SERTIFIKAT BULANAN
MONTHLY CERTIFICATE (MC)
KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH SERTIFIKAT : 07 (TUJUH)
NAMA PAKET : PENINGKATAN JALAN SINABANG-SIBIGO BULAN : OKTOBER
NOMOR KONTRAK : 13/SPPK/PBJ/DBC/APBA/III/2012 TANGGAL : 23 OKTOBER 2012
TANGGAL KONTRAK : 21 MARET 2012 HALAMAN : 1 dari 8
NILAI KONTRAK : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD-I : 13.1/SPPK/PBJ/DBC/APBA/VII/2012
TANGGAL KONTRAK ADD-I : 03 JULI 2012
NILAI KONTRAK ADD-I : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD FINAL : 13.2/SPPK/PBJ/DBC/APBA/X/2012
TANGGAL KONTRAK ADD FINAL : 16 OKTOBER 2012
NILAI KONTRAK ADD FINAL : Rp. 8,000,000,000.00,-
SUMBER DANA : APBA TAHUN ANGGARAN 2012
PENYEDIA JASA : PT. FLAMBOYANT HUMA ARTA
A SUB TOTAL 7,272,727,282.46 7,272,727,282.46 7,272,727,282.46 6,354,705,013.66 918,022,268.80 7,272,727,282.46 S/D BULAN INI
B PPN (10%) X A 727,272,728.25 727,272,728.25 727,272,728.25 635,470,501.37 91,802,226.88 727,272,728.25 100.00% 100.00%
C JUMLAH TOTAL A + B 8,000,000,010.70 8,000,000,010.70 8,000,000,010.70 6,990,175,515.02 1,009,824,495.68 8,000,000,010.70
D DIBULATKAN C 8,000,000,000.00 8,000,000,000.00 8,000,000,000.00 6,990,175,000.00 1,009,824,000.00 8,000,000,000.00 BULAN INI
E MATERIAL ON SITE (MOS)
12.62%
F JUMLAH KOTOR SERTIFIKAT BULAN INI
G POTONGAN - POTONGAN S/D BULAN LALU
1 SERTIFIKAT S/D BULAN LALU (KOMULATIF) 5,242,631,250.00
87.38%
2 5 % JAMINAN PEMELIHARAAN ( 5% X D ) 400,000,000.00
3 20 % PENGEMBALIAN UANG MUKA 1,600,000,000.00
H JUMLAH POTONGAN ( 1 + 2 + 3 ) 7,242,631,250.00
I JUMLAH BERSIH SERTIFIKAT BULAN INI TERMASUK PPN 10% (F-H) 757,368,750.00
J DIBULATKAN 757,368,750.00
Terbilang : tujuh ratus lima puluh tujuh juta tiga ratus enam puluh delapan ribu tujuh ratus lima puluh rupiah
MENGETAHUI OLEH :
KUASA PENGGUNA ANGGARAN / KUASA PENGGUNA BARANG
KEGIATAN PEMBANGUNAN JALAN DAN JEMBATAN
DINAS BINA MARGA DAN CIPTA KARYA ACEH
Ir. FAJRI, MT
PEMBINA
NIP. 19640831 199203 1 005
PEMERINTAH ACEH
SERTIFIKAT BULANAN
KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH SERTIFIKAT : 07 (TUJUH)
NAMA PAKET : PENINGKATAN JALAN SINABANG-SIBIGO BULAN : OKTOBER
NOMOR KONTRAK : 13/SPPK/PBJ/DBC/APBA/III/2012 TANGGAL : 23 OKTOBER 2012
TANGGAL KONTRAK : 21 MARET 2012 HALAMAN : 2 dari 8
NILAI KONTRAK : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD-I : 13.1/SPPK/PBJ/DBC/APBA/VII/2012
TANGGAL KONTRAK ADD-I : 03 JULI 2012
NILAI KONTRAK ADD-I : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD FINAL : 13.2/SPPK/PBJ/DBC/APBA/X/2012
TANGGAL KONTRAK ADD FINAL : 16 OKTOBER 2012
NILAI KONTRAK ADD FINAL : Rp. 8,000,000,000.00,-
SUMBER DANA : APBA TAHUN ANGGARAN 2012
PENYEDIA JASA : PT. FLAMBOYANT HUMA ARTA
NOMOR KUANTITAS JUMLAH HARGA S/D BULAN LALU BULAN INI S/D BULAN INI
HARGA SATUAN
MATA URAIAN PEKERJAAN SAT. ADD FINAL
KONTRAK KONTRAK KONTRAK (Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
PEMB. (Rp.) KUANTITAS KUANTITAS KUANTITAS
