Você está na página 1de 5

feature

Best Management Practices On


Soil Erosion And Sediment Control
In The Construction Industry Part 2
By Tew Kia Hui, Director/Soil Erosion Research Consultant, VT Soil Erosion Research & Consultancy

INCORPORATING BEST scheduling techniques should be Shrubs and trees must be


MANAGEMENT PRACTICES compared with other less effective adequately watered, fertilised, and
FOR EROSION AND erosion and sediment controls to pruned if needed. Grass may need to
SEDIMENT CONTROL achieve a cost-effective balance. be watered and mowed too.
However, permanent and
Specific BMPs should be ■ Preservation of temporary vegetation may not be
incorporated for common Existing Vegetation appropriate in dry periods without
construction activities that result in Carefully planned preservation of irrigation. Fertiliser requirements
erosion of construction sites and the existing vegetation minimises the may have the potential to create
generation of sediment, which impact potential of removing or injuring stormwater pollution if improperly
waterways and off-site properties. existing trees, shrubs, and/or grass applied.
Recommended erosion and that serve as erosion controls.
sediment control measures for Corridors of vegetation act as ■ Mulching
construction sites are summarised in buffer zones to separate disturbed Mulching is a temporary ground
Table 2 in relation to BMP objectives, land from an adjacent watercourse, covering that protects the soil from
and this information is suitable for protected forest, or other sensitive rainfall impacts, increases infiltration,
inclusion in the ESCP. areas. Leaving a clearly marked conserves moisture around trees,
buffer zone around these unique areas shrubs, and seedings, prevents
Site Planning Considerations will help to preserve them, as well as compaction and cracking of soil, and
benefiting from their natural erosion aids the growth of seedings and plants
■ Scheduling prevention and trapping by holding the seeds, fertilisers and
Defined as sequencing the characteristics. topsoil in place until growth occurs.
construction project to reduce the The inspection and maintenance
amount and duration of soil exposed requirements for protection of
to erosion by wind, rain, runoff, and vegetation are low and there is little
vehicle tracking. Proper sequencing cost associated with preserving
of construction activities should be existing vegetation if properly
incorporated into the schedule of planned during the project design.
every construction project. However, Aesthetic benefits may also enhance
use of other more costly yet less property values.
effective erosion and sedimentation
controls may often be reduced Vegetative Stabilisation
through proper construction
sequencing. ■ Seeding and Planting Mulching can be used either to
The approach would be to Seeding of grass and planting of temporarily or permanently stabilise
integrate into existing land contours trees, shrubs and ground covers cleared or freshly seeded areas. Types
as far as practicable, incorporate provide long-term stabilisation of soil. of mulches include organic materials,
existing natural areas, avoid rainy Grass may also be planted for straw, wood chips, bark or other wood
periods, practise erosion and sediment temporary stabilisation. It is fibres, decomposed granite and
control all year round, minimise the appropriate for site stabilisation - both gravel. A variety of mats of organic
extent of soil exposed at any one time during and after construction - in any or inorganic materials and chemical
and also carry out trenching graded or cleared areas where stabilisation may be used with
operations. construction activities have ceased, mulches.
This procedure may increase other open space, cut and fill areas, steep Mulch prevents erosion by
construction costs due to reduced slopes, spoil stockpiles, vegetated protecting the soil surface and
economies of scale in performing site swales, landscape corridors and fostering growth of new seedings that
grading. The cost-effectiveness of stream banks. do not stabilise by themselves.

B U L E T I N I N G E N I E U R 39
feature
Table 2: Erosion and sediment control measures and objectives
BMP OBJECTIVES

