Escolar Documentos
Profissional Documentos
Cultura Documentos
TECHNICAL SPECIFICATIONS
FOR BMC – ICOMC BUILDING
1 Excavation
Site Work
Subsurface Investigation
1.1 General
Contractor shall be deemed to have visited the site prior to submitting his Bid and made
all necessary inspection and investigations and to have decided for himself the means of
access and working space, the nature of the ground and subsoil, if any, level of water
table, extent of rock demolitions, alterations, support of neighboring properties, etc.
a. Related work
a) Clearing, grubbing and removing all vegetation from the site.
b) Excavation including getting out, and necessary dressing to make surface ready to
receive blinding.
c) Filling and back filling and compaction of fills
d) Removal and disposal of surplus material.
e) Stone soling to roads and paving.
The Contractor shall provide all labour, equipment, materials and any incidentals
necessary to complete all aspects of work included in the drawings and specifications.
b. Applicable Standards:
The following standards shall be followed:
c. Definitions
Clear: The removal of trees, scrub and artificial obstructions including fences, concrete
slabs, kerb and channel, remains of old buildings and the like.
Top soil: Topsoil is all surface soils, which have sufficient humus to support plant growth
without resort to artificial fertilization.
Cut: A general term for ‘in place’ material removed by digging from the ground. The
term ‘excavation’ or derivatives thereof may be used interchangeably.
Fill: A general term for material spread and compacted over the ground to make up
finished levels or levels to sub-grade. The term ‘Embankment’ or derivatives thereof
may be used interchangeably.
Sub-Grade: The finished, trimmed and prepared surface of the earth works after
completion of all cut and fills operations. The term ‘formation level’ or derivatives
thereof may be used interchangeably.
Sub-Base: A selected filling layer spread and compacted over the sub-grade to make up
levels to the underside of the base course or floor slab.
Base course: A selected filling layer spread and compacted to levels immediately below
road wearing course.
1.3 Antiquities
Any ancient carvings, relics, coins or other curiosities discovered during the excavation
or other work shall remain the property of the owner and shall be handed over to the
owner as required under the General Conditions of Contract.
a. Excavate foundation from existing ground level to the formation levels shown in
drawing.
Blasting of rock is not allowed and if necessary rock cutting shall be carried out by
chemical splitting and mechanical means.
a. Soils: Material such as sand, gravel, loam, clay, mud, black cotton, moorum, shingle,
river or nullah bed boulders, disintegrated rock, soling of roads, paths, hardcore,
macadam surface of any description (water bound, routed tarmac etc.) lime
concrete mud concrete or any combination of these. This class of material will yield
to the application of picks, shovels, or any other manual digging implements.
b. Ordinary Rock: Material such as limestone, sand stone, laterite, hard conglomerate.
This is any material that will not yield to manual implements, but is capable of being
excavated by conventional earthmoving plant applicable to the site and the
distances that material has to be moved. The use of a pusher unit or small crawler
tractor with ripper to facilitate excavation shall be considered as part of
conventional plant.
c. The Contractor may with the written permission of the Project Manager/Client
resort to a small amount of blasting to loosen any of this material but this action
will not in any way entitle the material to be classified as ‘Hard Rock”.
e. Hard Rock (blasting prohibited): Hard rock as described at c) above but where the
blasting is prohibited for any reason and excavation has to be carried out by
chiseling. Wedging or any other method agreed to by the Project Manager/Client.
a. Vegetable or Organic soil, turf, sand, silt, loam, clay, mud, peat, black cotton soil,
soft shale or loose murrum.
e. Stiff heavy clay, hard shale, or compacted murrum requiring close application of
excavation equipment.
f. Soft rock
g. Gravel and cobble stone usually rounded, having maximum dimension in one
direction of 300mm.
If the excavation is carried out to a greater depth than specified, extra depth shall be
made up by filling with lean concrete in a ratio of 1:4:8 (1 cement: 4 coarse sand: 8
stone graded aggregate of 40 mm size) or as directed by the employers representatives.
The cost of such extra excavation and of the filling therein as specified shall be borne by
the Contractor. No extra claims whatsoever will be entertained in this regard. The
bottom of excavation shall be trimmed, leveled, rammed and sides dressed and
trimmed in accordance with the drawings/directions of the Project Manager/Client. The
The Contractor shall ensure proper methods are adopted to control the creation of
Dust. Method adopted shall be approved by the Project Manager/Client.
Excavation shall include removal of all materials of whatever nature at all depths and
whether wet or dry necessary for the construction foundation and substructure
(including mass excavation for under ground reservoir where applicable) exactly in
accordance with lines, levels grades and curves shown in the drawing or as directed by
the Project Manager/Client. The bottom of excavation shall be leveled both
longitudinally and transversely or Sloped as directed by the Project Manager/Client.
Should the Contractor excavate to a greater depth or width than shown on the
drawings, then as directed by the employers representatives he shall at his own expense
fill the extra depth or width in cement concrete in proportion as directed by the Project
Manager/Client but in no case with concrete of mix leaner than 1:4:8 cement concrete.
The Contractor shall report to the Project Manager/Client when the excavations are
ready to receive concrete. No concrete shall be placed in foundations until the
Contractor has obtained Project Manager/Client approval in case, the excavation is done
through different strata of soil and if the same is payable as per provision in the
Schedule of Quantities the Contractor shall get the dimensions of the strata decided by
the Project Manager/Client for payment. If no specific provisions are made in the
Schedule of Quantities it will be presumed that excavation shall be in all types of soil
and other material and the Contractor's rate shall cover for the same.
After the excavation is passed by the Project Manager/Client and before laying the
concrete, the Contractor shall get the depth and dimensions of excavation and levels
(and nature of strata as applicable as per Schedule of Quantities like hard rock, soft rock
etc) and measurements recorded from the Project Manager/Client. Excavated pit should
The Contractor is responsible for finding suitable dumping yard and for the removal of
all sub grade obstructions, whether indicated or not, wherever it is likely to interfere
with execution and completion of the Project is deemed to be included in its rates.
Project document to be maintained as per Client/Project Manager instructions.
All surplus and unusable earth shall be carted out and disposed off outside the Site but
at a location approved by local authority and confirming to their specifications. The
Contractor shall quote its rate for disposing off or carting away the item considering
requirements and standards of the local authority with whose permission surplus and
unusable earth shall have to be disposed off.
1.11 Dewatering:
Rate for excavation shall include bailing or pumping out water which may accumulate in
the excavation during the progress of work either from seepage, rain water or any other
cause and for diverting surface flow, if any by bunds or other means. Pumping out water
shall be done in such approved manner as to preclude the possibility of any damage to
the foundation trench, concrete or masonry or any adjacent structure inside or outside
the wall front. When water is met in foundation trenches or in tank excavation, pumping
out water shall be from auxiliary pit of adequate size dug slightly outside the building
excavations. The depth of auxiliary pit shall be more than the working foundation
The Contractor shall adopt an appropriate method of dewatering work and shall submit
its proposal for carrying out the dewatering work for the approval of the Project
Manager/Client. The water shall be pumped continuously to keep the water level at a
minimum of two 2’ (feet) below the lowest point of excavation level. The operation
shall be continued until the entire excavation has been completed so as to ensure the
excavation is always dry. Scope of work under this contract to be carried till handing
over of project.Dewatering at site shall be carried out by the contractor without any
additional cost
Power / Fuel required for the operation of pumps etc shall be provided and paid for by
the Contractor .Electrically operated pumps are to be used to control sound pollution.
Softening of the bottom of excavation will not be allowed. If softening occurs due to
weather or any other source, the Contractor shall remove the affected area and replace
as specified and directed by the Project Manager/Client at no extra cost.
Necessary grading, trenching and temporary sumps shall be made around excavations
as required to prevent water runoff into excavation and to ensure proper protection to
slopes from erosion.
Protection and maintenance of all bench marks axis points and other similar reference
points if disturbed and/ or damaged, to be replaced by the Contractor at no extra cost
to the Client.
Location of existing utility lines; if shown on the drawings, is only approximate and only
for interpretation. The Contractor shall be responsible of their protection during the
duration of the Contract without causing any damage, dislocation, injury and/ or
interruption to these utility services. If so, to be replaced/ restored to their original
status at the Contractor's own cost.
All the temporary roads, constructions etc shall be made and maintained according to
the provisions of this Contract and as per the instructions of the Project Manager/Client
upon the completion of this Contract, the Contractor shall remove after getting the
approval from the Project Manager/Client all such temporary roads, structures, etc. and
restore the area in its original condition without any extra cost.
Sufficient safety signs /board to be placed in the site premises and all the safety
precautions should be strictly maintained.
2. Where material is dry, wet each layer to its optimum moisture content for
compaction purposes.
Each layer shall be uniformly moist and at the optimum moisture content for
compaction purposes.
Deposit material so that it is free from lenses, pockets, streaks and other imperfections.
b. Sample preparation
c. Sieve analysis
d. Liquid limits
f. Moisture content
h. Sand equivalent
l. Classification
iii) Carry out moisture density tests on representative samples prior to placing.
iv) Carry out gradation of materials prior to placing as the work proceeds.
v) Carry out site density tests of materials as the work proceeds and as follows:
Structural Fill:
General Fill:
Execute site density tests for compaction at a minimum depth of 100 mm below
compacted surface.
Execute a full compaction test or a one-point compaction test in conjunction with each
site density determination.
Execute a gradation test with each site density test and whenever there is an apparent
change in material being placed.
Execute the following site density tests and laboratory moisture density tests to
evaluate compaction achieved:
(ii) One test for every full shift of compaction operations on mass earthwork.
To consist of either:
1.14.8 Water
Water used for compacting fill or for washing crushed stone shall be clean and free from
oil, grease, organic matter, suspended sediments and other deleterious substances.
Backfill any excavations taken wider or deeper than required with mass concrete.
Where such excess excavation is carried out without approval, necessary extra
backfilling shall be at the Contractor's expense.
After removal of topsoil, the existing natural ground that will be under fill
embankments shall be scarified to a depth of not less than 150mm and compacted so
that the criteria called for on the specification are met.
1. Vibratory roller of either double or single vibrating drum of not more than 3.2
tonne mass per meter of roll width having a vibration frequency of not less than 37
Hz. Vibrating roller not exceeding the above weight limit but of frequency less
than 37 Hz are approved providing the nominal amplitude does not exceed that
shown relative to the weight in tones per meter roll width in figure1 any other
vibrating roller specifically approved by the Project manager. Vibrating rollers of
less than 1 tonne per meter of roll width shall not be used to compact any layer of
fill of more than 175mm of un-compacted thickness.
2. Three wheel steel- tired rollers having rear rolls each at least 0.50m wide and
having not less than 4.5 tonne per meter of roll width.
3. Pneumatic tyred roller having a minimum weight when operating of not less than
seven tonne, spread over at least seven pneumatic tyred wheels.
For filling in inaccessible places or against structures, hand tamping or small vibratory
compaction equipment may be used with the approval of the Project Manager/Client.
Care must be taken during compaction to ensure that no gaps are formed between
adjacent layers.
Fill material shall be compacted to attain the densities as called for in the
specifications.
As filling proceeds, test to verify the compaction being achieved shall be conducted.
Tests shall be done at a minimum frequency no less than one test per 150 cum. of fill
volume. Testing locations shall be distributed evenly throughout the fill volume and
In the event that tests do not verify the minimum compaction requirements, the
whole of the area for which the test is representative shall be reworked and retested,
unless otherwise directed by the Project Manager/Client.
Where the Project Manager/Client is of the opinion that a specific area within an
embankment cannot compact to the specified density, he shall order alternative
improvement works.
If selected earth kept aside as per the provisions is not sufficient for the back filling,
the Contractor, with its own cost, shall bring in good quality earth, murrum etc. from
borrow pits, either approved at the site and/ or elsewhere by the Project
Manager/Client. The cost of developing and reinstating the same after use as per the
directions of the Project Manager/Client and/or local laws prevailing for such borrow
pits, loading, transporting and re-handling of earth/ murrum etc. deemed to have
been included in its rates by the Contractor.
The Contractor at its own cost rectify and / or restore the damage (s) occurred due to
improper backfill and compaction done by it.
If any settlement occurs due to improper backfill and compaction and/ or cracks
developing in the sub-structure/ super structure works due to the same, the
Contractor shall make good its damages/ defects at no extra cost to the Client.
The Contractor at its own cost protect by bracing the basement walls till the proper
back filling and compaction are completed with the satisfaction of the Project
Manager/Client and complying with the conditions of the Contract and Technical
All the back filling and compaction works shall be of acceptable standard to both the
Project Manager/Client and the Structural Engineer.
The Contractor shall include in its rates the cost of removal of debris/ rubbish etc.
from the bottom of the basement wall prior to back filling.
Structural Fill:
Crushed stone:
Notes:
Apart from other factors mentioned elsewhere in this Contract, rates for the item of
excavation shall also include for the following:
a. Clearing site.
b. Setting out works as required.
c. Providing shoring and shuttering to avoid sliding of soil and to protect adjacent
structures and subsequently by removing the same.
d. Collection of excavated spoil and Sorting out useful excavated materials and
conveying beyond the structure and stacking them neatly on the site for back
filling or re-use as directed.
e. Bailing and pumping out water as required and directed.
f. Excavation at all depth (unless otherwise specified in the Schedule of Quantities)
and removal of all materials of whatever nature wet or dry and necessary for the
construction of foundation underground reservoir etc and preparing bed for
laying concrete.
g. Necessary protection including labour, materials, and equipment to ensure
safety and protection against risk or accident.
h. Drilling of small holes as directed to explore the nature of substratum if
necessary.
Excavation for foundation of columns, beams, walls and the like shall be measured
and paid net as per drawing, dimensions of concrete (bed concrete where so
specified) at the lowest level in regard to length and breadth and depth shall be
computed from the concerned excavation levels and ground levels taken before
excavation. Any additional excavation required for working space, planking
dewatering and strutting etc. shall not be measured and paid for separately but rates
quoted for excavation shall include for all these factors. No increase in bulk after
excavation shall be made.
Prior to start of Project the Contractor shall verify and approve the block levels and
benchmarks established for the entire Site and sign in acceptance of the same. In case
of any discrepancy the same shall be checked and will be recorded and agreed after
After site clearance a joint survey by the Contractor and the Project Manager/Client
will be carried out to establish ground levels before excavation which will be the basis
for computing quantities.
On completion of excavation, a joint survey will be carried out at the Contractor’s cost
to establish the excavated levels and ascertain if the work is as per Drawings and
Specifications with respect to depth and area. The portions excavated for working
space, slopes as shown on drawings will not be measured for payment. Extra portions
excavated, due to the Contractor’s working method, if any, will not be measured or
paid. No extra claims whatsoever will be entertained in this respect.
The method adopted for computing volumes shall be as per Simpson’s Rule.
Deductions for rock excavation quantity computed as specified will be made from
excavation in soil.
Apart from other factors mentioned elsewhere in this Contract, rates for the item of
backfilling item of work shall also include for the following:
a. Backfilling the trenches along side masonry or concrete with approved excavated
materials up to the natural ground level in layers as specified including watering
and ramming.
b. Earth filling in plinth: If there is approved surplus earth after backfilling the sides of
excavations, the same will be used for plinth filling if required. Any additional
approved earth if required for plinth filling the same shall be brought on the site,
by the Contractor from outside. No borrow pits shall be opened on the Site; Filling
in plinth shall be done in layers of 15cm thick each layer being consolidated by
1.17.1 Location
Soling shall be constructed under floors and other areas where shown n the
drawings.
The stones for soling shall be of a height equal to the required thickness of soling.
Their length or breadth shall not be greater than twice the soling thickness. This
means that the stones would pass through a ring 180mm in diameter but not a ring
100mm in diameter.
Soling stone shall be hand packed as close as possible with their broadest side
downward and greatest length across the road. Gauge pegs shall be driven at close
intervals to indicate the required thickness of the soling. The joints between stones
shall be placed at the edges of the area to be covered. All interstices between stones
shall be wedged in with smaller stones, well driven into achieve tight packing and
complete filling of the interstices.
Related Work
a. Concrete Formwork
b. Concrete Reinforcement
c. Concrete Finishing
d. Sealants
IS - 299 Specification for Ordinary, rapid hardening and low heat Portland Cement
IS - 383 Specification for Coarse and Fine aggregate for use in mass concrete
IS - 515 Specification for natural and manufactured aggregate for use in mass
concrete.
IS - 3025 Methods of sampling and test (physical and chemical) for water used in
IS - 2722 Specification for portable swing weigh batchers for concrete (single & double
bucket type)
IS - 457 Code of practice for general construction of plain and reinforced concrete for
dams and other massive structures.
IS - 3370 Code of practice for concrete (Part I to IV structures for storage of liquids
IS - 2210 Criteria for the design of R.C. shell structures and folded plates.
IS - 3558 Code of practice for use of immersion vibrators for consolidating concrete
Definitions
b. Hot Weather:
Shade air temperature of 37o C and higher.
Quality Assurance
a. Supervising staff shall have qualifications and experience specified in the Contract.
b. The following tests shall be carried out by the approved agency:
Testing preliminary test cubes;
Testing work test cubes;
Testing in situ concrete at site by hammer test, ultrasonic tests and core tests.
c. Standards: Comply with the following codes, specifications and standards and as
shown on the drawings.
IS 456: 2000 - Specifications for plain and reinforced concrete.
ii.IS 269:1976 or latest amendment - Specifications for ordinary and low heat
Portland cement.
Submittals
Samples
Slide bearings
Materials
All materials used in the works shall be of best quality of their respective kind as
specified herein, obtained from suppliers and sources approved by the Structural
Consultant and shall comply strictly to tests instructed by the Structural Consultant /
Project Manager/Client, and where tests are not laid out, with the requirements of the
latest issue of the relevant Indian Standard.
Test Certificate
All manufacturer’s test certificates, proof sheets, etc showing that the materials have
been tested in accordance with the requirements of the specification and of the
approved Indian Standard(s) are to be supplied free of charge on request to the Project
Manager/Client.
Cement
Cement shall be of Portland type /PPC and shall comply of IS: 269. The cement used
shall be of approved manufacture and the sources of supply shall not be changed
without approval of the Consultants / Project Manager/Client.
The size and dimensions of the cement godown shall get to be approved, before its
construction, from the Project Manager/Client.
For extra safety during monsoon, or when cement is expected to be stored for an
unusually long period, each stack shall be completely enclosed by a waterproofing
membrane, such as polyethylene which shall cover the top of the stack. Care shall be
taken to see that the stored cement is not damaged at any time during the use.
Storage of the cement at the Site shall be at the Contractor’s expense and risk. Any
damage occurring to cement due to faulty storage in the cement godown or on account
of negligence on its part, shall be the liability of the Contractor.
Aggregate
Course aggregates brought to site shall be washed clean if required and as directed by
the Project Manager/Client.
Fine Aggregate
a. Shall be washed dry sand and shall confirm to IS: 383 between Grading Zone I and
II for structural concrete.
b. Shall pass through IS sieve 4.75mm test sieve leaving a residue not more than 5%
c. Shall not contain any traces of silt, and the sand shall be thoroughly washed with
water so as to bring the percentage of silt content within the prescribed limit.
Nothing extra is payable to Contractor on this account.
d. Fine aggregates shall be so stacked as to prevent dust and foreign matter getting
mixed up with it as far as practically possible.
e. Since fine aggregates bulk to a substantial extent when partially wet,
measurements shall be taken when the stacks are dry or an appropriate allowance
has been made for bulking.
Water
Proportioning
a. Aggregate
b. Cement
c. Water
Only such quantity of water shall be added to the cement and aggregates in the
concrete mix as to ensure dense concrete, specified surface finish, satisfactory
workability, consistent with the strength stipulated for each class of concrete.
The water added to the mix shall be such as not to cause segregation of
materials or the collection of excessive free water on the surface of the concrete.
The water cement (W/C) ratio is defined as the weight of water in the mix
(including the surface moisture of the aggregates) divided by the weight of
cement in the mix.
e. Water/Cement Ratio
The W/C ratio specified for use by Project Manager/Client shall be maintained.
Contractor shall determine the water content of the aggregates as frequently as
desired by the Project Manager/Client as the work progresses and as specified in
IS 2386 (Part III) and the amount of mixing water added at the mixer shall be
adjusted as directed by the Project Manager/Client so as to maintain the
specified W/C ratio. To allow for the variation in their moisture content, suitable
adjustments in the weights of aggregates shall also be made.
Mixer and the weight batcher shall be maintained in clean and serviceable
condition. The accuracy of the weight batcher shall be periodically checked.
Both mixer and the weight batcher shall be set up level on firm base and the
hopper shall be loaded evenly. The needle shall be adjusted to zero when the
hopper is empty. Fine and coarse aggregates shall be weighed separately.
Each time the work stops, the mixer shall be cleaned out and the next
commencing he mixing, the first batch shall have 10% additional cement to allow
for striking in the drum.
Cleanliness
Clean mixer and handling plant by washing with clean water at the end of the work and
at intervals of 30 minutes during mixing.
If old concrete mix remains in the mixer drum, rotate the drum with clean aggregate and
water before mixing the cement.
Planning of Concrete
a. Consultant shall be informed 24 hrs in advance before the pour of each concrete
to allow for inspection of reinforcement, sizes and levels of the members to be
concreted, concrete cover, cleanliness, filling of gaps and wide and supporting
props.
b. Ensure that the spaces to revive concrete are clear free from debris and free from
water.
c. Transportation: Use approved method to identify that the grade of concrete to be
placed in proposed location.
d. Use suitable stools, walkways, barrow runs, for traffic over reinforcement or
freshly placed concrete.
e. Clean the transportation equipment immediately after use or whenever cement
and aggregate is used by using clean water.
Ordinary Concrete
The basic aim of Mix Design shall be to find the most economic proportion of cement,
aggregate and water which will give the desired target mean strength of concrete,
workability and durability for specified grade of concrete. Also it is important that the
Mix should be easily worked with the help of equipment available at the Site. The
operations involved are measurement of materials, their mixing, placing, compacting,
finishing required and curing. The design shall be carried out strictly to IS Specifications
and IS Codes of Practice, namely IS: 456- and S P –23-
In order to ensure that not more than the specified proportions of test results are likely
to fall below the characteristic strength, the concrete mix has to be designed for higher
average compressive strength for a specified grade of concrete is defined a target mean
strength.
Design Mix and weigh batching will be done as approved by the Project Manager/Client.
The Contractor shall submit to the Project Manager/Client the tentative Mix Design it
proposes to use at the site.
On receipt of the above, the Project Manager/Client may immediately order to carry out
work or site test before the final approval. This shall be done with the mixer, weigh
batches, etc. and materials actually used in the Project.
This shall give the Contractor additional chance to check for itself actual workability and
make sure that the mix proposed by it will be satisfactory with regards to slump, water-
cement ratio and workability.
Test cubes shall be of size 150mm x 150mm x 150mm. These are to be legibly marked
with location and date of concreting. Where concrete (in works) is to be vibrated or not
vibrated, the cubes are to be cast as per IS Standards.
Where the concrete in the works is un-compacted, pour the concrete into the mould in
three layers and compact each layer with a 16mm dia tamping rod.
Six (6) cubes shall be taken from each of the three batches to test the mix. Cube shall be
cast, stored, cured, transported and tested as per IS:516-1959. The test may be carried
out at the Site or at laboratory as approved by the Project Manager/Client.
a. Within 7 days of signing the Contract and before commencing work on site,
prepare trial mixes for each type of concrete and submit 6 preliminary test cubes
from each mix to the testing authority.
b. The testing authority shall test three test cubes at 7 days and three at 28 days for
each type of mix where the difference between the higher and the lowest test
results from any one trial mix at 7 days exceeds 15% of the average and any cube
weaker than the minimum requirement, make a further trial mix, increasing the
proportion of cement if necessary to obtain the required strength.
c. If any test results from any one-trail mix fail to exceed the minimum strength at
28 days:
i. Remove from site materials from which the trial mix was prepared.
ii. Provide new materials and prepare and test further trial mixes until specified
requirements are achieved.
The Design Mix shall hold good so long as the materials continue to be of the same
quality and from the same source. Minor adjustments are to be done daily based on the
tests of materials used.
Concrete shall be weighed batched. The dials of weigh-batching units shall be checked
with standard weights periodically.
The minimum cement content to be used for the job is as per IS:456
Further the Contractor has to provide and maintain all the equipment and stock at the
Site throughout to carry out the following tests in a small Site laboratory or get these
tests done from approved laboratories without extra cost to the Contract.
Grading of aggregate
Silt content of sand
Moisture content of aggregate
Slump test of concrete mix
Concrete cube test
The Contractor shall maintain full records for all above tests in a register. The format of
the records shall be prepared in consultation with the Project Manager/Client. It shall
have full access to the Contractor’s site laboratory. The Contractor shall include charges
Where sufficient test results for a particular grade of concrete are not available, the
value of standard deviation given in Table below may be assumed.
Deviation N/Sq.mm
M 10 2.3
M 15 3.5
M 20 4.6
M 25 5.3
M 30 6.0
M 35 6.3
M 40 6.6
However, when adequate post records for a similar grade exists and justify to the
designer a value of standard deviation different from the shown in table above, it shall
be permissible to use that value.
ii. The standard deviation of concrete to a given grade shall be calculated using the
following formula from the results of individual tests of concrete of that grade
obtained as specified for test strength of sample.
iii. Estimated standard deviation S=Square root of (sum of squared deviations of the
individual strength of n samples divided by n-1) where n = number of sample test
results.
iv. When significant changes are made in the production of concrete batches (for
example changes in the materials used. mix design, equipment of technical
control), the standard deviation value shall be separately calculated for such
batches of concrete.
Mixing of Concrete
Weigh Batching shall be followed if mixed at the site for all structural concrete works.
The Contractor shall provide Concrete Batch Mixers, Vibrators, Weigh Batchers
conforming to relevant IS Specifications and from approved and recognized
manufacturers. The capacity and number of mixers and vibrators required at the Site
from time to time shall be to the approval of Project Manager/Client. No equipment
from the site shall be removed without the prior written approval of the Project
Manager/Client. The Contractor shall maintain a platform weighing scale of capacity
300 kg with fraction of 100 gm at the site.
The machine will have to be got calibrated by the Contractor once in every two weeks or
after 200 cum of concrete whichever is earlier, and records of these calibrations shall be
maintained. The dials of the weigh batchers shall be checked with standard weights
periodically.
Consistency
Temperature of Concrete
The placing temperature of concrete shall not be more than 38 degrees Celsius. If it is
more, the Project Manager/Client may order addition of ice or chilled water to the
concrete. Also the Contractor shall take following precautions:
Mixer and Weigh Batcher shall be painted white color.
Aggregate storing bin shall not be exposed to the sun.
Water shall be sprinkled on aggregate well before concreting to keep the
temperature low.
Similarly, during the cold weather, concreting shall not be done when the temperature
falls below 4.5 Degrees Celsius. The concrete placed shall be protected against by
suitable covering. The concrete damaged by frost shall be removed and work redone
with no extra cost.
Shrinkage Cracks
Concreting shall be avoided in very warm weather. Under such circumstances, the
placed concrete shall be covered with damp hessian cloth within two hours of placing of
concrete.
To achieve good result the concrete shall be immediately covered with a plastic sheet
and not allowed to any direct wind contact to eliminate shrinkage cracks.
Workmanship
All works shall be true to level, plumb and square and all corners and edges in all cases
shall be unbroken and neat.
Transportation
Concrete shall be transported with the help of pumps of sufficient capacity to achieve
necessary heights wherever required from the mixer to the place of laying as rapidly as
possible by methods which will prevent the segregation or loss of any of the ingredients
and maintaining the required workability. The pumps can be either compressor type or
boom type. All the pumping equipments have to be maintained and kept operational by
the Contractor. Concrete shall be laid within 120 minutes from the time of batching as
per IS.
Placing of Concrete
Placing of concrete shall be done using pumps only at all levels. The pumps shall be of
sufficient capacity to achieve necessary heights wherever required.
The slump of concrete placed with the help of pumps shall not be more than 120mm
unless otherwise instructed by the Project Manager/Client. Concreting shall commence
only after formwork is approved reinforcement is recorded and permission to proceed
with concreting has been approved in writing from the Project Manager/Client.
Formwork should be clean, free from dust, pieces of wood or any other foreign material.
It should be treated by form releasing agent prior to the laying of reinforcement and
concrete, based on sample approved by the Project Manager/Client prior to start of
construction at Site. Concrete shall be as gently deposited as is practically possible, in
its final position to avoid re handling and shall be so deposited that segregation of
aggregates do not occur. In case of deep trenches and footings, it may be done with the
help of chutes. Concrete from wheelbarrows shall not be dumped away from the face
of concrete already been placed. It shall be dumped into the face of concrete already in
place. Concrete shall be laid during normal working hours. Concreting at night or on
holidays shall be permitted only on the written approval of the Project Manager/Client.
No concreting shall be done within half an hour of the closing time of the day, unless
permitted by the Project Manager/Client.
For concreting of slabs and beams wooden plant or catwalks of chequered MS plates or
bamboo mats or any other suitable materials supported directly on the centering by
means of wooden blocks or lugs shall be provided to convey the concrete to the place of
In case of columns and walls, it is desirable to place concrete without any construction
joints. The progress of concreting in the vertical direction, shall be restricted to one
meter per hour.
Concrete pouring shall be done by using appropriate methods like funnel system/chutes
for vertical elements, flexible hoses for horizontal elements etc.
Compaction of Concrete
Concrete shall be thoroughly compacted into a dense mass as depositing shall proceed
by means of suitable vibrators. The vibrator shall maintain the entire concrete under
treatment in an adequate state of agitation and shall continue during whole period
occupied by placing of concrete. Care should be taken not to over-vibrate the concrete.
While vibrating no holes should be visible in concreting. Compaction should be
completed before the initial setting time. Compaction shall be done till air bubbles
cease to appear. Concrete already set shall not be disturbed by successive vibration.
Hand tamping shall not be permitted. But only in exceptional cases, depending on the
thickness of the members and feasibility of vibrating the same, the Project
Manager/Client may permit hand tamping. Hand tamping or compaction shall be done
with the help of tamping rods so that concrete is thoroughly compacted and completely
worked around the reinforcement embedded fixtures, and into the corners of the form
look.
The layers of concrete shall be so placed that the bottom layer does not finally set
before the top layers are placed. The vibrators are so applied so that the centre of mass
being compacted at the time of placing of concrete.
Vibrator shall be of immersion type with frequency of 100 Hz minimum when operating
in concrete, or the exterior with a frequency of 50 Hz minimum.
Care shall be taken to ensure that at no time the vibrators and /or vibration action is
used to push the concrete ahead. Vibrators shall be applied systematically to overlap
zones of influence.
It shall be ensured that the needle vibrators are not applied directly on the
reinforcement on the formwork which may destroy the bond between concrete and
reinforcement.
When electric vibrators are in use the standby petrol, diesel or kerosene vibrator should
always be available at the concreting point.
Form horizontal joints in walls designed to be continuous with floor slabs at the top of
an integrally cast kickers minimum 25mm high. No other horizontal joints will be
allowed.
Isolation joints
Control joints
b) Form by either:
a) Locate near the middle of slabs, beams, or girders, unless a beam intersects a girder
at the middle location, in which case offset joints in girders a distance equal to twice
the width of the beam.
b) Make provision for transfer of shear and other forces through construction joints.
Space not exceeding 5m centers and also locate where abrupt changes in thickness or
height occur, at least 2m from corner.
Expansion Joint
Curing
In order to properly monitor the curing activity, the Contractor shall write legibly with
paint, the date of casting the concrete of each member of the structure which shall
remain clearly visible atleast till the completion of curing atleast. Chemical curing is not
allowed at site.
Finishing
Concrete surface shall be finished keeping in mind the next operation to be carried out
over the surface. For guidance the following points shall be noted:
Roof shall be trowelled even and smooth with a wooden float, before the concrete
begins to set.
Surface that will receive plaster shall be roughened immediately.
Surfaces that will be in contact with masonry shall be roughened immediately
Surfaces that will receive floor finishes, tiling, etc. shall be roughened while it is still
green.
Every care shall be taken not to disturb the freshly laid concrete.
For Ramps and Basements concrete shall be broom-finished.
Immediately on removal of formwork, the RCC surface shall be examined by the Project
Manager/Client. Till such time, no remedial measures shall be carried out by the
Surface defects minor in nature may be accepted as a special case by the Project
Manager/Client/Structural Consultants whose decision in this matter is final and binding
on the Contractor. Once accepted, the defects shall be rectified as follows and all
expenses incurred due to the rectification process, shall be to the Contractor’s account.
(a) Surface defects which require repair when forms are removed, usually consist of
bulges due to the movement of forms, ridges at form joint, honey combed areas,
damage, resulting from the stripping of forms and bolt holes, bulges and ridges are
removed by careful chipping or tooling and the surface is then rubbed with a
grinding stone. Honey combed and other defective areas must be clipped out, the
edges being cut as straight as possible and perpendicularly to the surface, or
preferably slightly undercut to provide a key at the edge of the patch.
(e) Or as an alternative to paragraph (d) above, epoxy based proprietary items like
grouts as directed by the Project Manager/Client / Structural Consultants, shall be
used. The methodology as specified by the manufacturers of the proprietary item
shall be strictly adhered to.
(f) Holes left by bolts are to be filled with non-shrink grouts, as specified and directed
by the Project Manager/Client/ Structural Consultants carefully packed in to places
in small amounts. The mortar is mixed as dry as possible to allow enough water to
go into it, so that it will be tightly compacted when forced into the place.
(g) Tie-rod holes extending right through the concrete may be filled with mortar or
non-shrink grout, as the case may be, a pressure gun similar to the gun used for
greasing motorcars.
(h) Normally, patches appear darker than the surrounding concrete when uniform
surface colour is important, this defect shall be remedied by adding 10 to 20
percent of while portland cement to the patching mortar, the actual quantity being
determined by trial.
(i) The same amount of care shall be taken to avoid the material in the patches as with
the whole structure. Curing shall be started immediately after packing is done to
prevent early drying. A membrane curing compound is these cases will be most
convenient.
Cracks
Cracks observed shall be examined. It shall be kept under observation and a record shall
be maintained for a period of 45 days. It shall be shown to the Project
Manager/Client/the Structural Consultant and the following procedure shall be
followed:
Cracks developing further and felt detrimental to the strength of construction shall
be tested as per the relevant Indian Standards.
Cost of above shall be borne by the Contractor if the failure is on its part unless it
is due to a design fault, decided at the discretion of the Project Manager/Client.
Decision of the Project Manager/Client in the matter shall be final and binding on all
parties. This decision shall not be open for arbitration.
The minimum frequency of cube testing shall be as follows. Each set of sample shall consist of 6
cubes.
Up to 5 cum a day 1
5 cum to 15 cum a day 2
15 cum to 30 cum a day 3
30 cum to 50 cum a day 4
More than 50 cum per day 4 + one additional for each 50 cum or part
thereof.
Three cubes shall be tested on the 7th day and three cubes on the 28th day.
Acceptance of Work
It shall be in accordance with in IS:456-2000, SP-23 and SP-24. The guidance brief is elaborated
below. Part or element of work shall be deemed to be accepted, provided the results of the
28th day cube testing confirm to the criteria stated as under:
Technical Specification Page 47
The average of the three consecutive cubes strength shall not be less than specified
strength.
No individual cube strength shall be less than 90% of the specified strength.
If the individual cube strength exhibit more than 133% of the specified strength such
a cube shall be specified as freak and the criteria in above two points shall be
applied to remaining two cubes and their acceptability determined.
If cubes fail at 7 days, defective concrete can be dismantled, removed and replaced
without awaiting 28 day test results.
If the concrete tests fail to meet the acceptance strength required for respective
grades of concrete, the Project Manager/Client may take one of the following
actions:
Instruct Contractor to carry out such additional tests (e.g. Core tests, load tests,
ultrasound, etc.) and/or remedial measures to ensure the soundness of the
structure at the Contractor’s expense
The work will be rejected and any consequential action as needed shall be taken at
the Contractor’s expense, including cutting out and replacing a part or whole of
work.
During hot or cold weather concreting should be done as per the procedure set out in IS:7861
Part I or IS:7861 Part II or as directed by the Project Manager/Client.
Fixtures
Any fixture, steel angles, holdfasts etc shall be embedded according to the drawing or as
instructed by the Project Manager/Client.
Precast Concrete
Terminology
Ready Mixed Concrete - Concrete delivered at site or into the purchaser's vehicle in a plastic
condition and requiring no further treatment before being placed in the position in
which it is to set and harden. All provisions for good workmanship, quality control and
treatment, as stated in previous clauses shall be applicable.
Agitation - The process of continuing the mixing of concrete at a reduced speed during
transportation to prevent segregation.
Agitator - Truck mounted equipment designed to agitate concrete during transportation to the
site of delivery.
Truck mixer - A mixer generally mounted on a self-propelled chassis capable of mixing the
ingredients of concrete and of agitating the mixed concrete during transportation.
Types
Materials
Cement - The cement used shall be ordinary Portland cement or low heat Portland
cement conforming to IS-269* or Portland slag cement conforming to IS 455-or
Portland-pozzolana cement conforming to IS: 1489-or rapid hardening Portland cement
conforming to IS 8041E-as may be specified by Consultant at the time of placing the
order. If the type is not specified ordinary Portland cement shall be used.
Fly ash when used for partial replacement of cement, shall conform to the requirements
of IS: 3812 (part I
Water used for concrete shall conform to the requirement of IS: 456.
Admixtures shall only be used when so agreed to between the purchases and the
manufacturer. The admixtures shall conform to the requirements of IS 456 and
Basis of Supply
The ready mixed concrete shall be manufactured and supplied on the following basis.
Specified strength based on 28-day compressive strength of 15-cm cubes tested in
accordance with IS: 456
When the concrete is manufactured and supplied on the basis of specified strength, the
responsibility for the design of mix shall be that of the manufacturer.
General Requirement
The minimum quantity of cement and the details regarding proportioning and works
control shall be as per Clauses above.
When a truck mixer or agitator is used for mixing a transportation of concrete, no water
from the truck-water system or from elsewhere shall be added after the initial
introduction of the mixing water for the batch, except when on arrival at the
site of the work, the slump of the concrete is less than that specified; such
additional water to bring the slump within required limits shall be injected into
the mixer under such pressure and direction of floor that the requirements for
uniformity specified in Appendix A are met.
Unless otherwise agreed to between the purchaser and the supplier, when a truck mixer
of agitator is used for transporting concrete, the concrete shall be delivered to
the site of the work and discharge shall be complete within 1.5 hours (when the
prevailing atmospheric temperature is above 20°C) and within 2 hours (when
the prevailing atmospheric temperature is at or below 20°C) of adding the
Temperature - The temperature of the concrete at the place and time of delivery shall
be not less than 5°C. Unless otherwise required by the purchaser, no concrete
shall be delivered, when the site temperature is less than 2.5°C and the
thermometer reading is falling.
The temperature of the concrete shall not exceed 50C above the prevailing shade
temperature, when the shade temperature is over 200C. The temperature of
concrete mass on delivery shall not exceed 400C.
Sampling and testing: Adequate facilities shall be provided by the manufacturer for the
purchaser to inspect the materials used, the process of manufacture and the
methods of delivery of concrete. He shall also provide adequate facilities for
the purchaser to take samples of the materials used.
Sampling and testing - Unless otherwise agreed to between the purchaser and the
supplier, the sampling and testing of concrete shall be done in accordance with
relevant requirements of IS: 456-, IS: 1199-and IS: 516-
Consistency or workability - The tests for consistency or workability shall be carried out
in accordance with requirements of IS: 1199- or by such other method as may
be agreed to between the purchaser and the manufacturer.
Strength Test - The compressive strength and flexural strength tests shall be carried our
in accordance wit the requirements of IS: 516- and the acceptance criteria for
concrete whether supplied on the basis of specified strength or on the basis of
mix proportion, shall conform to the requirements of Table 5 and other related
requirements of IS: 456-.
Cubes casted at site shall be given the criteria for acceptance of concrete and RMC
vehicle shall be allowed only with the computerized batching sheets.
Cost of Testing - Unless otherwise agreed to between the purchaser and the
manufacturer, the cost of the tests carried our in accordance with the
requirements of this specification shall be borne as follows:
By the manufacturer if the results show that the concrete does not comply with the
requirements of this standard.
Manufacturer's Records and Certificates - The manufacturer shall keep batch records of
the quantities by mass of all the solid materials, of the total amount of water
used in mixing and of the results of all tests. If required by the purchaser, the
manufacturer shall furnish certificates, at agreed intervals, giving this
information.
The concrete quality shall meet all requirements and Specifications of concrete as stated
hereof. Contractor shall be allowed to use own Batching Plant or procure concrete, but Quality
Tests will be the responsibility of the Contractor and off-site Batching Plants shall be open for
inspection to the Project Manager/Client throughout the Project.
Admixtures
General
Admixtures may be used in concrete only with the approval of Consultant / Project
Manager/Client based upon evidence that, with the passage of time, neither the
compressive strength not its durability get reduced. Calcium chloride shall not be used
for accelerating set of the cement for any concrete containing reinforcement, or
embodied steel parts. When calcium chloride is permitted to be used, such as in mass
concrete works, it shall be dissolved in water and added to percent of the weight of the
cement in each batch of concrete. When admixtures are used, the designed concrete
mix shall be corrected accordingly. Admixture shall be used as per manufacturer's
instructions and in the manner and with the control specified by Consultant / Project
Manager/Client.
Retarding Admixtures
f. The Contractor when requested shall provide the services of a full time field
technician of the admixture manufacturer to advise the proper addition of the
admixture to the concrete or adjustment of concrete mix proportions to meet
changing conditions.
Measurement
Unit rates shall allow for chamfers, grooves, lines etc. in reinforced concrete members
as well as necessary slope, drops, drip models etc.
Minimum cement content per cubic meter of cement concrete has been specified in
each item of cement concrete work, However, if cement is required to be used so as to
obtain the minimum strength specified for the grade of cement concrete, the Contractor
will not be paid for extra cement used.
Scope of Works
The following item are not intended to exclude any other items of works required by the
Design Consultants, or that may be required by local code or good construction practice.
The following work shall be included by the Contractor in its Tender and Contract Sum
as they may not have been detailed specifically on the architectural and engineering
drawings and specifications but we required in order that a complete job in every
respect can be.
a. The supply, maintenance and removal of all temporary rungs, and ramping as
necessary on the site
e. The excavation and concrete construction of all sump pits, manholes, drains
under slabs, etc as described in the specifications and shown on the drawings.
f. Formwork, reinforcing, embedded items and layout for concrete tank cradles.
g. All roof mechanical and other building services equipment pads and kerbs at the
HVAC and Electrical openings, concrete including dowels, formwork and
roughing of concrete
h. All fire grading and removal of standing water before the placing of concrete.
i. Included for all below slab, surface water and drainage, including brickfill, within
the Tender.
j. Points and in steel below slabs lightening protection systems as detailed. The
Contractor, in the preparation of his Tender, is to allow for watertight
construction.
k. Allow for keeping the works clear and tidy at all times and for the removal of
debris arising from the works, and to be disposed off at locations designated by
the Project Manager/Client, and frequent removed off the site. Any surplus
concrete deposited at the workfront of on the site (concrete droppings) must be
removed by the Contractor at its own expense.
m. Leaving all necessary holes and pockets for steel work beams for lifts and for
making good after installation by other Contractors. Casting in all slots and
inserts for fixings to guides and runners to lift shafts.
n. All trench drain box-cut with necessary recesses and casting in all anchor bolts
and providing and installing trench drains and other embedded items as shown
on the drawings.
r. Providing and casting into concrete slots to receive masonry or blockwork ties to
support all such walls as shown on the drawings or as directed by the Project
Manager/Client.
u. Forming in the concrete members chases for any asphalt "track-in" and/or
flashing and the like.
v. Provide grout for lift saddle and floor closures prior to setting (setting by
others).
3 Reinforcement
A. Concrete Formwork
IS - 432 Specification for Mild steel and medium tensile bars and hard drawn
steel wire.
IS - 1139 Specification for hot rolled mild steel, medium tensile steel and high
yield strength steel deformed bars for concrete reinforcement.
IS - 1566 Specification for plain hard drawn steel wire fabric for concrete
reinforcement
IS - 1785 Specification for plain hard drawn steel wire for prestressed
concrete.
IS - 1786 Specification for cold twisted steel high strength deformed bars for
concrete reinforcement.
IS - 2080 Specification for high tensile steel bars used in prestressed concrete
IS - 2751 Code of practice for welding of mild steel structures are folded
plates
IS - 2502 Code of practice for bending and fixing of bars for concrete
reinforcement
BIS Certification
Material received at the Site shall have BIS Certification mark. Such bundle or coil
containing the bars shall be suitably marked with BIS Certification mark. Bars shall also
be marked to identify categories. This shall be done as per IS: 1387.
In case bars are without BIS Certification mark, the manufacturer shall give a certificate
stating the process of manufacture, chemical composition and mechanical properties.
Each certificate shall indicate the number or identification mark of the cart to which it
applies, corresponding to the number or identification mark to be found on the
material.
All reinforcements shall be free from loose mill scale, excessive rust, loose rust, pitting,
oil, grease, paint, mud or any other foreign deleterious material present on the surface.
Cleaning should be done to the satisfaction of the Project Manager/Client.
Each batch of steel brought to the Site shall be tested prior to use. Cost of all tests shall
be borne by the Contractor.
Material acceptable as per IS Specifications will be allowed into the Project. All rejected
material shall be removed from the Site by the Contractor within 30 days of its rejection.
If the same is not done, the Project Manager/Client can get work done by third party at
the Contractor’s risk and cost shall impose a penalty of Rs 500 (Rupees Five Hundred
Storage
Reinforcement bars received at the Site shall be stored on hard, concreted platform and
clear of the ground to a minimum of 200 mm with the use of timber sleepers or any
other means. Reinforcements shall be kept covered by tarpaulins or plastic to avoid
excessive corrosion or any other contamination. It is advised to follow storage methods
as described in IS: 4082.
Quality Assurance
a. Supervisory staff shall have qualification and experience in the above field.
b. Welders qualified and having approved certificates for welding shall be employed.
Handling
a. Bend test requirements shall conform to the following and shall be based on
1800 bends of full size bars around pins.
i. Wire
Spacer material shall be of durable quality and shall not lead to corrosion of
reinforcement or spilling of concrete.
c. Tying wire shall be of 18 G black annealed mild steel wire or other approved type
double fold to tie the reinforcements confirming to is 280.
d. Cover blocks shall be non-corrosive material such as plastic, but not wooden or
broken bricks or stone. Specially made concrete blocks shall be used. Such
cover blocks shall be cast from concrete and not from cement mortar; strength
of these blocks shall be equal to the concrete in use.
e. Tying wire shall be of 18G black annealed mild steel wire or other approved type
double fold to tie the reinforcements. It shall be face from rust, oil, paint,
grease, loose mill seales or any other deleterious material undesirable for
concrete or reinforcement or which may prevent adhesion of concrete to
reinforcement.
Unit Weights:
Execution
b. Cut and bend reinforcement to approved shop drawings and details shall be
used.
d. Do not rebend without approval. In case of re bending, care shall be taken that
the rating of bend is not less than 4 x bar dia at construction joints for plain steel
bars and 6 x bar dia for high strength bars.
g. Bars should be inspected for visible defects such as cracks, brittleness, excessive
rust, loose mills scale, etc.
Welding
d. The length of run deposited in a single pass shall not exceed 5 x bar diameters. If
a longer welded length is required divide into sections with the space between
runs not less than 5 x bar diameters.
iii. The distance between staggered joints shall not be less than the
end anchorage length joints.
Mechanical Splicing
Inspection
b. Ensure that the Formwork to receive the reinforcement is clean and free from
debris.
Anchoring
Anchoring of bars and stirrups shall be provided exactly as detailed in the structural
drawings or as directed by Project Manager/Client/Structural Consultant.
In case of reinforcement steel in tension, deformed bars may be used without end
anchorage provided the development length requirement is satisfied. Hocks shall
normally be provided for plain bars in tension. Development length of the bars shall be
determined as per relevant clauses of IS: 456 -
Lapping of Bars
Laps shall be strictly as per the structural drawing or as directed by the Project
Manager/Client/Structural Consultant. For general guidance the following principles
shall be followed as given in IS: 456 -
In case Contractor wishes to use bars of shorter length, laps shall be provided at
the Contractor’s expense in the manner and the locations approved by the
Structural Consultant.
Splices shall be provided as far as possible away from the sections of maximum
stress and be staggered.
If more than half of the bars shall be spliced at a section, special case shall be
ensured such as increasing length of lap or closer spacing of stirrups around the
length of splice.
Lap splice shall not be used for bars having diameter larger than 36 mm. For
larger diameters bars it may be welded. Lap length including anchorage value of
hooks in flexural tension shall be La (as defined in Article 26.2.1 of IS: 456-2000)
or 30 times the diameter of the bar whichever is greater and for direct tension
2La or 30 times the diameter of the bar whichever is greater. The straight length
of lap shall not be greater than 15D or 20 cm, whereas D is the diameter of the
bar.
When above is not possible, the overlapping bars shall be bound together at
intervals not exceeding twice the diameter of such bars with two strands of
annealed binding wise of 0.90mm to 1.6mm diameter twisted together tightly.
As and when necessary welded laps shall be proved as specified by the Structural
Consultant.
Securing Reinforcement
a. Adequately secure with tying wire or approved steel clips.
Concrete Cover
a. Shall be in accordance with ISI: 456- and as per the instructions in structural
drawings.
b. Provide spacer bars of same diameter as longitudinal bars but not less than
25mm diameter between two layers at 1.5 mm centers except where bundled
bars are detailed.
Precautionary Measures
a. Do not insert bars into placed concrete.
b. Do not damage forms and form linings, if any when fixing reinforcement.
b. Ensure that reinforcement is clean and free from corrosive pitting, loose rust,
loose mill scale, oil and other substances, which may adversely affect reinforcement
concrete or the bond between the two.
c. Protect the projecting reinforcement from weather where the rust staining of
exposed concrete surfaces may occur.
Measurements
Reinforcement shall be measured as follows:
Length of different diameters of bars actually used including laps shall be
measured nearest to a centimeter and their weights calculated as shown on the
drawings or as instructed by the Structural Consultant
Weights per meter shall be as mentioned
Rolling margin to be considered in quoted rates.
The Contractor shall account for all these in its quoted rate.
Rate build-up shall include, in addition to cost of material (ie will not be
measured and paid for separately):
- Cutting, bending, placing and fixing in position in any size and shape and
placing in position as per detailed drawings
- Binding wire as approved (will not be measured and hence not paid
separately)
- Wastage
Approved Makes
4.0 Formwork
Design and construction shall be executed and supervised by fully qualified personnel.
In accordance with quality assurance programme, the Contractor shall provide the
Consultants / Project Manager/Client with information demonstrating that a system will
be used to ensure that the work carried out under this section (including that done by
sub-Contractors) will comply with the requirements of the specifications.
4.5 Formwork
Related Work
Concrete Form Work
Concrete Reinforcement
a. Supervisory staff shall have qualification and experience in the above field.
Formwork system shall be executed and designed by a specialist qualified to the shapes,
lines, forms and dimensions shown on drawings. The Contractor shall submit to the
Project Manager/Client a method statement backed by design calculations. Required
drawings and sketches shall be enclosed along with the statement for the proposed area
to be taken up for working at a time. The number of repetitions expected, type of
material used, etc shall be detailed therein.
Formwork shall start only after written approval from the Project Manager/Client &
Structural Consultant has been received. Approval of the proposal in submitted form an
acceptance of modification does not relieve the Contractor of its obligation to achieve
its required line finish within accepted tolerance limits in terms of quality of works
completed and safety. Neither will it diminish the Contractor’s responsibility for the
satisfactory performance of formwork.
b) Formwork system shall be of 12mm thick water resistant Ply board, and
shall be continuous, straight and without any warping.
Height of pour
Thickness of member
Rate of pour
Concrete slump
Texture of finish
Technical Specification Page 68
Placing temperature
Concrete density
Construction joints
Wind load
Method of Discharge
Dimensional tolerance
De mountable without shock, disturbance or damage to concrete
A portion remaining within the concrete shall be at least 38mm from the
outer concrete surface.
That will not leave a hole larger than 25mm dia meter on the concrete
surface.
All propping and centering shall be of adjustable steel supports (built-up sections of
rolled steel) and tubular props to full height without joints, and with sufficient bracing to
take into account the construction loads, namely full load of concrete with any live load
and impact load likely to occur during concreting.
4.9 Workmanship
Formwork shall be classified based on the ultimate finishes required of the concrete
surface as:
Textured or decorative finish
Fair-faced finish
Rough finish
The Contractor shall account for all material and labour to achieve the above finishes to
the satisfaction of the Project Manager/Client in his quoted price.
Following are a few points as guidelines for good workmanship in formwork and shall be
accounted for in his quoted price.
Supports shall be firm and maintained in position by nails, cross bracing, tie-rods,
locking bolts, nuts, etc. It shall be rigid and stiff so as to retain its shape during and
after concreting.
Joints shall be water-tight and no cement slurry shall be allowed to get through
Props shall be of steel only. Its spacing shall be as per design. It shall be vertical
and plumbed. Base shall be of proper steel plate or timber plank for equal
distribution of load
At the design and erection stage following additional points shall be considered
and be incorporated into the setting
Pouring points shall avoid high drops and provide easy access to vibrating needles
Surfaces shall be treated with suitable releasing oil or emulsion prior to the
reinforcement laying. Such releasing oil shall be got approved from the Project
Manager/Client.
Ensure that forms and adjacent surfaces are thoroughly cleaned to receive
concrete and debris.
Joints of formwork shall be watertight. It is easy to check from the bottom and
make sure no light is visible
Props shall be on solid base, plumbed, in straight line, braced horizontally and
cross
Tie-bars, bracing and spacers in beams, walls and columns shall be at correct
place/location and fully tight
Wedges shall be fully secured and nailed with heads left out for easy removal
All saw dust, dirt, shavings and any other unwanted material shall be cleaned and
hosed out
Provision shall be made for watching formwork while concreting and any other
platform needed for movement of workers without any disturbance to the
reinforcement
Provision is made for traffic on formwork: not to bear directly on reinforcing steel.
- To smooth concrete where fins and other projections have formed moisten
concrete surface within a day after forms have been removed and rub with
carborundum brick until surface is a uniform colour and texture within the
projection limits.
Surface defects shall include colour and texture irregularities, cracks, spills, air
bubbles, honeycombs, rock pockets, fins and other projection on the surface, stain
and form tie holes.
- Fill small holes and irregularities using 2:1 (Portland cement to fine sand by
volume) grout mixed with approved bonding admixture according to
manufacturer’s specification.
- Blend standard Portland cement with white Portland cement if necessary so that
final colour of dry grout will match adjacent surfaces.
- After applying grout to repair area, wipe with Hessian cloth to match adjacent
texture and within the specified surface tolerances.
- Keep concrete patch damp with fog *spray for at least 36 hours.
4.11 Measurements
Formwork shall be measured as the area (in square meters) of shuttering in contact with
the concrete including covers, angles, splays, mitres, bevels, etc. for which no special
rate shall be allowed.
It shall be measured to the nearest centimeter and the area worked out correct
to two decimal places
Lapping of formwork with previously laid out concrete will not be measured and
will not be paid for.
The quoted rate shall be applicable for all working conditions and at all heights
and depths or lifts specified in the drawings. The rate shall include the cost of
materials and labour for various operations involved including, but not limited to
the following:
Holes to be made in the formwork for inserting electrical conduits, piping for
plumbing works, etc
Temporary openings in the forms for pouring concrete and removing rubbish.
Raking or cutting.
Fixing inserts and openings at the correct line and level and at any stage to
support the same at the directed height and place.
Cleaning and washing of the complete floor during and after concreting to avoid
any damage to finished surface. It will be responsibility of the Contractor to
protect and retain all finished surfaces.
Should there be any laitance due to concreting of upper floors or other construction
activities within the said floor the Contractor shall be responsible to do all that is
required to bring the finish back to the original or as specified in the Technical
Specification/ directed by the Project Manager/Client.
No payment shall be made for temporary formwork used in concreting nor for
formwork required for joints or buttheads, in floors or elsewhere whether such joints
are to be covered late with concrete or mastic or other material.
4.12 Tolerances
Tolerance is a specified permissible variation from lines, grades or dimensions given in
drawings. No tolerances are specified for horizontal or vertical encroachments beyond
In the lines and surface of columns, walls, and other vertical members, viz inside
face of lift shaft, etc. 3 mm per 3.0 meter but not exceeding 10mm for the full height
of the building.
Variation of the linear building lines from established positions in plan and related
position of columns, wall and partitions
In bay up to 5 m maximum 5 mm
In 10 m or more 10 mm
(ii) Eccentricity in plan: 0.02 times the width of the footings in the direction of
deviation but not more than 50mm
Variation in steps
In a flight of stairs Risers Treads
In flight of stairs 3 mm 5 mm
In consecutive steps 1.5 mm 3 mm
All the tolerances mentioned above shall apply to concrete dimensions only, and not to
positioning of vertical steel or dowels.
Formwork shall be removed carefully without jarring the concrete and curing of
the concrete shall commence immediately. Sudden shocks / vibrations during
removal of wedges shall be avoided. Where finished edges have re-entrant angles,
remove formwork as early as possible to avoid shrinkage cracks.
Where concrete requires plastering or other finish later, the concrete surface shall
be hacked as directed.
For other cements the stripping time shall be suitably modified in consultation with the
Project Manager/Client.
Striking of Formwork within the time limits listed above is subject to successful crushing
of cubes compressive strength results. However re-shuttering and re-propping can be
done if the required strength is attained as per the instructions of Structural Consultant
/ Project Manager/Client.
The surface of the forms to be in contact with the concrete shall be coated with a
reliable coating that will effectively prevent the adherence of concrete and will not stain
the concrete surfaces. After each use, the surfaces of forms which have been in contact
with concrete shall be cleaned of mortar and any other material sticking to them, then
well wetted and treated with form oil approved by the Project Manager/Client.
The Contractor shall provide commercial form release agent that will not bond with,
stain or adversely affect concrete surfaces and will not impair subsequent treatment of
concrete surfaces.
Contractor shall provide all required openings, pockets, inserts as detailed in drawings.
The Contractor shall provide required material and labour for fixing and supporting
during concreting. In its quoted price, it is imperative to consider that all openings and
pockets shall be de-shuttered with care and all corners of openings shall be preserved,
ie shall be in correct line and level. After concreting the openings shall be secured
against any accident by proper covering and guard rail, warning notice, lighting, etc for
which no extra cost is payable to the Contractor.
5. Structural Steel
General
Description
Related Work
Applicable Standards
IS-456-- Code of practice for plain and reinforced concrete (third revision)
IS-814 - Covered electrodes for metal arc welding of structural steels: 814 (Part
1)-1974 Part 1 for welding products other than sheets (fourth revision)
IS-816-- Code of practice for use of metal arc welding for general construction in mild
steel (first revision)
IS-817-- Code of practice for training and testing of metal arc welders (revised)
IS-819-- Code of practice for resistance spot welding for light assemblies In mild steel
IS-962-- Code of practice for architectural and building drawings (first revision)
IS-1148-- Hot-rolled steel rivet bars (up to 40 mm diameter) for structural purposes
(second revision)
IS-1278-- Filler rods and wires for gas welding (second revision)
IS-1323-- Code of practice for oxy- acetylene welding for structural work in mild steel
(revised)
IS-1363- Black hexagon bolts, nuts and lock nuts (diameter 6 to 39 mm) and
black hexagon screws (diameter 6 to 24 mm) (first revision)
IS-1364-- Precision and semi-precision hexagon bolts, screws, nuts and lock nuts
(diameter range 6 to 39 mm) (first revision)
IS-1477 - Code of practice for painting of ferrous metals in buildings: 1477 (Part
1)-1971 Part 1 Pretreatment (first revision)(Part 2)-1971 Part 2 Painting
IS-4000-- Code of practice for assembly of structural joints using high tensile friction grip
fasteners
IS-5369-- General requirements for plain washers and lock washers (first revision)
IS-6419-- Welding rods and bare electrodes for gas shielded arc welding of structural
steel
IS-7280-- Bare wire electrodes for submerged arc welding of structural steels
IS-8500-- Weld able structural steel (medium and high strength qualities)
a. Shop drawings for trusses, bracings, purlins, columns, ties, base plates, crane girders,
etc.
b. Indicate profiles, sizes, spacing and locations of structural members, connections,
attachments, fasteners, cambers, loads and designs of joints.
c. Indicate welded connections using standard welding symbols and net weld lengths.
d. Indicate the method of erection, shop and field joints.
e. Indicate and identify all transportable parts and sub assemblies, associates with
special erection instructions, if any.
f. Provide design calculations for splices, joints, other details not specifically detailed in
design drawings on fabrication drawings considering standard detailing practices
and developing full member strengths.
g. Submit 3 sets of shop drawings to Project Manager/Client for approval.
h. Allow three weeks for Project Manager/Client to approve Shop Drawings.
