PT.

WASKITA KARYA (PERSERO)


Bidding for NGAWI RING ROAD Project – EAST JAVA

STRATEGIC ROADS INFRASTRUCTURE PROJECT

NGAWI RING ROAD


(01-28 / 04-SRIP-WP1 / NR / A / 4834 / 08-07)
EAST JAVA

CHAPTER I GENERAL

A. Project Brief

Strategic Roads Infrastructure Project “Ngawi Ring Road in East Java” the Government
of Republic Indonesia with source of funds from International Bank for Reconstruction and
Development (IBRD). The Project is located in Ngawi, East java province - Indonesia. This
project has functional length about 10.75 Km.

Lokasi Proyek

Project Location

1
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

The major scope of works are the New Road Construction and Road Betterment of the
part of the construvting a new Road by flexible Pavement 6.40 Km and the Road betterment
are 4.35 Km (Overlay of asphalt mixtures on existing pavement), additional/improvement of
both side shoulders and completing / finishing of a new bridge by constructing approach slab
and reinforced concrete slab deck with total span 120 m and 9 m wide. Duration of the project
completion is 540 calendar days (18 months).
Kind of work will be executed are as follows :
a. General :
- Mobilization
- Traffic management and Safety
- Relocation of Existing TELKOM Pole
- Relocation of Existing PLN Pole-Low voltage
- Relocation of Existing Tfraffic Sign pole
- Relocation of Electrical Panel
b. Drainage :
- Excavation for Drainage Ditches & Waterways
- Mortared Stonework
- Reinforcement Concrete Pipe Culvert Inside Diameter 75 cm to 120 cm
- Unreinforced Concrete Pipe Culvert Inside Diameter 20 cm
c. Earth Works :
- Common Excavation
- Structure Excavation, 0 - 2 m depth
- Excavation on Existing Asphalt Pavement Materials with Cold Milling Machine
- Common Embankment
- Selected Embankment
- Grade Preparation
d. Granular Pavement
- Aggregate Base Class A
- Aggregate Base Class B
e. Asphalt Pavement
- Prime Coat
- Tack Coat
- Asphalt Concrete - Wearing Course (AC-WC) t=4Cm
- Asphalt Concrete - Binder Course (AC-BC)
- Asphalt Concrete – Binder Course (AC-BC) Leveling
- Asphalt Concrete – Base Course (AC-Base)

2
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

f. Structure
- Structural Concrete Class K 350
- Structural Concrete Class K 250
- Unreinforced Concrete Class K 175
- Reinforcing Steel Plain Bars U-24
- Stone Masonry
- Joint Expansion Steel Angle Type
- Elastometric Bearing Type 3
- Steel Bridge Railing
- Bridge Name Plate
- Demolition of Prestressed Concrete
- Demolition of Steel Stringer
g. Reinstatement & Minor Works
- Hot Asphaltic Mixture for Minor Works
- Residual Bitumen for Minor Works
- Pavement Markings Thermoplastic Type
- Road Signs with Reflector of Engineering Grade
- Guide Posts
- Kilo meter Posts
- Guard Rail
- Precast Portland Cement Concrete Curb
- Block Paving on Sidewalks or Medians
- Ixora SP (Soka Jawa)
- Bougainviela SP (Bougenville Ungu)
- Erythrina Varigata (Dadap Kuning)
- Road Lighting Single Arm
- Road lighting Double Arm
- Traffic light System Type 1 for Intersection of three legs
- Guide Sign
- Sound barrier
h. Day Works
- Foreman
- Labour
- Skilled Labour
- Dump Truck
- Flat Bed Truck 3 - 4 ton

3
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

- Water Tank Truck 3000 - 4500 Liter


- Bulldozer 100-150 HP
- Wheel Wloader 1.0 - 1.6 M3
- Crawler Loader 75 - 100 HP
- Excavator 80-140 HP
- Crane On Wheels 10 - 15 ton
- Tandem Roller 6 - 9 ton
- Pneumatic Tire Roller 8.0 - 10 ton
i. Routine Maintenance Work
Routine maintenance of pavement, shoulders, ditches, drain, cutting & embankment, Road
Furniture and bridges.

B. Provision of site access work

Proper access roads are the first step to succesfully execute of the project. Good
access is needed to deliver equipment, materials, tools, and other material/goods for the
execution of the project. Access road should as short as possible have the adequate capacity to
carry the heavy equipments need for the project.

C. Environmental (preservation & impact)

Last some years very dominant environmental issue in execution of this matter project
is caused by the existence of progress of reform, so that more and more organizations office
non society and government about becoming direct supervisor of execution of environmental
project specially, although contractually the mentioned there no.
In order not to having a negative impact to the environment and in reverse not to be
disturbed by the environment, everything has to be arranged properly. All vehicles should be
regulated in order to undisturbed the traffic on existing road. Avoid any jam that can result
loss to any parties is our concern since this will directly influence to the project activities as
well. Waste material disposal will be maintaned as such that the waste will not to pollute the
environment surrounding the project location.
The noisy resulted from the operation of the heavy equipment to be used for the
project will be minimized so as not to disturb the inhabitant surrounding the project. The
intensive coordination with the relevant government institution will be arranged to ensure the
project can be proceeded in the safely manner. For the agenda of improving performance, PT.

4
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Waskita apply Environmental System Management which relate [at] Standard of ISO 14001 :
2004. In General, Environmental System Management is as drawn in scheme hereunder:
Planning

Identify Environmental Identify Environmetal law


Defect and Order

Evaluated important thing’s


Decicion
making

Execution

Monitoring

5
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Repair and Inprovement

Borrow material area


Change of land surfaces will be occured as a consequence of cutting and moving of soil
material needed as embankment material for the project. Impacts to the locations are dust,
and increasing volume of rains water flow because of the underbrush vanishes.
Measures will be taken to preserve the environment as much as possible. Measures will include
making some deep holes to hold the rains water, cutting layer by layer so as not to change the
surface flow of water significantly, and eliminating the dust during excavation by spraying
water as required.

Quarry material area


The source of material are from ........ Quarries. The nearest is Quarry ...............
(deposit .................. m3 of stone). The others are Quarry .............. (deposit ..........
m3 of stone), Quarry ............... (deposit .............. m3 of stone) and Quarry ...............
(deposit ............. m3 of sand). The map bellow shows quarries location from the project.

6
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Location of Quarry

Plant equipment area


Plant areas are Stone Crusher Plant, Batching Plant, and Asphalt Mixing Plant will be manage so
as to minimized unnecessary waste of material and negative impact to the environment.
Stone crusher area
The main effect to environment occurs at the stone crusher is the unavoidable noise.
Usually the stone crusher is operated 24 hours a day as such that the ideal location
should be selected as far as possible from the local community as long as have the proper
access.
Asphalt Mixing Plant area
Asphalt Mixing Plant has waste material such spilled of oil, fuel, and fail production
process. Its environment effects can be avoided by preparing good planning, doing as
planned, concerning in procedure and always making good communication of material
management between plant and site.

