Você está na página 1de 72

CYPRUS INTERNATIONAL UNIVERSITY

CIVIL ENGINEERING DEPARTMENT

BIDDING AND ESTIMATING

CLE 433

LECTURE NOTES

Prepared by: Prof. Dr. Tahir Çelik


2

September, 2010
CHAPTER 1

BILL OF QUANTITIES

1.1 Documents of Construction Contracts

A contract describes comprehensively what the works are and how payment is
to be made. The works are often quite complex, involving the contractor in
thousands of different operations and requiring him to buy hundreds of different
manufactured items and materials and to employ a wide variety of men and
machinery.

The construction contracts bind the contractor to construct the work and the
employer to pay to the contractor for them. Hence the contract itself comprises
a number of documents as follows.

a) Contract drawing
Contract drawings pictorially show the works to be built, their dimensions and
level, etc.

b) Specification
Specification describes in words the work to be built, the quality of materials,
workmanship to be used and method of testing etc.

c) Bill of quantities
Bill of quantities gives the expected measure of each operation of construction
as calculated from the drawings and classified according to trade or location
within the proposed works.

d) General conditions of Contract


General conditions of contract define the liabilities, responsibilities, and powers
of the employer, contractor and engineer. And also cover the method of
payments, insurance, liability of parties to the contract.

e) Tender
Tender is the signed financial offer of the contractor to construct the works
according with (a, b, c, d) above.

a) Letters of Explanation
They cover the matters, which are agreed between the parties of the contract to
elucidate their intentions.

2
3

g) Legal Agreements
Legal agreements documents that are signed by both parties, owner and
contractor, confirming their intentions as defined by all foregoing documents.

1.2 Specifications

While the drawings show the extend and quantity of the work, the specifications
define the quality and standards of it. Specifications are prepared by an
engineer while contracts are prepared by lawyers. Specifications are supposed
to be specific and not general.

In a satisfactory specification, following characteristics should be covered.

a) Balance Composition: The specification should contain all the


requirements consistent with the result desired.
b) Definite requirements: There must be directions, not suggestions that may
lead to uncertainty. Do not use indefinite expressions like “Reasonable” or “Best
Quality” and defined the days as “working days” or “calendar days”.
c) Accuracy: Non-accurate and misleading information will not take place in
the specifications. Repetitions in text are sources of error.
d) Practicability: Use standard sizes and patterns as much as possible. The
impracticable requirements let the contractor to add an extra safety factor to
protect himself.
e) Presentation of conflicting requirements: They are sources of error.
f) Fairness: Do not impose the contractor harsh and unfair conditions and do
not conceal difficulties from him. The risk, increases the cost of the construction.

The specifications are generally divided into two.

i) General specifications
ii) Technical specifications

1.2.1. General Provisions

They related to the whole work, to the standardized materials, the control of the
work and references to contract drawings.

Such as
a) Drawings: (If the contractor will prepare the drawings) they must be exact
and suitable to the drawing techniques. Details on large scale must be
prepared. The contractor should check all dimensions. He has the responsibility
of for all discrepancies.

3
4

b) The sequence of the work: The sequence of the work should be


determined by the contractor. But when the owner or public interests indicate
the necessity for a definite sequence of operations, details should be given in
specifications.

c) The progress schedule: Periodical reports to the engineer provide the


means for direct control and coordination of the whole work. A new schedule is
required when the construction time is extended.
d) Control of materials: The contractor is required to furnish all samples and
bear all expenses for their sampling, transportation and testing.

e) Space: In specifications, the space for constriction operations and storage of


materials should be written explicitly.

f) Information: Information on water, light sources and costs should be given


and also the expenses for their use must be written.

g) Facilities to the engineer: The contractor will be required to furnish at his


own expense the facilities necessary for the engineer (field office etc.) and it
must be given in how many weeks after commencing of work those facilities
should be prepared.

h) Warranties: The work must be free from defects for a special period (usually
one year from the acceptance date of the work).

i) The owners right to use: The owner; right to use completed portions of the
work should be stated. Such portions will be accepted by the owner and the
contractor will be relieved from his responsibility for maintaining them.

1.2.2. Technical Provisions

They contain the service and quality requirements of the work and technical
requirements for inspection and test during the construction. Sections are
divided to different works, equipment and materials following the order of the
practicable sequence of the construction operations.

Technical provisions (specifications) are divided as

a. Specifications for materials


b. Specifications for workmanship
c. Specifications for performance

4
5

a. Specifications for Materials


After an examination of their suitability and costs, the material should be
specified by their properties, which are capable to be tested (Physical and
chemical properties). The type of the tests must be specified (standard test if
possible). The tests may be omitted if the qualities of the materials are easily
determined.

b. Specification for Workmanship


Result will be specified and not the methods (the latter will be selected by the
contractor). The normal procedure is,
• Specifications of the results, tolerance
• Construction methods or procedure necessary for particular purposes.
• Limitations or restrictions on the contractor’s method in interest of the
coordination of the work.
• Precautions to protect the work or adjacent property.
• Methods of inspection and test.

c. Specifications for Performance


The desired operating characteristics and the working conditions are specified
and provisions are made for tests, inspections and warranties to guarantee
durability and avoid defects.

1.3 Bill Of Quantities

Bill of quantities is a list of numbered items where each of them describes the
work to be done in a civil engineering or building contract. Each item shows the
quantity of work involved. The bill is issued to tenderers, who return it with a
price opposite each item. This priced bill of quantities constitutes the tenderer's
offer. It is possible for the bill to include the specification.

Bill of quantities is a contract document to define the quantities of work to be


done in each type of the activity of the contract. The quantities are not
approximates, they are EXACT being measured as accurately as possible from
the drawings. When the work is constructed the quantities are replaced by the
measurement of the actual quantity of work the contractor carries out under
each item. Again this must be an accurate calculation.

1.3.1 Items

For large works it may be necessary to divide bills of quantities into separate
parts of the job, each group being subdivided into it’s various trades as listed in
some standards or perhaps as listed below:

5
6

Demolition work (if a major item in the contract)


Excavation and filling
Pipe-laying (if a major item in the contract)
Roads (if a major item in the contract)
Concrete-in situ
- Reinforcement
- Shuttering
- Pre – cast
- Pre – stressed

Brickwork, Masonry, Water proofing work, Steelwork and iron work, Roofing and
carpentry, Joinery, Flooring, Plastering, Glazing, Electrical, Plumbing, Painting,
Fencing.

The order given is not strict; it may be changed as seems reasonable. Besides,
some of the trades listed above may not exist in a particular contract. So it is a
usual practice to divide the job into its main sections. For example, the main bill
sections for a bridge might consist of:

i) Piers
ii) Abutments
iii) Superstructure
iv) Approach roads and surfacing
v) Miscellaneous

Within each section the items would be taken in order grouped under trades
-Excavation, compacting bottom soil, reinforcement, shuttering concreting etc. A
sense of proportion must be retained when billing quantities. If, for example, a
main civil engineering work for a bridge is likely to cost ten billion TL, it is a
waste of everyone’s time to bill every little quantity involved in constructing a
few ancillary roadside manholes on the approach roads such as, excavation for
manholes; concerting to manholes bases; brickwork to walls of manholes;
providing and setting manholes covers. However, if these manholes are more or
less similar they should be specified comprehensively in the specification and
shown on the drawings, and can then be billed in a single item: “Construct
manholes as specified on the drawings”.

1.3.2 Numbering of Items

The engineer who prepares the bill may find that an item or two has been
missed out. Even if his work is perfect, others may ask amendments involving
addition to the quantities. If the items have been numbered right through from
beginning to end it is then difficult to add a further item which has been

6
7

forgotten at the proof stage of producing the bill of quantities because this
mould involve renumbering all items subsequent to the insertion and checking
to see that all cross-references are corrected. The only possible way to avoid
this difficulty is to insert the forgotten items as an “A” item, e.g. Item 38 A or to
collect these as “Late Items” at the end of a bill.

A useful way of numbering the original bill items is to use a letter prefix to each
number, using different letter for each section of the bill. Thus, Excavation items
are numbered A1, A2, A3… etc; Concreting items, B1, B2… etc; Reinforcement
items C1, C2… etc. and so on. Hence if, before the bill is printed, additions
have to be made to it the additional items can at least be added at the end their
correct section without disturbing the numbering.

The pages in a bill of quantities are divided, into columns. See fig.3.1. The
descriptions of the work are printed clearly to enable the contract to price every
item. Each priced page in totaled and carried to a “collection”, and all the
collections relating to a section of the work is carried to a “summary”. Finally all
the summaries are collected at the back of the bills of quantities under a
heading of “General Summary”.

1.3.4 Costing

Accurate costing of civil engineering construction work is very undertaking


separate classes of work such as concerting, bricklaying, shuttering etc; or
finding out the cost of undertaking separate portions of the work-such as the
cost of access roads, subsidiary building, main buildings installation of
machinery etc. Costing involves finding charges for , material, plant and
overheads.

To apportion charges it is necessary for the workmen, or the section foreman


acting on behalf of the men in his team, to fill up time sheets showing the hours
spent each day by each day by each man on the various type of work. The
hours entered on these sheets must be priced out so that the cost can then be
allocated under the different headings by the cost clerk. Difficulties arise in
dealing with:

(i) Overtime and other miscellaneous wage payments, and


(ii) The time sheets of men such as fitters, time-checkers, flag-men, night-
watchmen, chairmen, storekeepers, etc., whose work cannot be directly
allocated to a specific site operation. Decisions have to be made (in advance of
setting up the costing system) as to how such men’s time sheets are to be
allocated. They may be separated out into different categories, of they may all
be put under the heading ‘site on-costs’.

7
8

The allocation of charges for materials presents further difficulties, since the
paper work on site is usually concerned only with checking the inflow of
materials against the supplier’s invoices, and none of the basic records may
show where the materials have been used in the separate parts of the job. The
bill-of-quantities measurements can be of assistance for calculating quantities
(and therefore price) of materials used in the permanent works, but there are
many more materials, such as timber for shuttering, scaffolding, small tolls,
diesel oil and fuel oil, nuts and bolts, etc., which are not used in the
measurement records. As with wages which cannot be directly charged to any
specific operation, so materials which cannot be coasted out to particular parts
of the job will have to be charged as part of ‘site on-costs’. Provided the plant-
hire charges are known, the allocation of plant charges is relatively easy on the
basis of the daily returns of plant usage provided by the plant foreman.