Materials
All metal materials shall be free from defects impairing strength, durability and
appearance and they shall have structural properties that comply fully with the
standards set. All ferrous metal shall be free from rust, scale and other defects. All non-
ferrous metal shall have uniform finished surfaces, machined and buffed, free from
defects. All sections shall conform accurately to sizes and shapes required.
Fabrication
Finish
Clean, prepare and shop rime structural steel members. Do not prime surfaces to be
field welded or bolted or in contact with concrete.
Execution
a. Proper jigs and fixtures shall be used to ensure correct positioning of structural
members during assembly.
b. Sharp edges, rusting of cutting edges, notches, irregularities, and fissures due to
faulty cutting shall be chipped and ground.
c. Edge preparation for welding shall be done properly taking care of cleaning,
providing dry surface, removing grease, dust or dirt, foreign matter, etc.
d. Finished dimensions of structure shall be ensured after taking into account the
shrinkage and distortions during welding.
Welding
Personnel:
a. Welders shall be fully trained, experienced and certified by the recognized welding
institutes.
b. Welders’ qualification tests shall be as per ASME SEC IX and approved by Project
Manager/Client.
Execution:
f. Before welding a second layer over the existing layer of weld, the layer shall be
cleaned metal bright by light chipping and wire brushing.
g. Execution shall proceed in strict compliance with Section 2/ 7 Safety Procedures.
Approval:
Bolting
Material
a. Bolts, nuts shall be in accordance with IS 1367 and tested as per IS 1608.
Preparation
a. Members shall be assembled for bolting with proper jigs and fixtures to sustain the
assemblies without deformation and bending.
b. All sharp edges, shavings, rust, dirt, etc. shall be removed before assembly.
c. Before assembly the contacting surfaces of the members shall be cleaned and given
a coat of primer.
d. Temporarily the assembly shall be done and checked for co-axiality of the holes after
which the assembly shall be finally bolted.
Execution
Identification
Structural members prior to dispatch for erection shall be marked with a weather
proof light coloured paint. The size and thickness of members shall be so chosen as
to facilitate easy identification.
Structural members small in size shall be bundled or crated and shall be marked with
metal tags for bundles and painted on crates for identification with particulars of the
bundle / crate size, weight, etc.
Shop - approvals
Pre Assembly
Pre assembly of bolted structures shall be done for all elements as well as for the
entire structure in conformity with the 'holes for field joints'.
Steel structures having same type of welding the shop test pre assembly shall be
performed at least one member out of ten members.
Inspection
b. Project Manager/Client shall have the access to the fabrication shop at all times for
satisfying himself regarding the fabrication of steel items to the drawings and
specifications.
d. Contractor to bear all the expenses for testing required by the Consultants / Project
Manager/Client for satisfying regarding the quality of workmanship.
Approvals
Intermediate approvals
b. For part of the work that will be difficult to perform inspection and even if done
results are not satisfactory.
Partial approvals
a. To the structural steel members and assemblies before the primer coat is applied.
b. of materials used for fabrication.
c. of test erection.
d. of markings.
e. of fillet joints.
f. of plain surfaces.
g. of special features such as rollers, etc.
Final approval
a. To all elements and assemblies of steel structures after having a shop primer coat
and ready for delivery.
b. Includes partial approval
c. Of shop primer coat.
d. Of mode of loading and transport.
e. Of storage of materials.
All metal work fabricated shall be approved by the Structural Consultant / Project
Manager/Client. The entire work shall be carried out by workmen skilled in this kind of
work in a shop fully equipped to carry out all phases of fabrication in accordance with
the best-accepted trade practices.
Painting
Preparation:
a. Surface to receive primer coat shall be sand blasted free of dust, oil, rust,
etc.toSA2.5 grade
b. Surfaces not accessible to painting shall be filled with approved type of oil and
putty.
g. After satisfying the above criteria the surfaces are to be provided with one coat of
red oxide / zinc chromate primer to the satisfaction of Project Manager/Client
before the material is dispatched for erection.
d. Planned surfaces shall receive a coat of hot oil or any approved resistant lubricant
only.
f. To give a coat of cement wash for any members either embedded or in contact
with concrete.
g. To give a bituminous coat for members in contact with ground, gravel, brickwork
and moisture.
h. Contractor to give a further coat of red oxide paint after erection and placing in
position of the assembly if called for by the Project Manager/Client.
a. Structural steel members shall be marked and approved in shop before packing
and loading for transportation.
b. Adequate packing must be done for all the steel members to protect them against
warping during loading and unloading.
g. To secure all small parts including gusset plates fish plates by securing them with
wire to their respective parts.
i. All structural parts to be delivered in the order required for construction and as
per instructions of Project Manager/Client and shall accompany the following
documents.
- Description of structure
- Identification number
Building/job symbol
a. Place for storage of steel member shall be prepared in advance and got approved
by the Project Manager/Client.
b. To provide concrete platform at the site for preliminary erection work.
c. To verify the quality of material obtained at site and for workmanship to the
specifications and drawings.
d. To verify whether the parts obtained at site is free from defects due to loading,
unloading transportation.
e. To avoid warping of members during unloading by taking sufficient precautionary
measures.
f. To store the members as per the symbol and markings and in order of erection.
g. To place the steel members at least 150mm above the platform on wooden or
steel locks for protection against direct contact with ground and to permit
drainage of water.
h. To equip for rectification of members like straightening at site and to provide
sufficient space for the same.
i. To see that the parts are clean before erection.
Field Erection
2. Alignment of structure.
3. Erection sequence
4. Progress
5. Workmanship
c. To position and level the structure including aligning and to plumb the stanchion and
fixing every member in position with bolts, erection bolts, weld as per design and
drawings.
f. Contractor to rectify any minor deviations in foundations, location of steel bolts and
orientation of bolt hole positions at no extra cost.
h. To anchor and fasten the erection joints after duly checking the plan, elevation
positions of the members with reference to the drawings after the approval of
Project Manager/Client.
i. To fasten bolts to the final position with bolt heads and nuts resting on the member
and on tapered washers with members having a sloping surface.
a. Contractor to submit As-built shop drawings for the approval of the Structural
Consultant / Project Manager/Client, as per the stipulation given in Conditions of
Contract.
Measurements
a. Payment of structural steel members including bolts, nuts, washers, gusset plates,
etc., will be done on weight basis.
b. The weight of members will be assessed from the final fabricated and approved
drawings and the respective Bill of Materials prepared by the Contractor and
approved the Structural Consultant / Project Manager/Client.
f. Built up of members will be paid as per the actual weight of the members.
g. Gusset plates shall be paid to the nearest rectangle enclosing the shape and no
deduction shall be made for any skew cuts.
h. Welds, bolts, anchors, washers, etc will not be measured and paid for separately.
i. Payment do not include any other related temporary works connected with this
work including welds, shims, wedge plates, etc.
k. Rate to include necessary scaffolding, temporary support, tool and tackles, touching
up primer coat grouting etc.
Grouting
a. To level, align and plumb the structural steel work and the base of stanchions by
providing steel shim plates.
b. To align anchor bolts in foundation to the required level, location and orientation
by using templates.
e. To use grade M 30 concrete to fill up the grout pockets left for fixing anchor bolts.
f. To pour the grout under a sufficient head and tam until the voids are thoroughly
filled and the grout overflows.
Tolerances
b. For structural steel for plumb 3.5mm for 10M and not more than 7mm for 30M
d. To provide tolerances for all structural steel members as per IS code other than
what is mentioned in a, b and c.
Inspection of weld All welds Naked Eye or Lens All faulty welds shall be
seam rectified
Performance &
electrodes
ANNEXURE - B
C = ±1mm
A) Depth weld
Chisel & grid
Below . – flat holded post – tensioning system shall be adopted the processing shall
consist of stands of 12.7 mm ( 0.5 “) dia and contained in a flat sheet metal duct.
Each strand is anchored by means of a barrel and wedge and individually stressed by
means of a nonstrand jack, which occupies limited space. The pre – stressing force is
transferred to the concrete by a flat anchor plate casting . By use of flat duct the static
depth of slab is more efficiently utilized compared to a round duct for same number of
strands.
6.2 Sheathing
The sheathing ducts shall be of the spiral - corrugated type. Unless otherwise specified ,
the material shall be Cold Rolled Cold Annealed (CRCA) Mild Steel conforming to IS 513
intended for mechanical treatment and surface refining but not for quench hardening or
tempering. The material shall be bright finished. The thickness of sheathing shall be
shown on the drawing, but shall not be less than 0.3 mm.
The sheathing ducts shall be manufactured at the project site using appropriate
machines or in the factory and dispatched to site as per suitable programme so as to
minimize period of site storage. Where sheathing duct joints are unavoidable, such joints
shall be made slurry tight by the use of corrugated threaded sleeve couplers, which
may be lightly screwed onto the outer side of the ducts.
The length of the coupler shall not be less than 150 mm but should be increased up to
200 mm wherever practicable. The joints between the ends of the coupler and the duct
shall be sealed with adhesive sealing tape to present penetration of cement slurry
during concreting. The couplers of adjacent ducts should be staggered wherever
practicable . As far as possible, couplers should not be located in curved zones.
The finished duct shall be flattered to form an oblong section out of the round pipes by
a suitable machine . The size of the flat duct shall be 70 mm x 26.2 mm for 405 size
anchorages (4 nos. of 0.5” strand )
All bearing surfaces of the anchorage shall be cleaned prior to concreting and
tensioning . Anchor cone shall be securely positioned and maintained during concreting
such that the centerline of the duct passes axially through the anchorage assembly. The
anchorages shall be recessed from the concrete surface by minimum cover of 100 mm or
as per construction drawings which ever is higher.
At the fixed end of tendon, Cona – flat loop anchorage for 405 shall be supplied as per
system supplier’s detail.
6.4 Strand
12.7 mm ( 0.5”) dia HT strand shall conform to class 2 of IS : 6006. The normal cross –
sectional area of the 7 ply 12.7 mm dia strand shall be 98.7 mm2 with minimum breaking
load of 183.7 KN rest certificate of manufacturer shall be supplied along with each lot
dispatched to site.
6.6 Straightening.
High tensile steel strand shall be supplied in coils of sufficiently larger diameter such
that tendon shall retain their physical properties and shall be straight as it unwinds
from the coil. Tendons of any type that are damaged , kinked or bent shall not be used.
The packing of pre- stressing strand shall be removed fast prior to marking of cable for
placement in ducts. Proper platform shall be provided to facilitate uncoiling of strand
without damage to steel. Care shall be taken to avoid the possibility of the such coming
into contact with the ground.
Sheathing shall be placed in correct position and profiles suitable ladders / spacers made
from 4 or 5 mm dia rod may be provided at intervals of approximately 1.0 m. Sheathing
shall be tied rigidly with such ladders / spacers bars so that they do not get disturbed
during concreting. The method of supporting and fixing shall be such that profile of
cables is not disturbed during vibrations, by pressure of wet concrete, by workmen or by
construction traffic. Where possible tendons shall not be handled with care to avoid
damage or contamination to either the tendon or the sheathing. Any tendons damaged
or contaminated shall be replace.
If Alternate Code is being planned to be used, copy of the code is to be submitted and any
deviations from IS code to be highlighted.
Material:
Additional Precautions
It is proposed that the strands are permanently anchored in concrete during casting.
The post tensioning force (actual) must be limited in such a way that accidental breaking of strand is
catered for.
Additional stresses during concreting of upper slab shall be considered to enable no back
propping of second or subsequent lower levels slabs beneath concreting slab.
Approvals:
Designs to be submitted to consultants for their approval and perusal much before actual
commencement of works at site.
Design in soft /hard copy to be submitted to consultants and if required to forward and
support to the local authorities for approval.
A copy of the stress details done at site shall be submitted to consultants for their perusal.
Co-ordination with consultants, architects, project managers, civil contractor and PMC team
is required at all times.
Final as built drawings to be submitted to consultant’s incl .soft and hard copies.
6. Miscellaneous Works
6.1. Anti Termite Treatment
The treatment shall be carried out generally in accordance with the stipulation laid
down by IS 6313 - Part II latest edition (Code of practice for anti termite measures in
6.4. Application
The chemical solution shall be prepared by mixing the chemical with the appropriate
quantity of water to obtain a chemical emulsion of the correct concentration as
stipulated above. The prepared emulsion shall be applied as described below.
In the case of RCC walls and columns, the treatment shall start at the depth of 50 cm.
below natural ground level.
From this depth the back fill around the RCC columns, walls, etc., shall be treated at the
rate of 15 ltr/m2 of the surface.
1.9 Measurements
The measurements shall be made in square meter on the basis of plinth area of the
building at ground floor only for all operations described in schedule of quantities.
Nothing extra shall be measured.
The rate shall include cost of all material and labour involved in all operations
described above.
1.11 Guarantee:
On completion of the treatment in all respects, a guarantee that the building is safe
from subterranean species of termite infestation for a period of 10 years is required
on stamp paper in a format which shall be approved by the Client who shall have the
final decision.
In the event of re-infestation of the said structure at any time during guarantee
period, an undertaking is required to carry out such treatment as may be necessary to
render the structure free from termite infestation without any extra cost including any
remedial work, resulting sleeves, cutout etc.
The Contractor shall further provide the following information concerning each
admixture to Consultants.
Whether or not the admixture leads to the entrainment of air when used in the
manufacturer’s recommended dosage.
Where two or more admixtures are proposed to be used in any one mix, the
manufacturer’s written confirmation of their compatibility.
In reinforced concrete, the chloride iron of any admixtures used shall not exceed 2
percent by weight of the admixtures in accordance with IS 6925 and the total
chloride iron in all admixtures used in concrete mix shall not exceed 0.03 % by
weight of cement
The admixtures when used shall conform to IS 9103 “The suitability of all
admixtures shall be verified by trial mixtures”.
The addition of calcium chloride to concrete containing embedded metal will not
be permitted under any circumstances.
1.13 Grouts
1.13.1 Grouting
The base plate shall be temporarily supported on steel wedges and properly
aligned before grouting. Forms shall be built around the base and wet mortar shall
be placed under pressure around and under the base. To ensure that no air
pockets are left after grouting additions holes may have to be cut if directed in the
base plate so that pressure grouting can be carried out thorough these holes also
and proper inspection of the grout can be ascertained. The wedges shall be
removed after the grouting has set and recess shall be properly pointed.
Grouting of machine foundations shall be done only after taking the written
instructions form the Consultants / Project Manager/Client.
The grouting work is included in the respective item of concrete and the rate for
these items and inclusive of proper pressure grouting after preparations of
surfaces to be grouted, necessary form work providing and removing necessary
wedges, cutting holes in the base plate to ensure that the air pockets are left etc.
No extra rate will be paid for grouting or any work that will be necessary to carry
out and ensure proper grouting entirely to the satisfaction of the Consultants /
Project Manager/Client. If however a concrete mix richer than the foundation is
specified for grouting, only the difference of the quantity of cement used in richer
mix of grout and the mix of the footing shall be paid.
General
Exposed precast surfaces shall be finished as called for on the drawing or as directed
by the Consultants / Project Manager/Client. All surfaces coming in contact with in
situ concrete shall be wire brushed and hosed down until the aggregate is free from
cement slurry. Castellation shall be provided wherever called for. Leaving grouting
holes, grooves, inserts, projections reinforcements, lifting hooks etc., to conform to
the erection procedure. All edges and delicate projection likely to be damaged during
erection shall be protected by means of wooden cover fillets, until placed in position.
All precast jali shall be exactly of the size and pattern shown on the drawings and shall
be made face up in the following manner. All units shall be integrally cast, steel
formwork shall be used for making jalis.
Stiff plastic concrete 1:1.5:3 shall be used with coarse aggregate 12mm and down size.
The precast units shall not be removed from the forms for three days. Precast work
shall be cured under cover and shall be kept under water for fifteen days before
placing in position.
Unit may require wetting before bedding. The concrete base shall be wetted and
coated with slurry and minimum of mixing water shall be used in the bedding mortar,
which shall be Portland cement and sand 1:3.
The section shall apply also to prestressed precast controlled concrete work.
For all precast controlled concrete work a specially equipped site factory, with casting
yard, pre-tensioning beds of individual moulds for vibrating plants, cement store,
concrete laboratory erection equipment, etc., are to be provided. The Contractor is
deemed to have included in his rates all the above provisions needed for a workman
like construction in precast controlled concrete. All precast design mix concrete shall
be weigh batched.
All precautions in handling and placing of high strength concrete mixes apply. The
concrete placed shall be compacted thoroughly by using pin, vibrators, shutter
vibrators or other suitable means. No construction joints shall be allowed in precast
design mix concrete work. Un-shuttered top surfaces are to be finished smooth with
trowel.
During the period of initial setting special precautions are to be taken to keep precast
members sufficiently moist to protect them against vibrations and any adverse loading
1.15 Waterproofing
Alternatives
Related Works
Material
e. Brick bats
Execution
Box Method
A. Basement
a First layer shall be laid after cleaning, brushing the PCC layer/ blinding concrete.
b. First coat of waterproof plaster is done with CM 1:3 & approved waterproofing
admixture as per manufacturer’s specification to be used with cement and
20mm size aggregates are embedded over the surface evenly. Weight of
aggregates shall be 20kgs/Sqm.
c. Second layer of waterproof admixture mixed mortar shall be applied a day after
the first coat to the thickness of the aggregate.
e. Third layer or finishing coat is done with waterproof admixture mixed cement
mortar and surface is finished smooth. Curing shall be carried out for a
minimum period of 7 days.
f. Total thickness of water proofing layers shall be not less than 50mm.
B. Retaining Wall
a. Shall be done in two layers of waterproof plastering leaving 2 hours gap between
each coat.
f. Back filling shall be done carefully with specified material. Care to take not to
puncture the layer.
C. Roof
Surface Method
Part - 1
b. First coat of bituminous water proof coating (two part highly purified Coal tar
and polyurethane polymer) shall be applied after necessary grouting at
construction joints and honey comb areas with cement grout
d. First coat of bituminous water proof coating (two part highly purified Coal tar
and polyurethane polymer) shall be applied over fabric layer
e. Treatment shall continue along the parapet for a height of 300mm above the
finished level.
Part - 2
b. Cement slurry with waterproof compound shall be provided over the cleaned
surface.
c. Brick coba shall be laid for necessary gradient for easy flow of rain- water
(joints shall be filled with CM 1:1 with water proof compound)
or
d. Metal coba shall be laid for specified thickness and necessary gradient for
easy flow of rain- water with CM 1:1 with waterproof compound
e. Coba to be covered with joint less water proof plaster with CM 1:2 with
water proof compound as per manufacturer’s specification finish shall be
smooth.
b. Toilets: Water proofing for floor shall be of 35mm thick, for walls shall be
25mm thick with CM 1:4
c. For OH Tank and UG Sump thickness of plaster shall be 35mm in two layers
DESCRIPTION OF WORK
QUALITY ASSURANCE
Manufacturer:
Provide products of manufacturers with not less than 10 years of successful
experience in supplying the principal materials for the required work.
The manufacturer shall preferable holder of the ISO 9001:2000 quality certificate
with a validity period of at least two years.
Installation Company:
Before starting the installation the contractor shall deliver a certificate, recognizing
the installation company as an approved applicator.
Before awarding the works, the contractor must present all necessary certificates
that allow the company to perform waterproofing works.
SUBMITTALS
Product Data:
Prior to delivering any waterproofing material the contractor shall submit two copies
of specifications, installation instructions and general recommendations by the
manufacturer of waterproofing materials.
Sample Installations:
Construct sample installations of waterproofing before proceeding with the work. Size
of samples shall be adequate to represent completed work and be retained for the
duration of the waterproofing work as minimum standards.
QA/QC-procedure
All parties concerned will check materials prior to installation.
During the works a QA/QC engineer of the manufacturer will control the works
and carry out inspections.
The applicator needs to provide the proof of its certification by the manufacturer.
All membranes must be stored vertically with the overlap side at the bottom.
Worker’s safety shall be ensured by providing proper access and safety gear.
Completion
The contractor shall deliver a clean site and wastage will be dumped at an
authorized location.
At the delivery of the works, the owner will receive an original and signed 10 year,
insurance-backed warranty for waterproofing and root resistance
A final quality inspection will take place and hand-over documents signed by all
responsible parties
MATERIALS
Waterproofing Membrane:
Primer:
2 Breaking strength:
3 Elongation
Transversal (%) ≥ 45
6 Puncture resistance
Static L3 UEAtc
Dynamic L3
INSPECTION
The Contractor must satisfy himself that satisfactory conditions exist for carrying out
the waterproofing work. Do not proceed with work until unsatisfactory conditions
have been corrected in a manner acceptable to the installer.
INSTALLATION
Preparation
Ground water level needs to be kept under raft concrete level by the contractor.
The raft/lean concrete surface has to be free of standing water, debris and mud.
Details
The details of the waterproofing comprises of material specifications, installation
procedures.
The membrane is either loose laid on the raft/lean concrete. Only the
prefabricated overlaps are torched or fully torched and bonded
The membrane is torched fully bonded to all vertical areas of beams and pile-caps.
The overlap of the head joint is 150mm. Head-overlaps cannot be next to each
other.
A first layer is torched around the member and on top of the PCC. The width of
this reinforcement slab of membrane is 150mm.
On top of the PCC the elastomer modified bituminous membrane with granular
topping shall be placed loose-laid and the pre-fabricated overlaps heat welded.
The top of the membrane is finished at the factory by granules that create a
perfect bonding when the concrete is poured on top of the membrane.
MATERIALS
Waterproofing Membrane:
Primer:
Bituminous, solvent based primer, modified with elastomers.
The technical properties of the membrane shall have or exceed the following
characteristics:
8 g / m² glass-fibre grill
SBS - 20°C
Warranty
The roof waterproofing is covered by an international, insurance backed warranty,
issued to the owner.
The warranty certificate has to mention the insurance policy number and project
data.
INSTALLATION
Preparation
The roof needs a minimum slope of 1%. The slope is achieved prior to the
waterproofing works. In case of a screed to fall, the minimum thickness of the
screed must be 25mm.
Verify that the roof surface is clean, dry, smooth and free of oil and grease.
All complementary items like roof drains, pipes, ducts and vents are solidly set.
Primer
Apply primer at a rate of 300 g/m².
Application
The works need to be done according to the rules of good craftsmanship.
Overlaps will follow the slope of the roof to prevent water stagnation.
Head-overlaps cannot be next to each other. The overlap of the head joint is
100mm.
1.15.5 ROOF GARDEN WATERPROOFING
A. System description
Waterproofing system for areas with vegetation like roof garden or planter
boxes.
Drainage layer with geo-textile covering topped with soil OR Duo Drain,
Tailor made subsoil drainage technology.
C. Warranty
The products and installation needs to be covered by an international,
insurance backed warranty, issued by the manufacturer to the owner.
The warranty certificate has to mention the insurance policy number and
project data.
The warranty covers product defaults and includes the following elements:
o Removal of the default waterproofing.
o product installation
Before awarding the works, the installation company must present all
necessary certificates that allow the company to perform waterproofing
works.
E. Materials
All materials have to be delivered with a certificate of origin of the
manufacturer. This certificate indicates the quantity and type of products.
All waterproofing materials should originate from one and the same
manufacturer.
Or
Fast installation
Lightweight
High water flow capacity
High compressive strength
Simple joints
Flexible
No on-site fabrication
No aggregates required
F TECHNICAL SPECIFICATIONS
Core Properties
Structure - - Non-woven
spunbonded
Material - -
1 x 10
Packing Details
H. Application
Preparation
The planter area needs a minimum slope of 1%. The slope is achieved prior to
the waterproofing works. In case of a screed to fall, the minimum thickness
of the screed must be 25mm.
Verify that the concrete surface is clean, dry, smooth and free of oil and
grease.
Treat honeycomb areas prior to the start of the waterproofing works.
All complementary items like floor drains and scupper drains are solidly set.
Primer
Apply primer at a rate of 300 g/m².
Allow the primer to dry for at least 4 hours.
Waterproofing
The works need to be done according to the rules of good craftsmanship.
Inclusion of humidity must at all times be avoided.
The concrete receives the primer and is allowed to dry.
The membrane is torched fully bonded to the concrete roof slab.
Side-overlaps shall be min 70mm. Head overlaps are 100mm
Head joints cannot be next to each other.
I. Completion
The contractor shall deliver a clean site and wastage will be dumped at an
authorized location.
At the delivery of the works, the owner will receive an original and signed 10
year, insurance-backed warranty for waterproofing and root resistance.
Optional Method
RCC surface to be cleaned, brushed and watered. Water stagnation test shall be done
for terrace slabs. RCC surface shall be Coated with compatible Multiplas primer / Cold
sticker / Multiplas blown bitumen of grade 85/25 or 90/15. Waterproofing treatment
with polymeric standard waterproofing membrane of 4kg/Sqm or 4mm thick
(Multiplas standard) shall be provided as per the manufacturer's specification
approved by Clients with an over lap of 10cms.Then membrane shall be bound by
torch application with 10cms overlap where required. Topping shall be done with
laying of 10mm thick thermo Cole sheet with necessary adhesive / hot blown bitumen.
Over thermo Cole sheet brick coba /Grano concrete / Lightweight concrete shall be
laid to slope and curing shall be done.
7. Weathering Thermoplast
Resistance ic material
Option - 2
Expansion joints shall be provided with 20 gauge copper strips/m.s. hot dip
galvanized strips of 250 mm width at locations shown on drawings or as approved by
Consultants / Project Manager/Client. The strips shall be bent to the shape
indicated on the drawing and embedded properly in masonry. The joint width shall
be uniform throughout and special care shall be taken to ensure proper bonding at
expansion joints. Expansion joints shall be continuous and where two or more strips
meet, they shall be lapped to the extent of 75 mm and joints properly soldered. The
expansion joints shall be filled with pre moulded joint fillers and sealed with mastic
compound. For purposes of measurement, the laps provided will be neglected.
Wherever an expansion joint between the existing part and new part is proposed
the rate quoted shall be inclusive of making necessary connections with existing
part.
1.15.6.4 Flashings
Metal or tar felt flashing shall be fixed as directed by the Consultants / Project
Manager/Client. Metal flashing where provided shall be welded/ soldered to obtain
continuity. Tar felt flashing shall be lapped for a minimum length of 150 mm.
Flashing shall be measured and paid for in linear meters for the specified width
disregarding laps or joints.
1.15.7.1 Material
The raw elastomer content of the compound shall not be lower than 60%. The ash
content shall not exceed 5% (as per test conducted in accordance with ASTM D-297)
Properties of Elastomer
The elastomer shall conform to all properties specified in the following table.
% IS : 3400 (Part X)
Duration Temperature
(h) (C)
Shear modules of the elastomer bearing shall not be less than 0.8Mpa nor greater
than 1.20Mpa.
The adhesive strength of elastomer to steel plates (determined as per IS 3400: Part
XIV method A) shall not be less than 7 kN/m
The thickness of all internal layers of elastomer "hi" shall be as specified in the Bill of
Quantities.
Thickness of outer layers shall be he = hi/2 subject to a maximum of 6mm and side
cover shall be 6mm for all bearings.
Elastomer bearing shall satisfy the criteria enumerated in Clause No. 916.3.3,
916.3.5 & 916.3.6 of IRC 83 (Part II) – 1987
1.15.7.3 Fabrication
Bearing with steel laminates shall be cast as a single unit in a mould and vulcanized
under heat and pressure. Casting of elements in separate units and subsequent
bonding is not permitted nor shall cutting from large size cast be permitted.
Bearings of similar size shall be produced by identical process and in one lot as for as
practicable.
Steel plates for laminates shall be sand blasted, clean of all mill scales and shall be
free from all contaminates prior to bonding by vulcanization. Rusted plates with
pitting shall not be used. All edges of plates shall be rounded.
The bearings shall be fabricated with the tolerance specified in the following table.
Sl No Items Tolerances
3. Parallelism
The moulding dies utilized for manufacturing the bearings should be so set inside
the platen of the press so that the pressure development during vulcanization of the
product is evenly distributed and the thickness maintained at all places is within
acceptable tolerance limits taking into consideration, the shrinkage allowance of
vulcanization.
The raw compound which has been introduced inside the metal dies for
vulcanization should be accurately weighed each time and it must be ensured that
sufficient quantity has been put inside the die for proper flow of material at every
place so that a homogeneous and compact bearing is produced without any sign of
sponginess or deficiency of material at any place.
Before any vulcanization of any batch of production is used for producing vulcanized
bearings, test pieces in the form of standard slab and buttons should be prepared in
accordance with prescribed standards and salient properties tested and recorded
regularly against each batch of production to monitor the quality of the products.
1.15.8.1 The manufacturer shall certify for each lot of bearing under acceptance:
a. That an adequate system of continuous quality control was operated in his plant.
b. That the entire process remained in control during the production of the lot of
bearings under acceptance as verified from the quality control records / charts
which shall be open to inspection of the Consultants / Project Manager/Client on
demand.
5.21.8.2 A certified copy of the results of process control testing done an samples of
elastomer used in the production of the lot shall be appended and shall include at
least the following information.
Classification
Bricks shall be classified on the basis of their minimum compressive strength as given below:
Class Average compressive strength
designation Not less than Less than
N/mm2 (Kgf/cm2) N/mm2 (Kgf/cm2)
7.5(75) 7.5 (75) 10 100
The brick shall have smooth rectangular faces with sharp corner and shall be uniform in colour
and emit clear ringing sound when stuck.
Water Absorption:
The average water absorption of bricks when tested in accordance with the procedure laid
down shall not be more than 20% by weight.
Soaking of Bricks:
Bricks shall be soaked in water before use for a period for the water to just penetrate the whole
depth of the bricks .Alternatively bricks may be adequately soaked in stacks by profusely
spraying with clean water at regular intervals for a period not less than six hours. When the
brick are soaked they shall be removed from the tank sufficiently early so that at the time of
laying they are skin-dry. Such soaked bricks shall be stacked on a clean place where they are not
again spolled by dirt earth etc.
Laying:
Bricks shall be laid in English bond unless otherwise specified. for brickwork in half brick wall
,brick shall be laid in stretcher bond .Half or cut bricks shall not be used except as closer where
necessary to complete the bond .Closer in such cases shall be cut to required size and used near
the ends of the wall .Header bond shall be used preferably in all courses in all courses
In case of walls one brick thick and under, one face shall be kept even and in proper plane,
while the other face may be slightly rough. In case of walls more than one brick thick, both the
faces shall be kept even and in proper plane.
Care shall be taken during construction that edges of jambs, sills and projections are not
damaged in case of rain. New built work shall be covered with gunny bags or tarpoulin so as to
prevent the mortar from being washed away. Damage, if any, shall be made good to the
satisfaction of the Engineer-in-Charge.
Finishing of Joints:
The face of brick work may be finished flush or by pointing. In flush finishing either the face
joints of the mortar shall be worked out while still green to give a finished surface flush with the
face of the brick work or the joints shall be squarely raked out to a depth of 1 cm while the
mortar is still green for subsequently plastering. The faces of brick work shall be cleaned with
wire brush so as to remove any splashes of mortar during the course of raising the brick work.
In pointing, the joints shall be squarely raked out to a depth of 1.5 cm while the mortar is still
green and raked joints shall be brushed to remove dust and loose particles and well wetted,
and shall be later refilled with mortar to give ruled finish. Some such finishes are ‘flush’,
‘weathered’, ruled, etc.
Curing
The brick work shall be constantly kept moist on all faces for a minimum period of seven days.
Brick work done during the day shall be suitably marked indicating the date on which the work
is done so as to keep a watch on the curing period.
Scaffolding
Scaffolding shall be strong to withstand all dead, live and impact loads which are likely to come
on them. Scaffolding shall be provided to allow easy approach to every part of the work.
Single Scaffolding:
Where plastering, pointing or any other finishing has been indicated for brick work, single
scaffolding may be provided, unless otherwise specified. In single scaffolding, one end of the
put-logs/pole shall rest in the hole provided in the header course of brick masonry. Not more
than one header for each put-log/pole shall be left out. Such holes shall not be allowed in the
case of pillars, brick work less than one metre in length between the openings or near the skew
backs of arches or immediately under or near the structural member supported by the walls.
The holes for putlogs/poles shall be made good with brick work and wall finishing as specified.
Measurements
Brick work shall be measured in cubic metres unless otherwise specified. Any extra work over
the specified dimensions shall be ignored.
Note : (i) Brick work in parapet walls, mumty, lift machine room and water tanks constructed on
the roof upto 1.2 m height above roof shall be measured together with the corresponding work
of the floor next below.
Rate
The rate shall include the cost of materials and labour required for all the operations
This specification covers the general requirements for the materials and construction of soling,
water bound macadam course and bituminous surface treatment of roads.
(part 1 to 3)
IS : 1834 : Specification for Hot Applied Sealing Compounds for Joint in concrete.
IRC : 19 : Standard specifications and code of practice for water bound macadam.
Ministry of
Surface trans-
MATERIALS
General
All materials shall be obtained from local sources and shall be subject to Consultants / Project
Manager’s approval prior to use.
Soling Stone
It shall be clean, sound, dense, hard, tough, durable stone of uniform quality free from unsound
material cracks, decay and weathering. Water absorption shall not be more than 5 percent.
The stone shall be in the smallest dimension equal to thickness of the soling course specified
with a tolerance of 25 mm. Soling stone shall be sufficiently flat bedded. The height of the
soling stone shall be equal to the specified thickness of soling. The length and breadth shall not
exceed twice the specified thickness. Contractor to note that available laterite stone of
specified strength at site shall be used as sling material in co-ordination with Project Manager
Stone Aggregatre/Metal
Coarse aggregate, stone chippings shall consist of natural or crushed stone, clean, hard tough,
durable and free from excess of flat, elongated, soft and disintegrated particles, dirt, salt, alkali,
vegetable matter, adherent coatings, organic and other objectionable matter, and shall
conform to the physical requirements given in Tables 1 or 2 hereunder, as applicable.
Aggregate for bituminous wearing courses shall in addition have good hydrophobic properties
i.e. capacity of retaining the film of bituminous material applied to the stone in all weather
conditions and especially in wet conditions. Basalt, dolerite are good in this respect; granite,
quartzite are comparatively poor.
PHYSICAL REQUIREMENTS OF COARSE AGGREGATE FOR WATER BOUND MACADAM (SUB BASE
/ BASE COURSE)
Or
IS:5640***
(***) Aggregates like brick metal, kankar, laterite etc., which get softened in
presence of water shall be tested for impact value under wet conditions in
accordance with IS:5640.
5 Soundness
(**) Requirement of flakiness index shall be enforced only in case of crushed broken stone.
The coarse aggregate for water bound Macadam shall conform to one of the
gradings given in Table-3 below:
TABLE – 3
1 90 mm to 45 mm 125 mm 100
90 mm 90 – 100
63 mm 25 – 60
40 mm 0 – 15
22.4 mm 0–5
2 63 mm to 45 mm 40 mm 100
63 mm 90 – 100
53 mm 25 – 60
45 mm 0 – 15
22.4 mm 0–5
3 53 mm to 22.4 mm 63 mm 100
53 mm 95 – 100
45 mm 65 – 90
22.4 mm 0 – 10
11.2 mm 0–5
Screenings shall conform to the gradings set forth in table-4. Screenings of Type-A in Table 4
shall be used with coarse aggregate of grading 1 in Table-3. Screenings of Type A or B, as
TABLE – 4
10.0 mm 90 – 100
4.75 mm 10 – 30
B 10 mm 10 mm 100
4.75 mm 85 – 100
150 micron 10 – 30
The use of screening shall be omitted in the case of soft aggregates such as brick
metal, kankar, laterites etc. as they are likely to get crushed to a certain extent
under rollers.
Binding Material
Application of binding material may not be necessary when the screenings used are of
crushable type such as moorum or gravel.
9.10.2 Gravel shall be composed of large, coarse, silicious grains, sharp and gritty to the
tough, thoroughly free from dirt, organic and deleterious matter. It shall be
hard, tough, dense and shall not contain particles bigger than 12mm and more
than 10% silt.
9.10.3 Sand used for blinding the bituminous road surgace shall be coarse, sharp, gritty,
clean, granular material. Only material passing through 4.75 mm sieve and
retained on 75 micron sieve shall be used.
Bituminous materials shall conform to IS:73, IS:215, IS:217 or IS:454 as applicable and be
of the grade specified in this specification.
9.3 EARTHWORK
9.12.2.1.2 Profiles of road excavation shall be laid at 50m intervals to conform to the required
alignment, sections, grades and side slopes and the lines of cuts shall be clearly
marked.
9.12.2.1.3 Contractor shall on no account excavate beyond the slopes or below the specified
grade unless so directed by the Consultants / Project Manager in writing. If
excavation is done below the specified level or outside the section it shall not be
9.12.2.1.4 The excavation shall be finished neatly, smoothly and evenly to the correct lines,
grades, sections and side slopes as shown in the drawings or directed by Project
Manager.
9.12.2.1.6 The embankment shall be formed of earth obtained from approved source.
9.12.2.1.7 The ground over which embankment is to be formed shall be cleared of all
brushwood, loose stones, vegetation, bushes, stumps, and all other objectionable
mater and materials so removed shall be burnt off or disposed off as directed by
Project Manager. The cost of this clearing, burning and disposal shall be included in
the unit rates quoted for embankment construction.
9.12.2.1.8 Profiles of embankment shall be set up with stout poles to mark the centre and
edges of the formation with the top levels of formation clearly marked by paint or
cut and the slopes with strings and pegs at every 10 meters on straight portions.
Toe line may be marked with pick marks.
9.12.2.1.9 Before placing any embankment materials the top 150mm of soil strata receiving it
shall be scarified and watered and compacted with one pass of 12 T roller.
9.12.2.2 When boulders, broken stones and similar hard materials are mixed up with the
embankment materials care shall be taken to see that they are distributed uniformly
9.12.2.3 If the embankment materials contains less than the optimum moisture, water shall be
added to the loose layers of the embankment to bring the moisture uniformly up to
requirement. If the material contains more than the required moisture if shall be
allowed to dry until the moisture is reduced to the required extent.
9.12.2.4 The moistured /dried loose layers shall be compacted with a power roller of 12
tonnes. The roller shall pass at least twice over the same area, once in the forward
move and the second time in backward move.
9.12.2.5 To allow for subsequent settlement the finished level of the embankment shall be
kept higher than the specified level by one centimeter for every meter of the height of
the bank.
9.12.2.6 Embankment shall be finished and dressed smooth and even to conform to the
alignment, levels, cross sections, and dimensions shown on drawings with due
allowance for shrinkage. Any damage caused by rain or any other reasons shall be
made good in the finishing operation.
9.13.1 Immediately prior to the laying of the soling the subgrade shall be cleaned of all foreign
substances, vegetation etc. Any roots or soft yielding patches that appear shall be
corrected and the subgrade dressed off parallel to the finished profile. The camber of
subgrade shall conform in shape to that of the finished road surface. Camber boards
shall be used to get the required section.
9.13.2 The prepared subgrade shall be lightly sprinkled with water, if necessary, and rolled with
power roller of not less than 12 tonnes, till the soil is evenly consolidated to 95% of
proctor density with 2% variation in optimum 5 runs on the subgrade. Roller shall pass
minimum 5 runs on the subgrade. Rolling shall commence at the edges and progress
towards the centre longitudinally. Each pass of the roller shall uniformly overlap not
less than one third of the track made in the preceding pass. Any undulations in the
9.5 SOLING
9.14.1 Soling shall not be constructed on a wet subgrade with available approved Laterite
stones at site / Approved soling material brought from outside.
9.14.2 Unless otherwise specified, the width of the soling shall be 200mm more on either side
than that of the water bound macadam wearing course and the finished thickness of the
soling course shall be 200mm.
9.14.3 The soling stones shall be laid with the largest face downwards and in contact with each
other. The stones shall break the joint as far as possible. The height of the soling stone
shall be equal to specified thickness of soling.
9.14.4 As the laying of rubble advances the soling shall be hand packed by wedging and packing
with 80 mm metal in the joints of the soling and driving them by hammer in place so as
to fill the voids as completely as possible. This operation of hand packing shall be laid
and had packed true to grade and section and these shall be often checked by boning
rods, template boards and fish line etc. The grades, sections etc. of the soling shall
correspond to those of the surfacing coming on it. The soling thus laid shall be finished
by knocking out projecting stones and filing depressions by chips to come up to the
grade and camber.
9.14.5 The quality of the 80mm metal shall be same as specified for the soling and the longest
dimension shall not be more than 100mm and the shortest dimension not less than
50mm.
9.14.6 The soling after it is properly laid and hand packed including filling of voids with 80mm
metal shall be rolled dry with 12T power roller to refusal i.e. till the stones in the soling
course cease to move under the roller and no more compaction can be achieved.
Rolling shall start at the edges and work towards the centre. The roller shall run over
the same surface of rolling for at least 8 times still the soling course is well consolidated.
The surface shall be checked by templates and in case of unevenness high spots shall be
knocked our and depressions filled by spalls and re-compacted fully. Bunds shall be laid
along the edges and compacted before starting rolling on soling to prevent spreading of
stones.
9.14.8 Measurements shall be made for the finished work in square meters of the actual plan
area covered with the soling stone. The rate shall include the cost of all materials,
labour, plant and equipment required in all the operations described in 7.1 to 7.7 above
including soling stone and gravel.
9.15.1 The surface over which water bound macadam is to be laid shall be prepared to the
specified grade and camber and made free of dust and other extraneous material. Any
ruts or soft yielding places shall be corrected in an approved manner and rolled until
firm. To prevent the spreading of the course aggregate during rolling, if necessary, two
parallel mud walls 200mm wide and of height equal to un compacted Macadam course
shall be made along the outer edges of the Macadam course having a clear distance
between them equal to the width to be metalled.
9.15.2 W.B.M. Sub-Base Course of specified thickness shall be provided in lieu of a soling
course where specified in the schedule of quantities. The course aggregate for this shall
conform to requirements of sub-base in Table-1 and its grading shall conform to Grading
1 of Table 3 and screening to type B of Table-4. The total consolidated thickness of the
sub-base course shall be as specified in the schedule of quantities/drawings.
9.15.3 W.B.M. Base Course: The coarse aggregate for this shall normally conform to
requirements for Base in Table-1 and its grading shall confirm to Grading 3 of Table 3 and
screening to type B of Table 4. The total consolidated thickness of the base course shall be as
specified.
9.15.4.1 The coarse aggregate shall be spread uniformly and evenly upon the prepared surface
in such quantities that the thickness of each compacted layer does not exceed 75mm
or as otherwise specified. In no case, however, shall the thickness of each compacted
layer exceed 100mm.
9.15.4.2 The spreading shall be done from stockpiles by raking the stacks with rakes so as to
leave behind mud and dust. In no case shall the aggregate be dumped in heaps
directly on the surface prepared to receive the aggregate not shall hauling over un-
compacted or partially compacted sub-base/base be permitted. The surface of the
aggregates spread shall be fully checked with templates and all high or low spots
remedied by removing or adding aggregate as may be required. No segregation of
large or fine aggregates shall be allowed and the coarse aggregate as spread shall be
of uniform gradation with no pockets of fine material. The surface shall be checked
frequently with a straight edge while spreading and rolling so as to ensure a finished
surface as per approved plan. The coarse aggregate shall not normally be spread in
lengths exceeding 3 days average work ahead of the rolling and bonding of the
proceeding section.
9.15.5 Rolling
9.15.5.1 Following the spreading of the coarse aggregate, rolling shall be started with three
wheeled power rollers of not less than 12 tonne capacity or tandem or vibratory roller
of approved type. Rolling shall begin from the edges and gradually progress towards
the centre. First the edges/edge shall be compacted with roller running forward and
backward and then move inwards parallel to the centre line of the road, in successive
passes uniformly lapping preceding tracks by at least one half width. Rolling shall be
discontinued when the aggregates are partially compacted with sufficient void space
in them to permit application of screenings. During rolling slight sprinkling of water
may be done, if necessary. Rolling shall not be done when the sub grade is soft or
yielding or when it causes a wave-like motion in the sub grade or sub-base. The rolled
surface shall be checked transversely and longitudinally with templates and all
undulations shall be corrected by loosening the surface, adding or removing necessary
amounts of aggregate and re rolling until the entire surface conforms to desired
camber and grade. In no case shall the use of screening be permitted to make up
9.15.6.1 After the coarse aggregate has been rolled in accordance, screenings to completely fill
the interestices shall be applied gradually over the surface. These shall not be damp
or wet at the time of application. Dry rolling shall be done while the screenings are
being spread so that vibrations of the roller cause them to settle into the voids of the
coarse aggregate. The screenings shall not be dumped in piles but be spread
uniformly in successive thin layers. Screenings shall be applied at a slow and uniform
rate (in three or more applications) so as to ensure filling of all voids. This shall be
accompanied by dry rolling and brooming with mechanical brooms, hand brooms or
both. In no case shall screenings be applied as fast and thick as to form cakes and
ridges on the surface in such a manner as would prevent filling of voids or prevent the
direct bearing of the roller on the coarse aggregate. These operations shall continue
until no more screenings can be forced into the voids of the coarse aggregate.
Spreading, rolling and brooming of screenings shall be carried out in only such lengths
of the road, which could be completed within one day’s operation.
9.15.7.1 After the screenings have been applied, the surface shall be copiously sprinkled with
water, swept and rolled. Hand brooms shall be used to sweep the wet screenings into
voids and to distribute them evenly. The sprinkling, sweeping and rolling operations
shall be continued, with additional screenings applied as necessary, until the coarse
aggregate has been thoroughly keyed, well bonded and firmly set in its full depth and
a grout has been formed of screenings. Care shall be taken to see that the sub-grade
or sub-base does not get damaged due to the addition of excessive quantities of water
during construction. In case the sub grade or sub-base gets damaged, the Contractor
shall, without additional compensation rectify the damaged portion.
9.15.9.1 After the final compaction of water bound macadam course it shall be allowed to dry
overnight. Next morning hungry spots shall be filled with screenings or binding
material as directed, lightly sprinkled with water if necessary and rolled. No traffic
shall be allowed on the road until the macadam has set.
9.15.10.1 When the total consolidated thickness of the water bound macadam course is more
than 100mm, it shall be constructed in layers. Each layer shall be constructed as per
all the operations described in the above clauses. The same degree of quality control
and refinement shall be used for constructing each layer.
9.15.11.1 The measurements shall be made for the finished work in sqm. Length and width
shall be measured correct to a cm. For the water bound macadam surface.
9.15.11.2 The rate shall include the cost of all materials, labour, plant and equipment
involved in all the operations described above including the coarse aggregates,
screenings and binding material.
9.16.1 This work shall consist of constructing in a single course of 40mm thick premixed
asphalatic carpet to the following specifications on a previously prepared base, to
serve as a wearing coat.
9.16.2.1 Binder
This shall be paving bitumen of suitable penetration grade within the range S-35 to
S-90 or A 35 to A 90 (30-40 ro 80/100) as per Indian Standard for Paving Bitumen
IS:73. The actual grade of bitumen to be used shall be decided by the Consultants
/ Project Manager appropriate to the region, traffic, rainfall and other
environmental conditions.
9.16.2.4 Filler
The filler shall be an inert material, the whole of which passing 710 micron, sieve,
at least 90 % passing 180 micron sieve and not less than 70 percent passing 90
micron sieve. The filler shall be stone dust, cement, hydrated lime, fly ash or any
other non-plastic mineral matter approved by the Consultants / Project Manager.
TABLE 5
20 mm --- - 100
10 mm 80 – 100 70 – 90
TABLE – 6
The Contractor shall intimate to the Project Manager in writing, well in advance of
the start of work, the job-mix-formula proposed to be used by him for the work
and shall give following details to the Project Manager for his approval.
Fine aggregate } }
Mineral filler }
iii. A single definite percentage passing each sieve for the mixed aggregate.
iv. The results of the best enumerated in Table-6 as obtained by the Contractor.
Should a change in the source of material be proposed, a new job mix formula
shall be established and got approved from the Project Manager before actual
using the materials.
9.16.7.1 The binder used for tack coat shall be bitumen of suitable penetration grade within
30/40 to 80/100 confirming to IS:73. The actual grade of bitumen to be used shall
be decided by the Project Manager, appropriate to the region, traffic, rainfall and
other environmental conditions. Binder shall be heated to the temperature
appropriate to its grade and as approved by the Consultants / Project Manager.
The binder shall be sprayed on the prepared based at the rate of 1.0 kg/sqm. The
binder shall be applied uniformly with the aid of either self propelled or towed
bitumen pressure sprayer with self heating arrangement and spraying nozzle
arrangement capable of spraying bitumen at the above specified rate and
temperature so as to provide uniform unbroken spread of bitumen. The tack coal
shall be applied just ahead of oncoming premixed asphalt carpet.
9.16.8.1 Hot mix plant of adequate capacity and capable of producing a proper and uniform
quality mix shall be used for preparing the mix. The plant may be either a weigh
batch type of volumetric proportioning continuous or drum mix type. The stone
aggregate shall be surface dry and contain not more then 2 percent moisture
before use. It shall be first screened of dust and measured in boxes, heated to
155oC – 163o C and then loaded into the drum mixer according to the capacity of
the mixing drum in the proportion specified. The binder shall be heated to 140 o C
9.16.8.3 The hot mix shall be discharged from the mixer carried to the point of use in
suitable tipler vehicles and shall be spread by means of a self propelled mechanical
paver with a suitable screeds capable of spreading tamping and finishing the mix
to specified lines and levels to a thickness sufficient to achieve after consolidation
the specified thickness. Temperature of the mix at the time of laying shall be in
the range of 120o C – 160o C. However, in restricted locations and in narrow width
where available equipment can not be operated in the opinion of the Project
Manager, he may permit manual laying of the mix. Longitudinal joints and edges
shall be constructed true to the delineating lines parallel to the centre line of the
road. Longitudinal joints shall be offset by at least 150mm from those in the
binder course )tack coat). All joints shall be cut vertical to the full thickness of the
previously laid mix and the surface painted with hot bitumen before placing fresh
material.
9.16.9 Rolling
9.16.9.1 Immediately after the spreading of mix it shall be thoroughly compacted by rolling
with a set of roller moving at a speed not more than 5 km per hour. The initial or
break down rolling shall be with 12 ton three wheel roller and the surface finished
by final rolling with the 12 ton tendem roller. Preferably before finishing with
tendem, breakdown rolling shall be followed by an intermediate rolling with a
fixed wheel pneumatic roller of 15 to 30 ton having a tyre pressure of 7 kg. Per
cum. The joints and edges shall be rolled with 12 ton three wheel roller. Any high
spot or depressions which become apparent shall be corrected by addition or
removal of mix material. The roller shall uniformly overlap not less than a third of
the track made in the preceding pass. The wheels of the roller shall be moistened
with gunny bags to prevent the mix sticking to the wheels while rolling, but in no
case shall fuel lubricating oil be used for this purpose. Rolling shall be continued
till the mix is thoroughly compacted and all roller marks are eliminated.
9.16.13 Materials
9.16.13.1 Binder: This shall be 30/40, 60/70 or 80/100 grade straight run bitumen
conforming to IS:73, The actual grade of bitumen to be used shall be decided by
the Project Manager, appropriate to the region, traffic, rainfall and other
environmental conditions. The quantity of binder to be utilised, shall be 9.8 kg and
6.8 kg per 10 sqm. of area for type A and type B seal coat respectively.
9.16.13.2 Stone chippings for Type A seal coat : These shall consist of angular fragments of
clean, hard, tough and durable rock of uniform quality throughout. They should be
free of elongated or flaky pieces, soft or disintegrated stone, vegetable or other
deleterious matter. Stone chippings shall be of 10mm size defined as 100 percent
passing through 12.5mm sieve and retained on 2.36mm sieve. The quantity used
for spreading shall be 0.09 cum per 10 sqm.
9.16.13.3 Fine aggregate for type B seal coat: This fine aggregate shall be sand or fine grit
and shall consist of clean, hard durable, soft or flaky material organic matter or
other deleterious substances. The aggregate shall pass 1.7mm sieve and be
retained on 180 micron sieve. The quantity used for premixing shall be 0.06 cum.
per 10 sqm area.
Immediately after the application of the binder, stone chippings in a dry and clean
state shall be spread uniformly on the complete surface. If necessary the surface
shall be broomed to ensure uniform spread of chippings. The surface shall be
checked by means of a camber board laid across the road and a 3 meter straight
edge laid parallel to the centre line of the road and undulations if any, shall be
corrected by addition or removal of blindage.
9.16.15.3 Rolling
Immediately after the application of the cover the material, the entire surface shall
be rolled with a 8 to 10 ton smooth wheeled roller. While rolling is in progress
additional material shall be spread by hand in whatever quantities required to
make up irregularities. Rolling shall continue until all material is firmly bedded in
the binder and presents a uniform closed surface. Generally five to six passes shall
be made for thorough compaction of the surface or as directed by Project
Manager. Along kerbs, manholes and at all places not accessible to roller,
thorough compaction shall be secured by means of steel rammers or hand rollers.
Traffic shall be allowed after 24 hours. After a period of seven days, surplus grit
shall be swept and collected and shall be used for binding the spots where
bleeding occurs.
9.16.18 Rolling
As soon as sufficient length has been covered with the premixed material, the
surface shall be rolled with 12 tonne smooth wheeled power rollers. Rolling shall
be continued till the premixed material completely seals the voids in bituminous
course and a smooth uniform surface is obtained.
Traffic may be allowed soon after final rolling when, the premixed material has
cooled down to the surrounding temperature.
9.17.1 GENERAL
9.17.1.1 All materials incorporated and all works performed shall be strictly in conformity
with the specification requirements. All works shall conform to the lines, grades,
cross sections and dimensions shown on the drawings or as directed by the Project
Manager subject to the permitted tolerances described hereinafter. The
Contractor shall be responsible for the quality of the work in the entire
construction within the Contract. He shall therefore have his own independent
and adequate set-up for ensuring the same.
9.17.1.3 For the work of embankment, subgrade and construction of subsequent layer of
same or the material over the finished layer shall be done after obtaining
permission from the Consultants / Project Manager. Similar permission from the
Project Manager shall be obtained in respect of all other items of works prior to
proceeding with the next stage of construction.
9.17.1.4 The Contractor shall carry out modification in the procedure of work, if found
necessary, as diirected by the Project Manager during inspection. Works falling
short of quality shall be rectified by the Contractor at his own cost as directed by
the Project Manager.
9.17.1.5 The Contract rate quoted for various items of works in the bill of quantities or the
lumpsum amount Tendered shall be deemed to be inclusive of all costs of the
quality control tests and operations necessary for ensuring quality of the material
and work so as to be in conformity with the specification requirement.
Horizontal alignments shall be reckoned with respect to the centre line of the
carriage way as shown on the drawings. The edges of the carriage way as
constructed shall be correct within a tolerance of ± 25mm therefrom. The
The levels of the subgrade and different pavement courses as constructed, shall
not vary from those calculated with reference to the longitudinal and cross-profile
of the road shown on the drawings or as directed by the Project Manager beyond
the tolerances mentioned below:
Subgrade ± 15mm
Sub-base ± 20mm
Provided, however, that the negative tolerance for wearing course shall not be
permitted in conjunction with the positive tolerance for base course if the
thickness of the former is thereby reduced by more than 6mm.
The surface regularity of completed subgrade, sub-bases, base course and wearing
surfaces in the longitudinal and transverse directions shall be within the tolerances
indicated in Table-7.
The longitudinal profile shall be checked with a 3 meter long straight edge, at the
middle of each traffic lane along a line parallel to the centre line of the road. The
transverse profile shall be checked with a set of three camber boards at intervals
of 10 meters.
9.18.4 Rectification
i. Subgrade
Where the surface is high, it shall be trimmed and suitably compacted. Where
the same is low, the deficiency shall be corrected by adding fresh material. The
degree of compaction and the type of material to be used shall conform to the
clauses.
Where the surface is high or low, the top 75mm shall be scarified, reshaped with
added material as necessary recompacted to clauses. The area treated at a place
shall not be less than 5 meter long and 2 meters wide.
For bituminous construction other than wearing course, where the surface is
low, the deficiency shall be corrected by adding fresh material and recompacting
to specifications. Where the surface is high, the full depth of the layer shall be
removed and replaced with fresh material and compacted to specifications.
For wearing course, where the surface is high or low, the full depth of the layer
shall be removed and replaced with fresh material and compacted to
specifications. In all cases where the removal and replacement of a bituminous
layer is involved, the areas treated shall not be less than 5 meter lon and not less
than 1 lane wide.
TABLE – 7
1 Earthen subgrade 24 30 - - - 15
2 Granular / Lime / 15 - 30 - - 12
Cement / stabilised
subbase
3 Water bound 15 - 30 - - 12
macadam with over
size metal (45-90mm
size)
4 Water Bound 12 - - 30 - 8
macadam with normal
size metal (22 4-
53mm & 45-63mm
size)
5 Bituminous concrete 8 - - - 10 4
**
Notes:
1 ** These are for machine laid surfaces. If laid manually due to unavoidable
reasons, tolerance up to 50 percent above these values in this column
may be permitted at the discretion of the Project Manager. However,
this relaxation does not apply to the values of maximum undulation for
9.19 TESTS
9.19.1 General
For ensuring the requisite quality of construction, the materials and works shall be subjected to
quality control tests, as described hereinafter. The testing frequencies set forth are the
desirable minimum and the Project Manager shall have the full authority to increase the
frequencies of tests as he may deem necessary to satisfy himself that the materials and works
comply with the appropriate specifications.
Test procedures for the various quality control tests are indicated in the respective sections of
these specifications or for certain tests within this section. Where no specific testing procedure
is mentioned, the tests shall be carried out as per the prevalent accepted engineering practice
to the directions of the Project Manager
A. Borrow material
a. Sand content {IS:2720 (part IV)}: 1-2 tests per 8000 cum. of soil
b. Plasticity Test {IS:1270 (Part V)}: Each type to be tested, 1-2 tests per 8000 cum. of soil
c. Density Test {IS:2720 (part VII)}: Each soil type to be tested, 1-2 tests per 8000 cubic meters
of soil
d. Deleterious content test {IS:2720 (part xxVII)}: As and when required by the Project Manager.
e. Moisture content Test {IS:2720 (part II)}: One test for every 250 cubic meters of soil
However, for earthwork in shoulders (earthen) and in top 500mm portion of the embankment
below the sub grade, at least one density measurement shall be taken for every 50 square
meters of the compacted area provided further that the number of tests in each set of
measurements shall be at least 10. In order respects, the control shall be similar to that
described earlier.
The tests and their frequencies for the different types of bases and sub-base
shall be as given in table-8. The evaluation of density results for compaction
control shall be on lines similar to those set out in clauses.
TABLE – 8
Density of
compacted layer
One test per 500 sqm.
Deleterious
constituents
CBR
As required
As required
Density of
compacted layer
One test per 250 cum.
Deleterious
constituents
As required
Grading
The tests and their frequencies for the different types of bituminous works shall
be as given table-9 hereunder:
TABLE – 9
No.
The following tests as well as other tests may be ordered during execution by PMC/
Architect/ Structural Consultant shall be carried out by the contractor within the quoted
rate and time schedule at the required frequency.
1 Cement:
a) Recommended tests:
i) Fineness
ii) Soundness
iii) Consistency
iv) Setting time
v) Compressive strength and
vi) Chemical analysis
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS: 4031- Method of physical tests for Hydraulic cement.
Concrete workers
2 Fine aggregate:
a) Recommended tests:
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS: 383- Specification for coarse and fine aggregate from
natural sources for concrete.
3 Concrete workers
4 Coarse aggregate:
a) Recommended tests:
i) Sieve analysis
ii) Flakiness index
iii) Specific gravity and density
iv) Soundness
v) Alkali aggregate reaction
vi) Mechanical properties
vii) Petrographic examination
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS: 383-Specification for coarse and fine aggregate from natural sources
for concrete.
Part 5 – Soundness
Concrete workers
5 Water
a) Recommended tests:
i) P-Alkalinity
ii) M-Alkalinity
iii) Inorganic solids
iv) Sulfates
v) Chlorides
vi) Suspended solids
vii) pH Value
c) Acceptance criteria
As per guidelines in relevant Indian Standards
IS: 3025 –Method of sampling and tests (Physical and chemical) for water
and waste water.
