Rate Analysis for Lightning work

Supply & Installing Air Terminal with all other accessories


P.sum 1
with boult and Nut
Per Nos
Description Unit Qty Rate Amount
Air terminal No 1 10,800.00 10,800.00
Air terminal mounting base
Arrengement No 1 2,000.00 2,000.00
Boult & nut Stainless Steel No 4 25.00 100.00
Self screw No 4 13.00 52.00
Electrician (Special) Day 0.5 1,500.00 750.00
Electrician Helper Day 0.5 1,300.00 650.00
Add transport 200.00
Allow for Scaffolding Item 300.00
Allow for tools and equipment Item 300.00
Total 15,152.00
Over head 22% 3,333.44
Per No 18,485.44
Say Rs 18,530.00

Supply & Fixing of Copper tape for down or earth conductor


P.sum 2
and clip support at maximum interval 450mm in roof
Per Lm
Consider 15m
Description Unit Qty Rate Amount
Copper Tap M 15 2,296.00 34,440.00
Clip Support No 35 200.00 7,000.00
Self screw 1" No 70 8.00 560.00
Nut No 70 3.00 210.00
Electrician (Special) Day 1 1,500.00 1,500.00
Electrician Helper Day 1 1,300.00 1,300.00
Allow for tools, Scaffolding and
equipment Item 300.00
Allow Scaffolding Item 300.00
Tansport 200.00
Total 45,810.00
Over head 22% 10,078.20
Per 10m 55,888.20
Per Lm 3,725.88
Say Rs Lm 3,715.00

Supply & Installation of pure copper plate with the dimension


P.sum 3
of 600x600 rate including excavation and civil works.

Per Nos
Description Unit Qty Rate Amount
Copper plat 600 x 600 M 1 31,900.00 31,900.00
Excavation M3 1.5 2,500.00 3,750.00
Electrician Day 0.5 1,500.00 750.00
Electrician (Special) Day 0.5 1,300.00 650.00
Electrician Helper M3 1.5 4,593.64 6,890.46
Unskilled Labour Day 0.25 1,200.00 300.00
Transport Allow 100.00
Allow for tools and equipment Item 300.00
Total 44,640.46
Over head 22% 9,820.90
Per No 54,461.36
Say Rs 54,370.00

P.sum 4 Supply & Installation of Testing clamp

Per Nos
Description Unit Qty Rate Amount
Testing clamp No 1 2,300.00 2,300.00
Screw 1" x 6 No 2 5.00 10.00
Electrician Day 0.25 1,500.00 375.00
Labour Day 0.25 1,200.00 300.00
Allow for transport Item 100.00
Allow for tools and equipment Item 100.00
Total 3,185.00
Over head 22% 700.70
Per No 3,885.70
Say Rs 3,900.00
Tessting the total installtion and submit the report by
P.sum 5
Electrical charted engineer

Per Item
Say Rs 25,000.00
1254.5

33.333333
8.49

10,764.00 1254.5

3,135.60 1254.5
3,834.00 1254.5
Rate Analysis for Electrical Work (BOQ Item Q1)
Supply & Fixing 18 w Circular type LED lamp ( Ceiling
P.sum 1 mount ) fittings and proper wiring arrangement to complete
the work
Per Nos
Description Unit Qty Rate Amount Remark
Flexible wire 1" M 1 60.00 60.00
Switch No 1 136.00 136.00
Screw 1" x 6 No 2 3.00 6.00
Sunk box No 1 40.00 40.00
1/.044 wire M 20 19.30 386.00
Conduit pipe 1" M 2 28.50 57.00
Insulation tape No 0.5 40.00 20.00
Electrician Day 0.5 1500.00 750.00
Labour Day 0.5 1200.00 600.00
18 w Circular type LED lamp
( Ceiling mount ) No 1 1700.00 1700.00
Allow for tools and equipment Item 300.00
Total 4,055.00
Over head 22% 892.10
Per No 4,947.10
Say Rs 4,945.00