In addition to the items already mentioned, it is necessary to add in the various


site administration charges to the account for site on costs-waters of general
foreman, engineers, site clerk, waters clerk, agent and sub-agents, etc.,
together withal such other charges as telephone, water supply, messing,
sanitation, insurance of works, petty cash, etc.

The result of all this is that a heavy proportion of the total cost virtually cannot
be analyzed and has to be put under the general heading of ‘site on-costs’. A
further difficulty then reveals itself, namely that the ratio of these site on-costs to
the direct charges varies from week to week of the job according to the output,
amount of overtime worked, amount of temporary works being built at any one
time, and so on. On-cost expenditure at the beginning of a job may be several
times the cost of the direct (or productive) expenditure because of the large
proportion of and materials used on preliminary works, such as access roads,
power and water supply, etc., etc. When productive effort is in full swing the on-
cost drop to their lowest, but they tend to rise again towards the end of the job
as productive work tails off and site clearance, removing sheds, transporting
plant off the site, etc., takes place.

The reader will not be surprised to learn that in consequence few, if any,
contractors’ cost works in the manner outlined above. The actual cost of a
portion of a job, or of a particular operation, is never known. What is known is
the estimated charge as set out in the bill of quantities according to the quantity
of work actually done and measured?

It is only possible to find out the ‘cost’ of separate parts of operations on a job
by using the estimator’s figures put in the bill of quantities, and the only way
these estimated figures can be checked against the real figures of actual

8
9

expenditure is by comparing the total estimate against the total expenditure. Of


course, the direct costs involved in any particular operation can be ascertained
without difficulty. The number of men and the hours they spent on that
operation, together with the materials and plant they have used, can be
carefully noted that apply; but the indirect costs, representing a heavy
percentage addition, can never be exactly apportioned out; they can only be
applied as a general percentage added to all the operations. Hence contractors,
if they do costing at all, carry it out on a different basis from what the layout of a
bill of quantities seems to imply.

The practicable headings under which a contractor can expect to analyze his
expenditure are more likely to be: gross waters paid, transport of men, ‘non-
productive’ hours (i.e. plus rates for overtime), cost of wet-time; materials used
in permanent works, materials used in temporary works, materials used in
shuttering; equipment, scaffolding, small stores; fuel and power; plant hire, plant
repairs; temporary offices and services; site staff and administration expenses.
To check any estimate submitted against a bill of quantities, the sum total of the
tendered prices in the bill will be compared with an estimate based on the
expected number of men and machines required for the job, together with a
calculation of the cost of the materials to be used in the permanent works, to
which are added all the other on-costs applicable, as judged from costing
records of other jobs undertaken as outlined above.

Thus, the price submitted individually in a bill-of-quantities contract may not


represent the actual separate cost to the contractor of each such item, but they
should in total represented the total expenditure to be incurred, including an
allowance for profit.

CHAPTER 2
ESTIMATING
9
10

2.1 Introduction

Client or promoters of the construction rely on competitive tendering to justify


the awarding of contracts. Most construction contracts are awarded after a
number of contractors have submitted a tender. Constructor contractors base
these tenders on an estimate of the cost to the contractor, of executing the work
described in the contract documents. The estimating department is therefore of
central importance to the commercial success of the contracting organization.

2.2 Estimating in Large and Small Organizations

Figure 2.1 shows a schematic representation of the nature of the predominant


estimating practices that can be associated with different types of construction
and related organizations. The client and design consultants often typically rely
on approximate estimates to make decisions at the early stages when the
scope and scale of the project are being formulated. The gradual progression
of the major contractor’s role from a traditional works contractor towards the
more managerial work-package integrator has resulted in a shift in emphasis
on estimating from first principles. Increasingly, such major contracting
organizations aggregate price quotes from work-package contractors and
provide adjustments for attendances, identified risks from both the quoted
prices and other allied project factors and margins.

Figure 2.1 Estimating practices in different types of construction organizations.


As such, the type of data collected for the estimating exercise is largely
influenced by the nature of the contractor’s organization. The smaller
contractors who often deliver the work packages have to compute their

10
11

estimates from first principles to be able to furnish accurate quotes to the larger
contractors. Irrespective of the level at which the estimating is being considered,
the important feature is that the estimators have to achieve all this normally
within a restricted time period of four to six weeks. The subsequent sections of
this chapter describe the parties involved in the production of an estimate and
tender, the process of estimating and tendering and the calculations involved.
The description of the process of estimating is addressed from the perspective
of the work-package contractor since this provides the bedrock of all the other
practices of estimating undertaken by other stakeholders in construction.

2.3 Parties Involved in Estimating and Tendering

The parties involved in estimating and tendering can be divided into three
classes:

a) The client’s staff or their professional representative


b) The contraction contract’s personnel including senior management,
Estimators, planners, buyers, plant managers, temporary works designers
and site management staff.
c) The external organizations such as material suppliers, plant hire companies
and sub-contractors.

The contribution of each of these is described below.

2.3.1 The Client’s Staff or Professional Representative

The contract documents prepared by the professional representatives of clients


include drawings, bill of quantities, specifications and other documents. These
are the main sources of information to the estimators who prepare the cost
estimates and tenders.

2.3.2 The Constructions Contractor’s Personnel

i) Senior Management is usually involved in the decision whether or not to


tender for a particular contract and it the decision on what tender to submit.
Here he considers the estimate of cost and resources involved as produced by
estimators.

ii) Estimators are employed in the estimating department. He is responsible of


producing estimates.
iii) Planners are employed to produce construction plans or program. The
estimators are usually concerned with a pre-tender plan which may not be as
detailed as one produced for site use. However it will provide overall duration of

11
12

the project, the duration and sequence of the key activities, and approximate
resource totals for and plant.

iv) Buyers are usually responsible for purchasing materials and placing orders
with plant wire companies and sub-contractors. They provide quotations for
materials, plant hire and sub-contractors.

v) Plant managers are responsible for the company’s plant department and
supply estimators with current internal hire rates and advice availability of
company owned-plant.

vi) Temporary works designers are responsible for designs of major


temporary works such as bridge, false work etc. Estimators would take advice
on the nature of the temporary works.

vii) Site management is the personnel who are employed to take responsibility
for the execution of projects on site. This expression covers agent works
mangers, engineers and surveyors. The contribution of site management to
estimating is to provide advice to the estimators on methods of construction.

2.3.3 External Organizations

Material suppliers, plant hire companies and sub-contractors all get involved in
the estimating process. They receive and respond to enquiries for quotations
from contractors.

2.3 The Estimating Process

Figure 2.2 shows a generic model of the estimating and tendering process
within a construction company. The process involves both the planning and
estimating departments. The estimating process commences with an invitation
by the client for the contractor to submit a tender for a proposed project.

Estimating practices within construction companies have in the past been based
only on the Bill of Quantities (BOQ) type of contract. Although this is still very
relevant today, there are a number of variants to the BOQ approach, such as
estimating for work packages that are finding increasing popularity.

12
13

Figure 2.2 Activity flow showing the role of estimating in the tendering process
of construction.

2.4 BOQ estimating

BOQ estimating is undertaken for contracts that rely on client-prepared contract


documents and a bill of quantities. This is still the most common type of contract
in the UK. The contractor's role is to estimate how much it will cost to do the
project so that it can be priced reasonably.

13
14

The process undertaken to produce a cost estimate, which can be used as the
basis of a tender, is described in the following steps:

The basic steps of estimates are:

a) Decision to tender
b) Programming the estimate
c) Collection and calculation of cost information
d) Project study
e) Preparing the estimate
f) Site overheads
g) Estimator’s reports

2.4.1 Decision to Tender

The decision to tender for a particular contract is mainly the responsibility of


senior management; there are three possible points during the estimating and
tendering process where this decision must be made. The first is during the pre-
selection stage, if a pre-selection procedure is being used. This decision would
be based on pre-selection information provided by the clients' staff or
representatives and would include such information as:

• Name of the job


• Name of the client architect and quantity surveyor or consulting engineers
• Names of any consultants with supervisory duties
• Location of the site
• General description of the work involved
• Approximate cost range of the project
• Details of any nominated subcontractors for major items
• Form of contract to be used
• Procedure to be adopted in examining and correcting priced bill{ s)
• Whether the contract is to be under seal or under hand
• Anticipated date for possession of the site
• Period for completion of the works
• Approximate date for the dispatch of tender documents
• Duration of the tender period
• Period for which the tender is to remain open
• Anticipated value of liquidated damages (if any)
• Details of bond requirements (if any}
• Any particular conditions relating to the contract

The contractor may have signified their intention to submit a tender at the pre-
selection stage, but has a further opportunity after receiving all contract

14
15

documents to review them and consider, in the light of fuller information,


whether they wish to proceed or not. The third and final point of decision
whether to submit a tender is after the estimate has been prepared and the
contractor is ready to submit. A decision at this stage not to tender is rare but
allows the contractor to review the events of the intervening four to six weeks
and the changes in workload that have occurred in that time.

The decision to tender is based on such factors as:

• The company’s current workload, turnover and recovery of overheads


• The company’s financial resources
• The availability of resources to undertake the work
• The type of work
• The location of the contract
• The identity of the client or promoters and his representatives
• A detailed examination of the contract documents

2.4.2 Programming the Estimate

After the contract documents have been received and a decision made to
tender, the tasks required to complete the estimate are program and a schedule
of key dates established to monitor progress. This is essential as the time to
submit a tender is limited. The two main tasks that can now take place are the
collection and calculation of the cost information, required to prepare the
estimate, and a study of the project to gain the required appreciation of the
work involved in the contract. These two tasks take place in parallel and are
interrelated.

2.4.3 Collection of Cost Information

The cost information required for, labor, plant, materials and subcontractor will
be collected.

