Start 0830hrs - finish 2030hrs.
Inspec
tor
(i) Mainline Sleepers:
a. Transfer age average cube strength test results at 12hrs - 42.55 & 43.45N/mm 2.
b. De-tensioning/cutting/de-moulding/trimming of PC wires - start 1130hrs - stop
1600hrs.
De-moulding (ii) Turnout Bearers:
(Min. No activity.
30.0 N/mm2) (iii) Depot Ballasted Sleepers:
No activity.
(iv) Guard Rail Sleepers:
No activity.
(i) Mainline Sleepers:
Preparation of moulds and inserts - start 1330hrs - stop 1700hrs.
(ii) Turnout Bearers:
Preparation of moulds and inserts - start 0930hrs - stop 1230hrs.
Mould
(iii) Depot Ballasted Sleepers:
No activity.
(iv) Guard Rail Sleepers:
No activity.
(i) Mainline Sleepers:
Preparation of PC wires - start 1710hrs - finish 1950hrs.
(ii) Turnout Bearers:
PC Wire Preparation of PC wires - start 1400hrs - finish 1620hrs.
Installation (iii) Depot Ballasted Sleepers:
No activity.
(iv) Guard Rail Sleepers:
No activity.
(i) Mainline Sleepers:
Tensioning of PC wire - start 2000hrs - finish 2030hrs.
(ii) Turnout Bearers:
Tensioning of PC wire - start 1630hrs - finish 1700hrs.
Tensioning
(iii) Depot Ballasted Sleepers:
No activity.
(iv) Guard Rail Sleepers:
No activity.
Reported by Setsco Inspector: Zainal B. Sariman Vetted by QA Engineer: Tan HK
SETSCO Services Pte Ltd Form. Ref: SS/QA-4
Daily Inspection Report
Date 01/11/13
QA/QC Inspection of prestressed sleepers for track work for DTL1, DTL2 and NSLE at For LTA C9309
ACPM Factory, Pontian, Johor Contract
a. ACPM office will be closed on the 02/11 & 05/11/13 due to public holidays.
b. Casting of depot ballasted sleepers was temporarily stopped since 29/06/13 due to
Remarks current available moulds are used for casting of BBG-JV Project. No information
is received from ACPM on the date of resumption of casting.
Safety Issues
(i) No major breach of safety rules.
NCRs with Corrective Action raised/closed out by Summary of NCRs raised/ closed
Nil.
ACPM
Nil.
A. Highlights of Inspection
(i) As to date, the mainline sleeper production (since 28/09/10) is summarized in table 1 below.
(ii) As to date, the turnout bearer production (since 19/07/11) is summarized in table 2 (Depot, Mainline,
NSLE & BTW) below.
Table 2: Summary of turnout bearers (Depot, Mainline, NSLE & BTW) production as at 01/11/13:
(iii) As to date, the depot ballasted sleepers production (since 24/10/11) is summarized in table 3 below.
(iv) As informed by ACPM/ALSTOM, production of guard rail sleepers was stopped on the 06/12/12 as
the required quantity had been achieved. Detailed breakdown of the guard rail sleepers production and
delivery as at 07/12/12 is as presented in table 4 below.
(i) Nil.
(3) Others
(i) Nil.