8 IRC Grade-I Metal ( 90mm to 45 mm) 530.00 134.00 664.00 50.40 714.40
9 IRC Grade-II Metal ( 63mm to 45 mm) 588.00 134.00 722.00 50.40 772.40
10 IRC Grade-III Metal ( 53mm to 22.4mm) 636.00 134.00 770.00 50.40 820.40
Certified that the lead have been provided in this estimate above are correct & minimum to the best of
my knowledge.
Junior Engineer Asst.Engineer Block Dev. Officer
Nabarangpur Block Nabarangpur Block Nabarangpur Block
Analysis of Rates 2009 for 8 hour of work.
1 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Data for 100 Cum
Man Mulia 21.50 Nos @ 90.00 Per No Rs 1935.00
Woman mulia 21.50 Nos @ 90.00 Per No Rs 1935.00
T & P , Sundries 2% Rs 77.40
Grand Total Rs 3947.40 Per 100 Cum
Grand Total Rs. 3947.40 Per 100 Cum
2 E/W in excavation in hard soil in Foundation with initial lead & lift
including rough dressing & breaking clods etc. complete.
Data for 100 Cum
Rate as per Item No.1 I.e Rs. 3947.40
Add 20% extra Lbour for excavation of Foundation Rs. 774.00
Grand Total Rs. 4721.40 Per 100 Cum
3 Filling the foundation & the plinth with excavated earth well
watered & rammed completely 2/3rd rate of the earth work in hard soil Rs. 2631.60 Per 100 Cum
4 Filling the Foundation & plinthwith sandwith well watered & rammed
etc. complete.
Filling Sand 1.00 Cum @ 193.00 Per Cum Rs. 193.00
Man Mulia 0.1236 Nos @ 90.00 Per No Rs. 11.12
T & P , Sundries 2% Rs. 4.08
Grand Total Rs. 208.21 Per Cum
5 RR stone massonary in sand grouted using stone other than granite
in F & P including all cost , conveyance , royality etc. complete.
Materials
Stone other than Granite 1.00 Cum @ 340.40 Per Cum Rs 340.40
Filling Sand 0.24 Cum @ 193.00 Per Cum Rs 46.32
Labour
Masson 2nd Class 1.41 Nos @ 116.00 Per No Rs 163.56
Man Mulia 1.06 Nos @ 90.00 Per No Rs 95.40
Woman Mulia 1.41 Nos @ 90.00 Per No Rs 126.90
Grand Total Rs. 772.58 Per Cum
6 RR stone massonary in sand grouted using granite stone
in F & P including all cost , conveyance , royality etc. complete.
Materials
RRHG stone 1.00 Cum @ 407.40 Per Cum Rs 407.40
Filling Sand 0.24 Cum @ 193.00 Per Cum Rs 46.32
Labour
Masson 2nd Class 1.41 Nos @ 116.00 Per No Rs 163.56
Man Mulia 1.06 Nos @ 90.00 Per No Rs 95.40
Woman Mulia 1.41 Nos @ 90.00 Per No Rs 126.90
Grand Total Rs. 839.58 Per Cum
7 RR stone massonary in CM (1:6) to the F&P including all
cost,conveyance,royality etc. complete.
Materials
RRHG stone 1.00 Cum @ 407.40 Per Cum Rs 407.40
Sand for mortar 0.34 Cum @ 196.00 Per Cum Rs 66.64
Cement 0.8151 Qtl @ 553.90 Per Cum Rs 451.48
Labour
Masson 1st Class 0.35 Nos @ 129.00 Per No Rs 45.15
Masson 2nd Class 1.41 Nos @ 116.00 Per No Rs 163.56
Man Mulia 1.76 Nos @ 90.00 Per No Rs 158.40
Woman Mulia 1.41 Nos @ 90.00 Per No Rs 126.90
Grand Total Rs. 1419.53 Per Cum
T & P , Sundries 2% 5.71
1425.24
8 CC (1:4:8) using 4 cm size hbg metal including all cost, conveyance
royality etc complete.
Materials
Hbg metal 40 mm size 0.96 Cum @ 694.40 Per Cum Rs 666.62
Sand for Mortar 0.48 Cum @ 196.00 Per Cum Rs 94.08
Cement 1.72 Qtl @ 553.90 Per Qtl Rs 952.71
Labour
Masson 2nd Class 0.18 Nos @ 116.00 Per No Rs 20.88
Man Mulia 2.50 Nos @ 90.00 Per No Rs 225.00
Woman Mulia 1.40 Nos @ 90.00 Per No Rs 126.00
Rs. 2085.29 Per Cum
T & P , Sundries 2% Grand Total 2092.31
Add 15% extra labour charges for 1st floor Rs 55.78
Grand Total Rs. 2148.09 Per Cum
9 CC (1:3:6) using 4 cm size hbg metal including all cost, conveyance
royality etc complete.
Materials
Hbg metal 40 mm size 0.96 Cum @ 694.40 Per Cum Rs 666.62
Sand for Mortar 0.48 Cum @ 196.00 Per Cum Rs 94.08
Cement 2.29 Qtl @ 553.90 Per Qtl Rs 1268.43
Labour
Masson 2nd Class 0.18 Nos @ 116.00 Per No Rs 20.88
Man Mulia 2.50 Nos @ 90.00 Per No Rs 225.00
Woman Mulia 1.40 Nos @ 90.00 Per No Rs 126.00
Grand Total Rs. 2401.02 Per Cum
10 CC (1:4:8) using 4 cm size cbg metal including all cost, conveyance
Labour
Masson 1st Class 0.13 Nos @ 129.00 Per No Rs 16.77
Man Mulia 0.14 Nos @ 90.00 Per No Rs 12.60
Woman Mulia 0.22 Nos @ 90.00 Per No Rs 19.80
Grand Total Rs. 120.74 Per Cum
T & P , Sundries 2% 0.65
Add 5% extra labour charges for 1st floor Rs 2.46
Grand Total Rs. 123.85 Per Cum
24 2.50 CmM thick Damp proof course in CC (1:2:4) using 12 mm size hbg
Chips including all cost , conveyance , royality etc. complete
Materials
Hbg Chips 12 mm size 0.023 Cum @ 943.40 Per Cum Rs 21.70
Sand for Mortar 0.012 Cum @ 196.00 Per Cum Rs 2.35
Cement 0.0754 Qtl @ 553.90 Per Qtl Rs 41.76
Labour
Masson 1st Class 0.103 Nos @ 129.00 Per No Rs 13.29
Man Mulia 0.36 Nos @ 90.00 Per No Rs 32.40
Grand Total Rs. 111.50 Per Sqm
Add 5% extra labour charges for 1st floor Rs 2.28
Grand Total Rs. 113.79 Per Sqm
25 Rough stone dry packing in appron & rivetment using
Hard stone ( 15 cm to 30 cm size ) including all cost , conveyance
royality etc. complete
Material
Hard stone 1.00 Cum @ 340.40 Per Cum Rs 340.40
Labour
Masson 1st Class 0.17 Nos @ 129.00 Per No Rs 21.93
Stone packer 0.35 Nos @ 103.00 Per No Rs 36.05
Man Mulia 0.52 Nos @ 90.00 Per No Rs 46.80
Woman Mulia 0.52 Nos @ 90.00 Per No Rs 46.80
Grand Total Rs. 491.98 Per Cum
26 Rough stone dry packing in appron & rivetment using
RRHG stone ( 15 cm to 30 cm size ) including all cost , conveyance
royality etc. complete
Material
RRHG stone 1.00 Cum @ 407.40 per Cum Rs 407.40
Labour
Masson 1st Class 0.17 Nos @ 129.00 Per No Rs 21.93
Stone packer 0.35 Nos @ 103.00 Per No Rs 36.05
Man Mulia 0.52 Nos @ 90.00 Per No Rs 46.80
Woman Mulia 0.52 Nos @ 90.00 Per No Rs 46.80
Grand Total Rs. 558.98 Per Cum
27 White washing 2 coats with shell lime un slaked
(Data for 93 Sqm)
Material
Shell Lime un slaked 18.66 Kg @ 16.00 per kg Rs 298.56
Labour
Masson 2nd Class 1.00 Nos @ 116.00 Per No Rs 116.00
Man Mulia 0.75 Nos @ 90.00 Per No Rs 67.50
Grand Total Rs. 482.06 Per Sqm
Rate per 1 Sqm Rs 5.18 Per Sqm
Add 3% extra labour charges for 1st floor Rs 0.06
Grand Total Rs. 5.24 Per Sqm
36 labour for Soling road surface with soling stone including filling
the interstics with earth & rolling with HRR excluding cost &
conveyance of soling stone.
Data for 2.83 Cum
Labour
Stone Packer 0.50 Nos @ 103.00 Per No Rs 51.50
Man Mulia 0.50 Nos @ 90.00 Per No Rs 45.00
Woman Mulia 2.50 Nos @ 90.00 Per No Rs 225.00
Add 2% for T&P, Sundries Rs 6.43
Grand Total Rs. 327.93 Per 2.83 Cum
Rate per 1 Cum Rs. 115.88 Per Cum
37 Fixing Tiles in floor,treads ,steps & laying in 25 mm thick bed of cement mortar
( 1:1) jointed with neat slurrymixed with pigment to match the shade of the
tiles including rubbing & polishing complete excluding cost of precast tiles.
Data for 10 Sqm
Materials
Cement 1.8570 Qtl @ 553.90 Per Qtl Rs 1028.59
Cement for slurry 0.4400 Qtl @ 553.90 Per Qtl Rs 243.72
Cement for grouting 0.4400 Qtl @ 553.90 Per Qtl Rs 243.72
Sand 0.1300 Cum @ 196.00 Per Cum Rs 25.48
Labour
Masson 1st Class 2.16 Nos @ 129.00 Per No Rs 278.64
Semi-Skilled Mulia 5.50 Nos @ 103.00 Per No Rs 566.50
Mulia 2.16 Nos @ 90.00 Per No Rs 194.40
Grand Total Rs. 2581.04 Per 10 Sqm
Rate per 1 Sqm Rs. 258.10 Per Sqm
Add for wax Polishing Rs 8.50 Per Sqm
Total Rs 266.60 Per Sqm
38 Fixing Tiles in dados skirting& risers of steps on 12 mm thick cement plaster
( 1:3) jointed with neat slurrymixed with pigment to match the shade of the
tiles including rubbing & polishing complete excluding cost of precast tiles.