Part 1 - Sampling
Part 2 - pH Value
Part 23 - Alkalinity
Part 24 - Sulfates
Part 32 - Chlorides
6 Admixtures:
(Accelerating, retarding, water reducing/workability improvement and air
entraining admixtures)
a) Recommended tests:
d) Relevant references:
IS:9103 - Specification for admixtures for concrete.
7 Fresh concrete:
a) Recommended tests:
c) Acceptance Criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS: 1199 – Method of sampling and analysis of concrete
8 Hardened concrete:
a) Recommended tests:
i) Compressive strength
a) Accelerated curing
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS : 456 – Code of practice for plain and reinforced concrete
9 Reinforcing Steel:
a) Recommended tests:
i) Tensile test on bars welded or otherwise.
ii) Bend and re-bend test
iii) Bond test
iv) Chemical analysis
c) Acceptance criteria:
As per guidelines in relevant Indian standards.
a) Recommended tests:
i) Dimensional tolerances
ii) Block density and compressive strength
iii) Water absorption
iv) Drying shrinkage
v) Moisture movement
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS: 2185 – Specification for concrete masonry units part-1
solid concrete blocks.
a) Recommended tests:
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS: 6072 – Specification for autoclaved reinforced cellular concrete wall
slabs.
products.
12 Door Shutters:
a) Recommended tests:
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS: 4020 – 1994 Door shutters method of test
Part 1 : General
13 Aluminium:
a) Recommended tests:
i) Thickness measurement of member
ii) Coating thickness
b) Sampling and frequency of sampling:
As per guidelines in relevant Indian Standards
c) Acceptance criteria:
As per guidelines in relevant Indian Standards
d) Relevant references:
IS: 5523 –Method of testing anodic coating on aluminium
14 Tiles (Concrete):
a) Recommended tests:
i) Dimensional tolerance
ii) Flatness
iii) Perpendicularity
iv) Straightness
v) Water absorption
vi) Wet transverse strength
vii) Resistance to wear
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant reference:
IS : 1237-Specification for cement concrete flooring tiles.
a) Recommended tests:
i) Dimensional tolerance
ii) Warp age
iii) Water absorption
iv) Impact strength
v) Cracking test
b) Sampling and frequency of sampling:
As per guidelines in relevant Indian Standards
c) Acceptance Criteria:
As per guidelines in relevant Indian Standards
d) Relevant references:
IS: 777 – Specification for glazed earthenware wall tiles.
16 Marble:
Recommended tests:
Moisture absorption
Hardness
Acceptance criteria:
Relevant references:
a) Recommended tests:
i) Ultrasonic pulse velocity test
ii) Rebound hammer test
b) Frequency of test:
About 5% of randomly selected reinforced concrete structural
components (in-situ of precast)
c) Acceptance Criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS:13311-Non-destructive testing of concrete
a) Recommended tests:
i) Texture of concrete
ii) Compressive strength test
b) Frequency of test:
Core to be taken from walls, slabs and footings whenever in doubt.
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
19 Load Test:
a) Recommended test:
Load testing of selected in-situ panels/pre-cast components (service load
test)
b) Frequency of test:
On representative in-situ panels in each type of housing whenever in
doubt about 0.5% of the total precast floor roof components.
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS: 456-Code of practice for plain and reinforced concrete.
IS: 6441 (part 7 & 8) Method of test for autoclaved cellular concrete
products subject to load test.
20 Earth-filling in Building:
a) Recommended tests:
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS: 2720- Method of test for soil
21 Mix design:
a) Recommended method:
Method outlined in SP-23-– Hand book on concrete mixes.
b) Frequency of design:
On every source of type of the following:
i) Aggregates
ii) Cement
iii) Admixtures and for different grades of workability.
d) Relevant references:
SP:23- Hand book on concrete mixes
GENERAL REFERENCES:
TOLERANCES:
No.
38 mm
19 mm
± 19 mm
a) Upto 3.05 mm
+ 10 mm
- 10 mm
- 5%
a) In 3.05 m length
b) Maximum for 15.24 m length ± 6 mm
± 13 mm
a) In 3.05 m length ± 6 mm
b) Maximum for 15.24 m length
a) Riser ± 3 mm
b) Tread
± 6 mm
a) Rise ± 3 mm
b) Run
± 6 mm
± 13 mm
± 13 mm
1) Cement Concrete
A VOLUMETRIC MIX
DESIGN MIX
2) Mortars
32) Flooring
iii) Mosaic/Marble/Blue
Tandoor/Kotah/Cudappah on
bed 20mm + slurry 4.4
kg/sqm
iv) Mosaic/Marble/Blue
Tandoor/Kotah/Cudappah on
bed 20mm + slurry 4.4
kg/sqm - Skirting
xi) Waterproofing
Cuddapah waterproofig -
c single layer sqm - 0.420 21.000
Cuddapah waterproofig -
d double layer sqm - 0.500 25.000
Conformance
Deviations
by
S.No Materials Approved Makes if any by
vendor Yes /
vendor
No
1
Chlorpyriphios De-Nocil// Cynamide/Tricel
Non-Absorbent Closed
11 Tristar intech /Supreme Ind
Cell PE Board
Expanded Polystyrene
13 Beardshell / Toshiba
(Thermocole)
Dehradun / approved
17 White Washing Lime
equivalent
Fosroc/ BASF/ Mc
19 Concrete admixture
Bauchemie
Fosroc/ EMALITE OF
20 Non Metallic Floor Structural/CICO
technologies / STP
Acrylic/polymer
22 BASF / FOSROC / SIKA
modified coatings
Membrane water
24 proofing SIKA / Tristar
(Bituminous)
Extruded Polystyrene
26 Isofoam / Styrofoam
(Insulation)
Fire protection
29 HILTI / Promat
Sealants/ Spray
Note: In the List of recommended above, out of makes mentioned in the list, only 1st make shall
be quoted for and used. However if due to non-availability or any other technical reasons,
the alternative make is allowed, it shall be subject to prior approval of the Project Manager
and price adjustment.
1. The contractor shall produce all samples including natural stones, before procurement of
the materials, for approval of the Architects/Project Managers.
2. Where more than one manufacturer is listed, the names are given in the order of
preference. The contractor shall quote the rates for the various items of work based on the
materials of first preference after ascertaining the availability, delivery schedule of the
same. Unless the contractor stipulates in this tender, it shall be presumed that the rates
quoted are for material of first preference only.
4. In respect of materials for which approved makes are not specified above, these will be
makes to be decided by the Architects/Project Managers and as per samples getting
approved.
The Building is designed for an Energy Efficient Structure and hence all products have to
be green rated and wherever not mentioned clarifications should be sought from the
Project Manager.
CEMENT PLASTER
Scaffolding:- For all exposed brick work or tile work double scaffolding independent of
the work having two sets of vertical supports shall be provided. The supports shall be
sound and strong, tied together with horizontal pieces over which scaffolding planks
shall be fixed.
For all other work in buildings, single scaffolding shall be permitted. In such cases the
inner end of the horizontal scaffolding pole shall rest in a hole provided only in the
header course for the purpose. Only one header for each pole shall be left out. Such
holes for scaffolding shall, however, not be allowed in pillars/columns less than one
metre in width or immediately near the skew backs of arches. The holes left in masonry
works for scaffolding purposes shall be filled and made good before plastering.
Note : In case of special type of brick work, scaffolding shall be got approved from
Engineer-in-charge in advance.
In case of concrete surface if a chemical retarder has been applied to the form work, the
surface shall be roughened by wire brushing and all the resulting dust and loose
particles cleaned off and care shall be taken that none of the retarders is left on the
surface.
Mortar:
The mortar of the specified mix using the type of sand described in the item shall be
used. It shall be as specified in Subhead 3.0. For external work and under coat work, the
fine aggregate shall conform to grading IV. For finishing coat work the fine aggregate
conforming to grading zone V shall be used.
Application of Plaster:
Ceiling plaster shall be completed before commencement of wall plaster.
Plastering shall be started from the top and worked down towards the floor. All putlog
holes shall be properly filled in advance of the plastering as the scaffolding is being
taken down. To ensure even thickness and a true surface, plaster about 15 × 15 cm shall
be first applied, horizontally and vertically, at not more than 2 metres intervals over the
entire surface to serve as gauges. The surfaces of these gauged areas shall be truly in
the plane of the finished plaster surface. The mortar shall then be laid on the wall,
between the gauges with trowel. The mortar shall be applied in a uniform surface
slightly more than the specified thickness. This shall be brought to a true surface, by
working a wooden straight edge reaching across the gauges, with small upward and side
ways movements at a time. Finally the surface shall be finished off true with trowel or
wooden float according as a smooth or a sandy granular texture is required. Excessive
troweling or over working the float shall be avoided.
All corners, arises, angles and junctions shall be truly vertical or horizontal as the case
may be and shall be carefully finished. Rounding or chamfering corners, arises, provision
Technical Specification Page 207
of grooves at junctions etc. where required shall be done without any extra payment.
Such rounding, chamfering or grooving shall be carried out with proper templates or
battens to the sizes required.
When suspending work at the end of the day, the plaster shall be left, cut clean to line
both horizontally and vertically. When recommencing the plastering, the edge of the old
work shall be scrapped cleaned and wetted with cement slurry before plaster is applied
to the adjacent areas, to enable the two to properly join together. Plastering work shall
be closed at the end of the day on the body of wall and not nearer than 15 cm to any
corners or arises. It shall not be closed on the body of the features such as plasters,
bands and cornices, nor at the corners of arises. Horizontal joints in plaster work shall
not also occur on parapet tops and copings as these invariably lead to leakages. The
plastering and finishing shall be completed within half an hour of adding water to the
dry mortar.
No portion of the surface shall be left out initially to be patched up later on. The
plastering and finishing shall be completed within half an hour of adding water to the
dry mortar.
POINTING
All exposed joints shall be pointed with mortar as specified. The pointing when finished
shall be sunk from stone face by 5 mm or as specified. The depth of mortar in pointing
work shall not be less than 15 mm.
Curing
Masonry work in cement or composite mortar shall be kept constantly moist on all faces
for a minimum period of seven days. In case of masonry with fat lime mortar, curing
shall commence two days after laying of masonry and shall continue for at least seven
days thereafter.
Scaffolding:
Double scaffolding having two sets of vertical supports shall be provided. The supports
shall be sound and strong, tied together with horizontal pieces over which scaffolding
planks shall be fixed.
Rate:The rate shall include the cost of materials and labour required for all the
operations described above
Before laying the first course, the alignment of the wall shall be marked on the damp-
proof course. The blocks for this course shall first be laid dry, that is, without mortar
along a string stretched between properly located corners of the wall in order to
determine the correct position of the blocks including those of the cross walls jointing it
and also adjust their spacing. When the blocks are set in proper position, the two corner
blocks shall be removed, a mortar bed spread and these blocks laid back in place truly
level and plumb. The string shall then be stretched tightly along the faces of two corner
blocks and the faces of the intermediate ones adjusted to coincide with the line.
Thereafter, each block shall be removed and relaid over a bed of mortar. After every
three or four blocks have been laid, their correct alignment, level and verticality shall be
carefully checked.
The construction of walls may be started either at the corners firstor started from one
end proceeding in the other direction. If the cornersof the wall are built first, they shall
be built four or five courses higherthan the centre of the wall. As each course is laid at
the corner, it shallbe checked for alignment and level and for being plumb. Each
blockshall be carefully checked with a level or straight-edge to make certainthat the
The use of a storey rod or course pole which is simply a board with markings 200
mm apart, provides an accurate method of finding the top of the masonry for
each course. Each course, in building the corners, shall be stepped back by a half-
block and the horizontal spacing of the block shall be checked by placing a
mason’s level diagonally across the corners of the blocks.
When filling in the wall between thecorners, a mason’s line shallbe stretched from
corner to corner for each course and the top outsideedge of each block shall be laid to
this line. The manner of handling orgripping the block shall be such as to position the
block properly withminimum adjustment.
To assure satisfactory bond, mortar shall not be spread too far ahead of actual
laying of the block or it will stiffen and loose its plasticity. As each block is laid,
excess mortar extruding from the joints shall be cut off with the trowel and
thrown back on the mortar board to be reworked into the fresh mortar. If the
work is progressing rapidly, the extruded mortar cut from the joints may be
applied to the vertical face shells of the blocks just laid. If there be any delay long
enough for the mortar to stiffen on the block, the mortar shall be removed to
the mortar board and reworked. Dead mortar that has been picked up from the
scaffold or from the floor shall not be used.
Closure Block -Wheninstalling the closure block, all edges ofthe opening and all four
edges of the closure block shall be butteredwith mortar. The closure block shall be
carefully lowered into place.If any mortar falls leaving an open joint, the closure block
shall beremoved, fresh mortar applied and the operation repeated.
FLOORING /SKIRTING
Base concrete or the RCC slab on which the tiles are to be laid shall be cleaned, wetted
and mopped. The bedding for the tile shall be with cement mortar 1:4 (1 cement: 4
coarse sand) or as specified. The average thickness of the bedding shall be 20 mm or as
specified while the thickness under any portion of the tiles shall not be less than 10 mm.
Over this mortar bedding neat grey cement slurry of honey like consistency shall be
spread at the rate of 3.3 kg of cement per square metre over an area upto one square
metre. Tiles shall be soaked in water washed clean and shall be fixed in this grout one
after another, each tile gently being tapped with a wooden mallet till it is properly
bedded and in level with the adjoining tiles. The joints shall be kept as thin as possible
and in straight lines or to suit the required pattern.
The surface of the flooring during laying shall be frequently checked with a straight edge
about 2 m long, so as to obtain a true surface with the required slope. In bath, toilet
W.C. kitchen and balcony/verandah flooring, suitable tile drop or as shown in drawing
will be given in addition to required slope to avoid spread of water. Further tile drop will
also be provided near floor trap.
Where full size tiles cannot be fixed these shall be cut (sawn) to the required size, and
their edge rubbed smooth to ensure straight and true joints.
Tiles which are fixed in the floor adjoining the wall shall enter not less than 10 mm
under the plaster, skirting or dado
After tiles have been laid surplus cement slurry shall be cleaned off.
Any issue in the technical specification will withdraw from the item and will stand the
decision of the engineer-in-charge.
Pressed Ceramic Tiles:The tiles shall be of approved make and shall generally conform to
IS 15622. They shall be flat, and true to shape and free from blisters crazing, chips,
welts, crawling or other imperfections detracting from their appearance. The tiles shall
be .Group B Ib and thick 7 - 8mm.
Base concrete or the RCC slab on which the tiles are to be laid shall be cleaned, wetted
and mopped. The bedding for the tile shall be with cement mortar 1:4 (1 cement: 4
coarse sand) or as specified. The average thickness of the bedding shall be 20 mm or as
specified while the thickness under any portion of the tiles shall not be less than 10 mm.
Mortar shall be spread, tamped and corrected to proper levels and allowed to harden
sufficiently to offer a fairly rigid cushion for the tiles to be set and to enable the mason
to place wooden plank across and squat on it.
Over this mortar bedding neat grey cement slurry of honey like consistency shall be
spread at the rate of 3.3 kg of cement per square meter over an area upto one square
meter. Tiles shall be soaked in water washed clean and shall be fixed in this grout one
after another, each tile gently being tapped with a wooden mallet till it is properly
bedded and in level with the adjoining tiles. The joints shall be kept as thin as possible
and in straight lines or to suit the required pattern.
The surface of the flooring during laying shall be frequently checked with a straight edge
about 2 m long, so as to obtain a true surface with the required slope. In bath, toilet
W.C. kitchen and balcony/verandah flooring, suitable tile drop or as shown in drawing
will be given in addition to required slope to avoid spread of water. Further tile drop will
also be provided near floor trap.
Where full size tiles cannot be fixed these shall be cut (sawn) to the required size, and
their edge rubbed smooth to ensure straight and true joints. Tiles which are fixed in the
floor adjoining the wall shall enter not less than 10 mm under the plaster, skirting or
dado.
After tiles have been laid surplus cement slurry shall be cleaned off.
The top surface of the tiles shall be glazed. The underside of the tiles shall not have
glaze on more than 5% of the area in order that the tile may adhere properly to the
base. The edges of the tiles shall be free from glaze, however, any glaze if unavoidable
shall be permissible on only upto 50 per cent of the surface area of edges.
The glaze shall be free from welts, chips, craze, specks, crawling or other imperfections
detracting from the appearance when viewed from a distance of one metre. The glaze
shall be either glossy or matt as specified. The glaze shall be white in colour except in
the case of coloured tiles when colours shall be specified by the Engineer-in-Charge.
There may be more than one colour on a tile.
Preparation of Surfaces
The joints shall be raked out to a depth of at least 15 mm in masonry walls. In case of
concrete walls, the surface shall be hacked and roughened with wire brushes. The
surface shall be cleaned thoroughly, washed with water and kept wet before skirting is
commenced.
Laying
The tiles should be soaked in water, washed clean, and a coat of cement slurry applied
liberally at the back of tiles and set in the bedding mortar. The tiles shall be tamped and
corrected to proper plane and lines. The tiles shall be set in the required pattern and
jointed. The joints shall be as fine as possible. Top of skirting or dado shall be truly
horizontal and joints truly vertical except where otherwise indicated. Odd size/cut size
of tile shall be adjusted at bottom to take care of slope of the flooring.Skirting and dado
shall rest on the top of the flooring. Where full size tiles cannot be fixed these shall be
cut (sawn) to the required size and their edges rubbed smooth. Skirting /dado shall not
project from the finished “surface of wall” by more than the tile thickness; undulations if
any shall be adjusted in wall.
The joints shall be cleaned off the grey cement grout with wire/coir brush or trowel to a
depth of 2 mm to 3 mm and all dust and loose mortar removed. Joints shall then be
flush pointed with white cement added with pigments if required to match the colour of
tiles. The work shall then be kept wet for 7 days. After curing, the surface shall be
washed and finished clean. The finished work shall not sound hollow when tapped with
a wooden mallet.
i) Mortar Bedding:
Cement mortar shall be prepared in a mortar mill or pan. The amount of water added shall be
the minimum necessary to give just sufficient plasticity for laying and satisfactory bedding. Care
The stone slabs shall be laid on the neat cement float and shall be evenly and firmly bedded to
the required level and slope in the mortar bed. The stone slabs shall be laid in the approved
pattern in single or two-tone colour. Each stone slab shall be gently tapped with a wooden
mallet till it is firmly and properly bedded. There shall be no hollows left. If there is a hollow
sound on gentle tapping of the stone slabs, such stone slabs shall be removed and reset
properly. The mason shall make the joint of uniform thickness and straight lines. The thickness
of joints shall not exceed 1.5mm. The joints shall be grouted with neat cement slurry. No border
stone slabs shall be less than 4" in width, unless otherwise approved by the Architect. When the
bedding and joints of the flooring have been completely set, the surface shall be machine
polished to give a smooth, even and true plane to the floor and thoroughly cleaned.
Apart from other factors mentioned elsewhere in this contract the contractor's rate quoted shall
include for the following:
Cleaning the base and providing and laying bedding mortar and levelling.
Providing and fixing the stone slabs in neat cement float on the bedding mortar.
Filling joints of stone slabs with neat cement slurry of required colour to match the
colour of the stone slabs.
Chiselling, polishing, finishing and cleaning.
All labour, materials and use of tools for carrying out the item as specified above.
The slabs shall be of selected quality, hard, sound, dense and homogeneous in texture
free from cracks, decay, weathering and flaws. They shall be hand or machine cut to the
requisite thickness. They shall be of the colour indicated in the drawings or as instructed
by the Client/Project manager.
The slabs shall have the top (exposed) face polished before being brought to site, unless
otherwise specified. The slabs shall conform to the size required. Before starting the
work the contractor shall get the samples of slabs approved by the Client/Project
manager.
Dressing
Every slab shall be cut to the required size and shape and fine chisel dressed on the
sides to the full depth so that a straight edge laid along the side of the stone shall be in
full contact with it. The sides (edges) shall be table rubbed with coarse sand or machine
rubbed before paving. All angles and edges of the slabs shall be true, square and free
from chippings and the surface shall be true and plane.
The specification shall be as described in 11.19.3 except that the edges of the slabs to be
jointed shall be buttered with grey cement, with admixture of pigment to match the
shade of the slab. The thickness of the joints should be minimum as possible. In any
location, it shall not exceed 1 mm.
The specifications shall be as described in 11.19.3 except that (a) first polishing with
coarse grade carborundum stone shall not be done, (b) cement slurry with or without
pigment shall not be applied on the surface before polishing.
Laying
The risers of steps and skirting shall be in grey or white cement admixed with or without
pigment to match the shade of the stone, as specified in the description of the item,
with the line of the slab at such a distance from the wall that the average width of the
gap shall be 12 mm and at no place the width shall be less than 10 mm, if necessary, the
slabs shall be held in position by temporary M.S. hooks fixed into the wall at suitable
intervals. The skirting or riser face shall be checked for plane and plumb and corrected.
The joints shall thus be left to harden then the rear of the skirting or riser slab shall be
packed with cement mortar 1:3 (1 cement: 3 coarse sand) or other mix as specified in
the description of the item. The fixing hooks shall be removed after the mortar filling
the gap has acquired sufficient strength.The joints shall be as fine as possible but not
more than 1 mm. The top line of skirting and risers shall be truly horizontal and joints
truly vertical, except where otherwise indicated. The risers and skirting slab shall be
matched as shown in drawings or as instructed by the Client/Project manager.
Curing, After the tiles/Slabs are laid all joints shall be cleaned of the grey cement grout
with a wire brush or trowel to a depth of 5 mm and all dust and loose mortar removed
and cleaned. Joints shall then be grouted with grey or white cement mixed with or
without pigment to match the shape of the topping of the wearing layer of the
tiles/slabs. The same cement slurry shall be applied to the entire surface of the tiles in a
thin coat with a view to protect the surface from abrasive damage and fill the pin holes
that may exist on the surface.
The floor shall then be kept wet for a minimum period of 7 days. The surface shall
thereafter be grounded evenly with machine fitted with coarse grade grit block. Water
shall be used profusely during grinding. After grinding the surface shall be thoroughly
washed to remove all grinding mud, cleaned and mopped. It shall then be covered with
a thin coat of grey or white cement, mixed with or without pigment to match the colour
of the topping of the wearing surface in order to fill any pin hole that appear. The
surface shall be again cured. The second grinding shall then be carried out with machine
fitted with fine grade grit block.
The final grinding with machine fitted with the finest grade grit blocks shall be carried
out the day after the second grinding before handing over the floor
Measurements
Length shall be measured along the finished face of riser, skirting or dado correct to a
cm. Height shall be measured from the finished level of tread of floor to the top (the
underside of tread in the case of steps). This shall be measured correct to a mm in the
case of risers of steps and skirting and correct to a cm in the case of dado. The area shall
be calculated in square metre correct to two places of decimal.
Rate
The rate shall include the cost of all materials and labour involved in all the operations
described above.
The slabs shall be hand or machine cut to the requisite thickness along planes parallel to
the natural bed of stone and should be of uniform size if required.
Dressing of Slabs
Every slab shall be cut to the required size and shape and chisel dressed on all sides to a
minimum depth of 20 mm. The top and the joints shall be fine tooled so that straight
edge laid along the face is fully in contact with it. In case machine cut stones are used,
chisel dressing and fine tooling of machine cut surface need not be done provided a
straight edge laid anywhere along the machine cut surface is in contact with every point
on it
The thickness of the slabs after dressing shall be 40 mm or as specified in the description
of item with a permissible tolerance of ± 2 mm
Laying
The tiles/slab should be soaked in water, washed clean, and a coat of cement slurry
applied liberally at the back of tiles/slab and set in the bedding mortar. The tiles/slab
shall be tamped and corrected to proper plane and lines. The tiles/slab shall be set in
the required pattern and jointed. The joints shall be as fine as possible. Top of skirting or
dado shall be truly horizontal and joints truly vertical except where otherwise indicated.
Odd size/cut size of tile shall be adjusted at bottom to take care of slope of the
flooring.Skirting and dado shall rest on the top of the flooring. Where full size tiles /slab
cannot be fixed these shall be cut (sawn) to the required size and their edges rubbed
smooth. Skirting /dado shall not project from the finished “surface of wall” by more
than the tile thickness; undulations if any shall be adjusted in wall.
Dressing of Slabs
Every stone shall be cut to the required size and shape, fine chisel dressed on all sides to
the full depth so that a straight edge laid along the side of the stone shall be fully in
contact with it. The top surface shall also be fine chisel dressed to remove all waviness.
In case machine cut slabs are used, fine chisel dressing of machine cut surface need not
be done provided a straight edge laid anywhere along the machine cut surfaces is in
contact with every point on it. The sides and top surface of slabs shall be machined
rubbed or table rubbed with coarse sand before paving. All angles and edges of the
marble slabs shall be true, square and free from chippings and the surface shall be true
and plane
Laying
Base concrete or the RCC slab on which the slabs are to be laid shall be cleaned, wetted
and mopped. The bedding for the slabs shall be with cement mortar 1:4 (1 cement: 4
coarse sand) or as given in the description of the item. The average thickness of the
bedding mortar under the slab shall be 20 mm and the thickness at any place under the
slab shall be not less than 12 mm.
Mortar of the specified mix shall be spread under the area of each slab, roughly to the
average thickness specified in the item. The slab shall be washed clean before laying. It
shall be laid on top, pressed, tapped with wooden mallet and brought to level with the
adjoining slabs. It shall be lifted and laid aside. The top surface of the mortar shall then
be corrected by adding fresh mortar at hollows. The mortar is allowed to harden a bit
and cement slurry of honey like consistency shall be spread over the same at the rate of
4.4 kg of cement per sqm. The edges of the slab already paved shall be buttered with
grey or white cement with or without admixture of pigment to match the shade of the
marble slabs as given in the description of the item.
The slab to be paved shall then be lowered gently back in position and tapped with
wooden mallet till it is properly bedded in level with and close to the adjoining slabs
with as fine a joint as possible. Subsequent slabs shall be laid in the same manner. After
each slab has been laid, surplus cement on the surface of the slabs shall be cleaned off.
The flooring shall be cured for a minimum period of seven days. The surface of the
flooring as laid shall be true to levels, and, slopes as instructed by the Client/Project
manager. Joint thickness shall not be more than 1 mm. The slabs shall be matched as
shown in drawings or as instructed by the Client/Project manager.
After the tiles/Slabs are laid all joints shall be cleaned of the grey cement grout with a
wire brush or trowel to a depth of 5 mm and all dust and loose mortar removed and
cleaned. Joints shall then be grouted with grey or white cement mixed with or without
pigment to match the shape of the topping of the wearing layer of the tiles/slabs. The
same cement slurry shall be applied to the entire surface of the tiles in a thin coat with a
The floor shall then be kept wet for a minimum period of 7 days. The surface shall
thereafter be grounded evenly with machine fitted with coarse grade grit block. Water
shall be used profusely during grinding. After grinding the surface shall be thoroughly
washed to remove all grinding mud, cleaned and mopped. It shall then be covered with
a thin coat of grey or white cement, mixed with or without pigment to match the colour
of the topping of the wearing surface in order to fill any pin hole that appear. The
surface shall be again cured. The second grinding shall then be carried out with machine
fitted with fine grade grit block.
The final grinding with machine fitted with the finest grade grit blocks shall be carried
out the day after the second grinding before handing over the floor
After the final polish, oxalic acid shall be dusted over the surface at the rate of 33 gm
per square metre sprinkled with water and rubbed .The following day the floor shall be
wiped with a moist rag and dried with a soft cloth and finished clean.
Measurement
Marble stone flooring with different kind of marble shall be measured separately and in
square metre correct to two places of decimal. Length and breadth shall be measured
correct to a cm before laying skirting, dado or wall plaster. No deduction shall be made
nor extra paid for voids not exceeding 0.20 square metre. Deductions for ends of
dissimilar materials or other articles embedded shall not be made for areas not
exceeding 0.10 square metre. Nothing extra shall be paid for laying the floor at different
levels in the same room. Steps and treads of stairs paved with marble stone slabs shall
also be measured under the item of Marble Stone flooring. Extra shall, however, be paid
for such areas where the width of treads does not exceed 30 cm. The width of treads
shall be measured from the outer edge of the nosing, as laid, before providing the riser
Rate
The rate shall include the cost of all materials and labour involved in all the operations
described above. However, extra shall be paid for making special type of
pattern/design/flowers as per drawings.
Flooring shall be laid on base concrete where so provided. The base concrete shall be
provided with the slopes required for the flooring. Flooring in verandah, Courtyard,
kitchens & baths shall have slope ranging from 1 : 48 to 1 : 60 depending upon location
and as decided by the Engineer-in-Charge. Floors in water closet portion shall have slope
of 1:30 or as decided by the Engineer-in-Charge to drain off washing water. Further,
necessary drop in flooring in bath, WC, kitchen near floor traps ranging from 6 mm to 10
mm will also be provided to avoid spread of water. Necessary margin to accommodate
this drop shall be made in base concrete. Plinth masonry off set shall be depressed so as
to allow the base concrete to rest on it.
The flooring shall be commenced preferably within 48 hours of the laying of base
concrete. The surface of the base shall be roughened with steel wire brushes without
disturbing the concrete. Immediately before laying the flooring, the base shall be wetted
and a coat of cement slurry @ 2 kg of cement spread over an area of one sqm so as to
get a good bond between the base and concrete floor
If the cement concrete flooring is to be laid directly on the RCC slab, the top surface of
RCC slab shall be cleaned and the laitance shall be removed and a coat of cement slurry
@ 2 kg of cement spread over an area of one sqm so as to get a good bond between the
base and concrete floor.
Laying:
Panels: Flooring of specified thickness shall be laid in the pattern including the border as
given in the drawings or as directed by the Engineer-in-Charge. The border panels shall
not exceed 450 mm in width and the joints in the border shall be in line with panel
joints. The panels shall be of uniform size and no dimension of a panel shall exceed 2 m
and the area of a panel shall not be more than 2 sqm. The joints of borders at corners
shall be mitred for provision of strips.
Laying of Flooring with Strips : Normally cement concrete flooring shall be laid in one
operation using glass/aluminium/PVC/brass strips/stainless steel strips or any other
strips as required as per drawing or instructions of the Engineer-in-Charge, at the
junction of two panels. This method ensures uniformity in colour of all the panels and
straightness at the junction of the panels. 4 mm thick glass strips or 2 mm PVC strips or
2 mm aluminium or brass strips shall be fixed with their tops at proper level, giving
required slopes. Use of glass and metallic strips shall be avoided in areas exposed to
sun. Cost of providing and fixing strips shall be paid for separately.
Finishing:
The finishing of the surface shall follow immediately after the cessation of beating. The
surface shall be left for some time, till moisture disappears from it or surplus water can
be mopped up. Use of dry cement or cement and sand mixture stiffening the concrete
to absorb excessive moisture shall not be permitted. Excessive trowelling shall be
avoided.
Fresh cement shall be mixed with water to form a thick slurry and spreaded @ 2 kg of
cement over an area of one sqm of flooring while the flooring concrete is still green. The
cement slurry shall then be properly processed and finished smooth.
Curing:
The curing shall be done for a minimum period of ten days. Curing shall not be
commenced until the top layer has hardened. Covering with empty gunnies bag shall be
avoided as the colour of the flooring is likely to be bleached due to the remanents of
cement dust from the bags.
Measurement
Length and breadth shall be measured before laying skirting, dado or wall plaster. No
deduction shall be made nor extra paid for voids not exceeding 0.20 sqm. Deductions
for ends of dissimilar materials or other articles embedded shall not be made for areas
not exceeding 0.10 sqm.
Chequered Tiles The tiles shall be of nominal sizes such as 20 × 20 cm, 25 × 25 cm and
30 × 30 cm or of standard sizes with equal sides. The size of tiles to be used shall be as
The overall thickness of the tiles shall not be less than 30 mm. The grooves in the
chequers shall be uniform and straight. The depth of the grooves shall not be less than 3
mm. The chequered tiles shall be cement tiles, or terrazo tiles as specified in the
description of the item. The thickness of the upper layer, measured from the top of the
chequers shall not be less than 6 mm.
Laying
Base concrete or the RCC slab on which the slabs are to be laid shall be cleaned, wetted
and mopped. The bedding for the slabs shall be with cement mortar 1:4 (1 cement: 4
coarse sand) or as given in the description of the item. The average thickness of the
bedding mortar under the slab shall be 20 mm and the thickness at any place under the
slab shall be not less than 12 mm.
Mortar of the specified mix shall be spread under the area of each slab, roughly to the
average thickness specified in the item. The slab shall be washed clean before laying. It
shall be laid on top, pressed, tapped with wooden mallet and brought to level with the
adjoining slabs. It shall be lifted and laid aside. The top surface of the mortar shall then
be corrected by adding fresh mortar at hollows. The mortar is allowed to harden a bit
and cement slurry of honey like consistency shall be spread over the same at the rate of
4.4 kg of cement per sqm. The edges of the slab already paved shall be buttered with
grey or white cement with or without admixture of pigment to match the shade of the
marble slabs as given in the description of the item.
The slab to be paved shall then be lowered gently back in position and tapped with
wooden mallet till it is properly bedded in level with and close to the adjoining slabs
with as fine a joint as possible. Subsequent slabs shall be laid in the same manner. After
each slab has been laid, surplus cement on the surface of the slabs shall be cleaned off.
The flooring shall be cured for a minimum period of seven days. The surface of the
flooring as laid shall be true to levels, and, slopes as instructed by the Client/Project
manager. Joint thickness shall not be more than 1 mm. The slabs shall be matched as
shown in drawings or as instructed by the Client/Project manager
WOODEN FLOORING
Seasoning and Preservation: All timber used for timber floors shall be thoroughly
seasoned in accordance with IS 1141. After seasoning the timber shall be treated with
preservative in accordance with IS 401. Seasoning and preservative treatment shall be
paid for separately unless otherwise specifically included in the description of the item
of flooring.
Supporting Joists: Main beams and joists of the class of wood sections specified in the
description of the item for beams and joists, or as instructed by the Engineer-in-Charge
shall be fixed in position to dead levels. The width of the joints shall not be less than 50
mm. The arrangement and spacing of beams joists etc. shall be as per design furnished.
It shall be of the class of timber and thickness specified in the description of the item.
The timber shall be as specified as per the direction of Engineer-in-charge/ClientOnly
selected boards of uniform width shall be used. Unless otherwise specified or shown in
the drawings, the width of boards selected shall not be less than 100 mm nor more than
150 mm. The same width of boards shall not be maintained throughout except where
the width of the room is not an exact multiple of the boards. In the latter case, the
difference shall be equally adjusted between the two end boards (adjacent to walls).
The length of the boards shall not exceed 3 metre anywhere. Ordinarily, the minimum
length of boards shall be such that the boards shall rest at least on three supports,
except where otherwise required by the pattern specified in the drawings or as directed
by the Engineer-in-Charge.
Fixing
The joists on which the planks shall be fixed shall be checked and corrected to levels.
The end boards shall be accurately fixed with the sides parallel and close to the walls.
Each adjoining board shall be carefully jointed and shall be tightened in position and
screwed. For fixing the boards to the joists, two screws shall be used at each end of the
The junction between timber flooring and adjacent flooring shall be formed by inserting
a metal strip (brass or aluminium) at the junction. The metal strip shall be fixed to the
end of the planks by screws. The strips shall be paid for extra.
The flooring shall be truly level and plane. The joints shall be truly parallel and or
perpendicular to the walls, unless otherwise specified.
The floor shall be plane in both directions and made perfectly even, true and smooth.
The boards shall be planed true on the top face only unless otherwise specified in the
description of the item. Where the bottom face is exposed and it is also required to be
planed, then such planing shall be paid for extra.
Unless otherwise described in the item, the longitudinal joints of planks shall be
tongued and grooved to a minimum depth of 12 mm while the heading joints shall be of
the square butt type and shall occur over the centre line of the supporting joists.
Heading joists in adjacent boards shall be placed over the same joists.
Rate:The rate shall include the cost of the labour and materials involved in all the
operations described above, with the exceptions noted in the relevant sub-paras
All timber for carpentry and joinery in touch with masonry or concrete shall be painted
with wood preservative before fixing.
All fully fabricated timber shall be seasoned and chemically treated. The preparation of
timber for joinery is to commence simultaneously with the beginning of the project
work generally and should proceed continuously until all the wood work is prepared and
fixed / stacked on/ near the site as the case may be.
Doors, Frames:
The specification for frames of doors, are described here. The frames shall wrought,
framed and fixed in position as per detailed drawing and as directed by the engineer in
charge. Specified timber shall be used, and it shall be sawn in the direction of the grains.
Sawing shall be truly straight and square. The scanting shall be planed smooth and
accurate to the full dimensions, rebates, rounding and mouldings as shown in the
drawings made, before assembling. Patching or plugging of any kind shall not be
permitted except as provided. A tolerance of 2 / 3 mm shall be allowed in the finished
cross section dimensions of door and windows frames.
Joints:
These shall be of mortise and tenon type, simple, neat and strong. Mortise and tendon
joints shall fit in fully and accurately without wedging or filling. The joints shall be glued,
framed, put together and planned with hard wood or bamboo pins not less than 10 mm
diameter after the frames are put together in position by means of a press.
Gluing of joints:
The contact surface of tendon and mortise joints shall be treated before putting
together with synthetic resin adhesive of make, approved by the engineer.
Fixing in Position:
Before the frames are fixed in position, these shall be inspected and passed by the
engineer. The frame shall be placed in proper position and secured to walls or columns
as the case maybe with metallic fastener, iron hold fasts as per direction of the
Engineer-in-charge.
In case of door frames without sills the vertical members shall be embedded in the
flooring to its full depth. When sills are provided, these sills shall be embedded and sunk
in the floor to its full depth. The door frames without sills while being placed in position
Measurement:
Wood work wrought and framed shall be measured for finished dimensions. No
allowance shall be made for wastage and for dimensions supplied beyond those
specified. Length of each peace shall be measured over all nearest to one cm, so as to
include projections for tendons, scarps or meters, width or thickness shall be measured
to the nearest mm.
In case of moldings, rounding, rebates, circular and varying section, the sectional area of
the piece shall be taken as the area of the least square of the rectangle from which such
a section can be cut.
Rate:
The rate is to include the cost of all materials required and labour involved in all the
operations, described above.
Core
The core of the flush door shutters shall be a block board having wooden strips held in a
frame constructed of stiles and rails. Each stile and rail shall be a single piece without
any joint. The width of the stiles and rails including lipping, where provided shall not be
less than 45 mm and not more than 75 mm. The width of each wooden strip shall not
exceed 30 mm. Stiles, rails and wooden strips forming the core of a shutter shall be of
equal and uniform thickness. Wooden strips shall be parallel to the stiles.
End joints of the pieces of wooden strips of small lengths shall be staggered. In a
shutter, stiles and rails shall be of one species of timber. Wooden strips shall also be of
one species only but it may or may not be of the same species as that of the stiles and
Face Panel
The face panel shall be formed by gluing, by the hot-press process on both faces of the
core, either laminate or cross-bands and face veneers. The thickness of the cross bands
as such or in laminate shall be between 1.0 mm and 3.0 mm.
Lipping
Lipping, where specified, shall be provided internally on all edges of the shutters.
Lipping shall be done with battens of first class hardwood or as specified of depth not
less than 25 mm. For double leaved shutters, depth of the lipping at meeting of stiles
shall be not less than 35 mm. Joints shall not be permitted in the lipping.
Adhesive
Adhesive used for bonding various components of flush door shutters namely, core,
core frame, lipping, cross-bands, face veneers, plywood etc. and for bonding plywood
shall conform to BWP type, phenol formaldehyde synthetic resin adhesive conforming
to IS 848.
Rates
The rate includes the cost of material and labour and all hardware fitting & fixtures
involved in all the operations.
Rates
The rate includes the cost of material and labour and all hardware fitting & fixtures
involved in all the operations.
MS SHEET DOOR
Door shall be made of 1 mm thick MS Sheet door with 40x40x6 mm angle iron frame
and 3 mm MS gusset plates using flats 30x6 mm for diagonal braces and central cross
piece. All the steel surfaces to be thoroughly cleaned, free from rust, mill scales, dirt, oil
Providing and fixing of Hollow metal fire rated doors as per IS 3614,Part 2 & BS 476,Part
20&22 for stability and integrity. The framing is made out of pressed Galvanised steel
confirming to IS 277with the following specification. Recommended fire door shall have
door tested earlier for maximum rating of 4 hrs tested either with or without vision
panel. All door and frames should be finished with Thermosetting powder coating in
desired RAL shades.Any deviation in specification and sheet thickness other than what is
mentioned in the test certificates are not allowed .approved manufacturer should be
ISO & CE certified & IGBC registered company .Rate should include supply and
installation of door and hardwares set.
Door frame shall be double rebate profile of minimum size 154mm x 77mm madeout of
minimum 1.5 mm thick GPSP sheet.NDRF 154mm x 77mm frames shall be butt jointed
and field assembled with self bolted .All provision should be mortised,drilled and tapped
for receiving appropriate hardware ,Frames should be provided with back plate bracket
and anchor fasteners for installations on a finished plastered masonry wall opening.
Door leaf shall be minimum 49mm thick fully flush double skin door with or without
vision lite.Door leaf shall be manufactured from 1.0 mm minimum thick GPSP sheet.The
internal construction of the door should be rigid reinforcement pads for receiving
appropriate hardware.The infill material shll be Rockwool treated with Viper FRS 881
LH.All doors NSD 12049 shall be factory prepped for receiving appropriate hardware and
provided with necessary reinforcement for hinges,lockand door closers. The edges
should be interlocked with a bending radius of 1.44mm.For pairs of doors astragals has
to be provided on the meeting stile for both active and inactive leaf. Vision lite wherever
applicable should be provided as per manufacturers recommendation with a beeding
and screw from inside.
o Preparation of Surface:- For new work, the surface shall be thoroughly cleaned off all
mortar dropping, dirt dust, algae, fungus or moth, grease and other foreign matter of
brushing and washing, pitting in plaster shall make good, surface imperfections such as
cracks, holes etc. should be repaired using white cement. The prepared surface shall
have received the approval of the Engineer in charge after inspection before painting is
commenced.
o Paint shall be applied with a brush on the cleaned and smooth surface.
Horizontal strokes shall be given, First and vertical strokes shall be applied
immediately afterwards. This entire operation will constitute one coat. The
surface shall be finished as uniformly as possible leaving no brush marks
i. Materials:
a. Paints to be used for interior wall shall be of 100% premium Acrylic emulsion paint
of approved make like NEROLAC ALLS CAPES 24 carrot emulsion/ BERGER luxel
luxury silk emulsion / ASIAN Royal / ICI velvet touch or equivalent make with low
VOC of approved shade
b.Paints to be used for exterior wall shall be of 100% Acrylic emulsion paint (1st
quality) exterior grade of approved make & shade manufactured by reputed
manufacturer like NEROLAC / ASIAN / BERGER / DULOX or equivalent of approved
shade with low VOC.
If for any reason thinning is necessary in case of ready mixed paint, the brand of
thinner recommended by the manufacturer or as instructed by the Engineer-in-
charge shall be used.
Approved, paints, oil or varnishes shall be brought to the site of work by the
Contractor in their original containers in sealed condition. The material shall be
brought in at a time in adequate quantities to suffice for the whole work or at least
a fortnight’s work. The materials shall be kept in the joint custody of the contractor
and the Engineer-in-charge. The empties shall not be removed from the site work,
till the relevant item of work has been completed and permission obtained from
the Engineer-in-charge.
ii. Commencing Work:
Painting shall not be started until the Engineer-in-charge has inspected the items
of work to be painted, satisfied himself about their proper quality and given his
approval to commence the painting work. Painting of external surface should not
be done in adverse weather condition like hail storm and dust storm.
Painting, except the priming coat, shall generally be taken in hand after
practically finishing all other builder’s work.
The rooms should be thoroughly swept out and the entire building cleaned up, at
least one day in advance of the paint work being started.
v. Measurements:
Laying Out:
Fabrication:-
Straightening, shaping to form, cutting and assembling, shall be as per CPWD clause
10.3.2 as far as applicable, except that the words “riveted or bolted” shall be read
as “welded” and holes shall only be used for the bolts used for temporary fastening
as shown in drawings.
Welding : Welding shall generally be done by electric arc process as per IS 816 and
IS 823. The electric arc method is usually adopted and is economical. Where
electricity for public is not available generators shall be arranged by the contractor
at his own cost unless otherwise specified. Gas welding shall only by resorted to
using oxyacetylene flame with specific approval of the Engineer-in-charge. Gas
welding shall not be permitted for structural steel work Gas welding required eating
of the members to be welded along with the welding rod and is likely to create
temperature stresses in the welded members. Precautions shall therefore be taken
to avoid distortion of the members due to these temperature stresses.
The work shall be done as shown in the shop drawings which should clearly indicate
various details of the joint to be welded, type of welds, shop and site welds as well
as the types of electrodes to be used. Symbol for welding on plans and shops
drawings shall be according to IS 813.
As far as possible every efforts shall be made to limit the welding that must be done
after the structure is erected so as to avoid the improper welding that is likely to be
Precautions : All operation connected with welding and cutting equipment shall
conform to the safety requirements given in IS 818 for safety requirements and
Health provision in Electric and gas welding and cutting operations.
Assembly : Before welding is commenced, the members to be welded shall first be
brought together and firmly clamped or tack welded to be held in position. This
temporary connection has to be strong enough to hold the parts accurately in place
without any disturbance. Tack welds located in places where final welds will be
made later shall conform to the final weld in quality and shall be cleaned off slag
before final weld is made.
Erection : The specification shall be as described in 10.3.3 except that while erecting
a welded structure adequate means shall be employed for temporary fastening the
members together and bracing the frame work until the joints are welded. Such
means shall consists of applying of erection bolts, tack welding or other positive
devices imparting sufficient strength and stiffness to resist all temporary loads
and lateral forces including wind. Owing to the small number of bolts ordinarily
employed for joints which are to be welded, the temporary support of heavy
girders carrying columns shall be specially attended. Different members which shall
be fillet welded, shall be brought into as close contact as possible. The gap due to
faulty workmanship or incorrect fit if any shall not exceed. 1.5 mm if gap exceeds
1.5 mm or more occurs locally the size of fillet weld shall be increased at such
position by an amount equal to the width of the gap.
Painting : Before the member of the steel structures are placed in position or taken
out of the workshop these shall be painted as specified in CPWD clause 10.2.2
Iron & Steel Surface :All rust and scales shall be removed by scrapping or by brushing
with steel wire brushes. Hard skin of oxide formed on the surface of wrought iron
during rolling which becomes loose by rusting, shall be removed.
All dust and dirt shall be thoroughly wiped away from the surface.If the surface is
wet, it shall be dried before priming coat is undertaken.
Application : The number of coats including the undercoat shall be as stipulated in
the item.
Under Coat : One coat of the specified ordinary Paint of shade suited to the shade of
the top coat, shall be applied and allowed to dry overnight. It shall be rubbed next
day with the finest grade of wet abrasive paper to ensure a smooth and even
surface, free from brush marks and all loose particles dusted off.
Top Coat : Top coats of synthetic enamel Paint of desired shade shall be applied
after the undercoat is thoroughly dry. Additional finishing coats shall be applied if
found necessary to ensureproperly uniform glossy surface.
Base
KERB STONE(PRECAST):-`
Laying:-
Trenches shall first be made along the edge of the wearing course of the road to
receive the kerb stones of cement concrete of specified grade. The bed of the
trenches shall be compacted manually with steel rammers to a firm and even
surface and then the stones shall be set in cement mortar of specified proportion.
The kerb stones with top 20 cm. wide shall be laid with their length running parallel
to the road edge, true in line and gradient at a distance of 30 cm. from the road
edge to allow for the channel and shall project about 12.5 cm. above the latter. The
channel stones with top 30 cm. wide shall be laid in position in chamber with
finished road surface and with sufficient slope towards the road gully chamber. The
joints of kerb and channel stones shall be staggered and shall be not more than 10
mm. Wherever specified all joints shall be filled with mortar 1:3 (1 cement : 3 coarse
sand) and pointed with mortar 1:2 (1 cement: 2 fine sand) which shall be cured for 7
days.
The necessary drainage openings of specified sizes shall be made through the kerb
as per drawings or as directed by the Engineer-in-Charge for connecting to storm
water drains.
Finishing:- Berms and road edges shall be restored and all surplus earth including
rubbish etc. disposed off as directed by the Engineer-in-charge. Nothing extra shall
be paid for this.
Cement Concrete Pipes (with and without Reinforcement) (Light Duty, Non-
Pressure)
The pipes shall be with or without reinforcement as required and shall be of class
not lesser than NP2. These shall conform to IS 458 and shall be capable of
withstanding a test pressure of 0.07 MPa (7 m head). The reinforced cement
concrete pipes shall be manufactured by centrifugal (or spun) process while un-
reinforced cement concrete pipes by spun or pressure process. All pipes shall be true
to shape, straight, perfectly sound and free from cracks and flaws. The external and
internal surface of the pipes shall be smooth and hard. The pipes shall be free from
defects resulting from imperfect grading of the aggregate mixing or moulding.
Concrete used for the manufacture of un-reinforced and reinforced concrete pipes
and collars shall not be leaner than 1:2:4 (1 cement: 2 coarse sand: 4 graded stone
aggregate). The maximum size of aggregate should not exceed one third of the
thickness of the pipe or 20 mm whichever is smaller for pipes above 250 mm
internal diameter. But for pipes of internal diameter 80 to 250 mm, the maximum
size of aggregate should be 10mm. The reinforcement in the reinforced concrete
pipes shall extend throughout the length of the pipe. The circumferential and
longitudinal reinforcements shall be adequate to withstand the specified hydrostatic
pressure and further bending stresses due to the weight of water when running full
across a span equal to the length of pipe plus three times its own weight.
The minimum clear cover for reinforcement in pipes and collars shall be as given in
Table.
(b) Over 75 mm 15
(vi) When the pipe is laid in a trench in rock hard clay, shale or other hard material
the space below the pipe shall be excavated and replaced with an equalising bed of
concrete, sand or compacted earth. In no place shall pipe be laid directly on such
hard material.
(vii) The method of bedding and laying the pipes under different conditions
(viii) When the pipes are laid completely above the ground the foundations
shall be made even and sufficiently compacted to support the pipe line without any
material settlement. Alternatively the pipe line shall be supported on rigid
foundations at intervals. Suitable arrangements shall be made to retain the pipe line
in the proper alignment, such as by shaping the top of the supports to
fit the lower part of the pipe. The distance between the supports shall in no case
exceed the length of the pipe. The pipe shall be supported as far as possible close to
the joints. In no case shall the joints come in the centre of the span. Care shall be
taken to see that super imposed loads greater than the total load equivalent to the
weight of the pipe when running full shall not be permitted.
Suitably designed anchor blocks at change of direction and grades for pressure lines
shall be provided where required.
(ix) Jointing: Joints are generally of rigid type. Where specified flexible type joints
may also be provided.
(a) Rigid Spigot and Socket Joint : The spigot of each pipe shall be slipped home well
into the socket of the pipe previously laid and adjusted in the correct position. The
opening of the joint shall be filled with stiff mixture of cement mortar in the
proportion of 1:2 (1 cement: 2 fine sand) which shall be rammed with caulking tool.
After a day’s work any extraneous material shall be removed from the inside of the
pipe and the newly made joint shall be cured.
(b) Rigid Collar Joint : The two adjoining pipes shall be butted against each other and
adjusted in correct position. The collar shall then be slipped over the joint, covering
equally both the pipes. The annular space shall be filled with stiff mixture of cement
mortar 1:2 (1 cement: 2 fine sand) which shall be rammed with caulking fool. After a
day’s work any extraneous materials shall be removed from the inside of the pipe
and the newly made joint shall be cured.
(d) Semi Flexible Collar Joint: This is made up of a loose collar which covers two
specially shaped pipe ends . Each end shall be fitted with a rubber ringwhich when
compressed between the spigot and the collar, seal the joint. Stiff mixture of cement
mortar 1:2 (1 cement: 2 fine sand), shall then be filled into the remaining annular
space and rammed with a caulking tool. After day’s work, any extraneous material
shall be removed from the inside of the pipe and the newly made joint shall be
cured.
(e) Internal Flush Joint: This joint is generally used for culvert pipe of 60 cm dia and
over. The ends of the pipe are specially shaped to form a self centering joint with an
internal jointing space 1.3 cm wide the finished joint is flush with both inside and
outside with the pipe wall as shown in Fig. 19.10. The jointing space is filled with
cement mortar 1:2 (1 cement: 2 fine sand) mixed sufficiently dry to remain in
position when forced with a trowel or rammer. After day’s work, any extraneous
material shall be removed from the inside of the pipe and the newly made joint shall
be cured.
(f) External Flush Joint : This joint is suitable for pipes which are too small for
jointing from inside. This joint is composed of specially shaped pipe ends . Each end
shall be butted against each other and adjusted in correct position. The jointing
space shall then be filled with cement mortar 1:2 (1 cement: 2 fine sand) sufficiently
dry and finished off flush. Great care shall be taken to ensure that the projecting
ends are not damaged as no repairs can be readily affected from inside the pipe.
(x) In all pressure pipe lines the recess at the end of the pipe line shall be filled with
jute braiding dipped in hot bitumen or other suitable approved compound. Pipes
shall be so jointed that the bitumen ring of one pipe shall set into the recess of the
next pipe. The ring shall be thoroughly compressed by jacking or by any other
suitable method.
(xi) Testing: For pressure pipes, the completed pipeline shall be tested for pressure
(Known as site test pressure) which shall not be less than the maximum pipeline
operating pressure plus the calculated surge pressure, but in no case shall it exceed
the hydrostatic test pressure. For nonpressure pipes the joints shall be tested as per
procedure laid down under CPWD specs19.2.1.2.
It is of outstanding merit in retention of shape and durability. The heart wood is one
of the most naturally durable woods of the world. It usually remains immune to
white ant attack and insect attack for very long periods. It is, however, not always
immune from fungus attack (rot). Taken as a whole, good quality teak is very
durable, it is relatively easy to saw and work. It can be furnished to a fare surface
and takes polish well. It is generally used for making furniture,door& window and all
important timber construction
Superior Class Teak Wood such as Balarsha, Malabar and Dandeli : Individual hard
and sound knot shall not be more than 12 mm in diameter and the aggregate area of
all the knots shall not exceed one half per cent of the area of the piece. It shall be
close grained.
Rates: The Rates shall be including of cost of all gasket hardware fittings.labours,
transportation etc. All complete as per the direction of Engineer-in-charge,
Supplying fitting and fixing of partially Glazed flush door confirming to IS:2202 (part
01/1991) with select seasoned timber and 32 mm thick block board core framed
with seasoned hard wood battens and bonded at high pressure with phonol
formaldehyde resin under the cross banding process, termite resistant and moisture
proof with both side 1mm thick laminate and fixing of 5mm thick clear glass as per
detailed drawing & design including cost of ss fittings and fixtures such as Dead
lock,Towerbolt,SS hinges , SS handle,Floor spring etc also including cost of
conveyance, taxes of all materials complete as per direction of Engineer-in-charge.
Providing and fixing aluminium powder coated louvered ventilator confirming to ISI
with 4mm thick tinted/other glass. Including cost of all gasket hardware
fittings.labours, transportation etc. All complete as per the direction of Engineer-in-
charge,
Design, supply and install semi unitized structural glazing system/curtain wall
designed to withstand the design wind pressure of 1.8 kPa confirming to IS -875 part
III.The system is with microwave cured EPDM gaskets in exposed and unexposed
The system designed include pressure equalization with barrier gaskets for
improved thermal performance and weather performance, drainage at ground floor
level thru bottom, spandrel panel shall have pressure release & condensation
drainage provisions, to accommodate building movements, thermal expansions and
the seismic movements. All metal joints in the wet area shall be small joint sealant
applied to ensure water tightness.
The extruded aluminum sections of Alloy 6063 T6 & T5 and tolerances confirming to
DIN standard from approved extruder. All the internal and external visible surfaces
shall have average 65 microns Powder Coating finish. Glazing shall be with double
layer of 6mm toughened glass one reflective and one clear with a 12 gap filled with
argon gas for energy efficiency and thermal insulation.
The window system shall have a u value of 0.31, SHGC(g value)- 0.3 and VLT 50%
with high acoustics level. The vendor is to provide execution drawings and get the
same approved before construction. The rates shall be inclusive of drawings, design
for requisite wind load, getting the design approved, supply, installation inclusive of
all taxes, T&P etc. complete including all support structural members necessary
hardwares, sealants, tapes etc. complete and all inclusive.
Design, supply and install semi unitized structural glazing system/curtain wall
designed to withstand the design wind pressure of 1.8 kPa confirming to IS -875 part
III.The system is with microwave cured EPDM gaskets in exposed and unexposed
area, structural and weather sealants of GE or approved make, Norton spacer
tape,backer rod, Bracketing system with MS hot dip galvanized brackets designed to
accommodate three dimensional movements, SS 316 grade fasteners and anchor
The system designed include pressure equalization with barrier gaskets for
improved thermal performance and weather performance, drainage at ground floor
level thru bottom, spandrel panel shall have pressure release & condensation
drainage provisions, to accommodate building movements, thermal expansions and
the seismic movements. All metal joints in the wet area shall be small joint sealant
applied to ensure water tightness.
The glazing system shall have a u value of 0.31, SHGC(g value)- 0.3 and VLT 50% with
high acoustics level. The vendor is to provide execution drawings and get the same
approved before construction. The rates shall be inclusive of supply, installation
inclusive drawings, design for requisite wind load, getting the design approved, of all
taxes, T&P etc. complete including all support structural members necessary
hardwares, sealants, tapes etc. complete and all inclusive.
Design, supply and install of fire stop smoke seal at every floor level with 48kg/m³
rockwool of approved make install in a G.I Tray of min 2.5mm thk . All screw used
shall be of SS grade.
CANOPYUSING LAMINATEDGLASS
Providing and fixing and finishing of Canopy glass with 12.5mm(5mm clear H.S
glass+1.52mm(4layer of PVB)+6mm clear toughened )Laminated Glass with spider
fitting including 4way, 2way spiders 1 way spiders and Routels bolt(316 grade) for 12
mm fixed glass fixed at 100x50x2.5 & 75x50x2.5 mm square tube M.S Structure etc.
complete as per the direction of Engineer-in-charge
CLADDING
Providing and fixing of Cladding with external wall with solid exterior grade compact
high pressure laminates as per EN 438-6 type EDS and EGS manufactured using
specially treated acrylic resin under high pressure and temperature and hardened
with electron beam curing providing weather resistence and UV resistence. The cost
is inclusive of Aluminum framework for the same, fixing details with Aluminum/MS
cleats and all necessary arrangement inclusive cost of adhesive, all hardware
,materials ,labour & T&P etc. complete as per the direction of Engineer-in-charge.
POLYCARBONATE SHEET:
STRUCTURAL GLAZING
Design, supply and install semi unitized structural glazing system/curtain wall
designed to withstand the design wind pressure of 1.8 kPa confirming to IS -875 part
III.The system is with microwave cured EPDM gaskets in exposed and unexposed
area, structural and weather sealants of GE or approved make, Norton spacer
tape,backer rod, Bracketing system with MS hot dip galvanized brackets designed to
accommodate three dimensional movements, SS 316 grade fasteners and anchor
bolts of approved make, nylon separators to prevent bi-metallic corrosion, all
complete required to perform as per specification and drawing in conjunction with
BOQ.
The system designed include pressure equalization with barrier gaskets for improved
thermal performance and weather performance, drainage at ground floor level thru
bottom, spandrel panel shall have pressure release & condensation drainage
provisions, to accommodate building movements, thermal expansions and the
seismic movements. All metal joints in the wet area shall be small joint sealant
applied to ensure water tightness.
The extruded aluminum sections of Alloy 6063 T6 & T5 and tolerances confirming to
DIN standard from approved extruder. All the internal and external visible surfaces
shall have average 65 microns Powder Coating finish. Glazing shall be with double
layers of 6mm toughened translucent glass with a 12 gap filled with argon gas for
energy efficiency and thermal insulation.
The extruded aluminum sections of Alloy 6063 T6 & T5 and tolerances confirming to
DIN standard from approved extruder. All the internal and external visible surfaces
shall have average 65 microns Powder Coating finish. Glazing shall be with double
layers of 6mm toughened translucent glass with a 12 gap filled with argon gas for
energy efficiency and thermal insulation.
Min 750mm wide plinth protection by providing 50mm thick of cement concrete
1:3:6 (1 cement :3 coarse sand : 6 graded stone aggregate 20 mm nominal size) over
75mm thick bed of dry brick ballast 40 mm nominal size, well rammed and
consolidated and grouted with fine sand shall be provided around all buildings.