7
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Batching Plant Area


Batching Plant has waste material as spilled of oil, fuel, fail production process and
wastewater. Doing better, and concern to procedure, can avoid environment problem.
Especially for wastewater, recycling process of that waste while the waste material can
be used for other purpose so as to eliminate the environment effect.
A long route of transportation material road
Impacts of transporting material on the road are dust, spilled material and noise.
Measures to be taken to minimize the impact including covering the material with canvas
or plastic sheet during transporting, washing the wheels of the dump trucks before
entering onto the public roads and hauling material in the day light so the noise of the
trucks do not disturb people at night. In case of working in the night arrange the speed
of dump truck safely to the environmental.
Project sites area.
Impacts of executing the project to the surrounding areas are noise from the equipment,
and dust especially when executing the soil embankment.
Excavated soil during the boring process will spill of the area, so the area will be
potentially dirty and wet. To avoid the spilled soil, some dick will be made as temporary
disposal and remove to the disposal area as soon as possible.
To eliminate the disturbance of noise to the nearest villages, the noisy equipment will be
scheduled to operate in the daylight period (not in the night times). To minimized dust,
the surfaces of earth works will be sprayed with water where required.
Worker barracks
The adequate toilets and bathrooms will be prepared in the worker barracks to avoid the
environment effect from the natural human processes and maintain of the worker
healthy.

D Site Planning

Site planning is made for managing the equipment location and other facilities that
will be utilized in construction project, such as warehouse, store, workshop, etc. Site facilities
of the project, planned locate at unused area beside the track of Ngawi Ring RoadProject or in
the other place adjacent to the project site.
The good site management will ensure in securing materials, controlling the equipments, and
securing labour. The Engineer approval will also be provided prior the usage of site. The
location of material and equipment will be managed as below :
- Avoid disturbance in public safety

8
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

- Provision the required access to simplify in inspection and material investigation by the
engineer.
For site lighting purpose such generator sets will be utulized for its power. For
minimizing traffic jam, the existing road is utilized to be temporary road by arranging its
traffic. The waste of material will be exited from site as soon as possible, so the space area
will free from waste material.

D.1. Project Management Target

The highest priority of all activities when executing the project is SAFETY while
ensuring the traffic in normal operations conditions, and finish the project in construction time
planned are the another goals.
To reach the target above, Project Management Team will intensively communicate
with the institution of :
- Ministry of Public Works
- DLLAJ
- Police
- PT. Jasa Marga
- Local sub District Authority
- Local community beside of project

D.2. Site Organization Structure


To oversee the total project management, there will be a Project Manager (General
Super Intendant) of high qualification in road and bridge works, and will be supported by some
site managers of similar qualifications and experience. Supervisors will head solid teamwork
and report directly to the site manager. The site managers and the supervisors will be directly
involved in the planning, organizing, implementing, directing, and supervising teamwork to
ensure the completion project in the timely manner. Depending on the volume of work, each
group will be divided into sub-groups, as necessary. Each subgroup shall be under one deputy
supervisor supported by foremen and leadsmen as required.
Coordination at the top group level shall be handled by the supervisor / group team
leader. The site manager, the supervisors, deputy supervisors, foremen, and leader are highly
qualified to handle the individual assignment.
The technical and logistic/equipment departments, the fabrication plant operation,
and the survey team as well will be under the responsibility of the general coordinator from
standpoint of performance and control. The contract/administration department in the other
hand will be directly under the project managers, and independent but in co-function with the

9
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

general coordination/operation for the overall project. The work safety operation, site security
and quality assurance will be likewise independent and directly reports to the project
manager. All the major departments will be in close coordinating and working in concerted
efforts toward the accomplishment of the overall objective under the project manager for the
successful completion of the poroject.
The experiences of selected management team of PT. Waskita Karya will undoubtedly
fulfill the high performance requirement in the management of the project in both work
quality and delivery (key-dates) including background experiences of personnel in the partinent
schedules under this proposal.

D.3. Coordination Meeting


In addition to the coordination meetings between main contractor and the Employer as
required under the contract. Internal coordination meetings between the different site
departments to be chaired by the Project Manager will be held at least twice a month, to keep
abreast of the project status in terms of accomplishment and schedule overall. The project
manager could call site management meetings anytime required. Individual departments will
be covened meetings as well depending on the needs. Meetings between departments among
work teams within a department or between departments is highly encouraged for the sake of
coordinating and resolving whatever differences/conflicts exist whether affecting the project,
departments or individuals.
It is undoubtedly that only through open dialogue most if not all problems are resolved
and hopefully give best solution for everybody’s benefit. To keep the records straight for
future reference, preparation of the minutes of meeting is necessary and should be strictly
observed.

D.4. Project Reporting


We realize that we must strictly comply with the contract requirements for project
reporting on weekly or monthly basis and other instruction during the project implementation.
The format, information needed, the period, and other needs usually come from the Employer.
Weekly reports usually are prepared for individual work items as may be required which is
indicating among others the actual cumulative progress to date, the weekly progress, the work
schedule for following week, weather report, problems encountered, unresolved problem,
anticipated problems, etc. This report reflects the overall contractor’s activities and direction
and will give the Employer all necessary information for decision-making.
On the other hand, the monthly report well be prepared / submitted with the primary
purpose of progress claim. Document evidences will properly support all claims by contractor.

10
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

The detailed accomplishment of the project will be shown and plotted against the original
schedule to define the actual performance against the plan. Among others, the equipment,
materials, accident if any and other relevant safety /security reports, and also progress photos
showing work progress between periods, accomplishment projection for original schedule and
cash flow will be prepared to monitor both weekly and monthly progress which are
essential/important project documents.

E. Safety and Sanitation


Usually lightly taken into account but in reality will cause big impact on project morals
are safety and sanitation aspects of the site. For this particular project, the safety needs as
well as the sanitation requirement levels are very high. These scopes of responsibility cover not
only the contractor but also the owner’s side as well and could even extend to third parties.
Particular attention and concern will be exercised by the contractor in order to accomplish
both missions coverage in its provisions/implementation.
Experience security personnel, safety teams, site medical attendants/aides, safety
equipment and stringent regulation such as safety work gears (helmet, shoes, buckles, nets,
platforms, fire extinguisher, etc.), sanitation facilities on the structures under construction and
within the project will be adequately provided. The contractor will leave nothing to chance
when it comes to safety/security and sanitation of site.
At the first time, the project management will provide a guidebook of Health and
Safety Works in the project, which contains at least the information as below:

Safety Plan Program


Safety Plan is guidance in executing of K3 management system at the project. The
safety plan is made with considerations that all of possibility can occur during the
project execution and how to anticipate and to handle them. This is including the
condition around the project location, method of works, even the technical
specification of each work.