Data for 10 Sqm
Materials
Cement 0.7150 Qtl @ 553.90 Per Qtl Rs 396.04
Cement for slurry 0.6600 Qtl @ 553.90 Per Qtl Rs 365.57
Sand 0.1500 Cum @ 196.00 Per Cum Rs 29.40
Labour
Masson 1st Class 3.25 Nos @ 129.00 Per No Rs 419.25
Semi-Skilled Mulia 7.60 Nos @ 103.00 Per No Rs 782.80
Mulia 3.25 Nos @ 90.00 Per No Rs 292.50
Grand Total Rs. 2285.56 Per 10 Sqm
Rate per 1 Sqm Rs. 228.56 Per Sqm
Add for wax Polishing Rs 8.50 Per Sqm
Total Rs 237.06 Per Sqm
Junior Engineer Asst. Engineer Block Development Officer
Papadahandi Block Papadahandi Block Papadahandi Block
Labour
Masson 2nd Class 0.18 Nos @ 116.00 Per No Rs 20.88
Man Mulia 2.50 Nos @ 90.00 Per No Rs 225.00
Woman Mulia 1.40 Nos @ 90.00 Per No Rs 126.00
Grand Total Rs. 2085.29 Per Cum
6 RCC of M-20 grade using 20 mm & down grade hard granite
Cbg Chips 12 mm size including all cost , conveyance
royality etc. complete.( Data for 15 Cum )
Materials
Cbg Chips 20 mm size 8.10 Cum @ 1092.40 Per Cum Rs 8848.44
Cbg Chips 10 mm size 5.40 Cum @ 1176.40 Per Cum Rs 6352.56
Sand for Mortar 6.75 Cum @ 196.00 Per Cum Rs 1323.00
Cement 52.10 Qtl @ 553.90 Per Qtl Rs 28858.19
Labour
Masson 2nd Class 1.50 Nos @ 116.00 Per No Rs 174.00
Man Mulia 20.00 Nos @ 90.00 Per No Rs 1800.00
Machinery
Concreete Mixer ( Cap 0.40 / 0.28 Cum )
6.00 Hrs @ 161.00 Hr Rs 966.00
Generator 33 KVA 6.00 Hrs @ 240.00 Hr Rs 1440.00
Grand Total Rs. 49762.19 Per Cum
Rate per 1 Cum Rs 3317.48 Per Cum
7 WBCB in CM (1:6) in superstructure including all cost, conveyance
royality etc complete.
Materials
WBCB brick 1.00 Cum @ 1053.84 Per Cum Rs 1053.84
Sand for Mortar 0.28 Cum @ 196.00 Per Cum Rs 54.88
Cement 0.672 Qtl @ 553.90 Per Qtl Rs 372.22
Labour
Masson 1st class 0.35 Nos @ 129.00 Per No Rs 45.15
Masson 2nd Class 1.05 Nos @ 116.00 Per No Rs 121.80
Man Mulia 1.55 Nos @ 90.00 Per No Rs 139.50
Woman Mulia 1.41 Nos @ 90.00 Per No Rs 126.90
Add extra towards extra labour & scaffolding Rs 33.00
Grand Total Rs. 1947.29 Per Cum
8 16 mm CP in CM (1:6) including all cost , conveyance , royality
etc. complete. Materials
Sand for Mortar 0.018 Cum @ 196.00 Per Cum Rs 3.53
Cement 0.043 Qtl @ 553.90 Per Qtl Rs 23.82
Labour
Masson 2nd Class 0.16 Nos @ 116.00 Per No Rs 18.56
Man Mulia 0.13 Nos @ 90.00 Per No Rs 11.70
Woman Mulia 0.11 Nos @ 90.00 Per No Rs 9.90
Grand Total Rs. 67.51 Per Sqm
9 20 mm CP in CM (1:6) including all cost , conveyance , royality
etc. complete.
Materials
Sand for Mortar 0.021 Cum @ 196.00 Per Cum Rs 4.12
Cement 0.057 Qtl @ 553.90 Per Qtl Rs 31.57
Labour
Masson 2nd Class 0.16 Nos @ 116.00 Per No Rs 18.56
Man Mulia 0.13 Nos @ 90.00 Per No Rs 11.70
Woman Mulia 0.11 Nos @ 90.00 Per No Rs 9.90
Grand Total Rs. 75.85 Per Sqm
10 20 mm CP in CM (1:4) including all cost , conveyance , royality
etc. complete.
Materials
Sand for Mortar 0.021 Cum @ 196.00 Per Cum Rs 4.12
Cement 0.0744 Qtl @ 553.90 Per Qtl Rs 41.21
Labour
Masson 2nd Class 0.16 Nos @ 116.00 Per No Rs 18.56
Man Mulia 0.13 Nos @ 90.00 Per No Rs 11.70
Woman Mulia 0.11 Nos @ 90.00 Per No Rs 9.90
Grand Total Rs. 85.49 Per Sqm
11 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Materials
HYSD bar including 5% extra for overlap & wastage
1.05 Qtl @ 3763.90 per Qtl Rs. 3952.10
Binding wire 0.80 Kg @ 60.00 per Kg Rs. 48.00
Labour
Black smith 1st Class 0.30 Nos @ 129.00 Per No Rs 38.70
Man Mulia 0.80 Nos @ 90.00 Per No Rs 72.00
Grand Total Rs. 4110.80 Per Qtl
12 2.50 CmM thick AS flooring in CC (1:2:4) using 12 mm size hbg
Chips including all cost , conveyance , royality etc. complete
Materials
Hbg Chips 12 mm size 0.023 Cum @ 943.40 Per Cum Rs 21.70
Sand for Mortar 0.012 Cum @ 196.00 Per Cum Rs 2.35
Cement 0.0858 Qtl @ 553.90 Per Qtl Rs 47.52
Labour
Masson 1st Class 0.13 Nos @ 129.00 Per No Rs 16.77
Man Mulia 0.14 Nos @ 90.00 Per No Rs 12.60
Woman Mulia 0.22 Nos @ 90.00 Per No Rs 19.80
Grand Total Rs. 120.74 Per Cum
13 White washing 2 coats with shell lime un slaked
(Data for 93 Sqm)
Material
Shell Lime un slaked 18.66 Kg @ 16.00 per kg Rs 298.56
Labour
Masson 2nd Class 1.00 Nos @ 116.00 Per No Rs 116.00
Man Mulia 0.75 Nos @ 90.00 Per No Rs 67.50
Grand Total Rs. 482.06 Per Sqm
Rate per 1 Sqm Rs 5.18 Per Sqm
14 Finishing wall surface with water proofing cement paint
of approved shade of 2 coats to give an even shade including
cost of paint.
(Data for 10 Sqm)
Material
Cement Paint 2.50 Kg @ 35.00 per kg Rs 87.50
Labour
Painter Spl. 0.22 Nos @ 129.00 Per No Rs 28.38
Man Mulia 0.32 Nos @ 90.00 Per No Rs 28.80
Add 2% for T&P,Sundries Rs 2.89
Grand Total Rs. 147.57 Per Sqm
Rate per 1 Sqm Rs 14.76 Per Sqm
15 Painting 2 coats with any approved paints ( Labour only)
( Data for 9.30 Sqm )
Labour
Painter 1st class 1.25 Nos @ 129.00 Per No Rs 161.25
Man Mulia 1.10 Nos @ 90.00 Per No Rs 99.00
Add 2% for T&P,Sundries Rs 5.21
Grand Total Rs. 265.46 Per Sqm
Rate per 1 Sqm Rs 28.54 Per Sqm
Labour
Masson 2nd Class 0.16 Nos @ 116.00 Per No Rs 18.56
Man Mulia 0.057 Nos @ 90.00 Per No Rs 5.13
Woman Mulia 0.057 Nos @ 90.00 Per No Rs 5.13
Grand Total Rs. 51.59 Per Sqm
Add 3% extra labour charges for 1st floor Rs 0.86
Grand Total Rs. 52.45 Per Sqm
19 16 mm CP in CM (1:6) including all cost , conveyance , royality
etc. complete. Materials
Sand for Mortar 0.018 Cum @ 196.00 Per Cum Rs 3.53
Cement 0.043 Qtl @ 553.90 Per Qtl Rs 23.82
Labour
Masson 2nd Class 0.18 Nos @ 116.00 Per No Rs 20.88
Man Mulia 0.148 Nos @ 90.00 Per No Rs 13.32
Woman Mulia 0.125 Nos @ 90.00 Per No Rs 11.25
Grand Total Rs. 72.80 Per Sqm
Add 3% extra labour charges for 1st floor Rs 1.36
Grand Total Rs. 74.16 Per Sqm
20 20 mm CP in CM (1:6) including all cost , conveyance , royality
etc. complete.
Materials
Sand for Mortar 0.021 Cum @ 196.00 Per Cum Rs 4.12
Cement 0.057 Qtl @ 553.90 Per Qtl Rs 31.57
Labour
Masson 2nd Class 0.18 Nos @ 116.00 Per No Rs 20.88
Man Mulia 0.148 Nos @ 90.00 Per No Rs 13.32
Woman Mulia 0.125 Nos @ 90.00 Per No Rs 11.25
Grand Total Rs. 81.14 Per Sqm
33 Labour for spreading muroom or gravel including watering but excluding cost
& conveyance of Muroom
Data for 2.83 Cum
Labour
Man Mulia 1.142 Nos @ 90.00 Per No Rs 102.78
Add 2% for T&P, Sundries Rs 2.06
Grand Total Rs. 104.84 Per 2.83 Cum
Rate per 1 Cum Rs. 37.04 Per Cum
34 Labour for spreading metal & packing the voids with small stones
& hand packing the same to proper camber including conveying , spreading
of filler material & filling the interstics by spreading the same over the surface
watering & consolidation with PRR including hire & running charges of PRR
but excluding the cost of metal & filler material.
Data for 2.83 Cum
Labour
Man mulia for removing from stacks,spreading metal to proper camber & turfedging
1.142 No @ 90.00 Per No Rs 102.78
Woman mulia for watering & conveyance etc.
3.428 Nos @ 90.00 Per No Rs 308.52
Machinery
Add hire & running charges of PRR for consolidation considering
42 Cum of out turn with PRR per day ( 8.00 Hrs)
0.539 Hrs @ 320.00 Per Hr Rs 172.48
Add 2% for T&P, sundries Rs 11.68
Grand Total Rs. 595.46 Per 2.83 Cum
Rate per 1 cum Rs 210.41 Per Cum
35 2.50 CM thick grading concreete (1:2:2) using 6 mm size cbg
chips on roof slab.
Materials
Cbg Chips 6 mm size 0.0169 Cum @ 828.40 Per Cum Rs 14.00
Sand for Mortar 0.0169 Cum @ 196.00 Per Cum Rs 3.31
Cement 0.1208 Qtl @ 553.90 Per Qtl Rs 66.91
Labour
Masson 1st Class 0.148 Nos @ 129.00 Per No Rs 19.09
Man Mulia 0.159 Nos @ 90.00 Per No Rs 14.31
Woman Mulia 0.25 Nos @ 90.00 Per No Rs 22.50
Grand Total Rs. 140.13 Per Cum
36 labour for Soling road surface with soling stone including filling
the interstics with earth & rolling with HRR excluding cost &
conveyance of soling stone.
Data for 2.83 Cum
Labour
Stone Packer 0.57 Nos @ 103.00 Per No Rs 58.71
Man Mulia 0.57 Nos @ 90.00 Per No Rs 51.30
Woman Mulia 2.857 Nos @ 90.00 Per No Rs 257.13
Add 2% for T&P, Sundries Rs 7.34
Grand Total Rs. 374.48 Per 2.83 Cum
Rate per 1 Cum Rs. 132.33 Per Cum
6 Fine dressing and turfing wi Mulia 1.14 Nos. @ Rs 90.00 per each = Rs 102.60
compact dub grasses with almulia for placing turf and ramming with thapies
lead and lift. 0.845 Nos. @ Rs 90.00 per each = Rs 76.05
conveyance 6.25 Cum @ Rs 102.00 per Cum. = Rs 637.50
Sundries & Tand P 2% = Rs 16.32
Total = Rs 832.47
per100 Sqm
Sarapanch
Chattahandi GP.
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF GUARD WALL AND CULVERT ON THE ROAD FROM PILIKA
CHHAK TO TRILIAMBAGUDA IN TARAGAM GP ".
