PROGRAM
PROJECT TITLE:
Prepared By:
FISSTS0207-0207-C-000453
SAFETY OFFICER:
Adopted by:
-------------------------------
PROJECT OWNER
CONTRUCTION SAFETY AND HEALTH PROGRAM FOR THE
The Project Safety and Health Policy are to protect every worker from the dangers of injury, sickness or
death through safe and healthy working condition. The purpose is to conduct every work safety and health by
continuous information dissemination.
The management commitment to the implementation of the BOSH program at the project site will be firm
and aggressive so that all work activities are performed with the utmost regard for the safety/; and health of the
workers and the other persons.
All construction workers from top to bottom will adhere to Hazard Reporting Program and must be
responsible in the promulgation of safety and health program and any violation committed will have
corresponding penalty/sanction.
The appointed member of the project Safety and Health Committee will “review, at least monthly, during
the duration of the project, this written construction safety and health policy and maintain and continuously
improve developed OSH Program to ensure that it will remain relevant and appropriate to the health and safety
needs of the construction workers.”
Also, during the implementation of the project, we shall abide and strictly enforce the rules and
regulations of Occupational Safety and Health Standards, As Amended and DOLE D.O. No. 13 Guidelines Governing
Occupational Safety and Health in the Construction Industry.
It is also policy to comply and implement with high standards the requirements of the following:
2.1 SAFETY COMMITTEE will be composed of the chairman, safety man, first aider and 3 markers. Meetings will be
conducted every 1" Tuesday of the month.
Note: Committee Members will be appointed before the start of the project.
2.2 OBJECTIVE: To ensure that Construction Safety and Health Program will be fully implemented at the project
site.
The Project Site Safety and Health Personnel will be appointed before the start of the
construction.
3.1 SAFETY OFFICER
3.1.1 Ramon Rommell Demosthenes V. Tabadero
3.1.2 BOSH Cart. No. FISST30207-0207-C-000453
4.1 ACCIDENTS AND INCIDENTS MUST BE REPORTED. AII occurrences that Is unplanned, uncontrolled and
in some way undesirable which disrupt the normal function of a person or persons that resulted to injury or
near injury will be reported.
4.2 THE FOREMAN IS THE PERSON RESPONSIBLE FOR ACCIDENT OR INCIDENT
REPORTING AND INVESTIGATION. The supervisor is the person who must
investigate and makes out report.
4.3 MINIMUM CONTENTS OF ACCIDENT OR INCIDENT REPORTS
The exact location, time, vehicles/equipment and people involve in the accident
or incident.
Take the physical picture of the accident/incident.
Look for witnesses and interview about the facts.
Get the facts and accounts from the people involve.
The Project Owner will install danger signs and safety instructions for workers and Public.
Providing also Construction Safety Signage's to warn the workers and the public regarding the existing
hazards in the workplace. Signages will be posted in prominent and strategic position in English and
Tagalog languages.
5.1 The signage’s that will be installed are but not limited to the following:
1. Mandatory requirement on the usage of personal protective equipment prior to the entry on the
project site.
2. Warning or danger signs on areas where there are potential risks of failing and falling objects.
3. Tripping or slipper areas.
4. Providing electrical danger signs on areas where there are possible contact with electrical
current.
5.2 Project Owner will ensure good housekeeping will be fully implemented in the worksite to prevent
accidents and illnesses.
Construction Site procedures for worksite good housekeeping:
1. Remove all protruding nails or bend them over.
2. Remove all slippery objects on the worksite.
3. Place all work materials in its proper places.
4. Keep loose materials on stairs, walkways, ramps and platforms.
The Project Owner will disseminate this contingency plan to all construction workers.
PREPARED by:
--------------------------------------------------
PROJECT OWNER
FIRST SAFETY SYSTEMS TRAINING SERVICES
DOLE/BWC Accreditation No: 1038-092413-6050
CERTIFICATION of COMPLETION
Is given to
Pallocan West
Batangas City