Supply & Fixing 18 w Circular type LED lamp fittings( Down


P.sum 2
light ) and proper wiring arrangement to complete the work
Per Nos
Description Unit Qty Rate Amount Remark
Flexible wire 1" M 1 60.00 60.00
Switch No 1 136.00 136.00
Sunk box No 1 40.00 40.00
1/.044 wire M 20 19.30 386.00
Conduit pipe 1" M 2 28.50 57.00
Insulation tape No 0.5 40.00 20.00
Electrician Day 0.5 1500.00 750.00
Labour Day 0.5 1200.00 600.00
18 w Circular type LED lamp
( Down light ) No 1 1400.00 1400.00
Allow for tools and equipment Item 300.00
Total 3,749.00
Over head 22% 824.78
Per No 4,573.78
Say Rs 4,575.00

Supply & Installation of ceiling fan approved quality 56"


P.sum 3 (KDK) sweep with regulator and proper wiring arrangement
to complete the work

Per Nos
Description Unit Qty Rate Amount Remark
Flexible wire 1" M 1 60.00 60.00
Switch No 1 136.00 136.00
Screw 1" x 6 No 2 3.00 6.00
Sunk box No 1 40.00 40.00
1/.044 wire M 20 19.30 386.00
Conduit pipe 1" M 2 28.50 57.00
Insulation tape No 0.5 40.00 20.00
Electrician Day 0.5 1500.00 750.00
Labourer Day 0.5 1200.00 600.00
Installation
Ceiling fan 56" (KDK) No 1 8280.00 8280.00
Hooks No 1 200.00 200.00
Earth wire 7/.029 M 15 57.39 860.85
3 core wire M 1 122.30 122.30
Electrician Day 0.125 1500.00 187.50
Labour Day 0.5 1200.00 600.00
Transport Allow 100.00
Allow for tools and equipment Item 300.00
Total 12,705.65
Over head 22% 2,795.24
Per No 15,500.89
Say Rs 15,500.00
Supply & Fixing of 1200 mm soffit mounded single fluorescent
P.sum 4 lamp with proper wiring arrangement and switch etc.All
complete to working order.

Per Nos
Description Unit Qty Rate Amount Remark
Round plug No 1 13.00 13.00
Switch No 1 136.00 136.00
Ceiling rose No 1 71.25 71.25
Holder with Adapter No 1 80.00 80.00
Flexible wire 1" M 1 60.00 60.00
Screw 1" x 6 No 2 3.00 6.00
Sunk box No 1 40.00 40.00
1/.044 wire M 20 19.30 386.00
2 core wire M 1 83.84 83.84
Conduit pipe 1" M 5 28.50 142.50
Insulation tape No 0.5 40.00 20.00
Electrician Day 0.5 1500.00 750.00
Labour Day 0.5 1200.00 600.00
1200 mm soffit mounded single
fluorescent lamp No 1 1000.00 1000.00

Allow for transport Item 1 50.00


Allow for tools and equipment Item 300.00
Total 3,738.59
Over head 22% 822.49
Per No 4,561.08
Say Rs 4,560.00
Supply & Fixing (14 w) water Tight lamp fittings and proper
P.sum 5
wiring arrangement to complete the work

Per Nos
Description Unit Qty Rate Amount Remark
Flexible wire 1" M 1 60.00 60.00
Switch No 1 136.00 136.00
Sunk box No 1 40.00 40.00
1/.044 wire M 20 19.30 386.00
Conduit pipe 1" M 5 28.50 142.50
Insulation tape No 0.5 40.00 20.00
Electrician Day 0.5 1500.00 750.00
Labour Day 0.5 1200.00 600.00
Water Tight lamp fittings No 1 650.00 650.00
CFL bulb 14w No 1 595.00 595.00
Allow for transport Item 50.00
Allow for tools and equipment Item 300.00
Total 3,729.50
Over head 22% 820.49
Per No 4,549.99
Say Rs 4,550.00

Supply & Fixing of 13 Amp. Socket out - w/ switch with proper


P.sum 6
wiring arrangement to complete the work

Per Nos
Description Unit Qty Rate Amount Remark
Plug with switch (Clipsal) No 1 471.75 471.75
7/.067 wire, M 10 123.04 1230.40
Screws (1 1/2"x6), brass No 2 12.50 25.00
Sunk box No 1 40.00 40.00
Earth wire 7/.029 M 10 57.39 573.90
Conduit pipe M 5 28.50 142.50
Electrician mate Day 0.5 1500.00 750.00
Total 3,233.55
Over head 22% 711.38
Per No 3,944.93
Say Rs 3,945.00