Est.Cost:- Rs.5,00,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
U/S Cutoff 1X 9.40 X 1.00 X 1.00 = 9.40 Cum
D/S Cutoff 1X 9.40 X 1.00 X 1.50 = 14.10 Cum
Abutment 2X 3.60 X 1.20 X 1.20 = 10.37 Cum
Bed 1X 3.60 X 2.70 X 0.45 = 4.37 Cum
Guard wall 1X 113.50 X 1.00 X 1.00 = 113.50 Cum
Total = 151.74 Cum
@ Rs. 5084.20 Per 100 Cum Rs
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
U/S Cutoff 1X 9.40 X 1.00 X 0.10 = 0.94 Cum
D/S Cutoff 1X 9.40 X 1.00 X 0.10 = 0.94 Cum
Abutment 2X 3.60 X 1.20 X 0.10 = 0.86 Cum
Bed 1X 3.60 X 2.70 X 0.10 = 0.97 Cum
Guard wall 1X 113.50 X 1.00 X 0.10 = 11.35 Cum
Total = 15.07 Cum
@ Rs. 181.00 Per Cum Rs
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
U/S Cutoff 1 X 9.40 X 1.00 X 0.15 = 1.41 Cum
1 X 9.40 X 1.00 X 0.75 = 7.05 Cum
D/S Cutoff 1 X 9.40 X 1.00 X 0.15 = 1.41 Cum
1 X 9.40 X 1.00 X 0.95 = 8.93 Cum
Abutment 2 X 3.60 X 1.20 X 0.95 = 8.21 Cum
2 X 6.00 X 1.00+0.60/2 X 2.40 = 23.04 Cum
Bed 1 X 3.60 X 2.70 X 0.25 = 2.43 Cum
Wing Wall 4 X 2.00 X 1.00+0.60/2 X 2.40 = 15.36 Cum
Guard wall 1 X 113.50 X 1.00 X 0.10 = 11.35 Cum
1 X 113.50 X 0.90+0.45/2 X 1.95 = 149.39 Cum
Total 228.58 Cum
@ Rs. 1622.80 Per Cum Rs
4 RCC of M-20 grade using 20 mm & down graded cbg chips including
all Cost,Conveyance , royality etc complete.
Pier cap 2X 6.00 X 0.60 X 0.15 = 1.08 Cum
2X 6.00 X 0.23 X 0.20 = 0.55 Cum
Slab 1X 6.00 X 3.75 X 0.35 = 7.88 Cum
Total = 9.51 Cum
@ Rs. 2554.95 Per Cum Rs
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
Deduction
Door 2X 1.20 X 2X 2.00 = 9.60
Total 9.60 Sqm
Net Qty 87.06 Sqm
@ Rs. 48.01 Per Sqm Rs
7 Rcc (1:1.5:3) uing 12 mm ize hbg chip including ll complete.
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur
Administratively approved for Rs.2,00,000/-
(Rupees Two Lakhs Only)
Block Dev. Officer
Nabarangpur
Junior Engineer
Nabarangpur Block
Junior Engineer
Nabarangpur
Sarapanch
Chattahandi GP.
DETAILED ESTIMATE FOR THE WORK:-"Impv. Of road at Taragam Kumbhar Sahi road ."
Est.Cost:- Rs.10,0
1 Collecting,conveying , supplying of good quality murrom & stacking
on the road side with box heap of size (1.50X1.50X0.50) mtr to be measured
as (1.50X1.50X0.44) mtr as 1 Cum
Road 1 X 211.00 X 3.00 X 0.075 = 47.48 Cum
@ Rs. 188.00 Per Cum Rs
2 Conveying from stacks & spreading murrom on the road surface
including watering etc complete.
Road 1 X 211.00 X 3.00 X 0.075 = 47.48 Cum
@ Rs. 32.44 Per Cum Rs
Grand Total Rs.
Limitted to Rs.
(Rupees Ten thousand O
Technically Sanctioned for Rs.10,000/-
(Rupees Ten thousand Only)
Junior Engineer
Nabarangpur Block
Junior Engineer
Nabarangpur
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF TRAINING CUM PRODUCTION CENTRE AT PILLIKA."
Est.Cost:- Rs.32,58,0
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Pillar 12 X 1.50 X 1.50 X 1.80 = 48.60 Cum
Long Wall 2X 11.08 X 0.75 X 0.75 = 12.47 Cum
1X 2.48 X 0.75 X 0.75 = 1.40 Cum
Short Wall 3X 5.03 X 0.75 X 0.75 = 8.49 Cum
Total = 70.95 Cum
@ Rs. 4721.40 Per 100 Cum Rs
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Pillar 12 X 1.50 X 1.50 X 0.30 = 8.10 Cum
Long Wall 2 X 11.08 X 0.75 X 0.05 = 0.83 Cum
1 X 2.48 X 0.75 X 0.05 = 0.09 Cum
Short Wall 3 X 5.03 X 0.75 X 0.05 = 0.57 Cum
Room 1 X 6.01 X 8.93 X 0.45 = 24.15 Cum
2 X 2.78 X 2.78 X 0.45 = 6.96 Cum
Total = 40.70 Cum
@ Rs. 208.21 Per Cum Rs
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Pillar 12 X 1.50 X 1.50 X 0.30 = 8.10 Cum
Long Wall 2X 11.08 X 0.75 X 0.15 = 2.49 Cum
1X 2.48 X 0.75 X 0.15 = 0.28 Cum
Short Wall 3X 5.03 X 0.75 X 0.15 = 1.70 Cum
Room 1X 6.01 X 8.93 X 0.15 = 8.05 Cum
2X 2.78 X 2.78 X 0.15 = 2.32 Cum
Total = 22.94 Cum
@ Rs. 2085.29 Per Cum Rs
4 RR stone massonary in CM (1:6) to the F&P including all
cost,conveyance,royality etc. complete.
Long Wall 2X 11.71 X 0.60 X 0.55 = 7.73 Cum
2X 11.71 X 0.45 X 0.45 = 4.74 Cum
1X 2.78 X 0.60 X 0.55 = 0.92 Cum
1X 2.78 X 0.45 X 0.45 = 0.56 Cum
Short Wall 3X 5.93 X 0.60 X 0.55 = 5.87 Cum
3X 5.93 X 0.45 X 0.45 = 3.60 Cum
Total = 23.42 Cum
@ Rs. 1419.53 Per Cum Rs
5 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Floor Slab 1X 6.70 X 12.85 X 0.10 = 8.61 Cum
Pillar 12 X 1.50 X 1.50 X 0.30 = 8.10 Cum
12 X (1+0.40)/2 X (1+0.30)/2 X 0.45 = 2.46 Cum
12 X 0.40 X 0.30 X 4.43 = 6.38 Cum
Plinth Beam 1X 47.83 X 0.23 X 0.23 = 2.53 Cum
Lintel Bend 1X 47.83 X 0.23 X 0.15 = 1.65 Cum
Beam 1X 3.00 X 0.23 X 0.23 = 0.16 Cum
Grade Beam 1X 47.83 X 0.30 X 0.23 = 3.30 Cum
Room Beam 2X 6.40 X 0.40 X 0.45 = 2.30 Cum
Chujja 10 X 1.50 X 0.60 X 0.06 = 0.54 Cum
1X 6.70 X 0.60 X 0.06 = 0.24 Cum
Slab 1X 13.50 X 7.30 X 0.10 = 9.86 Cum
Total = 46.13 Cum
@ Rs. 3317.48 Per Cum Rs
6 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 41.51 Qtl
@ Rs. 4110.80 Per Qtl Rs
7 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Pillar 12 X 2 X (1+0.40)/2 X 0.45 = 7.56 Sqm
12 X 2 X (1+0.30)/2 X 0.45 = 7.02 Sqm
Plinth bend 1X 2 X 47.83 X 0.23 = 22.00 Sqm
Floor Slab 1X 1 X 6.70 X 12.85 = 86.10 Sqm
Total = 122.68 Sqm
@ Rs. 60.93 Per Sqm Rs
ii) Lintel Bend 1X 2 X 47.83 X 0.15 = 14.35 Sqm
Total = 14.35 Sqm
@ Rs. 141.47 Per Sqm Rs
iii) Column,beam 12 X 1 X 4.43 X 1.40 = 74.42 Sqm
1 X 1 X 3.00 X 0.69 = 2.07 Sqm
1 X 2 X 47.83 X 0.23 = 22.00 Sqm
2 X 1 X 6.40 X 1.30 = 16.64 Sqm
Total = 115.14 Sqm
@ Rs. 278.27 Per Sqm Rs
iv) Slab & Chajja
10 X 1 X 1.50 X 0.60 = 9.00 Sqm
1X 1 X 6.70 X 0.60 = 4.02 Sqm
1X 1 X 13.50 X 7.30 = 98.55 Sqm
Total = 111.57 Sqm
@ Rs. 192.14 Per Sqm Rs
8 WBCB in CM (1:6) in superstructure including all cost, conveyance
royality etc complete.
Long Wall 2X 12.15 X 0.23 X 3.00 = 16.77 Cum
1X 3.00 X 0.23 X 3.00 = 2.07 Cum
Short Wall 2X 6.00 X 0.23 X 3.00 = 8.28 Cum
1X 6.23 X 0.23 X 3.00 = 4.30 Cum
Total = 31.42 Cum
Deduction
Grill Opening 1X 3.00 X 0.23 X 2.00 = 1.38 Cum
Door Opening 2X 1.20 X 0.23 X 2.00 = 1.10 Cum
Window Opening 10 X 0.90 X 0.23 X 1.20 = 2.48 Cum
Total = 4.97 Cum
Net Qty = 26.45 Cum
@ Rs. 1947.29 Per Cum Rs
9 16 mm CP in CM (1:6) to the Super structure
Long Wall 2X 2 X 12.15 X 3.00 = 145.80 Sqm
1X 2 X 3.00 X 3.00 = 18.00 Sqm
Short Wall 2X 2 X 6.00 X 3.00 = 72.00 Sqm
1X 2 X 6.23 X 3.00 = 37.38 Sqm
Total = 273.18 Sqm
Deduction
Grill Opening 1X 2 X 3.00 X 2.00 = 12.00 Sqm
Door Opening 2X 2 X 1.20 X 2.00 = 9.60 Sqm
Window Opening 10 X 2 X 0.90 X 1.20 = 21.60 Sqm
Total = 43.20 Sqm
Net Qty = 229.98 Sqm
@ Rs. 67.51 Per Sqm Rs
10 20 mm CP in CM (1:4) to the graded plaster
Slab 1X 1 X 13.50 X 7.30 = 98.55 Sqm
Total = 98.55 Sqm
@ Rs. 85.49 Per Sqm Rs
11 Finishing wall surface with water proofing cement paint
of approved shade of 2 coats to give an even shade excluding
cost of paint.