2.4.3.1 Labor

The estimator is required to calculate the all-in' rate for each category of , which
is an hourly rate covering all wages and emoluments paid to the operative, all
statutory costs incurred and allowances for holidays and non-productive
overtime. As an alternative to the hourly rate, the all in rate may be calculated
as a daily or weekly rate. An example of this calculation is set out below. As the

15
16

all-in rates are calculated by the estimator, they can be established early and
accurately in the estimating process.

The basis of this calculation is to determine the total worked hours in a year and
the total cost for the working year and hence the cost per worked hour. The
calculation is complicated by the difference between the hours worked and the
hours paid, which exceeds the hours worked by such items as overtime
allowances, public holidays and inclement weather.

The calculations set out in this example are based on a real example and
contain data that are available in the Working Rule Agreements, assumptions
made by a contractor's estimator and the data relating to statutory obligations.

Working times

The guaranteed minimum earning period for construction workers is 39 hours.


This is based on a 5-day working week for the site works. During the 44-week'
summer' period, the daily hours are 8.00 a.m. to 5.30 p.m. This gives a working
day of 8 hours plus 1 hour overtime for Monday to Thursday; and 7 hours plus 2
hours overtime for Friday, making up in all a working week of 39 hours plus 6
hours overtime. During the 8-week 'winter' period, the daily hours are 8.00 a.m.
to 4.30 p.m. This gives a working day of 8 hours for Monday to Thursday, and 7
hours plus 1 hour overtime for Friday, and giving a working week of 39 hours
plus 1 hour overtime.

2.4.3.2 Plant

The hourly or weekly cost of plant can be either as result of internal calculation
or as a result of quotations. Methods of calculating hire rates are given in CLE
491 Construction Plant Management Lecture Notes. Quotations for hire can be
either internal rates from the plant department or the contractor's plant
subsidiary, or external hire rates from an independent plant hire company.
Calculated rates or internal rates can be established very early in the estimating
process. External hire rates may take a little longer to obtain, but it is unusual to
suffer serious delays in receiving quotations.

16
17

17
18

18
19

19
20

2.4.3.3 Materials

Materials quotations are more problematic in that materials not only form a
significant percentage of the works but, because of the volatility of materials
prices, contractors have to send out unique enquiries for almost all materials in
every estimate prepared. The materials enquiries include information such as
the quantities required, the specification the approximate delivery dates and the
terms and conditions upon which the quotations are being invited.

To enable these enquiries to be sent out, the estimator must go through the bill
of quantities and specification, extract the relevant information and prepare a list
of required materials. Because of the time taken to send out and receive
quotations, this task of preparing the materials lists is undertaken very early in
the estimating process. In some companies, a 'buyer 1 may send out the
enquiries, chase the suppliers who fail to respond and check and compare the
quotations. In other companies, this task may be undertaken by the estimators.

Enquiries sent to suppliers normally include:

• Specification of the material


• Quantity of the material
• Likely delivery program including both the period for which supplies would
be needed and the daily or weekly requirements
• Address of the site
• Means of access
• Traffic restrictions and conditions affecting delivery
• Period for which the quotation is required to either remain open for
acceptance or to be firm
• Date by which the quotation is to be submitted
• Name of the person within the contractor's organization to whom any
reference concerning the enquiry should be made.

Buying departments usually have standard letters or forms for issuing enquiries
and, where convenient, parts of the contract documents—such as extracts from
the specification—are photocopied to accompany the enquiry. As the estimator
is responsible for completing the estimate an enquiry index or progress chart is
usually kept so that the stage of each enquiry can be readily monitored.
When checking quotations, the estimator is required to ensure that quality and
quantity of materials meet the specification of the contract documents, and can
be delivered to the site at the times required by the construction program. In
addition, the contractual obligations to be entered into for the supply of the
material must be satisfactory.

20
21

The determination of the materials prices for inclusion in the direct cost estimate
maybe considered to be one of the most precise aspects of estimating. The
process of obtaining materials prices, as has been described, can be seen to
consist solely of contacting suppliers who have the material available and
negotiating a suitable rate under satisfactory contractual conditions- In addition,
the estimator has to undertake the more difficult task of determining allowances
for material wastage, damage, theft, delivery discrepancies and handling insofar
as they affect the costs of the works.

2.4.3.4 Subcontractors

For the traditional BOQ approach, subcontractor enquiries also have to be sent
out early and the estimator will prepare lists of the items and work that will be
subcontracted. As with materials, these enquiries may be dealt with by a 'buyer'.

Following receipt, the quotations must be compared and the subcontractors


selected. The rates for the selected subcontractors will be included in the
estimate together with allowances for attendance and other services. The profit
to be added to the main contractor's own subcontractors and to the nominated
subcontractors may be included at the estimating stage or left until the final
additions following the tender meeting. The difference between materials and
subcontractors is that in most cases the materials costs are combined with plant
and to produce costs rates for items of work, whereas the subcontractors1 rates
in many cases will stand on their own together with an allowance for
attendance.

As part of the preliminary study, the work that is to be subcontracted would


have been identified by the estimator. The factors that control the decision of
which works to subcontract are mainly the specialization of the work involved
and the size of the contract. Most contractors establish by practice the type of
work they normally subcontract. In undertaking contracts larger than usual, a
company may wish to subcontract some work they would normally undertake
themselves, the reason being to offset some of the financial risk. The absence
of a direct financial risk in subcontracted work is not a total security because of
the indirect risk of losses caused by delay and disruption to the main works if
the subcontractors default. For this reason, effective control of subcontracted
operations is important and this control begins with the selection of
subcontractors. Most companies keep a list of approved subcontractors for
various classes of work as a guide to estimators in the comparison of
subcontractor quotations.

Since the 1980s, there has been an enormous growth in the use of
subcontractors by the main contractor. The reason for this development
primarily was to enable the contractor to take on additional workload without the
21
22

need for increasing internally the level of employment and capacity required to
execute the extra workload, thus ensuring greater flexibility. The need for this
degree of flexibility by the contractor derived from the volatility in the industry's
workload. The use of subcontracting transferred some of the financial risk
associated with maintaining the additional capacity to the subcontractor.

The trend towards the use of subcontractors continued through the 1990s. This
means that the relative importance of the areas of risk associated with using
subcontractors increased. This risk is acknowledged by contractors, who rely on
their vetting and selection procedures to reduce it to acceptable levels. The
contractor who bases a tender on a subcontractor's quotation merely because it
was the lowest would be unwise. Since the beginning of the 21st century,
changes in employment laws and taxation have reduced the advantage
associated with subcontracting for -only arrangements (LOSC), Under these
changes, the main contractor is still responsible for ensuring statutory
entitlements of all the LOSCs it employs. The following briefly views the risk
areas associated with the use of subcontractors.

Attendances

Estimating attendances, such as equipment, scaffolding and tools, when


comparing and selecting subcontractors is assuming a greater priority in
estimating work. Not all quotations are consistent in the attendance requirement
and comparing the simple quotations is inadequate. Very often, a subcontractor
will by negotiation take on more onerous attendances within the stated price.
Estimating attendances may in itself prove critical in winning a contract or
indeed in being able to execute a contract profitably.

Materials

The importance of material costs is that they represent above 50% of the cost
profile of the construction industry A small percentage cut in materials costs
could bring a sizeable increase in profits. For example, a 2% cut in materials
could increase profits by much more than that which could be achieved by a
2% cut in overheads.

The estimating of material cost in any tender is, therefore, an important element
and an inaccuracy in their estimates is likely to affect the outcome of the tender
and the profitability of the subsequent contract. Furthermore, it is obvious that
any appreciable waste is a significant item of cost and represents a great loss to
both the nation s resources and the main contractor.

22
23

Many estimators have established within their companies standards or norms


for wastage of materials. These standards, however, are largely based on the
experience with their own force, or where their own had a large share of the
work. There is potential for wastage rates to rise with the use of subcontractors'
whose desire to complete the work as soon as possible is high. Thus, the
materials wastage allowance is likely to be a growing factor in the accuracy of
an estimate. This may be obviated by tighter materials control, or in some cases
passing the responsibility for purchasing materials to subcontractors with
agreed limits as to quantity.

Output

The greater use of subcontractors has reduced the importance of one of the
estimator s most difficult tasks; that of estimating labor and plant outputs.
However, the task is not completely removed; companies do still employ their
own labor and even this lessening of the estimator's burden has been partially
offset by an increase in other difficulties. These difficulties lie in quantifying the
consequences of subcontractors who prove unreliable and fail to complete their
work or disrupt the sequence of work. A subcontractor who tackles the
straightforward work while failing to complete the smaller but more difficult
elements can cause disruption. So can the subcontractor who is slow, starts
late and finishes late. The main contractor may not actually suffer any financial
loss within the specific subcontract but will be left to face the consequences of
the disruption. Evaluating the effects of potential disruption for the purposes of a
claim against the subcontractor is difficult. Evaluating the effects of potential
disruption at the estimating stage is even more so. As a result, there now
seems to be much more effort in the 'back rooms1 of companies devoted to
trying to determine how this potentially costly element can be evaluated. The
use of computer simulations is now being practiced. Certainly, potential
disruptions are now a major factor in determining the accuracy level of
estimators measured by the difference between estimated cost and the actual
costs. However, in these competitive times estimators tend to rely on their
vetting procedures in assessing the subcontractor's record rather than explicitly
allowing for potential disruption.

Management control and efficiency

Site management control and efficiency have always been a major factor
affecting the level of estimating accuracy. When a job loses money and the
discrepancies between estimates and actual are large enough for an internal
enquiry, the estimators and the site managers can blame each other. That site
management got it wrong, or that the estimators got it wrong, have, through the
years, been equally valid and equally difficult to prove. The greater use of

23
24

subcontractors does not make site management less important but it has
altered its nature. The control and organization of the arrival, departure and
interactions of many subcontractors has had to be developed in companies that
were previously used to making their major efforts in controlling their own .
Squeezing more productivity out of the company's own force and ensuring that
subcontractors perform on time, with good quality workmanship, and dovetail
into the other activities on site has changed the role of general foremen and the
site agents. It has always been true that, all things being equal, the success of a
contract is determined by the quality of the site management team. The greater
use of subcontractors does not change this but has changed how it must be
achieved.