AWAL ADD-I ADD FINAL (Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8=6x7 9 10 = 7 x 9 11 12 = 7 x 11 13 = 9 + 11 14 = 10 + 12
1.2 Mobilisasi Ls 1.00 1.00 1.00 50,100,000.00 50,100,000.00 0.70 35,070,000.00 0.30 15,030,000.00 1.00 50,100,000.00
SERTIFIKAT BULANAN
KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH SERTIFIKAT : 07 (TUJUH)
NAMA PAKET : PENINGKATAN JALAN SINABANG-SIBIGO BULAN : OKTOBER
NOMOR KONTRAK : 13/SPPK/PBJ/DBC/APBA/III/2012 TANGGAL : 23 OKTOBER 2012
TANGGAL KONTRAK : 21 MARET 2012 HALAMAN : 3 dari 8
NILAI KONTRAK : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD-I : 13.1/SPPK/PBJ/DBC/APBA/VII/2012
TANGGAL KONTRAK ADD-I : 03 JULI 2012
NILAI KONTRAK ADD-I : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD FINAL : 13.2/SPPK/PBJ/DBC/APBA/X/2012
TANG GAL KO NTRAK ADD FINAL : 16 OKTO BER 2012
NILAI KONTRAK ADD FINAL : Rp. 8,000,000,000.00,-
SUMBER DANA : APBA TAHUN ANGGARAN 2012
PENYEDIA JASA : PT. FLAMBOYANT HUMA ARTA
NOMOR KUANTITAS JUMLAH HARGA S/D BULAN LALU BULAN INI S/D BULAN INI
HARGA SATUAN
MATA URAIAN PEKERJAAN SAT. ADD FINAL
KONTRAK KONTRAK KONTRAK (Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
PEMB. (Rp.) KUANTITAS KUANTITAS KUANTITAS
AWAL ADD-I ADD FINAL (Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8=6x7 9 10 = 7 x 9 11 12 = 7 x 11 13 = 9 + 11 14 = 10 + 12
2.1 Galian Untuk Selokan Drainase dan Saluran Air M³ 2,000.00 1,849.33 1,832.02 37,888.00 69,411,504.95 1,849.33 70,067,415.04 (17.31) (655,910.09) 1,832.02 69,411,504.95
2.3.5 Gorong-Gorong Pipa Baja Bergelombang Ton 1.50 0.15 0.23 37,703,990.35 8,671,917.78 - - 0.23 8,671,917.78 0.23 8,671,917.78
SERTIFIKAT BULANAN
KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH SERTIFIKAT : 07 (TUJUH)
NAMA PAKET : PENINGKATAN JALAN SINABANG-SIBIGO BULAN : OKTOBER
NOMOR KONTRAK : 13/SPPK/PBJ/DBC/APBA/III/2012 TANGGAL : 23 OKTOBER 2012
TANGGAL KONTRAK : 21 MARET 2012 HALAMAN : 4 dari 8
NILAI KONTRAK : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD-I : 13.1/SPPK/PBJ/DBC/APBA/VII/2012
TANGGAL KONTRAK ADD-I : 03 JULI 2012
NILAI KONTRAK ADD-I : Rp. 8,000,000,000.00,-
NO MOR KONTRAK ADD FI NAL : 13. 2/ SPPK/ PBJ /DBC/ APBA/ X/ 201 2
TANG GAL KO NTRAK ADD F INAL : 1 6 O KTO BER 2 01 2
NILAI KONTRAK ADD FINAL : Rp. 8,000,000,000.00,-
SUMBER DANA : APBA TAHUN ANGGARAN 2012
PENYEDIA JASA : PT. FLAMBOYANT HUMA ARTA
NOMOR KUANTITAS JUMLAH HARGA S/D BULAN LALU BULAN INI S/D BULAN INI
HARGA SATUAN
MATA URAIAN PEKERJAAN SAT. ADD FINAL
KONTRAK KONTRAK KONTRAK (Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
PEMB. (Rp.) KUANTITAS KUANTITAS KUANTITAS
AWAL ADD-I ADD FINAL (Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8=6x7 9 10 = 7 x 9 11 12 = 7 x 11 13 = 9 + 11 14 = 10 + 12
3.2.1 Timbunan Biasa M³ 2,000.00 511.46 477.20 71,022.00 33,891,698.40 505.13 35,875,342.86 (27.93) (1,983,644.46) 477.20 33,891,698.40
3.2.2 Timbunan Pilihan M³ 1,221.83 2,900.74 2,870.08 106,227.00 304,879,988.16 2,867.57 304,613,358.39 2.51 266,629.77 2,870.08 304,879,988.16