CHEMICAL REBARING
Rates
The rate includes the cost of material and labour and involved in all the operations.
CORE CUTTING
Core cutting of RCC Slab of required diameter and depth of the slab with the help of
required machineries as specified and direction of CLIENT/Project Manager specified
as per BOQ.
Rates
The rate includes the cost of material and labour and involved in all the operations
Note: In the List of recommended above, out of makes mentioned in the list, only 1st make shall
be quoted for and used. However if due to non-availability or any other technical reasons,
the alternative make is allowed, it shall be subject to prior approval of the Project Manager
and price adjustment.
5. The contractor shall produce all samples including natural stones, before procurement of
the materials, for approval of the Architects/Project Managers.
7. In the event, the contractor is permitted to use the material of lower preference because of
valid reasons, then the contract rates for the relevant items of work shall be suitably
adjusted on the basis of variation in prices of the materials of first preference and those
actually used. If the prices of the materials used are higher than the material of the first
preference, the owner shall not be liable to make any enhanced payment for the affected
items of work on this account.
8. In respect of materials for which approved makes are not specified above, these will be
makes to be decided by the Architects/Project Managers and as per samples getting
approved.
TECHNICAL SPECIFICATIONS:
Technical Specification Page 252
PUBLIC HEALTH ENGINEERING
1. INTRODUCTION
2. SCOPE
The scope of Public Health Engineering Services though not limited can be classified as follows
Water treatment system for meeting domestic & drinking water quality requirement in
acceptance limits as per IS 10500-2012
1.1 Scope
The General character and the scope of work to be carried out under this section as illustrated
in the drawings, specifications and scope of work attached herewith. The contractor shall carry
out and complete the said work under this contract in every respect in conformity with the rules
and regulations of the local authority. The Contractor shall furnish all labour, materials,
appliances, tools and equipment necessary for the work for plumbing services installation
including testing and commissioning as specified herein, and as per the relevant Bureau of
Indian Standards (BIS), British Standards codes, and as shown on the drawings. This also
includes any material, appliances and equipment not specifically mentioned here in or noted on
the drawings as being furnished or installed which are necessary and customary to make a
complete installation properly connected and in working order.
Carryout all incidental works connected with plumbing services installation such as excavation
of trenches and back filling, cutting and chasing in concrete and brick and making good,
cutting/drilling holes through walls, floors, and grouting for fixing of fixtures/equipment and so
forth.
Furnish and install complete workable plumbing services installation as shown on the drawings
and described in this specification and as per the latest Bureau of Indian Standards (BIS), British
Standards (BS) specifications including all that which is reasonably inferred to all the buildings,
internally and externally.
Complete installation of the sewerage and sewerage appurtenances internally as well as around
the building.
Co-operation with other trades in putting the installation in place. Any work done without
regards or consultation with other trades, shall be removed by the contractor without
additional cost to the Owner, to permit proper installation of all other work, as desired by the
Architect/Consultant.
Cleaning of all plumbing and sanitary fixtures, testing and providing the satisfactory
performance of all fixtures at the time of buildings are handed over to the Owner.
It is the responsibility of the contractor to take care of all the fixtures fitted until the time of
handing over to the Architect/Consultant.
Painting of all exposed pipes shall be done by contractor as specified in the specification.
Assume full responsibility for getting the entire installation duly approved by the authorities
concerned and for all expenses in connection with the same. Assume responsibility for
obtaining and delivering to the Owner certificate of final inspection and approval by the
concerned authorities.
All work performed by the contractor shall be through licensed plumbing supervisor possessing
a valid plumbing contractor’s license employing Engineers, Technicians, Foremen, Plumbers,
Masons, Helpers, etc., as required.
Sanitary Fittings
IS 2548 ( Part 1&2 ) : Specification for plastic seats and covers for water
closets.
Pumps
(Domestic type).
IS 12235 ( Parts 1 to 11) : Methods of test for unplasticized PVC pipes for potable
water supplies.
IS 1239 –(Part I) : Specifications for mild steel tube, tubular and other
steel pipe fittings.
IS 1239 –(Part II) : Specifications for mild steel tube, tubular and other
steel pipe fittings.
IS 732 & IS 2274 : Indian Standard code of practice for electrical wiring &
installation.
The installation shall be in conformity with the bylaws and requirements of the local authority in
so far as these become applicable to the installation. Wherever this specification calls for, a
higher standard of materials and /or workmanship than those required by any of the above
regulations and standards, then this specification shall take precedence over the said
regulations and standards.
Wherever drawings and specifications require something that may conflict with the regulations,
the regulations shall govern. This shall be referred to the Superintendent for arbitration.
The tender drawings indicate the extent and general arrangement of the fixtures, drainage
system, etc.. The drawings indicate the points of supply and termination of work shall be
installed as indicated in the drawings. However, any changes found essential to co-ordinate
with this work and other trades shall be made without any additional cost. The drawings and
specifications are meant for the assistance and guidance of the contractor, and exact location,
distance and levels will be governed by the individual building and site conditions. Therefore,
approval of the Superintendent shall be obtained before commencement of work.
Floor plans, Enlarged toilet details, schematic showing water supply and sanitary
installation works
Contractor shall provide exact length and sizes of all piping on all floors and vertical
stacks.
Ground and invert levels of all drainage pipes together with location of all manholes and
connections up to outfall.
Run of all water supply lines with diameters, location of control valves and access panels.
Contractor shall provide Location of all mechanical equipment with layout and piping
connections.
Contractor shall provide four sets of catalogues, performance data and list of spare parts
together with the name and address of the manufacturer for all electrical and
mechanical equipment provided by him.
All “Warranty Cards” given by the manufacturers shall be handed over to the
Superintendent.
1.8 Materials
Materials shall be of approved make and quality specified. They shall conform to the respective
Bureau of Indian Standards, British Standards Specifications and supported by Manufacturing
Certificate / test certificate.
Samples of all materials shall be as per the list of approved brand manufacture, which shall be
approved by the Superintendent before placing the order.
In any case of non availability of materials in metric sizes, the nearest size of FPS units shall be
provided with prior approval of the Superintendent at no extra cost to the owner.
1.9 Guarantee
The contractor shall guarantee both the material and workmanship of first class quality
corresponding to standard engineering practice. Any defective materials / workmanship shall
be rejected, the contractor has to rectify / replace at his own cost. Guarantee certificate of the
materials supplied shall be handed over to the owner.
SECTION – II: SOIL, WASTE AND VENT PIPES AND RAIN WATER PIPES
Materials shall be of the approved make and quality specified. They shall conform to the
respective Bureau of Indian Standards, British Standards Specifications, supported by
Manufacturing Certificate and any other specification referred to herein.
Pipes and fittings shall be fixed truly vertical, horizontal or on slopes as required in neat
manner.
Pipes shall be fixed in a manner as to provide easy accessibility for repair and
maintenance and shall not cause obstruction in shafts, and in suspended ceilings.
Pipes shall be fixed securely to walls and ceilings by suitable pipe supports at intervals
specified.
Access door for fittings and cleanouts shall be located that they are easily accessible for
repair and maintenance.
Soil, waste & vent pipes shall be PVC pipes & fittings.
PVC (SWR) class pipes conforming to IS 13592 of dia 63mm up to 250mm dia of Type A are used
in rain water & ventilation and Type B for soil and waste discharging system shall be used. The
pipes shall be supplied in nominal lengths of 2, 3, and 4 or 6 meters, tolerance on specified
lengths shall be +10mm and – 0mm. Any physical test requirements shall be as per IS 13592.
And Pipe of higher Dia i.e. 160mm Dia. and above shall be agricultural series (6kg / sq. cm
pressure rated) made as per IS 4985.
1.2.1 HANDLING
Because of their light weight, there may be a tendency for the PVC pipes to be thrown much
more. Reasonable care should be taken in handling and storage to prevent damage to the pipes.
Contractor should hold the fullest responsibility in this case. On no account the pipes should be
dragged on the ground. Pipes should be given adequate supports at all times.
1.2.2 LAYING
The PVC pipes shall be laid under the floors below slab or on walls either buried or exposed as
the case may be, as shown in the drawings. The minimum thickness of fittings shall be of 3.2
mm. the fittings shall be of injection mould type with solvent cement joint or rubber ring joint.
The pipes and fittings shall be capable of withstanding sun’s rays. PVC pipes laid below slab or
suspended in ceiling shall be supported by angle brackets / supports as detailed in the drawings.
1.2.3 JOINTING
The jointing of pipes to fittings shall be done as per the manufacturer’s instructions /
recommendations. The UPVC pipes and fittings shall be joined with Solvent Cement and jointing
shall be carried out as follows:
2. All burrs from the internal and external surfaces should be removed.
3. The spigot should be marked with a pencil line and a distance equivalent to the socket
depth. Clean the surface within the marked area.
4. Apply uniform coat of solvent cement on the external surface to the pipe and a lighter
coat on the internal surface of the fitting.
5. Insert the pipe end into the socket of the fitting and push it in up to the mark.
6. Remove the excess solvent cement and hold the joint firmly in position for 30seconds to
dry. Gluing should be avoided in a rainy or foggy weather.
1.2.4 TESTING
PVC pipes and fittings shall be tested for water tightness in accordance with IS 13592. The
openings of the pipes shall be sealed for the section to be tested. The water pressure of 1mtr
water column to be applied for a period of 15 minutes. The Engineer-in-Charge shall examine
carefully all the joints for leakage.
The PVC pressure pipes and fittings shall be used for conveying waste water from wash basins,
Urinals, kitchen sinks, floor drain connecting to washing machines, etc. The pipes shall be class
III, 6 Kg/cm2. PVC pipes and fittings shall be jointed with solvent cement. The pipes shall
conform to IS 4985. Fittings shall be of injection moulded PVC conforming to IS 7634 (Part1) -
1975.
The pipe laying and jointing shall be done in accordance with IS 7634 (Part 3) – 1975. Pipes shall
be cut to size and chamfered well. Pipes and fittings shall be jointed using solvent cement or
rubber ring joints. The pipes and fittings shall be jointed accurately without any stress to
achieve leak proof joints.
1.3.2 TESTING
The method which is commonly in use is filling the pipe with water, taking care to evacuate any
entrapped air and slowly raising the system to the test pressure. The water pressure of 1mtr
water column to be applied for a period of 15 minutes.
Standard weight, dimension and DRIP SEAL required for joints shall be as follows:
inches mm mm kg. mm mm
2 50 3.5 8.5 73 25
3 75 3.5 12.7 99 25
TOLERANCES
Tolerances on the external diameter of the barrel as mentioned below. The internal diameter
of the socket and the depth of socket shall be as follows:
150 + 4.0
5 5 5 5
Socket {Thickness, H 6 6 6 6
{Internal depth, J 60 66 70 75
All lumps, blisters and excess coating shall be removed from the socket and spigot end of each
pipe. The outside of the spigot and the inside of the socket shall be wire brushed and wiped
clean and dry and free from oil and grease before the pipe is laid.
Closing the Ends of Pipe to Prevent Entry of Foreign Materials While Laying Pipe
Every precaution shall be taken to prevent foreign material entering the pipe while it is being
placed in the line. If the pipe laying team cannot put the pipe into the trench and in place
without getting earth into it, the Engineer in charge may order a heavy tightly woven canvas
bag of suitable size be placed over each end and left there until the connection is to be made to
the adjacent pipe that before lowering the pipe into the trench. During laying operations, no
debris, tools, clothing or any other material shall be placed in the pipe. After laying and jointing
of a reach is completed the two free ends shall be kept closed to prevent entry of foreign
materials, rodents and other animals.
The cutting of pipe for inserting fittings or closure pieces shall be done in a neat and good
workmanship without any damage to the pipe so as to leave a smooth end at right angles to the
axis of the pipe. For this purpose use of a pipe cutter is recommended. Pipe cutting machines
are recommended for large dia of pipes. When pipe-cutting machines are not available for
cutting pipes of large diameters, the electric arc cutting method may be permitted using carbon
or steel rods.
Only qualified and experienced workmen shall be employed on this work. When the pipe-
cutting machine is not available and the site conditions do not permit pipe cutting by machine,
the pipe can be cut using a chisel. Flame cutting of pipes by means of ox-acetylene torches shall
not be allowed.
On level ground, the socket ends should face the upstream. When the line runs uphill the
socket ends should face the upgrade. The permitted tolerance for deflection for lead joint shall
be 2.5 millimetres.
Jointing
Jointing of socket and spigot pipes is done by DRIP SEAL (under dry conditions).
1.4.2 Testing
The method which is commonly in use is filling the pipe with water, taking care to evacuate any
entrapped air and slowly raising the system to the test pressure. The pressure of 1mtr water
column to be applied for a period of 60 minutes.
Cast Iron Pipes shall be measured along the centre line of the pipeline including the specials in
running meter (Rmt). Quoted rate shall include specials and the pipes shall be measured
between:
a. Chambers: Shall be recorded from the inside of one chamber to inside of another
chamber.
1.5 MS BRACKETS
The brackets should be of 25x5mm MS angle and 50x 5 mm MS flat. The length and profile of
bracket shall be as per site conditions. The brackets shall be provided hot dip galvanizing after
fabrication. The brackets shall be fixed in true alignment and level. The bracket shall be fixed to
the RCC members using 8mm dia anchor fasteners in adequate number based on length of
bracket. The brackets can be fixed to masonry wall using holdfast arrangement. In such cases
curing shall be done for at least 3 days.
The pipes shall be fixed to the brackets with the help of threaded U bolts or C clamp with 25x 6
mm GI Nut bolts. Spacing of bracket shall be governed by the pipe material.
The khurras shall be straight type or bend type as per the location of outlet. It consists of a rigid
PVC body, leaf trap with grating, PVC sheet 400mmx400mm welded to collar. The khurra should
be fixed firmly on to the parapet wall or roof slab with concrete. Due consideration shall be
given to the finished level of roof while fixing the same.
The pipes shall be with or without reinforcement as required and of the class NP2 as specified.
These shall confirm to IS 458-2003. The reinforced cement concrete pipes shall be
manufactured by centrifugal (or spun) process. All pipes shall be true to shape, straight, perfect
sound and free from cracks and flaws. The external and internal surface of the pipes shall be
smooth and hard. The pipes shall be free from defects resulting from imperfect grading of the
aggregate, mixing or moulding.
Loading, transporting and unloading of concrete pipes shall be done with care. Handling shall be
such as to avoid impact. Gradual unloading by inclined plane or by chain block is recommended.
All pipe sections and connections shall be inspected carefully before being laid. Broken or
defective pipes or connections shall not be used. Pipes shall be lowered into the trenches
carefully. Mechanical appliances may be used. Pipes shall be laid true to line and grade as
specified. Laying of pipe shall proceed upgrade of a slope.
If the pipes have spigot and socket joints, the socket end shall face upstream in the case of pipe
with joints to be made with loose collars. The collar shall be slipped on before the next pipe is
laid. Adequate and proper expansion joints shall be provided where directed.
In cases where the natural foundation is inadequate the pipes shall be laid either in concrete
suitably designed structure as specified. If a concrete cradle bedding is used the depth of
concrete below the bottom of the pipe shall be at least 1/4th of the internal dia and shall
extend up to the sides of the pipe at least to a distance of ¼ of the outside diameter of pipes
300 mm dia.. The pipes laid in trenches in earth shall be bedded evenly and firmly and as far up
the haunches of the pipe as to safely transmit the load expected from back fill through the pipe
to the bed. This shall be done either by excavating the bottom of the trench to fit the curve of
the pipe or by compacting the earth under around the curve of the pipe to form an even bed.
Necessary provision shall be made for joints wherever required.
When the pipe is laid in the trench in rock, hard clay, or other hard material, the space below
the pipe shall be excavated and replaced with an equalizing bed of concrete, sand or compact
earth. In all place pipe shall be laid directly on such hard material.
When the pipes are laid completely above the ground the foundations shall be made even and
sufficiently compacted to support the pipe line without any material settlement. Alternatively
the pipe line shall be supported on PCC saddle blocks. Similar arrangement shall be made to
retain the pipe line in the proper alignment, such as by shaping the top of the supports to fit the
lower part of the pipe, the distance between the supports shall be no case exceed the length of
the pipe. The pipe shall be supported as far as possible close to the joints. In no case shall the
joint come in centre of the span. Care shall be taken to see that superimposed loads greater
than the total load equivalent to the weight of the pipe when running full shall not be
permitted.
Joints are generally of rigid type. When specified flexible type joints may also be provided.
The spigot of each pipe shall be slipped home well in to the socket of the pipe previously laid
and adjusted in the correct position. The opening of the joints shall be filled with stiff mixture of
cement mortar in the proportion 1:2 (1cement, 2fine sand) which shall be rammed with
caulking tool. After a day’s work any extraneous material shall be removed from the inside of
the pipe and the newly made joint shall be cured.
1.8.1 Material
The pipes covered in this standard are not meant for potable water applications. The
dimensions are grouped into two sections Section A & B. Section A covers dimensions of straight
pipes and all such fittings which normally from part of pipeline and which are subjected to same
conditions. Section B includes dimensions of fittings, which are commonly used but do not form
part of the normal pipeline.
1.8.2 Laying
The pipes shall be carefully laid to the levels and gradients shown in the plans and sections by
making use of sight rails and boning rod and socket up the gradient. The pipes crossing the road
shall be encased in Plain Cement Concrete of 1:3:6 to the required depth as per the drawings
and bill of quantities. The pipes laid in the soil shall be enclosed with selected sand filling as per
the bill of quantities.
1.8.3 Jointing
Hemp rope socked in neat cement slurry shall be passed round the joint and inserted in it by
means of caulking tool. More skins of yarn shall be added and well rammed. Cement mortar
with one part of cement and one part of sand with minimum water content, but on no account
soft or sloppy, shall be carefully inserted by hand into the joint & more cement mortar added
until the space of the joint has been filled completely with tightly caulked mortar. The joint shall
be then finished off neatly outside the socket at angle of 45 degree.
1.8.4 Curing
1.8.5 Testing
As per IS 4127 – 1983 – code of practice for laying of glazed stoneware pipes, the pipelines and
fittings shall be subjected to a test pressure of at least 2.5 m head of water at the highest point
of section under test. This pressure shall be maintained for not less than 30 minutes. The
contractor shall also carry out the smoke test for the drains and sewers. Any leakage will be
visible & the defective part should be cut out and made good.
Stoneware pipes shall be measured along the centreline of the pipeline including the specials in
running meter (Rm.) between:
a. Chambers: Shall be recorded from the inside of one chamber to inside of another
chamber.
b. Gully trap and chamber: shall be recorded between socket pipe near gully trap and
inside of chamber.
1.1 General
All fixtures shall be fixed in a neat workman like manner true to line and as recommended by the
manufacturer or shown in the drawings. Care shall be taken to fix all fixtures, brackets and
accessories by proper wooden cleats, rawl plugs, bolts and nuts.
Care shall be taken in fixing all approved chromium plated (CP) single lever fixtures and
accessories so as not to leave any tool marks or damages on the finish. All such fixtures shall be
tightened with fixed spanners. Use of `Stiltson' type pipe wrenches with toothed jaws shall not
be allowed.
All fixtures shall be thoroughly tested after connecting the drainage and water supply system. All
fixtures shall be thoroughly finished and any leakage in piping valves and waste fittings corrected
to the complete satisfaction of the Consultant/Engineer.
Upon completion of the work, all labels, stickers, plasters, etc. shall be removed from the fixtures
and all fixtures shall be cleaned with soap and water so as to present a neat and clean toilet.
All appliances, fixtures and fittings shall be provided with all such accessories are required to
complete the item in working condition whether specifically mentioned or not in the schedule of
quantities, specifications and drawings. Accessories shall include proper fixing arrangements,
brackets, nuts-bolts, washers, screws and required connection pieces etc.
The closet shall be white or colored as per BOQ and made of vitreous China and shall be of the
best quality manufactured by an approved firm, and fixed by approved means. It shall have 100
mm dia `P` or `S` trap depending on the location of water closets and soil stacks with effective
a. Double flapped heavy urea formaldehyde seat cover of approved make quality and color
with rubber buffers and C.P. brass screws fixed to the pan.
b. Exposed ceramic cistern of approved design.
c. Cast-iron chair or rag bolt for wall hung type with C.P bolt & nut.
They shall be white or colored as per BOQ and of vitreous China with best quality manufactured
by an approved firm and size as specified. Oval/circular wash basins shall be supported on a RC
counter with necessary steel reinforcement and rectangular wash basins with or without
pedestals shall be supported by a pair of rag bolts of approved design. The washbasin shall be
circular or oval shape below or above counter or rectangular with or without pedestal type as
specified in Schedule of Quantities. The basin shall be provided with waste coupling, bottle trap,
angle cocks, pillar cock/ basin mixer, connecting pipes and other accessories. The flow rate of
pillar cock or basin mixer shall be less than 2 liters per minute at 60 psi pressure.
The shower unit shall be brass chromium plated with hot and cold single lever mixer / 3/4 way diverter /
rain shower unit along with CP spout, pressure jet set. The shower unit shall be fitted with an overhead
shower set comprising of shower arm, rose, wall mixer etc., complete with wall flange. The make and
model shall be as specified in the BOQ.
Bucket spout.
Hand shower
Overhead shower with rose-Rabbit cleaning system / Normal.
Exposed mixer / concealed mixer – as applicable
Rain shower set(24”x24”/normal size)
1.5 Sink
Bath tub shall be of approved color made of Acrylic plastic, comprising of Hot & cold mixer, with
telephonic shower, Tub filler etc., complete with overflow arrangement, waste coupling.
These shall be of brass CP .The make and model shall be as specified in the BOQ. These shall be
fixed by means of stainless steel counter sunk screws to wooden/ plastic cleats firmly
embedded in the wall.
15 mm CP health faucet with 1.0m long flexible tube with end nuts & Hook.
1 No 15mm CP brass angular stop cock with wall flange
Hook with CP brass counter sunk screws.
These shall be of best approved make and type and capacity as per schedule of quantities.
They shall be mounted on the wall with necessary bolts of approved make. They shall have
braided hose inlet pipe, angle stop cocks, Built in safety valve, non-return valve. These shall be
measured per number and the quoted rate shall include.
Cost of water heater with all the built -in electrical accessories like pilot lamp, thermostat,
standard length of cable and 3 pin 15A plug. Remote control assembly.(optional)
Two angle stop cocks and connection pipes.
Fixing accessories like bolts, nuts, etc.
These shall be of brass, CP. The make and model shall be as specified in the BOQ. These shall be
fixed by means of Teflon tape, extension nipple of suitable length shall be provided, if required.
The stopcock shall be provided with CP wall flange.
A bibcock is a draw off tap with a horizontal inlet and free outlet and stopcock (stop tap) valve
with a suitable means of connections for insertion in a pipeline for controlling or stopping the
flow. They shall be of specified size and shall be screw down type. The closing device should
work by means of a disc carrying a renewable non-metallic washer which shuts against water
pressure on a seating at right angles to the axis of the threaded spindle which operates. The
handle shall be either crutch or butterfly type securely seated pattern. The cocks (taps) shall
open in anticlockwise direction. The bib cock and stop cock shall be polished bright (Chrome
plated).
2.1 Urinal
Urinal shall be back inlet type, white colored and of vitreous China with best quality manufactured by
an approved firm. The urinal shall be fixed with hangers and brackets. The urinal shall be provided with
auto flush system with sensor, solenoid valve / pneumatic push cock / angle valve etc., complete. Make
and model shall be as specified in the BOQ. The complete set shall comprise of the following.
Urinal with auto flush system along with battery / electrically operated solenoid valve / with
push cock.
Fixing brackets,
32mm CP Bottle Trap, dome type grating, spreader etc., if the specified model is not having in-
built units as indicated above the same shall be part of the scope of work.
CP wall flanges (if required).
2.3 Jacuzzi
Jacuzzi shall be of approved color made of Acrylic plastic, comprising of Hot & cold mixer, with
telephonic shower, overhead shower, Tub filler, pressure pump, pressure tank, multiple jets etc.,
complete with overflow arrangement, waste coupling.
The bidet shall be white or colored as per BOQ and made of vitreous China and shall be of the
best quality manufactured by an approved firm, and fixed by approved means. It shall have 100
mm dia `P` or `S` trap depending on the location of bidet and soil stacks with effective seal. Bidet
shall be provided with its fittings, seat cover, CI bracket/rack bolt for support,15mm CP bidet cock
with connection to spray outlet,15mm CP angle cock , CP bolts and nuts with all the
arrangements of approved make.
Towel rack shall be of C.P. with reinforced bends and circular flanges. The size of the rail shall be
as specified. The bracket shall be fixed by means of stainless steel screws to wooden/plastic cleats
firmly embedded in the wall.
Toilet paper holder shall be of chromium plated as specified in the Material specification.
These shall be of CP as specified in the material specification. These shall be fixed by means of
stainless steel screws to wooden / plastic cleats firmly embedded in the wall.
The grab bars shall be of stainless steel of approved quality. The size and location shall be as
specified in the BOQ.
The floor trap frame and grating shall be of approved material as specified in the BOQ. The trap
shall be fitted with stainless steel square grating. A minimum of 40mm depth of water seal shall
be provided in the trap.
These shall be of CP as specified in the material specification. These shall be fixed by means of
stainless steel screws to wooden / plastic cleats firmly embedded in the wall.
These shall be of CP as specified in the material specification. These shall be fixed by means of
stainless steel screws to wooden / plastic cleats firmly embedded in the wall.
The electric hand drier shall be twin blower type integrated with timer range 0 to 3 minutes. The
drier shall be fully automatic. The make and model shall be as specified in the BOQ.
The hand drier shall be no touch operating type with solid state time delay to allow user to keep
hand in any position. The hand drier shall be fully hygienic, rated for continuous repeat use (CRU).
The rating of hand drier shall be such that time required to dry a pair of hands up to wrists is
approximately 30 seconds. The hand drier shall be of wall mounting type suitable for 230 V, single
phase, 15A, 50 Hz, AC power supply
1.1 General
1.1.4 Training
It is the responsibility of the Contractor to train the Owner’s personnel in the operation
and maintenance of the system.
Valves shall be capable of operating and maintaining automatically the respective delivery
pressure and flow rates as indicated and shall not be liable to creep. Valves shall also be
capable of maintaining the pre-set downstream pressure under static condition.
Butterfly valves shall be slim seal, short wafer type with standard finish. The valves shall be suitable for
mounting between flanges drilled to ANSI 125. The valve body shall be cast iron. The disc shall consist of
disc pivot and driving stem shall be in one piece centrally located. The disc shall move in bearings on
both ends with ‘O’ ring to prevent leakage. The seat shall be molded with black nitrile rubber or nylon
and shall line the whole body. The spindle shall be of AISI 41 steel. The valve shall be suitable for a
working pressure of 16.5 kg/sq.cm and shall be complete with flow control lever and notches, factory
machined companion flanges and bolts and nuts. These valves conform to BS 5155 with electro steel
nickel coated SG Iron (N) and seat material EPDM3.The pressure rating & dia of valve shall be indicated
on the valve body for proper identification.
The ball valve shall be of high-pressure type and shall be of sizes as specified and/or shown in
the drawings the normal size of a ball valve shall be that, corresponding to the size of the pipe
to which it is fixed. Ball valves shall have body of carbon steel. The ball and the shaft shall be of
stainless steel. The seat shall be of PTFE. The valve shall be complete with socket weld ends and
the float of copper sheet. The minimum thickness of copper sheet used for making the float
shall be 0.45mm for a float exceeding 115mm dia. The body of the high pressure ball valve
when assembled in working condition with the float immersed to not more than half of its
diameter shall remain closed against a test pressure of 3.5kg/sqcm. The ball valve shall
generally conform to IS specification No.1703:1977. The weight of ball cock and the size of the
ball cock shall be as per IS specification.
Body : Brass
Pressure rating : PN 10 / 16 / 25
CI Frame with Covers: Covers shall be of heavy duty cast iron with lifting hooks as per IS 1726 – 1991.
The details given in the drawing and fixed on the CI frame embedded in concrete. Cover placed on the
frame shall be airtight. Weight of the cover on frame shall be specified in the schedule of quantities. All
castings shall be free from voids whether due to shrinkage, gas inclusion or other causes. Covers shall
have a raised checkered design on the top surface to provide an adequate non-slip grip. The sizes of
covers specified shall be taken as the clear internal dimensions of the frame.
The covers and frames shall be coated with a black bituminous composition. The coating shall
be smooth and tenacious. It shall not flow when exposed to a temperature of 63° C and shall
not brittle as to chip off at a temperature of 0° C.
b. Deburring / Bevelling: Burrs should be removed from the outside and inside
of pipe with a deburring tool/ pocket knife or file otherwise burrs may
prevent proper contact between pipe and fittings during assembly. Also the
outer end of pipe should be slightly chamfered.
e. Assembly: After applying the solvent cement on both pipe and fitting socket,
pipe should be inserted into the fitting socket within 20 seconds, and
rotating the pipe ¼ to ½ turn while inserting so as to ensure even distribution
of solvent cement within the joint. The assembled system should be held for
10 seconds (approximately) in order to allow the joint to set up.
An even bead of cement should be evident around the joint and if this bead is not continuous
remake the joint to avoid potential leaks.
Solvent cement set and cure times shall be strictly adhered to as per the below mentioned
table.
Size
Ambient
Temperature 1/2" to 1 1/4" 1 1/2" to 3" 4" to 8"
Above 15 deg C 1 hr 2 hr 6 hr
4 to 15 deg C 2 hr 4 hr 12 hr
Below 4 deg C 8 hr 16 hr 48 hr
Inch Ft Ft Ft Ft Ft
2 6 5 1/2 5 3 1/2 3
3 7 7 6 4 3 1/2
Colour code for water-supply pipes shall be as per standard requirement. Details as mentioned
below.
A WATER
The entire water distribution network is to be disinfected by using residual chlorine of 0.2 ppm
for a period of 2 (two) hours. The entire chlorinated pipe network is to be flushed out with
fresh water before the water supply system is put into operation for domestic usage.
1.6.1 General
This section deals with different type of valves like butterfly valves, gate valves, ball valves,
check valves, balancing valves and Strainers and pressure gauges. The contractor shall refer to
the approved make of materials specified in the document & relevant drawings.
Valves shall be provided on branch pipe connections to mains and at connection to equipment
where indicated. All valves are to be located for easy access. All valves shall be supported
wherever necessary with MS brackets. Valves shall comply with IS 780 (Class I) for C.I sluice
valves and IS 778 for G.M valves and tested.
Pressure gauges shall have outer diameter not less than 115mm with 10mm BSP full thread,
brass body siphon and gauge cock of size10mm. Dial gauges shall have adequate response
for the pressures encountered within the specified (Range 0-15Kg/sq.cm).
1.6.2 Valves
All valves (gate, ball, check, safety) shall be of brass suitable for the particular service as
specified. All valves shall be of the particular duty and design as specified. Valves shall either
be of screwed type or flanged type, as specified, with suitable flanges and non-corrosive bolts
and gaskets. Tail pieces as required shall be supplied along with valves. Gate, ball and check
valves shall conform to Indian Standard IS: 776 and non-return valves and swing check type
reflux to IS: 5312.
d. Flap Type – Non return valve 40 mm and above Cast Iron Flanged
Sufficient number of flanges and unions shall be provided as required to facilitate maintenance
work after the piping is installed. Mild steel flanges shall be used for pipes. The flanges shall be
connected to the pipeline by screwing or welding depending on the requirement. The flanges
shall conform to the relevant ASTM standard for the particular material used for its
manufacture. The flanges shall also conform to IS 5211.
Drainage systems, especially those in tall buildings, are frequently found to develop extremely
high and objectionable pneumatic effects in several specific portions of such piping. Special air
pressure relief vents are recommended to control, within tolerable limits.
The air pressure relief vent ,at least one-half the diameter of the building drain , should be
provided at the top of vertical offset so as to supply such additional air to the drain as may be
required by the sudden increase in liquid velocity in the vertical offset Where a building trap or
other sharp change in flow direction is provided in the building drain downstream from the
vertical offset ,an air pressure relief vent should be provided at the base of, and within 3 ft
(0.900m) of, the vertical offset. Lower relief vent should be branch –connected to the upper
relief vent at a sufficient height.
The recommended provision for soil and waste stacks more than ten stories in height is to
provide a yoke relief vent at each tenth story of the drainage stack, counting downward from
the top story. The lower end of the yoke relief vent should connect to the drainage stack by
means of a Y located below the horizontal branch drain serving fixtures in that story, and the
upper end should connect to the vent stack by means of a T or inverted Y located at least 3 ft
(0.900m) above the floor level as shown in the drawing.
Valves should be installed in true tolerance of +/-5mm with respect to the center line of the
pipe. Where threaded joints are encountered the threads should be initially sealed with PVC
tape to avoid leakage due to improper tightening and leakage from threading.
Before putting the line in operative mode the valves should be checked for free and easy
operation of the hand wheel. Any burrs or foreign materials should be removed by flushing
before final operation so that no choking in the valves should occur which might damage the
valve seat.
1.7 PUMPS
Supply, testing & commissioning of Horizontal Single/ Multi- stage submersible pump suitable
for pumping clean, less viscous, non-aggressive liquids without solid particles or fibre. Pumps
are fitted with standard & approved motor. Impeller & other parts of pump are made of SS304
with 3-phase motor, sand shield, liquid-lubricated bearings and pressure equalizing diaphragm.
Pump Enclosure class (IEC 34-5):IP58. Pumps should contain integral suction strainer & fitted
with priming mechanism. Motor parts are CED coated, fitted with carbon bushes. Double lip
Seal back to back to arrangement to ensure no water leakage inside the motor. Motor should
be fitted with mechanical seal & withstand upto 6 kN having 4 SS segments and carbon thrust
pads. Pumps are provided with stop ring. Motors should be locally rewindable. Motor should
capable of good starting torque and low starting current. Pumps shall be of NEMA with
Standard AISI 416 Stainless steel shaft Rubber O-ring for all fasteners. All bearing should be
water lubricated and square shape to enabling sand particular from the pump. At the delivery
of the pump each pump shall be fitted with a NRV & a valve of appropriate size & make of
components shall be as per approved list. The pump shall be placed in a pump pit of adequate
size such that the minimum submergence level is maintained at all times. Dry run protection,
overload trip, shall be provided for each pump system. The pump shall be provided with a
chain/ guide rope to lift the same. The pump shall be placed such that dust particles, etc do not
enter the pump impeller & damage the same. A min clear ht of 100 mm shall be provided at the
base of the pump to avoid dust particles entering the pump. The pump shall work with a min
motor efficiency of 55-80%. Motor should be suitable for horizontal installation. Operating
voltage 220 + 10% -15% for single phase and 415+ 10% -15% for three phases.
Supply, testing & commissioning of Vertical single-stage stainless steel submersible pump
with vertical discharge port and integrated submersible 1/3-phase totally enclosed motor
in insulation class F with thermal overload protection. Pump should be fitted with a suction
strainer. The impeller is a SEMI OPEN impeller for 12 mm free passage suitable for
pumping groundwater, surface water & rain water and similar. Pump is with a double shaft
seal and an intermediate oil chamber pre-filled with non-toxic special oil.
The pump shall come with a riser pipe, a cooling jacket for continuous cooling of the motor
by the pumped liquid and long-life deep-groove greased-for-life ball bearings. The pump
shall fitted with carrying handle and supplied with a 10 m mains cable. The mains cable
should of the plug type with glass sealing compound in the socket to prevent penetration
of humidity into the stator windings. The pump shall work with a min motor efficiency of
55-80%. Operating voltage 220 + 10% -15% for single phase and 415+ 10% -15% for three
phase
Supply, testing & commissioning of Horizontal centrifugal multi-stage pump with axial
suction port and radial discharge port close-coupled with a single/ three-phase TEFC motor
with thermal overload protection. Pump and motor are mounted on a common base plate.
The pump should be fitted with mechanical shaft seal. Impellers, intermediate chambers
and shaft are made of stainless steel. Suction and discharge chambers are made of Cast
iron. Motor should be IP 54 protection & Class F winding insulation. The pump shall work
with a min motor efficiency of 65-80%. Operating voltage 220 + 10% -15% for single phase
and 415+ 10% -15% for three phase
The pumps shall be of the vertical multi-stage centrifugal design. The pump
suction/discharge chamber (base) shall be in CI or SS as per requirement. Motors tool and
pump shaft coupling shall be constructed of cast iron. The impellers, pump shaft, diffuser
chambers, outer discharge sleeve, impeller seal rings, and seal ring retainers shall be
constructed of stainless steel. Optional materials for the suction/discharge chamb er and
motor stool liner shall be stainless steel.
The pump impellers shall be secured directly to the pump shaft by means of a spine shaft
arrangement for model of the lower sizes, and the pump impellers shall be secured to the
shaft by a split cone and nut for higher sizes. The shaft journal and chamber bearings shall
be Tungsten Carbide and Ceramic/ Bronze. All pumps shall be equipped with a high
temperature cartridge mechanical seal assembly with Tungsten Carbide/ Carbon or
Tungsten Carbide seal faces mounted in stainless steel components. The shaft seal shall be
of the cartridge design; the larger pumps (with 7.5 Kw and above motors) shall be designed
so that the cartridge seal may be replaced without removing the motors.
The motors shall be TEFC type, class F insulation, 2 pole, efficiency class “Eff –1”, should be
a NEMA standard motor. Drive-end motor bearings shall be designed to absorb thrust and
shall be adequately sized to ensure long motor life.
The variable frequency drive enclosure shall include dry-contact fault-output relay contacts
along with analog and digital inputs. The motor shall detect/protect itself against under voltage,
over voltage, excessive temperature, and set-point signal fault.
An electronic dedicated pump logic controller shall be a Hydro pneumatic system (Multi Pump
Controller) or approved equal. The controller shall operate the pumps to maintain the required
system pressure while using minimum energy and alternating between pumps to maintain
relatively equal pump operating hours.
As flow demand begins, one of the pumps will start at low speed. As demand increases, the
pump will speed up until it reaches full RPM. At this point the second pump will start in full
Pumps shall changeover automatically to maintain the system pressure depending on demand,
time, and fault.
If the system includes an optional standby pump, the controller shall exercise the standby
pump as a part of the system and equally run the pump as other pumps in the system.
The controller shall accept a low-suction pressure or other suction fault input to shut down the
system. The controller shall have a keypad and a graphical user interface display with
Installation wizard for easy commissioning of the system.
System functions shall be programmable through the keypad. These programmable functions
and information shall include, but not be limited to:
The controller shall be mounted in a control cabinet with an IP 52 enclosure of suitable rating
(or specified optional cabinet) with the keypad and display screen mounted through the outer
door. In addition to the electronic pump controller, the control cabinet shall include circuit
breakers for each pump and the control circuit and control relays for alarm functions. Control
cabinet shall include the following, but not be limited to:
1. Motor protection
2. Dry run protection – Float switch / Inlet pressure monitoring device for suction lift
condition
3. Ethernet connectivity (Web based control)
4. 320 X 240 pixels VGA display with adjustable backlight
5. Pump Fault Lights – A Red light for fault indications
6. Visual Alarm
7. Pump Elapsed Time Meters
8. Manual Operation
The entire packaged pumping system shall be mounted on a Hot Dipped Galvanized MS or SS
fabricated skid. The control cabinet shall be mounted in one of the following ways depending
on the size of the cabinet.
1. On a Hot Dipped GI or MS fabricated with powder coated control cabinet stand attached
to the system skid
2. On a Hot Dipped GI or MS fabricated with powder coated skid, separate from the main
system skid
3. Floor mounted control cabinet with plinth.
1.7.10 Plumbing
The suction and discharge manifolds shall be fabricated of Hot Dipped Galvanized MS or SS.
Both manifolds shall be designed to attach to the system piping at either end of the manifold.
Delivery manifold shall include a pressure gauge. The suction manifold shall have as standard a
pressure switch or pressure sensor to detect low suction pressure or a float switch to prevent
dry running. The discharge manifold shall include a pressure transducer with a 4-20mA output.
The pressure transducer shall be factory installed and wired.
Isolation valves shall be installed on the suction and discharge of each pump. A check valve shall
be installed on the discharge of each pump (optional on the suction side for suction lift
applications).
1.7.11 Hydro pneumatic System Specification for Pressurised Water Boosting System Using
Variable Speed Drive
Supply of booster set consisting upto a maximum of six identical vertical multistage in - line
pumps in cast iron GG20 pump head & base c/w cataphoresis coating, cartridge type
mechanical seal, all internals in AISI 304 stainless steel, mounted on common galvanized steel
base frame and controlled by variable frequency drives & a logic controller, which have features
like application optimized software, regular optimization of operating conditions and read-out
of operating data, Bus Communication possibility, Digital remote-control functions, pump &
system monitoring functions, Display, Alarm & signal functions and clock programs. Panel to
have 2x24 character LCD display, green & red LED’s for operating & fault indication, potential
free contacts for remote interfacing, and an inbuilt lifetime battery backup for all clock
functions.
Booster set should include non return valves, isolating valves, pressure transmitter on discharge
side, non-return valve, and pressure gauge. Booster set should ensure constant pressure on
discharge side through continuously variable adjustment of speed of one of the pumps, while
the remaining pumps in operation are running on mains operating at full speed to bring about
pump performance to meet consumption levels. Also provision should be made for alternate
change over between pumps in operation once every 24 hours & frequency converter
operation of pumps by rotation - all should be built in, cyclically, in the controls to ensure equal
wear and tear of all pumps in the booster set. Means should be provided for friction loss
compensation for increased consumption rate.
Compulsory change of staring of sequence, i.e. Equal operating time for pump, both for
frequency control and ON/OFF regulation.
System On / Off
Set point control
Switching of individual pumps
Motors IP 55.
The water level controller shall be microprocessor based with LED indicators. Each transfer
pump shall be provided with a level controller. The level controller shall be integrated with
OHTs of all the four blocks. Tinned copper cable shall be run in conduits from pump room to
individual OHT’s. The level controller shall switch on the pump incase of low water level in any
of the OHT. However the OHT having low water level shall only receive water as flow of water
The contractor shall provide all inlets, outlets, washouts, vents, ball cocks, overflows control
valves and all such other piping connections including level indicator to water storage tanks as
called for. All pipes crossing through RCC work shall have puddle flanges fabricated from GI pipes
of required size and length and welded to 6mm thick MS plate. All puddle flanges must be fixed
in true alignment and level to ensure further connection in proper order.
Valves of an approved make shall be provided as near to the tank as practicable on every outlet
pipe from the storage tank except the overflow pipe. Overflow and vent pipes shall terminate with
mosquito proof grating.
The overflow pipe shall be so placed to allow the discharge of water being readily seen, except for
flushing water tank, incase of which the overflow should be connected to waste pipe. The
overflow pipe shall be of size as indicated. A stop valve shall also be provided in the inlet water
connection to the tank.
MATERIAL
Insulation material for Pipe insulation shall be vidoflex/armaflex.
Thickness of the insulation shall be as specified for the individual application. Each lot of
insulation material delivered at site shall be accompanied with manufacturer test certificate for
thermal conductivity values.
Insulating material in tube form shall be sleeved on the pipes. On existing piping, slit opened
tube from insulating material shall be placed over the pipe and adhesive (as recommended by
the manufacturer) shall be applied as suggested by the manufacturer. Adhesive must be
allowed to tack dry and then press surface firmly together starting from butt end and working
towards centre.
Wherever flat sheets shall be used it shall be cut out in correct dimension. All longitudinal and
transverse joints shall be sealed as per manufacturer recommendations. The insulation shall be
continuous over the entire run of piping, fittings and valves. All valves, fittings, joints, strainers
etc. In hot water piping shall be insulated to the same thickness as specified for the main run of
All insulation work shall be carried out by skilled workmen specially trained in this kind of work.
All exposed insulated pipes shall be labelled (HWS / HWR) and provided with 300 mm wide
band of paint along circumference at every 1200 mm for colour coding. Direction of fluid shall
also be marked. All painting shall be as per relevant BIS codes.
To provide mechanical strength and protection from damage & UV rays all exposed pipe
insulated with nitrile rubber as indicated in BOQ shall be provided with 28SWG aluminium
Cladding. Due care shall be taken to ensure no damage is caused to the insulation while
cladding.
MEASUREMENT OF INSULATION
Unless otherwise specified measurement for pipe insulation for the project shall be on the
basis of centre line measurements described herewith
Pipe Insulation shall be measured in units of length along the centre line of the installed pipe,
strictly on the same basis as the piping measurements. The linear measurements shall be taken
before the application of the insulation. It may be noted that for piping measurement, all
valves, orifice plates and strainers shall not be separately measurable by their number and size.
It is to be clearly understood that for the insulation measurements, all these accessories
including valves, orifice plates and strainers etc. shall be considered strictly by linear
measurements along the centre line of pipes and no special rate shall be applicable for
insulation of any accessories, fixtures or fittings whatsoever.
The system shall be of Thermosyphon type and system shall be provided with all accessories,
equipments whether specifically mentioned in BOQ, drawings or not to meet the daily
requirement as specified in BOQ- efficiently with due consideration for peak demands. Brief
specifications of components are as following.
ii) Medium and Heavy tube : + Not limited - 10 percent butt welded
vi) For quantities per load of 10 tonnes, + /- 5 percent Min (light series)
Where pipes have to be cut or re-threaded, ends shall be carefully filed so that no obstruction
to the bore is offered. Approved quality thread seal tapes and sealants shall be used for joints.
For internal work all pipes and fittings shall be fixed truly vertical and horizontal, either by
means of brackets or by hanger type supports or concealed as directed. For external work, G.I.
pipes and fittings shall be laid in trenches. The width of the trench shall be the minimum width
required for working. The pipes laid underground shall be not less than 60cm. from the
finished ground level and a minimum horizontal distance of 60CM shall be maintained between
other services lines. All buried pipes shall be provided with suitable anti corrosive treatment.
1.12.2 Testing
Before any pipes are painted or covered, they shall be tested to a hydrostatic pressure of
7kg/sqcm or 1.5 times the working pressure whichever is higher. Pressure shall be maintained
for at least 6 hours without an appreciable drop in pressure. In addition to the sectional testing
G.I. pipes shall be measured along the centre line of the pipes and fittings. The quoted rate for
respective item shall be per Rmt and shall include the following:
b) Laying, fixing and jointing with standard pipe clamps available for different sizes inside the
wall chase and fixed on Hot dip galvanized MS angle iron brackets and GI U clamps for pipes in
ducts as shown on the drawing.
c) Cutting holes and chases in walls, floors, etc. and making good the same.
Water meters of approved make and design shall be supplied for installation at locations as
shown. The water meters shall meet with the approval of local supply authorities, if they are
used at municipal inlet lines. Suitable valves and chambers or wall meter box to house the
meters shall also be provided along with the meters, but the same shall be measured
separately.
The meters shall conform to Indian Standard IS: 779 and IS: 2373/2104
All electrical works shall be carried out as per the specifications and special conditions
mentioned above under package – “Electrical works.”
SCOPE
This specification covers requirements, test methods, and methods of marking for chlorinated
poly (vinyl chloride) plastic hot-and cold-water distribution system components made in one
standard dimension ratio and intended for water service up to and including 180 0F (820C).
These components comprise pipe and tubing, socket-type fittings, street fittings, plastic-to-
metal transition fittings, solvent cements, and adhesives. Requirements and methods of test
are included for materials, workmanship, dimensions and tolerances, hydrostatic sustained
pressure strength, and thermo-cycling resistance. The components covered by this specification
are intended for use in residential and commercial, hot and cold, potable water distribution
systems.
The values stated in either inch-pound or SI units are to be regarded separately as standard.
Within the text, SI units are shown in brackets. The values stated in each system are not exact
equivalents therefore each system shall be used independently of the other. Combining values
from the two systems may result in non-conformance with the specification.
Materials
Basic Materials Description—Chlorinated poly (vinyl chloride) plastics used to make pipe,
tubing, and fittings meeting the requirements of this specification are categorized by two
criteria; namely, basic short-term properties, and long-term hydrostatic strength.
Basic Short-Term Properties—This specification covers CPVC 41 pipe, tubing, and fittings made
from plastic materials meeting the mechanical strength, heat resistance, flammability, and
chemical resistance requirements for CPVC 23447-B in Specification D 1784.
CPVC 23447-B was formerly designated as CPVC Type IV Grade 1, and is herein designated as
CPVC 41. This is also used in marking pipe, tubing, or fittings.
Long-Term Hydrostatic Strength—This specification covers CPVC 41 pipe, tubing, and fittings
which are further defined by hydrostatic design stress as CPVC 4120. Pipe and tubing are so
defined on the basis of long-term hydrostatic strength tests and are made from compounds
having an established 180°F [820C] hydrostatic design stress of 500 psi [3.45 MPa] or greater in
accordance with Appendix XI and Test Method D 2837. Fittings are so defined by hydrostatic
No hydrostatic design stress, as such, exists for finings until such time as long-term hydrostatic
strength test methods for fittings are developed.
Rework Material—clean rework material generated from the manufacturer's own production
may be used by the same manufacturer provided the pipe, tubing, or fittings meet all the
requirements of this specification.
Classification
Pipe, Tubing, and Fittings—This specification classifies CPVC 4120 pipe, tubing, and fittings by a
single standard dimension ratio which shall be SDR II, by a maximum continuous use
temperature which shall be 1800F [820C] and by nominal pipe or tubing diameters from 3/8
in.[9.5 mm] through 2 in. [50 mm].
Solvent Cements and Adhesives— this specification classifies solvent cements and adhesives
meeting the requirements contained herein as CPVC Solvent Cement or CPVC Adhesive.
General
Wall Minimums—Table 1 and Table 2 show wall thickness minimums. Calculated SDR 11 tubing
wall thicknesses that fall below 0.068 in. [1.73 mm] shall be arbitrarily increased to that value.
Calculated SDR 11 fitting wall thicknesses that fall below 0.102 in. [2.59 mm] for the fitting
socket bottom, or 0.I28 in. [3.25 mm] for the fitting body, shall be arbitrarily increased to these
values.
Interference Fit—the diameters and tolerances in Table I and Table 2 provide for socket-type
joints having an interference fit based on the major diameter of pipe and tubing having a
degree of out-of-roundness. This does not necessarily imply interference based on the minor
diameter of the pipe or tubing.
Outside Diameter and Wall Thickness—The outside diameters and wall thicknesses for pipe and
tubing shall meet the requirements for dimension and tolerance given in Table 1 when
measured in accordance with Test Method D2122.
Wall Thickness Range—the wall thickness range for pipe and tubing shall be within 12 % when
measured in accordance with Test Method D 2122.
Flattening—there shall be no evidence of splitting, cracking, or breaking when the pipe is tested
in accordance with 9.2
Length— Pipe and tubing supplied in straight lengths shall have a tolerance on any specified
length of +1/2 -0 in. [+12.5, -0 mm].
Socket-Type Fillings:
Dimensions—Fitting sockets, inside diameters (waterways), wall thicknesses, laying lengths, and
reducing bushing minimums shall meet the requirements for dimension and tolerance given in
Table 2. Table 3, and Table 4 when measured in accordance with Test Method D2122. The
spigot ends of street fittings shall meet the outside diameter and minimum wall requirements
of Table 1.
Alignment—the maximum angular variation of any socket opening shall not exceed 1/20 off the
true centreline axis.
Back Dimensions—Plastic parts of plastic to metal transition fittings shall meet the
dimensional requirements of Table 1 and Table 2 where applicable with
the following exceptions. Such parts shall be exempted from the requirements for inside
diameter (waterway) and wall thickness tolerance.
Thread Dimensions — Transition fittings that rely on interference fit and sealant shall be
threaded with American National Standard Taper Pipe Threads meeting
the dimensional requirements of ANSI B2.1
Thread Tolerance — The manufacturing tolerance on CPVC threads, measured with a ring
gauge, shall be a maximum variation of 1½ turns large or small when measured in accordance
with Test Method D 2122.
General — Pipe, tubing, and fittings (tested as assemblies) shall meet the minimum hydrostatic
sustained pressure requirements of both test conditions shown in Table 5 when tested in
accordance with 9.2.
Pipe and Tubing Quality—Test condition B shall be termed the primary sustained pressure test
for pipe and tubing and shall be used for quality control. Test condition A shall be termed the
secondary sustained pressure test for pipe and tubing and shall be used for periodic
performance qualification. Failure to pass either lest is cause for rejection.
Fitting Quality—Test condition A shall be termed the primary sustained pressure test for fittings
and shall be used for quality control .Test condition B shall be termed the secondary sustained
pressure test for fittings and shall be used for periodic performance qualification. Failure to
pass either test is cause for rejection.
Thermo cycling — Plastic-to-metal transition fittings (other than metal socket-type transitions
for use with adhesives assembled according to the manufacturer's instructions, shall not
separate or leak when thermo cycled 1000 times between the temperatures of 600Fand 1800F
[160C and 820C] in accordance with 9.3.8
Note 6—CPVC solvent cements may exist which meet the requirements of the specification
when used in accordance with the manufacturer's recommendations, without a primer or
cleaner. It is recommended that those CPVC solvent cements which may be used without a
primer or cleaner be dear or yellow in color. Otherwise, it is recommended that CPVC solvent
cement requiring the use of 3 primer or cleaner be orange in color. Color identification is
recommended to facilitate cement recognition to prevent the misuse of the cement and to the
minimize the unintentional use of other cements that may fail at elevated service
temperatures.
Hydrostatic Burst Strength—2-in. [50-mm] CPVC solvent cement joints shall exceed the
minimum hydrostatic burst strength requirements given in Table 6 after a maximum drying
interval of 2 h when tested in accordance with 10.1.3, Failure to pass the burst requirement at
either temperature is cause for rejection.
Hydrostatic Sustained Pressure Strength—½-in. [I5-mm] CPVC solvent cement joints shall meet
the requirements of 6.2 when tested in accordance with 9.3.
CPVC ADHESIVES
General—CPVC adhesives (other than CPVC solvent cement), shall qualify for use in CPVC
socket-type joints by a rigorous simulated use testing program as further defined in 7.2.2 and
7.2.3. CPVC adhesives shall be tested in the largest size joint and in the exact type of joint for
which they are intended; that is, 2-in. [50-mm] plastic-to-metal or 2-in. [50-mm] plastic-to-
plastic.
Hydrostatic Sustained Pressure Strength—Socket-type CPVC adhesive joints, made and cured
according to the adhesive manufacturer's recommended procedure, shall not separate or leak
when tested in accordance with 10.2 at the
hydrostatic sustained pressure condition given in Table 7.
Thermo-cycling—Socket-type CPVC adhesive joints, made and cured according to the adhesive
manufacturer's recommended procedure, shall not separate or leak when thermo-cycled 10000
times between the temperatures of 600F and 1800F [160C and 820C] in accordance with 10.2.
The pipe shall be homogeneous throughout and essentially uniform in color, capacity, density,
and other properties. The inside and outside surfaces shall be semi-matte or glossy in
appearance (depending on the type of plastic) and free of chalking, sticky or tacky material. The
surfaces shall be free of excessive bloom, that is slight bloom is acceptable. The pipe walls shall
be free of cracks, holes, blisters, voids, foreign inclusion, or other defects which are visible to
the naked eye and which may affect the wall integrity. Holes deliberately placed in perforated
pipe are acceptable. Bloom or chalking may develop in pipe exposed to direct rays of the sun
CPVC SCHEDULE 40 PRESSURE PIPES AND FITTINGS FOR WATER SUPPLY AS PER ASTM F- 441
Outside Diameters and Wall Thicknesses For CPVC 4120, SDR 11 Plastic Pipe As Per ASTM D-
2846
To ensure the satisfactory operation of a PVC piping system the location and type of hangers
should be carefully considered. Hangers should not compress, distort, cut or abrade the piping.
All piping should be supported with an approved hanger at intervals sufficiently close to
maintain correct pipe alignment and to prevent sagging or reversal. Pipe should also be
supported at all branch ends and at all changes of direction. Support traps arms as close as
possible to the trap. In keeping with good plumbing practices support and brace all closet bends
and fasten closet flanges.
1.15.2 Handling
The pipe should be handled with reasonable care. Thermoplastic pipe is much lighter weight
than the metal pipe. There is sometimes a tendency to throw it around. This should be avoided.
The pipe should never be dragged or pushed from a truck bed. Pallets for pipe should be
removed with a fork lift. Loose pipe can be rolled down timbers, as long as the pieces do not fall
on each other or on any hard or uneven surface. In all cases, severe contact with any sharp
objects (rocks, angle irons, forks on forklifts, etc.) should be avoided.
1.15.3 Storing
If possible, pipe should be stored inside. When this is not possible, the pipe should be stored on
level ground, which is dry and free from sharp objects. If different schedules of pipe are stacked
together, the pipe with the thickest walls should be at the bottom.
The pipe should be protected from the sun and be in an area with proper ventilation. This will
lessen the effects of ultraviolet rays and help prevent heat build-up. If the pipe is stored in
When storage temperatures are below 32°F, extra care should be taken when handling the
pipe. This will help prevent any problems, which could be caused by the slightly lower impact
strength of PVC and CPVC pipe at temperatures below freezing.
1.15.4.1 Systems should be installed in a good and workmanlike manner consistent with normal
industry standards and in conformance with all local plumbing, fire and building code
requirements. Failure to follow proper installation practices procedures or techniques can
result in system failure, property damage or personal injury.
Pipe and fitting systems should be used for their intended purpose as defined by local plumbing
and building codes and the applicable ASTM standard.
Cut pipe square as joints are sealed at the base of the fitting socket. An angled cut may result in
joint failure.
Acceptable tools include miter saw, mechanical cut off saw or wheel cutter. Wheel type cutters
must employ a blade designed for plastics.
Remove all burrs from inside and outside of pipe with a knife-edge, file, or de-burring tool.
Chamfer (bevel) the end of the pipe 10° -15°
With light pressure, pipe should go one half to one third of the way into the fitting socket. Pipe
and fittings that are too tight or too loose should not be used.
Use an applicator that is one half the pipe diameters. Too large an applicator will force
excessive cement into the inside of small diameter fittings. Too small applicator will not apply
sufficient cement to large diameter systems.
1.15.4.3 Recommended initial set times Apply a full even layer of cement to the outside of a
pipe and medium layer of cement to inside of a fitting. Assemble pipe and fitting socket until it
contacts socket bottom. Give pipe a quarter turn. Hold pipe and fitting together until the pipe
Prior to testing, safety precautions should be instituted to protect personnel and property in
case of test failure. Conduct pressure testing with water. DO NOT USE AIR OR OTHER GASES for
pressure testing.
The piping system should be adequately anchored to limit movement. Water under pressure
exerts thrust forces in piping systems. Thrust blocking should be provided at changes of
direction change in size and at dead ends.
The piping systems should be slowly filled with water, taking care to prevent surge and air
entrapment. The flow velocity should not exceed 1 foot per second.
Primers are used in solvent cement joints of PVC plastic pipe and fittings as per ASTM F 656
Provided at all high points of the piping system. All valves and air relief mechanisms should be
opened so that the air can be vented while the system is extremely dangerous and it must be
slowly and completely vented prior to testing.
The piping system can be pressurized to 125% of its designed working pressure. However care
must be taken to ensure the pressure does not exceed the working pressure of the lowest rated
component in the system (valves, unions, flanges, threaded parts etc.) The pressure test should
not exceed one hour. Any leaking joints or pipe must be cut out and replaced and the line
recharged and retested using the same procedure
The effective fluid hammer, which results in breaking of pipeline caused due to series of
hydraulic shock, should be arrested by means of a water hammer arrestor. The arrestor shall be
capable of withstanding pressures upto 30 Kg/ Sq.cm and temperatures in the range of –400F
to 2120F (-540C to +1000C). It shall be maintenance free with a companion flange to suit in the
pipeline. The following materials are used for its manufacture
Body : CI
Pressure rating : PN 10
Strainer : Inbuilt
Inspection chambers of minimum Internal size 600 x 600mm up to a depth of 1.0M and
manholes of varying sizes as per IS 4111 shall be constructed beyond 1.0M (depth of the
manhole from the formation ground level).
The size indicated in the drawings shall be the internal size of chamber. Unless otherwise
specified, manholes and inspection chambers are provided at all changes of direction of drains
and where branch drain meets the main drain. Chambers shall be of such size as to allow
necessary examination and clearance of drains. The minimum internal sizes shall be taken as
per detail drawings; standards specified and local bye laws if any. In the absence of local
byelaws, the requirements stipulated in IS 4111 (Part I) Code of Practice for Ancillary
Structures on Sewage System shall be followed. The work shall be done strictly as per
standard drawings and the following specifications:
Bed concrete shall be in 1:4:8 cement concrete 150 mm thick for inspection chambers, 200 mm
for depths upto 2 m and 250 mm for greater depths in case of manholes.