The safety plan consists of:


1. Project Description Head Line
a. General Lay Out :
Describe the condition of the project such as the contract value, time of
execution, sequence of works, etc.

b. List of the major works which describe the type and volume of each works
c. Project Location

11
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Describe the condition around the project location such as the culture and
social condition of the people and others, which related with the safety of the
project execution, the personnel, and the manpower.
2. K3 Project Organization which consists of :
a. Main PT. Waskita Karya Organization Structure
The organization will be made in a complete arrangement and the
responsibility of each section.

b. K3 Organization Structure
The organization will be made in a complete arrangement and the
responsibility of each section.

c. Subcontractor Organization Structure


The organization will be made in a complete arrangement and the
responsibility of each section.

F. Quality Assurance
To ensure work-result as required could be achived it is necessary to control the quality
in every stage of work process and production line.
The classification of verivication will consist of :
- All of materials are used in the project.
- Selection of manpower to be used.
- Equipment maintenance.
- Control of material in the laboratory, and material on site.
- The quality controller who is responsible to the technical and equipment division
manager.
The best product is result from the good material (good quality and good delivery),
good proccess (right methode, right equipment, right person inchase), good control (material,
proccess, and product). Waskita already applying the Quality Control Standard in a Quality
Control Flowchart. The flowchart is based on ISO 9002, its shown as follows :

Quality Assurance Flowchart

12
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

PROJECT COMPANY EKSTERNAL


Quality Plan consist of : Manual Standard, Rules, Keppres,
Construction Method Administration Kepmen, Perda, etc
Work Instruction Procedure
Schedule of Time Work Organization
Work Procedure, etc Personnel
Financing

MATERIAL SUPERVISION
Raw material
Equipment
Labor
OUTPUT
CONSTRUCTION PROCESS Final Product (Cost,
Quality, Time)

INSPECTION & TEST Yes

No No

QUALITY REPAIR EVALUATION

Yes

ACCEPTANCE CRITERIA
Shop Drawing REPORT &
Spesification MONITORING

Consider to the ISO certificate, we have 13 Procedures of the project as below :

NO Document Code Name of Document


1 PM-WK-PROD-01 Procedure of Quality Plan
2 PM-WK-PROD-02 Procedure of Design and Development
3 PM-WK-PROD-03 Procedure of Purchasing
4 PM-WK-PROD-04 Procedure of Identification, Handling and storing
5 PM-WK-PROD-05 Procedure of Product Supplied by Employer
6 PM-WK-PROD-06 Procedure of Production Process Control
7 PM-WK-PROD-07 Procedure of Infrastructure and Environment
8 PM-WK-PROD-08 Procedure of Inspection and Test
9 PM-WK-PROD-09 Procedure of Validation
10 PM-WK-PROD-10 Procedure of Control for Monitoring and
Measurement Facility
11 PM-WK-PROD-11 Procedure of Unsuitable Product Control
12 PM-WK-PROD-12 Procedure of Identification Being Able to Trace

13
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Product
13 PM-WK-PROD-13 Procedure of Product Protection

Procedure is one of tools to control of product quality corform to the requirement.


Procedure Project above can be shown completely when the owner or tender comitee ordered.

G. Target Obtaining Method


The management system is supported by the other element, namely software as a means of
controlling and hardware as a mean of supporting work performance.

G.1. Project Control System

A means of controlling is a very important thing to ensure the successful of an


execution of work. Prior to the commencement of the works anything related to the controlling
activities is prepared and will be poured into a list/form (control-form), which refer to Time
Schedule, equipment, material, and manpower schedule.
The main program that has been put into network planning and bar chart will be
detailed on the site. Daily program will be used. The realization will be controlled by the
report of work activity form. As to guide the performance on the site, the detail of
construction method must be furnished with shop drawing to be read and understood by each
worker involved on the execution. With the above mentioned, it is hoped that the target will
be obtained as required.

G.2. Quality plan

A. Material

No Material Test Test Period


1 Sand Gradation, Mud Content Sample, and Random
2 Aggregate Abrasion, Gradation Sample and Random
3 Cement Factory Certificate Copy Ordered
4 Asphalt Viscosity, Fire point Sample
temperature
5 Stone Abrasion Sample
6 Rebar Steel Size, yield strength Sample and Random

B. Process

No Process Test Test Period


1 Asphalt Job mix, Temperature Trial mix, Routine

14
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

2 Embankment Compaction Test Routine

C. Product

No Work Scope Test Test


1 AC WC/ AC WC MOD Core drill Routine

2 AC BC / AC BC MOD Core drill Routine

D. Equipment

No Description Test/Control Test Period Location


1 All Legal certificate, Calibration, Routine Work shop,
equipment Operation procedure, site
maintenance and services

G.3. Equipment

Based on our experiences, the plant and major equipments are as follows:

No Equipment
1 Stone Crusher, 80 ton/jam
2 Asphalt Mixing Plant, 70 ton/jam
3 Dump Truck, 10 - 20 Ton
4 Flat Bed Truck, 4 ton
5 asphalt/concrete paver, ton/jam
6 tired roller, 8-10 ton
7 Tandem roller, 8 ton
8 Steel Wheel roller, 10 ton
9 Vibrator Roller, 8 ton
10 Wheel Loader, 1.2 m3
11 Track Loader, 100 HP
12 Bulldozer, 100 HP
13 Excavator 100 HP
14 Motor Grader, 120 HP
15 Asphalt Sprayer, 1000 Ltr
16 Water Tanker, 5000 lt
17 Concrete Mixer, 0.3 m3
18 Generator Set, 200 KW

15
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

19 Crane, 10 Ton
20 Air Compressor, 6000 litre/minute
21 Scale Bridge, 35 Ton
22 Survey Equipment
23 Concrete Vibrator, 3 HP
24 Vibrator Compactor, 3 HP
25 Water Pump, 100 mm
26 Pick Up Truck, 1 Ton
Concrete Batching Plant,
27 m3/hr
29 Concrete Mixing Truck, 6 m3
30 Concrete Pump, 40-60 m3/h
31 Crane, 30 ton

Number of each kind equipments and calculation will be shown in detailed analysis
calculation. Equipment will mobilized from nearest owned equipment sources if not possible
will mobilize from Jakarta.

G.4. Material

Material used in this package are Structure Concrete Class K350, Structure Conctrete
Class K250, Sturcture Concrete Class K175, reinforcing steel plain bars U-24, stone masonry,
asphalts, aggregate base and soil embankment with material from borrow excavation. Some
material should be processed in factory and delivery to the site in large size and heavy weight,
some time needed special transportation.

G.5. Supplier (Vendor)

Supplier with enough experiences should be selected. PT. Waskita Karya have of
supplier list (Daftar Rekanan Waskita/DRW). If the supplier registered on DRW, he is one of the
selected and confident suppliers. He has success to show the requirement in Quality, Quantity
and Delivery time.

G.6. Manpower

To handle the project, the site management team will consist of;
- Manager and staffs;
- Supervisors, operators, mechanics;
- Labors.