Qty as per Item No 9 i.e = 229.98 Sqm
Add for ceiling = 98.55 Sqm
Total = 328.53 Sqm
@ Rs. 14.76 Per Sqm Rs
12 Cost of Iron Griil,Door & Window
Total 658.80 Kg
@ 49.00 Per Kg Rs
13 Painting 2 coats with any approved Paint ( Labour Only )
Door 2X 2.25 X 1.20 X 3.00 = 16.20 Sqm
Window 10 X 2.75 X 0.90 X 1.20 = 29.70 Sqm
Grill 1X 1.25 X 3.00 X 2.00 = 7.50 Sqm
Total = 53.40 Sqm
@ Rs. 28.54 Per Sqm Rs
14 Cost of Paint
Qty = 6.68 Litre
@ Rs. 150.00 Per Litre Rs
15 Cost of electrification ( To be paid as per actual ) Rs
16 Cost of Sign board ( 1.50X1.80 ) mtr. Size 1 No Rs
Grand Total Rs.
Limitted to Rs.
(Rupees Three Lakhs O
DETAILED ESTIMATE FOR THE WORK:-"SPECIAL REPAIR TO OLD HOSPITAL QUARTERS AT NABARANGPUR."
Est.Cost:- Rs.2,27,5
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Septic Tank for Qr. No.7 1X 2.40 X 1.50 X 2.40 = 8.64 Cum
Septic Tank for CDMO Qr 1X 2.40 X 1.50 X 2.40 = 8.64 Cum
Boundary Wall 1X 6.50 X 0.75 X 0.75 = 3.66 Cum
Bath room for Qr No. 7 1X 2.00 X 0.75 X 0.75 = 1.13 Cum
1X 0.68 X 0.75 X 0.75 = 0.38 Cum
Bath room for CDMO Qr 1X 2.00 X 0.75 X 0.75 = 1.13 Cum
1X 0.68 X 0.75 X 0.75 = 0.38 Cum
Total = 23.95 Cum
@ Rs. 4721.40 Per 100 Cum Rs
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Septic Tank for Qr. No.7 1X 2.40 X 1.50 X 0.10 = 0.36 Cum
Septic Tank for CDMO Qr 1X 2.40 X 1.50 X 0.10 = 0.36 Cum
Boundary Wall 1X 6.50 X 0.75 X 0.10 = 0.49
Total = 1.21 Cum
@ Rs. 208.21 Per Cum Rs
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Septic Tank for Qr. No.7 1X 2.40 X 1.50 X 0.15 = 0.54 Cum
Septic Tank for CDMO Qr 1X 2.40 X 1.50 X 0.15 = 0.54 Cum
Boundary Wall 1X 6.50 X 0.75 X 0.15 = 0.73
Bath room for Qr No. 7 1X 2.00 X 0.75 X 0.15 = 0.23 Cum
1X 0.68 X 0.75 X 0.15 = 0.08 Cum
Bath room for CDMO Qr 1X 2.00 X 0.75 X 0.15 = 0.23 Cum
1X 0.68 X 0.75 X 0.15 = 0.08 Cum
Total = 2.41 Cum
@ Rs. 2085.29 Per Cum Rs
4 RR stone massonary in CM (1:6) to the F&P including all
cost,conveyance,royality etc. complete.
Boundary Wall 1X 6.50 X 0.60 X 0.45 = 1.76 Cum
1X 6.50 X 0.45 X 0.45 = 1.32 Cum
Bath room for Qr No. 7 1X 1.85 X 0.60 X 0.45 = 0.50 Cum
1X 0.83 X 0.60 X 0.45 = 0.22 Cum
1X 1.80 X 0.45 X 0.45 = 0.36 Cum
1X 0.98 X 0.45 X 0.45 = 0.20 Cum
Bath room for CDMO Qr 1X 1.85 X 0.60 X 0.45 = 0.50 Cum
1X 0.83 X 0.45 X 0.45 = 0.17 Cum
1X 1.80 X 0.45 X 0.45 = 0.36 Cum
1X 0.98 X 0.45 X 0.45 = 0.20 Cum
Total = 5.59 Cum
@ Rs. 1419.53 Per Cum Rs
5 WBCB in CM (1:6) in superstructure including all cost, conveyance
royality etc complete.
Septic Tank for Qr. No.7 2X 2.40 X 0.23 X 2.40 = 2.65 Cum
2X 1.04 X 0.23 X 2.40 = 1.15 Cum
Septic Tank for CDMO Qr 2X 2.40 X 0.23 X 2.40 = 2.65 Cum
2X 1.04 X 0.23 X 2.40 = 1.15 Cum
Boundary Wall 1X 6.50 X 0.23 X 1.80 = 2.69 Cum
Bath room for Qr No. 7 1X 1.80 X 0.23 X 2.50 = 1.04 Cum
1X 1.20 X 0.23 X 2.50 = 0.69 Cum
Bath room for CDMO Qr 1X 1.80 X 0.23 X 2.50 = 1.04 Cum
1X 1.20 X 0.23 X 2.50 = 0.69 Cum
Deduction Total = 13.74 Cum
Door Opening 2X 0.75 X 0.23 X 1.80 = 0.62 Cum
Total = 0.62 Cum
Net Qty = 13.12 Cum
@ Rs. 1947.29 Per Cum Rs
6 16 mm CP in CM (1:6) to the superstructure
Qty = 216.61 Sqm @ 67.51 Per Sqm Rs
7 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Slab of septic tank 2X 2.40 X 1.50 X 0.10 = 0.72 Cum
Total = 0.72 Cum
@ Rs. 3317.48 Per Cum Rs
8 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 0.65 Qtl
@ Rs. 4110.80 Per Qtl Rs
9 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
iv) Slab & Chajja 2X 1 X 1.50 X 2.40 = 7.20 Sqm
Total = 7.20 Sqm
@ Rs. 192.14 Per Sqm Rs
10 Fixing Tiles in floor,treads ,steps & laying in 25 mm thick bed of cement mortar
( 1:1) jointed with neat slurrymixed with pigment to match the shade of the
tiles including rubbing & polishing complete excluding cost of precast tiles.
CDMO Qr 1X 1 X 5.80 X 3.35 = 19.43 Sqm
1X 1 X 2.10 X 3.35 = 7.04 Sqm
1X 1 X 4.85 X 3.35 = 16.25 Sqm
1X 1 X 1.80 X 2.40 = 4.32 Sqm
Dados 1X 2 X 5.80 X 0.15 = 1.74 Sqm
1X 2 X 3.35 X 0.15 = 1.01 Sqm
1X 2 X 2.10 X 0.15 = 0.63 Sqm
1X 2 X 3.35 X 0.15 = 1.01 Sqm
1X 2 X 4.85 X 0.15 = 1.46 Sqm
1X 2 X 3.35 X 0.15 = 1.01 Sqm
Lat & Bath 1X 2 X 1.80 X 1.50 = 5.40 Sqm
1X 2 X 2.40 X 1.50 = 7.20 Sqm
ADMO Qr 1X 1 X 3.60 X 3.35 = 12.06 Sqm
1X 1 X 3.60 X 3.90 = 14.04 Sqm
1X 1 X 1.20 X 1.80 = 2.16 Sqm
1X 1 X 0.60 X 2.40 = 1.44 Sqm
Dados 1X 2 X 3.60 X 0.15 = 1.08 Sqm
1 X 2 X 3.35 X 0.15 = 1.01 Sqm
1 X 2 X 3.60 X 0.15 = 1.08 Sqm
1 X 2 X 3.90 X 0.15 = 1.17 Sqm
Lat & Bath 1 X 2 X 1.20 X 1.50 = 3.60 Sqm
1 X 2 X 1.80 X 1.50 = 5.40 Sqm
1 X 2 X 0.60 X 0.90 = 1.08 Sqm
1 X 2 X 2.40 X 0.90 = 4.32 Sqm
OFFICER Qr 1 X 1 X 3.60 X 3.35 = 12.06 Sqm
1 X 1 X 3.60 X 3.60 = 12.96 Sqm
1 X 1 X 0.60 X 2.40 = 1.44 Sqm
Dados 1 X 2 X 3.60 X 0.15 = 1.08 Sqm
1 X 2 X 3.35 X 0.15 = 1.01 Sqm
1 X 2 X 3.60 X 0.15 = 1.08 Sqm
1 X 2 X 3.60 X 0.15 = 1.08 Sqm
Lat & Bath 1 X 2 X 1.20 X 1.50 = 3.60 Sqm
1 X 2 X 1.80 X 1.50 = 5.40 Sqm
1 X 2 X 0.60 X 0.90 = 1.08 Sqm
1 X 2 X 2.40 X 0.90 = 4.32 Sqm
Qr No.2 1 X 1 X 3.35 X 3.60 = 12.06 Sqm
1 X 1 X 3.60 X 3.60 = 12.96 Sqm
Dados 1 X 2 X 3.35 X 0.15 = 1.01 Sqm
1 X 2 X 3.60 X 0.15 = 1.08 Sqm
1 X 2 X 3.60 X 0.15 = 1.08 Sqm
1 X 2 X 3.60 X 0.15 = 1.08 Sqm
Lat & bath for Qr No 7 1 X 1 X 1.20 X 1.80 = 2.16 Sqm
Dados 1 X 2 X 1.20 X 0.15 = 0.36 Sqm
1 X 2 X 1.80 X 0.15 = 0.54 Sqm
Total = 192.34 Sqm
@ Rs. 266.60 Per Sqm Rs
11 Fixing Tiles in dados skirting& risers of steps on 12 mm thick cement plaster
( 1:3) jointed with neat slurrymixed with pigment to match the shade of the
tiles including rubbing & polishing complete excluding cost of precast tiles.
CDMO Qr
Dados 1X 2 X 5.80 X 0.15 = 1.74 Sqm
1X 2 X 3.35 X 0.15 = 1.01 Sqm
1X 2 X 2.10 X 0.15 = 0.63 Sqm
1X 2 X 3.35 X 0.15 = 1.01 Sqm
1X 2 X 4.85 X 0.15 = 1.46 Sqm
1X 2 X 3.35 X 0.15 = 1.01 Sqm
Lat & Bath 1X 2 X 1.80 X 1.50 = 5.40 Sqm
1X 2 X 2.40 X 1.50 = 7.20 Sqm
ADMO Qr
Dados 1X 2 X 3.60 X 0.15 = 1.08 Sqm
1X 2 X 3.35 X 0.15 = 1.01 Sqm
1X 2 X 3.60 X 0.15 = 1.08 Sqm
1X 2 X 3.90 X 0.15 = 1.17 Sqm
Lat & Bath 1X 2 X 1.20 X 1.50 = 3.60 Sqm
1X 2 X 1.80 X 1.50 = 5.40 Sqm
1X 2 X 0.60 X 0.90 = 1.08 Sqm
1X 2 X 2.40 X 0.90 = 4.32 Sqm
OFFICER Qr
Dados 1X 2 X 3.60 X 0.15 = 1.08 Sqm
1X 2 X 3.35 X 0.15 = 1.01 Sqm
1X 2 X 3.60 X 0.15 = 1.08 Sqm
1X 2 X 3.60 X 0.15 = 1.08 Sqm
Lat & Bath 1X 2 X 1.20 X 1.50 = 3.60 Sqm
1X 2 X 1.80 X 1.50 = 5.40 Sqm
1X 2 X 0.60 X 0.90 = 1.08 Sqm
1X 2 X 2.40 X 0.90 = 4.32 Sqm
Qr No.2
Dados 1X 2 X 3.35 X 0.15 = 1.01 Sqm
1X 2 X 3.60 X 0.15 = 1.08 Sqm
1X 2 X 3.60 X 0.15 = 1.08 Sqm
1X 2 X 3.60 X 0.15 = 1.08 Sqm
Lat & bath for Qr No 7
Dados 1X 2 X 1.20 X 1.50 = 3.60 Sqm
1X 2 X 1.80 X 1.50 = 5.40 Sqm
Total = 70.07 Sqm
Deduction
Door Opening 4X 1 X 0.75 X 1.50 = 4.50 Sqm
Total = 4.50 Sqm
Net Qty = 65.57 Sqm
@ Rs. 237.06 Per Sqm Rs
12 Cost of Precast Tiles
Floor Tiles 192.34 Sqm @ 499.00 Per Sqm Rs
Wall Tiles 65.57 Sqm @ 422.00 Per Sqm Rs
13 Cost of signboard & photograph Rs
Grand Total Rs.
