QF-DGN-01

TITLE: DOCUMENT/DRAWING APPROVAL/COMMENT TRANSMITAL

Project : Design, Supply, Installation, Testing & Commissioning of 132/33kV AIS Substation
at Barguna on Turnkey Basis.

Contract Number : PGCB/132kV/Barguna/SS, Date: 14.01.2018


Document Submittal Ref : CCC/PGCB/Barguna/SS/2018/D029; Date: 21.10.2018
CCC/PGCB/Barguna/SS/2018/D030; Date: 21.10.2018
CCC/PGCB/Barguna/SS/2018/D031; Date: 21.10.2018
CCC/PGCB/Barguna/SS/2018/ D032; Date: 21.10.2018
Subject : Comments on Design Drawing of Boundary Wall Layout, Boundary Wall Structure, Pilecap &
Pile of Boundary Wall for Barguna 132/33kV AIS Substation.

Copy to
To
Managing Director, PGCB
Project Director
Barguna Substation Project √ Executive Director (P & D), PGCB
Power Grid Company of Bangladesh Limited (PGCB)
Aftabnagar, Rampura, Dhaka-1212. √ Chief Engineer (P & D/Project), PGCB

√ China National Cable Engineering Corporation.


Kind Attn :

Dear Sir √ Executive Engr. (Civil Design), PGCB


We are pleased to enclose the following documents for the purpose
√ Master File
indicated below:

In case of any modification other than those desired are carried out, the Issued by:
same shall be highlighted clearly in the Drawing/Document with full
justification thereof and resubmitted for approval.
(Engr. Md. Delowar Hossain)
Approval/Comments/Information conveyed herein neither relieves the Superintending Engineer
contractor of his contractual obligation and his responsibilities for Civil Design, P&D.
correctness of dimensions, material of constructions, weight, quantities, Our Ref: 27.21.0000.412.49.001.18.600
design details, assemble fits, performance particulars and conformity of
the supplies with the Statutory Laws of Bangladesh as may be applicable, Date: 30/10/2018
nor does it limit the Employer’s right under the contract.

Item Description of Document Drawing Number Revision Status Enclosed


No Drawing/ Documents Number

Approved (A)
Yes
Approved with
Comment /
Please refer to Annexure -1 Correction (C)

Request for re- No


Submission (RR)

For information
(FI)

Please acknowledge receipt of documents:


Received by Date
Ref. No. 27.21.0000.412.49.001.18.600 Date: 30/10/2018

Annexure-1

SL No. Description Drawing Number Comments

01. Layout of Boundary CCC-PGCB-BARGUNA-40-002 Approved with


Wall Foundation Sheet: 1/1, Rev:00 Correction
02. Details of Boundary CCC-PGCB-BARGUNA-40-003 Approved with
Wall Sheet: 1/1, Rev:00 Correction
03. Details of Entrance CCC-PGCB-BARGUNA-40-004 Not Approved
Gate Sheet: 1/1, Rev:00 Requested to submit
as per discussion.
04. Details of Pile CCC-PGCB-BARGUNA-40-005 Approved with
Sheet: 1/1, Rev:00 Correction
05. Gabion Wall CCC-PGCB-BARGUNA-40-002 Not Approved
Sheet: 1/1, Rev:00 Requested to submit
as per discussion.