16
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

The selected personnel who are experienced in the execution of major project or the
kind will be used as key-personnel. The workers, who will handle the work directly, will be
mobilized from outer region. The workers should be skilled, experienced and well developed
while helpers will be employed from the surrounding of the project. The total amount of
manpower will be employed and adjusted as necessary.

G.7. Interface Coordination

There will be many various kinds of activities, which are related one to another called
interfaces during the implementation of the works. Therefore, a good and integrated
coordination the works shall be very important factor to avoid any friction and uncontrollable
performance of works, which can cause unexpected obstruction in according to specified
phases. So the completion of the whole project will be done in accordance with the approved
master schedule.

G.8. Security

For securing of the project, PT. Waskita Karya provides a number of people who have
the main tasks are especially as follows:
- Watching the activity of labor.
- To control material and equipment owned by contractor to prevent from thief.
- To prevent and avoid fire in project, and maintain the fire extinguisher.
- To control of safety equipment for labor as helmet, safety belt, shoes, etc.
- To control and prepare the security fences at danger areas.
- To control of the equipments security.
- To control of the security against the disturbance and threat from outside and also
prevent from the possibility of fight within the project.

H. Detour
Due to prevent and minimized the existing traffic from being interrupted / disturbed,
the following detour will be proposed:
a. In the edge (start and end) of project
The edges of the project are starting point where the activity of project will interrupt the
existing traffic road.
Traffic signage, movable fence, rubber cones and warning plank will also be provided in
certain location to manage the traffic.
b. Crossing between existing roads with new elevated roads.

17
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Parts of existing roads on crossing position will reroute with temporary road construction to
other location, during constructing the elevated road on crossing position. After elevated
road on crossing position finished, temporary road will reroute to crossing the elevated
road with the temporary abutment.
c. Some place, where the activities of project disturb the existing traffic road.

I. Overall Strategy to Manage the Project


- Key Personnel of projects will be selected from the company personnel who have similar
experiences and fulfill the requirement.
- Works will be carried out in all area at the same time, since the works in each region has
its own resources and will be act as an independents subsystem.
- The priority execution of structure is on crossing between existing roads and new elevated
roads.
- Minimize disturbance of the public traffic by arranging such traffic management and
traffic detour.
- All kind of the construction in lower elevation position will be executed first.
- All kind of the independent construction in each region will be started as soon as possible.
- Use the available space area in nearest location for the workshop and base camp.
- Time implementation of project is 540 calendar days. One day is 8 hours. Overtime
working will also be done where required.
- Push the progress in dry seasons.
- Use night time to delivery and install the large dimension material or heavy material,
where the process can disturb the traffic.

J. Traffic Management

Generally traffic condition at location of project is not busy. The act of maintaining
traffic conditions in the roadway to assure safe and pleasant driving conditions for public.
Traffic management consists of furnishing traffic control devices and services for the control
and protection of traffic through areas of construction, for roadway will be in conformity with
the “Pedoman Rambu-Rambu Sementara (PRRS)”.
Contractor will be at all times keep roads, affected by the operations, in good
condition, free from soil and material spillage, and will carry out repair and reinstatement
work, including asphalt pavement repair. We will co-operate with the pertinent agencies
regarding traffic control and all details will be subject to maintaining traffic safety and the
avoidance of traffic delay.

18
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

In order to facilitate traffic through the work area, it will be installed and maintained at
prescribed points on the work area and at the approaches to the work: traffic signs, lights,
flares, barricades, rubber cone with traffic lamps, warning and guide signs, temporary barriers
and fences, flagmen, and other facilities as required.
During construction period, the traffic management will be implemented according to the
stages of work progress following construction stages.
Target of this work is:
- To ensure Safety & Security of Traffic operations, workers and equipments also maintain
pleasant for the road user during construction period.
Efforts to achieve the target: -
- Arrange special meeting to coordinate all safety and security aspect required with the
Institution involved such as the Police Department, DLLAJR office etc.
- Install the Traffic Sign at the certain location.
- Secure the construction activities boundaries:
 Concrete barrier
 Temporary fences
 Plastic barrier
- Provide the required signage
 Lining (as police line tape)
 Lamp line
 Marking
- Install alarm at the strategic location
 Flash lamp
 Rotary lamp
 Announcing
- Provide person in charge as safety and security officer, flagman etc.
- Install the safety net where required.

19
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

A SET TRAFFIC SIGN FOR PAVEMENT WORKING

CURRENT TRAFFIC
RUBBER CONE

50 m' 50 m' 75 m' 75 m' 75 m' 75 m' 75 m'

PEMBANGUNAN JALAN
KM

350 M'

KECEPATAN
SEKARANG
40

KURANGI

ADA PEKERJAAN
HATI - HATI
KM

800 M'
60
ON ROAD IMPROVEMENT OR WIDENING

20
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

ON ROAD OVERLAY

21
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

22
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

23
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

3. Preparation of the sign board


4. Preparation of the site office, store, stockyard, warehouse, etc in which location have
been agreed by The Engineer.
5. Mobilization of equipment, manpower, and material.
Mobilization of equipment will be consisted of delivering and locating all equipment
required to site in the timely manner.
6. Temporary water and electrical service for construction purpose. For temporary water
service ground water will be prepared. For temporary electrical service such generator
sets will be provided.
7. Shop drawing preparation will be proposed to and agreed by engineer.
8. The preparation works will be started soon after the possession of work.

In addition to these works included in site preparation are as follows: -


a. Provision of photographs and reports
b. K3 scheduling
c. Inspection of work, etc.

24
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

B. Drainage Work

The drainage works at Ngawi Ring Road will consist of the construction of excavation
for drainage ditches and waterways, mortar stonework, Reinforcement Concrete Pipe Culvert
and Unreinforcement Concrete pipe. Volume of this work is 23,266.43 m3 (Item 2.1 only). The
Work of Drainage is Excavation for Drainage Ditches & Waterways, Mortared Stone Works and
Installing concrete pipe culvert both of diameter 75 to 150 cm and un reinforced concrete pipe
culvert diameter 20 cm. Ditches will be excavated and installed with stone masonry parallel
with roads. Culverts will be installed across with roads following desgn that’s required. All
Implementation process of Division 2 shall be done as a required in Tender Document under
caption specification.
No specific work item to explain statement because all work is common work. All
Implementation process of Drainage works shall be done as required in Tender Document under
caption specification. Excavation will be done by excavator if space available and dump truck
hauling the material excavated to disposal, finishing surface by man power.

Excavator
Dump Truck

EXCAVATION FOR DRAINAGE

B.1 General

Drainage works at Ngawi Ring Road project consist of:

Box Culvert

U-Ditch

Reinforced Conctere Pipe Inside Ø 75-120 cm

Unriforced Concrete Pipe Inside Ø 20 cm

Since box culvert more specific then the others drainage works, we prepare separate
proposal for this works.

25
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

B.2 Drainage Pipes

Excavations

Prior to starting excavation for drainage pipe works, all necessary measures to keep the
excavation free from free-surface water of surface water run-off will be taken.
Temporary drainage will be made if its needed.