3.3 Penyiapan Badan jalan M² 27,900.00 25,840.15 26,746.55 2,922.00 78,153,419.10 25,840.15 75,504,918.30 906.40 2,648,500.80 26,746.55 78,153,419.10
SERTIFIKAT BULANAN
KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH SERTIFIKAT : 07 (TUJUH)
NAMA PAKET : PENINGKATAN JALAN SINABANG-SIBIGO BULAN : OKTOBER
NOMOR KONTRAK : 13/SPPK/PBJ/DBC/APBA/III/2012 TANGGAL : 23 OKTOBER 2012
TANGGAL KONTRAK : 21 MARET 2012 HALAMAN : 5 dari 8
NILAI KONTRAK : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD-I : 13.1/SPPK/PBJ/DBC/APBA/VII/2012
TANGGAL KONTRAK ADD-I : 03 JULI 2012
NILAI KONTRAK ADD-I : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD FINAL : 13.2/SPPK/PBJ/DBC/APBA/X/2012
TANG GAL KO NTRAK ADD FINAL : 16 O KTO BER 2012
NILAI KONTRAK ADD FINAL : Rp. 8,000,000,000.00,-
SUMBER DANA : APBA TAHUN ANGGARAN 2012
PENYEDIA JASA : PT. FLAMBOYANT HUMA ARTA
DIVISI 4. PELEBARAN DAN PERKERASAN BAHU JALAN JUMLAH KONTRAK ADD FINAL Rp 573,747,932.55
NOMOR KUANTITAS JUMLAH HARGA S/D BULAN LALU BULAN INI S/D BULAN INI
HARGA SATUAN
MATA URAIAN PEKERJAAN SAT. ADD FINAL
KONTRAK KONTRAK KONTRAK (Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
PEMB. (Rp.) KUANTITAS KUANTITAS KUANTITAS
AWAL ADD-I ADD FINAL (Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8=6x7 9 10 = 7 x 9 11 12 = 7 x 11 13 = 9 + 11 14 = 10 + 12
4.2.2 Lapis Pondasi Aggregat Klas B M³ 1,860.00 1,289.79 1,259.31 455,605.00 573,747,932.55 - - 1,259.31 573,747,932.55 1,259.31 573,747,932.55
DIVISI 4. PELEBARAN DAN PERKERASAN BAHU JALAN TOTAL PEMBAYARAN - - 573,747,932.55 573,747,932.55
SERTIFIKAT BULANAN
KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH SERTIFIKAT : 07 (TUJUH)
NAMA PAKET : PENINGKATAN JALAN SINABANG-SIBIGO BULAN : OKTOBER
NOMOR KONTRAK : 13/SPPK/PBJ/DBC/APBA/III/2012 TANGGAL : 23 OKTOBER 2012
TANGGAL KONTRAK : 21 MARET 2012 HALAMAN : 6 dari 8
NILAI KONTRAK : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD-I : 13.1/SPPK/PBJ/DBC/APBA/VII/2012
TANGGAL KONTRAK ADD-I : 03 JULI 2012
NILAI KONTRAK ADD-I : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD FINAL : 13.2/SPPK/PBJ/DBC/APBA/X/2012
TANGG AL KO NTRAK ADD FINAL : 16 OKTO BER 2012
NILAI KONTRAK ADD FINAL : Rp. 8,000,000,000.00,-
SUMBER DANA : APBA TAHUN ANGGARAN 2012
PENYEDIA JASA : PT. FLAMBOYANT HUMA ARTA
NOMOR KUANTITAS JUMLAH HARGA S/D BULAN LALU BULAN INI S/D BULAN INI
HARGA SATUAN
MATA URAIAN PEKERJAAN SAT. ADD FINAL
KONTRAK KONTRAK KONTRAK (Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
PEMB. (Rp.) KUANTITAS KUANTITAS KUANTITAS
AWAL ADD-I ADD FINAL (Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8=6x7 9 10 = 7 x 9 11 12 = 7 x 11 13 = 9 + 11 14 = 10 + 12
5.1.1 Lapis Pondasi Agregat Klas A M³ 2,790.00 2,906.64 3,010.14 526,671.00 1,585,353,443.94 2,849.04 1,500,506,745.84 161.10 84,846,698.10 3,010.14 1,585,353,443.94
5.1.2 Lapis Pondasi Agregat Klas B M³ 3,720.00 3,875.52 3,904.56 449,249.00 1,754,119,675.44 3,798.72 1,706,571,161.28 105.84 47,548,514.16 3,904.56 1,754,119,675.44
