Escolar Documentos
Profissional Documentos
Cultura Documentos
Background:
Leakage was reported by VCM Operation Department from line # 80-SCL-6016600-BB31C in Pipe
rack.External visual inspection and UT thickness monitoring were carried out adjacent to location of
leaked pipe and other accessible area(with scaffolding) of connecting branch line # 25-SCL-02213-
BB31C(Steam condensate outlet line of TE-1306).The following were the observations:
Observations:
1.0 External Visual inspection :
Leakage was observed at bottom portion of 3" Ø pipe of line # 80-SCL-6016600-BB31C.
Temporarily repaired by furmanite clamp was found at 1" Ø Tee of line # 25-SCL-02213-BB31C.
2.0 UT thickness measurement :
Random UT thickness measurement was carried out on all established TMLs and reduction of
thickness recorded with a minimum of 1.3 mm & 1.6 mm thickness against the nominal thickness of
2.6 mm & 2.9 mm for 1" Ø & 3" Ø respectively (As per piping specification) with 1.2 mm corrosion
allowance.
.
LEAKAGE AT BOTTOM PORTION OF 3" Ø PIPE OF LEAKAGE AT BOTTOM PORTION OF 3" Ø PIPE OF
LINE # 80-SCL-6016600-BB31C LINE # 80-SCL-6016600-BB31C (FULL VIEW)
Prepared by:
Mario, Ali
Reviewed by:
Hazaa M. Al-Harbi