2.4.4 Project Study

To gain an appreciation of the project the estimator will undertake the following
tasks:

i) A study of the drawings


ii) A site visits and meeting with the clients or promoter’s representative
iii) The preparation of a method statement determining how the project will be
constructed.

2.4.4.1 Drawings

I n civil engineering contracts, the contract drawings are sent to each


contractor tendering. In building work, it is now common practice to issue a set
of contract drawings. However, in cases where this is not so, estimators and
planners may have to visit the architects offices to inspect a complete set of
drawings and to discuss unclear aspects with the architect. Unclear aspects of
the drawings are also frequently clarified by telephone consultation.

2.4.4.2 Site visit

Incivil engineering works, it is normal practice for the promoter's engineer to


arrange a site visit, which gives the estimators and planners an opportunity to
study the site with the design personnel on hand to answer queries. In building
work, the site visit may not be arranged so formally but nevertheless most
contractors arrange one for themselves. As a result of these site visits, the
estimator and planner prepare a report or set of notes which includes:

• Description of the site


• Positions of existing services
• Description of ground conditions
• Assessment of the availability of labor
24
25

• Any problems related to the security of the site


• Description of the access to the site
• Topographical details of the site
• Description of the facilities available for the disposal of soil
• Description of any demolition works or temporary works to adjoining
buildings.

2.4.4.3 Method statement

Method statements are descriptions of how the work will be executed with
details of the type of labor and plant required and a pre-tender program. It is in
the preparation of these method statements that alternative methods of
construction are considered, together with alternative sequences of work,
differing rates of construction and alternative site layouts. As these evaluations
progress, the preferred method of construction is chosen and the pre-tender
construction program illustrating this is prepared.

In preparing the method statements, the estimators and planners work closely
and also consult with site staff, plant managers and temporary works designers.
The pre-tender program prepared will show the sequence of all the main
activities and their durations, as well as the duration of the overall project. From
this pre-tender program, approximations of the labor and plant resources will be
calculated. This pre-tender program is not an exercise carried out once only
and left, but is subject to continual refinement and modification as both the
estimator and planner become more and more aware of the implications of the
project details. Thus, throughout the preparation of the estimate the estimator
and planner remain in close consultation. In many contracts, the pre-tender
program is prepared in the form of a bar chart; in some of the larger and more
complex projects some form of network analysis is used. Networks are also
used in smaller contract companies, who have become skilled in their
preparation and use and aware of their advantages.

2.4.5 Preparing the estimate

The estimator's task is to determine the cost to the contractor of executing the
work defined in the contract documents. This cost estimate will be modified by
senior management in consultation with the estimator to determine the tender or
selling price. The estimator is required to establish the direct cost rates for each
item in the bill of quantities. A direct cost rate is a rate for the labor, plant,
materials and subcontractors, but exclusive of additions for site overheads,
head-office overheads and profit. These will be assessed and included later.

Determining a direct cost rate involves selecting the appropriate resources of


labor, plant and materials for the item of work (either a single bill item or a

25
26

group of bill items), selecting the output or usage rates for each resource or
determining the elapsed time that each resource (labor and plant) will be
employed and combining this with the cost information collected. This
combination of the unit cost of resources, together with the usage of resources
to produce a direct cost for the work described in the bill item or group of bill
items, is illustrated in Fig 2 . 3 .

Figure 2.3 Selection of production rates and cost data and their combination to
produce cost rates.

2.4.6 Site Overheads

26
27

The estimator assesses the site overheads

i) Site staff and clearing the site


ii) Site transport facilities
iii) Mechanical plant not previously included in the item rates
iv) Scaffolding and gantries
v) Site accommodation
vi) Small plant
vii) Temporary services
viii) Welfare, first aid and safety provisions
ix) Final clearance and handover
x) Defects liability
xi) Transport of men to site
xii) Abnormal overtime
xiii) Risk
The costs of these site overheads are frequently allocated to the preliminary'
section of the bill, but may sometimes be allocated, at least partially, to bill item
rates.

2.4.7 Estimator’s Reports

On completion of the estimate, the estimators prepare a set of reports for


consideration by the senior management. These reports contain,

(i) A Brief Description of the project


(ii) A description of the method of construction
(iii) Notes of any unusual risks, which are not covered by the condition of
contract or bills of quantities.
(iv) Any unresolved or contractual problem
(v) An assessment of the state of the design proves and the possible
financial consequences thereof.
(vi) Notes of any major assumptions made in the preparation of the
estimate
(vii) Assessment of the profitability of the project
(viii) Any pertinent information concerning market and industrial conditions.

The cost of work include in the estimate are reported to senior management in
cost reports that give the details of:

• Main contractor’s
• Main contractor’s plant allocated to rates and in preliminaries
• Main contractor’s materials
• Main contractor’s own subcontractors

27
28

• Sums for nominated subcontractors


• Provisional sums and dayworks
• Contingencies
• Amount included for attendance on domestic and nominated
subcontractors
• Amounts included for materials and subcontract cash discounts.

In addition, a bill of quantities marked up with the direct cost rates showing the,
plant, materials and subcontractor breakdown for each rate may form part of the
report.

As well as reporting the costs estimated for labor, plant and materials, the
estimators also assemble the total hours for each category of labor and the
total hours or weeks for each major item of plant and total quantities for
materials. These resource totals are compared with the planners' calculated
resource totals and any difference reconciled. Figure 4.4 shows an example of
such a report showing resource totals and costs.
The estimators may also calculate the cash flow for the contract based on a
range of assumed mark-ups, which will assist senior management’s judgment
as to what is the appropriate markup to select.

28
29

Figure 2.4 Resource consolation report

2.5 Estimating in management contracting

Management contracting is a form of procurement strategy in which a contractor


is appointed manage and provide leadership for the project during the pre-
construction stage, usually after the preliminary design and project definition
have been completed. The main advantage of such an arrangement derives
from the experience that the contractor brings to the project to ensure greater
buildability and more effective project management. A contractor engaged in
such a role is described as a management contractor, and performs a
coordinating rather than the traditional construction role associated with
contractors. Under the NEC: ECC Option F, the management contractor's
responsibilities for the construction work are the same as those under priced
contract or target contracts. However, other contractors that are appointed in
the role of subcontractors or work-package contractors undertake the
construction work as a series of work packages. ECC Option F [20.2] requires

29
30

that all work packages that must be subcontracted should be clearly identified.
All other works not to be subcontracted are covered by the fee of the manage-
ment contractor- With the exception of the managerial role, the management
contractor is allowed to subcontract any other work package not identified in the
list of work packages. These may include site preparation, the provision of
temporary works elements and other general and specific attendances common
to all the work-package contractors.

From a management contractor's perspective, the estimating function


described for the BOQ type of contracts plays a lesser role in the tendering
process. This is because the work-package contractors perform the detailed
estimating function. The management contractor's estimate for the actual cost
of the works is made up of all the estimates from the work-package contractors.
The management contractor tenders a fee for the coordinating services in
addition to the estimated total of the prices for all work-package contracts. The
fee is usually based on the actual cost of the work packages defined in Option
F [11.2(22, 26)]. The actual cost comprises solely the payments due to work
package contractors for those work packages identified in the contract
documents. Where additional works not identified in the contract documents
are subcontracted, this is covered by the fee of the management contractor.

A typical management contracting tender submission will comprise the


following:

• Confirmation of acceptance for the conditions and any specific details


defined in the tender documentation of the proposed project
• Fees to cover the management role performed during the pre-construction
phase of the project
• Fees to cover the management of the construction phase of the project
• Proposed project team and the management structure
• Project strategy, detailing execution plans, overall program and method
statement
• Project budget estimates covering costs of providing works not identified
in the work packages
• Project budget estimates for work packages defined in the tender
documents from the work-package estimates submitted by work-package
contractors

Confirmation of acceptance of conditions is based on the contractor's decision


to tender for the project, which is arrived at after detailed examination of the
tender documents, establishing the potential workload and resource
requirements for the project and evaluating the conditions of contract for the
management service to be provided. In particular, the scope and responsibilities

30
31

of the management contractor as defined in the conditions of contract will have


an impact on the level of fees in order to adequately cover all risks to the
contractor. The management decision to tender or decline the offer is taken
based on the same factors as in the BOQ approach for tendering.

2.5.1 Estimating the management contractor's fee

The management contractor's fee comprises four main elements. These are:

• Profit
• Corporate overheads
• Other specific items
• Project and business risks

2.5.1.1 Profit

The level of profit is set to reflect the contractor’s long-term business objectives
and the conditions prevailing in the industry with respect to common practice
and extent of competition. The level of profit is a managerial decision that is
taken at the tender adjudication.

2.5.1.2 Corporate overheads

This covers all overheads not charged directly to the contract. The corporate
overheads comprise general head-office expenses such as company
administration, market research and business development, tendering,
accounting and auditing, head-office support for regional offices, legal services,
professional indemnity and public liability insurance. The level of overhead
charges is set either as a percentage of the project costs or as lump-sum items
to cover each specific overhead by taking account of the size, duration and the
extent of support envisaged for the contract.

2.5.1.3 Specific items


Costs included in the specific items comprise project-related services required
for the efficient management of the contract. They include

• Site-based services such as:


• Inspections
• Safety advice, planning and supervision
• Preparation of documentation for cost plan, safety plan and quality plan
• Industrial relations management
• Post-contract administration
• Project-related insurances to cover:

31
32

• Physical works
• Third party
• Plant and equipment
• Guarantees
• Other client interests
• Bonds:
• Bid bond
• Performance bond
• Additional works:
• Any non-management work not defined as part of the project's work
packages.

2.5.1.4 Risk

The risk associated with each of the following risk elements will be estimated
and included as part of the fee:

• Cost overrun on lump-sum work or management elements to cover any


future cost escalation or estimating error
• Fee that is not recovered as a result of variation to the project
• Defective work
• Neglect of duty by work-package contractors
• Bankruptcy of work-package contractors
• Liquidated and ascertained damages not recovered from work-package
contractors

2.6 Types Of Estimates

An estimate can be prepared at any point in the life of a project. Estimates are
developed early in the design process so that the owner and designer have cost
information to guide the design. They are also developed during later stages of
design to ensure that costs are within a given budget. During bidding, the owner
uses estimates to check that the bids are a fair cost for the work. At bid time,
the most extensive estimate is done by the contractor. This bid represents the
actual costs as the project goes forward into construction. Estimates continue to
be used during construction in case there are changes on the job or to help
organize a specific set of activities.