Limitted to Rs.
(Rupees Two Lakhs twenty seven thousand five hundred Only)
Technically Sanctioned for Rs.2,27,500/-
(Rupees Two Lakhs twenty seven thousand five hundred Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur
ASST. ENGINEER
NABARANGPUR BLOCK
Administratively Approved for Rs.5,00,000/-
( Rupees Five Lakhs Only)
BLOCK DEV.OFFICER
NABARANGPUR BLOCK
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF PATIENT CABIN AT DISTRICT HEAD QUARTER HOSPITAL
CAMPUS,NABARANGPUR."
Est.Cost:- Rs.14,00,0
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Pillar 18 X 1.20 X 1.20 X 1.20 = 31.10 Cum
Long Wall 3X 16.15 X 0.75 X 0.75 = 27.25 Cum
10 X 1.05 X 0.60 X 0.60 = 3.78 Cum
Short Wall 6X 2.86 X 0.75 X 0.75 = 9.65 Cum
2X 0.60 X 0.75 X 0.75 = 0.68 Cum
10 X 1.05 X 0.60 X 0.60 = 3.78 Cum
1X 4.50 X 3.00 X 3.00 = 40.50 Cum
Drain 1X 100.00 X 1.20 X 0.75 = 90.00 Cum
Total = 206.74 Cum
@ Rs. 4721.40 Per 100 Cum Rs
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Pillar 18 X 1.20 X 1.20 X 0.15 = 3.89 Cum
Long Wall 3X 16.15 X 0.75 X 0.15 = 5.45 Cum
10 X 1.05 X 0.60 X 0.15 = 0.95 Cum
Short Wall 6 X 2.86 X 0.75 X 0.15 = 1.93 Cum
2 X 0.60 X 0.75 X 0.15 = 0.14 Cum
10 X 1.05 X 0.60 X 0.15 = 0.95 Cum
1 X 4.50 X 3.00 X 0.15 = 2.03 Cum
Drain 1 X 100.00 X 1.20 X 0.05 = 6.00 Cum
Total = 21.32 Cum
@ Rs. 208.21 Per Cum Rs
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Pillar 18 X 1.20 X 1.20 X 0.15 = 3.89 Cum
Long Wall 3X 16.15 X 0.75 X 0.15 = 5.45 Cum
10 X 1.05 X 0.60 X 0.15 = 0.95 Cum
Short Wall 6X 2.86 X 0.75 X 0.15 = 1.93 Cum
2X 0.60 X 0.75 X 0.15 = 0.14 Cum
10 X 1.05 X 0.60 X 0.15 = 0.95 Cum
1X 4.50 X 3.00 X 0.15 = 2.03 Cum
Room 5X 3.98 X 1.98 X 0.15 = 5.91 Cum
5X 0.53 X 1.39 X 0.15 = 0.55 Cum
Ver 1X 21.70 X 1.35 X 0.15 = 4.39 Cum
Drain 1X 100.00 X 1.20 X 0.10 = 12.00 Cum
2X 100.00 X 0.30 X 0.60 = 36.00 Cum
Road 1X 70.00 X 3.00 X 0.10 = 21.00 Cum
Total = 95.18 Cum
@ Rs. 2085.29 Per Cum Rs
4 RR stone massonary in CM (1:6) to the F&P including all
cost,conveyance,royality etc. complete.
1st footing Long Wall 3X 21.00 X 0.60 X 0.45 = 17.01 Cum
10 X 1.13 X 0.50 X 0.45 = 2.54 Cum
Short Wall 6X 3.83 X 0.60 X 0.45 = 6.20 Cum
2X 1.57 X 0.60 X 0.45 = 0.85 Cum
10 X 1.13 X 0.50 X 0.45 = 2.54 Cum
2nd footing Long Wall 3X 21.00 X 0.45 X 0.45 = 12.76 Cum
10 X 1.28 X 0.45 X 0.45 = 2.59 Cum
6X 3.83 X 0.45 X 0.45 = 4.65 Cum
Short Wall 2X 1.57 X 0.45 X 0.45 = 0.64 Cum
10 X 1.28 X 0.45 X 0.45 = 2.59 Cum
Total = 52.38 Cum
@ Rs. 1419.53 Per Cum Rs
5 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Pillar 18 X 1.20 X 1.20 X 0.30 = 7.78 Cum
18 X (1+0.23)/2 X (1+0.23)/2 X 0.45 = 3.06 Cum
18 X 0.23 X 0.23 X 3.95 = 3.76 Cum
Plinth Beam 1X 121.42 X 0.23 X 0.23 = 6.42 Cum
Lintel Bend 1X 97.28 X 0.23 X 0.15 = 3.36 Cum
Ver Beam 1X 21.00 X 0.23 X 0.23 = 1.11 Cum
2X 1.57 X 0.23 X 0.23 = 0.17 Cum
Chujja 5X 1.20 X 0.50 X 0.06 = 0.18 Cum
1X 22.38 X 0.50 X 0.06 = 0.67 Cum
Slab 1X 22.68 X 6.40 X 0.10 = 14.52 Cum
Septic Tank 1X 4.50 X 3.00 X 0.10 = 1.35 Cum
Total = 42.37 Cum
@ Rs. 3317.48 Per Cum Rs
6 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Total 36.02 Qtl
@ Rs. 4110.80 Per Qtl Rs
7 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Pillar 18 X 2 X (1+0.23)/2 X 0.45 = 9.96 Sqm
Plinth bend 1X 2 X 121.42 X 0.23 = 55.85 Sqm
Drain 1X 2 X 100.00 X 0.60 = 120.00 Sqm
Total = 185.82 Sqm
@ Rs. 60.93 Per Sqm Rs
ii) Lintel Bend 1X 2 X 97.28 X 0.15 = 29.18 Sqm
Total = 29.18 Sqm
@ Rs. 141.47 Per Sqm Rs
iii) Column,beam 18 X 1 X 3.95 X 0.92 = 65.41 Sqm
1X 1 X 21.00 X 0.69 = 14.49 Sqm
2X 1 X 1.57 X 0.69 = 2.17 Sqm
Total = 82.07 Sqm
@ Rs. 278.27 Per Sqm Rs
iv) Slab & Chajja 5X 1 X 1.20 X 0.50 = 3.00 Sqm
1X 1 X 22.38 X 0.50 = 11.19 Sqm
1X 1 X 22.68 X 6.40 = 145.15 Sqm
Total = 159.34 Sqm
@ Rs. 192.14 Per Sqm Rs
8 WBCB in CM (1:6) in superstructure including all cost, conveyance
royality etc complete.
Long Wall 2X 21.00 X 0.23 X 2.95 = 28.50 Cum
1X 21.00 X 0.23 X 0.60 = 2.90 Cum
10 X 1.73 X 0.23 X 2.95 = 11.74 Cum
Short Wall 6X 3.83 X 0.23 X 2.95 = 15.59 Cum
10 X 1.50 X 0.23 X 2.95 = 10.18 Cum
2X 1.57 X 0.23 X 0.60 = 0.43 Cum
Septic Tank 2X 4.50 X 0.23 X 3.00 = 6.21 Cum
3X 2.50 X 0.23 X 3.00 = 5.18 Cum
Total = 80.72 Cum
Deduction
Door Opening 5 X 1.20 X 0.23 X 2.00 = 2.76 Cum
5 X 0.75 X 0.23 X 2.00 = 1.73 Cum
10 X 0.75 X 0.23 X 2.00 = 3.45 Cum
Vantilator 15 X 0.30 X 0.23 X 0.30 = 0.31 Cum
Window Opening 10 X 0.90 X 0.23 X 1.20 = 2.48 Cum
Total = 10.73 Cum
Net Qty = 69.99 Cum
@ Rs. 1947.29 Per Cum Rs
9 2.50 CM thick grading concreete (1:2:2) using 6 mm size cbg
chips on roof slab.
Roof 1X 22.68 X 6.40 = 145.15
Total = 145.15 Sqm
@ Rs. 133.39 Per Sqm Rs
10 CC (1:2:4) using 12 mm size hbg Chips including all cost, conveyance
royality etc complete.
Drain 1X 100.00 X 0.60 X 0.05 = 3.00 Cum
2X 100.00 X 0.30 X 0.05 = 3.00 Cum
Road 1X 100.00 X 3.00 X 0.075 = 22.50 Cum
Total = 399.52 Cum
@ Rs. 78.88 Per Cum Rs
11 12 mm CP in CM (1:6) to the Super structure
Out side 1X 2 X 22.38 X 3.10 = 138.76 Sqm
1X 2 X 21.92 X 0.83 = 36.39 Sqm
1X 2 X 1.57 X 0.83 = 2.61 Sqm
Inside 5X 2 X 4.20 X 3.10 = 130.20 Sqm
5 X 2 X 3.83 X 3.10 = 118.73 Sqm
10 X 2 X 1.50 X 3.10 = 93.00 Sqm
10 X 2 X 1.50 X 3.10 = 93.00 Sqm
Septic Tank 2 X 1 X 4.50 X 3.00 = 27.00 Sqm
4 X 1 X 2.50 X 3.00 = 30.00 Sqm
Total = 669.68 Sqm
Deduction
Door Opening 5 X 2 X 1.20 X 2.00 = 24.00 Sqm
5 X 2 X 0.75 X 2.00 = 15.00 Sqm
10 X 2 X 0.75 X 2.00 = 30.00 Sqm
Vantilator 15 X 2 X 0.30 X 0.30 = 2.70 Sqm
Window Opening 10 X 2 X 0.90 X 1.20 = 21.60 Sqm
Total = 93.30 Sqm
Net Qty = 576.38 Sqm
@ Rs. 48.01 Per Sqm Rs
12 Finishing wall surface with water proofing cement paint
of approved shade of 2 coats to give an even shade excluding
cost of paint.
Qty as per Item No 9 i.e = 576.38 Sqm
Add for ceiling = 159.34 Sqm
Total = 735.72 Sqm
@ Rs. 14.76 Per Sqm Rs
13 Cost of Iron Door & Window
Total 827.16 Kg
@ 63.00 Per Kg Rs
Vantilator 08 Nos @ 1000.00/No Rs
14 Providing,fitting,fixing of Alluminium door with OEL anodized Alluminium
door section of 9202 as vertical member & 9200 as bottom & middle
member & 6 mm plain glass in top portion with 12 mm thick pre-laminated
board in bottom portion fixed on door frame by means of tappered clip No.
4660 & the frame to be completed by means of jointing angle No. 1855
including all cost,hire charges of drilling machine etc complete.
Door 6X 1.20 X 2.00 = 14.40
Window 3X 0.75 X 2.00 = 4.50
Total = 18.90 Sqm
@ Rs. 3678.60 Per Sqm Rs
15 Fixing Tiles in floor,treads ,steps & laying in 25 mm thick bed of cement mortar
( 1:1) jointed with neat slurrymixed with pigment to match the shade of the
tiles including rubbing & polishing complete excluding cost of precast tiles.