Brick work shall be with best quality table moulded bricks in 1:5 cement mortar as per
specification for brick masonry. The thickness of masonry shall be as per Bill of Quantities.
1.1.4 PLASTER
Inside walls of chambers/manholes shall be plastered with 15mm thick cement plaster 1:3 and
finished smooth with a floating coat of neat cement. External walls shall be plastered in CM 1:3
mixed with waterproofing material and sponge finished.
1.1.5 BENCHING
Channels and benching shall be done in cement concrete 1:3:6 rendered smooth with neat
cement. The following sizes of channels for the bench shall be adopted:
Covers shall be of heavy duty cast iron or fiber reinforced cement concrete as per material
specification with lifting hooks as per IS 1726 - 1974 and as per the details given in the drawings
and fixed on CI frame or cement concrete embedded in concrete. Covers placed on the frames
shall be airtight. The weight of frame and cover shall be as per bill of quantities.
1.1.7 STEPS
PVC steps shall be provided wherever the depth of the manhole/chamber is more than 1.2M.
Steps shall be arranged in a staggered manner as per drawings.
In case the difference in invert levels between the main drain and the branch line requires a drop
more than 600 mm, a drop connection should be provided with a PVC fourway junction, fixed at
right angles to the drop pipe at the level where the branch pipe enters the manhole. Access for
cleaning the bend should be provided at finished ground level
PVC gully traps of specified size shall be provided as per relevant IS code. It shall be fixed on 15
cm. thick and 70 cm square 1:4:8 cement concrete bedding and the gully outlet shall be jointed
similarly to the jointing of stoneware pipes. A brick masonry chamber 300 x 300 mm (internally)
shall be constructed in 1/2 brick masonry with 1:6 cement mortar and the spaces between the
trap and the wall shall be filled up with 1:3:6 concrete and the upper portion of the chamber shall
be finished with neat cement. The corners and bottom of the chamber shall be rounded off so as
to slope towards the grating and the bottom of the chamber shall not be less than 230 mm. In
addition to 150mm x 150mm CI grating, the chamber shall have a CI frame cover (300mm x 300
mm). It shall then be placed on top of the brick masonry.
SL no Material Make
2 Toilet Accessories
10
12
13
16
18
20
21
22
NOTE : 1) Quote should be for the first preference make only, if not available then second
preference can be quoted same has to be mentioned in the BOQ.
2) All bought-out items shall be of makes approved by Architect, Consultants & Equivalent
makes to be got approved by Architect / Consultant / Owner prior to placement of
order.
2. The rate for each item of work included in the bill of quantities shall unless expressly
stated otherwise included cost of: -
c) All taxes, duties, octroi, including works contract tax, sales tax, transit insurance, packing
and forwarding charges, loading, transportation, unloading, handling, hoisting, to all levels,
setting and fixing in position, disposal of debris and all other labor necessary in accordance with
contract documents, good practice and recognized principles.
f) Preparation of shop drawing, As built drawing, O & M Manuals, Soft Copies ‘CD’ to be
submitted after final completion of work.
3. All requirements of system whether such of them are mentioned in the item or not the
specifications and drawings are to be read as complimentary to and part of the schedule of
quantities and any work called for in one shall be taken as required for all.
4. In the event of conflict between the bill of quantities and other documents, the most
stringent shall apply and interpretation of the Architect shall be final and binding.
5. The installation price of switchboards, metering panels, DB's or any other items shall
include supply and fixing of supporting steel structures/MS channels grouting of the same civil
works etc., as required.
6. No change in unit rate shall be allowed for any change in quantity or for any other reason
whatsoever.
8. The successful contractors shall submit the Schematic diagrams, fabrication drawings with
details of all equipments wirings diagrams etc., for approval prior to supply/commencement of
such works. The approval of these drawings will be general and will not absolve to contractor of
the responsibility of the correctness of these drawings. Atleast four copies of the approved
drawings shall be supplied to Consultants for their distribution to various agencies at site at no
cost of Owner.
9. The tenderers must see the site conditions such as type of soil, locations etc., and take all
factors into consideration while quoting the rates as no extra cost will be allowed on any ground
arising out of or relating to the site conditions.
10. Any error in description or in quantity or omission of items from the contract shall not
vitiate this contract but shall be corrected and deemed to be a variation required by the
Architect/Owners.
i) Follow up expenses with the Local Statutory authorities from the drawing approval up to
servicing the installation and getting the safety certificate.
iii) Obtaining approval of drawings and installation from Local statutory Authorities as
applicable.
Official deposits paid to the above agencies will be reimbursed separately at actuals by the
Owners.
12. The tenderer shall take into account the expenses of pre-commissioning tests to be
conducted as per specification of the complete installation by licensed agencies.
13. Tenders to submit performance curves, Schematic & GA drawing of pumps, Hydro
pneumatic system and other bought out components along with offer for proper
evaluation.
FOR
ELECTRICAL SERVICES
B A SI C EL E CT RI CA L R E Q U IR EM EN T S
S WI TC H B O AR D S
PO W ER F A CT OR CO RR EC TI ON
M E D IUM V O LT AG E C AB L E S
WI RIN G D E VI C ES
B U SB A R T RU N KIN G
LUM IN A IR E S
INV E RT OR U P S S Y ST E M
E AR T HIN G
LI GH TN IN G P RO T EC T ION
RE CO M M EN D E D M A K E OF M A T ER I AL S
1.0 General
1.1 Scope
The scope of work covers complete electrical installation system for all buildings including but not limited
to:
Supply, storage, installation, testing and commissioning of all equipment, components, accessories,
labour, tools and tackles required for the operation of the buildings to the extent specified and
detailed on the drawings and specifications.
All Civil works in connection with the Electrical Installation including supply, laying and fixing of
necessary inserts, hooks, brackets and sleeves etc.
Any work which can be reasonably inferred as necessary for the safe, satisfactory operation whether
such work is specified or shown on the drawings or not.
Arranging permanent supply including necessary submissions of drawings as required to the supply
authorities and arranging inspections and obtaining necessary approvals of all the concerned
authorities.
All work shall be carried out by a licensed Electrical Contractor who is approved by the Consultant /
Developer and who possesses a valid local Electrical Contractor's license employing licensed Supervisors
and licensed Electricians, Helpers, as required. Required 3 years of documented experience at least.
The installation shall conform in all respects to the Indian Standard Code of Practice for Electrical Wiring
Installation IS.732-1963 and IS.2274-1963. It shall also conform with the current Indian Electricity Rules
and the Regulations and requirements of the local Electric Supply Authority applicable to the installation.
Wherever this specification calls for a higher standard of materials and/or workmanship than those
required by any of the above Regulations, this Specification shall take precedence over the said
Regulations and Standards.
In general, the materials, equipment and workmanship not covered by the above shall conform to the
latest Indian Standards.
All bolts and nuts used shall be metric size with corrosion protection suitable for the location.
1.4 Documentation
The indication and/or description of and item on the drawings or in the Specifications, unless otherwise
specifically stated, implies an instruction to supply and fix such items.
Drawings show general run of cables, approximate locations of outlets and equipment, utility symbols and
schematic diagrams of no dimensional significance. Refer to the Architectural drawings for locations and
also obtain approval from the Consultant / Developer wherever dimensions are not shown, or locations
cannot be determined from the drawings. Do not scale drawings to obtain locations.
Electrical materials and equipment shall comply in all respects, as a minimum to the latest Indian
Standards Institution's recommendations.
Should any difference arise between ISI and the specification, the requirement of the Specification shall
prevail.
The components of submain switchboards, distribution boards and other electrical equipment shall be
clearly labeled in English.
Distribution boards shall have circuit schedules fastened to the inside cover of the board showing rating of
the circuit breakers, type and number of points and their connected loads.
2.0 Submissions
Shop drawings shall be provided of the Main and Sub-Main Switchboards, Distribution Boards, Cable
Trays, Reactive Power Compensation Panel, and any other switchboards and panels, wherever applicable
and approval shall be obtained from the Consultant / Developer before commencing fabrication or
procurement.
Any equipment or switchboard manufactured without the written consent of the Consultant / Developer
prior to the approval drawings shall be liable for rejection.
3.0 Foreman/Supervisor
3.1 Qualifications
The Electrical Contractor shall employ a competent, licensed qualified full time electrical
foreman/supervisor to direct the work of electrical installations in accordance with the Drawings and
Specifications. Required 5 years of documented experience at least.
3.2 Responsibility
The foreman/supervisor shall be available at all times on the site to receive instructions from the
Consultant / Developer in the day to day activities throughout the duration of the work.
The foreman/supervisor shall correlate the progress of the work in conjunction with all the relevant
requirements of the Supply Authority. The skilled workers employed for the work shall have the requisite
qualifications and shall possess competency certificates from the Electrical Inspectorate of Local
Administration.
4.1 Responsibility
The Contractor shall be responsible for filing and follow up of application for getting the drawings/scheme
approved by the Electrical Inspector and finally the approval by the Electrical Inspector of the whole
installation.
4.4 Tests
The Consultant / Developer shall have full powers to require the materials or works to be tested by an
independent agency at the Contractor's expense in order to establish their soundness and adequacy.
The Contractor shall notify the Consultant / Developer at least 7 working days before testing of each
system. The Consultant / Developer reserves the right to be present when such tests are being made.
If the Electrical Inspectorate requires manufacturer's test reports for HT cables, HT switch gear,
transformers or any other equipment used in the project, the Contractor shall obtain such approvals at no
extra cost to the Developer. Such approved reports shall be handed over to the Consultant / Developer.
Calibration certificates shall be obtained from the Meter and Relay Testing Department of the Electricity
Board for all relays and meters used in the project at no extra cost to the Developer.
S WI TC H B O AR D S
Distribution boards shall be deemed to be approved when a sample has been inspected and when the
sample workshop drawings have been approved, by the Consultant / Developer.
1.2 General
Distribution boards shall be suitable for 433 volts, 3 phase AC supply and 240 volts single phase AC supply,
as required. Distribution boards shall generally conform to IS:2675 or BS:214.
All the distribution boards shall be of Class IP 54 with approved type of components of recommended
make of MCB. The sheet steel MCB DB shall be flush mounting type unless otherwise specified and shall
consist of MCB/ELCB as incomer and MCB as outgoings. The short circuit rating of MCB shall be 10kA as a
minimum, unless otherwise specified.
1.10 Terminals
Distribution Boards shall be provided with an approved make terminal block of adequate size to receive
mains and outgoing circuits. The location of the terminal block shall be so located that crowding of wires
in the proximity of live parts is avoided. A neutral link having a rating equal to that of phase bus shall also
be provided.
1.11 Directory
Distribution boards shall be provided with a directory indicating the area or loads served by each circuit
breaker, the rating of breakers, size of conductors and other components as determined necessary for
clear identification of the function and operation of the distribution board.
Indication labels shall be machine engraved on laminated plastic and attached with approved adhesive or
mechanical fasteners. The font shall be ARIAL and sized to suit the application. The minimum font size
shall be 3.5mm. Hand painted directory or text is not acceptable.
2.0 LT Switchboards
2.1 General
The switchboard shall be metal clad, totally enclosed, rigid, compartmentalized design, floor mounting, air
insulated, extensible cubicle type for use on medium voltage power, 3 phase 4 wire 50 cycles system.
The equipment shall be designed for operation in high ambient temperature and high humidity tropical
atmospheric conditions. Means shall be provided to facilitate ease of inspection, cleaning and repairs for
use in installations where continuity of operation is of prime importance.
a. Sheet steel enclosed, indoor floor mounted free standing cubicle type.
b. Made up of the requisite vertical sections modular type which when coupled together shall form
continuous dead front switchboards.
c. Dust, vermin and damp proof and enclosure protection of not less than IP 54.
d. Each feeder/instrument compartment shall be provided with a hinged door interlocked with
MCCB inside the compartment such that door can only be opened when MCCB in off position.
e. Readily extendable as required by the addition of vertical sections after removal of the end
covers.
f. Switchboards shall have access to the feeders, bus bars, cable termination, cable alley, etc. as
required.
g. Main Breakers need to be lockable.
a. A front framed structure of rolled/folded CRCA sheet steel angle section of minimum 3 mm
thickness rigidly bolted together. This structure shall house the components contributing to the
major weight of the equipment such as circuit breaker cassettes, main horizontal bus bars,
vertical risers and other front mounted accessories.
b. The structure shall be mounted on a rigid base frame of folded CRCA sheet steel of minimum 6
mm thickness and 75 mm height. The design shall ensure that the weight of the components is
adequately supported without deformation or loss of alignment during transit or during
operation.
c. A cable chamber housing the cable end connections and power or control cable terminations.
The design shall ensure generous availability of space for ease of installation and maintenance of
cabling and adequate safety for working in one vertical or horizontal section without coming into
accidental contact with live parts of the adjacent section.
d. A cover plate at the top of the vertical section, provided with a ventilating hood where
necessary. Any aperture for ventilation shall be covered with a perforated sheet having less than
1mm diameter perforations to prevent entry of vermin.
e. Front and rear doors fitted with dust excluding neoprene gaskets with fasteners designed to
ensure proper compression of the gaskets. When covers are provided in place of doors generous
The height of the panel shall not be more than 2200 mm unless otherwise specified and maximum height
of switch operating handle shall not be more than 1800mm from FFL. The total depth of the panel shall be
adequate to cater for proper cabling space.
Doors shall be of minimum 14 gauge sheet steel and covers and partitions of 160 sheet steel. All sheet
steel work forming the exterior of switchboards shall be smoothly finished, levelled and free from flaws.
The corners shall be rounded.
The Components in the switchboards shall be so arranged as to facilitate ease of operation and
maintenance and at the same time to ensure necessary degree of safety.
Components forming part of the switchboards shall have the following minimum clearances:
a. Between phases 25 mm
b. Between phases and neutral 25 mm
c. Between phases and earth 25 mm
d. Between neutral and earth 19 mm
When, for any reason, the above clearances are not available, suitable insulation barrier/shielding shall be
provided. Clearances shall be maintained during normal service conditions.
Functional units such as circuit breakers, MCCBs, etc. shall be arranged in multi-tier formation except that
not more than two air circuit breakers shall be housed in a single vertical section.
Metallic and/or insulated shrouding shall be provided within vertical sections and between adjacent
sections to ensure prevention of accidental contact with:
a. Main bus-bars and vertical risers during operation, inspection or maintenance of functional units
and front mounted accessories.
b. Cable terminations of one functional unit, when working on those of adjacent units.
All covers providing access to live power equipment or circuits shall be provided with tool operated
fasteners to prevent unauthorized access.Provision shall be made for permanently earthing the frames
and other metal parts of the switch gear by two independent distinct connections.
Only CRCA steel sheets shall be used for fabricating the cubicle.
Generally the treatment and finish of the metal surface shall be as per detailed specifications in Clause 8.4
Metal Treatment and Finish.
The bus bars shall be made of high conductivity high strength E91E aluminium alloy suitable for 440 volts
3phase 4 wires 50 Hz 20KA unless otherwise specified.
The bus bars shall be suitably supported with non-hygroscopic supports to provide a fault withstand
capacity as specified.
High tensile bolts and spring washers shall be provided at all bus bar joints.
Fish plates of equal type and size shall be used at all joints.
The bus bars shall have uniform cross section throughout and shall be capable of carrying the rated
current at 433V continuously. The bus bars shall be designed to withstand a temperature rise of 45 Deg C
above the ambient. A current density of 1.00 Amp/Sqmm shall not be exceeded for copper bus bars.
The neutral bus bars shall have a continuous rating of at least 100% of the phase bus bars, unless
mentioned otherwise. 200% Neutral Busbar up to 200A
Bus bars shall be fully sleeved using heat shrunk PVC sleeves appropriately colour coded to identify
different phases and neutral bar.
An earth bus of size not less than 40 x 6 mm aluminium shall run throughout the length of switchboard at
top or bottom as required.
3.1 General
The ACBs shall conform to IS 13947-172/IEC60947-1&2; confirming to test sequence 1. The ACBs shall be
suitable for 3 phase 415 Volts. 4 pole ACBs shall have settable neutral at site (0,50, 100% In). All the
breakers shall have tropicalisation as a standard feature.
3.2 CON S T RU C TI ON :
The Breaker shall be suitable for rear and vertical mounting and line load reversibility without duration.
The operating mechanism shall be designed such that the handle can only be in `OFF' position if the Main
contacts are actually separated and vice versa. It shall confirm to Isolation as per standard.
3.3 CON T RO L UN I T S:
The Control Units shall be housed in a separate enclosure and there shall be total insulation of the control
unit with respect to the power unit.
The Control Unit shall be suitable to provide short circuit, overload and earth fault protection (wherever
specified). The Control Unit shall not be a peak sensing device and shall measure the true RMS values to
make the measurement free from the influence of harmonics. It shall have thermal memory.
3. 4 Prot e cti on s:
All breakers shall have segregated Led fault Indications & mP failure indication.
3.5 AC CE SS OR IE S :
All ACB feeders shall have metering and local display features viz. Ammeter, Voltmeter, frequency, KVA,
KW, KWAh, p.f, maximum demand. It shall be possible via COM (485 port) to transmit the protection &
metering settings to PC.
ACB shall be provided with following accessories, in addition to the item specified in Bill of Quantities.
Further these devices shall be fit-table at site accessible from the top and front and shall be common for
all ratings.
The connection for the auxiliary shall be accessible from the front.
All ACBs shall have Under Voltage trip, shunt trip, auxiliary switches with NO. + NC. In EDO type, closing
coil shall be provided.
INTERLOCKING:
ACBs shall be provided with the following interlocking devices for interlocking the door of a switchboard:
4.1 General
MCCB shall conform to IS 13947-1&2/IEC60947-1&2; confirming to test sequence 1 and Isolation as per
standard. It should be suitable for Horizontal and Vertical mounting and line load reversibility without any
duration.
The Moulded Case Circuit Breaker incorporated in the switchboard shall be of the current limiting type,
cat A, upto 630A. 800A and above shall be cat B i.e with Short time withstand capacity Icw/0.5 sec of
minimum 20kA. MCCB shall be suitable either for Single Phase AC 230V On Three Phase 415V. The MCCB
shall be available in fully rated four pole versions for neutral isolation. It shall have tropicalisation as
standard feature.
The MCCB cover and case shall be made of high strength heat-resistant and flame-retardant
thermosetting insulating material. The operating handle shall be quick make, quick break, trip - free type.
The operating handle shall have suitable `ON' `OFF' `TRIPPED' indicators and in order to ensure suitability
for isolation complying with IS 13947-2/IEC60947-2, the operating mechanism shall be designed such that
the toggle or the handle can only be in `OFF' position: if the main contacts are actually separated.
AC CE SS OR IE S :
All M CC B fe ed e rs sh all h av e mon ito rin g & d i sp lay f ea tu r e viz . A m m et er, Vol t me te r,
fr eq u en cy , KV A, KW, K W Ah , p . f,, THD with C OM M p o rt.
4.2 Accessories
MCCB shall be designed to have following accessories and it shall be fittable at site.
4.3 Interlocking
MCCB shall be provided with following interlocking devices for interlocking the door of a switchboard.
n addition to the above, and other features indicated elsewhere shall also be provided.
Type of Release TM TM TM
Instantaneous - - - -
MG-compact NS
S4H-200/250A VL-
STR 22SE- 200/250A
Upto 630A rating S5H - 400A 200/250/400/630A
STR 23SE -
S6H - 630A (mP rel)
400/630A
Type of Release mP mP mP
Instantaneous - - - -
* mP rel has to be
Default releaseis mP when adjO/,
Yes Yes mentioned in case of
adj S/c reqd-
Siemens.
5.1 Contactors
Contactors shall comply with IS 13947-1 for general rules and IS 13947 - 4.1 for Standards pertaining to
Contactor and Motor Starter.
The Contactors shall be capable of withstanding breaking and making capacities per following:
--------------------------------------------------------------------------------------
AC3 Category AC4 category
--------------------------------------------------------------------------------------
Making Current 10 x Rated Current 12 x Rated Current
Breaking Current 08 x Rated Current 10 x Rated Current
---------------------------------------------------------------------------------------
Contactors shall be capable of withstanding an impulse voltage of 8kV and have an insulation voltage of
1000V.
Contactors shall be suitable for copper termination with a maximum permissible temperature rise of 65
Deg; C at the terminals with an ambient temperature of 50 Deg; C.
The auxiliary contact block shall have a switching capacity of 240V at 2A. Contactors shall have one
auxiliary in built and it shall be possible to have additional normally opened, normally closed contacts in
steps of two.
MCB shall be in 1,2,3 or 4, pole versions. MCB casing shall be made of self extinguishing, tropicalised
material.
MCB shall comply with IS 8828-1996/1EC 898-1995. It shall be suitable for use in frequency range 40Hz to
60Hz and shall accommodate AC/DC supply according to requirements. It shall have a trip-free
mechanism and toggle shall give a positive contact indication. It shall be suitable for mounting on 35mm
DIN rail/surface mounting.
Line supply may be connected to either top or bottom terminals i.e. there shall be no line-load restriction.
Degree of protection, when the MCB is flush mounted, shall be IP40. MCB shall be supplied with clamping
terminals fully open. Contact closing shall be independent of the speed of the operator. The breaking
capacity of the MCB shall be 10kA. The MCB shall be capable of being used as Incomer Circuit Breaker and
shall be suitable for use as an isolator. In case of multiple MCBs in a single location (DB), it shall be
possible to remove any MCB without having to disturb other MCB's in the vicinity.
RCCB shall be available in 2 pole and 4 pole versions and threshold sensitivities of 30mA, 100mA, 300mA
and current ratings from 25 to 80A. Rating and sensitivities shall be as specified.
RCCB shall comply with IS 12640-1988/IEC 1008. The short circuit withstand of the RCCB without the
associated short circuit/overhead protection shall not be less than 3 kA. It shall be operationally
independent of line voltage. The sensitivity thresholds (30mA, 100mA, 300mA) shall be of non-user
adjustable type by construction.
Provide RCCB per 6 branch circuits for General Purpose (Normal Power) or when indicated.
No RCCB will be provided at UPS Boards.
Current transformers shall comply with the requirements of IS 2705. They shall have ratios, outputs and
accuracy as specified/required. All CT's shall be of resin cast type unless otherwise specifically called for.
All CTs shall be of bar type primary or suitable for the cable given type and size.
For all the CTs suitable type and size clamps are to be supplied for mounting in the switchboards.
Polarities and terminal markings of primary and secondary shall be clearly marked on all CTs.
d) System Voltage
1. LT:415V, 3Ph, 50Hz
All the Potential Transformers shall comply with the requirements of IS 3156 latest edition. All PT's shall
be resin cast type and shall have Voltage ratios, output and accuracy class as Specified in Data Sheer.
All PT's shall be single phase, dry type suitable for mounting inside the panel or cubicles. Clamps, brackets
and supports required for the mounting shall be supplied along with PT.
Polarities and Terminal markings shall be clearly marked in all PT's. Name plate indicating, voltage ratio,
burden, accuracy class, type, serial number, make and model plus other related data, shall be provided.
A common earth terminal for earthing of core, bolts, clamps (non current carrying metal parts) etc., shall
be provided.
All instruments and meters shall be enclosed in dust proof, moisture resistant black finished cases and
shall be suitable for tropical use. They shall be calibrated to read directly the primary quantities. They
shall be accurately adjusted and calibrated at Works and shall have means of calibration, check and
adjustment at site. Definition of various meters as follows:-
a. Power Qulaity meters Needs Complete Electrical Data that includes Analyzer Harmonics,
Voltage Sags,Swells, Current Peaks, Vectorial Information on V and I etc.
b. Load Manager : It is derived from managerial terms that to have effective Control (Manual or
Automatic ) over electrical loads need to have comprehensive information.
c. Multi Function meter : A meter that Can Monitor Control and Communicate meter and Expand to
Interface with External Environment like PC/PLC/DCS SCADA etc.
e. Power & Energy Energy meter is an Indication of Consumption it also needs to meter Show Work
Done , need to Have Power and Energy
f. Multi Data Meter A single Instrument will Display Many Electrical Parameters
a. Individual Voltmeter /Ammeter (Used on all Outgoings feeders or DB feeders located outside
Sub Stations) ) – Equvalent to New Horizon’s VM 300 or AM 301 series)
1. Meter to Simultenously display all three Phases of the chossen parameter i.e V in
Voltmeter and Amps in ammeter
2. Suitable for Three Phase 3 OR 4 Wire LT Systems
3. in ammeter cabpable of Handling 1/5 Amps with programmable CT ratio from 0-8000
Amps
4. 3 ½ or 4 ½ Digit Meters
b. VAF POWER METER ( Used on Main outgoing Panels Located within Sub station) ( Equvalent
to New Horizon make model mdm)
5.9.2 Energy meters with Power ( used in all panels where Loads are running 30 % of the utility Time of the
factory /Building ) (Equvalaent to New Horizxon make model mico 3 )
A. Must Indicate kw and Kwh through Selectable Display Switch on LCD display
B. Inputs: Voltage: 250V from 20 to 800 Hz
5.9.3 Dual Energy meter ( Used in Multi tenant Billing or Multi product Energy Accounting) - Equvalaent to New
Horizon make model mico 3 2 T
A. Must Indicate kw and KWH of EB and Dg selectable through Seprate Display Switch
B. Tarrif Change to be initated through Volt Free Contacts ( NO Aux or DG power will be available
C. Inputs: Voltage: 250V from 20 to 800 Hz
D. Current: 5 A from 20 to 800 Hz with Field programmable Ct ratios
E. Input overload: Voltage: max.264 Vrms phase to neutral Current: max 20 Arms,
F. Automatic Scale Change on V and I for linearity of reading min scales: 2 current scales 1 voltage scale
and Auto offsetting of Errors for Consistent reading
G. Accuracy: Class 1 according to IEC1036 standards
H. IP rating : Instrument = IP20 Front panel = IP40
I. Temperature range: from -10°C to +40°C Relative humidity: R.H. max 90% Condensation: not
permitted
J. Isolation: in accordance with group B VDE 0110 standards for 250 VACrms operating voltages.
K. Output through RS 485 confirming to J MODBUS MODICON communication Protocol
5.9.4 Energy Analyzer Used in Electrical Panels (Equivalent to New Horizxon make model PLUS 96 )
1. To Display Voltage Current Frequency Active Power Power factor and kWh
2. LCD Display with Seprate switch for Selecting the Required parameters
3. Inputs: Voltmetric: 500VAC 20-800 Hz Input impedance: 2 Mohm
4. Current 0-5 A from external CTs with Field Programabamle CT ratio
5. Overload: V: max. 800 Vrms, A: max. 7 Arms
6. Connection: Three phase delta networks (3 phases without neutral wire) Three phase STAR
connection (3 phase + neutral )
7. Accuracy: ≤0,5% of the reading x V and I, 1% of the reading x P. as per IEC 1036
8. Automatic Scale Change on V and I for linearity of reading min scales: 2 current scales 1 voltage scale
and Auto offsetting of Errors for Consistent reading
9. Protection class: Front= IP40
10. Temperature range: -10°C + 50°C Relative humidity: RH: max. 90%. Condensation: not allowed.
11. Insulation: according VDE 0110, group C for rated voltages of 500 VAC rms.
12. Output through RS 485 confirming to J MODBUS MODICON communication Protocol
5.9.5 Load Manager /Multi Function meter used on All Transformer and Outgoing Panels (Equvalaent to New
Horizxon make model FLASH NH )
5.9.6 Power Quality meter - Used on Main HT Incoming /UPS panels /Power Qulaity affects production
Equvalent to New horizon X3mH series
a) To Display All Electrical parameter V,I,Hz,kw,kVA,kVAr ,Energy(kwh kVAh,kVArh), Max Demand and
Neutral Current
b) To Display Individual harmonics from 0 to 31 on V , I and KW with Indication of Direction of Harmonic
from load to Source or Vice versa
c) POWER QUALITY EVENTS (EN 50160 standards) Meter should detect and stores, with individual date-
time stamp several events giving an accurate monitoring of the power supply quality according to the
EN 50160 standards. It should store on 2 MB Flash memory
d) Voltage sags/dips , Temporary over voltage/swell and Temporary current peak and direction of flow
i.e. short duration events (1 cycle resolution) with registration of date-time, event type, phase
involved, duration in number of cycles and min/max parameter value attained during each event.
e) Under voltage/voltage interruption Over voltage and Over current and direction of flow i.e. medium
and long duration events with registration of event start-end date/time, event type, phase involved
and parameter min/max value attained during each event.
f) MIN. AND MAX. VALUE per Phase of V A KW and PF
g) LOAD PROFILES AND CONSUMPTION DATA on all Energy and MD parameters
h) HARMONICS SURVEYS to Cover Individual harmonics with the direction of Harmonic recorded with
date/time stamped sample of 42 default readings is automatically saved to the instruments'built-in
memory on a circular buffer (FIFO) covering a 10-day survey period with samples taken every 2
minutes and data organised in daily files.
i) Accuracy Class 1 on energy complying with IEC EN 61036. Quadrants ........ 2 and 4 quadrant
measurement (programmable) with Auto Automatic Scale Change on V and I for linearity of reading
min scales: 2 current scales 1 voltage scale and Auto offsetting of Errors for Consistent reading
j) Standards - Safety: ...............IEC EN 61010 class 2 – E.M.C.....................IEC EN 61326-1A
k) Protection degree .......... IP51 on front panel.
l) OUTPUT through RS 485 confirming to J MODBUS MODICON communication Protocol or Output
thru RS 4*20mA
m) 2 Set Points as 2 digital outputs rated 27Vdc-27mA (DIN43864) with programmable functionality
(pulse output or alarm)
n) Galvanic Isolation on all inputs and outputs to Attunate RFI Disturbance
5.9.7. TVSS
TVSS shall be as per IEEE standards & UL listed. The current rating of TVSS for different panels shall be as
specified below.
The TVSS shall be mounted in a separate chamber away from control components. The cable length
between bus & TVSS shall be less as much as possible.
T e st ed i n a cco rd an c e wi th AN SI /IE E E C 62 .1 1 C6 2. 45 te st ed .
UL 14 4 9 ( 2n d ed it ion ) , UL 12 83 & CS A li st ed .
Th e mod u l e u s ed in th e T VS S sh ou ld b e UL at 60 0V A C an d 3 00, 0 00 AI C.
SURGE
200KA
3000 ABOVE L-N, L-E, N-E 200KA
1.0 GENERAL
1.1 Scope
A. Furnish and install automatic transfer switches (ATS) with number of poles, amperage, voltage,
withstand and close-on ratings as per schematic. Each automatic transfer shall consist of an
inherently double throw power transfer switch mechanism and a microprocessor controller to
provide automatic operation. All transfer switches and controllers shall be the products of the
same manufacturer.
The automatic transfer switches and controls shall conform to the requirements of:
2.0 PRODUCTS
A. The transfer switch shall be electrically operated and mechanically held. The
electrical operator shall be a momentarily energized, single-solenoid
mechanism. Main operators which include overcurrent disconnect devices,
linear motors or gears shall not be acceptable. The switch shall be
mechanically interlocked to ensure only two possible positions, normal or
emergency.
D. All main contacts shall be silver composition. Switches rated 600 amperes
and above shall have segmented, blow-on construction for high withstand and
close-on capability and be protected by separate arcing contacts.
E. Inspection of all contacts shall be possible from the front of the switch without
disassembly of operating linkages and without disconnection of power
conductors. Switches rated 600 amps and higher shall have front removable
and replaceable contacts. All stationary and moveable contacts shall be
replaceable without removing power conductors and/or bus bars.
H. Where neutral conductors are to be solidly connected as shown on the plans, a neutral conductor plate
with fully rated AL-CU pressure connectors shall be provided.
A. The controller's sensing and logic shall be provided by a single built -in microprocessor for
maximum reliability, minimum maintenance, and the ability to communicate serially through an
optional serial communication module.
B. A single controller shall provide twelve selectable nominal voltages for maximum
application flexibility and minimal spare part requirements. Voltage sensing shall be true RMS type
and shall be accurate to ± 1% of nominal voltage. Frequency sensing shall be accurate to ± 0.2%.
The panel shall be capable of operating over a temperature range of -20 to +60 degrees C and
storage from -55 to +85 degrees C.
C. The controller shall be connected to the transfer switch by an interconnecting wiring harness. The
harness shall include a keyed disconnect plug to enablethe controller to be disconnected from
the transfer switch for routine maintenance. Sensing and control logic shall be provided on
multi-layer printed circuit boards. Interfacing relays shall be industrial grade plug-in type with dust
covers. The panel shall be enclosed with a protective cover and be
mounted separately from the transfer switch unit for safety and ease of maintenance. The
protective cover shall include a built-in pocket for storage of the operator's manuals.
E. The controller shall meet or exceed the requirements for Electromagnetic Compatibility (EMC)
as follows:
2.3 Enclosure shall be provided by local switch gear manufacturer, manufacturer shall follow the guidelines of
ASCO while installing the same.
B. All standard and optional door-mounted switches and pilot lights shall be 16-mm industrial grade
type or equivalent for easy viewing & replacement. Door
controls shall be provided on a separate removable plate, which can be supplied loose for
open type units.
3.0 OPERATION
A. A four line, 20 character LCD display and keypad shall be an integral part of the controller for viewing
all available data and setting desired operational parameters. Operational parameters shall also be
available for viewing and limited control through the serial communications input port. The following
parameters shall only be adjustable via DIP switches on the controlller:
All instructions and controller settings shall be easily accessible, readable and accomplished without
the use of codes, calculations, or instruction manuals.
A. Voltage and frequency on both the normal and emergency sources (as noted
below) shall be continuously monitored, with the following pickup, dropout,
and trip setting capabilities (values shown as % of nominal unless otherwise
specified):
B. Repetitive accuracy of all settings shall be within ± 0.5% over an operating temperature range of -
20°C to 60°C.
C. Voltage and frequency settings shall be field adjustable in 1% increments either locally with the
display and keypad or remotely via serial communications port access.
D. The controller shall be capable (when activated by the keypad or through the serial port) of sensing
the phase rotation of both the normal and emergency sources. The source shall be considered
unacceptable if the phase rotation is not the preferred rotation selected (ABC or CBA).
E. Source status screens shall be provided for both normal & emergency to provide digital readout of
voltage on all 3 phases, frequency, and phase rotation.
B. A time delay shall be provided on transfer to emergency, adjustable from 0 to 60 minutes, for
controlled timing of transfer of loads to emergency.
D. A time delay shall be provided on shut down of engine generator for cool down, adjustable
from 0 to 60 minutes.
E. A time delay activated output signal shall also be provided to drive an external relay(s) for selective
load disconnect control. The controller shall have the ability to activate an adjustable 0 to 5 minute
time delay in any of the following modes:
F. The controller shall also include the following built-in time delays for optional Closed Transition and
Delayed Transition operation:
1. 1 to 5 minute time delay on failure to synchronize normal and emergency sources prior to closed
transition transfer.
2. 0.1 to 9.99 second time delay on an extended parallel condition of both power sources during
closed transition operation.
3. 0 to 5 minute time delay for the load disconnect position for delayed transition operation.
G. All time delays shall be adjustable in 1 second increments, except the extended parallel
time, which shall be adjustable in .01 second increments.
H. All time delays shall be adjustable by using the LCD display and keypad or with a remote device
connected to the serial communications port.
A. A three position momentary-type test switch shall be provided for the test / automatic / reset
modes. The test position will simulate a normal source failure. The reset position shall bypass
the time delays on either transfer to emergency or retransfer to normal.
B. A SPDT contact, rated 5 amps at 30 VDC, shall be provided for a low-voltage engine start signal. The
start signal shall prevent dry cranking of the engine by requiring the generator set to reach proper
output, and run for the duration of the cool down setting, regardless of whether the normal
source restores before the load is transferred.
D. LED indicating lights (16 mm industrial grade, type 12) shall be provided; one to indicate when the ATS is connected to the
normal source (green) and one to indicate when the ATS is connected to the emergency source (red).
E. LED indicating lights (16 mm industrial grade, type 12) shall be provided and energized by controller outputs. The lights shall
provide true source availability of the normal and emergency sources, as determined by the voltage sensing trip and reset
settings for each source.
The following features shall be built-in to the controller, but capable of being activated
through keypad programming or the serial port only when required by the user:
G. Terminals shall be provided for a remote contact which opens to signal the
ATS to transfer to emergency and for remote contacts which open to inhibit
transfer to emergency and/or retransfer to normal. Both of these inhibit
signals can be activated through the keypad or serial port.
H. An Inphase monitor shall be provided in the controller. The monitor shall control transfer so that motor load inrush currents do
not exceed normal starting currents, and shall not require external control of power sources. The inphase monitor shall be
specifically designed for and be the product of the ATS manufacturer. The inphase monitor shall be equal to ASCO Feature 27.
I. The controller shall be capable of accepting a normally open contact that will allow the transfer switch to function in a non-
automatic mode using an external control device.
J. Engine Exerciser - The controller shall provide an internal engine exerciser. The engine exerciser shall allow the user to program
up to seven different exercise routines. For each routine, the user shall be able to:
At the end of the specified duration the switch shall transfer the load back to normal and run the
generator for the specified cool down period. A 10-year life battery that supplies power to the real
time clock in the event of a power loss will maintain all time and date information.
K. System Status - The controller LCD display shall include a "System Status" screen which shall be readily accessible from any point
in the menu by depressing the "ESC" key a maximum of two times. This screen shall display a clear description of the active
operating sequence and switch position. For example,
Controllers that require multiple screens to determine system status or display "coded" system status
messages, which must be explained by references in the operator's manual, are not permissible.
L. Self Diagnostics - The controller shall contain a diagnostic screen for the purpose of detecting
system errors. This screen shall provide information on the status input signals to the controller
which may be preventing load transfer commands from being completed.
M. Communications Interface - The controller shall be capable of interfacing, through an optional serial
communication module, with a network of transfer switches, locally (up to 4000 ft.) or remotely
through modem serial communications. Standard software specific for transfer switch applications
shall be available by the transfer switch manufacturer. This software shall allow for the monitoring,
control and setup of parameters.
N. Data Logging - The controller shall have the ability to log data and to maintain the last 99
events, even in the event of total power loss. The following events shall be time and date
stamped and maintained in a nonvolatile memory:
1. Event Logging
2. Statistical Data
O. Communications Module - A full duplex RS485 interface shall be installed in the ATS controller to
enable serial communications. The serial communications shall be capable of a direct connect
or multi-drop configured network. This module shall allow for the seamless integration of existing or
new communication transfer devices. The serial communication interface shall be equal to ASCO
Accessory 72.
P. External DC Power Supply - An optional provision shall be available to connect an external 24 VDC
power supply to allow the LCD and the door mounted control indicators to remain functional when
both power sources are dead. This option shall be equivalent to ASCO accessory 1G.
A. The ATS shall be rated to close on and withstand the available RMS symmetrical short
circuit current at the ATS terminals with the type of overcurrent protection shown on the
plans.
B. The ATS shall be UL listed in accordance with UL 1008 and be labeled in accordance with that
standard's 1% and 3 cycle, long-time ratings. ATSs which are not tested and labeled with 1%
and 3 cycle (any breaker) ratings and have series, or specific breaker ratings only, are not
acceptable.
A. The complete ATS shall be factory tested to ensure proper operation of the individual
components and correct overall sequence of operation and to ensure that the operating
transfer time, voltage, frequency and time delay settings are in compliance with the specification
requirements.
B. Upon request, the manufacturer shall provide a notarized letter certifying compliance with
all of the requirements of this specification including compliance with the above codes and
standards, and withstand and closing ratings. The certification shall identify, by serial number(s),
the equipment involved. No exceptions to the specifications, other than those stipulated at
the time of the submittal, shall be included in the certification.
C. The ATS manufacturer shall be certified to ISO 9001 International Quality Standard and the
manufacturer shall have third party certification verifying quality assurance in
design/development, production, installation and servicing in accordance with ISO 9001.
B. The manufacturer shall maintain records of each switch, by serial number, for a minimum of 20 years.
A. Furnish data monitors at locations shown to monitor all functions Specified below.
B. The Data Monitors shall be listed to UL 3111-1, CSA, CE Mark, and industrially rated for an operating
temperature range of -20 °C to 60 °C.
E. Each Data Monitor shall be capable of interfacing with an optional communications module to
permit information to be sent to central locationfor display, analysis, and logging.
F. The Data Monitor shall accept inputs from industry standard instrument transformers (120 VAC
secondary PT's and 5A secondary CTS.) Direct phase voltage connections, 600 VAC and under, shall
be possible without the use of PT's.
G. The Data Monitor shall be applied in single, 3-phase, or three & four wire circuits.A fourth CT input
shall be available to measure neutral or ground current.
H. All setup parameters required by the Data Monitors shall be stored in nonvolatile memory and
retained in the event of a control power interruption.
I. The following metered readings shall be communicated by the DataMonitor, via serial
communication, when equipped with optional serial
communications module:
Push buttons shall be of momentary contact type with rear terminal connection. These shall be suitably
shrouded to prevent inadvertent operation. Integral inscription plates engraved with their functions shall
be provided. All push buttons shall have two Normally Closed and two Normally.
Open contacts comprising rivets of pure silver. The contacts shall be able to make and carry 5 A and break
up one amp inductive loads at 250V DC.
Cable entries and terminals shall be provided in the switchboard to suit the number, type and size of
copper conductor power cables and copper conductor control cable specified in the detailed
specifications.
Provision shall be made for top or bottom entry of cables as required. Generous size of cabling chambers
shall be provided with the position of cable gland and terminals such that cables can be easily and safely
terminated.
Barriers or shrouds shall be provided to permit safe working at the terminals of one circuit without
accidentally touching that of another live circuit.
Cable risers shall be adequately supported to withstand the effects of rated short circuit currents without
damage and without causing secondary faults.
All control wiring shall be carried out with 660/1100V grade single core PVC cable having stranded copper
conductors with minimum cross section of 1.5Sqmm for potential circuits and 2.5Sqmm for current
transformer circuits.
Wiring shall be neatly bunched, adequately supported and properly routed to allow for easy access and
maintenance.
Wires shall be identified by numbered ferrules at each end. The ferrules shall be of ring type and of non-
deteriorating material. They shall be firmly located on each termination so as to prevent free movement.
Terminal blocks shall have a minimum current rating of 10 Amps and shall be shrouded. Provisions shall
be made for label inscriptions. At least 20% spare terminals shall be provided on each panel and these
spare terminals shall be uniformly distributed on all terminal blocks.
Terminal blocks for current transformer and voltage transformer secondary leads shall be provided with
test links and isolating facilities. Also current transformer secondary leads shall be provided with short
circuiting and earthing facilities.
5.14 Relays
All Relays shall conform to the requirement of IS : 3231/IS 8686 or other applicable approved standards
Relays
All AC Relays shall be suitable for operation at 50Hz. AC Voltage operated relays shall be suitable for 110v
3 Volts PT secondaries and Current operated relays for 5Amp CT secondaries, as specified in this
specification. Voltage operated relays shall have adequate thermal capacity for continuous operation.
Auxiliary Relays and Timers, shall have pairs of contacts as required to complete the scheme. Contacts
shall be silver faced with spring action.
All Protective Relays, Auxiliary Relays and Timers except the lockout relays and Interlocking relays
specified, shall be provided with self reset type contacts. All Trip relays and Timers shall be provided with
externally hand reset positive action provided with inscription subject to Consultant/Developer approval.
Timers shall be of the electromagnetic or solid state type.
Wherever solid state relays are used the following requirement shall be met:
(a). All Relays shall be designed for operating under an ambient temperature 55 Deg; C and 100%
relative humidity.
(b) All accessories required for correct operation of each relay shall be supported by the Contractor
without any extra cost.
(c) The solid state relays shall be stable and suitably protected against transient or induced over
voltages. The Bidder shall state clearly in his list special requirements, if any, for DC input
arrangement or cabling considered necessary for satisfactory operation of solid state relays
quoted by him.
6.0 Labelling
6.1 General
Every switchboard, switchboard control contactor, time switch, relay, indicator lamp, meter. motor
starter, link and any control or protection equipment within or on a switchboard shall be clearly and
accurately labelled.
Labels shall be engraved laminated plastic or photo anodised rigid aluminium and shall comply with the
following requirements.
Except where otherwise required, labels shall be fixed adjacent to, but not on any item of equipment.
Engraved lettering shall be black on a white background, except that the label for a main switch shall have
red lettering on a white background, and warning and caution labels shall have white lettering on a red
background.
The minimum height of lettering shall be 3mm and of sufficient definition to allow easy reading.
Screws shall be tightened with nuts or into tapped holes in the switchboard. Mechanically expanded
plastic rivets of minimum 6mm head diameter are acceptable instead of screws. Aluminium rivets may be
used to fix aluminium labels only. Self-tapping screws, thread-cutting screws or other fixings are not
acceptable.
A switchboard designation label shall be provided. For other than main switchboards, the designation
label shall also state the source of electrical supply. Separate sections of enclosures shall be identified.
The label for any section or enclosure containing Supply Authority equipment shall be to the satisfaction
of the Consultant / Developer and the Supply Authority.
(a) Circuit designation for all main switches, main controls and submain controls.
(b) Details of the consumer's mains and all submains.
(c) Incoming busbar or cable rating to the first tee-off.
For identification of final sub circuits, a typed schedule, cross-referenced to the lighting and power layout
plans shall be provided. The schedule shall be protected by a plastic sheet and fixed in a suitable frame
mounted on the inside of the relevant switchboard door or, if the switchboard has no door, on the wall
immediately adjacent to the switchboard.
Labels identifying equipment within a switchboard shall be located such that the item referred to is
obvious and the lettering is not substantially obscured by the temporary or permanent position of any
equipment or wiring.
For plug-in equipment where items are physically but not functionally interchangeable, the label wording
shall be expanded to clearly identify the removable section (e.g. to identify the contact configuration or
timing range). Where this is not possible, a second identifying label shall be glue fixed to the removable
section.
The function and coding shown on the circuit diagram shall be used.
The MEN link shall be labeled, or stamped and infilled, `MEN LINK' on the link.
WARNING
PAINTED COATING ON BUSBARS OR TERMINATIONS IS NOT INSULATION.
If a stand-by power supply is installed, an appropriate warning label shall be fixed at the main switch or
local main switch. An example of a typical label is:
WARNING
IN THE EVENT OF LOSS OF NORMAL SUPPLY GENERATOR SET WILL AUTOMATICALLY START AND BE
CONNECTED TO THIS SWITCHBOARD
When anti-condensation heaters are fitted, a label shall be provided at each heater reading
WARNING
THERMOSTATICALLY CONTROLLED ANTI-CONDENSATION HEATER-DO NOT SWITCH OFF
7.0 Tests
7.1 General
The routine tests shall be conducted as per IS standards on each Power Control Center and shall comprise:
Inspection of the Switchboards including inspection of wiring and electrical operational and functional
tests where necessary.
Insulation resistance of all secondary wiring between phase and earth shall be measured. Insulation test
shall be carried out both before and after high voltage test.
8.1 Storing
The panels shall be stored in a well ventilated dry place.
Suitable polythene covers shall be pro-aided for necessary protection against moisture, dust, and vermin.
8.2 Erection
Switchboards shall be installed over trench/floor as required. Suitable grouping holes shall be provided in
the flooring. Suitable MS base channel shall be embedded in the flooring on which the panel can directly
be installed The switchboards shall be properly aligned and bolted to the flooring by at least four bolts.
Cables shall be terminated on the bottom plate or top plate as the case may be, by using brass
compression glands. The individual cables as shall then be led through the panel to the required feeder
The base channel used for erection of panels shall form part of the cost of the panel and shall not be
measured or paid separately.
(a) All main and auxiliary bus bar connections shall be checked and tightened.
(b) All wiring terminations and bus bar joints shall be checked and tightened.
(c) Wiring shall be checked to ensure that it is according to the approved drawing.
(d) ll wiring shall be tested for insulation resistance by a 500 volt megger
(f) Suitable injection tests shall be applied to all the measuring instruments to establish the
correctness and accuracy of calibration and working order if required by the Developer.
(g) All relays and protective devices shall be tested for correctness of settings and operation by
introducing a current generator and an ammeter in the circuit or shall produce calibration or test
certificate as required by the inspectorate or Consultant / Developer.
(i) Make, type and ratings of all components shall be checked and verified as per the approved
drawings.
All steel work used in this Contract shall in general, undergo the following process of treatment and finish.
(a) Degreasing: by hot alkaline degreasing solution followed by cold water rinsing to remove
traces of alkaline solution.
(b) Phosphating: by a recognised phosphating process to facilitate durable coating of the paint on
the metal surfaces and also to prevent the spread of rust in the event of the paint film being
mechanically damaged. This again shall be followed by hot water rinsing to remove traces of
phosphate solution.
(d) Primer : Primer coating with a coat of corrosion resistant primer applied on wet surface.
(e) Finish coat: Two finishing coats of stoving synthetic enamel paint to the specified shade of IS 5.
Both the finish coats shall be only spray painted.
(f) For outdoor units the finishing coat shall be of weather resistant stoving epoxy paint of specified
shade of IS5.
The installation shall be guaranteed against faulty workmanship for minimum of one year from the date
of practical completion. All faulty workmanship shall be replaced and restored to full operation at no cost
to the Developer within the guarantee period.
Manufacturer's guarantees and warranties shall be obtained in accordance with Clause 9.11 of the
Preliminaries. The warranty period shall be for eighteen months commencing from the date of installation
or twelve months from the date of practical completion, whichever is the first to occur.
1.0 General
1.1 Type
Medium voltage cables shall be aluminium conductor, XLPE/ PVC insulated, PVC sheathed and steel wire
armoured or steel tape armoured construction. The cables shall conform to IS 1554 Part I in all respects.
Cables shall be laid in tray/hume pipe/in ready-made trenches etc., as required.
1.2 Rating
Cores shall be provided with the following colour scheme of PVC insulation:
1 core : Red/Black/Yellow/Blue
2.1 Storing
On receipt of cables at site the cables shall be inspected and stored in a safe place.
2.2 Laying
Cables shall be laid in outdoor trenches wherever called for. The depth of the trenches shall not be less
than 75 cm from the final ground level. The width of the trenches shall suit easy laying of cable. Where
more than one cable has to be laid in the same trench, all attempts shall be made to keep the axial
distance between successive cables to be atleast 1d where 'd' is the diameter of the bigger cable. The
trenches shall be cut square with vertical sidewalls and with uniform depth. Wherever cables are bent,
the minimum bending radius shall not be less than 12 times the diameter of the cable. After the cable is
laid and straightened, it shall be covered with sand cushion. Over this a course of cable protection tiles or
burnt brick shall be provided on either sides and above. Trench shall be back filled with earth and
consolidated. Cables shall be laid in hume pipes / stoneware pipes at all road crossings & wall entries.
Approved cable markers made of CI indicating the voltage, no. of cables and the direction of run of the
cables shall be installed at regular intervals.
Cables shall be laid in indoor trenches wherever specified. Suitable angle iron brackets, clamps, hoods and
saddles shall be used for securing the cable in position.
Cables shall be laid on cable trays/racks wherever specified. Cable racks/trays shall be of perforated steel
section slotted angles for suitable purpose. The trays/racks shall be complete with plates, tees, elbows,
risers and all necessary hardware. The steel trays shall be painted. Cable trays shall be erected properly to
present a neat and clean appearance. Suitable cleats or saddles shall be used for securing the cables to
the cable trays. The cable trays shall comply with the following requirements:
a) The trays are ladder type and shall have suitable strength and rigidity to provide adequate
support for all contained cables.
b) It shall not present sharp edges, burrs of projections injurious to the insulation of the
wiring/cables.
c) If made of Sheet metal, it shall be adequately strength protected against corrosion or shall be
made of corrosion resistant material.
e) It shall include fittings such as horizontal, vertical bends, tie rods, hooks etc., or other suitable
means for changes in direction and elevation of runs, fishplates and hard ware.
2.6 Installation
a) Cable trays shall be installed as a complete system. Trays shall be supported properly from the
building structure. The entire cable tray system shall be rigid.
b) Each run of the cable tray shall be completed before the installation of cables.
e) Where cables of different system are installed on the same cable tray, non-combustible solid
barriers shall be used for segregating the cables.
f) Cable trays shall be grounded by two nos. earth continuity wires. Cable trays shall not be used
as equipment grounding conductors.
Cable jointing shall be done as per the recommendations of the cable manufacturer. Jointing shall be
done by qualified cable jointers.
Each terminations shall be carried out using brass compression glands and cable sockets. Hydraulic
crimping tool shall be used for making the end terminations. Cable gland shall be bonded to the earth
by suing suitable size G.I. wire/tape.
Suitable identification tags with the feeder designation inscribed on an aluminium/G.I. sheet shall be tied
to either ends of each cable.
Cables shall be tested at factory as per the requirements of IS 1554 Part I. The tests shall incorporate
routine tests, type tests and acceptance tests. Copy of such test certificates shall be furnished to the
Developer prior to dispatch.
3.1 Generally
The general requirements for all joints and terminations of aluminium cables shall be:
a. To remove oxide from the conductor and prevent the oxide re-forming.
For all aluminium cables, the oxide shall be removed by thoroughly wire-brushing the bare end of the
cable. After brushing, a liberal coating of an approved oxide-inhibiting, moisture-excluding thermally
stable grease shall be applied, and the cable shall be wire-brushed again through the grease. Cable
strands shall not be separated before brushing.
Bare aluminium lugs, ferrules and other connectors, unless factory-tinned or factory pre-filled with
inhibiting grease, shall be wire-brushed and grease coated in the same way as cables.
Before making any joints or terminations in aluminium cables, the Contractor shall submit the proposed
method for the Consultant / Developer approval. Notice of at least three working days shall be given
before making any joints or terminations, to enable the Consultant / Developer to witness the work.
Tinned copper ferrules shall be terminated using the compression method. For compression connections
on stranded cables, a hexagonal die shall be used, on solid conductor cables, indent type dies shall be
used, with at least two indentations per cable connection. Lugs of ferrules shall be selected to suit the size
and shape of the conductor. Compression dies shall be selected to suit the particular lug or ferrule.
Aluminium crimp lugs shall be filled with oxide inhibiting grease.
Joints by the fusion welding method shall be made by jointers experienced in this method. Particular care
shall be taken to protect the cable insulation from heat by fixing substantial heat sinks to the cable near
the joint. After completion of the weld the joint shall be wire brushed and all sharp projections filed
smooth.
Where electro-tinned aluminium lugs are used, they shall be fixed to the cable using the compression
method. The palm of the lug shall be bolted to the copper bus-bar or terminal using a stainless steel bolt
and nut, with one large diameter stainless steel flat washer and two "Belleville" spring cup washers.
All nuts shall be adequately torque tightened to manufacturer's recommended levels. Identification
tags for feeder designation shall be by using `Phoenix' plastic cable markers, tied to either end of each
cable.
All pipelines laid below roads shall be taken through suitable underground trenches. The size of trenches
shall be as per drawings.
All works across roads shall be carried out as per the directions of the Development Manager. Necessary
safety measures shall be taken to divert traffic. Care shall be taken not to disturb electrical and
communication cables.
All pipes, water mains, cables, etc. met with during the course of excavation shall be carefully protected
and supported. In any case damage is caused, the same shall be made good at no extra cost, failing which
necessary rectification will be done by Development Manager at the risk and cost of the Contractor.
4.3 Refilling:
The filling shall be done in layers not exceeding 15mm in depth. Each layer shall be watered, rammed and
compacted. Ramming shall be done with iron rammers where possible and with blunt end of the crow
bars where rammers cannot be used. Special care shall be taken to ensure that no damage is caused to
the pipes, drains, masonry or concrete in the trenches.
Filling in trenches shall be commenced soon after the joints of pipes, cables, conduits etc. have been
tested and approved by Development Manager. The space around the pipes shall be cleared of all debris
where the trenches are excavated in hard/soft soil. The filling shall be done with earth on the sides and
top of pipes in layers not exceeding 15mm in depth. Each layer shall be watered rammed and compacted.
The clods and lumps of earth exceeding 8cm in any direction shall be broken or removed before the
excavated earth is used for filling. Generally no test is done to determine the instu density of filled earth
but on the discretion of Development Manager the 95 proctor’s compaction test may be done to ensure
the in situ density after filling. Consolidation is removal of water from the pores and compaction is the
The Contractor shall at his own cost make good promptly during the whole period the works are in hand,
any settlements that may occur in the surfaces or roads, beams, footpaths, gardens, open spaces etc.
Whether public or private caused by his trenches or by his other excavations due to not using the method
of compaction as given in clause 3/2.8.3.5 and he shall be liable for any accidents caused thereby.
He shall also at his own expense and charges, repair and make good any damage done to the building and
other properties.
4.5 Testing
Cables shall be tested at the factory as per the requirements of 1S 1554 Part 1. The tests shall incorporate
routine tests, type tests and acceptance tests. A copy of such test certificates shall be furnished to the
Consultant / Developer prior to dispatch.
Light control switches shall be of a 240V, 6A rating for controlling light points as specified. Light control
switches shall be of plate type design with metal or PVC boxes suitable for flush mounting for general
lighting. Light control switch boxes shall be of metal or PVC as specified.
All sockets 6A and 16 A ratings shall be of flush mounting type (unless otherwise indicated with control
switches of plate type design of the same rating as that of the sockets. All socket outlets shall be of 3 pin
type with PVC boxes. UPS sockets should not contain switch, need to be different consistent color from
others.
Industrial tax: sockets shall be provided wherever specifically called for on the drawings. Industrial sockets
shall be rated as specified. Plugs and sockets shall have 3 pins for single phase applications and 5 pins for
3 phase applications. The sockets shall be provided with suitable plug top and cable entry device and shall
be controlled by a suitably rated rotary switch. The sockets shall be housed in suitable PVC housings of IP
54 protection class.
Accessories for light outlets such as lamp holders, 3 plate ceiling rose, etc. shall be in conformity with
requirements of relevant IS specification. Only approved make of accessories shall be supplied.
1.4 Installation
All switch connections shall be made only after ensuring the continuity of wires and terminations. Tapping
of wires shall be done only at the terminals of switches, sockets and ceiling roofs and terminal blocks.
The arrangement of switches and sockets shall be neat, systematic, and aesthetic. The Contractor shall
obtain approval from the Consultant / Developer with regard to the proper location of switches and all
outlets.
The enclosures of sockets and pin of the sockets shall be connected to the ground through a proper size
insulated earth continuity wire. Metal or hylam phase barriers shall be interposed between switches
located in a common enclosure, when wired on different phases.
Wiring of sub-mains and circuit mains in concealed or surface conduit systems shall be with 2mm thick
rigid PVC conduits and conduit accessories with 660/1100V grade PVC insulated copper flexible wires for
phase neutral and earth.
Sub-main shall include Ms or PVC draw-boxes, sized as required to be located at every floor for easy
drawing of wires.
Wiring of light points and 6A switched socket outlets by providing PVC or 16G rigid MS Box with
accessories, and 2.5 sqmm 660V/1100V grade PVC flexible multi strand copper wires, SP MCB 6A modular
plate switch, and other point wiring accessories and carrying out surface/concealed conduit point wiring.
All light points, 5A sockets shall be earthed using the third core of green colour insulated copper wires.
1.7 Labeling
The Contractor shall provide labelling for all light control switches, industrial-type sockets, socket outlets,
permanently connected devices, etc, identifying the distribution board and circuit breaker number, in an
approved manner, acceptable to the Consultant / Developer, to provide ready identification.
General
There are no devices or methods capable of modifying the natural weather phenomena to the extent that they can
prevent lightning discharges. Lightning flashes to, or nearby, structures (or lines connected to the structures) are
hazardous to the structures, their contents and installations as well as to lines. This is why lightning protection
measures are essential
Lightning Protection System shall be in accordance with IS IEC 62305-3 & NBC-2016. Lightning Protection consists of
external Protection for the building with Air termination, Down Conductors and Earthing and Internal protection for
power lines with Surge Protective devices.
Generally lightning between cloud and ground creates failures. How ever inter-cloud and intra-could lightning also can
create potential differences and failures in electronic installation. More than 95 % of Lightning strikes are of Negative
impulse and less than 5 % are of positive impulse. Positive impulses are mainly due to dry lightning in cold areas.
Current parameters as per IS/IEC 62305 and the effects of lightning are as below
Damages from lightning strike are due to Peak Current (I), Charge (C), Specific Energy (W/R) & Rate of change of
current (di/dt). Lightning protection is designed to take care of these effects of lightning and hence the following
parameters shall be strictly followed.