A series of estimate types has been developed that serves each of these sit-
uations. The differences among these estimates are a function of the infor-
mation available at the time of the estimate. Generally, estimates done in the
later stages of design and during the bidding period are more accurate than
ones done early.

32
33

2.6.1 Estimating during Design

Design estimates are important tools for the owner and the project management
team as they develop the project's scope of work. The discipline of providing
cost information throughout the design phase makes cost a significant driver for
the project team. Designers, in their zeal to provide exciting solutions to the
program, sometimes lose sight of the budget parameters. Owners can also get
caught up in the excitement of desirable design features that in reality could
compromise the budget or mean cutting the project in other areas. By providing
cost information early and updating it throughout the project, cost professionals
can keep the project team well grounded in the realities of cost.

2.6.1.1 Rough Order of Magnitude Estimates

In the conceptual stages of a project, very little is known about specifications.


Design information may only contain sketches or concepts. Descriptions are
generally in terms of capacity, such as the number of hotel rooms, hospital
beds, or parking spaces. Rough order of magnitude (ROM) estimates typically
establish a cost per unit of capacity (see Figure 2.5). These units are developed
mainly from past projects. Examples are cost per bed for a hospital, cost per
apartment, cost per pupil for a school, or cost per mile for a highway. By
multiplying this cost times the number of units proposed for the project, a
preliminary number can be established. If the costs are developed according to
a national average, they must be adjusted using the appropriate city cost index.
Costs taken from past projects must be adjusted to current or future dollars. If
the project is smaller or larger than normal, the cost is adjusted for size. An
appropriate contingency should also be applied to allow for scope adjustments
and economic or market conditions.

As with all estimates, the accuracy of a ROM estimate depends on the quality of
data used. If the company doing the estimate has a good historic data base of
similar projects, that is the best source for that information. If this data is not
available, there are nationally published data bases that can be consulted.

One advantage of a ROM estimate is that it can be calculated quickly, often in a


few hours, and is typically assumed to have an accuracy of plus or minus 20
percent. This quick turnaround can enable an owner to look at several options
without having to invest too heavily in any one. These estimates are often the
first costs that an owner sees. Although they are normally accomplished with
little information, the number put forward at this time tends to be the number
that the owner remembers; and consequently all estimates that follow are

33
34

compared to this. It is therefore important for the estimate to be qualified. All


assumptions should be listed and all information considered identified. In the

34
35

Figure 2.5 Rough order of magnitude estimate (From Means Assemblies Data
Book, 2001).
early stages of project development, this type of estimate is an important tool,
but its limitations must be fully understood and articulated.

2.6.1.2 Square Foot/Cubic Foot Estimates

Once a design has reached the early schematic stage, it will start to produce
floor plans, elevations, and building sections. This information makes possible
the calculation of floor areas or building volumes, which can then be multiplied
by appropriate unit costs to produce a square foot or cubic foot estimate. The
appropriate unit costs are derived from either in-house sources that track past
similar projects or outside data sources. This base cost is adjusted to reflect
more project-specific factors. Any actual project data that can be folded into the
historic data will improve the accuracy of the estimate, Information regarding
structural systems, building height, exterior closure, and overall footprint of the
building are all factors that will be assumed by the estimator if real data are not
available.

A square foot or cubic foot estimate, while more complete than a ROM es-
timate, is still quite schematic in detail. It is, however, easy to prepare, taking
only a couple of hours. The general assumption for accuracy is plus or minus 15
percent—better than the ROM estimate because it is based on more project-
specific information.

Example - Problem
Estimate the cost to construct a 55,000 square-foot motel. The motel will be a
two-story building. The exterior wall will be made of decorative concrete block,
and the building will use a precast concrete floor system. Other features include
150 ceiling smoke detectors, 10 nickel-cadmium emergency lights, and a 500-
square-foot gunite pool.

Solution

Refer to the 2001 Means Square Foot Cost Data Book, pp. 162 and 163 (see
Figures 2.6 and 2.7). This two-page model is one of seventy different types of
commercial, industrial, and institutional models included in the Means data
book. Examples include a factory, a jail, and a warehouse.

The first page of the model displays a pricing breakout by size and exterior wall
and structure. At the bottom of the first page are the prices of some common
building additives. The second page provides a detailed breakout of one of the
building models (notice the highlighted $111.15 on the first page)-, a 49,000-

35
36

square-foot, three-story motel. This page provides a good overview of what is


included In the $111.15 per square foot price.

36
Figure 2.6 Model of costs for constructing a motel: Pricing breakout by size and
exterior wall and structure; detailed breakout for a 49,000ft2, 3-story motel.
37
38

Figure 2.7 From Means Square Foot Book, 2001.


38
39

Notice that the general contractor's overhead and profit and a 6 percent design
fee are included in this price. Also notice that any site work beyond the
excavation and backfill for the foundation is not included.

Calculation

1. Interpolate a base price between $111.15 (49,000 square feet) and


$110.15 (61,000 square feet). The interpolation can be set up as follows:

$110.15 61,000
? 55,000
$111.15 49,000

111.15 – ($6,000 x 1.00) / 12,000 = $110.65

The base cost for the building = $110.65/square foot x 55,000 square feet
= $6,085,750

2. Add the costs of the pool, smoke detectors, and emergency lights.

150 smoke detectors x $149/each = $23,350


10 emergency lights x $655/each = $6,550
500-square-foot gunite pool x $50/square foot = $25,000

Total additive cost = $53,900

Total project cost (with additives) = $6,139,650

This cost assumes a construction start in early 2001 in a national average


location. The price does not include the cost of land purchase or any substantial
site work.

2.6.1.3 Assemblies Estimates

In the later stages of design, when more information is available, it is possible to


configure estimates into a series of systems. This method, called assemblies
estimating, uses system or assembly units of a project. In a ROM estimate the
unit is the number of beds or miles of road. In a square foot estimate, the unit is
the square foot area of the project or gross areas of the project. In an assemblies
estimate, the unit is the foundation, the roofing, the electrical system, and so on.
Since the units are smaller, the estimate becomes more flexible but also requires
more designer input, takes longer, and costs more money to prepare. However,
its accuracy is in the 10 percent range.

39
40

The information needed for an assemblies estimate must be in a form that can be
quickly itemized system by system. Most companies use a breakdown called the
uniformat system (see Figure 2.8). This allows estimators to work with smaller
and smaller subsystems within the bigger system. For instance, interior
construction may have as one of its subsystems drywall partitions. This
subsystem includes the cost of the metal studs, drywall installation, taping, and
finishing. It is listed by different fire ratings, whether or not it is insulated, and
whether or not it is finished on both sides. Both in-house data bases and off-the-
shelf systems include these options. The smaller the system, the more flexibility
there is in the use of the estimate. Figure 2.9 illustrates a partition assembly.

Specification Formats
Master Format Uniformat
1. General requirements 1. Foundation
2. Site works 2. Substructure
3. Concrete 3. Superstructure
4. Masonry 4. Exterior closure
5. Metals 5. Roofing
6. Wood and plastics 6. Interior construction
7. Moisture protection 7. Conveying
8. Doors, windows and glasses 8. Mechanical
9. Finishes 9. Electrical
10. Specialists 10. General conditions
11. Architectural equipment 11. Specialists
12. Furnishings 12. Site works
13. Special construction
14. Conveying systems
15. Mechanical
16. Electrical

Figure 2.8 Projects may be organized according to the CSI (Construction


Specifications Institute) sixteen-division master format or the twelve-division
uniformat.

The uniformat reflects how the project is built; the master format reflects how
the trades are organized.

40
41

As the project design develops, the systems estimate is updated to inform the
project team of design decision impacts. As long as good data are available, the
designer should be able to look at the costs of different alternatives and make a
selection based on cost as well as durability over time. Take, for instance,
choices for flooring: vinyl tile, carpet, terrazzo, quarry tile, ceramic tile, and many
more. By comparing cost, intended use, and maintenance issues, the choices
become clarified. Terrazzo is the most expensive of the options but will last the
longest and keep its finish. However, if the terrazzo is laid in an area where there
will be renovations, it is not easy to patch. Vinyl tile, on the other hand, usually
has the least first cost but over time wears down. Assemblies estimating allows a
project team to prepare this sort of analysis.

2.6.2 Estimating during Construction

Once the design documents are complete, companies interested in actually per-
forming the work price the project. Estimators working on this type of bid hope
to win the job with the most competitive number while maintaining a reasonable
profit for the company. This estimate is the most detailed of all estimate types
and is also the most important. It carries with it legal implications. If its bid is
accepted, a construction company is legally bound to a specific price for a
specific scope of work. During the actual construction, however, there is give
and take over the individual prices of each piece of the construction. The con-
tractor must continually negotiate with suppliers and subcontractors over these
prices throughout the procurement stage. If the contractor is a good negotiator
and has priced the project with an adequate contingency, then the final outcome
should give the company a fair profit.

Especially on large complex projects, the scope of work is a continual focus of


discussion between the contractor and the designer. No matter what type of
contract is signed, someone is always at risk. Wherever that risk exists is where
team members hotly debate about what is reasonable to include and what
should be accepted as a change. Contractor can help this situation by listing
any qualifications when bid is submitted. Thus, discussions about the real scope
of work can happen before there is any legal commitment regarding costs.

41
42

Figure 2.9 Partition assemblies listed are differentiated by the type of framing,
thickness, type of drywall, and whether or not insulation is used. (From Means
Square Data Book, 2001).

42
43

Many factors affecting costs lie outside the scope of work. There are owner-
requested changes, unforeseen conditions, and new regulatory requirements.
These also must be priced as they emerge. Because the pricing established at
bid time is done on a unit basis, it can help the contractor give information
quickly to the owner about the cost impact of each change.