SERTIFIKAT BULANAN
KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH SERTIFIKAT : 07 (TUJUH)
NAMA PAKET : PENINGKATAN JALAN SINABANG-SIBIGO BULAN : OKTOBER
NOMOR KONTRAK : 13/SPPK/PBJ/DBC/APBA/III/2012 TANGGAL : 23 OKTOBER 2012
TANGGAL KONTRAK : 21 MARET 2012 HALAMAN : 7 dari 8
NILAI KONTRAK : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD-I : 13.1/SPPK/PBJ/DBC/APBA/VII/2012
TANGGAL KONTRAK ADD-I : 03 JULI 2012
NILAI KONTRAK ADD-I : Rp. 8,000,000,000.00,-
NOMO R KO NTRAK ADD FI NAL : 1 3. 2/ SPPK/ PBJ /DBC/ APBA/ X/ 201 2
TANGG AL KO NT RAK ADD FI NAL : 16 OKT OBER 2 01 2
NILAI KONTRAK ADD FINAL : Rp. 8,000,000,000.00,-
SUMBER DANA : APBA TAHUN ANGGARAN 2012
PENYEDIA JASA : PT. FLAMBOYANT HUMA ARTA
NOMOR KUANTITAS JUMLAH HARGA S/D BULAN LALU BULAN INI S/D BULAN INI
HARGA SATUAN
MATA URAIAN PEKERJAAN SAT. ADD FINAL
KONTRAK KONTRAK KONTRAK (Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
PEMB. (Rp.) KUANTITAS KUANTITAS KUANTITAS
AWAL ADD-I ADD FINAL (Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8=6x7 9 10 = 7 x 9 11 12 = 7 x 11 13 = 9 + 11 14 = 10 + 12
6.1.(1)(a) Lapis Resap Pengikat - Aspal Cair Liter 13,950.00 14,691.41 15,189.31 11,249.00 170,864,548.19 14,178.41 159,492,934.09 1,010.90 11,371,614.10 15,189.31 170,864,548.19
6.3.(6a) Laston Lapis Antara (AC-BC) (gradasi halus/kasar) Ton 2,027.22 2,134.97 2,203.27 521,662.00 1,149,362,234.74 2,056.64 1,072,871,053.78 146.63 76,491,180.96 2,203.27 1,149,362,234.74
6.3.8.a Aspal Ton 126.20 132.91 123.32 10,809,425.00 1,333,018,291.00 115.12 1,244,352,036.74 8.20 88,666,254.26 123.32 1,333,018,291.00
6.3.10 Bahan Pengisi (Filler) Tambahan Kg 41,371.98 43,570.79 44,964.74 1,206.85 54,265,696.47 41,972.16 50,654,105.64 2,992.58 3,611,590.83 44,964.74 54,265,696.47
SERTIFIKAT BULANAN
KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH SERTIFIKAT : 07 (TUJUH)
NAMA PAKET : PENINGKATAN JALAN SINABANG-SIBIGO BULAN : OKTOBER
NOMOR KONTRAK : 13/SPPK/PBJ/DBC/APBA/III/2012 TANGGAL : 23 OKTOBER 2012
TANGGAL KONTRAK : 21 MARET 2012 HALAMAN : 8 dari 8
NILAI KONTRAK : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD-I : 13.1/SPPK/PBJ/DBC/APBA/VII/2012
TANGGAL KONTRAK ADD-I : 03 JULI 2012
NILAI KONTRAK ADD-I : Rp. 8,000,000,000.00,-
NOMOR KONTRAK ADD FINAL : 13.2/SPPK/PBJ/DBC/APBA/X/2012
TANGG AL KONTRAK ADD FI NAL : 16 OKTOBER 2012
NILAI KONTRAK ADD FINAL : Rp. 8,000,000,000.00,-
SUMBER DANA : APBA TAHUN ANGGARAN 2012
PENYEDIA JASA : PT. FLAMBOYANT HUMA ARTA
NOMOR KUANTITAS JUMLAH HARGA S/D BULAN LALU BULAN INI S/D BULAN INI
HARGA SATUAN
MATA URAIAN PEKERJAAN SAT. ADD FINAL
KONTRAK KONTRAK KONTRAK (Rp.) JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
PEMB. (Rp.) KUANTITAS KUANTITAS KUANTITAS
AWAL ADD-I ADD FINAL (Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8=6x7 9 10 = 7 x 9 11 12 = 7 x 11 13 = 9 + 11 14 = 10 + 12
7.9 Pasangan Batu M³ 80.00 161.57 174.22 613,517.00 106,886,931.74 161.57 99,125,941.69 12.65 7,760,990.05 174.22 106,886,931.74