Control Internal
Disturbed Area
Disturbed Area
Contain Waste
Standard

Numbers

Project Slopes
Housekeeping
Practise Good
Drawing

and Channels

Control Site
Perimeter
Minimise

Stabilise

Erosion
BMP CATEGORY

Site Planning Considerations


Scheduling √ √ √ √ √ √ √
Preservation of Existing Vegetation √ √ √ √
Vegetative Stabilisation
Seeding and Planting √ √
Mulching √ √
Physical Stabilisation
Geotextiles and Mats √ √
Dust Control √ √ √ √
Temporary Waterway Crossing √ √ √ √
Construction Road Stabilisation √ √ √ √
Construction Access Stabilisation √ √ √ √
Diversion of Runoff
Earth Bank √ √ √ √
Diversion Channel √ √ √
Slope Drain √
Flow Velocity Reduction
Drainage Outlet Protection √
Check Dam √
Sediment Trapping / Filtering
Sediment Fence √ √
Sand Bag Barrier √ √ √
Brush or Rock Filter √ √ √
Drainage Inlet Protection √ √
Sediment Traps √
Sediment Basins √

Organic mulch materials such as absorb and hold moisture near the soil applied in clearing and grading
straw, wood chips, bark and wood surface. Additionally, mattings may activities, construction vehicle traffic
fibre are most effective where re- be used alone or with mulch during on unpaved roads, drilling and
vegetation will be provided by the establishment of protective cover blasting activities, sediment tracking
reseeding. The choice of mulch on critical slopes. onto paved roads, soil and debris
should be based on the size of the Mattings are typically suited for storage stockpiles, batch drop from
area, site slopes, surface conditions permanent site stabilisation, but may front end loaders and areas with
(such as hardness and moisture), weed be used for temporary or permanent unstabilised soil. Final grading/site
growth and availability of mulch stabilisation of highly erosive soils. stabilisation usually is sufficient to
materials. Mattings may be applied to disturbed control post-construction dust
However, the limitation is that soils and where existing vegetation sources.
organic mulches are not permanent has been removed. Installation costs for water/
erosion control measures. Mulches Mattings, on the other hand, are chemical dust suppression are low, but
tend to lower the soil surface more costly than other BMPs, limiting annual costs may be quite high since
temperature, and may delay their use to areas where other BMPs these measures are effective for only
germination of some seeds. are ineffective (e.g. channels, steep a few hours to a few days.
slopes). They may also delay seed The limitations include watering
Physical Stabilisation germination, due to reduction in soil prevents dust only for a short period
temperature. and they should be applied daily (or
■ Geotextiles and Mats more often) to be effective, and over-
Mattings are made of natural or ■ Dust Control watering may cause erosion.
synthetic material, which are used to Dust control measures are used to
temporarily or permanently stabilise stabilise soil from wind erosion and ■ Temporary Waterway Crossing
soil. Mattings reduce erosion from reduce dust generated by construction A temporary access waterway
rainfall impact, hold soil in place, and activities. They are suitable to be crossing is a temporary culvert, ford,