Detailed estimates take weeks to prepare and involve people from many
different disciplines. A general contractor who is preparing a bid, requests
proposals from subcontractors and quantifies (takes off) and prices work that
will be done by his or her own work force. Quotes from material suppliers (also
called vendors) are used where possible to get precise material prices. When
quotes cannot be obtained, contractors use company records and published
cost data. Current wage rates and perceived worker productivity are figured into
these costs. The estimator must, in essence, build the project on paper.
Hypothetical methods of construction; logistics of the site, with its constraints for
storage and maneuverability; delivery strategies; and the schedule of activities
all must be understood before a realistic price can be assembled.

2.6.2.1 Organization of the Estimate

Good organization is key to preparing reliable estimates and avoiding mistakes.


Preparing a detailed estimate is a complex organizational task. Many people,
both inside and outside the company, are involved. Information comes from a
variety of sources and must be carefully catalogued. The estimating team's goal
is to minimize the number of company hours involved while preparing a
competitive estimate.

To begin, adequate space is set up, the right mixture of senior and junior team
members are assigned, and procedures and forms are assembled. A notebook
or file system is set up to track all activities. Much of this tracking is done with
computer estimating software.

The most important information for the estimating team comes from the contract
documents, which explain the scope of the work, the quality of the work, the
conditions the contractor is expected to meet, the legal requirements of the job,
and the schedule of completion. Of all sources of information received during
the bid period, these require the most careful consideration and handling.
Drawings and specifications, which make up the contract documents, are
usually available from the owner or architect for a refundable deposit. By setting
up a plan room in the office or some other central location, the contractor makes
these documents available to subcontractors. When the contractor receives the
set of documents, the first task is to verify that a full set has actually been
received. The drawings are numbered by discipline and the specifications

43
44

separated by trade. Addenda, which are issued during the bid period, need to
be carefully tracked and the information made available to the subcontractors.

2.6.2.2 Quantity Takeoff

Once the estimating tasks are identified, categorized, and organized, the team
begins the quantity takeoff. This is the foundation of the estimate. Its purpose is
to accurately determine the quantity of work that needs to be performed on the
project. Every work item is measured and quantified, separating the work into
units of labor, material, and equipment. Most estimators use the CSI's sixteen
divisions (see Figure 2.8). The goal of the quantity takeoff process is to
calculate every item of the project—no more and no less. To effectively
accomplish this, the takeoff must use the correct units. The process requires a
thorough understanding of the work involved in each of the different disciplines
of the project. Often the best approach is to build the project item by item on the
takeoff form and then quantify each item. Preprinted takeoff forms, which
identify all estimate items, can serve as checklists.

2.6.2.3 Unit Pricing

The next task is to determine how much each unit will cost to produce, deliver to
the site, accept and store at the site, install in the correct position, and maintain
until the project is turned over to the owner. Production of the product and
delivery to the site are included in the material unit price. The cost of installing
the product is part of the labor unit price. The equipment necessary to move the
unit into place and install it is included in the equipment unit price. Project
overhead covers the costs of accepting the material, storing it at the job site,
and protecting it until the project is accepted. Company overhead includes the
cost of preparing the estimate, marketing the company and providing broad
based technical and administrative support for the project.

2.6.2.4 Material Costs

Of all the prices that need to be identified, the material prices are usually the
most straightforward to determine. The most reliable source is the supplier.
However, the estimator must ensure that the price quoted actually covers all the
specification requirements and the estimator's assumptions. The following
points must be verified:

• The material quoted is the correct model number, color, and


finish.
• The price is valid until the scheduled delivery time.
• The price includes delivery to the job site.

44
45

• Adequate warranties and guarantees are provided.


• The lead time fits into the scheduled need on site.
• There is adequate stock available.
• Payment terms, discounts, and credits are well documented.

2.6.2.5 Labor Costs

The price of labor is the most difficult factor to determine because both the
hourly wage rate and crew productivity must be considered. The wage rate is a
factor of the rates paid to a specific trade. Union rates are available from the
union locals and employer bargaining groups. Nonunion labor rates are de-
termined by each company and depend on the geographic area. In either case,
wage escalation must be factored in, particularly on long-term projects. Union
rates are generally negotiated for one to three years by each trade, so these
agreements need to be researched. Factors to consider include the following:

• Expiration dates of the union agreements


• Amount of overtime anticipated
• Availability of skilled labor in the area
• Amount and nature of any hazardous conditions

The expiration of a union agreement probably means increases in labor rates


and could, with disputes, mean interruption in the project. For projects with an
aggressive schedule, overtime is likely; and if the project is in a remote area,
there will be increased costs in bringing in labor. If the conditions have any
special hazards, the rates will also be higher to compensate for the increased
risk.

Once the quantity of work is known and the hourly wage determined, the last
step in determining labor cost is to estimate how long the activity will take.
Determining crew durations or productivity requires experience and the ability to
visualize how the work will be done in the field. An estimator needs to know the
following:

• Expected efficiency rate


• Other work occurring at the same time that could interfere with
this activity
• Expected weather conditions
• Specific conditions of the work: that is, working on ladders or scaffolding
versus working on the ground
• Duration and frequency of overtime

45
46

Past project experience is essential in determining these factors. Thus, in most


offices the quantity takeoff may be assigned to a junior estimator, but senior
members almost always determine the unit prices.
2.6.2.6 Equipment Costs

Equipment, which includes small tools needed to complete specific tasks, are
covered item by item. However, large, mechanically driven machinery such as
cranes, lift trucks, and the like are usually covered on a project basis since they
often are used throughout the project for different activities. Equipment costs fall
into two general categories: the equipment itself and the cost of operating it.
The first category covers ownership, lease or rental, interest, storage, insurance
taxes, and license. If the company owns the equipment, these costs are
determined in-house. If not, the equipment supplier provides a quote. The
second category includes gasoline, oil, periodic maintenance, transportation,
and mobilization. The cost of the operator is normally covered under the labor
line item.

2.6.2.7 Subcontract Work

The contractors bidding on the project break down the job into work packages
and request bids from prequalified subcontractors for each package. Most
general contractors do some of the work with their own work force and therefore
do not request bids in these areas. It is important for the estimator to be in
contact with the subcontractors during the bid period. This communication can
minimize misunderstandings about the scope of work assumed by the
subcontractor. It also encourages the subcontractor to put in a fair bid. When
the bids arrive from the subcontractors, a debriefing session should take place
to ensure that commonly missed items have been picked up. When the
estimator is starting to apply overhead and profit to the base costs, it is
important to be able to separate subcontractors' work from the contractor's.
Because subcontract prices include tax, insurance, and overhead and profit, the
adjustment on this price will be different from the adjustment done for the work
of the contractor's own forces.

2.6.2.8 Overhead

In the CSI format, Division 1 is general requirements- This line item is also
called project overhead. It picks up the costs associated with operating the job
site and some home office expenses. Job site costs include the field office
people, safety security photography and cleanup. These costs are typically
itemized, with quantities and unit prices figured exactly. Figure 2.10 lists typical
general requirements. One of the line items on this summary is for main office
expense. This is usually carried as a percentage and includes costs such as

46
47

office rent or real estate costs, vehicles, engineering support, clerical staff, top
management salaries, marketing, legal, and accounting fees.

47
48

Figure 2.10 A checklist of common overhead items.

48
49

Figure 2.10 Continued (From Means Form Book).

49
50

The equipment overhead accounts for the costs of managing the purchase or
rental, storage, and handling of materials and equipment. Labor overhead is the
greatest of the cost categories. The base labor cost includes the worker's take-
home pay plus any fringe benefits, including vacation time and paid sick days.
Added are the costs associated with workers' compensation insurance,
unemployment, social security taxes, builders' risk insurance, and public liability
costs. Subcontractors' costs also are adjusted for overhead as a percentage.
Although the subcontractors include overhead for most of these categories in
their own prices, the contractor's price covers the costs associated with
organizing the bid packages, prequalifying subcontractors, reviewing the bids,
and managing the subcontractors' work in the field.

2.6.2.9 Profit

A company grows and maintains its corporate health through its ability to make
a profit. The investment of time and energy and the acceptance of risk inherent
in a construction project make the inclusion of profit even more critical. Profit is
added after the contractor has priced the labor and equipment involved.
Overhead has covered the costs associated with managing the job in the field
and the costs of supporting the project in the home office. If no profit were
added, the business might stay afloat for some time but would not grow. The
company would also have no financial tolerance for mistakes or unforeseen
conditions. Eventually, a company without adequate profit would not survive.

Companies must add a profit margin into each project. The amount of profit
added is a factor of the type of project, its size, the amount of competition
anticipated, the desire to get the job, and the extent of the risks. If the company
needs work, is faced with substantial competition, or has a strong desire to
move into a new relationship with a client, the profit charged might be small.
However, the company should not have too many small-margin jobs on the
books at the same time so that it has sufficient coverage if something occurs on
one job. A project with a high risk or one with little competition allows a
company to add a higher profit.

2.7 Add mark-ups

Facilities for adjusting the amount of monies in the cost categories of labor, plant,
materials and own subcontractors exist, together with facilities for entering
overheads as percentages or lump sums and profits as percentages.

50
51

2.8 Reports

Figure 2.4 presents a typical layout from a computed operational estimate.


Printed reports available include:

• Bills of quantities giving the labor, plant a n d materials breakdowns, in


directs costs rates a n d rates including mark-ups; Fig. 2.11 is an example
• The same listing without the labor, plant and materials breakdowns
• Direct cost summaries; Fig. 2.12 is an example
• Resource reconciliation reports; Fig. 2.4 is a n example.

Figure 2.11 Bill of quantities listing with, plant, materials and subcontractor
breakdowns.

Bill of Quantities listing

Figure 2.12 Direct cost summary.

51
52

CHAPTER 3
TENDERING
3.1 Tendering Adjustments

Based on the reports prepared by the estimators, the staff charged with the
responsibility of submitting the tender will assess the estimate and decide on the
additions to cater for risk, company overheads and profit. The groups of staff
concerned, sometimes referred to as the tender adjudicating panel, will comprise
representatives of senior management and representatives of the estimating
team. It is the responsibility of this panel to satisfy themselves that the estimate is
adequate. This is done by studying the reports prepared by the estimator and
interrogating the estimator on the underlying assumptions and decisions. It does
result on many occasions that the estimate is adjusted, usually in the form of
lump-sum additions or subtractions.

