Você está na página 1de 3

Preliminary inspection report of line # 80-SCL-6016600-BB31C at VCM Plant UNIT-60(Pipe rack)

Plant: VCM Unit-60


Date: 24-05-2016

Background:
Leakage was reported by VCM Operation Department from line # 80-SCL-6016600-BB31C in Pipe
rack.External visual inspection and UT thickness monitoring were carried out adjacent to location of
leaked pipe and other accessible area(with scaffolding) of connecting branch line # 25-SCL-02213-
BB31C(Steam condensate outlet line of TE-1306).The following were the observations:
Observations:
1.0 External Visual inspection :
 Leakage was observed at bottom portion of 3" Ø pipe of line # 80-SCL-6016600-BB31C.
 Temporarily repaired by furmanite clamp was found at 1" Ø Tee of line # 25-SCL-02213-BB31C.
2.0 UT thickness measurement :
 Random UT thickness measurement was carried out on all established TMLs and reduction of
thickness recorded with a minimum of 1.3 mm & 1.6 mm thickness against the nominal thickness of
2.6 mm & 2.9 mm for 1" Ø & 3" Ø respectively (As per piping specification) with 1.2 mm corrosion
allowance.
.

LEAKAGE AT BOTTOM PORTION OF 3" Ø PIPE OF LEAKAGE AT BOTTOM PORTION OF 3" Ø PIPE OF
LINE # 80-SCL-6016600-BB31C LINE # 80-SCL-6016600-BB31C (FULL VIEW)

TEMPORARILY REPAIRED BY FURMANITE CLAMP TEMPORARILY REPAIRED BY FURMANITE CLAMP


AT 1" Ø TEE OF LINE # 25-SCL-02213-BB31C BB31C AT 1" Ø TEE OF LINE # 25-SCL-02213-BB31C BB31C
Form No.: INSP-046-02
Rev. No.: 02 EQUIPMENT / PIPING THICKNESS MEASUREMENT SHEET
Dated: 07-09-2015
SMP / WI No.: SMP-INSP-051
INSPECTION DEPARTMENT
Page: 1 of 1
Thickness Thickness Reading
Orig.
Drawing / Sketch Measurement (mm)
Thk. Remark(s)
Location *
(mm) 0 90 180 270 N E S W
(TMLs)
1- 3"Ø 2.9 2.9 2.9 2.9 3.0
NORTH 2- 3"Ø 2.9 5.0 5.0 5.1 5.1
3- 3"Ø 2.9 5.0 1.6 5.0 5.1 LEAKAGE
4- 3"Ø 2.9 5.0 5.1 5.1 5.1
5- 3"Ø 2.9 2.6 2.8 2.9 2.9
6- 1"Ø 2.6 4.1 4.2 4.1 4.2
7- 1"Ø 2.6 4.1 4.0 4.1 4.2
8- 1"Ø 2.6 1.3 - 4.0 4.1 BEND PIPE
9- 1"Ø 2.6 4.0 4.1 1.4 - BEND PIPE
10- 1"Ø 2.6 4.1 4.1 4.2 4.1
11- 1"Ø 2.6 4.1 4.2 4.1 4.2
12- 1"Ø 2.6 1.3 - 4.1 4.2 BEND PIPE
13- 1"Ø 2.6 4.1 4.0 4.0 4.1

Thickness Gauge S.R. No. : DMS 2 # 01VKH1 (INSP-TM-03)


Calibration date : 08-06-2015
Probe # and Frequency : HT 400 / 5 MHZ
Applicable Procedure : PK SHEM 7.05 & SMP-INSP-051
Criteria for passing Inspection :
Eqpt. / Piping Material : ST 35 ( CARBON STEEL )
Corrosion Allowance (mm) : 1.2 mm
Corrosion Rate (mm / Year) : 1.3 mm
Remaining Life (Year) :
Surface Temperature (ºC) : 105
Condition of Piping : Satisfactory Unsatisfactory X
Recommendation (if any) :

Plant : VCM UNIT-60 Description : Inspector(s) : MARIO / ALI Date : 24-05-2016


Eqpt / Line No. : 80-SCL-6016600-BB31C Service : STEAM CONDENSATE (SCL)

* Nozzle size to be specified


Recommendations:
 Replace leaked portion of 3”Ø pipe (TML # 3) and 1”Ø bend pipe low thickness area (TML# 8,9 & 12) .
 Replace furmanite clamp as shown in the above sketch (line no #25-SCL-02213-BB31C) in the nearest
opportunity.
 For replacement activity, Maintenance has to submit the repair / Welding Procedure Specification (WPS)
to INSP for review and approval.
 Fit-up, root & final visual / Dye penetrant test (DPT), Radiographic testing & Hydro testing (if possible) will
be performed after the welding repair to ensure the quality of welding.
 VCM operation has to ensure all the requirements / guidelines mentioned as per the procedure (CGPE-
012) for temporary repair (Furmanite clamp) in the line

Prepared by:
Mario, Ali

Reviewed by:
Hazaa M. Al-Harbi

Você também pode gostar