Supply & Fixing of 5 Amp. Socket out - w/ switch with proper


P.sum 7
wiring arrangement to complete the work

Per Nos
Description Unit Qty Rate Amount Remark
Plug with switch (Clipsal) No 1 416.50 416.50
Brass screws (1 1/2"x6) Nos. 2 12.50 25.00
Sunk box No 1 40.00 40.00
1/.044 wire M 20 19.30 386.00
Earth wire 7/.029 M 10 57.39 573.90
Conduit pipe M 5 28.50 142.50
Electrician Day 0.50 1500.00 750.00
Mason Day 0.25 1450.00 362.50
Allow for tools and equipment Item 300.00
Total 2,996.40
Over head 22% 659.21
Per No 3,655.61
Say Rs 3,655.00

1800 way ABC distribution box with necessary fitting in upper


P.sum 8
floor
Per Nos
Description Unit Qty Rate Amount Remark
1800way ABC box No 1 2000.00 2000.00
Main switch 40 Amp No 1 1020.00 1020.00
Main switch 63 Amp No 1 1062.00 1062.00
RCCB 40 Amp No 1 3264.00 3264.00
Barkers No 11 268.83 2957.13
Bus bar copper No 12 30.00 360.00
Conduit pipe M 3 28.50 85.50
Electrician Day 2 1500.00 3000.00
Labour Day 2 1200.00 2400.00
Mason Day 0.5 1450.00 725.00
Allow for tools and equipment Item 300.00
Total 17,173.63
Over head 22% 3,778.20
Per No 20,951.83
Say Rs 20,950.00

1800 way ABC distribution box with necessary fitting in


P.sum 9
Ground floor
Per Nos
Description Unit Qty Rate Amount Remark
1800way ABC box No 1 2000.00 2000.00
Main switch 40 Amp No 1 1020.00 1020.00
RCCB 40Amp No 1 3264.00 3264.00
Barkers No 11 268.83 2957.13
Bas bar copper No 12 30.00 360.00
Conduit pipe M 2 28.50 57.00
Electrician Day 2 1500.00 3000.00
Labour Day 2 1200.00 2400.00
Mason Day 0.5 1450.00 725.00
Allow for tools and equipment Item 300.00
Total 16,083.13
Over head 22% 3,538.29
Per No 19,621.42
Say Rs 19,620.00

Supply and fixing earthning system with copper rod and


P.sum 10
necessary wiring & fitting )

Per Item

Description Unit Qty Rate Amount Remark

Copper rod No 2 500.00 1000.00

Earth wire 7/.029 M 48 57.39 2754.72

Conduit pipe M 25 28.50 712.50

Electrician Day 2 1500.00 3000.00

Labour Day 2 1200.00 2400.00

Allow for tools and equipment Item 300.00

Total 10,167.22
Over head 22% 2,236.79
Per No 12,404.01
Say Rs 12,400.00

Supply and Laying 1/0.04 6 mm2 Cu/PVC/ 2 C cable from DB to


P.sum 11
CEB
Per Item

Description Unit Qty Rate Amount Remark


1/0.04 6 mm2 Cu/PVC/ 2 C cable Lm 56 283.04 15850.24

Conduit pipe M 28 28.50 798.00

1" x 1" casing M 5 175.00 875.00

Electrician Day 2 1500.00 3000.00

Labour Day 3 1200.00 3600.00

Allow for tools and equipment Item 300.00

Total 24,423.24
Over head 22% 5,373.11
Per No 29,796.35

Say Rs 29,795.00

Rate Analysis for Electrical Work (BOQ Item Q2)


P.sum 1 Allow for CEB services connection

Per Item
Description Unit Qty Rate Amount Remark
21/2 x 21/2 bracket No 1 5000.00 5000.00
Anger bolt nut No 4 150.00 600.00
Electrician Day 1 1500.00 1500.00
Labour Day 1 1200.00 1200.00
Allow for tools and equipment Item 1000.00
CEB Services Connection
Services connection 18846.80
32mm PVC pipe Lm 4 84.19 336.75
32mm Bend PVC No 8 30.00 240.00
Total 28,723.55
Over head 22% 6,319.18
Per No 35,042.73
Say Rs 35,040.00
Remark