The additions for risk, overheads and profit are frequently referred to as the
'mark-up' and are allowances for:

• 'Risk' if the chance of probability of making a loss is assessed as being


greater than that of breaking even
• 'Company overheads1 to cover the central head-office costs that are
involved in administering the contract
• The ‘profit’ considered to be possible in the existing market.

The manner in which contractors assess these additions varies enormously from
company to company. These additions are incorporated into the tender in a
variety of ways, including lumpsum additions and subtractions and pro rata
adjustments.

The discounts' taken on materials and subcontract quotations are sometimes


considered as an extra source of profit and it is not unknown for a contractor in
very poor markets to submit a tender with a zero or negative profit allowance and
rely on such discounts to produce the profit required. Thus, strictly speaking, the
'discounts1 should be considered as part of the tender additions.

3.2 Submitting the tender

The tender figure arrived at above is entered by the estimators into the contract
documents in the manner required by the contract documents, which is either as
a priced bill of quantities or submitted on a form of tender with no bill of
quantities.

52
53

3.2.1 Tendering with a priced bill of quantities

In submission of a tender with a priced bill of quantities the direct cost rates
calculated for each item need to be amended to take account of both the
estimate adjustments and the mark-up. As previously stated, the estimate
adjustments tend to be made as lump-sum additions or subtractions: logically
however, they require the adjustment of the direct cost rates. In apportioning the
mark-up there are a variety of practices such as:

• Marking up all items by a percentage calculated to cover overheads and


profit.
• Including the mark-up additions as lump sums in the preliminary section of
the bill.
• Marking up the bill items by different percentages to create some element
of rate loading in order to create a favorable cash flow;

The preliminary section of the bill is frequently used to include site overheads,
estimate adjustments and the balance of the mark-up. In some cases, lump sums
are included in the preliminaries and the remainder of the mark-up additions are
apportioned over the bill items.

3.2.2 Tendering without a bill of quantities

In cases where tenders require only the submission of the form of tender, the
contractor need y submit the global sums as required. If the submitted tender is
seriously being considered, then the completed bill of quantities maybe called for
by the professional quantity surveyor. This practice is frequently used in building
contracts.

3.3 Calling For Tenders

An employer may publicly advertise (by press) that he is open to receive tenders.
It is usual for the engineer to draft this notice so that it contains a brief but
adequate description of the proposed works and their location, so that contractor
can judge whether they are interested in tendering. It is also usual to state that
no expenses incurred in tendering will be reimbursed and that the employer does
not bind himself to accept the lowest, or any ender. Contractors are normally
required to pay a deposit, before they get a set of tender file.

An alternative procedure to public advertisement of tender is to invite certain


contractors only to submit tenders. Probably the best way to do this is to
advertise that contractors may if they send in their qualifications and experience,
apply to be placed on a list of “selected tenders”. This is called pre-qualification,

53
54

and it saves time for both contractors and the engineer and employer. Thus, for
the construction of a bridge, a public advertisement might be issued inviting
contractors, experienced in bridge building to apply to be placed on the list of
selected tenderness. Applications would be asked to provide details of their past
experience, present force, plant, and equipment, and to give the names of
previous employers they have worked for.

However, sometimes the engineer may himself draw up a list of selected tenders
in consultation with the employer, without resorting a public advertisement. But
this may not be fair to certain contractors.

3.4 Comparing Tenders

It is the engineer’s job to recommend to the employer which contractor’s offer


should be accepted. It should be noticed that, the engineer does not accept the
offer, or does he make the final decision. The engineer recommends, the
employer decides and acts.

The first criterion is of course, the sum total offer made by each contractor. It is
important to see whether each contractor is, in fact. Some tenders may be
submitted with certain reservations which are contrary or additional to the
conditions give in the tender documents. Some tenders may contain arithmetical
mistakes or mistakes of interpretation of the documents. All these matters are
listed side by side and where necessary, adjustments made to the total sums
offered. After this comparison 3 or 4, offer are selected and examined in detail. If
the tenders are based on bills of quantities, the detailed prices submitted by
different contractors for the same portions of the work are compared. This will
reveal relatively high or low unit prices for certain types of work, so that the
engineer can decide what trouble could be in certain parts of the work. The
engineer will not like a contract making high profit from some part of the work and
high loss from the other part.

3.5 Choosing a Tender

With the completion of the close check, and comparison, the engineer may invite
one or two of the lowest tenderness to his office, to discuss certain points of their
offer. Principally he may wish to be provided with further evidence from a
tendered, such as, proposed methods of construction, and his proposed
program. The engineer will not of course reveal to any contractor the prices
offered by others. Meantime, the engineer Amy made private contract with the
referees named by the contractors. Then the decision is made as to which tender
should be recommended for acceptance.

54
55

3.6 Those Who Can’t Take Part in Bidding Committee

1. Member of the bidding commission


2. Employees linked to the bidding or bidding commission (secretary, etc.)
3. Highest ranking of civil and military official
4. Fathers, mothers, brothers, children, wives, husbands, sons in law, father
in law of items 1, 2 and 3 above.
5. Those not allowed to take part in biddings. (as penalty)

3.7 Documents That a Bidder Should Submit

1. Registration
2. Bonds
3. Contractorship license
4. Permission to take part in biddings
5. Documents show that the company is active
6. Lists of signatures

3.8 Bonds

There are two types of bonds used in construction projects.

a) Bid bond
b) Performance bond

3.8.1 Bid bond

Bid bond is a kind of guarantee given by the contractors to the client. The
guarantee includes the condition that if the contractor wins the bidding he will
definitely sign the construction contract. Otherwise, the contractor will lose the
guarantee (bid bond) he offered to the client.

Amount of bid bond is normally about 5% of the tender. At the end of the bidding
if a company doesn’t win, the bid bond is paid back to him. But if a company wins
the bidding and then gives up doing the job, the bid bond is not given back to
him. Those are accepted as Bid Bonds.

1- Money
2- Bank guarantee letter
3- National bends
4- Shares of companies
5- First rate of mortgage

55
56

3.8.2 Performance Bond

Performance is a kind of guarantee given by the contractor to the client that, the
contractor will do the job according to the contract signed between the client and
the contractor and the quality of the job is guaranteed by the contractor for a
specific duration of time mentioned in the contract. This duration is one year in
many construction projects.

The amount of performance bond is normally about 10% of estimate cost. But
when a company signs a contract, the bid bond is transferred as performance
bond, which is 5% of tender where it is half of the performance bond. The rest of
the performance bond is cut from the payments. At each payment, 10% of the
payment is cut transferred to performance bond.

Example:

Tender: 10,000,000.- TL
Bid Bond: 10,000,000 * 5% = 500,000.- TL
Performance bond: 10,000,000 * 10% = 1,000,000.- TL

Although bid bond is transferred to performance bond, to complete performance


bond another 500,000.- TL is necessary. And that amount will be cut from
payments as 10% of the payment.

Suppose: 1st payment 1,750,000.- TL


As performance bond 1,750,000TL x 0,1 = 175,000TL is cut
2nd payment = 2,500,000 - TL 2,500,000 x 0,1 = 250,000TL is cut
Summation of Performance bond = 425,000.- TL

To complete performance bond another 500,000 – 425,000 = 75,000TL must be


deducted (only) from the 3rd payment.

 1st payment: 1,750,000 – 175,000 = 1,575,000TL


 2nd payment: 2,500,000 – 250,000 = 2,250,000TL
 3rd payment: 3,000,000 – 75,000 = 2,925,000TL

From the rest of the payments no money will be cut as performance bond.

The contractor can take back his performance bond if


• The permanent acceptance of the work is done
• The contractor brings a certificate from social Insurance office to rove that
all the insurances of the s are paid.

56
57

3.9 Types Of Bidding

a- Closed bidding
b- Open bidding
c- Limited bidding
d- Bargaining

3.9.1 Closed Bidding

There are two envelopes one inside the other one. First envelope (other one)
contains, name, address of company, and other documents of bidding. If there
are any missing among them the second envelope is not opened, and the
company is asked to complete. Otherwise the second envelope is opened and
the signed tender is read. This bidding is used specially for large jobs.

3.9.2 Open Bidding

There is only one envelope, and every documents and signed tender are in that
envelope. It is used for small jobs.

3.9.3 Limited Bidding

If the job requires a certain quality, the tender of all contractor companies are not
accepted and a limitation is required. It may be open or closed bidding.

3.9.4 Bargaining

It is used for,
i) Small, urgent job
ii) Jobs that can be carried out by only one company.
iii) Under forced conditions (such as earthquake, flood war etc).
iv) Jobs not planned but urgent.
v) Bids with no offer or offers above expected value.