B U L E T I N I N G E N I E U R 40
feature
or bridge placed across a waterway erosion, but significantly speeds on- Earth banks are typically used to
to provide access for construction site work, avoids instances of divert concentrated runoff through
purposes for a period of less than one immobilised equipment and delivery disturbed areas into another BMP (e.g.
year. Temporary access crossings are vehicles, and generally improves site a sediment trap or basin), to divert
not intended to be used by the general efficiency and working conditions runoff away from disturbed or
public. during adverse weather. unstable slopes, to divert runoff from
The roadway however, must be off-site and undisturbed areas around
removed or paved when construction disturbed areas, and as containment
is complete. Certain chemical for construction materials and wastes.
stabilisation methods may cause The on-site banks should remain in
stormwater or soil pollution and place until the disturbed areas are
should not be used. permanently stabilised and must
safely convey anticipated flood flows.
■ Construction Access Banks should not be used for
Stabilisation drainage areas greater than four
A stabilised construction access is hectares, or along slopes greater than
a stabilised pad of aggregate 10%. For larger areas, more
underlain with filter cloth located at permanent drainage structures should
The purpose of a temporary any point where traffic will be be built.
crossing is to provide a safe, erosion- entering or leaving a construction site
free access point across a waterway from or to a public right-of-way, ■ Diversion Channel
for construction equipment. An street, alley, footpath or parking area. Temporary diversion channels
engineer should establish minimum Stabilising the site entrance may be used to divert offsite runoff
standards and specifications for the significantly reduces the amount of around the construction site, divert
design, construction, maintenance sediment (dust and mud) tracked off- runoff from stabilised areas around
and removal of the structure. site, especially if a wash rack is disturbed areas, and direct runoff into
Crossings may be necessary to prevent incorporated for removing caked-on sediment traps or basins. Diversion
construction equipment from causing sediment. channels should be installed when the
erosion of the waterway and tracking Applications include all points of site is initially graded and remain in
of pollutants into the waterway. construction entry and exit from the place until permanent BMPs are
However, the temporary waterway site and unpaved areas where installed and/or slopes are stabilised.
crossings may be an expensive sediment tracking occurs from the site Diversion channels are
measure for a temporary onto paved roads. This access should appropriate for diverting any upslope
improvement and require other BMPs be used in conjunction with street runoff around unstabilised or
to minimise soil disturbance during sweeping on the adjacent public right- disturbed areas of the construction
installation and removal. of-way and it requires periodic top site in order to prevent slope failures,
dressing with additional stones. prevent damage to adjacent property,
■ Construction Road Stabilisation prevent erosion and sediments into
Access roads, subdivision roads, Diversion of Runoff waterways, increase the potential for
parking areas, and other on-site infiltration and divert sediment-laden
vehicle transportation routes should ■ Earth Bank runoff into trapping devices.
be stabilised immediately after A temporary earth bank is a However, they must conform to local
grading, and frequently maintained temporary beam or ridge of floodplain management requirements.
to prevent erosion and control dust. compacted soil used to divert runoff
Areas which are graded for or channel water to a desired location, ■ Slope Drain
construction vehicle transport and thereby reducing the potential for A slope drain is a temporary pipe
parking purposes are especially erosion and off-site sedimentation. or lined channel to drain the top of a
susceptible to erosion and dust. The Earth banks may also be used to divert slope to a stable discharge point at
exposed soil surface is continually runoff from off-site and from the bottom of a slope without causing
disturbed, leaving no opportunity for undisturbed areas away from erosion. It is typically used in
vegetative stabilisation. Such areas disturbed areas, and to divert sheet combination with an earth bank or
also tend to collect and transport flows away from unprotected slopes. diversion channel at the top of the
surface runoff. During wet weather, An earth bank does not in itself slope.
they often become muddy quagmires, control erosion or remove sediment A slope drain is effective because
which generate significant quantities from runoff; it prevents erosion by it prevents runoff from flowing
of sediment that may pollute nearby directing runoff to an erosion control directly down a slope by confining
streams or be transported off-site on device such as a sediment trap or all of the runoff into a channel or
the wheels of construction vehicles. basin, or directing runoff away from enclosed pipe. However, the
Dirt roads can become so unstable an erosive area. Temporary earth maximum drainage area per slope
during wet weather that they are banks should not adversely impact drain is two hectares. Larger areas
virtually unusable. adjacent properties and must conform would require a paved chute, rock
Efficient construction road to any local floodplain management lined channel, or additional pipes.
stabilisation not only reduces on-site regulations. Other limitations are that the clogged