Room 5X 4.20 X 2.20 = 46.20
5X 0.75 X 1.73 = 6.49
10 X 1.50 X 1.50 = 22.50
Ver 1X 22.38 X 1.80 = 40.28
Total = 115.47 Sqm
@ Rs. 266.60 Per Sqm Rs
16 Fixing Tiles in dados skirting& risers of steps on 12 mm thick cement plaster
( 1:3) jointed with neat slurrymixed with pigment to match the shade of the
tiles including rubbing & polishing complete excluding cost of precast tiles.
Room 10 X 2 X 1.50 X 1.50 = 45.00 Sqm
10 X 2 X 1.50 X 1.50 = 45.00 Sqm
Total = 90.00 Sqm
Deduction
Door Opening 10 X 1 X 0.75 X 1.50 = 11.25 Sqm
Total = 11.25 Sqm
Net Qty = 78.75 Sqm
@ Rs. 237.06 Per Sqm Rs
17 Cost of Precast Tiles
Floor Tiles 115.47 Sqm @ 355.00 Per Sqm Rs
Wall Tiles 78.75 Sqm @ 320.00 Per Sqm Rs
18 Painting 2 coats with any approved Paint ( Labour Only )
Door 2X 2.25 X 1.20 X 2.00 = 10.80 Sqm
2X 2.25 X 0.75 X 2.00 = 6.75 Sqm
Window 4X 2.75 X 0.90 X 1.20 = 11.88 Sqm
Total = 29.43 Sqm
@ Rs. 28.54 Per Sqm Rs
19 Cost of Paint
Qty = 3.68 Litre
@ Rs. 150.00 Per Litre Rs
20 Cost of Electrical Fittings (Taking10% of Civil Works) Rs
21 Cost of PHD Fittings (Taking10% of Civil Works) Rs
22 Cost of 03 Nos Of Air Conditioner ( 1.50 ton ) LS ( To be Paid as Per Actual ) Rs
23 Cost of Sign board ( 1.50X1.80 ) mtr. Size 1 No with photograph Rs
24 Provision for plinth protection work LS Rs
Grand Total Rs.
Say Rs.
(Rupees Forteen Lakhs O
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block Block Dev. Officer
Nabarangpur
Administratively approved for Rs.2,50,000/-
(Rupees Two Lakh & Fifty thousand Only)
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF GUARD WALL AT AMBADOLLA CHALAN SAHI."
Est.Cost:- Rs.25,0
1 E/W excavation in hard soil with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Levelling of campus 1X 9.50 X 0.90 X 0.90 = 7.70 Cum
Total = 7.70 Cum
@ Rs. 4721.40 Per 100 Cum Rs
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Guard wall 1X 9.50 X 0.90 X 0.90 = 7.70 Cum
Total = 7.70 Cum
@ Rs. 208.21 Per Cum Rs
3 CC (1:4:8) using 40 mm size cbg metal including all cost,conveyance
royality etc.complete
Guard wall 1X 9.50 X 0.90 X 0.15 = 1.28 Cum
1X 9.50 X (0.75+0.45)/2 X 1.65 = 9.41 Cum
Total = 10.69 Cum
@ Rs. 2085.29 Per Cum Rs
4 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Guard wall 1X 2 X 9.50 X 1.65 = 31.35 Sqm
Total = 31.35 Sqm
@ Rs. 60.93 Per Sqm Rs
5 12 mm CP in CM (1:6) to the Super structure
Guard wall 1X 2 X 9.50 X 0.90 = 17.10 Sqm
Total = 17.10 Sqm
@ Rs. 48.01 Per Sqm Rs
6 PCC (1:2:4) using 12 mm size cbg chips including all complete.
Guard wall 1X 9.50 X 0.45 X 0.05 = 0.21 Cum
Total = 0.21 Cum
@ Rs. 3219.24 Per Cum Rs
7 Provision for work Transperancy board (1.50X1.80) mtr size & Photograph Rs
Grand Total Rs.
Say Rs.
(Rupees Twenty Five Thousand O
Technically Sanctioned for Rs.25,000/-
(Rupees Twenty Five Thousand Only)
Junior Engineer
Junior Engineer Nabarangpur Block
Nabarangpur Block
SARAPANCH
BADAMASIGAM GP
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM BADAMASIGAM VILLAGE TO TEMPLE ROAD."
Est.Cost:- Rs.20,0
1 Collecting,conveying,supplying of good quality murrom & stacking on the
road side with box heap of size (1.50X1.50X0.50) mtr to be measured as 1 Cum
Road 1X 320.00 X 3.00 X 0.10 = 96.00 Cum
Total = 96.00 Cum
@ Rs. 186.40 Per Cum Rs
2 Labour for spreading murrom on the road surface including watering
etc complete
Road 1X 320.00 X 3.00 X 0.10 = 96.00 Cum
Total = 96.00 Cum
@ Rs. 28.81 Per Cum Rs
Grand Total Rs.
Say Rs.
(Rupees Twenty Thousand O
Technically Sanctioned for Rs.20,000/-
(Rupees Twenty Thousand Only)
Junior Engineer
Junior Engineer Nabarangpur Block
Nabarangpur Block
SARAPANCH
BADAMASIGAM GP
DETAILED WORK DONE ESTIMATE FOR THE WORK:-"CONST. OF CC ROAD FROM RD ROAD TO MOULIBANDH
TARAGAM GP".
Est.Cost:- Rs.1,50,00
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Road 2 X 89.00 X 0.23 X 0.23 = 9.42 Cum
Total = 9.42 Cum
@ Rs. 4721.40 Per 100 Cum Rs
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Road 1 X 89.00 X 3.54 X 0.05 = 15.75 Cum
Total = 15.75 Cum
@ Rs. 208.21 Per Cum Rs
3 CC (1:4:8) using40 mm size cbg metal including all cost,conveyance
royality etc.complete
Road 1 X 89.00 X 4.00 X 0.10 = 35.60 Cum
Road 2 X 89.00 X 0.23 X 0.23 = 9.42 Cum
Total = 45.02 Cum
@ Rs. 2085.29 Per Cum Rs
3 CC (1:2:4) using 12 mm size cbg Chips including all cost, conveyance
royality etc complete.
Road 1 X 89.00 X 4.00 X 0.075 = 26.70 Cum
Total = 26.70 Cum
@ Rs. 3219.24 Per Cum Rs
4 Provision for work Transperancy board (1.50X1.80) mtr size Rs
Grand Total Rs.
Say Rs.
(Rupees One Lakh & Fifty thousand On
Technically Sanctioned for Rs.1,50,000/-
(Rupees One Lakh & Fifty thousand Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
Block Dev. Officer
Nabarangpur
Administratively approved for Rs.1,50,000/-
(Rupees One Lakh & Fifty thousand Only)
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF MARKET SHED AT ."
Est.Cost:- Rs.2,50,0
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Pillar 15 X 1.20 X 1.20 X 1.20 = 25.92 Cum
Long Wall 2X 5.72 X 0.60 X 0.60 = 4.12 Cum
Short Wall 5X 2.86 X 0.60 X 0.60 = 5.15 Cum
Total = 35.19 Cum
@ Rs. 4721.40 Per 100 Cum Rs
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Pillar 15 X 1.20 X 1.20 X 0.05 = 1.08 Cum
Long Wall 2X 5.72 X 0.60 X 0.05 = 0.34 Cum
Short Wall 5X 2.86 X 0.60 X 0.05 = 0.43 Cum
Room 4X 4.13 X 2.40 X 0.45 = 17.84 Cum
Total = 19.69 Cum
@ Rs. 208.21 Per Cum Rs
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Pillar 15 X 1.20 X 1.20 X 0.15 = 3.24 Cum
Long Wall 2X 5.72 X 0.60 X 0.15 = 1.03 Cum
Short Wall 6X 2.86 X 0.60 X 0.15 = 1.54 Cum
Room 4X 4.13 X 2.40 X 0.10 = 3.96 Cum
Total = 9.78 Cum
@ Rs. 2085.29 Per Cum Rs
4 RR stone massonary in CM (1:6) to the F&P including all
cost,conveyance,royality etc. complete.
Long Wall 2X 9.60 X 0.60 X 0.40 = 4.61 Cum
2X 9.60 X 0.45 X 0.45 = 3.89 Cum
Short Wall 5X 4.80 X 0.60 X 0.40 = 5.76 Cum
5X 4.80 X 0.45 X 0.45 = 4.86 Cum
Total = 19.12 Cum
@ Rs. 1419.53 Per Cum Rs
5 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Pillar 15 X 1.00 X 1.00 X 0.30 = 4.50 Cum
15 X (1+0.23)/2 X (1+0.23)/2 X 0.45 = 2.55 Cum
10 X 0.23 X 0.23 X 2.95 = 1.56 Cum
5 X 0.23 X 0.23 X 3.55 = 0.94 Cum
Plinth Beam 1 X 43.20 X 0.23 X 0.23 = 2.29 Cum
Grade Beam 1 X 43.20 X 0.23 X 0.20 = 1.99 Cum
Room Beam 1 X 9.60 X 0.23 X 0.23 = 0.51 Cum
Cantilever Beam 10 X 0.75 X 0.23 X 0.15 = 0.26 Cum
Slab 1 X 11.05 X 7.50 X 0.10 = 8.29 Cum
Total = 22.88 Cum
@ Rs. 3317.48 Per Cum Rs
6 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 18.30 Qtl
@ Rs. 4110.80 Per Qtl Rs
7 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Pillar 15 X 2 X (1+0.23)/2 X 0.45 = 8.30 Sqm
Plinth bend 1X 2 X 43.20 X 0.23 = 19.87 Sqm
Total = 28.17 Sqm
@ Rs. 60.93 Per Sqm Rs
ii) Column,beam 10 X 1 X 2.95 X 0.92 = 27.14 Sqm
5 X 1 X 3.55 X 0.92 = 16.33 Sqm
Room Beam 1 X 1 X 43.20 X 0.69 = 29.81 Sqm
1 X 1 X 9.60 X 0.69 = 6.62 Sqm
Cantilever Beam 10 X 1 X 0.75 X 0.69 = 5.18 Sqm
Total = 85.08 Sqm
@ Rs. 278.27 Per Sqm Rs
iii) Slab 1X 1 X 11.05 X 7.50 = 82.88 Sqm
@ Rs. 192.14 Per Sqm Rs
8 20 mm CP in CM (1:4) to the graded plaster
Slab 1X 1 X 11.05 X 7.50 = 82.88 Sqm
Total = 82.88 Sqm
@ Rs. 85.49 Per Sqm Rs
9 20 mm CP in CM (1:6) to the Plinth
Plinth 1X 2 X 10.75 X 0.60 = 12.90 Sqm
1X 2 X 5.50 X 0.60 = 6.60 Sqm
Total = 19.50 Sqm
@ Rs. 75.85 Per Sqm Rs
10 Finishing wall surface with water proofing cement paint
of approved shade of 2 coats to give an even shade excluding
cost of paint.