Effect of Lightning on External LPS (Air termination, Down Conductor and Earthing)
Effects on air-termination systems arise from both mechanical and thermal effects. Effects on down-conductors are
thermal effects due to resistive heating & mechanical effects in parallel conductors and in Bends. The real problems
with earth-termination electrodes are linked with chemical corrosion and mechanical damage caused by forces other
than electro dynamic forces.
Sizing and fixing of Materials are selected to handle the mechanical and thermal effects. Bends in down conductor shall
strictly NOT be at 90 degree (right angles) & should have a curved path of 45 degree bend. Earth electrodes are
selected based on the current handling capacity up to 1 second. To avoid corrosion problems as explained in IS/IEC
62305 (clause E.4.3.4 and E.5.4.3.2), GI is strictly not recommended inside concrete and in soil.
Effect of Lightning on Internal LPS (SPD’s for POWER, DATA lines etc)
Effect on internal LPS is mainly due to coupling and the rate of change of current. Due to Very high di/dt of the first
negative stroke. The expected problem is the response time of SPD and the voltage drop in the connecting wires. SPD’s
at the incoming panels shall have a response time less than 1 nano sec & shall be of BUSBAR Mounted type to avoid
connecting wire length.
LPL is a number associated with a set of lightning current parameters relevant to the probability that the associated
minimum & maximum values do not exceed the normally occurring lightning. LPL can be determined by Risk analysis as
explained in IS IEC 62305-2 or can be selected based on the guideline in NBC-2016.
Application LPL*
Computer Data Centers, Military Applications, Nuclear Power Stations, High raise 1
Hotels/Hospitals, airports, essential services such as telecom towers
EX-Zones in the industry and chemical sector, Low raise Hospitals & Hotels, fuel retail outlets, 2
gas station, compressor station etc
Class of LPS
80
70
0
a 60
50
40
30
IV
I II III
20
10
0
10 20 30 40 50 60
H m
Material, Configuration and Minimum cross sectional area of air terminal & down conductors
Air Termination Rod: 10 mm, 16 mm & 40 mm solid Aluminium rods (combination of sizes) (tubes are not allowed)
Aluminium to Steel SS
Aluminium accessories if connection is between Aluminium materials are necessary. SS accessories if connections are
between aluminium and copper / copper coated materials.
Earth Termination Conductor: 10 mm solid copper coated steel conductor (100 microns min coating)
GI material for earthing shall not be used as per the recommendation in IS/IEC62305 as well as Kerala electrical
inspectorate guideline.
If the structure height is more than 60 meters, top 20% of the height of the structure shall be protected with a lateral
air termination system. This is needed because the probability of flashes to the side is generally more for structures
more than 60 meters in height. More importance need to be provided to Corners, Edges and significant protrusions
such as balconies. Metallic handrails/ Aluminium frame of wall cladding if used in balconies shall be conned to air
termination / down conductors.
In PEB / Steel buildings where GI sheet roofing, air termination mesh / Rod shall be directly mounted on the sheet.
Fixing materials used shall be in good electrical contact with the sheet, shall not create water leakage.
No drilling is allowed in the terrace for fixing the air terminal, if the roof is made of concrete. Parapet wall is
exception to this.
Concrete Roof structure: Conductors shall be securely fixed on the terrace by means of concrete air terminal holders
with suitable fixing materials which is fixed on the roof by adhesive or cement mortar taking care of varying weather
conditions. Plastic air termination conductor holder is not allowed. The minimum height of this air terminal holder shall
be 50 mm to avoid the contact of conductor with water
Metal Roof structure: Conductors shall be securely fixed on the terrace by means of air terminal holder which is fixed
on the roof by metal conductor holder made of Stainless steel. As metal roof structures are normally tapered at an
angle, there are no min height criteria for metal conductor holder.
If antenna, Chillers or any other roof top electrical equipment is present in terrace, the same have to be protected by
using vertical air terminal after calculating the safety or separation distance. The vertical air terminal has to have
suitable supports to hold it. Wind speed need to be taken into account. Vertical air terminal must be connected to
horizontal air terminal by using suitable connectors.
At the crossings of the horizontal air terminals, suitable Cross connector has to be used.
Safety or Separation distance: (not required for LPS using structural natural components)
To avoid flash over to electrical/electronic apparatus, this equipment shall be kept at a distance away from LPS
components more than the safety distance as per the following calculation.
Coefficient ki depends on class of LPL/LPS (ki = 0.08 for LPL1, 0.06 for LPL 2, 0.04 for LPL3 and 4)
Coefficient kc depends on no of down conductors: kc = 0.66 for 2 down conductors, kc = 0.44 for 3 or more down
conductors
Value of coefficient km = 1
Value of L is the total distance between the equipment to be protected (for e.g. Antenna) to the equi-potential bonding
bar situated just above the ground.
Expansion piece
In order to take care the expansion of the metal in summer and contraction of the metal in winter, expansion piece
with suitable connectors have to be used at every 20m distance of horizontal air termination mesh.
The lightning protective system shall have few joints as far as possible & air terminal & down conductor have to be
straight. Where it is not possible, it should NOT be bent at 90 degree (right angles) & should have a curved path of 45
degree bend.
In order to reduce the probability of damage to electronic/electrical equipment, the down conductors shall be
arranged in equi distance in such a way that from the point of strike to earth, several parallel current paths should exist
Test joints:
At the connection to the earth conductor, a test joint should be fitted on each down conductor at a height of 1 m from
the ground, except in the case of natural down conductors combined with foundation earth electrode. The purpose of
test joint is to measure the earth resistance value. The remaining portion of down conductor (i.e., after the test joint
should be mounted inside a plastic pipe of minimum 3 mm thickness.)
Earth Terminations
For earth termination system, 2 basic types of earth electrode arrangements are applicable. Type A & Type B
arrangement.
Type A arrangement: Comprises of horizontal or vertical earth electrode installed outside the structure to be protected
connected to each down conductor. Minimum Length of vertical earth electrode shall be as below
Class of Typical Length of each vertical earth electrode based on Soil resistivity
LPS
Up to 500 Ω M 1000 Ω M 2000 Ω M 3000 Ω M
If horizontal electrodes are used, the length shall be double. In type A arrangement, the total number of earth
electrodes shall not be less than two. Type A arrangement is suitable in places where electronic equipment are not
located.
Type B arrangement: This type of arrangement comprises either a ring conductor external to the structure to be
protected, in contact with the soil for at least 80% of its total length or a foundation earth electrode. Ring earthing
must be 1 meter away from the building and 0.5m below the ground as a closed loop. Such earth electrodes can also be
meshed. For structures with extensive electronic systems or with high risk of fire, type B earthing is most preferable
method. There is no limit in the resistance of Ring Earthing if the ring radius of the ring is larger than 50 meters or 80
meters for LPL 1 and 2. For LPL 3 and 4 this radius is about 5 meters. The overall resistance of earthing system shall not
exceed 10 ohms.
Lightning Counters: At least 2 down conductors in an installation shall have a lightning counter tested as per IEC
62561. The counter shall be digital type with replaceable battery. Battery life shall be minimum 3 years. The
minimum measuring current is 1KA (8/20) and the maximum is 100 KA (10/350). The counter shall be outdoor
type, IP65 and shall be able to record date, time and no of strikes.
All materials and accessories shall be tested as per IEC 62561 for its mechanical / corrosion resistant / electrical
conductivity. Vendor shall provide test reports along with completion certificate. GI (Hot dip galvanised or zinc
electroplated) fixing materials and fasteners are not allowed.
References:
IS/IEC62305 – PROTECTION AGAINST LIGHTNING:
UP S – IN V ER T ER TY P E
1.0 General
1.1 Scope
Supply, install and commission RATED KVA / 230V (single phase) UPS systems with necessary batteries for
a battery back up time of 90 minutes. For lighting & general power applications.
1.4 Submissions
Full details of the systems, including technical specifications and shop drawing showing precise layout of
UPS and batteries, shall be provided to the Development Manager.
Once the warranty expires the Developer may at his discretion enter in to an annual maintenance
contract (AMC) or ask, the Specialist Agency to support the maintenance of the system on a per call basis
with the same commitment as in the case of AMC.
2.1 Conditions
The following details are the minimum requirements:
The UPS shall be fully covered on all the sides, and with front opening for servicing ventilation
system).
UPS shall have potential Free contacts corresponding to fault conditions I/P mains failure,
Inverter O/P failure, Battery low pre-alarm so that this information can be carried to the paging
system.
UPS shall have a LCD Panel for measuring various other parameters related to UPS operation.
Output of the both UPS's shall be paralleled so as to form a parallel redundant configuration.
2.2 Batteries
All batteries shall be sealed maintenance-free batteries of appropriate rating to provide 90 minutes back
up at full load.
3.0 Execution
3.1 Installation
The UPS System and batteries shall be installed as per the approved drawing.
3.2 Commissioning
The Development Manager shall witness the commissioning
The Contractor shall be responsible for the testing and satisfactory performance of the complete UPS
system which shall include as a minimum:
(a) Switch off all the output breakers that are connected to the load. Run the UPS in no load
condition at least for 15 minutes.
(b) Measure and confirm output voltage. Phase difference, frequency and all other specified
parameter are within the allowed range.
(c) Conduct the load test of the UPS system by connecting the UPS to a dummy load like water load
Contractor shall arrange for test facility.
d) Measure and confirm at full load, voltage, frequency, phase difference, Battery backup time,
battery charging current, DC ripple, parallel redundancy operation, and all other necessary
and/or specified parameters are within the approved range.
e) Once the result of the load test is satisfactory, and approval is received for connecting the power
to the electric circuit; connect the UPS output to the actual computer load.
f) Check for any malfunctioning with the computers and UPS system. Observe for 15 minutes.
g) Repeat step
3.3 Manuals
Two sets of all manuals for the systems, including instruction, administration and maintenance manuals,
shall be submitted to the Consultant / Developer.
Non-maintained emergency lighting luminaries with 2 high luminosity LEDs (average life time
1,00,000 h) to ensure 1 lux along the center of an escape route.
Screw terminals with high capacity : 4mm2 for mains and 2.5mm2 for remote control
1 dia. 20 cable entry at the top and 1 rectangular one at the back side.
E AR T HIN G
Scope of work
Supply and installation of all Earth Electrodes as enumerated in earthing schematic.
Supply installation of earthing conductors for the electrical works covered under this scope of work.
Supply and installation of Rigid PVC pipes up to the nearest shaft or cut in building or the cable trench in
the vicinity to enable laying of earthing strips by other agencies at a later date.
Earthing electrodes shall be designed as per the requirements of clause 17.2 of IS:3043. The number and
size of earth electrodes shall be calculated so that under fault conditions no electrode is loaded above its
maximum permissible current density. The resistance of earth electrodes shall not exceed one Ohm.
The number of earth electrodes shown in the drawing is indicative. The Contractor shall provide required
additional earth electrodes to contain the ohmic value at no extra cost.
Earthing electrodes of plate type shall be used. The choice of pipe or plate electrode shall be decided
according to the anticipated fault level of the network and local soil conditions.
All grounding electrodes shall be tested with earth meggers and grounding resistances are recorded.
Plate electrodes shall be made of copper plate of 3.15 mm thick and 60 x 60 cm size. The plate shall be
buried vertically in ground at a depth of not less than 2 meters to the top of the plate, the plate being
encased in salt and charcoal to a thickness of 15 cm all around. It is preferable to bury the electrode to a
Characteristics
1. Copper bonded Earth Rod at a depth of minimum 3 meters (3 rod per pit)
2. Ground Enhancing Material (GEM).
3. Earth Rod Clamps.
Copper bonded Steel Earth Rods shall have the UL certification, which calls for a minimum molecular
bonding of 250 microns. These Coppers bonded rods are provided with a Nickel bonding interface to
avoid galvanic corrosion.
Ground Enhancing Material:
Earth Enhancing Material shall be supplied in bags consists of Earth Enhancing chemical for good
conductivity.
Method of Installation:
One number or three numbers as per Bill of material, Copper bonded Earth Rod shall be placed in an Earth
Pit of 10-inch diameter. The earth pit has to be connected by means of Copper Earth Rod Clamp. The
whole setup is treated by Ground Enhancing Material (GEM).
Precautions
Earthing system shall be mechanically robust and the joints shall be capable of retaining low resistance,
even after passage of fault currents.
Joints shall be welded, bolted or double-riveted. All welded joints are painted with cold zinc galvanizing
paint. All the joints shall be mechanically and electrically, continuous and effective. Joints shall be
protected against corrosion.
On the completion of the entire installation, tests on the earth resistance of the electrodes shall be
conducted using an earth-testing Megger.
All meters, instruments and labour required for the tests shall be provided by the Contractor. The test
results shall be submitted in triplicate to the AE / Owner for approval. Tests shall be conducted in the
presence of AE / Owner.
Ground resistance test shall be conducted to verify impedance of the electrical ground systems. For sizes
of conductors of earthing refer to earthing schematic.
Luminaires
1.1 General
Luminaries shall be installed in an approved manner and shall be complete with incandescent lamps,
fluorescent tubes, discharge lamps and accessories necessary for their proper functioning and shall be in
accordance with the provisions indicated herein.
All discharge luminaries shall be power factor corrected to a minimum of 0.8 lagging. Lead lag circuits or
blocking Inductors shall be incorporated where indicated.
Supply of Luminaries
Luminaries shall be purchased from a reputable supplier and shall be manufactured in accordance with
relevant standards.
The catalogue numbers or trade designations for luminaries used in the schedule of equipment are
intended to indicate the required quality, style and performance of the luminaries. Where alternative
luminaries are offered all performance data shall be submitted to the Consultant / Developer for
approval. If requested, by the Consultant / Developer, a sample shall be submitted for approval.
2.1 General
All screws, battens, roses, trims, packing, etc., necessary for the proper fixing of luminaries shall be
provided by the Contractor as part of the works. Packing pieces of approved material shall be fitted where
required to level the luminaries and to prevent distortion.
Where painted surfaces are damaged, they shall be made good by painting to the same standard as the
original paintwork.
Where rod suspensions are indicated, rods shall be steel water pipe. Rods shall be gimbal mounted from
ceiling and lengths shall be adjusted so that the luminaries hang true.
End to end luminaries shall be correctly aligned using packing strips where necessary.
Plastic boxes attached to luminaries or cable protection shall not be used as part of the fixing method.
Where a PVC conduit enters a luminary, a screwed PVC adaptor with circular lock nuts shall be used to
secure the conduit to the luminary. Lock nuts are not required for luminaries with screwed conduit
entries.
Where indicated, luminaries shall be suspended level with electroplated welded link chains at each end.
Luminaries shall be securely fixed to structural members of the ceilings or walls, or fixed by hangers or
brackets, which are securely fixed to structural members.
The minimum size of fixing for luminaries, hangers, or brackets for various surfaces shall be as follows:
(a) Fixing to timber: steel wood screw No.10 x 25, round head, cadmium plated.
(c) Fixing to hollow blocks: M5 electro-galvanized, round head screws with spring loaded butterfly
toggles. Where a deep cast iron junction box is provided in the centre, M5 metal screws shall be
used with approved expanding fixings at each end.
All fixings shall be fitted with large diameter (minimum 3 mm screw dia.) cadmium plated washers under
the heads of each screw.
Recessed luminaries shall be fitted with flexible cords and 3 pin plugs. The flexible cord shall be PVC
insulated, 3 core with 1.5 mm 2 conductors, and shall comply with the relevant IS. It shall be of suitable
length not greater than 1500 mm.
A plug socket shall be located within 500 mm from the edge of the access aperture to allow the luminary
to be plugged-in prior to fixing.
Recessed luminaries installed in timber-framed ceiling shall be fixed to the ceiling members and noggins
using the proprietary fixings supplied by the luminary manufacturer, subject to the approval of the
Consultant / Developer.
Recessed luminaries using incandescent or discharge, lamps and installed in a confined space (e.g.
covered way, counter canopy, integrated ceiling or roof) shall be wired to a near-by junction box using
cable having insulation at least rated to 200 deg.C maximum operating temperature.
Recessed luminaries for suspended or modular ceilings shall be attached to suspended ceilings with
proprietary mounting brackets supplied by the luminary manufacturer.
Unless otherwise indicated, post-top luminaries shall be mounted on tapered steel lighting columns.
Unless otherwise indicated, lighting columns shall consist of proprietary brand steel poles, hot dipped
galvanized and suitable for base plate mounting on galvanized rag bolt assembly set in a concrete pad.
The poles shall be adequately drained and shall be fitted with an approved weatherproof lockable
enclosure to house the control gear and fuse(s), in the lower section of the pole, within 1000 mm of the
ground.
23 Conduits - MS GB / Bharath
The scope briefly shall include supply, erection, testing and commissioning of External Water
Supply Distribution Network , containing various requirements of piping, valves, supports,
specialities etc.
The water requirement for building shall be calculated as per Plumbing section of IS: SP: 7-2005.
The pipe shall be concealed and painted with anti-corrosive bituminous paint (as per IS:158)
wherever required as per requirement and direction of Engineer-in-charge /Client
The total water requirement shall be met with underground source by providing deep tube wells or
by any other nearby water source.
Construction of Borewells with adequate capacity of submersible pumps(Including complete set as
per requirement) shall be in scope of Work as per requirement and direction of Engineer-in-charge
/Client..
Water source shall be tested for potable water quality and suitable water treatment shall be
provided as per WHO standards.
The scope of the proposal includes Design, Engineering, Construction including supply of all
material, mechanical / electrical equipments i.e. pumps, motors, level switches, cables, MCC etc.,
Erection / Commissioning & maintenance of Water Treatment Plant (WTP) to treat the required
water per day.
The contractor shall have to maintain the plant for a period of 12 months including all the materials
etc. at their own cost after satisfactory commissioning of the plant. The contractor shall provide
training to the operators of the owner for a minimum period of three months during the
maintenance of the plant. The responsibility for any defect due to design, construction,
performance lies solely with the contractor.
The scope shall cover the following activities and services in respect of all the works of WTP:
Basic Engineering
Detailed design of all the civil structures,
Providing engineering drawings, data, Operation & Maintenance/ instruction manuals, as
built drawings and other information,
Compliance with statutory requirements and obtaining clearances from statutory
authorities, wherever required,
Finalisation of sub-vendors, manufacturing quality plans and Field quality plans,
Special tools and tackles, if any, required for maintenance of the manufactured items.
PUMPS
Suitable capacity of Drinking water Pumps along with drive motor (Vertical turbine wet pit
type) (as per requirement including all) to be provided at underground water tank.
UNDERGROUND TANKS
Earth pressure for all underground structures shall be calculated using coefficient of earth
pressure at rest or co-efficient of active earth pressure, whichever is applicable, depending
upon the structural configuration
Minimum 100 mm thick PCC of grade M-10 as per IS:456 shall be provided as mud mat
below the bottom slab / raft. The PCC shall extend 100 mm beyond the outer edge of the
structural concrete. A layer of bitumen paper or craft paper shall be provided over the
blinding layer (lean concrete) to destroy the bond between structural concrete and blinding
layer.
Water proofing cum plasticizer compound shall be mixed with the concrete.
For the design of substructure of pump houses, earth pressure at rest shall be considered.
Co-efficient of passive earth pressure shall be used only in design of shear keys for stability
against sliding.
The design of all liquid retaining structures shall be carried out by working stress method of
IS 3370 (All parts)
STP
Design, drawing, supply, erection, testing and commissioning of Sewage Treatment Plant as
per the Schematic, Flow Scheme, Specification consisting of :
Bar Screen Chamber ( Bucket Screen )
Equalisation Tank
FRP treatment plant comprising of pre-aeration in contact media, aeration treatment,
sedimentation and disinfection. System is equipped with settling and anaerobic filtration as
an integral part of the FRP module.
Semi Treated Effluent sump
Treated Effluent sump
Screen Filter
Diffusers
Note:
All works to be carried out to the relevant IS Specifications whether so mentioned in the
description of works or not.
Including all Electrical, mechanical and piping works complete in all respects. Rate quoted
shall also include for obtaining necessary approvals from the Pollution Control Board &
other statutory bodies as applicable, for trial run & commissioning of the plant with
performance Guarantee for 12 months from the date of commissioning for trouble free
performance. The Total plant is to be above ground with only Equalisation tank, Semi
Treated water tank & Final treated water tank located below ground level. Galvalume sheet
roof with pump room in masonry to be provided above ground.
The cost inclusive of all civil structure.
SCOPE OF WORK
Work under this section consists of furnishing all labor, materials, equipment and
appliances necessary and required to completely install drainage system as
required by the drawings, specified herein after and given in the schedule of
quantities.
Without restricting to the generality of the foregoing, the drainage system shall include
the following: -
These pipes shall conform to IS 458-1988. This shall be of class Non Pressure (NP)
2. The design and strength thickness and test requirements of pipes shall be as
per table 2. of IS 458.
Joints shall be of collar joint and the caulking space shall be filled with CM. 1:1
mixture of cement & sand. The caulking shall be employed on both the ends and
finished neatly outside the socket at an angle of 450. Wooden caulking tool shall
be used for forcing the mortar home into the collar.
All the joints shall be kept moist by means of wet gunny cloth to protect them from
quick drying. The joints shall be cured at least for seven days.
TESTING
A leakage test shall be conducted currently with the pressure test. Leak age is
defined as the quantity of water to be supplied into the newly laid pipe, or any
valve section thereof within 0,035 N/Sq.mm /0.35 Kgf/Sq.cm, of the specified
leakage test pressure after the air in the pipeline has been expelled and the pipe
has been filled with water (in case of test pressure is 10 Kgf/Sq.cm the leakage
test pressure will be 3.5 Kgf/Sq.cm.)
No pipe installation shall be accepted until the leakage is less than the number of
cu.cm/h as determined by the formula:
ND x (P)1/2
QL = -----------------
3.3
the pipeline
D = diameter in mm and
in Kg/Sq.cm
The leakage or quantity of water supplied during testing shall not exceed 0.2
lts/mm diameter of pipe per kilometer of length per day.
When pipes are laid under roads and payments subjected to heavy traffic loads
the trenches may be covered with plain cement concrete slabs of suitable
dimension, supported on edges to relieve the load on pipes to the adjoining
earth.
The Contractor shall at his own cost make good promptly, during the whole period that
the works are in hand, any settlement that may occur on the surfaces of roads, berms,
footpaths, gardens, open spaces, etc. whether public or private caused by trenches or
his other excavations and he shall be liable for any accidents caused thereby. He
shall also, at his own expense, repair and make good any damage done to the buildings
and other properties.
The term Grading, Grading Plan, Site Grading shall mean the following in singular and
collectively:
Surface dressing: Trimming of natural ground and / or excavated surface / filled up area to
remove vegetation and undulations not exceeding 150 mm deep shall be described as surface
dressing. Measured in sq Mts.
Surface Excavation: Excavation exceeding 1.5m width and 10 sq mts in plan but not exceeding
300 mm in depth.Measured in sq Mts.
Area Excavation: Excavation exceeding 1.5m width and 10 sq mts in plan and exceeding 300 mm
in depth. Measured in Cu M.
Loose soil: Generally any soil which yeilds to ordinary application of, shovels
Soft rock: Rocks which can be split by picks and crowbars. This will include
laterite.
Hard rock: rock that is to be displaced by wedging, chiselling (taapkari). Hard rock on site shall
not be blasted.
Measurement of Cut: Where the ground is not uniform, levels shall be taken before the
commencement of works and after completion of works and the quantity of cutting calculated
from this measurement.
Measurement of Fill: Where the ground is not uniform, levels shall be taken before the
commencement of works. Works shall be measured during compaction of fills at suitable
intervals, and the final measurement taken after achieving and after completion of neat surface
dressing.
The following works shall not be measured seperately and allowance for the same shall be
deemed to have been made in the description of the main item.
1. Setting out
2. Profiles
3. Site clearance
4. Informal Battering or benching of excavation
5. Pumping out water from excavated areas and sub soil.
6. Slinging or supporting pipes and cables encountered during work.
This specification includes furnishing all the materials, equipment and labour necessary for the
excavation, fumigation, pest control, pre and post and emergent weedicide application,
placement of soil mix, planting of plant materials, irrigation, protection, maintenance and
guarantee and all related items to complete the landscape work as shown in the drawings and
specified herein for plantation of trees, shrubs, groundcovers and lawns.
The site shall be cleared of all debris and construction materials. Existing structures, planters,
fences etc. shall not be damaged. If damaged, they should be repaired.
Excavation upto 2’ depth for shrubs, groundcover and lawn; and upto 1m depth for
trees, shall be carried out by contractor with his own labourers and tools necessary for
the operation. The contractor shall have to carry away and dump the rejected excavated
material to a place shown by the Engineer in charge and the excavated area shall be
filled with soil mixture as specified.
(c) Laying of the drainage layer (below soil surface):
If required, in absence of natural soil below 2’ depth, drainage will be provided as
described herein. Perforated PVC pipes 6” (150mm) in diameter cut into two half rounds
shall be laid as indicated in the drawing. These shall be laid to provide unobstructed
flow of water towards the drainage outlets at sub surface levels. A 3” (75mm) thick layer
of cinder (burnt bricks) shall be laid in between these pipes as draining bed. The soil mix
as specified herein shall be spread over this layer.
Conventional methods of using FYM in the soil mix, in the pre and post planting stage are
avoided since it heats up the soil, increases methane production, thus affecting plant roots,
it also increases weed, pest and disease incidence. This also reduces the cost of
maintenance.
The soil used shall be properly screened into coarse texture and fine texture to suit the
type of plant (coarser for trees and shrubs and finer for lawns) containing adequate amount
of humus, friable and free from perennial weeds, stones and pebbles, foreign materials,
plastic bags, roots, half decayed leaves, debris etc. It shall be fine textured soil that breaks
into clods and lumps when crushed. All the soil should be of the same structure and
composition throughout. The soil shall not be delivered, handled or placed in a muddy
condition.
Manures used to upgrade and increase efficiency and richness of soil shall be sterilized (if
possible) free of smell, insect eggs and larvae, weeds, and harmless. Amrut compost is
recommended, since it contains cocopeat, sterilized and sun dried FYM, Neem, and
Trichoderma (N fixing) bacteria.
Contractor shall submit soil test reports of the soil, specifying pH values, N, P, K values,
micronutrient content, soil structure and texture, so that additives can be determined
accordingly.
Organic fertilizers like ValueMeal (5:10:5, N, P, K) should be top dressed, at the rate of half
kg/ cum, at every ten days interval during monsoon and fifteen days interval otherwise.
Groundnut cake or Neem oil cake can be used alternatively bi-monthly at the rate of half
kg/ cum.
For lawns, in addition to the organic fertilizer, Sufala (15:15:15, N, P, K) should be top
dressed at every fifteen days interval at the rate of half kg/ cum.
Avoid using inorganic fertilizers like urea etc. as they are harmful to the plants in the long
run.
Tonics like Plantakola and Bahar at the rate of 0.01% should be sprayed at every fifteen days
interval alternately.
Adjuvants like APSA-80 (0.01%) should be mixed with any of the pesticides or fungicides
mentioned above and used as foliar sprays to increase their durability and efficiency.
Organic insecticides like Neemark, Go-Neem, Vermiwash, Humus Acid should be used as
post emergent sprays to control insects. Inorganic insecticides like Monocrotophos (Phoskil)
should be used alternating with organic insecticides. Bactericides like Streptocycline,
fungicides like Blitox should be used on the foliage as post emergent sprays.
Care should be taken to ensure that no single formulation should be used continuously
to avoid resistance building.
(G) PLANTING
All plants shall be well formed, healthy, transplanted or pot grown with vigorous sound
roots, true to type. Plants which do not meet the specifications shall be rejected by the
Horticulturist/ Landscape Architect. No substitutions shall be made without the Landscape
Architect’s approval in writing. Detailed specifications for trees/ shrubs/ creepers/ lawn
discussed below.
(1)Excavation
1. The pits of 1x1x1 mt are to be dug two to three weeks prior to planting. The pit should
be kept exposed to sunlight for these two to three weeks. Soil mix as specified above
should then be filled into the pit. For longer and better favourable conditions it is
suggested to plant at the beginning of monsoon. For proper and strong growth of the
plant pruning should be done at a regular interval at an early stage of the plant growth.
Manuring is necessary and should be done as per suggestions. Trees need generous
watering and should be done one time daily.
2. Trees shall be supplied in containers or the trees shall be burled. In the latter case, trees
shall be dug up with a ball of soil around the roots and the soil ball wrapped and tied in
polythene or hassian sacking. The trees shall be in good condition with no broken
branches or bark injury. The foliage shall be adequate and shall show no signs of wilting.
The roots shall be growing in a thick unbroken tangle.
(3) Stakes
Each tree shall be secured to a stout straight stake of average diameter of 2”. These stakes
of soft wood or bamboo should have a clear height of 6’-0” above the ground and 2’-0”
below ground. They shall be driven into the hole before the tree is planted and the trees
shall be secured to them immediately below the bottom branch. The second tie is to be
staked as practicable.
(1) Excavation
Since soil mix is loose and friable to 2’ depth, direct planting to be done with diameter of pit
being slightly larger than the root ball.
Shrubs/ groundcovers provided shall be in accordance with the specifications in the plant
list. They shall be in good condition with no broken branches. The foliage shall be healthy
(1) Excavation
Since soil mix is loose and friable to 2’ depth, direct turfing to be done
The cultivation of lawn shall consist of excavation of area and refilling in with the soil
mixture as specified earlier. The soil mixture shall be laid to proper slopes for surface
drainage. The soil shall be properly raked and watered thoroughly before receiving the
strips of turf of specified grass variety (minimum 1’ wide).
(3) The contractor shall be required to do proper top dressing, rolling and periodical hand
cutting or machine mowing as per consultants instructions during maintenance period in
order to bring and maintain the lawn in perfect green thick and springy carpet of turf.
(H) WORKMANSHIP
(A) Trees
(a) Tree pits: After making out the positions for planting the trees, pits shall be made
minimum 1 cum or at least 150mm wider and deeper than the space the roots will
occupy when they are spread out in their natural positions.
(b) Handling: The container of the trees shall be removed before planting the trees. The
tree shall be handled by the soil ball. The trunk of the tree shall not be used as a handle
as this may injure the tree by breaking of fragile roots or loosening the whole root
system, while planting a small hole shall be made in the centre of the pit slightly larger
than the ball of earth holding the roots.
(c) Placing/ Protection: If the plant is tall and likely to sway by the wind, it shall be
supported by a stick to which it is tied. For a young tree under 2.5” to 3” dia., support of
2” x 3” wooden stake 4’ long shall be used. The end of the stake shall go into the
ground. The tree shall be tied to the stake with coir tie (sutli). The stakes and ties shall
be removed after they have done their job between one year to three years.
(d) Planting: The pits shall now be filled with the prepared mixture of manure and earth,
working the soil between the roots. The soil shall be pressed down firmly by treading on
it, leaving a shallow depression all around for watering. When the tree has lawn around
it, the surface of the lawn shall have a slight slope around the tree.
Technical Specification Page 383
(e) Watering: The tree shall be watered heavily soon after planting in the absence of rain,
the trees shall be watered every three days for smaller trees and once a week for larger
trees. The interval between watering shall gradually be increased to twice a month,
once in a month to once in six months in the case of large trees only.
(D) Lawns
Ground preparation: Thorough and adequate ground preparation shall be carried out as
mentioned earlier. In absence of rain, the surface shall be watered heavily. Any weeds
that come up shall be removed thoroughly. As soon as the surface is dry enough, the
levels shall be rechecked, slight surface settling that occurs shall be filled in before grass
planting is commenced for turfing. Turf (minimum 1’ wide) shall be spread on the
ground without any gaps. Any cavities shall be filled with fine soil. The entire area shall
be watered liberally. Any soil settling/ turf settling should be corrected by removing the
turf at this stage and refilling with soil mix, and re-turfing. After six months, all levels
should be resurfaced to required grade by top dressing the turf with soil mix, and
washing it down.
Growing and shaping: When the growth of the grass has progressed sufficiently to
require mowing, hand weeding shall be done. After each mowing, sieved soil mix shall
be spread, watered and smoothed down. Planks of wood shall be used for this purpose.
(I) INSPECTION
The site will be inspected by the Architects, Clients, Landscape Architect and Horticulturist
from time to time at different stages of work. All the stages of work will be under
continuous supervision and observation by the horticultural supervisors appointed by the
Landscape Architect. Security measures will have to be provided by the Clients during the
entire period of planting and maintenance.
All the trees/ shrubs/ creepers will have free maintenance period of 6 months, during which
the contractor is supposed to maintain all these items in all respects such as watering,
pruning, spraying of pesticides, fungicides, insecticides, adding fertilisers, removing of
weeds etc. The maintenance of the horticultural work includes employment of required
malis and others continuously for period as per contract agreement.
All plant materials furnished or relocated shall be warranted for a period of six months from
the date of pre-maintenance inspection against defective, unsound, or diseased condition
that may appear. Any damaged plant material shall be promptly replaced with new material
of the same size and condition and installed according to the specifications. The expense of
replacement shall be borne by the contractor. The contractor shall not be held liable for the
loss of plants due to accidents, severe storms or inclement weather or theft.
Final acceptance shall be based upon a visual inspection operation by the Architect/ Landscape
Architect at the completion of the maintenance period.
LIFT
Scope the section death with technical requirement of lift installation. Its components safety devices
various type of controls and methods of operation will be guided by the requirements in individual case
such as nature of building, usage occupancy, traffic pattern etc. and has to be decided in individual cases.
2.7. Bearing :
Bearing shall be either of the anti-friction metal sleave type with oil reservoirs, self,
lubricant, oil, gauges, capped filler opening and drains of the ball roller type subject to
oil flood lubrication or grease lubrication.
Grease lubricated bearing shall have grease gun connection and drains plugs. The
bearing and lubricant reservoirs shall be dust tight and shall incorporate effective seals
to prevent leakage. The outer end of the bearing shall be closed with a removable oil
tight plate. Thrust bearing shall be of the ball or roller type and shall have two sets of
balls arranged to minimize backlash for efficient working.
A control for a driving machine induction motor which is arranged to run at a single speed.
Incoming mains as power is first rectified to dc and then inverted to provide controlled ac
current to the elevator drive. Precision monitoring of motor speed and car direction position
and load enable the pulse width of the ac power supplied to the motor to be adjusted to ensure
that elevator speed is maintained very accurately to an ideal profile.
4.1. Installation in machine room- lift machine room to accommodate the drive machinery,
controller, etc., shall as far as possible be located on top of the lift shaft. The layout of
equipment there should be such as to allow free movement of maintenance personnel inside.
Machine room shall not be used for storage purpose.
4.1.1 Verification of machine room: - machine room shall be provided with natural air and
mechanical ventilation to avoid over healing of the electrical equipments and to ensure proper
operation of the controller. Entry of dust etc shall also be suitable prevented.
4.1.2 Vibration isolation- vibration and isolation arrangement shall be provided to prevent
transmission of vibration to the building and structure.
4.2 General illumination of lift well. : Suitable light points shall be provided in the lift well at
a spacing of not more than 10meters in suitable light at the ground floor. All the points should
be group controlled from the M/C room. The wiring shall be carried out in surface conduit as
per CPWD General Specification. One socket outlet shall be provided in the shaft for use by
maintenance personnel at a level slightly above the ground floor landing.
Guide rails shall be in accordance with clause 3 of IS14665(part 4-sec.2)2000. Only machined
guide rails shall be permitted for cars for passengers and hospital lifts. Formed sheet metal rails
The guide rails shall be supported by brackets secured to the hoistway frame at each floor. The
rails shall be securely fastened to the brackets or other supports by approved heavy rail clamps.
Ali necessary guide rails packing or additional supports shall be provided to prevent guide rail
deflection and stresses exceeding the prescribed limits. The stresses on the guide rail due to the
horizontal forces imposed on it during loading. Unloading and running calculated without
impact. Shall not exceed 1100 kg/sq cm based upon the class fastenings and supports shall be
capable of resisting the horizontal forces mentioned above. With the total deflection at the
point of support not in exceed of 3mm.
Guide rails shall extend from pit floor to the underside of concrete slabs or grafing at top of the
lift well. They shall be erected in plumb and parallel with a maximum deviation of 3mm. all
shimming required shall be of metal securely held in place. Jointing plates shall be so located as
not to interfere with supporting clamps and brackets. The bolts shall be used with spring lock
washers. The guide rail anchorage at pit floor must be made without puncturing the water
proofing. The expansion joints in the guide rails shall be so designed as to avoid jerks in the left
car. Machined guide rails shall be maintained till the commissioning of the installation. Before
the car is a placed in operation, the preventive coaling shall be removed and the guide rails
thoroughly cleaned and smoothened.
The car frame shall be in accordance with clause -4 of IS 14665(part4-sec3):2001 made of sheet
steel of rigid construction withstand without permanent deformation the operation of safety
gear. The car shall be so mounted on that vibration and noise transmitted to the passengers
inside is minimized.
6.2.2 A load place along with overload alarm, giving the rated load and permissible maximum
number of passenger should be fitted in each lift car in a conspicuous position.
The car shall be enclosed on all sides by a metallic enclosure. The enclosure including the door
shall withstand deformation a thrust of 35kg applied normally at any point and as per IS
14665(per-4sec 3)-2001 ventilation specified shall be as per IS 14665(per-4sec3)2001.
6.3.1 Stretcher guards/ trolley guards made of PVC / rubber extrusion housed in a stainless
steel beading shall be fitted at suitable level (s) rear/side panels for bed lifts / goods lifts.
6.3.2 Lift car door shall have a fire resistance ration of one hour.
6.3.3 Grounding switch (es) at ground floor level shall be provided on all the lifts to enable the
fire service to ground the lifts.
The roof of the car shall be solid type capable of supporting a weight of at least 140 kg and as
per IS 14665(Part-4 SEC3)2001
Car entrance shall be provided with metal thresholds having a grooved surface. Thresholds for
lifts having horizontally sliding car doors or gates shall have machined or extruded guide
grooves.
The toe guard apron of gauge not less than 1.6 mm sheet may be provided extending at least
15mm beyond entrance jambs at each side. The guards shall have a straight vertical face
6.7 Clearance
The clearance between the top of the car and the soffit of the lift shall roof. Bottom of the car
and the pit floor, the buffers etc. and the clearance between the car and the lift well, between
the car and the landing sill, between two lift cars in the same shaft etc. shall be provided as per
IS 14665(Part 1.2&4)and relevant lift rules mentioned in appendix-1.
An apron shall be fitted to the car platform such that no dangerous gap exists at any time when
the land door is opening. Thresholds and sill plates shall be provided at the landings also. The
distance between landing sill and the sill on car platform shall not be more than 30mm.
6.9.1 Though Para 8.4.3 of IS 14665 (part2/sec: 1):2000 recommends for provision of either
and emergency signal or a telephone inside the car but as a general experience. It is seen that
over a period of time these devices become inoperative due to one reasons or the other.
Therefore, in order to have at least one device of communication functioning at all the times.
As an alternative arrangement, provision of both i.e. telephone with minimum two connections
– one at the operator’s room and other at guard room and the emergency signal with re-
chargeable batteries as source of supply shall be made in the lift cars.
6.9.2. The device used for emergency signals should incorporate a feature that gives immediate
feedback to the car passengers that the device has worked properly and the signal has been
passed on to the intended agency. This shall be achieved by pressing of button from control
room which shall give audio signal to the passengers in the car.
This shall include suitable secondary battery with trickle/ boost charge arrangement and
invertors power pack with necessary contactors for supplying the light fixtures in the lift car.
The same battery shall also feed the alarm bell and communication equipment.
Inside the lift car, the lift supplier shall also provide a stainless steel metallic plate indicating the
rated load and detailed instructions for the passengers. This shall be mounted at a suitable
place.
The side, rear facia panel shall be of scratch free stainless steel sheet. The flooring shall be with
3mm thick PVC tiles for passenger lifts and chequered aluminium sheet for goods lifts and
goods –cum- passenger lifts. The false ceiling in the lift car shall be crafted from mild steel
power coated to suitable colour with CFL lamps and fan diffuse (s)in different colour.
The car operating panel shall be of metal. Flush mounted and duly finished to match the car
interior décor and shall contain all the devices as may be specified depending upon the type of
operation required. In addition separate illuminated panel for indicating the floor and direction
may be provided on the top or the door way. All switches shall be fade proof and the devices
shall be of suitable quality.
Each device and its operating position shall be legible fade proof and marked.
7.1.1 The car door shall be hung from the top M.S fabricated and means shall be provided to
prevent the door from jumping off the track. The doors shall be provided with two point
suspension sheave type hangers suitable for the type of door operation specified. The hungers
shall be securely fastened on bearings mounted on a malleable iron or steel bracket.
Arrangement shall be provided for vertical and lateral adjustment of car doors. The sheaves
shall move on a M.S fabricated track so shaped as to permit free movement of sheaves with
regard vertical adjustment of sheave bracket or housing.
The car door shall be centre opening horizontal sliding stainless steel scratch proof(moon rock
finish) for office. Residential and goods lift applications whereas telescopic horizontal sliding
stainless scratch proof surface(moon rock finish) for hospitals.
7.1.2 A potential cause of accidents could be the attempts made to open the landing door of
lower floor in case the car stops away from floor level due to power failure. Since the car door
can be opened in case of power failure so as to improve the ventilation and avoid
claustrophobic situation etc. as outlined in IS 14665(part2/sec1):2000para 10.9.1 there is a
tendency among trapped passengers to make attempts to open any accessible landing door
which can be opened by a electromechanical latch in the landing doors as the lock is accessible
through open car doors. This attempt in panic may result in accidental fall in to the lift pit. In
order to ensure that the trapped passenger do not attempt opening the landing door, the
electromechanical latch should be so designed that it is inaccessible or invisible to the
passengers in the car.
7.2.1 wherever lift is required as per by- laws, provision of at least one lift shall be made for the
wheel chair user with the following cage dimensions of lift recommended for passenger lift of
13 persons capacity by Bureau of Indian standards.
7.2.2 A hand rail not less than 600mm long at 900mm above floor level shall be fixed adjacent
to the control panel.
7.2.3 The time of an automatically closing door should be minimum 5 seconds and the closing
speed should not exceed 0.25 m/sec. The interior of the cage shall be provided with a device
that audible indicate the floor the cage has reached and indicate that the door of the cage for
entrance/exit I either open or closed.
8. Landing doors
Each landing door shall be complete with locks. Headers, skill frames rims hanger supports with
cover plates etc. the finished work shall be strong, rigid and neat in appearance plain surfaces
shall be smooth and free from warp or buckle. Moulded surfaces shall be clean out,straight and
true. Fastenings shall be concealed from the face side of the material. Steel sills shall be
provided with a suitable noising of approximately 25mm depth on the shaft side.
Car landings
All the lift car landings shall be well lit to an illumination level of 150 lux and shall be free from
obstructions. The control for landing lights and the sign lights shall be temper proof. Wherever
standby power supply is available, these lights shall be connected to standby circuits also.
For the purpose of identification, the lift number should be displayed outside the
landing door, inside the car and in the machine room. This numbering may be used as reference
for the purpose of routine/ preventive maintenance, for operating from machine rooms and
reporting of any incidental etc.
Instructions
It is seen generally, that though the instruction on DO’s and Don’ts, as per provision of the
relevant. IS, are displayed in lift cars but the same are either displayed in inconspicuous
location. Or are very small in size or are in one language only. To make these instructions serve
the intended purpose, and not a mare compliance of relevant IS clause. That these instructions
should be displayed at a conspicuous location with larger and understandable script and should
be written in Hindi, English and regional language (where official regional language is notified).
Leveling
All lift (s) shall be incorporated with suitable floor leveling devices. In case of lifts automatic
power operated doors and with A.C VVVF controller a separate level device for automatic
leveling with leveling accuracy of ±5mm shall be incorporated.
The counter weight for lift cars shall be in accordance with clause 6 of IS14665 (part4/sec-
3)2001 and shall be designed to balance the weight of empty lift car plus approximately
50percent of the rated load. If shall consist of cast sections firmly secured in relative movement
by at least two numbers steel tie rods having lock nuts/split pins at each end and passing
through each section and housed in a rigid steel frame work. Cracked and broken sub weights
shall not be accepted.
Guards of wire metal/mesh shall be provided in the lift pit to a suitable height above the pit
floor to eliminate the possibility of injuries to the maintenance personnel.
Two numbers of guide shoes at the top and two numbers at the bottom shall be provided on
the lift car and counter- weight.
a. For speed upto 1.5 mps sliding guide shoes shall be used. Sliding guided shoes for car
shall be always flexible and for counterweight solid guide shoes can be used up to
1.0mps.
b. for speeds more than 1.5 mps roller guide shoes shall be used for car and counter
weight.
The car shall be provided with solid or spring loaded swiveling guide shoes with renewable
liners. Where the lift car speeds are upto and including 1MPS. The cars with speeds beyond
1MPS shall be provided with spring loaded guided shoes with renewable liners or the guide
shoes shall be of roller type.
Each roller shall be of an approved type consisting of rollers assembled on a substantial metal
base and mounted as to proved continuous contact of all rollers with the corresponding guide
rail surfaces under all conditions of load and operation. The rollers shall run on the three
finished guide rail surfaces and shall operate quietly.
Guide shoes shall be provided with adjustable mountings and shall be rigidly secured in
accurate alignment at the top and bottom on each side of the car sling and counter weight
frame construction. When oil buffers attached to the bottom of counter weight are used,
Additional guide shoe shall be provided on each side of the buffer frame. The design of guide
and car safety device shall be coordinated so as to ensure the provision and installation of
equipment with clearance specified in clause 5.7of this chapter.
Round strand steel wires ropes made from steel wire ropes having a tensile strength not less
than 12.5 tonnes.cm2 and of good flexibility shall be used for lift. Lubrications between the
strands shall be achieved by providing impregnated hemp core. The lift ropes shall conform to
IS 14665(part-4/sec-8): 2001 and the following factor of safety shall be adhered to. The
minimum diameter of rope for cars and counter weight of passenger and goods lift shall be
8mm.
The ends of lift ropes shall be properly secured to the and counter weight hitch plates as the
case may be with adjustable rope shackles having individual tapers babbit sockets,or any other
suitable arrangement. Each lift rope shackle shall be fitted with a suitable shackle spring, seat
washer, shackle nut & lock & shackle nut split pin.
Where lift ropes run round a sheave or sheaves on the car and for counterweight of geared/
gearless machine suitable guards shall be provided to prevent injury to maintenance personnel.
Every lift installation shall necessarily be provided with the following safety features.
12.1 The Safety gear shall be provided in accordance with IS 14665(part-4/sec.4)2001,each type
of car safety shall be actuated by a speed governor.
12.2 Governor – the car safety shall be operated by speed governor located overhead and
driven by governor rope suitable connected to the car and mounted on its own pulleys. The
rope shall be maintained in tension by means of weighted or spring loaded tension sheaves
located in the pit. Governor shall be provided for lifts with a travel of more than 5.5 meters. The
governor rope shall be not less than 6mm in dial and shall be made of steel or phosforbroze.
These shall be in accordance with IS 14665 (part4/sec-4):2001. Governor for car safety gears
shall be adjusted to actuate the safety gear at the following speeds.
a. For rated speeds upto 1m/s maximum governor tripping speed shall be either 140
percent of rated speed or 0.88m/s. whichever is higher. For rated speed above 1m/s maximum
governor tripping speed shall be 115percent of the rated speed plus 0.25m/s.
12.2.1 The governor shall be of “v” groove wheel design and only wheel is stopped to actuate
the car safety upon a pre- determined over speed downward without damaging the rope.
12.3 The governor, rope and sheave shall be so located so as to minimize danger of
accidental injury to the equipment.
12.3.1. The governor sheave and tension sheave shall be according to clause 2.4 and the sheave
bearing shall be according to clause 2.7of this chapter.
12.3.2. The requirements for field tests on car safety and governor and for drop tests to sliding
type car safeties shall be as specified in section IV of this specifications.
12.4.2 Terminal stopping devices located in shaft or in the car and operated by cams shall be
fitted with rollers having a rubber or other approved composition to provide silent operation
when actuated by the cam. When the lift car cross head is 60cm from the nearest obstruction
above it, no projection on the car shall strike any part of the overhead structure.
12.4.3 Lifts with speeds over 1.25 meters/ second shall have the normal terminal stopping
device located on the car or on the guide rails or in the machine room.
These shall be provided in accordance with the statutory requirements and standing practices.
When provided these shall arrange to stop the car automatically within top and bottom
clearances independently of the normal terminal switches but with the buffers operative. These
shall be in accordance with clause 8 of IS: 14665(part3/sec-1):2000.
Buffers shall be oil resistant rubber pad type for speeds upto 0.25 mps and spring/ oil type for
speeds up to 1.5 mps and only oil type for speed higher than 1.5mps.
Buffers shall be suitable for installation in the space available. Buffer anchorage at pit floors
shall be installed avoiding puncturing of water proofing.
Oil buffers of the car and counter weight shall be of the spring return type or of gravity type.
The partial compression of spring return oil buffers when the car is in level with terminal land
will not be acceptable. All buffers shall be tested at manufacturer’s works and a copy of the test
report shall be submitted. When the lift car rests on fully compressed buffers there shall be at
least 60cms clearance between the lowest point in its car frame and any obstruction in the pit
exclusive of buffers and their supports. Similarly when the lift car cross head is 60cm from the
nearest obstruction above it, no projection on the car shall strike any part of the overhead
structure.The contractor must indicate the name of buffer manufacturers. Buffer stroke and
certified maximum loads.
All the locks and contacts shall conform to IS 14665 (part 1/sec-6)2001 shall be positive and
pass the prescribed endurance and reliability test a recognized testing laboratory. They shall be
so located as to be inaccessible or invisible to the passengers in the car.
Besides these safety devices mentioned above, motor operated electro –mechanical brake
(clause 1.6) counter –weight guards (clause8.1) alarm bell, emergency door lock released
operating key and associated safety and other safety requirements shall also be included.
13.1.1 Single automatic push button with without attendant – the operating devices for this
operation shall incorporate in the car control panel, car buttons corresponding to the various
landing served and single landing button landing button at each landing, all electrically
connected to controller governing floor selection, direction of travel, Acceleration, retardation
etc.
This system shall be so arranged that when the car is not in use. On pressing a landing call
button the start automatically provided all the doors are closed during the movement of the car
and also when car stops at floor landing, other landing call buttons are in – cooperative or a
predetermined time. The pressing of a car button shall automatically start the car and send if to
the desired landing. In all the cases, the starting of the car is contingent on the establishment of
landing door and car inter – lock circuits. To indicate the availability or in use’ light shall be
placed in the landing call button panel. When light shall be OFF the passenger shall be able to
call the car. In case of manual operated door if the lift is standing at any landing with doors
open (when not in use.) the pressing of the landing call button shall ring a bell, fitted at the top
of car to attract the attention of the people soliciting their help for closing the lift door if any
one of the them happens to be near the lift.
Incase of power operated doors. The landing and car doors shall be arranged to open
automatically when the car is parked at landing after all the calls are served and the lift is
The lift shall be suitable for dual operation with or without attendant by the provision of key
operated transfer switch indicating attendant and automatic positions. During attendant
operations the landing call shall be disconnected from the control system and shall be
connected to an annunciate in the lift car. The attendant shall then operate the car to answer
the registered calls. This operation is recommended for single speed control lift for low rising
building having a single lift installation.
Automatic operation by means of one button in the car for each landing level and by up and
down buttons at the landings. Wherein all stops registered by the momentary actuation of the
car made as defined under non- selective automatic operation but where in the stops
registered by the momentary actuation of the landing buttons are made in the order in which
the landings are reached each direction of travel (irrespective of the sequence in which the
buttons have been actuated). With this type of operation, all up landing calls are answered
when the car is travelling in the up direction and all down land calls are answered when the car
is travelling in the down direction, except in the case of the uppermost or lowermost calls
which are answered as soon as they are reached in respective of the direction of travel of the
car.
The control system for this operation shall be similar to the one described under simplex
selective – collective operation except that in this system there shall be two lift cars in adjacent
wells. It shall be arranged to co- ordinate both cars for efficient service and prevent them from
answering the same calls by the provisions of only one set of landing call button fixtures. It shall
automatically assign each call to the car that will be in the best position to answer promptly.
The system shall be so arranged that when the cars are idle, normally one car will be parked at
the lower main landing with its doors closed or open and the other car shall be free car parked
with the doors closed or open to the landing where it answered its last call, shall be the one to
attend to the nearest call.
Each shall always respond to calls registered by its own car call buttons. When either car is
parked out of service for any reasons the other car shall function as single car (simplex)selective
A by – pass button (non-stop button) shall also be provided inside the car to enable the
attendant to by – pass any landing if the car is full or if otherwise so required.
The two lefts shall be arranged with or without attendant operation and shall function as
described using single car selective – collective operation. When the transfer switch is in the
attendant position the operation of the cars shall be identical with that described for automatic
operations except that:
a. closing of doors and starting of cars shall be initiated by the car buttons
only:
The pressing of an up down landing call shall illuminate appropriate direction indicator in the
car panel, which is to answer that call and if the doors open shall also sound buzzers as a signal
to the attendant. If both car ore parked at the lower landing the above signals shall be given to
the car which has been at the floor for longest time.
The call registered inside the car as well as the landings are answered in the sequence in
which the floors are reached irrespective of the sequence in which the buttons have been
pressed. Only one car will stop in response to any one landing call and will be the nearest car
travelling in the corresponding direction of the call. While this car is stopping at this landing, the
call will be automatically cancelled to prevent other cars stopping against the same call.
The group supervisory control continuously examines traffic conditions in the building and
automatically puts into operation the programme which can best cope with the demand at any
particular time. This is fully automatic and requires no supervision or attendant. To suit the
a. Up peak programme.
d. Night programme
a. Up peak programme:- The group supervisory control responds to the increasing influx of
passengers at the main landing in the morning hours. At the start of work, by automatically
switching on the up peak programme. The car are dispatched from the main landing
automatically ot a pre- determined interval after the previous dispatched car. The leaves first
signal is transferred instantaneously from the car dispatched to another car at the main landing.
The car answers the registered calls in the natural sequence of the floors and returns directly to
the main landing after last passenger has been discharged. However, a car starts its up travel
the moment it becomes fully loaded,without waiting for the dispatch interval to lapse.
b. Down peak programme.:- An intense traffic flow from the upper floors towards main landing
will automatically switch on the down peak programme. The cars when fully loaded at upper
floors travel directly to the main landing and after discharging the passenger. Immediately start
up to answer further down landing calls. The down landing call which has been by passed gets a
priority over other down calls which ensure equal service to all floors.
c. Up down interfloor programme. :- A steady traffic between main floor and upper floor and
between floor to floor causes automatic switching on of the interfloor programme. Specific cars
are assigned to answer specific calls by traffic analyzer so that the calls are handled most
efficiently. The cars are so well distributed that every call gets equal service with short waiting
intervals.
As soon as the number of calls drops to occasional calls only such as at night, the cars get
automatically parked in their assigned zones to give personalized service with minimum lift
travel. If no calls are registered for some time the motor generator sets are automatically
switched off.
In case where more than 3lifts installed in a bank, a better utilization of these lifts can be
obtained by two additional programmes to deal with heavier traffic in each direction in difficult
time. These are (I) heaver up programme (II) heaver (DOWN programme)
I. Heaver UP programme :- This shall require the cars to make more stops in the up direction,
necessitating more time for the up travel. For this purpose the automatic – traffic analyzer shall
dispatch cars from both terminal at automatically adjusted time intervals so that the cars are
equally spaced. Thus reducing passenger waiting interval (this programme caters for the traffic
which is likely to be in both directions but predominantly in the up direction e.g. immediately
after the morning peak or after lunch.
II. Heaver DOWN programme :- This shall require the cars to make more stops in the down
direction and the dispatch times shall be adjusted accordingly by the traffic analyzer.
If any of the cars in the group develops any defect it shall be automatically disconnected from
the group control until it is rectified.
In the event of failure of automatic dispatch system the lifts shall function by auxiliary means to
avoid any disruption of service.
The lifts shall be designed for attendant operation as described under single
(simplex) selective collective operation car except as follow.
b. Landing call be pass switch and car reversal switch and switches shall be effective and load
weighting devices shall be inoperative.
c. Call above signal shall be illuminated whenever a call is registered at a landing above the car
location indicating to attendant that car is to proceed upwards. When the highest call has been
answered the light shall be extinguished indicating to the attendant that when the car is started
it will proceed downward.
The movement of the car shall be eclectically controlled by means of a controller located in the
machine room.
The control circuit shall be designed to the type of lift specified for safety operation. It shall not
be possible to start the car unless all the car and landing doors are fully dosed and landing
doors locked. The circuit shall have and independent fuse protection for fault and over loads
and be arranged that for the stoppage of the car at specialized landing or for actuation of a
contactor by emergency switches or operation of safety gears the system shall not depend
upon the completion or maintenance of an electrical circuits to cut off power supply and apply
the breaks. This requirement is not applicable to dynamic breaking and speed control devices.
All wiring for external control circuits shall be brought to a terminal board with means of
identification of each wire. Metallic/ plastic identification lags shall invariably be provided all
connections of wires to terminal boards shall be adequately clamped or screwed.
On top of the lift car an emergency stop switch shall be provided for use by maintenance
personnel. Stop switch shall be provided in the machine room. Operation of these switches/
buttons shall cancel all the registered calls and landing calls for that particular lift.
For purpose of inspection and maintenance, maintenance switch shall be provided on top of
the car. The control circuitry shall be so arranged that in the event of the operation of this
switch.
a. The car speed shall be less than the rated speed not exceeding 0.85
metres/sec.
b. the car movement shall be possible only on the application of the continuous
pressure on a button. It shall be so mounted to prevent any inadvertent
operation.
Fireman switch with glass to break for access shall be provided at ground or main floor for all
the lifts. The operation of this switch shall isolate or cancel all calls to all the lifts and the lifts
will stop at the next nearest landing. If travelling upward. The doors will not open at this
landing and the lifts will start travelling to ground floor. If these were already travelling
down,they will go straight to ground floor direct without stopping enroute.
An inspector’s change over switch and set of test buttons shall be provided in the controller
operation of the inspector’s change over switch shall make both the car and landing buttons
inoperative and permit the lift to be worked in either direction from machine room for test
purpose by pressing corresponding test buttons in the controller. It shall not however interfere
with the emergency stop switches inside the car or on the top of the car.
It specified visual tell tale lights may be provided to monitor the conditions of faults in the
safety line of the lift for easier fault finding. These indicators will remain lit when safety circuits
are normal. One indicator shall be provided for each safety on the controller. If any indicators
fail to light up as the lift proceeds in its sequence of operation, there shall be visual indication of
the safety line open circuit and also its location for easier fault finding.
A. i. Control cables carrying DC and power cable carrying AC shall not be run in the same
conduit or metal duct and they shall be laid as per I.E rules.
III. in case of control cables also the harness shall be separate as far as feasible for separate
functions and laid separately in suitably dimensioned metal duct or in a separate conduit such
as the signaling, locking lamp indication and safeties. Control cables for different voltages in the
lift installation works should be laid as per IE rules.
B. At least 5percent with a minimum of 5 unconnected spare wires shall be available out of
all the lines to be provided the wiring harness from the midway junction box to the machine
room.
C. There shall be a master isolating switch fuse associated with the controller heavy duty
load break. Quick make quick break type. TP&N preferably interlocked with controller cabinet
door isolator handle shall have provision for external locking in off position.
All relay shall be suitable for lift service and shall incorporate adequate contact wipe for reliable
operation. Relay shall operate satisfactorily between 80 percent to 110 percent of their
voltage.Main motor contactors shall be suitable for A.C duty. Tenderer shall be required to
furnish full details of make, Type applicable standard. Voltage and current rating duty class,
type and routine tests done etc. on contactors and relays. Copies of type test certificates and
other lest certificates shall also be furnished by the successful tenderer. All cables shall be with
copper conductors and flame retardant or PVC insulated of appropriate size. The cables feeding
motor and in heavy current flow paths shall be so selected that the size matches the protecting
fuses and will not result in more than 2percent voltage drop from the main board in the
terminals of motor. Control cables shall not be less than 0.5 sq mm or equivalent of stranded.
Where installation of heavy gauge conduits present difficulties Short lengths of flexible conduits
will be permitted but effective electrical continued by earth bonding shall be ensured. Ferrules
shall be slipped at the ends of all cables as per standard control wiring practice. All terminal
blocks shall be suitable marked.
Trailing cable shall run from a junction box on the top of the car to a junction box located in the
shall near midpoint of travel and from those junction boxes conductors shall be run to the
various locations.