B U L E T I N I N G E N I E U R 42
feature
slope drains will force water around for support. Sediment fences trap stormwater drain, drop inlet, or kerb
the pipe and cause slope erosion, and sediment by intercepting and inlet which prevents excessive
failure of the slope drain can result detaining small amounts of sediment sediment from entering stormwater
in flooding and severe erosion. from disturbed areas during drainage systems prior to permanent
construction operations in order to stabilisation.
Flow Velocity Reduction promote sedimentation behind the All on-site stormwater inlets
fence and decrease the velocity of low receiving sediment-laden runoff
■ Drainage Outlet Protection flows (up to 15 l/s) in swales and small should be protected, either by
Drainage outlet protection is a diversion channels. covering the inlet or promoting
physical device composed of rock, Sediment fences are generally sedimentation upstream of the inlet.
grouted riprap, or concrete rubble effective in locations where the flow Off-site inlets should be protected in
which is placed at the outlet of a is concentrated, and are only areas where construction activity
culvert, conduit or channel to prevent applicable for sheet overland flows tracks sediment onto paved areas or
scour of the soil caused by high flow and not to be used in streams, where inlets receive runoff from
velocities, and to absorb flow energy channels, or any places where the disturbed areas.
to produce non-erosive velocities. flow is concentrated, and in locations Drainage inlet protection is
Rock outlet protection is effective where ponded water may cause recommended only for drainage areas
when the rock is sized and placed flooding. smaller than 0.4 hectares, unless a
properly. When this is accomplished, sediment trap first intercepts the
rock outlets do much to limit erosion ■ Sand Bag Barrier runoff. However, ponding will occur
at pipe outlets. Rock size should be Stacking sand bags along a level at a protected inlet, with possible
increased for high velocity flows. The contour creates a barrier, which short-term flooding.
best results are obtained when sound, detains sediment-laden water by
durable, angular rock is used. ponding upstream of the barrier water, ■ Sediment Traps
However, large storms often wash thereby promoting sedimentation. A sediment trap is a small
away rock outlet protections and Sand bags provide a semi-permeable temporary ponding area, usually with
leave the area susceptible to erosion. barrier in potentially wet areas and a gravel outlet, formed by excavation
Sediment captured by the rock outlet are more permanent than sediment and/or construction of an earth
protection will be difficult to remove fences. They also allow for easy on- embankment. Its purpose is to collect
without removing the rock. site relocation to meet changing needs and store sediment from sites cleared
during construction. and/or graded during construction. It
■ Check Dam is intended for use on small catchment
A check dam is a small temporary Sand bag barriers are most costly, areas with no unusual drainage
dam constructed across a diversion but typically more durable, having a features, where construction will be
channel or swale. Check dams reduce longer useful life than other barriers completed in a reasonably short
the velocity of concentrated and may be used in drainage areas period of time. It should help in
stormwater flows, therefore reducing up to two hectares. removing coarse sediment from
erosion of the diversion channel or runoff. The trap is a temporary
swale and promoting sedimentation ■ Brush or Rock Filter measure with a design life of
behind the dam. If properly anchored, A rock filter berm is made of rock, approximately six months, and is to
brush or rock filter berms may be used with diameter between 20 to 75 mm, be maintained until the site area is
for check dams. placed along a level contour where permanently protected against
Check dam is primarily used in sheet flow may be detained and erosion by vegetation and/or
small channels in steep terrain, where ponded to promote sedimentation. A structures.
velocities exceed 0.6 m/s, in brush barrier is composed of brush Intended for use in any disturbed
preventing erosion by reducing the (usually obtained during the site area less than two hectares, and the
velocity of channel flow in small clearing) wrapped in filter cloth and sediment traps only remove coarse
intermittent channels and temporary anchored to the toe of the slope. If sediment (medium silt size and larger).
swales. Check dam is to be used only properly anchored, brush or rock
in small open channels, which drain filters may be used as a check dam ■ Sediment Basins
an area of four hectares or less and for sediment trapping and velocity A sediment basin is a structure
not to be used in streams, or in lined reduction. formed by excavation and/or
or vegetated channels. Rock filter berms should only be construction of an embankment
applied to drainage areas not across a waterway or other suitable
Sediment Trapping/Filtering exceeding two hectares, but if there locations to collect and store sediment
is insufficient storage space, runoff from sites cleared and/or graded
■ Sediment Fence will pond at upstream of the filter, during construction for extended
A sediment fence is a temporary possibly causing flooding in the area. periods of time before re-
sediment barrier consisting of filter establishment of permanent
fabric stretched across and attached ■ Drainage Inlet Protection vegetation and/or construction of
to supporting posts, entrenched, and, Drainage inlet protection consists permanent drainage structures. It is
depending upon the strength of the of a sediment filter or an impounding intended to trap sediment before it
fabric used, backed by a wire fence area around or upstream of a leaves the construction site. The basin

B U L E T I N I N G E N I E U R 43
feature
is a temporary measure (with a design of specific mitigation measures impacts posed by soil erosion and
life of 12 to 18 months) and is to be imposed for the control of soil sedimentation could be effectively
maintained until the site area is erosion and sedimentation during the prevented or minimised.
permanently protected against pre-construction, construction and Last but not least, mutual
erosion, or a permanent detention post-construction phases. The responsibilities and commitment by
basin or water quality control introduction of a more both the approving authorities and
structure is constructed. comprehensive Urban Stormwater the respective project proponents
Management Manual for Malaysia by should also be emphasised in order
DID has also outlined the BMPs on to ensure the soil erosion and
erosion and sediment control to sedimentation issues arising from the
better manage and mitigate the construction activities could be
erosion and sedimentation issues. effectively controlled and minimised
Therefore, with proper enforcement for the benefits and interests of all
and implementation of these parties concerned and the general
requirements, the dangers and public at large.