Add for ceiling = 82.88 Sqm
Total = 82.88 Sqm
@ Rs. 14.76 Per Sqm Rs
11 2.50 CmM thick AS flooring in CC (1:2:4) using 12 mm size hbg
Chips including all cost , conveyance , royality etc. complete
Room 5X 4.13 X 2.40 = 49.56 Sqm
Total = 49.56 Sqm
@ Rs. 120.74 Per Cum Rs
12 Cost of Sign board ( 1.50X1.80 ) mtr. Size 1 No with Photograph Rs
Grand Total Rs.
Limitted to Rs.
(Rupees Two Lakhs & Fifty Thousand O
Technically Sanctioned for Rs.2,50,000/-
(Rupees Two Lakhs & Fifty Thousand Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
Junior Engineer
Tentulikhunti Block
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF RESIDENTIAL BUILDING CUM SHOPPING
COMPLEX OF SRI SANTI TALUKDAR AT RAIGHAR OVER KHATA NO PLOT NO
MOUZA RAIGHAR.
Est.Cost:- Rs.5,36,0
1 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
1st Floor
Pillar 24 X 0.23 X 0.35 X 2.85 = 5.51 Cum
Grade Beam 4X 3.75 X 0.23 X 0.30 = 1.04 Cum
6X 4.15 X 0.23 X 0.30 = 1.72 Cum
16 X 3.60 X 0.23 X 0.30 = 3.97 Cum
12 X 2.70 X 0.23 X 0.30 = 2.24 Cum
Staircase (Treads) 40 X 1.20 X 0.25 X 0.10 = 1.20 Cum
(Rise) 40 X 1.20 X 0.150 X 0.10 = 0.72 Cum
Landings 1X 2.40 X 1.20 X 0.10 = 0.29 Cum
Slab 1X 10.50 X 23.75 X 0.100 = 24.94 Cum
Total = 41.61 Cum
@ Rs. 2730.95 Per Cum Rs
2 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Total 35.37 Qtl
@ Rs. 3600.00 Per Qtl Rs
3 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete. 1st Floor
i) Column,beam 24 X 1 X 2.85 X 1.16 = 79.34 Sqm
4X 1 X 3.75 X 0.83 = 12.45 Sqm
6X 1 X 4.15 X 0.83 = 20.67 Sqm
16 X 1 X 3.60 X 0.83 = 47.81 Sqm
12 X 1 X 2.70 X 0.83 = 26.89 Sqm
Total = 187.16 Sqm
@ Rs. 246.18 Per Sqm Rs
iv) Slab & Chajja 1 X 1 X 10.50 X 23.75 = 249.38 Sqm
Stair case 40 X 1 X 1.20 X 0.25 = 12.00 Sqm
40 X 1 X 1.20 X 0.15 = 7.20 Sqm
1 X 1 X 2.40 X 1.20 = 2.88 Sqm
Total = 271.46 Sqm
@ Rs. 177.17 Per Sqm Rs
4 WBCB in CM (1:6) in superstructure including all cost, conveyance
royality etc complete. 1st Floor
Long Wall 4X 3.75 X 0.23 X 2.85 = 9.83 Cum
2X 4.15 X 0.23 X 2.85 = 5.44 Cum
6X 2.70 X 0.23 X 2.85 = 10.62 Cum
8X 3.60 X 0.23 X 2.85 = 18.88 Cum
Parapet 2X 20.70 X 0.23 X 1.20 = 11.43 Cum
2X 10.50 X 0.23 X 1.20 = 5.80 Cum
Deduction Total = 61.99 Cum
Door Opening 4X 1.20 X 0.23 X 2.00 = 2.21 Cum
Window Opening 4X 0.90 X 0.23 X 1.20 = 0.99 Cum
Total = 3.20 Cum
Net Qty = 58.79 Cum
@ Rs. 1591.38 Per Cum Rs
5 16 mm CP in CM (1:6) to the Super structure 1st Floor
Out side 2X 1 X 23.70 X 2.85 = 135.09 Sqm
Inside 2X 1 X 10.50 X 2.85 = 59.85 Sqm
12 X 1 X 3.60 X 2.85 = 123.12 Sqm
6 X 1 X 3.75 X 2.85 = 64.13 Sqm
2 X 1 X 4.15 X 2.85 = 23.66 Sqm
2 X 2 X 10.50 X 1.20 = 50.40 Sqm
2 X 2 X 20.70 X 1.20 = 99.36 Sqm
Deduction Total = 555.60 Sqm
Door Opening 4X 2 X 1.20 X 2.00 = 19.20 Sqm
Window Opening 4X 2 X 0.90 X 1.20 = 8.64 Sqm
Total = 27.84 Sqm
Net Qty = 527.76 Sqm
@ Rs. 54.27 Per Sqm Rs
6 Finishing wall surface with water proofing cement paint
of approved shade of 2 coats to give an even shade excluding
cost of paint. 1st Floor
Qty as per Item No 9 i.e = 527.76 Sqm
Add for ceiling = 271.46 Sqm
Total = 799.22 Sqm
@ Rs. 13.70 Per Sqm Rs
7 Cost of Iron Door & Window Rs
8 2.50 CmM thick AS flooring in CC (1:2:4) using 12 mm size hbg
Chips including all cost , conveyance , royality etc. complete
1st Floor
Room 2X 1 X 3.75 X 2.70 = 20.25 Sqm
2X 1 X 3.60 X 2.70 = 19.44 Sqm
1X 1 X 2.95 X 4.15 = 12.24 Sqm
1X 1 X 3.95 X 4.15 = 16.39 Sqm
1X 1 X 11.25 X 4.15 = 46.69 Sqm
Total = 115.01 Sqm
@ Rs. 97.70 Per Sqm Rs
9 20 mm CP in CM (1:4) including all cost , conveyance , royality
etc. complete.
1X 1 X 10.50 X 23.75 = 249.38 Sqm
@ Rs. 68.47 Per Sqm Rs
10 Cost of Electrical Fittings Rs
Grand Total Rs.
Say Rs.
(Rupees Five Lac & Thirty six thousand O
Certified that the estimate has been prepared basing on Schedule of rates 2008 of Works
Department,Govt. of Orissa & enhanced labour rates as per 2008
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF CC ROAD AT MANTRIGUDA PUJARIGUDIA SAHI".
Est.Cost:- Rs.1,06,00
Head of Account:- T
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Road 1 X 78.00 X 3.00 X 0.10 = 23.40 Cum
Total = 23.40 Cum
@ Rs. 4721.40 Per 100 Cum Rs
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Road 1 X 78.00 X 3.00 X 0.10 = 23.40 Cum
Total = 23.40 Cum
@ Rs. 208.21 Per Cum Rs
3 CC (1:4:8) using40 mm size cbg metal including all cost,conveyance
royality etc.complete
Road 1 X 78.00 X 3.00 X 0.10 = 23.40 Cum
Total = 23.40 Cum
@ Rs. 2085.29 Per Cum Rs
4 CC (1:2:4) using 12 mm size cbg Chips including all cost, conveyance
royality etc complete.
Road 1 X 78.00 X 3.00 X 0.075 = 17.55 Cum
Total = 17.55 Cum
@ Rs. 3219.24 Per Cum Rs
5 Collecting,conveying & supplying of good quality murrom or gravel
& stacking on the road side with box heap of size (1.50X1.50X0.44) mtr
to be measured as 1 cum
Road 2 X 78.00 X 0.60 X 0.15 = 14.04 Cum
Total = 14.04 Cum
@ Rs. 188.00 Per Cum Rs
6 Conveying from stacks & spreading murrom on the road with
watering etc complete excluding cost & conveyance of materials.
Road 2 X 78.00 X 0.60 X 0.15 = 14.04 Cum
Total = 14.04 Cum
@ Rs. 32.44 Per Cum Rs
7 Provision for work Transperancy board with Photograph Charges. Rs
Grand Total Rs.
Say Rs.
(Rupees One Lakh six thousand On
Technically Sanctioned for Rs.1,06,000/-
(Rupees One Lakh six thousand Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
Block Dev. Officer
Nabarangpur
Administratively approved for Rs.1,06,000/-
(Rupees One Lakh six thousand Only)
Sarapanch
Mantriguda GP
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF SHG BUILDING - CUM - TRAINING CENTRE AT NABARANGPU
BLOCK PREMISES."
Est.Cost:- Rs.5,00,0
1 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
1st Floor
Pillar 15 X 0.23 X 0.23 X 3.00 = 2.38 Cum
Lintel bend 1X 42.27 X 0.23 X 0.15 = 1.46 Cum
Grade Beam 1X 42.27 X 0.23 X 0.23 = 2.24 Cum
Room Beam 2X 6.66 X 0.30 X 0.50 = 2.00 Cum
Ver Beam 1X 2.40 X 0.23 X 0.23 = 0.13 Cum
1X 1.95 X 0.23 X 0.23 = 0.10 Cum
Stair Landing 1X 2.41 X 1.00 X 0.10 = 0.24 Cum
Steps 16 X 0.80 X 0.19 X 0.10 = 0.24 Cum
16 X 0.80 X 0.20 X 0.10 = 0.26 Cum
Chhaja 5X 1.20 X 0.50 X 0.08 = 0.24 Cum
1X 5.54 X 0.50 X 0.08 = 0.22 Cum
Slab 1X 12.16 X 6.66 X 0.10 = 8.10 Cum
1X 2.83 X 4.31 X 0.10 = 1.22 Cum
1X 4.01 X 2.18 X 0.10 = 0.87 Cum
Total = 19.70 Cum
@ Rs. 3373.22 Per Cum Rs
2 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 15.76 Qtl
@ Rs. 4117.77 Per Qtl Rs
3 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Lintel Bend 1X 2 X 42.27 X 0.15 = 12.68 Sqm
Total = 12.68 Sqm
@ Rs. 141.47 Per Sqm Rs
ii) Column,beam 15 X 1 X 3.00 X 0.92 = 41.40 Sqm
Room Beam 2 X 1 X 6.66 X 1.30 = 17.32 Sqm
Ver Beam 1 X 1 X 2.40 X 0.69 = 1.66 Sqm
1 X 1 X 1.95 X 0.69 = 1.35 Sqm
Grade Beam 1 X 1 X 42.27 X 0.69 = 29.17 Sqm
Total = 90.88 Sqm
@ Rs. 278.27 Per Sqm Rs
iii) Slab 1 X 1 X 12.16 X 6.66 = 80.99 Sqm
1 X 1 X 2.83 X 4.31 = 12.20 Sqm
1 X 1 X 4.01 X 2.18 = 8.74 Sqm
Stair Landing 1 X 1 X 2.41 X 1.00 = 2.41 Sqm
Steps 16 X 1 X 0.80 X 0.19 = 2.43 Sqm
16 X 1 X 0.80 X 0.20 = 2.56 Sqm
Chajja 5 X 1 X 1.20 X 0.50 = 3.00 Sqm
1 X 1 X 5.54 X 0.50 = 2.77 Sqm
Total = 115.10 Sqm
@ Rs. 192.14 Per Sqm Rs
4 20 mm CP in CM (1:4) to the graded plaster
Slab 1X 1 X 12.16 X 6.66 = 80.99 Sqm
1X 1 X 2.83 X 4.31 = 12.20 Sqm
1X 1 X 4.01 X 2.18 = 8.74 Sqm
Total = 101.92 Sqm
@ Rs. 87.12 Per Sqm Rs
5 WBCB in CM (1:6) in superstructure including all cost, conveyance
royality etc complete. 1st Floor
Long Wall 2X 10.94 X 0.23 X 3.00 = 15.10 Cum
Cross Wall 2X 5.97 X 0.23 X 3.00 = 8.24 Cum
3X 2.45 X 0.23 X 3.00 = 5.07 Cum
1X 3.55 X 0.23 X 3.00 = 2.45 Cum
3X 1.95 X 0.23 X 3.00 = 4.04 Cum
1X 2.40 X 0.23 X 3.00 = 1.66 Cum
1X 3.60 X 0.23 X 3.00 = 2.48 Cum
Stair Room 2X 3.60 X 0.23 X (2.70+2.10)/2 = 3.97 Cum
1X 1.95 X 0.23 X 2.70 = 1.21 Cum
1X 1.95 X 0.23 X 2.10 = 0.94 Cum
Parapet 1X 2.41 X 0.23 X 0.23 = 0.13 Cum
1X 3.75 X 0.23 X 0.23 = 0.20 Cum
2X 11.86 X 0.23 X 1.00 = 5.46 Cum
1X 6.20 X 0.23 X 1.00 = 1.43 Cum
2X 2.45 X 0.23 X 1.00 = 1.13 Cum
1X 4.58 X 0.23 X 1.00 = 1.05 Cum
Deduction Total = 54.55 Cum
Door Opening 5X 1.20 X 0.23 X 2.00 = 2.76 Cum
Grill Opening 1X 2.40 X 0.23 X 1.00 = 0.55 Cum
1X 1.95 X 0.23 X 1.00 = 0.45 Cum
Stair room Vantilator 1X 1.00 X 0.23 X 2.00 = 0.46 Cum
Vantilator 5X 0.60 X 0.23 X 0.45 = 0.31 Cum
2X 0.45 X 0.23 X 0.30 = 0.06 Cum
Window Opening 5X 1.20 X 0.23 X 1.20 = 1.66 Cum
Total = 6.25 Cum
Net Qty = 48.30 Cum
@ Rs. 2017.62 Per Cum Rs
6 16 mm CP in CM (1:6) to the Super structure 1st Floor
Qty as per Item No.5 = (48.50/0.23)X2 419.99 Sqm
@ Rs. 69.14 Per Sqm Rs
7 Finishing wall surface with water proofing cement paint
of approved shade of 2 coats to give an even shade excluding
cost of paint.