In areas of fill, filling will be compacted to a depth of one pipe diameter above the top
of the pipe before excavations begins. All excavation will be carried out so as to
minimize damage to existing surfaces.

Area of excavation will be protected from collapse by adequately support.

Bedding, Laying and Surrounding Pipes.

All pipe will be laid, using cradles if necessary, to true line and level as shown on
Approved Shop Drawings. After the Engineer has checked and approved the pipes and
joints, the concrete bedding and haunching or surrounding will be completed. Concrete
will be compacted below and around the pipe to the dimensions shown on Drawings.

Backfilling and Reinstatement

Backfilling will not be commenced until the concrete has achieved sufficient strength.
Backfilling will be done in accordance with the requirements of specifications.

B.3 U-Ditch

Excavations

Prior to starting excavation of foundations we will be:

- take steps to regulate the natural drainage of the water flowing on the surface of
the ground, to prevent flooding of excavations.

- ensure that all necessary site clearance and demolition in that area has been
performed base on equipment specification and safety regulations.

- Determine the location of existing utilities by dig the trial pits.

The excavation will be done at sufficient size to permit placing of structure foundation
of the full width and length. The side of excavation will be supported adequately.

Lay out

All work on U-Ditches, inlets, pipe headwalls and joint boxes will be set out carefully and
constructed with due recognition being taken of the fact that the upper surfaces must be

26
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

incorporated exactly curbs, footpaths, etc. Bottom surface of ditches will be smoothly
and neatly finished.

Cast in place concrete for waterways, drainage ditches, joint boxes, manholes, pipe
headwalls, inlet and outlet of waterways will be constructed according to the related
specifications.

Backfill and reinstatement

Backfill will be carefully made so as to obtain a bearing capacity equal to the adjacent
subgrade. In compacting subbase or base course in contact with drainage structure,
rammers or small compactor will be used and care taken to prevent damage to the
adjacent structures. Backfill will be constructed carefully so as to prevent erosion by
overflow of drain water or rain.

B.4 Box Culvert

Since the box culvert at STA 9+199 is the biggest one, we use this box culvert as typical
method. Plan lay out of box culvert STA 9+199 as shown on drawing below.

General Lay out Box Culvert STA. 9+182

27
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

General Box Culvert STA. 9+182

Construction Stages
Construction stages of box culvert STA. 9+182 as shown on drawing below.

Methods of concreting for box culvert and other structure

The drainage excavation will be done parallel with pavement for ditches and
across the pavement for culvert.
Sequences to installing box culvert :
 Demolish for existing pavement if its needed
 Excavate material to achieve required depth and width by excavator at the
point that already marked
 If we meet ground water level, we will dewatering, that so it can’t watering
the hole
 At the bottom of box culvert, we will compact soil material to achieve density
that required
 Install material above the bottom soil, such as soil replacement or compacted
material to foundation of culvert
 Installing Level concrete at the bottom of box culvert
 Preparation form work for bottom slab box culvert
 Assembling reinforcement bar inside the formworks
 Pouring concrete into formworks appropriate with specification

28
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

 Remove the existing formwork


 Preparation form work for wall and Top Slab box culvert
 Assembling reinforcement bar inside the formworks
 Pouring concrete into formworks appropriate with specification
 If concrete has strong enough, we will put material above
 Compacting material above box culvert until achieve elevation level that
allowed design.
 Installing gabion mattres at the bottom in front of side box culvert

29
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

30
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Estimated quantity of this work is about 41,911.03 m 3. The equipment used is


Excavator in the excavation area, Dump trucks for hauling to site and compacting set
Motor Grader, Vibrator Roller, and water tanker in site area. One fleet of equipment
will execute this work.
Method to execution this work is
- Material embankments mobilized by dump truck and dump at location.
- Bulldozer spread out material in 20 – 30 cm thickness
- Vibratory roller will compacted and water tanker maintain the Water content

PENDATANGAN MATERIAL TIMBUNAN

1
DUMP TRUCK

LAYER TIAP 20 CM

2 PENGHAMPARAN MATERIAL TIMBUNAN

MOTOR GRADER
BULLDOZER

3 PEMADATAN TANAH TIMBUNAN

VIBRO ROLLER
WATER TANK

Dilakukan Trial Pemadatan

A.6 Grade Preparation (total item 111,904.22 M2)

Scope of this work are:


 Preparation work, it consist measuring and installing temporary bench mark
 If necessary to make access road, we will make it
 This work will be done to achieve elevation that required
 This work is done by combination between excavator and dozer to take material from
dump truck to area surface, push material to achieve grade level that required, motor
grader to spreading material

31
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

PENDATANGAN MATERIAL TIMBUNAN

1
DUMP TRUCK

LAYER TIAP 20 CM

2 PENGHAMPARAN MATERIAL TIMBUNAN

MOTOR GRADER
BULLDOZER

3 PEMADATAN TANAH TIMBUNAN

VIBRO ROLLER
WATER TANK

Dilakukan Trial Pemadatan

B. Pavement Widening and Shoulder & Granular Pavement

Work item in this division is Aggregate Base class A and class B. Material aggregate will
be produced on mixing plant if raw material is not attended. Loader will mix to increase the
quality of composition material. Material aggregate mobilized by dump truck and dump at
location site. Motor grader will spread material in specification thickness. Vibratory roller will
compacted the spread layer until fulfill as the compacted design. Water tanker will supply the
water to maintain the water content of aggregate.

Motor grader
Dump truck Vibro roller

SPREADING AND COMPACTING AGGREGATE BASE CLASS A & B

32
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

C. Asphalt Pavement
Asphalt pavement has two various mix for two kind usage pavement i.e. Asphalt
Concrete - Wearing Course (AC-WC) and Asphalt Concrete – Binder Course (AC-BC). Sampling
test of Asphalt pavement will be provided to check and assure the specified quality.
Initial Job Mix Formula will be prepared to fine out the mixing formula. Periodical
sampling will be carried out during mixing process. Compaction test, checking temperature and
random core drill to check the quality will also be conducted during construction. Kind and
agreed number of test, and all process required for quality checking of pavement should be
fulfilled as required in the tender document or other related document. Government
accredited institution or competent university laboratory will be involved to carry out
independent quality tests of asphalt pavement.
The flowchart of general asphalt pavement works are shown as the next figure :

General Flow Chart of Asphalt Pavement

33
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

34
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Ngawi Ring Roadproject is a road rehabilitation work. Next are kind of pavement works
that will be executed for the project.

C.1 Construction of sub grade layers

a. On the embankment

Below flowchart shows the sequence:

Flowchart of sub grade layer on the embankment

Quarry/material sources

Aggregate sub grade material was selected from approved sources in accordance with
specification.

35
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Quarry material for sub grade

Transportation

Sub grade material was transported to site by using dump truck.

Spreading

The sub grade material was placed in uniform layers so that the compacted depth did
not exceed 15cm. Spreading work had been done by excavator and motor grader for
perfection.