REFERENCES

(1) Asian Development Bank, 1986. Environmental Guidelines for


Sediment basins are suitable for
Selected Infrastructure Projects, Infrastructure Department, Asian
nearly all types of construction
projects. Wherever possible, sediment Development Bank, Manila, Philippines.
basins should be constructed before (2) Beasley, R. P., 1972. Erosion and Sediment Pollution Control, lowa
clearing and grading work begins. State Univ. Press, USA.
They are applied at the outlet of all (3) Department of Environment, 1996. Guidelines for Prevention and
disturbed catchment areas greater Control of Soil Erosion and Siltation in Malaysia, Kuala Lumpur,
than two hectares or at the outlet of Malaysia.
smaller disturbed catchment areas, as (4) Department of Irrigation and Drainage Malaysia, 2000. Urban
necessary.
Stormwater Management Manual for Malaysia, Kuala Lumpur,
However, sites with very fine
sediment (fine silt and clay) may Malaysia.
require longer detention times for (5) Hosoyomada, K. and Roslan, Z. A., 1989. On the application of
effective sediment removal. Basins USLE concerned with the prediction of Soil Erosion Loss, Publication
in excess of certain depth and storage in the JSIDRE, Japan.
volume criteria must also meet State (6) Public Works Department Malaysia, 1995. The Environmental Impact
and/or Federal dam safety criteria. Assessment of Highway / Road Projects, Road Branch, Kuala Lumpur,
Malaysia.
CONCLUSION
(7) Roslan, Z. A. and Tew, K. H., 22 - 25 August 1995. “Erosion Study
Soil erosion and sedimentation in Cameron Highlands”, Malaysian Science and Technology Congress
arising out of construction activities ‘95, Perdanasiswa, Universiti Malaya, Kuala Lumpur, Malaysia.
has posed a persistent threat to the (8) Roslan, Z. A., Amir Hashim, M. K. and Tew, K. H., 25 - 26 March
environment, and cases of prolonged 1996. “Water-Soil Erosion Features in Cameron Highlands”, World
and uncontrolled erosion would lead Water Day Seminar 1996, Allson Klana Resort, Seremban, Negeri
to untoward incidences such as Sembilan Darul Khusus, Malaysia.
landslides and mudslides. It has also
(9) Roslan, Z. A., Bakri, D. and Tew, K. H., 25- 27 November 1996.
led to the cumulative effects of
siltation and sedimentation as well as “Assessment of Soil Erodibility Potential in Malaysia - A case study”,
the shallowing of riverbeds and water 14th Conference of Asean Federation of Engineering Organization,
courseways, thus prompting flash and Malacca, Malaysia.
regular floods in low-lying areas. (10) Rubber Research Institute of Malaysia, 1980. Soil Erosion and
Fully aware of the impact of soil Conservation in Peninsular Malaysia, Kuala Lumpur.
erosion, the Government has initiated (11) Tew, K. H., 1999. Production of Malaysian Soil Erodibility Nomograph
a number of measures to minimise
in relation to Soil Erosion Issues, Selangor, Malaysia.
and control soil erosion resulting from
road construction and land (12) Roslan, Z. A. and Tew, K. H., 1999. Compilation of Presented Research
development projects. The mandatory Papers on Soil Erosion Issues in Malaysia – 2nd Edition, Selangor,
requirements of the EIA, EMP and Malaysia.
ESCP have now been formally (13) Wischmeier, W. H. and Smith, D. D., 1965. “Predicting rainfall erosion
documented as guidelines for losses - a guide to conservation planning”, USDA, Agriculture
construction activities. These Handbook No. 537, USA. BEM
guidelines also specify the proposal

B U L E T I N I N G E N I E U R 44

Você também pode gostar