Trailing cables exceeding 30metres in length shall have steel supporting fillers and shall be
suspended directly by then without rubbing over other supports.
Cables less that 30metres in length shall have no metallic fillers and shall be suspended by
looping cables around supports of porcelain spools type or equivalent.
5 percent of the total capacity subject to a minimum of 5wires shall be available unutilized in
the trailing cable everywhere suitable distributed between various functions.
14.4.3 Earthing
Metal frames and all metal work of the lift controller frame etc. shall be earthed with double
earth leads taken to the earth bar. Looping shell be permitted if such routing is feasible all other
individual metallic work of components etc. shall be loop earthed.
14.5 Miscellaneous
Principle of segregation function wise shall be accepted as far as possible in the general
arrangement of components – All terminal blocks shall be of 650v grade.
The controller unit comprising of the main circuit breaker adjustable overload and phase
reversal and phase failure protection all the elements transformer, rectifier for D.C control
supply, inverter power pack, terminal blocks etc. shall be enclosed in an insect proof, sheet
steel floor or wall mounted cabinet with hinged doors at front or at both from and rear. Proper
warming boards and danger plates shall be provided on both sides of the controller casing.
Sheet steel used for controller cabinet shall not be less than 18 gauge and shall be properly
braced where necessary. Suitable gland plate shall be provided for cable entry. The battery for
the charge unit shall be suitably placed in the machine room.
All sheet steel work shall be painted with two coats of synthetic enamel paint of suitable shade
both inside and outside over two coats of zinc primer.
The lift rope compensation for the travel shall be provided for lift travels beyond 40m in all
cases.
The automatic rescue devices (ARD) meant for the purpose of bringing the lift car to the nearest
landing doors, are being used selectively and is generally restricted to commercial buildings
having heavy traffic. However, frequent power failures being the common phenomenon, the
provision of ARD shall be made in all the lifts in public buildings. The ARD shall have the
following specifications.
16.1. ARD should move the elevator to the nearest landing in case of power failure during
normal operation of elevator.
16.2. ARD should monitor the normal power supply in the main controller and shall activate
rescue operation within 10 seconds of normal power supply failure. It should bring the elevator
to the nearest floor at a slower speed than the normal run. While proceeding to the nearest
floor the elevator will detect the zone and stop. After the elevator has stopped, it automatically
opens the doors and parks with door open. After the operation is completed by the ARD the
elevator is automatically switched over to normal operation as soon as normal power supply
resumes.
16.3. In case the normal supply resumes during ARD in operation the elevator the elevator will
continue to run in ARD mode until it reaches the nearest landing and the doors are fully
opened. If normal power supply resumes when the elevator is at the landing, it will
automatically be switched to normal power operation.
16.4. All the lift safeties shall remain active during the ARD mode of operation.
16.5 The battery capacity should be adequate so as to operate the ARD at least seven times a
day provided the duration between usage is at least 30 minutes.
CONTENTS
1 INTENT OF SPECIFICATION
2 DESIGN PHILOSOPHY
4 SCOPE OF WORK
5 EQUIPMENT SPECIFICATIONS
2.0 PIPING
3.0 VALVES
15.1 PIPING
15.2 PUMPS
C ELECTRICAL WORKS
D
FIRE ETECTION SYSTEM
I
ADDRESSABLE FIRE DETECTION SYSTEM
II
CONVENTIONAL FIRE DETECTION & ALARM SYSTEM
E
PUBLIC ADDRESS SYSTEM
F FIRE EXTINGUISHERS
G SIGNAGE
6 MAKE OF EQUIPMENT
This specification is intended to cover design, residual, engineering, manufacture, test and
inspection at works, delivery to site properly packed for transportation, erection, testing,
commissioning, performance demonstration at site and handing over to purchaser of Fire
Protection System as indicated in the schedule of Requirement and scope of work and as
required for reliable and effective fire protection at “Lodha Belleza” Phase-III at Kukatpally,
Hyderabad.
1.1 This specification also includes complete earthwork, i.e. excavation and back filling for the entire
buried piping for hydrant and Sprinkler System.
1.2 The specification also includes the supply of erection and commissioning of spares as specified
and special tools and tackles.
1.3 This specification also makes it obligatory for the contractor for arranging and obtaining
necessary clearance / approval from all Local / statutory authorities.
1.4 It is not the intent to completely specify all the details of design and construction herein. Never
the less the equipment and installation shall confirm to high standard of engineering, design, and
workmanship in all respect and shall be capable of performing continuous satisfactory operation
and acceptable to the purchaser as well as to the various statutory authorities. In case of any
violation of the above contract, the purchaser reserves the right to change / reject / modify the
equipment / system during detail engineering.
1.5 Wherever material or article is specified or described by the name of particular brand,
manufacturer or vendor, the specific item mentioned shall be understood as established type
function and quality desired. Other manufacturer’s product will be considered provided
sufficient information is furnished to allow the purchaser to determine that the product
proposed is equivalent to those brands.
1.6 The entire system shall be designed and engineered by the Bidder based on the guidelines
furnished in the specification, various codes / standards. Bidder’s experience and also good
engineering practice. Items and quantities, which have been furnished in this specification, are
tentative and indicative only. During quoting, the Bidder shall vet the above Bill of Material and
may furnish additional items necessary for satisfactory operation of the system.
1.7 Supplies and services to be covered under this tender specification and the conditions thereof
are detailed in the subsequent sections of the specifications. In case of conflict among various
sections, subsections, documents, drawings the same shall be referred to purchaser whose
decision shall be final and binding to the Bidder. In all cases, the best advantages will go to the
purchaser.
1.8 Bidder to note that no technical deviation shall be permitted for the system
The Fire protection system for “Lodha Belleza” Phase-II at Kukatpally, Hyderabad. shall be
designed and installed as per National Building Code (NBC) of India 2005, Part- 4, Fire and life
safety and detailed specifications, also the recommendations made by the Andhra Pradesh State
Fire Services shall be followed.
Tower 7 have been classified, as Residential buildings, Group – A, Sub -division A4 (Above 60 m
in height).
Wet riser cum down comer system with multi risers for different pressures and heights.
Yard Hydrants
Electrically driven main pump multi out let type (two out lets) for Hydrant system.
(One outlet shall feed up to 14th floor at 120 MWC and other outlet shall feed from 15 th
onwards at 215MWC)
Electrically driven main pump multi out let type (two out lets) for Sprinkler system.
(One outlet shall feed up to 14th floor at 120 MWC and other outlet shall feed from 15 th
onwards at 215MWC)
Diesel Engine driven common standby pump multi out let type (two out lets) for both
systems. (One outlet shall feed up to 14th floor at 120 MWC and other outlet shall feed
from 15th onwards at 215MWC)
Electrically driven common Jockey pump multi out let type (two out lets) for both systems
(One outlet shall feed up to 14th floor at 120 MWC and other outlet shall feed from 15th
onwards at 215MWC)
Wet riser cum down comer for every 1000 sq.mts floor area for all buildings, there shall be
two risers one shall feed up to 14th floor at 120MWCand other shall feed from 15th floor
onwards. at 215MWC for each Block (Tower – 7)
Wet riser cum down comer for every 1000 sq.mts floor area for all buildings.
This is to reduce the constant pressure on the equipment and same is ease to operate. All
wet risers are interconnected with Terrace level water tank with Booster pump to increase
the pressure in case of emergency.
Yard Hydrants are at every 30m of periphery of the Building to protect the building from out
side. Yard hydrants are consisting with Single headed Hydrant valve fixed on the standpipe
and internal hydrants as required and all hydrant points consisting of 2 x 15 mts long fire
hoses, Branch pipe with Nozzle kept in the hose cabinet located next to the Hydrants.
2.9 INTERNAL HYDRANTS
Internal hydrants shall be fitted on the wet risers which shall locate in side the dedicated fire
shaft. Wet risers shall be minimum 150 mm dia in size and shall run up to terrace.
Internal hydrants shall be on each floor near landing of each staircase with single headed
hydrant valve for buildings which are less than 30 m in height and in case of buildings more
than 30 m in height hydrants valves shall be double out let type, 2x 15m long fire hoses.
Branch pipe with nozzle and a hose reel with 19 mm hose of 40 m long and nozzle. Internal
hydrants shall be installed inside the fire shaft and fire shaft shall be fitted with glass fronted
door.
THE TEST PRESSURE OF THE SPRINKLER SHALL BE EQAL TO 150% OF THE PUMP HEAD.
Sprinklers at one level (at ceiling) in the apartments and basement floor parking areas
Coverage per Sprinkler is 25 sq.mts and Sprinklers are Pendant / sidewall / upright (as
suitable at site) type with 79 deg. Temperature rating.
2.11 ADDRESSABLE FIRE DETECTION AND ALARM SYSTEM
Addressable Analogue type fire detection and alarm system shall be designed and installed as per
NFPA 72E / BS 5839 for complete building and for all blocks.
Dry chemical powder type fire extinguisher conforming to IS 2171 near car parking lots, main
switch board room, transformer, generator room, pump room, AHU rooms and lift machine
room.
Water expelled carbon-dioxide type fire extinguisher conforming to IS 940 located near each
staircase landing on every floor.
Carbon dioxide type fire extinguishers conforming to IS 2878, located in electrical panel
room, pump room, lift machine room and Kitchens.
Mechanical foam type fire extinguishers at HSD Yard, D.G. Rooms, and Firewater pump
house and near oil filled Transformers.
Unless specifically mentioned otherwise, all the applicable Codes and Standards published by the Bureau
of Indian Standards and their subsequent revision / BS Standards shall govern in respect of design,
workmanship, quality and properties of materials and method of testing; standards listed below shall be
applicable, in particular:
API 600 / BS 5163 : Specifications for Gun Metal gate, globe &
IS778/780/2906 check Valves for water supply.
Alarm System
IS-2175 : Detectors
4.1 INTRODUCTION
The scope of work includes complete design, Engineering with necessary design calculations, Fit – up details,
Supporting details, Manufacture / Fabrication, supply, Storing. Installation / erection, testing, commissioning the fire
hydrant system, Hose Reel system, Sprinkler system, Fire detection and alarm system, Public address system, first aid
fire extinguishers & Signage and quoted rates should includes complete earth works ie, excavation, back filling for the
buried pipes wherever applicable & with all necessary accessories as per Specifications and National Building Code of
India, at “Lodha Belleza” Phase-III at Kukatpally, Hyderabad.
The drawings enclosed herewith are for the general guidance to Bidder. The contractor shall upon the award of the
work, furnish detailed working drawings (as mentioned under Clause No. 4.1 above) necessary to carryout the work
at site with detail design calculation. These shall be submitted to the Employer/Architect for the approval and the
work shall be commenced only after the approval of drawing by the Employer/Architect.
The contractor shall obtain approval to the installation from the Andhra Pradesh State Fire Services. Successful
Bidder shall be responsible for preparation of documents / applications / drawings & hydraulic calculations and flow
up action at all stages, (Drawing / completion) arranging inspections, revisions / modifications for obtaining approval
from Andhra Pradesh State Fire Services within the overall completion period stipulated in the Tender. The
Contractor shall also make payment of all statutory payments like payment for Andhra Pradesh State Fire Services
approval etc. The quoted rates shall take care of such contingencies.
The contractor shall guarantee both the material and workmanship of first class quality corresponding to standard
engineering practice. Any defective materials/workmanship shall be rejected, the contractor has to rectify/ replace at
his own cost. Guarantee certificate of the materials supplied shall be handed over to the clients.
List of data/document/drawings to be submitted after the award of contract shall be indicated. The list shall
essentially contain the following:
The contractor shall be responsible for training of the Employer's personnel (minimum 6 rounds) in the
period of operation and maintenance of the system and conduct Fire drill. The rates quoted shall inclusive of
submitting 6 sets of the following documents (HARD COPIES) along with CDs (Soft copy) and the following,
Submission of the above documentation shall form a precondition for final acceptance of the plant and
installation and final payments.
EQUIPMENT SPECIFICATIONS
1.0 Without restricting to the generality of the foregoing, the fire hydrant system shall include the following:
1.1 Pumps, suction / delivery pipes, Valves, control panel and Instrumentation and pump set shall be in auto
operation.
1.2. M.S Class "C" (heavy grade) ring mains / riser main within the building and as well outside the building.
1.3 Landing valves, external hydrant valves, hose reels, fire duct shutters. Hose cabinets, fire brigade
connections and connections to pumps and appliances.
1.4 All materials shall be of the best quality and brand new, conforming to these specifications / standards and
subject to the approval of the Client / consultant.
1.5 Pipes shall be fixed in a manner as to provide easy accessibility for repair and maintenance and shall not
cause obstruction in shafts, passages etc.,
1.6 Pipes and fittings shall be fixed to walls and ceilings by suitable clamps at intervals specified. Only approved
types of anchor fasteners shall be used for RCC ceilings and walls.
1.7 Pipes and fittings shall be fixed truly vertical, horizontal or in slopes as required in a neat manner.
The pipes shall be supported by structural steel fabricated (like, channel / angle / flat / plate etc) supports with
suitable anchor fasteners / suspended thread rods not less than M16 in size.
1.8 Valves and other appurtenances shall be as located that they are easily accessible for operation, repairs and
maintenance. Valves / other equipments fitted above the false ceiling shall be provided with trap / access
doors.
1.9 Pipes for wet risers within the Building shall be M.S. tubes conforming to IS 1239 (heavy duty 'C' class) with
flanged/welded joints.
1.10 Fittings for steel pipes shall be malleable iron or forged iron fittings with screwed / welded joints.
1.11 Inter connection between sprinkler and hydrant pumps shall be carried out at discharge side with
Check valve and isolation valves.
1.12 All equipment should be confirmed with Technical data sheets as enclosed along with this tender.
In case Technical data sheet for any of ht equipment is not enclosed Bidder shall consider reputed make of
equipment, manufactured under good engineering practice for the same details to be furnished along with bid.
1.13 Construction of Fire water tanks, Fire water pump house, Puddle flanges at water tanks for suction /
delivery / test lines and core cutting / opening if required on floor is exempted by Fire protection contractor.
All pipes inside the building and where specified, outside the building shall be M.S. tubes conforming to IS:
1239 - heavy duty up to 150 mm dia. Fittings for pipes shall be as per IS: 1239, Part II (heavy grade) up to 150mm
dia,. and pipes 200mm dia & above shall be M.S. as per IS: 3589 with minimum 6 mm wall thick & fittings shall be
fabricated from pipes confirming to IS 3589.
Pipes shall be carefully laid to the alignment, levels and gradients shown on the plan and sections and great care shall
be taken to prevent any sand, earth or other matter from entering the pipes during laying. Pipes shall be kept
thoroughly clean during the course of laying. The ends of pipes shall be blocked with wooden plugs wedged home, at
the end of each days work to prevent dirt and rodents, insects etc., entering the pipe.
Pipes up to 50mm dia, tapered screwed / Socket welded / Butt welded type jointing shall be adopted, while for pipes
above 50mm dia welded or flanged connections shall be used. Flanged joints shall be made with 3 mm thick
insertion rubber washer / Gaskets. All boltholes in flanges shall be drilled & making hole by using gas cutting is not
acceptable. The drilling of each flange shall be in accordance with relevant Bureau of Indian Standards.
Flanged joints shall be used for connections to vessel equipment, flanged valves and also on suitable straight lengths
of pipeline at strategic points to facilitate erection and subsequent maintenance work.
The Bolts /Nuts / Washers used in the system shall be Galvanised as per IS 1367 and suitable length & not more
than 15mm beyond the Nut.
All pipes above ground and in exposed locations shall be painted with two coats of Zincrich primer for G.I
pipes and etching primer for M.S. pipes and two or more coats of synthetic enamel paint of approved shade with
minimum thickness if 75 microns. The pipes should be initially brushed to remove all foreign matter before applying
paint / primer.
The pipes (buried) should be initially brushed to remove all foreign matter and apply the primer over the
pipe. Primer is allowed to dry until the solvent evaporates and surface becomes tacky. The tape 4mm thick and
150/250mm wide shall then be wound in a spiral fashion and bonded completely to pipe by thermo fusion process.
The overlap is to be maintained at 15mm.
2.2.1 Excavation for pipelines shall be in open trenches to line and grade or as required at site including disposal
outside of site at approved dumping yard with the prior approval of concerned authorities. Pipelines shall be buried
to a minimum depth of 1M (top of the pipe) from the finished ground level.
2.2.2 The contractor shall support all trenches or adjoining structures with adequate timber supports wherever
required.
Contractor shall provide suitable PCC blocks of suitable dimensions at Change – in – direction and regular intervals of
6 meters to support the pipes. Minimum Size of Blocks shall be 600mmx600mmx450mm.
Supports for above ground pipes of 65 mm dia and above shall be fabricated by structural steel of suitable sections
with suitable fasteners. The spacing of supports shall be 3mts minimum and painted two coats of enamel paint of
approved color over a coat of primer.
Suitable type hangers shall support pipes below 50 mm dia with clamps, anchor fasteners and suspended rods etc.
3.0 VALVES
Butterfly valves shall be as per BS 5155 & provided for pipes 50mm dia and above on down stream (delivery side) of
the pumps. The valves shall be CI /C.S construction (as per the BOQ), seat shall be black nitrile rubber with insitu
moulding. The valves shall be PN 30 rating for high pressure side and PN 20 rating for Low pressure side PN 16 rating
for terrace .
Gate valves shall be as per IS: 14846 / 780, with C.I. body and bronze / brass internal parts and shall be used on
suction side of the pumps. Valve shall be flanged end type, PN 10 with rising Spindle type with C.I hand wheel etc.
Non – return valves shall be reflux swinging disc OR dual plate type The The valves shall be PN 30 rating for high
pressure side and PN 20 rating for Low pressure side, PN 16 rating for low pressure side as per the schematic drawing
with C.I. body and bronze / brass internals as per Technical data sheet enclosed and as per IS: 5312.
External (yard) hydrant valves shall be single headed as per IS: 5290 (Type A). The valves should be complete with
hand wheels, quick coupling connections, springs and blank caps. The hydrants shall be fixed to stand posts of 80mm
dia for single headed hydrants at 1.0M from ground level. External hydrant valves shall be consisting with 2 nos. fire
Hoses of 15m long 63 mm dia, One No. Gun metal Branch pipe with Nozzle housed in the M.S cabinet and cabinet
shall be mounted (next to stand post) on free standing support fabricated by suitable structural steel / pipe of not less
than 80 mm dia. Please refer the tender drawings for the details.
The landing valve (internal) shall be gunmetal Single headed type conforming to IS: 5290 complete with hand wheel,
quick coupling, spring and blank cap. 2 Nos. of RRL type hose pipe of 63mm dia and 15 mts. length as per IS: 636 with
63mm dia instantaneous type Gun metal heavy duty couplings & Gun metal Branch pipe and nozzle to be provided.
Fire hoses and branch pipes shall be mounted inside the fire shaft with suitable supports.
The Fire shaft shall be sealed at all floors with fire retardant material.
Fire hoses shall be Reinforced Rubber Lined (RRL) type as per IS: 636 & 63 mm dia and 15 mts long. Hoses shall be
bounded by G.I wire to heavy-duty instantaneous gunmetal couplings as per IS 903.
Branch pipe shall be gunmetal, 63 mm dia with Nozzle of 19 mm dia made as per IS: 903 and suitable fitted with
hoses as specified else where in this specifications.
Hose cabinet shall be fabricated by M.S. sheet of 16 swg and size shall be 750mm x 600mm x 250mm. Hose cabinet
shall have glass fronted door fitted with 4mm thick clear glass & powder coated finish of red out side & white inside.
Cabinet shall be suitable for stand mounting and shall have built in breakable glass type feature to keep key.
Fire shaft shall have shutter fabricated by M.S. sheet of 16 swg with glass-fronted door (glass shall be 4mm thick) and
size of the shutter shall be 900mm x 1500mm minimum. The door shall be in two leaves with necessary stiffeners.
Shutter shall be powder coated finish of red out side and white inside and on the glass label of “FIRE” shall be stick,
the letter size shall be min. 75 mm height. Also there shall be built in breakable glass type feature to keep key.
FBIC shall be as per IS 5131 & gunmetal four away connecting head with 4 x 63 mm dia instantaneous type inlets with
built in check valve and 150mm dia outlet connection to the fire main grid with 150mm dia Butterfly valve and non –
return valve. Also there shall be an additional fire brigade inlet connection to the fire water tank with necessary
accessories.
Air release valve is 25mm screwed inlet GM single acting type and shall be fixed on all high points in the system (wet
riser) with Ball valves or as shown on drawings.
Contractor shall provide suitable brick masonry chambers in cement mortar 1:5 (1 cement: 5 Coarse sand) on cement
concrete foundations 150mm thick 1:5:10 mix (1 cement: 5 fine sand: 10 graded stone aggregate 20mm nominal
size) 15mm thick cement plaster inside and outside finished with a floating coat of neat cement inside with cast
iron surface box ( OR top cover fabricated by M.S. chequered plate of 6 mm thick with frame / stiffeners etc)
approved by local fire brigade including excavation, back filling and additional Iron rungs for entering in to valve
chamber etc, complete.
15.1 PIPING
All piping in the system shall be tested to hydrostatic pressure of 1. 5 times of the pump head without drop in
pressure for at least 120 minutes. The test should be made in the presence of and to the satisfaction of the Employers
/ consultants representatives. Any defects / leakage should be repaired or if necessary defective works / equipment
should be replaced with new work / equipment. Tests should be repeated until work is done to the satisfaction of
concerned representatives. After testing, all pipes shall be flushed with portable water to remove foreign materials.
Under ground Pipes after lowered in to trenches shall be Holiday tested for damages of the anticorrosion treatment
and damages should be rectified, bring it to the notice of the engineer – in –charge of site before closing the
trenches.
Also the under ground pipes joints shall be tested for Radiographic for 10 % of the total under ground joints. The test
results and films shall be submitted for approval and any defects found in the welding process shall be rectified the
contractor with out any extra cost to the clients.
15.2 PUMPS
On completion of installation works at site the complete system shall be tested for satisfactory performance in line
with specifications as per Tender / requirements of Employer / Consultants. Pumps should test for Sequential Auto
start in case of using the Hydrants / sprinklers system. Also pump shall deliver minimum required flow & pressure at
top most hydrant point. All instruments for testing should be arranged by the Contractor. The performance test
includes commissioning spares like, diesel oil, engine oil, coolant, grease, gland packs and spare refills for Fire
extinguishers etc complete.
The pumps shall be exclusively used for fire fighting purposes and shall be BIS approved as mentioned in the BOQ.
One set main pump for each hydrant & sprinkler system with electrical motor driven direct couple centrifugal
pump of adequate discharge & head and in addition common standby Diesel engine driven direct coupled
The pumps shall be horizontal centrifugal horizontal split casing multi out let type ( Two out lets) type, pump
designed for continuous operation and shall have a continuously dropping head characteristic without any zone of
instability. The pump shall deliver with one out let a low head of 12 and high head of 21.5 bar. The power capacity
characteristic shall be non-over loading type. The head vs. capacity, input power vs. capacity characteristics, etc.,
shall match to ensure load sharing and trouble free operation throughout the range. In case of accidental reverse
flow through the pump the driver shall be capable of bringing the pump to its rated speed in the normal direction
from the point of maximum possible reverse speed. The contractor under this specification shall assume full
responsibility in the operation of the pump and the drive as one unit. The pump shall be capable to discharge 150
percent of rated capacity at a total head of not less than 65 percent of the total rated head. The total shut off
head shall not exceed 120 percent of total rated head on the pump. An automatic air release valve shall be
provided to vent air from the pump discharge and also to admit to the pump to dissipate the vacuum there, upon
stopping of the pump.
This valve shall be located at the highest point in the discharge line between the pump and the discharge check
valve. Pump coupled with motor or engine on a common base plate shall perform smoothly without any excessive
noise or vibration. Also pump shall be provided with re-circulation piping with valves.
The casing shall be cast iron to IS 210 and capable of withstanding to the maximum pressure developed by the
pump at the pumping temperature.
16.3 IMPELLER
The impeller shall be of standard bronze. The impeller shall be secured to the shaft with hydraulically balanced and
shall be retained against circumferential movement by keying, pinning or lock rings. All screwed fasteners shall
tighten in the direction of normal rotation.
16.4 SHAFT
Shaft size shall be selected on the basis of maximum combined shear stress. The shaft shall be of stainless steel
AISI-410 ground and polished to final dimensions and shall be adequately sized to withstand all stresses from
motor weight, hydraulic loads, vibrations and torque’s coming in during operation. Pump Shaft-Motor Shaft
Coupling
shall be connected with adequately sized flexible couplings with spacer of suitable approved design. Necessary
guards shall be provided for couplings. Pump shall be consisting with Gland plate for gland packing.
A common base plate for mounting both the pump and drive shall be provided. The base plate shall be of rigid
construction, shall be fabricated by M.S. channels. Base plate and pump supports shall be so constructed, the
The rotating elements shall be so designed to ensure least vibration during start and throughout the operation of
the equipment. All rotating components shall be statically and dynamically balanced at workshop. All the
components of pumps of identical parameters supplied under these specifications shall be interchangeable.
A comprehensive instruction manual shall be provided by the sub-contractor indicating detailed requirements for
operation, dismantling and periodic operation and maintenance procedures. Recommended tools/spares shall be
provided along with the Pump set.
17.1 GENERAL
The diesel engine shall be of multi-cylinder type four-stroke cycle with mechanical (airless) injection, cold starting
type. The engine shall be manufactured as per IS 10000 and shall be ease of maintenance, repair, cleaning and
inspection. This will also provide interchangeability of parts. All parts susceptible to temperature changes shall
have tolerance for expansion and contraction without resulting in leakage, misalignment of parts or injury to parts.
17.2 STARTING
The engine shall be capable of both automatic and manual start. Generally the engine shall start automatically but
in case of the auto-start system failure the engine shall be capable of manual start. Engine shall be able to start
without any preliminary heating of combustion chamber; cranking mechanism shall also be provided. All controls/
mechanism, which has to be operated in the starting process, shall be within easy reach of the operator. A DC
motor charged by battery shall initiate automatic start of diesel engine. The battery shall hold adequate retainable
charge to provide the starting of the diesel engine. Starting power will be supplied from two sets of storage
batteries. One set of battery is for automatic starting of the engine and the other provided for manual starting. A
selector switch will be provided at automatic starting control panel to select any of the two sets of battery for
manual / auto starting of the engine. The battery capacity shall be adequate for ten consecutive starts without
recharging with a cold engine under full compression. The battery banks shall be used for no other purpose other
than starting of the engine and shall be fully charged at all times with provision for trickle and boost charges. After
start of the engine the charger shall be disconnected, the battery being fed from the engine dynamo. The two-
battery charger of air-cooled type shall be able to charge on battery bank at a time. The D/E starting panel along
with the battery chargers should be of reputed approved makes.
The engine shall have a speed control device which will control the speed under all conditions of load, the
governor shall be suitable for operation without external power supply. The Governor shall offer following
features: An adjustable governor to regulate engine speed within a range of 10% between shut-off and maximum
load conditions of the pumps. The governor shall be set to maintain rated pump speed at maximum pump load.
The diesel engine is to run on high-speed diesel, the tank provided being enough to hold the volume required for 6
hours (minimum) continuous operation. Fuel tank shall be double wall type, so that over flow of the fuel shall be
collected in the secondary tank. Fuel supply and return piping shall be metal with necessary valves. Fuel tank shall
be mounted on the fabricated consisting with air vent, over flow, drain, filling and manhole etc.
Direct cooling system shall be employed for the diesel engine. Water shall be tapped from the fire pump
discharge. This water shall be led through duplex strainer, pressure breakdown orifice and then after passing
through the engine, the outlet water shall be taken directly to the sump through an elevated funnel. Re-circulating
thermo siphon system of cooling using a fan cooled radiator or indirect cooling system using heat exchanger shall
not be accepted.
17.6 ACCESSORIES
The engine shall be mounted on a base plate of fabricated steel construction. Adequate access shall be provided
for the big end and main bearings, camshaft and governor drives, water jackets etc., The engine shall have a base
plate made from MS sections. There shall be reasonable space at the big end, camshaft, water jackets, governor
drives and main bearings. The engine shall be provided with intake and discharge ductwork, inlet filter and
silencer, outlet muffler, expansion joints, dampers etc., as necessary for efficient operation. Intake air should be
taken from inside the building in which the engine is located, but the exhaust should be discharged outside the
building and exhaust duct shall be adequately sized for minimum pressure drop as per relevant code/standard, and
shall be housed clearing man height. The flywheel shall have graduated marking around the periphery to facilitate
checking of valve and fuel pump timings. Full set of diesel engine spares as per Standard requirement to be
provided along with tool kit.
17.7 INSTRUMENTATION
The diesel engine shall be provided with adequate instrumentation. The gauges etc., as required are provided for
in the Engine Panel. Also Bidder shall supply one set of Spare parts recommended by the manufacturer for
maintenance purposes.
The sprinkler system shall be provided in all floors. This system shall include the following :
Sprinkler risers shall be of two pressure levels, one can feed up to 14 th floor at 120mwc and other shall feed
from 15th floor onwards at 215mwc with necessary valves etc,-
The sprinkler heads shall be UL listed fixed temperature type with a quartzoid bulb containing liquid having high
vapor pressure held in position by a forged GM yoke and deflector. The rated temperature of quartzoid bulb shall
be 79°C.The spacing shall however conform to the detailed drawing, in Co-ordination with electrical and other
allied services at the ceiling level. Sub-contractor shall supply spare sprinkler heads and spanners neatly installed
in a steel box with glass shutter at an appropriate position approved by the Engineer-in-Charge.(THE TEST
PRESSURE OF THE SPRINKLER SHALL BE EQAL TO 150% OF THE PUMP HEAD).
A water motor gong and an inspection test connection shall be provided on the down streamside of the system.
The water curtain fire control system is designed to prevent the fire from propagating into adjacent cars and areas
in case of a fire incident. The system will encapsulate the fire between the water curtain sections in order to make
the evaluation of people who may be trapped inside.
The present system is designed as a fire controlling system where the curtains will effectively stop the fire from
propagation. The physics in this respect and the task is to create an effective water wall fire barrier. When hot
smoke and air is reaching the fire curtain, the ambient temperature in this area will be significantly reduced as a
function of rapid heat exchange/heat absorption. Water Curtain fire protection system, consisting of plurality of
nozzles are forming a water barrier.
For design water curtain system each compartment is envisaged as independent zone and each wall will protect by
independent system. Each system will consisting of Motorized valve, water supply pipe lines, isolation valves, Flow
switches, water curtain nozzles.
Water curtain system shall be interlocked with either smoke detection system OR flow swatches for activation. If
any zone comes on the adjacent zones also should discharge water and create curtain to avoid spread of fire /
smoke to another compartment. Logic control shall be done in such a way that three / four zones should operate
simultaneously to create compartment.
Pipes for the sprinkler system shall refer to the clause No. 2.0,
C. ELECTRICAL WORKS
1.1 General
The CONTRACTOR shall supply and install the electrical equipment and services necessary for the efficient
and safe operation of the fire protection systems detailed elsewhere in the specification, including :-
(b) MCC cum control panel housing the starters for all motors and complete with the switches, relays, push
buttons, indicating lamps, etc. necessary for the control of the fire protection system
(c) Power and control cabling between the MCC, motors, pressure switches, etc. including
accessories like conduits, cable trays ,etc.,
(d) To carry out the electrical installation works in accordance with specifications and as required by the local
statutory departments.
(e) To include the preparation of shop drawings and construction drawings for submission to the Consulting
Engineers to review prior to construction. Final as-built drawings after commissioning of the Fire Protection
System.
The motor shall be as per IS: 325 and with class “F” insulation, totally enclosed fan cooled, horizontal induction
foot mounted type and rated not to draw starting current more than 6 times normal running current. Motor shall
be capable of driving the pumps at rated discharge and head & at 150% of its rated discharge at 65 % of the rated
head ( in any case 15 % safety load should add) and shall be designed for continuous full load duty. The motor
shall be capable of handling the required starting torque of the pumps. Speed of motor shall be compatible with
the speed of the pump. The cooling fans shall be directly driven from motor shaft. Motor situated outdoors or
exposed to the weather shall be weather protected. Motors shall be enclosed type and shall have dust tight
construction with suitable means of breathing and of drainage to prevent accumulation of water from
condensation. Drain holes shall exclude bodies greater than 6mm diameter.
All components shall be of adequate mechanical strength and robustness and shall be constructed of metal unless
otherwise approved. All motors shall be dynamically balanced.
The switch board shall be metal clad, totally enclosed, rigid, compartmentalized design, floor mounting, air
insulated, extensible cubicle type for use on medium voltage power, 3 phase 4 wire 50 cycles system. The degree
of protection shall be of IP55 incase of outdoor application as detailed in BOQ. The equipment shall be designed
for operation in high ambient temperature and high humidity tropical atmospheric conditions. Means shall be
provided to facilitate ease of inspection, cleaning and repairs for use in installations where continuity of operation
is of prime importance.
The entire logic of the fire protection system shall be built in this panel. It shall have necessary relays/contactors
for accepting contacts from Pressure/limit switches and for switching ON/OFF motors accordingly. It shall have
ammeter, voltmeter, start / stop push buttons, manual and automatic selector switches, pumps on, off, trip
indicating lamps, relays and other control equipment necessary for the efficient indication and operation of the
system. A visual and audio alarm shall also be provided to raise an alarm when any of the pumps is tripped. It
shall have provision for annunciating the water tank water level high / low / overflow conditions.
Provision shall be made for interfacing with the Building Automation system. Potential free contacts for motors
ON / OFF / TRIP, MCC trouble and fire water tanks level LOW/HIGH/OVERFLOW conditions be provided in the
control panel for BAS. Also provision shall be made for receiving signals from BAS.
2.2 STANDARDS
Moulded Case Circuit Breaker (MCCB) - IS 13947 - 1,2/ IEC 947 - 1&2
2.3 CONSTRUCTION
Sheet steel enclosed, indoor floor mounted free standing cubicle type. Made up of the requisite vertical
sections modular type which when coupled together shall form continuous dead front switchboards. Dust, vermin
and damp proof and enclosure protection not less than IP 52. Each feeder/instrument compartment shall be
provided with a hinged door interlocked with MCCB/SFU inside the compartment such that door can only be
opened when MCCB/SFU in off position. Readily extendable as required by the addition of vertical sections
after removal of the end covers. Switch boards shall have access to the feeders, bus bars, cable termination,
cable alley, etc. as required
A front framed structure of rolled/folded CRCA sheet steel angle section of minimum 3 mm thickness
rigidly bolted together. This structure shall house the components contributing to the major weight of the
equipment such as circuit breaker cassettes, fuse switch units, main horizontal bus bars, vertical risers and
other front mounted accessories. The structure shall be mounted on a rigid base frame of folded CRCA sheet steel
of minimum 6 mm thickness and 75 mm height. The design shall ensure that the weight of the components is
adequately supported without deformation or loss of alignment during transit or during operation. A cable
chamber housing the cable end connections and power/control cable terminations. The design shall ensure
generous availability of space for ease of installation and maintenance of cabling and adequate safety for
working in one vertical/horizontal section without coming into accidental contact with live parts of the adjacent
section. A cover plate at the top of the vertical section, provided with a ventilating hood where necessary. Any
aperture for ventilation shall be covered with a perforated sheet having less than 1mm diameter perforations to
prevent entry of vermin. Front and rear doors fitted with dust excluding neoprene gaskets with fasteners designed
to ensure proper compression of the gaskets. When covers are provided in place of doors generous overlap shall
be ensured between sheet steel surfaces with closely spaced fasteners to preclude the entry of dust. The height
of the panel shall not be more than 2200 mm unless otherwise specified and maximum height of operating
handle shall not be more than 1800mm from FFL. The total depth of the panel shall be adequate to cater to
proper cabling space. Doors shall be of minimum 14 gauge sheet steel and covers/partitions of 16G sheet steel. All
sheet steel work forming the exterior of switchboards shall be smoothly finished, leveled and free from flaws.
The corners should be rounded. The Components in the switch boards shall be so arranged as to facilitate ease
of operation and maintenance and at the same time to ensure necessary degree of safety.
Components forming part of the switchboards shall have the following minimum clearances:
When, for any reason, the above clearances are not available, suitable insulation barrier/shielding shall
be provided. Clearances shall be maintained during normal service conditions. Creep age distances shall
comply with those specified in relevant standards. All insulating material used in the construction of the
equipment shall be of non-hygroscopic material treated to withstand the effects of high humidity, high
temperature and tropical ambient service conditions. Functional units such as circuit breakers, fuse switches,
MCCBs, etc. shall be arranged in multitier formation except that not more than two air circuit breakers shall be
housed in a single vertical section. Metallic/insulated shrouding shall be provided within vertical sections and
between adjacent sections to ensure prevention of accidental contact with: Main bus-bars and vertical risers
during operation, inspection or maintenance of functional units and front mounted accessories. Cable
terminations of one functional unit, when working on those of adjacent unit/units. All covers providing access
to live parts/circuits shall be provided with tool operated fasteners to prevent unauthorized access. Provision
shall be made for permanently earthing the frames and other metal parts of the switchgear by two independent
distinct connections. Only CRCA steel sheets shall be used for fabricating the cubicle. Thickness tolerance for
sheets shall be as applicable in relevant IS.
Generally the treatment and finish of the metal surface shall be as per detailed specifications enumerated
elsewhere in this document.
DEGREASING
Effective cleaning by hot alkaline degreasing solution followed by cold water rinsing to remove traces of alkaline
solution.
PHOSPHATING
A recognized phosphate process to facilitate durable coating of the paint on the metal surfaces and also to prevent
the spread of rusting in the event of the paint film being mechanically damaged. This again shall be followed by hot
water rinsing to remove traces of phosphate solution. Drying in dust free atmosphere.
Primer : Primer coating with a coat of corrosion resistant primer applied on wet surface.
Finish coat : Two finishing coats of stoving synthetic enamel paint to the specified shade of IS:5. Both the finish
shall be only spray painted or powder coating. For outdoor units the finishing coat shall be of weather resistant
stoving epoxy paint of specified shade of IS5.
The bus bars shall be made of high conductivity high strength E91E aluminum alloy suitable for 415
volts,3phase 4 wires 50 Hz 20KA unless otherwise specified. The bus bars shall be suitably supported with non-
hygroscopic supports to provide a fault withstand capacity as specified. High tensile bolts and spring washers
shall be provided at all bus bar joints. Fish plates of equal type and size shall be used at all joints. The bus bars shall
have uniform cross section throughout and shall be capable of carrying the rated current at 415V continuously.
The neutral bus bars shall have a continuous rating of at least 50% of the phase bus bars, unless mentioned
otherwise. Bus bars shall be fully sleeved using heat shrunk PVC sleeves appropriately colour coded to identify
different phases and neutral bar. An earth bus of size not less than 40 x 6 mm aluminum/GI shall run throughout
the length of switch board at top or bottom as required.
The Moulded Case Circuit Breaker shall be incorporated in the switch board wherever specified and shall be of
the current limiting type. MCCB shall conform to IS 2516, IS 13947-1/ IEC 947-1 (part I & II / section 1) 1977 for
general rules. It should be suitable for Horizontal and Vertical mounting and line load reversibility. MCCB shall
be suitable either for Single Phase AC 230V On Three Phase 415V. The MCCB shall be available in four pole
versions for neutral isolation. It shall have tropicalisation as standard feature.
The MCCB cover and case shall be made of high strength heat-resistant and flame-retardant thermosetting
insulating material. The operating handle shall be quick make, quick break, trip - free type. The operating handle
shall have suitable `ON' `OFF' `TRIPPED' indicators and in order to ensure suitability for isolation complying with IS
13947-2/IEC947-2, the operating mechanism shall be designed such that the toggle or the handle can only be in
`OFF' position : if the main contacts are actually separated.
2.8 ACCESSORIES
MCCB shall be designed to have following accessories and it shall be fittable at site.
Under voltage trip , Shunt trip, Alarm switch, Auxiliary switch, Remote operation using motor mechanism with
facility of using the same in auto/manual mode.
2.9 INTERLOCKING
MCCB shall be provided with following interlocking devices for interlocking the door of a switch board. Handle
interlock to prevent unnecessary manipulations of the breaker. Door interlock to prevent door being opened
when breaker is in ON position. The interlocking device to open the door even if the breaker is in ON position. In
addition to the above, ant other features indicated in the Bill of Quantities shall also be provided.
Short time with standing capacities different ratings of MCCB's shall be as follows :
[Amps] [KA]
2.11 CONTACTORS
Contactor shall comply with IS 13947-1 for general rules and IS 13947 - 4.1 for Standards pertaining to Contactor
and Motor Starter. The Contactors shall be capable of withstanding breaking and making capacities per following
:
Contactor shall be capable of withstanding an impulse voltage of 8KV and have an insulation voltage of 1000V.
Contactor shall be suitable for aluminum termination with a maximum permissible temperature rise of 650 C at
the terminals with an ambient temperature of 500 C. The coils shall have three terminals and the insulation
should be of class H type. The auxiliary contact block shall have a switching capacity of 220V, 2A. Contactor shall
have one auxiliary in built and it should be possible to have additional NO/NC contacts in steps of two. Miniature
Circuit Breakers [MCB] :
MCB shall be in 1,2,3,4, pole versions. MCB casing shall be made of self extinguishing, tropicalised material. MCB
shall comply with IS 8828-1996/IEC 898-1995. It shall be suitable for use in frequency range 40Hz to 60Hz and
shall accommodate AC/DC supply according to requirements. It shall have a trip-free mechanism and toggle shall
give a positive contact indication. It shall be suitable for mounting on 35mm DIN rail/surface mounting. It may be
installed horizontally, vertically on the ceiling in any place without any change in electrical performance. Line
supply may be connected to either top or bottom terminals i.e. There should be no line-load restriction. Degree of
protection when the MCB is flush mounted, shall be IP40. MCB shall be supplied with clamping terminals fully
open. Contact closing shall be independent of the speed of operator. The breaking capacity of the MCB shall be
9KA/10KA. The MCB shall be capable of being used as Incomer Circuit Breaker and shall be suitable for use as
isolator. In case of multiple MCBs in a single location (DB), it should be possible to remove any MCB without
having to disturb other MCB in the vicinity.
Deleted
Dleted
Current transformer shall comply with the requirements of IS 2705. They shall have ratios, outputs and accuracy
as specified/required. All CT's shall be of resin cast type unless otherwise specifically called for. All CT's shall be of
bar type primary or suitable for the cable given type and size and the CT’s shall be provided with shorting links
irrespective of the CT’s ratio’s preferably with ELMEX / PHOENIX. For all the CT's suitable type and size clamps are
to be supplied for mounting in the switch boards. Polarities and terminal markings of primary and secondary shall
be clearly marked on all CT's.
a. Current Ratios :
ii. Secondary : 5A
5P10-O/C,E/F, RPR
d. System Voltage
All instruments and meters shall be enclosed in dust proof, moisture resistant, black finished cases and shall
be suitable for tropical use. They shall be calibrated to read directly the primary quantities. They shall be
accurately adjusted and calibrated at Works and shall have means of calibration, check and adjustment at site.
Indicating instruments shall be flush mounted with anti-parallel white circular scales with black pointer and
with black numbers and lettering. Knife edge pointers shall be preferred. Unless otherwise specified, the size of all
instruments shall be 96mm x 96mm type. The dials shall be free from warping, fading and discolouring. Spring
controlled instruments shall be provided with front of board zero adjuster, capable of being safely handled while
the instrument is in Service. Instrument covers shall also have red marks on the dial corresponding to rated
values of the associated primary equipment. Synchronising instruments shall also meet the requirements of this
clause. The indicating instruments shall conform to IS:1248 and shall have on an accuracy class of 1. The Ammeter
and Wattmeter current coils shall withstand 200% of rated current continuously and 10 times the rated current
for 0.5 seconds without loss of accuracy . Voltmeter and Wattmeter potential coils shall withstand 120% of rated
voltage continuously and twice the rated voltage for 0.5 sec. without loss of accuracy.
2.17 VOLTMETER
Voltmeter shall be suitable for operating directly on LT supply voltage 415V, 50Hz or with a PT as per the
requirements. All the Voltmeters used for rated operating Voltage of 415/110V as required at 50Hz AC. With a
scale as required at site.
All Voltmeters are 96 x 96mm, suitable for mounting on the panel. Type Sl.No. accuracy class and borders of
the Voltmeter shall be indicated on the dial.
All the Ammeters shall be CT operated (5A) with a dial marked for line currents.
Type, Sl.No., Accuracy class, Operating Current, Burden etc., shall be indicated on the dial. All Ammeter shall be
of panel mounting type and shall be provided with zero setting screw.
Push buttons shall be of momentary contact type with rear terminal connection. These shall be suitably
shrouded to prevent inadvertent operation. Integral inscription plates engraved with their functions shall be
provided. All push buttons shall have two Normally Closed and two Normally Open contacts comprising rivets
of pure silver. The contacts shall be able to make and carry 5 A and break up one amp inductive load at 250V
DC.
Cable entries and terminals shall be provided in the switch board to suit the number, type and size of
aluminium conductor power cables and copper conductor control cable specified in the detailed specifications.
Provision shall be made for top or bottom entry of cables as required. Generous size of cabling chambers shall
be provided with the position of cable gland and terminals such that cables can be easily and safely terminated.
Barriers or shrouds shall be provided to permit safe working at the terminals of one circuit without accidentally
touching that of another live circuit. Cable risers shall be adequately supported to withstand the effects of rated
short circuit currents without damage and without causing secondary faults. Cable sockets shall be of tinned
copper and of the crimping type.
All control wiring shall be carried out with 1100V grade single core PVC cable having stranded copper
conductors with minimum cross section of 1.5 Sqmm for potential circuits and 2.5 Sqmm for current transformer
circuits. Wiring shall be neatly bunched, adequately supported and properly routed to allow for easy access and
maintenance. Wires shall be identified by numbered ferrules at each end. The ferrules shall be of ring type and
of non-deteriorating material. They shall be firmly located on each termination so as to prevent free movement.
All control circuit fuses shall be mounted in front of the panel and shall be easily accessible.
Terminal blocks shall be of 500 Volts grade and of stud/screwless type. Terminal blocks shall have a minimum
current rating of 10 Amps and shall be shrouded. Provisions shall be made for label inscriptions. At least 20%
spare terminals shall be provided on each panel and these spare terminals shall be uniformly distributed on all
terminal blocks.
Terminal blocks for current transformer and voltage transformer secondary leads shall be provided with test
links and isolating facilities. Also current transformer secondary leads shall be provided with short circuiting and
earthing facilities.
2.23 RELAYS
All Relays shall conform to the requirement of IS: 3231/IS 8686 or other applicable approved standards Relays
shall be suitable for flush and Semi-flush mounting on front At with connections from the rear. All Protective
Relays shall be of draw out or plug in type/Modular cases with proper built in test facilities. Test blocks and
switches shall be located immediately below each relay for testing. The auxiliary relays shall be self reset type.
All AC Relays shall be suitable for operation at 50Hz. AC Voltage operated relays shall be suitable for 110/v3 Volts
PT secondaries and Current operated relays for 5Amp. CT. secondaries as specified in this specification. Voltage
operated relays shall have adequate thermal capacity for continuous operation. Auxiliary Relays and Timers
shall have pairs of contacts as required to complete the scheme. Contacts shall be silver faced with spring
action.
All Protective Relays, Auxiliary Relays and Timers except the lockout relays and interlocking relays specified
shall be provided with self reset type contacts. All, Trip and Timers shall be provided with externally hand reset
positive action provided with inscription subject to /Consultant approval. Timers shall be of the electromagnetic
or solid state type.
Wherever solid state relays are used the following requirement shall be met with:
All Relays shall be designed for operating under or ambient temperature 55.C and 100% relative humidity.
Electronic type timers shall be as far as possible avoided.
All accessories required for correct operation of each relay shall be supported by the Sub-contractor without any
extra cost. The solid state relays shall be stable and suitably protected against transient/induced over voltages.
The bidder shall state clearly in his list special requirements, if any, for DC input arrangement or cabling
considered necessary for satisfactory operation of solid state relays quoted by him.
The panel as well as feeder compartments shall be provided with name plate of anodized aluminum with white
engraving on black background. They shall be properly secured with fasteners/rivets. The panel/feeder
descriptions shall be as indicated in the drawings/ by the employer.
2.25 TESTS
The routine tests shall be conducted as per IS standards on each Power Control Centre and shall comprise:
Inspection of the Switch Boards including inspection of wiring and electrical operational/functional tests where
necessary.
Insulation resistance of the power circuit between each pole and the earth and that between the poles shall be
measured. Insulation resistance of all secondary wiring between phase and earth shall be measured. Insulation
test shall be carried out both before and after high voltage test. Checking of protective measures and electrical
continuity of the protective circuits.
A high voltage test with 2.5 KV for power circuit and 1.5KV for Control Circuit, Duration one minute shall be
applied between each pole and earth and between poles. Test certificate shall be submitted along with panel.
2.29 STORING
The panels shall be stored in a well ventilated dry place. Suitable polythene covers shall be provided for
necessary protection against moisture, dust and vermin.
2.30 ERECTION
Switch boards shall be installed over trench/floor as required. Suitable grouting holes shall be provided in the
flooring. Suitable MS base channel shall be embedded in the flooring on which the panel can directly be installed.
The switch boards shall be properly aligned and bolted to the flooring by atleast four bolts. Cables shall be
terminated on the bottom plate or top plate as the case may be, by using brass compression glands. The
individual cables shall then be led through the panel to the required feeder compartments for necessary
terminations. The cables shall be clamped to the supporting arrangement. Either side, the switch board earth
bus shall be connected to the local earth grid. The base channel used for erection of panels shall form part of the
cost of the panel and shall not be measured or paid separately.
The panels shall be commissioned only after successful completion of the following tests. The test shall be
carried in the presence of Architect's representative. All main and auxiliary bus bar connections shall be checked
and tightened. All wiring terminations and bus bar joints shall be checked and tightened. Wiring shall be checked
to ensure that it is according to the approved drawing.
All wiring shall be tested for insulation resistance by a 500 volt megger. Phase rotation tests shall be conducted.
Suitable injection tests shall be applied to all the measuring instruments to establish the correctness and
accuracy of calibration and working order if required by the Employer. All relays and protective devices shall be
tested for correctness of settings and operation by introducing a current generator and an ammeter in the
circuit or shall produce calibration/test certificate as required by the Employer / Inspectorate / consultant.
Functional tests on all feeders. Makes, type and ratings of all components shall be checked/verified as per
approved drawings.
3.1 TYPE
Low voltage cables shall be aluminum conductor, PVC insulated, PVC sheathed and steel wire armored or steel
tape armored Andhra Pradesh State Fire Services, FRLS- PVC out sheathed construction. The cables shall conform
to IS 1554 Part I in all respects. Cables shall be laid in tray/Hume pipe/in ready made trenches etc., as required.
i) The oxygen index value shall be minimum 29 when tested at 27 2 C as per ASTM-D-
2863-77 and temperature index value shall be minimum 250 C when tested as per
NES 715.
ii) The maximum total acid gas generation as determined by titration shall be less than 20
% by weight. The test shall be conducted as per IEC-754-1 (1994).
iii) The smoke density shall be 60 % maximum, when tested as per ASTM-D-2843-77
(1988).
iv) The finished cable shall pass the flammability test as per IEC-332-1 (1993), In addition,
it shall also pass flammability test as per Class F3 of Swedish Standard SS-424-1475
(1978).
The sizes of cables shall be selected to limit the voltage drop during running and voltage dip during starting to 5%
and 10% respectively. Adequate derating factors shall be considered
3.2 RATING
Cores shall be provided with the following colour scheme of PVC insulation:
1 core : Red/Black/Yellow/Blue
4.1 STORING
On receipt of cables at site the cables shall be inspected and stored in a safe place.
4.2 LAYING
Cables shall be laid in outdoor trenches wherever called for. The depth of the trenches shall not be less
than 75 cm from the final ground level. The width of the trenches shall suit easy laying of cable. Where more
than one cable has to be laid in the same trench, all attempts shall be made to keep the axial distance between
successive cables to be at least 1d where 'd' is the diameter of the bigger cable. The trenches shall be cut square
Cables shall be laid in indoor trenches wherever specified. Suitable angle iron brackets, clamps, hoods
and saddles shall be used for securing the cable in position.
Cables shall be laid on cable trays/racks wherever specified. Cable racks/trays shall be of perforated
steel section/slotted angles suitable for the purpose. The trays/racks shall be complete with plates, tees, elbows,
risers and all necessary hardware. The steel trays shall be painted. Cable trays shall be erected properly to present
a neat and clean appearance. Suitable cleats or saddles shall be used for securing the cables to the cable trays.
The cable trays shall comply with the following requirements :
The trays are ladder type and shall have suitable strength and rigidity to provide adequate support for all
contained cables. It shall not present sharp edges, burrs of projections injurious to the insulation of the
wiring/cables. If made of Sheet metal, it shall be adequately protected against corrosion or shall be made of
corrosion resistant material. It shall have side rails or equivalent structural members. It shall include fittings
such as horizontal, vertical bends, tie rods, hooks etc., or other suitable means for changes in direction and
elevation of runs, fish plates and hard ware.
8.0 INSTALLATION
Cable trays shall be installed as a complete system. Trays shall be supported properly from the building
structure. The entire cable tray system shall be rigid. Each run of the cable tray shall be completed before the
installation of cables. In-portions where additional protection is required, non-combustible covers/enclosure shall
be used. Cable trays shall be exposed and accessible. Where cables of different system are installed on the same
cable tray, non-combustible solid barriers shall be used for segregating the cables. Cable trays shall be grounded
by two nos. earth continuity wires. Cable trays shall not be used as equipment grounding conductors.
Cable jointing shall be done as per the recommendations of the cable manufacturer. Jointing shall be done by
qualified cable jointers. Each terminations shall be carried out using brass compression glands and cable sockets.
Hydraulic crimping tool shall be used for making the end terminations. Cable gland shall be bonded to the
earth by suing suitable size G.I. wire/tape.
Suitable identification tags with the feeder designation inscribed on an aluminum/G.I. sheet shall be tied to either
ends of each cable.
10.0 TESTING
1.1. DESCRIPTION
A. This section of the specification includes the Design, engineering, furnishing, installation, and connection
of a microprocessor controlled, analog addressable fire alarm equipment required to form a complete coordinated
system ready for operation. It shall include, but not be limited to, alarm initiating devices, alarm notification
appliances, control panels, auxiliary control devices, annunciators, power supplies, and wiring as per tender
drawings and specified herein.
1.2. SCOPE
A. A new addressable analogue reporting, microprocessor controlled fire detection system shall be installed
in accordance with the specifications and approved shop drawings.
B. The system shall be designed such that each loop shall limited to only 80% of its total capacity at initial
installation.
C. BASIC PERFORMANCE
1. Alarm, trouble and supervisory signals from all intelligent reporting devices shall be encoded on type – A
loop.
2. All Detectors shall be wired Class A, as part of an addressable device connected by the loop Circuit.
3. Notification Appliances shall be wired Class A, as part of an addressable device connected by the loop
Circuit.
4. A single ground fault or open circuit on the system loop shall not cause system malfunction, loss of
operating power or the ability to report an alarm.
5. Alarm signals arriving at the FACP shall not be lost following a primary power failure (or outage) until the
alarm signal is processed and recorded.
When a fire alarm condition is detected and reported by one of the system initiating devices, the following
functions shall immediately occur:
3. The LCD display shall indicate all information associated with the fire alarm condition, including the type
of alarm point and its location within the protected premises.
4. Printing and history storage equipment shall log the information associated each new fire alarm control
panel condition, along with time and date of occurrence.
5. All system output programs assigned via control-by-event interlock programming to be activated by the
particular point in alarm shall be executed, and the associated system outputs (notification appliances and/or
relays) shall be activated.
6. The audio portion of the system shall sound the proper signal (tone or voice) to the appropriate zones.
a. The monitoring of the status of various detectors/devices should be report at the Panel and at PC in
Security room /Reception
c. In the event of fire alarm, FAS shall directly activate the motorized butterfly valve for the water curtain
system.
1.3. SUBMITTALS
A. GENERAL
1. Six copies of all submittals shall be submitted to the Architect/Engineer for review.
2. All references to manufacturer's model numbers and other pertinent information herein is intended to
establish minimum standards of performance, function and quality. Equivalent compatible equipment from other
manufacturers may be substituted for the specified equipment as long as the minimum standards are met.
3. All substitute equipment proposed as equal to the equipment specified herein, shall meet or exceed the
following standards. For equipment other than that specified, the contractor shall supply proof that such
substitute equipment equals or exceeds the features, functions, performance, and quality of the specified
equipment.
1. Sufficient information, clearly presented, shall be included to determine compliance with drawings and
specifications.
2. Include manufacturer's name(s), model numbers, ratings, power requirements, equipment layout, device
arrangement, complete wiring point-to-point diagrams, and conduit layouts.
C. MANUALS
1. Submit simultaneously with the shop drawings, complete operating and maintenance manuals listing the
manufacturer's name(s), including technical data sheets.
2. Wiring diagrams shall indicate internal wiring for each device and the interconnections between the items
of equipment.
3. Provide a clear and concise description of operation that gives, in detail, the information required to
properly operate the equipment and system.
4. Approvals will be based on complete submissions of manuals together with shop drawings.
5. Also contactor should submit operation and maintenance manuals with as built drawings in six sets. All
test certificates, field test reports, and performance test reports etc on handing over of the system.
D. SOFTWARE MODIFICATIONS
1. Provide the services of a factory trained and authorized technician to perform all system software
modifications, upgrades or changes. Response time of the technician to the site shall not exceed 4 hours.
2. Provide all hardware, software, programming tools and documentation necessary to modify the fire alarm
system on site. Modification includes addition and deletion of devices, circuits, zones / loops and changes to
system operation and custom label changes for devices or zones / loops. The system structure and software shall
place no limit on the type or extent of software modifications on-site. Modification of software shall not require
power-down of the system or loss of system fire protection while modifications are being made.
E. CERTIFICATIONS
Together with the shop drawing submittal, submit a certification from the major equipment manufacturer
indicating that the proposed supervisor of the installation and the proposed performer of contract maintenance is
an authorized representative of the major equipment manufacturer. Include names and addresses in the
certification.
1.4. GUARANTY
A. All work performed and all material and equipment supplied & installed under this contract shall be free
from defects, Brand-new. The full cost of maintenance, labor and materials required to correct any defect during
DLP / Warranty shall be included in the quoted prices.
A. Complete maintenance and repair service for the fire alarm system shall be available from a factory
trained authorized representative of the manufacturer of the major equipment for a period of five (5) years after
expiration of the guaranty.
B. As part of the bid/proposal, include a quote for a maintenance contract to provide all maintenance, tests,
and repairs described below. Include also a quote for unscheduled maintenance/repairs, including hourly rates for
technicians trained on this equipment, and response travel costs for each year of the maintenance period. Rates
and costs shall be valid for the period of five (5) years after expiration of the guaranty.
C. Maintenance and testing shall be on a semiannual basis or as required by the facility maintenance team. A
preventive maintenance schedule shall be provided by the contractor, describing the protocol for preventive
maintenance. The schedule shall include:
1. Systematic examination, adjustment and cleaning of all detectors, manual fire alarm stations, Sounders,
strobe lights, voice alarm speakers, control panels, power supplies, relays, water flow switches, modules and all
accessories of the fire alarm system.
3. Each smoke detector shall be tested in accordance with the requirements of NFPA 72 Chapter 7.
A. The contractor shall have the ability to provide parts and labour to expand the system specified, if so
requested, for a period of five (5) years from the date of acceptance.
B. As part of the Bid, include a quotation for all parts and material, and all installation and test labor of
intelligent or addressable devices for ten percent (10%) as mentioned under spare parts list. This quotation shall
include intelligent smoke detectors, intelligent heat detectors, addressable manual stations, addressable monitor
modules and addressable modules equal in number to one tenth of the number required to meet this specification
(list actual quantity of each type).
C. Do not include cost of conduit or wire or the cost to install conduit or wire.
1.7. APPROVALS
A. The design, supply, installation, testing and commissioning of the entire fire detection and alarm system
shall conform to EN 54,or BS: 5839. The Detectors shall conform to relevant codes for Fire Alarm System.
b) EN 54
c) BS 5839
A. All equipment and components shall be brand new, and the manufacturer's current model. The materials,
appliances, equipment and devices shall be tested and listed by a nationally recognized approvals agency for use as
part of a protected premises protective signaling (fire alarm) system. The authorized representative of the
manufacturer of the major equipment, such as control panels, shall be responsible for the satisfactory installation
of the complete system.