Excavator spread granular fill for sub grade

36
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Compaction

Immediately followed final spreading and smoothing, each layer was compacted to full
width by compacter. Rolling was gradually progress from the low to the high point of
the cross section, parallel to the center line of the road, and shall continue until the
entire surface has been rolled.

Any irregularities or depressions that was developed, was corrected by loosening the
material until the surface was smooth and uniform. For the places that had no
accessible for the roller, the material was compacted by using hand stamper. The
material was both bladed and rolled until a smooth, even surface had been obtained.

Sub grade compaction

Test

The sub grade layers were test by density and CBR to met required specification.

37
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Sub grade compaction test

Degree of compaction

The layers of sub grade, to 20cm depth, below the sub grade layer were compacted to
at least 100% of the maximum dry density as determined according to AASHTO T99. The
minimum CBR that require for sub grade in pavement works was 6%.

b. In earth cut
Below flowchart shows the sequence:

Flowchart of sub grade on earth cut

38
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Earth cut

The level of sub grade was formed to the correct transverse and longitudinal profiles
but at grade level higher than the final grade in order to allow for the effect of
compaction.

Compaction

The soil surface/level was compacted with roller. Prior to compaction, the moisture
content was adjusted by watering with sprinkler trucks or by drying out, as required, in
order that the degree of compaction specified may be attained.

Sprinkler truck

Degree of compaction

The layers of sub grade, to 20cm depth, below the sub grade layer were compacted to
at least 100% of the maximum dry density as determined according to AASHTO T99. The
minimum CBR that require for sub grade in pavement works was 6%.

39
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

C.2. Construction of base course class A and B layers

Flowchart of base course class A and B

a. Quarry/material source

Aggregate sub grade material was selected from approved sources in accordance with
specification.

b. Crushing at stone crusher

Material that has been approved transported to stone crusher for crushed purpose.
Excavator and dump truck was used for excavation and transportation works.

40
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

c. Mixing

Mixing had been done by using excavator at location of stone crusher. All aggregate
was free from organic matter and lumps of clay or other deleterious matters and the
grading was conformed to the grading requirement as shown on specification.

d. Transportation

Crushed stone that have been mixed was transported to site by using dump truck.

e. Spreading

The granular base material A and B was placed in uniform layers so that the
compacted depth was not exceeding 15 cm. Spreading by using motor grader.

Motor Grader

f. Compaction

Immediately followed final spreading and smoothing, each layer was compacted to
full width by compacter. Rolling was gradually progress from the low to the high point of
the cross section, parallel to the center line of the road, and shall continue until the
entire surface has been rolled.

Any irregularities or depressions that was developed, was corrected by loosening the
material until the surface was smooth and uniform. For the places that had no accessible
for the roller, the material was compacted by using hand stamper. The material was both
bladed and rolled until a smooth, even surface had been obtained.

41
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Compaction

g. Degree of compaction

The density of compaction surface/layers were compacted to at least 100% of the


maximum dry density as determined according to AASHTO T180. The finished surface had
been uniform, dense and even.

Compaction Test

42
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

SPREADING AND COMPACTING AGGREGATE CLASS B LAYER

SPREADING AND COMPACTING AGGREGATE CLASS A LAYER

C.3. Construction of Asphalt Pavement


Asphalt pavement works will executed after construction of base course is finished.
Work flow of asphalt pavement works in Muara Enim – SP. Sugihwaras Project describes as
the next flowchart :
START

Composition of
Mixture Test
Preparation of Surface

Spraying ofAPrime Coat Mixing of Material at AMP

Composition of
Spreading of AC - Base Mixture Test
Transporting to Site
Spraying of Tack Coat
Compaction
No
Mixing of Material at AMP
Yes
Spreading of AC – BC Leveling Temperature
No
Degree of
Compaction Transporting to Site

Compaction
Yes No

A Yes
Temperature
No
Degree of
Compaction

Yes
43
B
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Composition of
Mixture Test
Spraying of Tack Coat

Mixing of Material at AMP

Spreading of AC – BC

Transporting to Site

Compaction
No

C Yes
Temperature
No
Degree of Composition of
Compaction Mixture Test
Spraying of Tack Coat
Yes
Mixing of Material at AMP
C
Spreading of AC – WC

Transporting to Site

Compaction
No

Yes
Temperature
No
Degree of
Compaction

Yes
44
Finish
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

a. Preparation of surface

If there was an existing pavement, the first step is cleaning of existing pavement. The
surface of existing pavement was cleaned by manually of workers or by brushing machine
or equipment.

- Scarifying the existing pavement


The existing pavement was sacrificed by scarifier in a depth of minimum 5 cm, to
make good connection with the base A layer.

- Spreading base A layer


The granular base material A was placed in uniform layer so that the compacted
depth was not exceeding 15cm. Motor grader was used for spreading.

- Compaction
Immediately followed final spreading and smoothing, each layer was compacted to
full width by compacter. Rolling was gradually progress from the low to the high point
of the cross section, parallel to the center line of the road, and shall continue until
the entire surface has been rolled.

Any irregularities or depressions that was developed, was corrected by loosening the
material until the surface was smooth and uniform. For the places that had no
accessible for the roller, the material was compacted by using hand stamper. The
material was both bladed and rolled until a smooth, even surface had been obtained.

45
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

- Degree of compaction
The density of compaction surface/layers were compacted to at least 100% of the
maximum modified dry density as determined according to AASHTO T180. The
finished surface had been uniform, dense and even.

Demolish of existing pavement

Immediately before applying the bituminous material, all loose dirt another
objectionable material was removed from surface with air compressor.

Preparation land with air compressor

46
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

b. Mixing at asphalt mixing plant

The dried aggregate was combined in the mixer in the amount of each fraction of
aggregates required to meet the job mix formula. The bituminous material was measured
or gauged and introduced into the mixer in the amount specified by the job-mix formula.
After the required amounts of aggregate and bituminous material have been introduced
into the mixer, the material was mixed until a complete and uniform coating of the
particles and a thorough distribution of the bituminous material throughout the aggregate
was secured.

Asphalt mixing plant

c. Transportation

The mixture was transported from the mixing plant to the point of use by dump truck.
No loads were sent out so late in the day as to prevent completion of the spreading and
compaction of the mixture during daylight hours. At the night works, satisfactory
illumination was provided.

47
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Dump truck unloaded asphalt to spreader

d. Spraying of prime coat or tack coat

Prime coat was applied to the width of the section to be primed by means of a
bitumen distributor in a uniform, continuous spread. The rate of application of prime coat
was usually being in the range of 1.0 to 2.5 kg/sqm. The rate of application of tack coat
was usually being in range of 0.4 to 0.8 kg/sqm.

Prime Coat

Prime Coat layer contain asphalt with kerosin that used as prime coating and absorption
for locking aggregate base A material. Prime coat is spread above aggregate base A
material that already through density test and its level following required design.