57
58

APPENDIX A
Unit Prices announced by Chamber of Civil Engineers and Chamber of Architects
of Cyprus Turkish Union of Chambers of Engineers and Architects.
MİMARLAR ODASI VE İNŞAAT MÜHENDİSLERİ ODASI
YÖNETİM KURULLARINCA BELİRTİLEN
1 TEMMUZ 2010 – 30 EYLÜL 2010 TARİHLERİ ARASINDA
“YAPI BİRİM MALİYETLERİ”
BİRİM
S.No: YAPI TÜRLERİ
MALİYETLERİ
1 Konut ( IV. Sınıf ) 616.-TL./M²
2 Konut ( III. Sınıf ) 1155.-TL./M²
3 Konut ( II. Sınıf ) 930.-TL./M²
4 Yardımcı Binalar ( I. Sınıf ) 595.-TL./M²
5 Apartman Tipi Konut 908.-TL./M²
6 Sendeli Dükkan 908.-TL./M²
7 Sendesiz Dükkan 792.-TL./M²
8 Okul 808.-TL./M²
9 Yurt 994.-TL./M²
10 Ofis Tipi Binalar (Standart) 774.-TL./M²
11 Ofis Tipi Binalar (Özellikli) 974.-TL./M²
12 Yanları Kapalı Garaj 616.-TL./M²
13 Fabrika (Atölye Tipi Binalar) 616.-TL./M²
14 Süthane, Salhane 697.-TL./M²
15 Fırın 932.-TL./M²
16 Otel I 1154.-TL./M²
Otel II 1320.-TL./M²
Otel III 1473.-TL./M²
17 Bungalov 980.-TL./M²
18 Yüzme Havuzu 1074.-TL./M²
Yüzme Havuzu Olimpik 1186.-TL./M²
19 Sinema, Çok Maksatlı Salon 1297.-TL./M²
20 Gazino, Lokanta 1106.-TL./M²
21 Benzin İstasyonu 764.-TL./M²
22 Oto Tamirevi 616.-TL./M²
23 Ağıl 306.-TL./M²
24 Kümes 306.-TL./M²
25 Çatısı saç veya atermit türü duvarları yığma basit yapılar 591.-TL./M²
26 Otopark ( Yanları Açık) 570.-TL./M²
27 Bodrum (Otopark, Depo) 615.-TL./M²
28 Sığınak Amaçlı Bodrum 764.-TL./M²
29 Sığınak (Blok) 646.-TL./M²
30 Parselasyon 215.-TL./M²
31 Telleme 113.-TL./M²

58
59

32 Bahçe Duvarı 260.-TL./M²


33 Kapalı Havuz 1618.-TL./M²

APPENDIX B

59
60

EXAMPLE FOR BILL OF QUANTITIES

60
61

61
62

62
63

63
64

64
65

65
66

66
67

Dimension Quantity
Ite Num
m Description of work ber Length Width Height Unit + - Total
A Earth work
A1 Excavation footing T1 4 1.00 1.00 1.00 m3 4.000
A2 Sand under footing T1 4 1.00 1.00 0.10 m3 0.400
A3 Compacted soil 1 5.80 5.80 0.25 m3 4x.25x.1x.1 8.410
4x.25x.1x.1
A4 Hard core 1 5.80 5.80 0.15 m3 5 5.046

B Concrete work
Plain Concrete
B1 Footing T1 4 1.00 1.00 0.60 m3 2.400
B2 Slab on grade 1 5.80 5.80 0.10 m3 4x.1x.1x.1 3.364
B3 Concrete pavement 2 6.80 0.30 0.20 m3 0.816
2 6.20 0.30 0.20 m3 0.744
7.324
Reinforced Conrete
B4 Footing T1 4 1.00 1.00 0.30 m3 1.200
B5 Ground beam 2 6.20 0.20 0.50 m3 4x.1x.1x.5 1.240
Ground beam 2 5.80 0.20 0.50 m3 1.160
B6 Column 4 0.30 0.30 2.65 m3 0.954
B7 Slab concrete 1 5.80 5.80 0.15 m3 5.046
4x.1x.1x.2
B8 Beam concrete 2 6.20 0.20 0.40 m3 5 0.992
2 5.80 0.20 0.40 m3 0.928
B9 Parapet bottom 2 6.60 0.20 0.15 m3 0.396
2 6.20 0.20 0.15 m3 0.372
Parapet sides 2 6.60 0.10 0.15 m3 0.198
2 6.40 0.10 0.15 m3 0.192
12.678
C Formwork
C1 Ground beam 4 6.20 0.50 m2 12.400
Ground beam 4 5.80 0.50 m2 4x2x.1x.5 11.600
C2 Column 16 0.30 2.65 m2 12.720
C3 Beam sides 4 6.20 0.25 m2 6.200
Beam sides 4 5.60 0.25 m2 4x2x.1x.5 5.600
Beam bottom 4 5.60 0.20 m2 4.480
C4 Slab 1 5.80 5.80 m2 33.640
C5 Parapet bottom 2 6.60 0.20 m2 2.640
Parapet bottom 4 6.60 0.30 m2 7.920
Parapet sides 4 6.40 0.15 m2 3.840
C6 concrete pavement 4 6.8 0.2 m2 5.440
106.480
E Brickwork
E1 20cm brick
(A-A),(1-1),(2-2) 3 5.60 2.65 m2 2x1.6x1.2 33.000
B-B 1 5.60 2.65 m2 1x1x2.2 12.640
45.640

67
68

Item Description of work Number Length Width Height Unit + - Total


F Plastering
Internal Plastering
F1 (3 coats)
(A-A),(1-1),(2,2) 1 5.60 2.65 m2 6x1.6x1.2 33.000
B-B 1 5.60 2.65 m2 1x1x2.2 12.640
Ceiling 1 5.80 5.80 m2 33.640
Columns 8 0.10 2.90 m2 2.320
Beams 4 5.60 0.25 m2 5.600
87.200

External Plastering (2
F2 coats)
(A-A),(1-1),(2,2) 3 6.20 3.20 m2 6x1.6x1.2 48.000
B-B 1 6.20 3.20 m2 1x1x2.2 17.640
parapet bottom 2 6.60 0.20 m2 2.640
parapet bottom 2 6.20 0.20 m2 2.480
parapet sides 4 6.60 0.30 m2 7.920
parapet sides 4 6.40 0.15 m2 3.840
parapet top 2 6.60 0.10 m2 1.320
2 6.40 0.10 1.280
85.120
G Tiles
G1 Floor tiles 1 5.80 5.80 m2 4x0.1x0.1 33.600
G2 Wall skirts 4 5.60 m 4x0.2 1 22.200
G3 Window sill 6 1.60 m 9.600
G4 Stairs (1m) 1 1.00 pcs 1.000

H Painting
H1 Internal painting m2 87.200
H2 External finish spirit m2 85.120

I Aluminum works
I1 Aluminum door (1*2.2) 1 pcs 1.000
I2 Aluminum window 6 1.60 1.20 m2 11.520

J Isolation for slab 1 6.60 6.60 m2 43.560

68
Description Reinforcement Quantity Reinforcement Bar Sizes
of Diameter No: Similar: Length: 8 10 12 14 16 18 20 22 24
Item activity Weight per unit length(kg/m) 0.395 0.617 0.888 1.208 1.578 1.998 2.466 2.984 3.551

Subtotal
D Steel Reinforcement

D1 Footing Reinforcement
T1 Ǿ16 16 4 1.156 73.984

D2 Starting Columns R.
A1,B1,A2,B2 Ǿ16 4 4 1.962 31.392
Ǿ8 5 4 1.128 22.56

D3 Ground beams R.
BK 20/50 Ǿ14 4 4 6.374 101.984
Ǿ8 29 4 1.328 154.048

D4 Column reinforcement Ǿ16 4 4 3.300 52.8


A1,B,A2,B2 Ǿ8 17 4 1.128 76.704

D5 Reinforcement for slab


K101
Straight bars Ǿ14 4 4 6.374 101.98
Bend up bars Ǿ14 2 4 7.220 57.76
Stirrups Ǿ8 29 4 1.128 130.848

D6 Slab D101
Straight bars Ǿ10 23 2 6.566 302.04
Bend up bars Ǿ10 23 2 6.848 315.01
Ǿ10 2 4 1.500 12.00

Sum of Length: 384.16 629.04 0 261.73 158.18


Sum of Weight: 151.743 388.12 0 316.17 249.59

69
Item Description of work Unit Quantity Unit prices Sum
A Earth work
A1 Excavation footing T1 m3 4 2.600 10.400
A2 Sand under footing T1 m3 0.4 27.420 10.968
A3 Compacted soil m3 8.41 4.300 36.163
A4 Hard core m3 5.05 42.000 212.100
269.631
B Concrete work
Plain Concrete
B1 Footing T1 m3 2.4 100.000 240.000
B2 Slab on grade m3 3.36 100.000 336.000
B3 Concrete pavement m3 1.56 100.000 156.000
732.000
Reinforced Concrete
B4 Footing T1 m3 1.2 125.000 150.000
B5 Ground beam m3 2.4 125.000 300.000
B6 Column m3 0.954 125.000 119.250
B7 Slab concrete m3 5.046 125.000 630.750
B8 Beam concrete m3 1.92 125.000 240.000
B9 Parapet m3 1.152 125.000 144.000
1584.000

C Formwork
C1 Ground beam m2 24 8.000 192.000
C2 Column m2 12.72 15.380 195.634
C3 Beams m2 23.68 15.380 364.198
C4 Slab m2 33.64 15.380 517.383
C5 Parapet m2 16.86 15.380 259.307
1528.522

70
71

Item Description of work Unit Quantity Unit prices Sum


D Reinforcement
D1 Footing tons 0.1151 580 66.758
D2 Starting Columns tons 0.06285 580 36.453
D3 Ground Beams tons 0.268 580 155.440
D4 Columns tons 0.1496 580 86.768
D5 Beams tons 0.256 580 148.480
D6 Slab tons 0.5896 580 341.968
835.867
E Brickwork
E1 20cm brick m2 45.64 28.720 1310.781

F Plastering
F1 Internal Plastering (3 coats) m2 89.52 12.620 1129.742
F2 External Plastering (2 coats) m2 75.08 10.680 801.854
1931.597

G Tiles
G1 Floor tiles m2 33.640 15.570 523.775
G2 Wall skirts m 24.000 15.570 373.680
G3 Window sill m 9.600 15.570 149.472
G4 Stairs (1m) pcs 2.000 15.570 31.140
1078.067
H Painting
H1 Internal painting m2 89.52 10.500 939.960
H2 External finish spirit m2 75.08 8.520 639.682
1579.642

I Aluminum works
I1 Aluminum door (1*2.2) pcs 1 230.560 230.560
I2 Aluminum window m2 11.52 110.460 1272.499
1503.059
-
J Isolation for slab m2 42.25 130.000 5492.500

71
72

ITEM ACTIVITY COST


A EARTH WORK 269.63
B CONCRETE WORK 2316.00
C FORMWORK 1528.55
D REINFORCEMENT 835.87
E BRICKWORK 1310.78
F PLASTERING 1931.60
G TILES 1078.07
H PAINTING 1579.64
I ALUMINUM WORKS 1503.06
J ISOLATION 5492.50
TOTAL 17845.70

72

Você também pode gostar