B. All equipment and components shall be installed in strict compliance with each manufacturer's
recommendations. Consult the manufacturer's installation manuals for all wiring diagrams, schematics, physical
equipment sizes, etc. before beginning system installation. Refer to the riser/connection diagram for all specific
system installation/termination/wiring data.
C. All equipment shall be attached to walls and ceiling/floor assemblies and shall be held firmly in place (e.g.,
detectors shall not be supported solely by suspended ceilings). Fasteners and supports shall be adequate to
support the required load.
A. CONDUIT
1. Conduit shall be in accordance with The National Electrical Code (NEC), local and state requirements.
2. Where possible, all wiring shall be installed in conduit or raceway. Conduit fill shall not exceed 40 percent
of interior cross sectional area where three or more cables are contained within a single conduit.
3. Cable must be separated from any open conductors of Power, or Class 1 circuits, and shall not be placed
in any conduit, junction box or raceway containing these conductors.
4. Wiring for 24 volt control, alarm notification, emergency communication and similar power-limited
auxiliary functions may be run in the same conduit as initiating and signaling line circuits. All circuits shall be
provided with transient suppression devices and the system shall be designed to permit simultaneous operation of
all circuits without interference or loss of signals.
5. Conduit shall not enter the fire alarm control panel, or any other remotely mounted control panel
equipment or back boxes, except where conduit entry is specified by the FACP manufacturer.
6. Conduit shall be 3/4-inch (19.1 mm) minimum, all conduits / junction boxes / collars shall be painted
before installation and there shall be marking (for identification) on the conduits at interval of 2m minimum.
B. WIRE
3. All wire and cable shall be listed and/or approved by a recognized testing agency for use with a protective
signaling system.
4. If Wires / cables not installed in conduit shall have a fire resistance rating suitable for the installation, may
be FRLS cables / wires used.
5. The system shall permit the use of Detectors and notification devices wiring in the same conduit with the
multiplex communication loop.
6. All field wiring shall be completely supervised. In the event of a primary power failure, disconnected
standby battery, removal of any internal modules, or any open circuits in the field wiring, a trouble signal will be
activated until the system and its associated field wiring are restored to normal condition.
7. All voice speaker and telephone circuits shall use twisted/shielded pair to eliminate cross talk.
All boxes and cabinets shall be as approved by the client / consultants for their intended purpose.
D. Initiating circuits shall be arranged to serve like categories (manual, smoke, water flow). Mixed category
circuitry shall not be permitted except on signaling line circuits connected to intelligent reporting devices.
E. The fire alarm control panel shall be connected to a separate dedicated branch circuit, maximum 20
amperes. This circuit shall be labeled at the main power distribution panel as FIRE ALARM. Fire alarm control panel
primary power wiring shall be 12 AWG. The control panel cabinet shall be grounded securely to either a cold water
pipe or grounding rod.
The main FACP Central Console shall contain a microprocessor based Central Processing Unit (CPU). The
CPU shall communicate with and control the following types of equipment used to make up the system:
intelligent addressable smoke and thermal (heat) detectors, addressable modules, panel modules
including initiating circuits, control circuits, and notification appliance circuits, local and remote operator
terminals, annunciators, and other system controlled devices.
The Bidder shall undertake the responsibility of the complete installation, commissioning, user trials,
training and maintenance of the System as required. The Bidder shall take all responsibility for
preparation and installation of System Software into the FACP. The Software shall be such so as to be
easily operated by the Client’s Personnel and secured against Software errors, ability to be upgraded so
as to incorporate more features at a later date.
The panel shall also have automatic dialer with speech processor for transmit fire message to select
telephone numbers in case of fire.
The logic circuitry shall be based on high noise immunity solid state hardware.
All addressable units shall be connected to the FACP through the Loop Cards and shall be addressed
through individual numbers. The FACP shall be able to obtain analogue value for all detectors in the
circuit through a pulsed digitalized current data. The FACP shall be able to analyse all analogue inputs
from all addressable units, and through its own software and ambient level screening the FACP shall be
able to identify fire, possible fire or fault conditions. The unit supervision shall be dynamic and
continuous.
The FACP shall also give adequate warning signal whenever there is dust accumulation in detectors, and
up to the point of its replacement it should be possible to change the level of ambient alarm calibration
condition either by the use of software program operable by the owner or by resetting the detector.
Short / Open circuit units shall also be reported at the FACP In such cases, the system through the use of
fault isolators shall be able to isolate that segment between the two fault isolators. The missing
Detectors/Devices shall also be reported at the FACP with identification of the location.
The Bidder shall also undertake to trip the AHUs from the Fire Alarm Panel through the use of
Addressable Output Modules and necessary AC/DC relays, activated by the fire signal of specified
detectors and Input Modules for monitoring contacts from Fire exit doors.
The FACP shall also be able to discriminate between false alarms and fire conditions, as well as priority
selection of alarm in case alarm activates in two or more remotely located units simultaneously. In such
cases, the Manual Call Points shall have the highest priority.
The FACP shall have its own Battery Backup of a minimum of 24 hours in normal run and then 15 min in
alarm condition. The Battery shall be of sealed lead acid re chargeable maintenance free type. Necessary
battery calculations for the system shall be provided along with the bid.
It shall be able to withstand temperature variations from 00 centigrade to 500 centigrade. Further,
Relative Humidity (non-condensing type) up to 95% shall not hamper its performance. The voltage rating
shall be from 17V DC to 31V DC, though the voltage may be change depending upon the working voltages
of a proprietary FACP.
The FACP shall also capable of repeating all the events & messages to a Passive Repeater Panel.
Display & Indication : The backlit LCD display shall atleast be of 168 characters that indicate all
information associated with the fire alarm condition, including the type of alarm point and its location
within the protected premises. It shall also provide Light-Emitting-Diodes (LEDs), that indicate the status
of the following minimum system parameters: POWER STATUS, TEST STATUS, FIRE ALARM, FAULT, CPU
FAILURE, POINTS DISABLED etc.,
Alarm Acknowledge: Activation of the control panel acknowledges function in response to new alarms
and/or troubles shall silence the local panel piezo electric signal and the associated LED on the panel shall
be turned ON.
Signal Silence: Signal Silence function shall cause all programmed alarm notification appliances
and relays to return to the normal condition. The selection of notification circuits and relays
that are silence able by this switch shall be fully field programmable within the confines of all
applicable standards.
System Reset: Depression of System Reset switch shall cause all electronically latched initiating devices
to return to their normal condition. And the system reset operation starts. The associated Yellow LED
shall flash during this operation to inform the user of the progress status of the reset cycle. The LED shall
flash fast during the smoke detector power down sequence, then it shall flash slowly during the restart
phase, and shall illuminate steadily for the restoral phase. The LED shall go out completely when the
system is back to normal mode.
Evacuation/ Fire drill: Depression of the Drill switch shall activate all programmed notification appliance
circuits. The drill function shall latch until the panel is silenced or reset.
Lamp Test: The Lamp Test function shall activate all local system LEDs, light each segment of the liquid
crystal display to check all the components are working OK..
Supervise and monitor all intelligent addressable detectors and monitor modules connected to the
system for normal, trouble and alarm conditions. System response to any alarm condition must occur
within 3 seconds, regardless of the size and the complexity of the installed system.
Supervise all initiating signalling and notification circuits throughout the facility by way of connection to
monitor and control modules.
Upon alarm activation of any area smoke detector, heat detector, manual pull station, sprinkler water
flow, the following functions shall automatically occur:
The LCD Display shall indicate all applicable information associated with the alarm condition including:
zone, device type, device location and time/date.
Any remote or local annunciator LCD/LED's associated with the alarm zone shall be illuminated.
A pre-evacuation message shall be sounded on all floors (zones), Stair cases, Lifts. It is the intent of this
message to advise occupants hearing this message that they are near danger and await further
instructions for leaving the building via the stairs (nearest exit).
Activate visual strobes /Sounders based on programmed sequence. The visual strobe shall continue to
flash or the sounders will hoot until the system has been reset.
An alert message shall be transmitted thro a telephone line on a preprogrammed telephone numbers.
All automatic events programmed to the alarm point shall be executed and the associated outputs
activated.
The system shall be fully supervised for all fault conditions with distinctive alarm operated for fault and fire
conditions. Test buttons and software features shall be provided to test the electronic circuits and detector health
System Programming: Advanced Windows based software shall be used to configure the system during system
start-up or system commissioning. Time and Date Stamps of all modifications made to the program must be
included to allow full retention of all previous program version data. All System operational software is to be
stored in FLASH memory. Control Panel disassembly and replacement of electronic components of any kind shall
not be required in order to upgrade the operations of the installed system to conform to future application code
and operating system changes. It shall have the ability to download all system applications programs and
“firmware” from a computer through a single point into the FACP.
Event Buffer: The panel shall maintain a history file of at least the last 1000 events, each with a time
and date stamp. History events shall include all alarms, troubles, operator actions, and programming
entries.
Early warning capability: To obtain early warning of incipient or potential fire conditions, the system
shall support a programmable option to determine system response to real-time detector sensing values
above the programmed setting.
It shall be possible to set individual smoke detectors for pre-programmed pre-alarm thresholds. If the
individual threshold is reached, the pre-alarm condition shall be activated and an alert displayed on the
panel.
When the detector reaches a level exceeding the pre-programmed level, the control panel shall indicate
an action condition. Sounder bases installed with either heat or smoke detectors shall automatically
activate on action Pre-Alarm level, with general evacuation on alarm level.
Alarm verification delay: The FACP shall provide means to cause alarm signals to only sound in specific
areas with a delay of the alarm after start of alarm processing. If the alarm is not acknowledged within
programmed delay, all local and remote outputs shall automatically activate immediately. The control
panel shall ignore the alarm verification timer if another alarm is detected during the verification period.
Enable/ Disable points: The FACP shall allow the operator to restore a disabled point (device) in the system,
allowing that point (device) to operate as originally intended by the application program of the system.
Additionally, the system shall allow the operator to restore any group function, function, Panel, system module,
“software - defined zone”, operator control, or time control function.
The FACP shall allow the operator to disable any point (device) in the system, inhibiting that point (device) from
operating as originally intended by the application program of the system. Additionally, the system shall allow the
operator to disable any group function, function, Panel, system module, “software - defined zone”, operator
control, or time control function within the system.
Check/Alter parameters: The system shall allow the operator to manually turn on any system output point, or
system function. Alter Smoke Detector sensitivity, message routing within the system shall be modifiable with this
simple command from the control panel.
The system shall allow the operator to restore the primary (application program defined) operation to the Smoke
Detector sensitivity and the message routing functions with this simple command from the control panel.
The system shall allow the operator to manually command and control relays. Relays shall be able to be
commanded to “Latch”, to energize as a “High Priority”, or as a “Low Priority”, to “Energize”, or to “De-Energize”.
Sensitivity Adjust: The system shall provide Automatic Detector Sensitivity Adjust based on Day/Night
schedules.
Environment Drift Compensation: The system shall automatically compensate for the drift in the sensitivity that
can occur due to dust & environment changes. Environmental compensation shall mean that the sensing element
adapts to long-term changes caused by dirt, humidity, aging etc. It shall even compensate for small amounts of
normal ambient smoke. The detector shall periodically adjust and updates the sensitivity (% obscuration) baseline
for its photoelectric sensing element. Periodically this information shall be written to its permanent memory.
When the detector accumulates dust in the chamber above the allowed limit, the control panel shall indicate a
maintenance urgent warning.
The system shall allow the operator to determine the status of individual system components, including active
points, disabled points, and active points by panel.
The LCD shall show the system time, and the number of active points and disabled points in the system in this
section of the LCD Display.
The LCD shall show the first active event of the highest priority. The text shall show the sequence number in
which the displayed event was received, as well as its event type. It shall also display an identification message
related to the displayed event.
The LCD shall show the total number of active events in the system, by event type. There shall be atleast three
different System Event Types that shall be displayed, “Alarm Events”, “Supervisory Events” and “Active Trouble
Events”. The Main LCD shall include queues for each of the System Event Types. The Main LCD shall allow the
operator to access to the System Status information contained within those queues by pressing an associated
select switch. Whenever there is an unacknowledged event in any of the System Event queues, the associated
Status LED shall flash. Viewing each event listed in a queue shall acknowledge all events in that queue, and shall
cause the associated LED to illuminate steady.
Passwords and Users: The system shall support at least two password levels, master and user.
Passwords shall be available, each of which may be assigned access to the programming change menus,
the alter status menus, or both. Only the master password shall allow access to password change
screens.
Report Generation capability: The system shall have the capability to connect to a printer to print at least the
following
It shall give a detailed description of the status of certain system parameters for corrective action, or for
preventative maintenance programs. The system shall provide these reports via the Main LCD, and shall be
capable of being printed on any of the connected system printers.
The system shall provide a report that provides a sensitivity listing of any particular detector or all detectors
The system shall provide a listing of all of the firmware revision listings for all of the installed network components
in the system.
One-Man Walk Test: The system shall provide walk test for testing the entire fire alarm system. The
walk test shall allow a single operator to run audible tests on the panel. When points are activated, each
initiating event shall latch the input. The test shall be audible and shall be used for pull station
verification, magnet activated tests on input devices, input and output device and wiring
operation/verification.
Response based on event: The panel software functions shall provide means to program a variety of
output responses based on various initiating events.
The system shall support at least 500 general purpose software zones for linking inputs to outputs. When
an input device activates, any zone programmed into that device's zone map will be active and any
output device.
Maintenance Menu: The Main LCD in the FACP shall also allow the System Operator to access system maintenance
functions through a multi level password system.
Enclosures: The control panel shall be housed in cabinet suitable for surface or semi-flush mounting. The
cabinet and front shall be corrosion protected, given a rust-resistant prime coat, and manufacturer's
standard finish.
The back box and door shall be constructed of steel with provisions for electrical conduit connections into
the sides and top.
The door shall provide a key lock and shall include a glass or other transparent opening for viewing of all
indicators. For convenience, the door may be site configured for either right or left hand hinging.
Power Supply: The Addressable Main / auxiliary Power Supply shall operate on 120/240 VAC, 50/60 Hz,
and shall provide all necessary power for the FACP and the notification appliances.
The Addressable Main Power Supply shall also incorporate a battery charger for 24 hours of standby
power for normal working & another ½ hour in alarm condition using dual-rate charging techniques for
fast battery recharge
The Addressable Main Power Supply shall provide a very low frequency sweep earth detect circuit,
capable of detecting earth faults.
Event Display: here shall be an event display field to display the current event. When there are no
events then it shall display an ALL CLEAR message. It shall be possible to manually scroll all the current
events both forwards & backwards. Facility shall be provided to add notes to the current event display.
Each type of event shall be represented in different colours It shall be possible to acknowledge the event
Status Bars shall be provided for events such as Fire, Fault, Disabled and warning. The Status Bar shall
Graphic Screen Display: It shall be possible to view manually the events in graphic screens, to view the
site plan and also to view in graphics the current device in fault or in alarm
The scrolling of the current event display with corresponding graphics shall also be shown automatically.
It shall be possible to manually select, view the details of devices and zones by selecting the relevant sub
screens.
It shall also be possible to enable or disable any zone or device and the same shall be restricted to higher
level users only.
Control Functions: It shall be possible to mute the PC alarm sound and the fire Panel buzzer, activate &
silence all sounders and print automatically alarm events from the software. It shall be possible to
add/delete new users.
The Loop Control Module shall monitor and control addressable devices. This includes intelligent
detectors (Ionization, Photoelectric, or Thermal) and fault isolation / monitor / control / control relay modules.
The Loop Control Module shall contain its own microprocessor and shall be capable of operating in a
local/degrade mode (any addressable device input shall be capable of activating any or all addressable device
outputs) in the unlikely event of a failure in the main CPU.
The Loop Control Module shall provide power and communicate with all intelligent addressable detectors
and modules on a single pair of wires.
The loop interface board shall be able to drive an NFPA Style 4 twisted shielded circuit up to maximum
length. The loop Interface shall also be capable of driving an NFPA Style 4, no twist, no shield circuit up to
maximum length. In addition, loop wiring shall meet the listing requirements for it to exit the building or structure.
"T"-tapping shall be allowed in either case.
The loop interface board shall receive analog or digital information from all intelligent detectors and shall
process this information to determine whether normal, alarm, or trouble conditions exist for that particular device.
Each Loop shall be isolated and equipped to annunciate an Earth Fault condition. The loop interface board
software shall include software to automatically maintain the detector's desired sensitivity level by adjusting for
the effects of environmental factors, including the accumulation of dust in each detector. The analog information
may also be used for automatic detector testing and the automatic determination of detector maintenance
requirements.
All wiring terminal blocks shall be the plug-in/removable type and shall be capable of terminating up to 1.5 sq.mm
wire. Terminal blocks that are permanently fixed to the PC board are not acceptable.
1. Addressable devices shall provide an address-setting means using rotary decimal switches.
2. Addressable devices shall use simple to install and maintain decade (numbered 0 to 9) type address
switches. Devices which use a binary address or special tools for setting the device address, such as a dip switch
are not an allowable substitute.
3. Detectors shall be Analog and Addressable, and shall connect to the fire alarm control panel's Signaling
Line Circuits.
4. Addressable smoke and thermal detectors shall provide single / dual (2)status LEDs. Both LEDs shall flash
under normal conditions, indicating that the detector is operational and in regular communication with the control
panel, and both LEDs shall be placed into steady illumination by the control panel, indicating that an alarm
condition has been detected. If required, the flashing mode operation of the detector LEDs can be programmed off
via the fire control panel program.
5. The fire alarm control panel shall permit detector sensitivity adjustment through field programming of the
system. Sensitivity can be automatically adjusted by the panel on a time-of-day basis.
6. Using software in the FACP, detectors shall automatically compensate for dust accumulation and other
slow environmental changes that may affect their performance.
7. The detectors shall be ceiling-mount and shall include a separate twist-lock base which includes a tamper
proof feature.
c. Isolator base
9. The detectors shall provide a test means whereby they will simulate an alarm condition and report that
condition to the control panel. Such a test may be initiated at the detector itself (by activating a magnetic switch)
or initiated remotely on command from the control panel.
10. Detectors shall also store an internal identifying type code that the control panel shall use to identify the
type of device (ION, PHOTO, THERMAL).
2. The two-wire monitor module shall mount in a 4-inch square (101.6 mm square), 2-1/8 inch (54 mm) deep
electrical box or with an optional surface backbox.
3. The IDC zone shall be wired for operation. An LED shall be provided that shall flash under normal
conditions, indicating that the monitor module is operational and in regular communication with the control panel.
1. Addressable control modules shall be provided to supervise and control the operation of one
conventional devices of compatible, 24 VDC powered, polarized audio/visual notification appliances. For fan
shutdown and other auxiliary control functions, the control module may be set to operate as a dry contract relay.
2. The control module shall mount in a standard 4-inch square (101.6 mm square), 2-1/8 inch (54 mm) deep
electrical box, or to a surface mounted backbox.
3. The control module shall be wired with up to 1 amp of inductive A/V signal, or 2 amps of resistive A/V
signal operation, or as a dry contact relay. The relay coil shall be magnetically latched to reduce wiring connection
requirements, and to insure that 100% of all auxiliary relay may be energized at the same time on the same pair of
wires.
4. Audio/visual power shall be provided by a separate supervised power circuit from the main fire alarm
control panel or from a supervised remote power supply.
5. The control module shall be suitable for pilot duty applications and rated for a minimum of 0.6 amps at 30
VDC.
1. Addressable Relay Modules shall be available to activate the motorized butterfly valve of water curtain
system. The relay shall be rated for a minimum of 2.0 Amps resistive or 1.0 Amps inductive. The relay coil shall be
magnetically latched to reduce wiring connection requirements, and to insure that 100% of all auxiliary relay may
be energized at the same time on the same pair of wires.
A. BATTERY:
2. Battery shall have sufficient capacity to power the fire alarm system for not less than twenty-four hours
plus 15 minutes of alarm upon a normal AC power failure.
3. The batteries are to be completely maintenance free. No liquids are required. Fluid level checks refilling,
spills and leakage shall not be required.
2. Shall be rated for fully charging a completely discharged battery within 48 hours while simultaneously
supplying any loads connected to the battery.
4. Shall have protection for overloads and short circuits on both AC and DC sides.
3.0 EXECUTION
3.1. INSTALLATION:
A. Installation shall be in accordance with the NEC, NFPA 72, local and state codes and as recommended by
the major equipment manufacturer.
B. All conduit, junction boxes, conduit supports and hangers shall be concealed in finished areas and may be
exposed in unfinished areas. Smoke detectors shall not be installed prior to the system programming and test
period. If construction is ongoing during this period, measures shall be taken to protect smoke detectors from
contamination and physical damage. Conduits shall be marked in color for easy identification OR colored conduits
shall be used.
C. All fire detection and alarm system devices, control panels and remote annunciators shall be flush
mounted when located in finished areas and may be surface mounted when located in unfinished areas.
3.2. TEST
Provide the service of a competent, factory-trained engineer or technician authorized by the manufacturer of the
fire alarm equipment to technically supervise and participate during all of the adjustments and tests for the
system.
1. Before energizing the cables and wires, check for correct connections and test for short circuits, ground
faults, continuity, and insulation.
2. Close each sprinkler system flow valve and verify proper supervisory alarm at the FACP.
4. Open initiating device circuits and verify that the trouble signal actuates.
5. Open signaling line circuits and verify that the trouble signal actuates.
6. Open and short notification appliance circuits and verify that trouble signal actuates.
11. Check installation, supervision, and operation of all intelligent smoke detectors during a walk test.
12. Each of the alarm conditions that the system is required to detect should be introduced on the system.
Verify the proper receipt and the proper processing of the signal at the FACP and the correct activation of the
control points.
13. When the system is equipped with optional features, the manufacturer's manual should be consulted to
determine the proper testing procedures. This is intended to address such items as verifying controls performed by
individually addressed or grouped devices, sensitivity monitoring, verification functionality and similar.
At the final inspection a factory-trained representative of the manufacturer of the major equipment shall
demonstrate that the systems function properly in every respect.
3.5. INSTRUCTION
A. Provide instruction as required for operating the system. Hands-on demonstrations of the operation of all
system components and the entire system including program changes and functions shall be provided.
B. The contractor and/or the systems manufacturer's representatives shall provide a typewritten "Sequence
of Operation."
C. The contractor / supplier should furnish the Operation and maintenance manuals along
with as built drawings in six sets of hard copies and a soft copy in CD.
GENERAL
The Fire Alarm system shall conform to IS 2189 in respect of design and installation, and it shall give Audio/visual
alarm signals when the Signals are transmitted form the Manual call points located at strategically at all escape
routes. The system shall give pin point location of fire with fore warning system zone or floor wise, two tone for
alert and voice communication for commands and instructions. Alternatively the main panel shall have the facility to
accommodate provision for (a) manual control of alarm (b) cut off facility of alarm in case of false alarm. The panel
shall also have selective audio facility for evacuation of particular zones and provision for floor/main control room
hook for communications.
The system shall be suitable to operate on 250 AC+10% or 24 volts DC. The design shall be modular so that
additional zones can be added to cater for large installations and to provide facility for future expansions up to 25%
more of present capacity. The system shall be fully supervised for all fault conditions with distinctive alarms operated
for fault and fire conditions. All audible alarms either for fire or fault conditions shall be push button cancellation
c. Normal conditions
d. Fire conditions
e. A.C.Mains Failure
A common fault meter shall be provided to indicate each of the 1 to 4 conditions, on the panel with push
button selection.
Dual tone hooter shall be of electronic type and shall give discontinuous / intermittent audible alarm
automatically whenever smoke detector operates. Hooter shall be complete with electronic oscillations, magnetic
coil (Sound coil) and accessories, ready for mounting (fixing);
Manual call point shall be of break glass type unit completely encased in a CRCA M.S. Sheet housing, with
provision for cable or conduit coupling. It shall have facility for voice communications for commands if required.
The Manual push button shall have the word prescribed in clear bold letters on facia window "In case of Fire
Break Glass". Installation of Manual push button shall be as per IS 2189. It shall be provided with a push button of
30V, 3 AMP rating and with 2 sets of NO & NC contacts. The manual push button shall be wall mounting type
and shall be provided with chain and hammer attached to it and shall be of weather proof type. The area of
Glass shall not be less than 30 sqmm.
The smoke detector shall work on dual chamber ionization principle to detect the products of combustion during
the incipient stage of fire i.e, to detect in its early stage by sensing visible and invisible products of smoke. The
radioactive sources shall be Americium 241 with max radioactive of 0.9 U micro curie. Each zone shall be
connected to the zonal or main control panel as called for by a multi core cable. Under fire condition, presence of
smoke shall trigger the circuit of the detector and shall send a signal to the control panel. Number of detectors
shall be connected in parallel to form a zone to cover larger areas. Coverage of one detector shall not be less than
50 sq.mts, of floor area. as per list of Fire officers committee, U.K. or Under writer’s laboratory U.S.A, or any other
international Testing Agency and also as included in the local fire body list
Heat Detectors shall be of Electro Pneumatic type working on two methods, ie., rate of rise and fixed
temperature. The rate of rise element shall be an air chamber, a flexible metal diaphragm and a moisture proof,
trouble proof vent, carefully calibrated to ignore any normal fluctuation in temperature, but to respond quickly
when the temperature rise is 9 degrees centigrade or more per minute. The fixed temperature feature should be
of bimetallic type. The operating temperature of fixed temperature element should be of bimetallic type. The
operating temperature of fixed temperature element should be factory set at 72 degrees C, +5 and respond to any
when the room temperature indicator facility and to be with two wire system on DC low voltage. It shall be
possible to loop the heat detectors with smoke detectors and Manual Push Button, in the same circuit. The area of
coverage per heat detector will depend upon structural configuration, but for flat ceiling and un-partitioned space.
It shall be 50 SQM. as per list of Fire officers committee, U.K. or Under writer’s laboratory U.S.A, or any other
international Testing Agency and also as included in the local fire body list.
Control panel in general shall conform to IS :2189. The panel shall be totally enclosed dust and vermin
proof type made of 16 gauge rust inhibited sheet with oven baked finish. The panel shall be of completely
solid state design. The primary function of control panel shall be to respond automatically to the operation of
one or more Manual call points to give fire alarm and to indicate area/areas, where the device has activated. The
operation of Manual call points shall result in alarm being given by the following :
The secondary function on the control panel shall be to indicate the faults within the system. An
immediate fault warning shall be given by an audible and visual signal on the control panel. A fault warning
shall be given in case of any of the following occurring :
a. Failure or disconnections of normal supply or stand by battery or low batter voltage beyond 5%.
There shall be one indicator for fire and one for fault in the control panel corresponding to each zone.
Each zone shall have two bulbs of fire fault indication. Each indicator shall be clearly labeled with zone no. and
inscribed with the "Code Name" i.e., words "FIRE" or "SERVICE". Separate indicator must be provided in green for
system stand by ON. etc. The control panel shall derive 230 volts power from normal supply. A stand by power
2.6 PRODUCTS
A. Complete maintenance and repair service for the fire alarm system shall be available from a factory
trained authorized representative of the manufacturer of the major equipment for a period of five (5) years after
expiration of the guaranty.
B. As part of the bid/proposal, include a quote for a maintenance contract to provide all maintenance, tests,
and repairs described below. Include also a quote for unscheduled maintenance/repairs, including hourly rates for
technicians trained on this equipment, and response travel costs for each year of the maintenance period. Rates
and costs shall be valid for the period of five (5) years after expiration of the guaranty.
C. Maintenance and testing shall be on a semiannual basis or as required by the facility maintenance team. A
preventive maintenance schedule shall be provided by the contractor, describing the protocol for preventive
maintenance. The schedule shall include:
1. Systematic examination, adjustment and cleaning of all detectors, manual fire alarm stations, Sounders,
strobe lights, voice alarm speakers, control panels, power supplies, relays, water flow switches, modules and all
accessories of the fire alarm system.
3. Each smoke detector shall be tested in accordance with the requirements of NFPA 72 Chapter 7.
A. The contractor shall have the ability to provide parts and labour to expand the system specified, if so
requested, for a period of five (5) years from the date of acceptance.
B. As part of the Bid, include a quotation for all parts and material, and all installation and test labor of
intelligent or addressable devices for ten percent (10%) as mentioned under spare parts list. This quotation shall
include intelligent smoke detectors, intelligent heat detectors, addressable manual stations, addressable monitor
modules and addressable modules equal in number to one tenth of the number required to meet this specification
(list actual quantity of each type).
C. Do not include cost of conduit or wire or the cost to install conduit or wire.
3.0 EXECUTION
3.1. INSTALLATION:
A. Installation shall be in accordance with the NEC, NFPA 72, local and state codes and as recommended by
the major equipment manufacturer.
B. All conduit, junction boxes, conduit supports and hangers shall be concealed in finished areas and may be
exposed in unfinished areas. Smoke detectors shall not be installed prior to the system programming and test
period. If construction is ongoing during this period, measures shall be taken to protect smoke detectors from
contamination and physical damage. Conduits shall be marked in color for easy identification OR colored conduits
shall be used.
C. All fire detection and alarm system devices, control panels and remote annunciators shall be flush
mounted when located in finished areas and may be surface mounted when located in unfinished areas.
D Manual Pull Stations shall be suitable for surface mounting or semiflush mounting and shall be installed
not less than 1200 mm above the finished floor.
E. Sounders cum strobes / strobes shall be suitable for surface / flush mounting and shall be installed at
2200 mm above the finished floor level.
F. All Voice alarm Speakers shall be ceiling mounted type round in shape (color / finish shall be as approved
by Architects / clients).
A. Actuation of any manual station, smoke detector / heat detector or water flow switch shall cause the
following operations to occur unless otherwise specified:
3. A smoke detector in any elevator lobby shall, in addition to the above functions, return all elevators to the
primary or alternate floor of egress
4. Smoke detectors in the elevator machine room or top of hoistway shall return all elevators in to the
primary or alternate floor. Smoke detectors or heat detectors installed to shut down elevator (if any) power and be
coordinated with the electrical contractor
5. Duct type smoke detectors shall, in addition to the above functions shut down the ventilation system or
close associated control dampers as appropriate.
Provide the service of a competent, factory-trained engineer or technician authorized by the manufacturer of the
fire alarm equipment to technically supervise and participate during all of the adjustments and tests for the
system.
1. Before energizing the cables and wires, check for correct connections and test for short circuits, ground
faults, continuity, and insulation.
2. Each of the alarm conditions that the system is required to detect should be introduced on the system.
Verify the proper receipt and the proper processing of the signal at the FACP and the correct activation of the
control points.
3. When the system is equipped with optional features, the manufacturer's manual should be consulted to
determine the proper testing procedures. This is intended to address such items as verifying controls performed by
individually addressed or grouped devices, sensitivity monitoring, verification functionality and similar.
4. Open initiating device circuits and verify that the trouble signal actuates.
5. Open signaling line circuits and verify that the trouble signal actuates.
6. Open and short notification appliance circuits and verify that trouble signal actuates.
10. Check presence and audibility of tone at all alarm notification devices.
11. Check installation, supervision, and operation of all intelligent smoke detectors during a walk test.
At the final inspection a factory-trained representative of the manufacturer of the major equipment shall
demonstrate that the systems function properly in every respect.
3.5. INSTRUCTION
A. Provide instruction as required for operating the system. Hands-on demonstrations of the operation of all
system components and the entire system including program changes and functions shall be provided.
B. The contractor and/or the systems manufacturer's representatives shall provide a typewritten "Sequence
of Operation."
C. The contractor / supplier should furnish the Operation and maintenance manuals along
With as built drawings in six sets of hard copies and a soft copy in CD.
1.0 OBJECTIVES
The main objective of the Public Address System is to convey clear and audible instructions to all the
people on all floors / buildings incase of occurrence of fire / other emergency to reach a place of safety in
the open, outside the buildings. The sound output should not be so loud that people nearest to the
speakers feel uncomfortable, nor so weak that people away cannot discern what is being broadcast. This
is achieved by working the system at 60 to 75% power output and distributing speakers uniformly all over
floor area.
The system will comprise of a microphone of suitable for voice communication / Announcements through speakers
on various floors/buildings. The system shall consist of :
b. Amplifiers
c. Speakers
The local control console shall be placed in the security blocks. Announcement shall be made from the security
room.
The control desk fabricated of sheet metal and designed to be mounted on table top and shall be located at
security room.
b. One gooseneck type moving coil / cardoid / hyper cardiod or equivalent microphone with ON/OFF switch.
c. Push switch buttons calling all the buildings with LED Indicator.
d. Push switch buttons, calling individually selected buildings with led indication.
h. Pre-amplifier with output connection to output transformer and a standby pre-amplifier should also be provided.
i. Monitor loudspeaker.
j. Volume unit meters (V.U.Meter) with red LED to flash if the input signal exceeds.
k. Push switch button for dual tone oscillator for testing the system
a. Amplifier shall necessarily have solid-state circuitry properly trivialized and capable of AC/DC operation.
This shall be able to drive low impendence speakers (2 to 16 ohms) and speakers with transformer for 100V/70V
systems. All amplifiers in the suitable racks located at respective Security rooms.
iii. Hum and noise level below rated output. All volume controls minimum 68 db. One microphone volume
and master volume control maximum - 60 db.
viii. Frequency response - over the entire speech and music range.
c. Amplifiers should be in a module of suitable Watts R.M.S only. Maximum 75% capacity should be used.
Amplifiers should have standard concealed controls.
d. Mains AC power supply input, D.C output and standby automatically supplying power in case of mains
failure, shall be provided.
e. The amplifiers rack shall be of mild steel with suitable anticorrosion protective coating. The rack shall
have provision for fixing to floor/wall.
g. The racks shall have lockable steel doors having proper ventilation slots for heat dissipation.
1.4 SPEAKERS
Wall mounted talk back speakers of 6 watts power rating on landings of staircases on all floors
1.4 CONDUITS
These shall be 16 swg mild steel, welded, thread type and having perfectly circular tubing and capable of being
cleaned and tight fitting joints. Conduits shall be laid either surface or in recess as required. All conduits / junction
/ fittings should be painted with approved color and shall be marked for easy identification.
1.6 WIRES
The wiring shall be approved make and PVC insulated copper multi strand as specified.
1.7 SAMPLES
The contractor shall submit the samples of all equipments for approval by architects / consultants before
installation.
F. FIRE EXTINGUISHERS
Fire extinguishers shall be in such a way that the occupants shall not travel more than 15m to reach a Fire
extinguisher. Also there shall be a Fire extinguisher for every 300 sq.m of floor plate / rooms of suitable type / size.
Fire extinguishers shall be on each landing of every floor, inside Electrical room, D.G. rooms, Meter rooms, RMU
and parking areas. In addition to above mention areas Extinguishers to be provided at Surface car parks, out door
Transformers / electrical instillations.
All Fire extinguishers shall be portable and hand held, a operating instruction should be pasted on the extinguisher
body.
Portable Fire extinguishers should be BIS approved and valid ISI certificates to be furnished at the time of delivery
to site.
G. SIGNAGE
Required, as per Local fire force like exit signs & Floor indication (Eg: Ground floor, 1 st floor..), size shall 200mm x
500mm & action chart ( size shall be 600mm x 1000mm) in case of fire / emergency, Staircase location indication
etc. The location / quantity shall be on each landing of every staircase on each floor.
Please refer the specimen BOQ format for the details to be printed on the Fire order boards.
SECTION - 6
MAKE OF EQUIPMENT
INTERVALVE
HAWA
FLOW
HAWA
/ BELLS CONTROL
MINIMAX / ARIHANT
MINIMAX / ARIHANT
MINIMAX / ARIHANT
MINIMAX
MINIMAX
VIJAY / EVERSAFE
/ LEVCON
MINIMAX
ENGINEERING/ELLINS / LOTUS
FINOLEX
STANDRD / PABASONIC
CABLE / WIRES
SHAKTHCAB / FINECORE
FINECORE / ANCHOR
HVAC
The system has been designed on the following basic design parameters, tenderer has to
verifythe design before quoting. Any discrepancy in the design, shall be discussed in the pre-
bid meeting :
The total calculated low side cooling load for the office space is estimated to be about 320 TR.
Indoor units shall wall mounted type/ Ceiling Suspended Cassette type /Ceiling Mounted
Ductable type
All the equipment and ancillary work shall conform to the technical specifications and
standardsof workmanship described in section 9.
Supply of Air Cooled Inverter type VRF unit, comprising with Rotary Compressor Unit by using R-
410A refrigerent. Unit shall be provided with micro processor based panel for sequential
starting of condensing units,coils, Electronic expansion valves,fins with specially factory coated
hydrophilic treatment for heat & rust corrossion.
The condensing unit shall be capable of assessing the requirement of liquid refrigerant
volumetric flow of each evaporating unit at all times by means of a sophisticated
microprocessor controller and generating the required total volume of refrigerant liquid for
supply to the evaporator units. The condensing unit shall be a factory-assembled unit housed in
a sturdy weatherproof casing constructed from rust proof galvanized powder coated steel
panels. The noise level of the unit shall not be more than 70dB (A) measured horizontally 1 m
away and 1.5 m above base level.
The compressors shall be hermetically sealed Inverter driven variable speed type scroll or
rotary type, capable of changing the capacity in accordance to the cooling load requirement.
The condenser coils shall be constructed out of copper tubes mechanically bonded to aluminum
fins. The surface of the condenser coil shall be coated with suitable chemical coating to prevent
deterioration due to coastal climate. All necessary safety devices shall be provided to ensure
safe operation of the system. Unit should be equipped with a highly efficient oil separation
system to ensure stable operation with long refrigerant piping. The VRF condensing unit shall
Each unit shall be selected as the requirement of the cooling load and interior. layout in the
respective space to be air-conditioned as specified in the Tender BOQ. The unit shall be
equipped with an electronic expansion valve, which can communicate with the VRF controller
in the condensing unit. The fan shall of the dual suction multi blade type and statically and
dynamically balanced to ensure low noise and vibration free operation. Each indoor unit shall
be equipped with cordless local control unit for setting the operating parameters. The address
of the indoor unit shall be set automatically in case of individual and group control. Option of
centralized control should also be achievable.
Controls shall be provided to maintain the set room temperature within close tolerance limits.
A Remote Control Unit shall be provided for the system, suitable to be mounted near the
entrance door of the premises. It should be possible to operate the entire air conditioning
system and set working parameters of all indoor units and the VRF outdoor unit from this
control unit. The unit shall be equipped with self-diagnosis for easy and quick maintenance and
service. The remote controller shall memorize the latest malfunction code for easy
maintenance. The controller shall be equipped with a battery back-up and a real time clock. It
should be possible to control several number of indoor units and change fan speed and angle of
swing flap individually and in group.
HRV unit for Fresh air supply with heat recovery from exhaust, consisting of fresh air blower,
exhaustblower, air to air, non- flammable, cross- flow heat exchanger, all housed in a sheet
metal cabinet dulyinsulated.
The panel shall be fabricated from high quality 14 gauge sheet, stiffened and suitably
reinforced. Thesteel sheet shall be painted with seven tank process& the final paint coat shall
All motor feeders above 7.5 KW shall be provided with ammeters. Indicating instruments shall
be tautbandtype only.
Minimum size of power wiring shall be 2.5 mm2 copper/4.0 mm2 aluminium. Control wiring
shall bedone with 2.5 mm2 stranded copper conductor, PVC insulated wires.All overload relay
shall be with built-in single phasing preventer. All spare contacts shall be wired upto terminal
block.
Circuit breakers and large isolating switches shall be positioned as far as possible below the
bus-barchamber to allow for ease of cabling. All equipment such as meters and indicating lights
shall belocated adjacent or on the unit with which these are connected to achieve a neat and
symmetrical
arrangement. Facility shall be provided for termination of all normal types of cables entering
fromabove and clamps shall be provided to support the weight of cables. Name plates to
indicate theequipment of circuit controlled by the switches shall be fixed on the panels.
NOTES:
. The VRF system’s Indoor and outdoor units shall be tested in accordance the provision of
ARIstandards, AHRI -1230 2009 for VRF System.
VRF SYSTEMS
1.0
Refrigerant
-Type (R-410)
-Qty. Charged
-Any additional control
or features provided
Refrigerant
-Type (R-410)
-Qty. Charged
-Any additional control
or features provided
2.0
I. GENERAL INFORMATION
maintenance spares
SIGNATURE __________________________
NAME __________________________
DESIGNATION __________________________
1 VRF System
2 HRV Unit
5 G.I. Sheets
7 Copper Piping
SIGNATURE __________________________
NAME __________________________
DESIGNATION __________________________
1. __________________________________ ________________________________
2. __________________________________ ________________________________
3. _________________________________ _______________________________
4. __________________________________ ________________________________
5. __________________________________ ___________________________
I, _______________________, certify that all the furnished data and information pertaining to
this offer arecorrect and are true representation of the equipment offered by our proposal
number_____________________ dated _____________.
I confirm that the plant offered has been designed to achieve performance as
per the design parameters andguarantee to achieve the same.
I confirm that I am duly authorized representative of the Bidder whose name appears below my
signature.
SIGNATURE __________________________
NAME __________________________
DESIGNATION __________________________
The refrigerant piping interconnecting to indoor & outdoor units shall be made out of hard
copper tubes, in brazed construction. The refrigerant line sizing should be designed to achieve
minimum pressure drop and avoid oil return problem. The pipe sizes and connections shall be
designed such that the evaporator units do not face back pressure due to the functioning of the
evaporator next to it. All suction piping shall be insulated with closed cell elastomeric class ‘O’
nitrile rubber foam tubes of suitable diameter and thickness. All piping shall be neatly laid and
supported on galvanized perforated sheet metal trays and clamped firmly. Piping should be
shrouded, where necessary, to protect it from accidental damage/leaks during work by any
agencies. All the wiring interconnecting the indoor and outdoor units shall be PVC insulated
copper conductor flexible wires of appropriate rating, and shall be laid through PVC conduits.
The refrigerant piping for the VRF system shall be of minimum wall thickness as per Copper
pipe- ASTM B88, L-Type standard HARD drawn copper pipes. The copper pipe shall be
internally chemically cleaned, free of dirt, dust, oxidation and any other deposits. All joints shall
be made by brazing. Inert gas purging shall be used during the brazing process to prevent
oxidation Suction line shall be insulated with 19mm thick sleeve made out of closed cell
elastomeric nitrile rubber foam insulation of fire retardant ‘O’ class. Wiring interconnecting the
indoor and outdoor unit shall be done with PVC insulated copper conductor flexible wires of
appropriate rating. U-bends shall be provided for efficient oil return in suction line, at
appropriate locations. All piping shall be supported on GI perforated cable trays, and covered
by GI sheet channels from the top, to prevent accidental damage during work of other
agencies. The GI covers and trays shall be fixed to MS angle supports by bolting, to facilitate
removal of the trays for verification of pipe leaks. All pipe supports/clamps shall be painted
with red oxide primer followed by 2 coats of synthetic enamel finish paint.
The piping and wiring shall be laid such that it does not spoil the aesthetics of the premises, and
is safe, secure and approachable for leak detection/repair/replacement.
1. SCOPE
The scope of this section will cover supply fabrication, installation and testing of all sheet metal
ductsand diffusers and balancing thereof in accordance with these specifications, general
arrangement shownon the Drawings and Bill of quantities.
All ductwork including straight sections, tapers, elbows, branches, shores, collars, terminal
boxes andother transformation pieces( except pieces to suit may be made at site ) must be
factory fabricatedwithin the following parameters :
Raw Material
3. Dampers
All dampers shall be of robust construction and tightly fitting. The design, method of handling,
andcontrol shall be suitable for the location and service required.Dampers shall be provided
with suitable links, levers and quadrants as required for their properoperation. Control or
setting devices shall be made robust, easily operable and accessible throughsuitable access
doors in the ducts. Every damper shall have an indicating device clearly showing thedamper
position at all times.Dampers shall be placed in ducts and at every branch supply or return air
duct connection, whether ornot indicated on the drawings, for the proper volume control and
4.Acoustic Treatment
The material for acoustic treatment of ducts, shall be resin bonded fibre glass, as described
earlier,conforming to I.S. 8183 of 1976. The density of fibre glass shall be 32 kg/cub.m and the
material shallbe in the form of boards of uniform density. The ‘k’ value at 10oC shall not be less
than 0.03 W/mK.Facing shall be provided with 0.5 mm perforated aluminium sheet held with
G.I. Nuts bolts or nailed tothe batten work as required.
5.Material Specifications
Ducts shall be made out of galvanized steel sheets of ducting quality. The galvanized sheet shall
havethickness as specified below and zinc coating of minimum 120 gms/sqm.
Fabrication of Ducts
at 1.2m centers.
at 1.2m centers.
at 1.2m centers.
Up to 750 2.4 40 x 40 x 3 10
Duct hangers shall be fixed to R.C.C. slab of the roof by means of anchor fasteners and M.S.
anglecleats. Hangers for ducts running below pitched sheet roof shall be fixed to M.S. angle
cleats weldedto roof structure. Soft neoprene rubber gasket of uniform thickness and width
shall be used as gasketbetween flange joints. The gasket will be fixed with a suitable adhesive
to the flange.
Galvanized hexagonal full threaded nut-bolts of minimum 6mm dia. shall be used for fastening
theflanges. Spacing between two nut-bolts shall not exceed 125mm.All ducts shall be rigid and
shall be adequately supported and braced where required with crossbreaking of M.S. angle
bracings of ample size to keep the ducts true to shape and to prevent buckling,vibration or
breathing.
Ducting over false ceiling shall be supported independently from the roof structure above. In no
casea duct shall be supported from the false ceiling hangers or be permitted to rest on a hung
ceiling.Bottom level of all ducts should be maintained as shown in the drawing. Leveling of
ducts should be
Fans shall be connected to duct work by a double canvass sleeve. Each sleeve shall be
minimum150mm long, securely bolted to duct and units. Each sleeve shall be made smooth and
the connectingduct work rigidly held in line with unit inlet or outlet.
The supply and return air grills and ceiling diffusers shall be made of powder
coated extruded aluminium sections. The supply air grills/ diffusers shall be
provided with screw operated opposed blade volume control device made of
The linear continuous supply/return air grills shall be made of powder coated
extruded aluminium construction with fixed horizontal bars. The thickness of fixed
bar louvers shall be 5mm in front and the flange shall be 20mm wide with round
edges. The register shall be suitable for concealed fixing and horizontal bars of
the grills shall mechanically crimped from the back to hold them.
The colour of grills shall be as per the approval of the Engineer in Charge. The
The fresh air intake louvers atleast 50 mm deep will be made of powder coated
pitch to minimise water ingress. The lowest blade of the assembly shall be
Insulation Material: Closed Cell elastomeric Nitrile Rubber foam, Fire retardant class’O’
Application Procedure:
Clean the surface of the duct to be insulated free from dust grease and other matter.Prepare
the pieces of sheet as per the dimensions of the duct and apply the adhesive on the duct
surface,the sheet surface as well as the edges of the sheets & leave it for 2-3 minutes for
drying.Once the adhesive is half dry and tacky, bring both the ends of insulation where the
adhesive is appliedin contact and stick them well. Ensure that both the surfaces are matched
properly.Apply self adhesive black cotton tape on all the joints. Before fixing the tapes it must
be ensured thatall the joints are sealed properly.
Clean the surface of the pipe to be insulated free from dust grease and other matter.
Prepare the pieces of sleeve as per the dimensions of the pipe and slide the sleeve or pipe.
Sleeveshould fit tightly over the pipe with no air gap.
Apply the adhesive on the ends of rubber sleeves & leave it for 2-3 minutes for drying. Once
theadhesive is half dry and tacky, bring both the ends of sleeves where the adhesive is applied
in contactand stick them well. Ensure that both the surfaces are matched properly.
Apply self-adhesive black cotton tape on all the joints. Before fixing the tapes it must be
ensured thatall the joints are sealed properly.
The panel shall be fabricated from high quality 14 gauge sheet, stiffened and suitably
reinforced. Thesteel sheet shall be painted with seven tank process& the final paint coat shall
be stove enamelled. Thehousing shall be of sectionalized construction with space provided for
All motor feeders above 7.5 KW shall be provided with ammeters. Indicating instruments shall
be tautbandtype only.
Minimum size of power wiring shall be 2.5 mm2 copper/4.0 mm2 aluminium. Control wiring
shall bedone with 2.5 mm2 stranded copper conductor, PVC insulated wires.
All overload relay shall be with built-in single phasing preventer. All spare contacts shall be
wired upto terminal block.
Circuit breakers and large isolating switches shall be positioned as far as possible below the
bus-barchamber to allow for ease of cabling. All equipment such as meters and indicating lights
shall belocated adjacent or on the unit with which these are connected to achieve a neat and
symmetrical
arrangement. Facility shall be provided for termination of all normal types of cables entering
fromabove and clamps shall be provided to support the weight of cables. Name plates to
indicate theequipment of circuit controlled by the switches shall be fixed on the panels.
The work shall be carried out in accordance with specification of Indian Electricity Rules as
amendedup to date and local Municipal Bye-Laws.
The power wiring system shall be suitable for 415V, 3 phase, 50 cycles, 4 wire supply. Wiring
formotors shall be carried out in PVC sheathed and steel wire or tape armored cable.
The control wiring shall be in PVC insulated and PVC sheathed, multi core, stranded copper
cable(minimum 1.5 mm2 Cu) with the required number of cores.
Power cables and wire shall be of copper or aluminum of 1100 V grade, control wires of copper
660 Vgrade and shall confirm to IS: 1554 / IS: 694.
Cables shall be carried on walls or in racks or in cable trays suspended from hangers or laid in
trenchesas required. Where more than one cable is running, proper spacing shall be provided
to minimize theloss in current carrying capacity.
Where cables pass through pipes, PVC/Neoprene rubber bushes shall be provided at the ends.
Wherecables pass through floors or walls, pipe inserts shall be provided and opening shall be
sealed.
Cables shall terminated using weather proof double compression brass nickel plated cable
glands andtinned copper crimped lugs shall be provided.
Conduits, where used, shall be of heavy gauge PVC. Metal saddles of approved type shall be
used forfixing conduits on surface. Bends and elbows shall be of inspection type where
required. All jointsshall be water tight. Conduits shall be secured to the switches, junction boxes
etc., by threaded
couplers. Flexible PVC conduits shall be used for connections with vibrating equipment.Suitable
means to isolate each motor in case of emergency shall be provided as per IS:900.
The main panel shall be connected to the main earthing stations by means of G.I. Strips as per
Indianelectricity rules and IS: 3043 - 1987.
All electrical equipment shall be provided with two separate earth connections. The current
carryingcapacity of earth conductors shall be as per IS: 3043-1987.
All equipment, ducts, pipes etc. shall be painted by the following colour code with 1 coat of
primer and2 coat of good quality enamel paint
All painting works shall form part of the cost of equipment, piping etc. No separate payment
shall beapplicable.
Before commissioning of the equipment the entire installation shall be tested in accordance
withIndian Electricity Rules and IS: 732 and the Test Report of a licensed electrical contractor
shall befurnished.
On Commissioning of the HVAC System, the following parameters shall be tested by the
HVACContractor under full load conditions, to confirm compliance with the data furnished
earlier andachievement of specified room conditions. All readings to be taken every 2 hours
during 12 hourscontinuous operation, for 4 days:
1. Balancing:
2. Room Conditions:
Room conditions in each A/C Area to be recorded under full load conditions.
Corresponding ambient conditions should also be recorded.
Uniformity of temperature
Air CFM
Air Inlet / Outlet Temperature
Power Consumption
Corresponding Ambient Conditions
Suction Pressure
CFM
SP
Power Consumption
Noise Level & Vibrations (should not be objectionable)
NOTES:
1. After completing air & refrigerant-side balancing, the HVAC Contractor shall carry out
testing of theentire HVAC System; and submit specified test results to Consultant in a Test
Results Format preapprovedby the HVAC Consultant. After carrying out
modifications/balancing/corrections (as required),the Contractor shall carry out final testing in
the presence of representatives of IPR & the Architect KGA.
2. The VRF system’s Indoor and outdoor units shall be tested in accordance the provision of
ARIstandards, AHRI -1230 2009 for VRF System.
3. In addition to the initial testing of the System on commissioning, two subsequent tests shall
be carried outonein the following summer and the second in the following monsoon.
4. Noise level & vibrations of all equipment shall be within acceptable limits appropriate for the
application& use of the Area.
5. All the instruments, special test materials (e.g. Nitrogen gas, helium gas for VAC) required for
Testing
7. In addition to the above, tests & measurements specified in Technical Specifications of the
respectiveequipment shall also be performed, and test-results thereof submitted.
1. Terrace level layout including outdoor units, ducts, refrigerant piping, fresh air &
exhaust air, HVAC power panels, etc.
2. SA & RA ducting layout for each floor/level including diffusers/grilles coordinated
with lighting, false ceiling & equipment layout, other services, etc. with indoor
units details
3. HVAC plan & sections
4. Schematic refrigerant piping
5. Schematic electrical drawing
6. GA drawing of panel boards
7. Requirements of civil work (pedestals, foundations, cutouts, structural
supports/platforms, etc),drain, electrical power, etc.
8. Requirements of electrical power on schematic & layout drawings
SIGNATURE __________________________
NAME __________________________
Organization chart giving details of partners/executives and engineers, who will look after the
sales,project execution and site supervision for this project.
SIGNATURE __________________________
NAME __________________________
DESIGNATION __________________________
5 G.I. Sheets
6 Nitrile Rubber Foam
Insulation
7 Copper Piping
8 Metallic Grid Ceiling
9 G.S. Tiles for Grid Ceiling
SIGNATURE __________________________
NAME __________________________
DESIGNATION __________________________
1. __________________________________ ________________________________
2. __________________________________ ________________________________
3. __________________________________ ________________________________
4. __________________________________ ________________________________
5. __________________________________ ________________________________
6. __________________________________ ________________________________
I, _______________________, certify that all the furnished data and information pertaining to
this offer arecorrect and are true representation of the equipment offered by our proposal
number_____________________ dated _____________.
I confirm that the plant offered has been designed to achieve performance as per the design
parameters andguarantee to achieve the same.
I confirm that I am duly authorized representative of the Bidder whose name appears below my
signature.
SIGNATURE __________________________
NAME __________________________
DESIGNATION __________________________
Sl.
No. Short Title B.I.S Number
I. CEMENT
Specification
1 to ordinary Portland cement 33 grade (4th Rev) 269-1989
Specification
2 for Portland Pozzolana Cement 1489-1976
Portland
3 Slag Cement (Fourth revision) 455-1989
Method
4 for physical tests for hydraulic cement (Reaffirmed 1980) 4031-1968
Method
5 of Chemical analysis for hydraulic cement (First revision) 4032-1985
Hydrophobic
7 Portland cement 8043-1978
High Strength
8 ordinary Portland cement 8112-1976
II. AGGREGATES
Specification
1 for coarse and fine Aggregates from natural source for 383-1970
concrete (Second Revision)
Specification
2 for sand for masonry mortars 2116-1965
Method
3 of Tests for aggregates for concrete 2385-1969 (Part- I
to Part- VIV)
Standard
4 sand for testing of cement (First revision) with 650-1966
amendment 1 and 2 Reaffirmed 1980
Methods
5 for sampling of aggregates for concrete 2430 -1969
III. STEEL
Specification
2 for cold worked steel deformed bars for concrete 1786-1979
reinforcement
Code 3of practice for welding of MS Bars used for reinforced 2751-1966
concrete construction.
Code 4for practice for use of Metal are welding for general 818-1989
construction of mild steel
Deformed
5 bars for concrete reinforcement hot rolled mild steel and 1139-1966
medium tensile steel (Revised)
Recommendations
6 for detailing of reinforcement in reinforced 5525-1969
concreted works
Specification
7 for Mild Steel and medium tensile steel Bars for 432-1966(Part I)
Concrete reinforcement.
Code 8for practice for safety and health requirement in Electric and 818-1968
Gas welding and cutting operations
Code 9for practice for fire precautions in welding and cutting 3016-1965
operation.
Code of procedure for manual or metal ARC and welding of Mild 823-1964
steel
Specification for filler rods and wires for gas welding 1278-1972
Hard drawn
1 steel wire fabrics for concrete reinforcement 1566-1982
IV. CONCRETE
Method
1 of Measurement of building and Civil Engineer work Part-II 1200-1968
cement concrete works.
(Part-II)
Specification
3 for pre cast concrete coping blocks. 5751-1969
Methods
4 of tests for strength of concrete 516-1959
Code 5of practice for laying in situ cement concrete lining on canals 3873-1993
Specification
6 for Admixtures for concrete 9103-1979
Method
7 of Test for Autoclaved cellular concrete products. 6441-1972-73
(Part-I to IX)
Method
8 of Sampling and Analysis of concrete 1199-1959
Specification
9 of Batch type concrete mixtures (Second Revision) 1791-1968
Specification for fly ash for use as pozzolana as admixture for 3812-1981
Concrete
(Part-II)
Specification for Portable swing weigh batch for concrete (single 2722-1964
and double bucket type)
General requirement for concrete vibrator screed board type (First 2506-1985
revision)
Code of practice for concrete structures for shortage of liquids 3370 (Part-1 to 4)
Specification
3 for admixtures for concrete (First Revision) 9103-1999
Method
1 of Measurement of building and Civil Engineering 1200-1969
Code 5of practice for protection of slope for Reservoir embankment 8237-1985
Guidelines
7 for lining of canals in expansive soils 9451-19
Method
8 of test for soils Part-II Determination of water concrete 2720-1973
(Part-II)
Method9 of test for soils Determination of water content dry density 2720-1974
relation using light compaction.
(Part-VII)
Safety code for blasting and related drilling operation with 4081-1967
Amendment No. I (Reaffirmed 1978)
Guidelines for design of under seepage control measures for earth 8414-1977
and rock fill dams
Guidelines for design of large earth and rock fill dams 8826-1978
(Part-1 to V)
Detonators 7632-1975
Method for standard penetration test for soil (first revision) 2131-1981
(Part-I of 1967)
(Part-1 of 1969)
Safety
1 code for scaffolds and ladders part I scaffolds 3696-1966
Safety
2 code for scaffolds and ladders Part 2 ladders. 3696-1966
(Part-II)
Recommendation
3 s on stacking and storage of construction materials at site. 4082-1977
Plywood
4 for general purposes ( Second revision amendment 1 to 3) 303-1975
Code
6 practice for under drainage of lined canals (2nd revision) 4558-1995
Code
7 of for practice for in situ permeability test 5529 (Part-1 & 2)
Structural
8 steel (Standard quality) (with amendment No.1 to 3) IS: 226-1975
Hard
9 drawn steel wires (Third revision) IS: 432-1982
(Part-II)
Concrete pipes (with and without reinforcement) (2nd revision) IS: 458-1971
Specification for mild steel tubes, tubular and other wrought Steel fittings Part-I mild steel IS:1239-1979
tubes (fourth revision) (With Amendments No. 1 to 5)
Hard drawn steel wire fabric for concrete reinforcement (Second revision) IS: 1566-1982
Preformed filler for expansion test in concrete payment and structures (non extruding and IS: 1838-1961
resilient type)
Cast iron detachable joints for use with asbestos cement pressure pipes. IS:8794-1978
Code of practice for laying of cast iron pipe (With amendment No. I) IS: 3114-1965
Rubber sealing rings for gas mains water mains and sewers IS: 5382-1969
Centrifugally cast (spun) iron low pressure pipes for water gas and sewage (First revision) IS: 6163-1978
Code of practice for laying of asbestos cement pressure pipes IS: 6530-1972
Cast iron detachable joints for use with asbestos cement pressure pipes IS: 8794-1978
Other Publications: Ministry of shipping and transport Specification for Road and Bridge No. 7900
works
Paving
1 bitumen (revised) (with Amendment No.1) IS: 73-1961
Cut back
2 bitumen (Revised) IS: 217-1982
Glossary
3 of terms relating to bitumen and tar(2nd revision) IS:454-1961
Digboi
4 type cut back bitumen (revised) IS: 454-1961
Distributors
5 for hot tar and bitumen (first revision) IS: 2093-1974
Heaters
6 for tar and bitumen (first revision) IS: 2094-1974
Bitumen
8 emulsion for roads (anionic type) IS: 3117-1965
Asphalt
9 pavers’ finisher (first revision with amendment No.1) IS: 3251-1965
Method of test for determining aggregates impact value of soft coarse IS: 5640-1970
aggregates.
Safety code for construction involving use of hot bituminous materials. IS: 5916-1970
Method of test for determination of stripping value of road aggregates. IS: 6241-1971
Coarse aggregates for water bound macadam (first revision) IS: 6579-1981
Method for testing tar and bituminous materials Determination of effect of heat IS: 9382-1979
and air by thin film over test.