Prime coating Procces


Aggregat or surface layer must be clean before prime coating began.

Tack Coat

Tack Coat contain asphalt with kerosin that used as coat. It’s spread above asphaltic
surface. Aggregat or surface layer must be clean before it’s sprayed by asphalt sprayer
and compressor.

48
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Spraying prime or tack coat

e. Spreading Asphalt
The mixture was laid upon an approved surface, spread and struck off to the grade
and elevation established. Asphalt paver was used to distribute the mixture either width
or over such partial width as it practical. On areas where irregularities or unavoidable
obstacles made the use of mechanical spread and finishing equipment impracticable. The
mixture was spread, raked, and lute by hand tools. For such area the mixture was
dumped, spread and screed to give required compaction thickness.

49
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Spreading asphalt

SPREADING AND COMPACTING LASTON LAYERS (AC-WC)

f. Compacting
After the mixture had been spread, struck off and surface irregularities adjustment. It
was throughout and uniform compacted by using rolling. The surface was rolled when the
mixture is in the proper condition and when the rolling did not cause undue displacement,
cracking and shoving.

Roller was moved at slow but uniform speed with the drive roll or wheels nearest the
paver. Rolling began at the sides and proceeds longitudinally parallel to the road center
line. Each trip was overlapping one-half the roller width, and then gradually progressing to
the crown at the road.

The surface level of pavement had been test. The specific gravity of the consolidated
mixture, as determined by AASHTO T230, was not less than 95 percent of the specific
gravity of laboratory compacted specimens that was composed of the same material in like
proportion. Laboratory specimen was consist of the mixture compacted by the procedure
of AASHTO T167.

50
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Compaction of asphalt

C.4 Construction of overlay layers

Flowchart of overlay

51
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

a. Cleaning of existing pavement


The surface of existing pavement was cleaned by manually of workers or by brushing
machine or equipment.

Demolish of existing pavement

Form overlay with thickness >15cm

- Scarifying the existing pavement


The existing pavement was sacrificed by scarifier in a depth of minimum 5cm, to
make good connection with the base A layer.

- Spreading base A layer


The granular base material A was placed in uniform layer so that the compacted
depth was not exceeding 15cm. Motor grader was used for spreading.

52
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Spreading base A

b. Compaction
Immediately followed final spreading and smoothing, each layer was compacted to full
width by compacter. Rolling was gradually progress from the low to the high point of
the cross section, parallel to the center line of the road, and shall continue until the
entire surface has been rolled.

Any irregularities or depressions that was developed, was corrected by loosening the
material until the surface was smooth and uniform. For the places that had no
accessible for the roller, the material was compacted by using hand stamper. The
material was both bladed and rolled until a smooth, even surface had been obtained.

c. Degree of compaction

The density of compaction surface/layers were compacted to at least 100% of the


maximum modified dry density as determined according to AASHTO T180. The finished
surface had been uniform, dense and even.

d. Spraying of tack coat/prime coat

Tack coat/prime coat was applied to the width of the section to be primed by means of
a bitumen distributor in a uniform, continuous spread. The rate of application of prime
coat will usually be in range of 1.0 to 2.5 kg/sqm. The rate of application of tack coat
will usually be in range of 0.4 to 0.8 kg/sqm.

53
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Spraying tack coat or prime coat for overlay

e Spreading of ATB/ATBL layer

The mixture of ATB/ATBL was laid upon an approved surface, spread and struck off to
the grade and elevation established. Asphalt paver was used to distribute the mixture
either over the entire width or over such partial width as may be practical. On areas
where irregularities or unavoidable made the use of mechanical spread and finishing
equipment impracticable, the mixture was spread, raked and lute by hand tools. For
such area, the mixture shall dumped, spread and screed to give required compacted
thickness.

Spreading asphalt for ATB/ATBL layer

54
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Compacting of the ATB/ATBL layer


After the mixture had been spread, struck off and surface irregularities adjustment. It
was throughout and uniform compacted by using rolling. The surface was rolled when
the mixture is in the proper condition and when the rolling did not cause undue
displacement, cracking and shoving.

Roller was moved at slow but uniform speed with the drive roll or wheels nearest the
paver. Rolling began at the sides and proceeds longitudinally parallel to the road
center line. Each trip was overlapping one-half the roller width, and then gradually
progressing to the crown at the road.

The surface level of pavement had been test. The specific gravity of the consolidated
mixture, as determined by AASHTO T230, was not less than 95 percent of the specific
gravity of laboratory compacted specimens that was composed of the same material in
like proportion. Laboratory specimen was consist of the mixture compacted by the
procedure of AASHTO T167.

Compaction for ATB/ATBL

f. Spreading of asphalt concrete (AC)

The mixture of asphalt concrete was laid upon an approved surface, spread and struck
off to the grade and elevation established. Asphalt paver was used to distribute the
mixture either width or over such partial width as it practical. On areas where
irregularities or unavoidable obstacles made the use of mechanical spread and finishing
equipment impracticable. The mixture was spread, raked, and lute by hand tools. For

55
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

such area the mixture was dumped, spread and screed to give required compaction
thickness.

g. Compacting of the asphalt concrete (AC) layer

After the mixture had been spread, struck off and surface irregularities adjustment. It
was throughout and uniform compacted by using rolling. The surface was rolled when
the mixture is in the proper condition and when the rolling did not cause undue
displacement, cracking and shoving.

Roller was moved at slow but uniform speed with the drive roll or wheels nearest the
paver. Rolling began at the sides and proceeds longitudinally parallel to the road
center line. Each trip was overlapping one-half the roller width, and then gradually
progressing to the crown at the road.

The surface level of pavement had been test. The specific gravity of the consolidated
mixture, as determined by AASHTO T230, was not less than 95 percent of the specific
gravity of laboratory compacted specimens that was composed of the same material in
like proportion. Laboratory specimen was consist of the mixture compacted by the
procedure of AASHTO T167.

56
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

57
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

B.2. Moulding
Moulding can be conducted by per span of bridge. Because the distance of enough far big
volume, moulding better be conducted to use pump concrete. Stop of mould can be done
on course joint expantion. Broadcasts dilatation require special attention in order not to
complicate at the time of installation of joint expantion.
Skematis work of moulding of Deck Slab :

B.3. Work Of Others

Which is scope in work of others here is work of :


- approach Slab
- Work of Side Walk
- Works of railing.

Work of Approach Slab


Work of Approach Slab using materials of multipleks 15 mm as becisting. For reinforcement
and concreting do the ways with Concrete Slab Deck
Work of Side Walk
Works of Side Walk executed after works of slab. preceded by survey team to make
marking at work of Side Walk. Bekisting weared is from given by plywood strength and
nubed with cream by using oil mold can wear to repeatedly. Before executed by moulding,
is beforehand attached by bolt of angkur for railing.
Work of Railing
If the him of using railing, hence can be executed [by] after work of Side Walk. Materials
weared in general is GIP ø 2,5 ". Before installation of pipe of railing is beforehand
attached by post rail every distance 2 m ( ace to ace ). For that before moulding of side
walk, anchor for the tyings of plate anchor with concrete as post guide dudukan have to
have been attached.