1254.5

Remark
1254.5

Remark

6950

8,280.00

10,764.00 1254.5
Remark

3,135.60 1254.5
Remark

3,834.00 1254.5

Remark
1254.5

Remark

1254.5

Remark
1254.5

Remark

1254.5

Remark
1254.5

Remark

1254.5

Remark
1254.5
Summary for BOQ Item Q1
Item No Description Unit Qty Rate Amount
Supply & Fixing 18 w Circular type LED
P.sum 1 lamp ( Ceiling mount ) fittings and proper Nos 12 4,945.00 59,340.00
wiring
Supplyarrengement
& Fixing 18 to
w complete the work
Circular type LED
lamp fittings( Down light ) and proper wiring Nos 15 4,575.00 68,625.00
P.sum 2 arrangement to complete the work
Supply & Installation of ceiling fan approved
quality 56" (KDK) sweep with regulator and Nos 12 15,500.00 186,000.00
proper
Supplywiring arrangement
& Fixing of 1200 mmto complete the
soffit mounded
P.sum 3 work
single fluorescent lamp with proper wiring
arrangement and switch etc.All complete to Nos 23 4,560.00 104,880.00
P.sum 4 working
Supply &order.
Fixing (14 w) water Tight lamp
fittings and proper wiring arrangement to Nos 2 4,550.00 9,100.00
P.sum 5 complete
Supply & the workof 13 Amp. Socket out - w/
Fixing
switch with proper wiring arrangement to Nos 12 3,945.00 47,340.00
P.sum 6 complete
Supply & the workof 5 Amp. Socket out - w/
Fixing
switch with proper wiring arrangement to Nos 6 3,655.00 21,930.00
P.sum 7 complete the work
1800 way ABC distribution box with Nos 1 20,950.00 20,950.00
P.sum 8 necessary fitting in upper floor
1800 way ABC distribution box with Nos 1 19,620.00 19,620.00
P.sum 9 necessary fitting in Ground floor
Supply and fixing earthning system with 1 12,400.00 12,400.00
P.sum 10 copper rod and necessary wiring & fitting ) Item
Supply and Laying 1/0.04 6 mm2 Cu/PVC/ 2 1 29,795.00 29,795.00
P.sum 11 C cable from DB to CEB Item
Total 579,980.00

Summary for BOQ Item Q2

P.sum 1 Allow for CEB services connection Item 1 35,040.00 35,040.00

Total 35,040.00
Summary for BOQ Item Q1
Item No Description Unit Qty Rate
Supply & Fixing 18 w Circular type LED lamp
P.sum 1 ( Ceiling mount ) fittings and proper wiring Nos 19 4,945.00
arrengement to complete
Supply & Fixing the work
18 w Circular type LED lamp
fittings( Down light ) and proper wiring arrangement to Nos 22 4,575.00
P.sum 2 complete the work
Supply & Installation of ceiling fan approved quality
56" (KDK) sweep with regulator and proper wiring Nos 24 15,500.00
P.sum 3 arrangement to complete
Supply & Fixing of 1200 the
mmwork
soffit mounded single
fluorescent lamp with proper wiring arrangement and Nos 22 4,560.00
P.sum 4 switch etc.All complete to working order.
Supply & Fixing (14 w) water Tight lamp fittings and Nos 5 4,550.00
P.sum 5 proper wiring arrangement to complete the work
Supply & Fixing of 13 Amp. Socket out - w/ switch Nos 14 3,945.00
P.sum 6 with proper wiring arrangement to complete the work
Supply & Fixing of 5 Amp. Socket out - w/ switch with Nos 7 3,655.00
P.sum 7 proper wiring arrangement to complete the work
1800 way ABC distribution box with necessary fitting Nos 1 20,950.00
P.sum 8 in upper floor
1800 way ABC distribution box with necessary fitting Nos 1 19,620.00
P.sum 9 in Ground floor
Supply and fixing earthning system with copper rod 1 12,400.00
P.sum 10 and necessary wiring & fitting ) Item
Supply and Laying 1/0.04 6 mm2 Cu/PVC/ 2 C cable 1 29,795.00
P.sum 11 from DB to CEB Item
Total

Summary for BOQ Item Q2


1 35,040.00
P.sum 1 Allow for CEB services connection Item
Total
Amount

93,955.00

100,650.00

372,000.00

100,320.00

22,750.00

55,230.00

25,585.00

20,950.00

19,620.00

12,400.00

29,795.00

853,255.00

35,040.00

35,040.00