B.4. Work Surface Layers of Work


- Tack Coat
- Laston AC-WC
- Concreting Oprit Area

58
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Tack Coat
Tack Coat carpeted above surface which paving or above surface of cement concrete.
Materials endue fastener consist of settled Asphalt Emulsion type quickly which pursuant to
SNI 03-4798-1998.
In B.O.Q. mentioned tack Coat 0,4 liter/m2.

Tack Coat isn't it above asphalt covering and concrete which have been cleared of by dirt,
free material and dirt. Sweeping of surface of concrete and asphalt use Water and Air
Compressor. Tack Coat carpeted to use Sprayer Pave Hand ( Hand Sprayer).
Mixture Pave Heat - Laston ( AC)
Laston ( AC) consist of three kinds of mixture, Laston layers Timewornly ( AC-WC), Laston
Layer separator ( AC-BC) and of Laston Layer Foundation ( AC-BASE) and maximum measure
of aggregate is each mixture is 19mm, 25,4mm, 37,5mm.

Ad for nominal of Coat minimum Pave and the tolerance of is :

Mix Type Tickness Nominal tolerance (mm)


Minimum (cm)
AC - WC 4,0 ± 3,0
AC – BC 5,0 ± 4,0
AC - BASE 6,0 ± 5,0

Bridge project of Ngawi work of Laston AC-WC. Laston AC-WC is enduing surface at
Reinforced Earth and bridge floor, so that work of Laston AC-WC can be done by after
entire good Deck Slab Earth Reinforced and bridge floor have been done.
Mixture pave to consist of asphalt and aggregate. Filler or additive type will be added
if/when needed to to guarantee the nature of mixture fulfill clauses in technical
specification of work. Mixture composition and gradation of aggregate relate to technical
specification. To get mixture of Laston fulfilling specification made by Formula Mixture
( Job Mix Formula).
When asked by Board of directors Supervisor hence conducted by attempt of condensation
to ensure that every Tool available for work, Asphalt Finisher can carpet materials as
according to thick which required without segretion. And composition of mold proposed can
reach required density during normal productions carpet.

59
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

Ad for before carpet of Laston, surface to be carpeted to be to be cleared of by free


materials and which do not desire with and Air Compressor. coat prime or Tack Coat have
been carpeted beforehand.
Laston produced by Asphalt Mixing Plant and brought to carpet location use Dump Truck.
Temperature of Aggergat at the time of mixing may not exceed 180 oC. To take care of
temperature of Laston fulfill the specification of moment arrive field hence during journey
process, mixture of Laston in Dump Truck closed densely use ratch.
Carpet use Asphalt Finisher. To get thick which wanted by hence is beforehand made by
Reference Edge. For the appliance of penghampar owning Automatic edge reference
levelling changed with reference yarn which the was height of accomodating thick carpet
which planned.
Immediately after Laston carpeted and smoothed down the, the surface checked and
every direct unperfect that happened repaired. Temperature of Laston in a state of un
compacted condition and running over to be started in spanning temperature according to
asphalt viskosity.
Running over of Laston consist of three operation that is : condensation early, condensation
between and final condensation.
Running over early conducted by means of steel wheel ( tandem roller). Second running
over to use rubber wheel ( roller tire). Second running over executed near by possibly run
over first. Final running over use appliance condenser of wheel become militant without
vibrator.
Running over to be conducted first of all at athwart connection by tide of kasau thickly
needed to detain movement of mixture pave running over effect. Running over is later
started from long extension place and then from external edge. Hereinafter running over,
running over to be conducted parallel with successive road tinder head for road tinder.
Trajectory which is is successive to be made by the trajectories and overlap may not end at
point which less than one metre of trajectory before all.
Speed of maximum condenser appliance 4 km / hour for wheel Steel and 10 km / hour for
the wheel of rubber. All running over operations continue to obtain density which flatten.
Appliance condenser wheel wetted continually to prevent mixture juxtaposition pave at
condenser appliance wheel, but abundant water do not be allowed. Rubber wheel a little a
few to prevent stickyly of mixture him pave at wheel.
Heavy equipments or condenser appliance do not be permitted to reside in above new
surface have been done, until entire the surface chilled.
For link between carpet location with AMP used by communications radioes ( HT). Sketch
Composition appliance work of Laston like picture following :

60
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

LASTON WORK
EQUIPMENT COMBINATION
PEKERJAAN LASTON
GAMBAR KOMBINASI ALAT

DUMP TRUCK ASPHALT FINISHER TANDEM ROLLER TIRE ROLLER

WATER TANKER

PLAN LAY OUT

ARAH HAMPAR TIRE ROLLER

DUMP TRUCK ASPHALT FINISHER TANDEM ROLLER

WATER TANKER

B.5. Road Concrete 30 cm


Concrete road of K-350 thick 30 cm reside in at bridge oprit. This work will be conducted
with manual. Concrete produced in] Batching Plant, brought to work location use Concrete
Truck Mixer. Concrete decanted to hard location of rigid where have been prepared by
bekisting. Condensation of concrete use Electric Concrete Vibrator. Flattening of surface
use margin. After concrete rather setting, conducted by work of grooving follow pattern
which have been determined in drawing shop. Is hereinafter executed by curing by closing
surface of concrete with wet sack. Curing executed continuously minimize 5 day
commencing from infusion of concrete.

C. Retaining Wall At West Side


This work cover retaining wall structure of assembling ground of concrete, reinforcement and
preparation of ground foundation, location and also concrete levelling, material of back fill and
according to granulous material with specification, thick desain and dimension posed at
drawing shop.

61
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

C.1 Construction
1). Sweeping and dig
a. Cleaning entire structure of existing, material and tree of existing other at wall
location penahan of ground.
b. Dig of ground of existing until foundation level.
2). Condensation of Foundation
Foundation will be compacted to use roller vibratory
3). Pad Leveling
a. Preparing pad leveling as long as wall. We use bekisting for the bone of pad leveling
b. Survey accuracy of pad levelling pursuant to matras aktual elevasi every panel
c. Pad Leveling is concrete without bone matching with desain.
this Work can use system of bekisting by using materials of multipleks 15 mm.

C.2 Installation Of Reinforcement


Installation will be conducted in the some breath with installation bekisting of
retaining wall wall. Form and dimension follow drawing shop. Installation of must be done by
hati liver to ensure that the installation of correctness and not happened damage of
installation moment. Heavy equipment may not be operated direct above iron line.
Flattening and condensation of Material hoard hoard material will be conducted
concurrently with wall. Every iron line level, hoard will be filled in before carpet and
installations of iron Thick can be added to obtain appropriate to specific gravity.

62
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

63
PT. WASKITA KARYA (PERSERO)
Bidding for NGAWI RING ROAD Project – EAST JAVA

64