Qty as per Item No.6 = 419.99
Add for ceiling = 101.92 Sqm
Total = 521.92 Sqm
@ Rs. 14.93 Per Sqm Rs
8 Providing,fitting,fixing of Alluminium door with OEL anodized Alluminium
door section of 9202 as vertical member & 9200 as bottom & middle
member & 6 mm plain glass in top portion with 12 mm thick pre-laminated
board in bottom portion fixed on door frame by means of tappered clip No.
4660 & the frame to be completed by means of jointing angle No. 1855
including all cost,hire charges of drilling machine etc complete.
Door 1X 1.20 X 2.00 = 2.40
Window 5X 1.20 X 1.20 = 7.20
Total = 9.60 Sqm
@ Rs. 3678.60 Per Sqm Rs
9 Fixing Tiles in floor,treads ,steps & laying in 25 mm thick bed of cement mortar
( 1:1) jointed with neat slurrymixed with pigment to match the shade of the
tiles including rubbing & polishing complete excluding cost of precast tiles.
Room 2X 1.66 X 2.45 = 8.13
1X 11.40 X 6.20 = 70.68
1X 1.95 X 2.40 = 4.68
1X 1.95 X 1.00 = 1.95
Total = 85.44 Sqm
@ Rs. 266.60 Per Sqm Rs
10 Fixing Tiles in dados skirting& risers of steps on 12 mm thick cement plaster
( 1:3) jointed with neat slurrymixed with pigment to match the shade of the
tiles including rubbing & polishing complete excluding cost of precast tiles.
Room 2X 1 X 11.40 X 0.20 = 4.56 Sqm
2X 1 X 6.20 X 0.20 = 2.48 Sqm
2X 1 X 2.40 X 0.20 = 0.96 Sqm
2X 1 X 1.95 X 0.20 = 0.78 Sqm
2X 2 X 2.45 X 1.50 = 14.70 Sqm
2X 2 X 1.66 X 1.50 = 9.96 Sqm
1X 1 X 1.95 X 0.20 = 0.39 Sqm
Total = 33.83 Sqm
Deduction
Door Opening 4X 2 X 1.20 X 0.20 = 1.92 Sqm
Total = 1.92 Sqm
Net Qty = 31.91 Sqm
@ Rs. 237.06 Per Sqm Rs
11 Cost of Precast Tiles
Floor Tiles 85.44 Sqm @ 499.00 Per Sqm Rs
Wall Tiles 31.91 Sqm @ 422.00 Per Sqm Rs
12 Cost of Iron Door
Door 4X 1 X 1.20 X 2.00 = 9.60 Sqm
@ 30.50 Kg per Sqm 292.80 Kg
@ Rs. 49.00 Per Kg Rs
13 Cost of Vantilator LS Rs
14 Cost of MS Grills LS Rs
15 Cost of Electification 6% of estimated cost Rs
16 Cost of sanitary Fittings 4% of estimated Cost Rs
17 Add Cost,Fittings,Fixing of GCI sheet in stair room & add for architectural design work LS Rs
18 Cost of Sign board ( 1.50X1.80 ) mtr. Size 1 No with Photograph Rs
Grand Total Rs.
Limitted to Rs.
(Rupees Five Lacs O
Technically Sanctioned for Rs.5,00,000/-
(Rupees Five Lacs Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
Certified that the estimate has been prepared basing on Schedule of Rates 2008 & enhanced labour rate.
JUNIOR ENGINEER
NABARANGPUR BLOCK
Junior Engineer
Nabarangpur Block
Junior Engineer
Nabarangpur Block
Administratively approved for Rs.40,000/-
(Rupees Forty thousand Only)
Sarapanch
Chattahandi GP
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF KITCHEN CUM STORE ROOM AT ."
Est.Cost:- Rs.60,0
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Long Wall 2X 3.98 X 0.75 X 0.75 = 4.48 Cum
Short Wall 2X 1.98 X 0.60 X 0.60 = 1.43 Cum
Total = 5.90 Cum
@ Rs. 4721.40 Per 100 Cum Rs
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Room 1X 2.78 X 2.28 X 0.475 = 3.01 Cum
Total = 3.01 Cum
@ Rs. 208.21 Per Cum Rs
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Long Wall 2X 3.98 X 0.75 X 0.15 = 0.90 Cum
Short Wall 2X 1.98 X 0.75 X 0.15 = 0.45 Cum
Room 1X 2.78 X 2.28 X 0.10 = 0.63 Cum
Total = 1.97 Cum
@ Rs. 2085.29 Per Cum Rs
4 RR stone massonary in CM (1:6) to the F&P including all
cost,conveyance,royality etc. complete.
Long Wall 2X 3.83 X 0.60 X 0.30 = 1.38 Cum
2X 3.73 X 0.50 X 0.30 = 1.12 Cum
2 X 3.68 X 0.45 X 0.45 = 1.49 Cum
Short Wall 2 X 2.13 X 0.60 X 0.30 = 0.77 Cum
2 X 2.23 X 0.50 X 0.30 = 0.67 Cum
2 X 2.28 X 0.45 X 0.45 = 0.92 Cum
Total = 6.35 Cum
@ Rs. 1336.53 Per Cum Rs
5 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Plinth Bend 1X 11.92 X 0.45 X 0.15 = 0.80 Cum
Lintel Bend 1X 11.92 X 0.23 X 0.15 = 0.41 Cum
Chajja 3X 1.50 X 0.50 X 0.06 = 0.14 Cum
Slab 1X 4.06 X 3.56 X 0.10 = 1.45 Cum
Total = 2.80 Cum
@ Rs. 3317.48 Per Cum Rs
6 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 2.24 Qtl
@ Rs. 4110.80 Per Qtl Rs
7 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
Plinth bend 1X 2 X 11.92 X 0.15 = 3.58 Sqm
Total = 3.58 Sqm
@ Rs. 60.93 Per Sqm Rs
ii) Lintel Bend 1X 2 X 11.92 X 0.15 = 3.58 Sqm
Total = 3.58 Sqm
@ Rs. 141.47 Per Sqm Rs
iii) Slab,Chajja 1X 1 X 4.06 X 3.56 = 14.45 Sqm
3X 1 X 1.50 X 0.50 = 2.25 Sqm
Total = 16.70 Sqm
@ Rs. 192.14 Per Sqm Rs
8 20 mm CP in CM (1:4) to the graded plaster
Slab 1X 1 X 4.06 X 3.56 = 14.45 Sqm
Total = 14.45 Sqm
@ Rs. 85.49 Per Sqm Rs
9 20 mm CP in CM (1:6) to the Plinth
Plinth 1X 2 X 3.68 X 0.60 = 4.42 Sqm
1X 2 X 3.18 X 0.60 = 3.82 Sqm
Total = 8.23 Sqm
@ Rs. 75.85 Per Sqm Rs
10 WBCB in CM (1:6) in superstructure including all cost, conveyance
royality etc complete.
Long Wall 2X 3.46 X 0.23 X (3.00+2.85)/2 = 4.66 Cum
Short Wall 2X 2.50 X 0.23 X 2.85 = 3.28 Cum
Deduction Total = 7.93 Cum
Door Opening 1X 1.20 X 0.23 X 2.00 = 0.55 Cum
Window Opening 1X 0.90 X 0.23 X 1.20 = 0.25 Cum
Grill Opening 1X 1.80 X 0.23 X 1.20 = 0.50 Cum
Vantilator 3X 0.60 X 0.23 X 0.30 = 0.12 Cum
Total = 1.42 Cum
Net Qty = 6.51 Cum
@ Rs. 1947.29 Per Cum Rs
11 16 mm CP in CM (1:6) to the Super structure
Out side 1X 2 X 3.46 X (3.00+2.85)/2 = 20.24 Sqm
1X 2 X 2.96 X 2.85 = 16.87 Sqm
Inside 1X 2 X 3.00 X (3.00+2.85)/2 = 17.55 Sqm
1X 2 X 2.50 X 2.85 = 14.25 Sqm
Deduction Total = 68.91 Sqm
Door Opening 1X 2 X 1.20 X 2.00 = 4.80 Sqm
Window Opening 1X 2.00 X 0.90 X 1.20 = 2.16 Cum
Grill Opening 1X 2.00 X 1.80 X 1.20 = 4.32 Cum
Vantilator 3X 2 X 0.60 X 0.30 = 1.08 Sqm
Total = 12.36 Sqm
Net Qty = 56.55 Sqm
@ Rs. 67.51 Per Sqm Rs
12 Finishing wall surface with water proofing cement paint
of approved shade of 2 coats to give an even shade etc Complete
Qty as per Item No.11 i.e = 56.55
Add for ceiling = 14.45 Sqm
Total = 71.01 Sqm
@ Rs. 14.76 Per Sqm Rs
13 2.50 CmM thick AS flooring in CC (1:2:4) using 12 mm size hbg
Chips including all cost , conveyance , royality etc. complete
Room 1X 3.00 X 2.50 = 7.50 Sqm
Total = 7.50 Sqm
@ Rs. 120.74 Per Cum Rs
14 Cost of Iron Door,Window & Grill LS Rs
15 Painting 2 coats with any approved Paint ( Labour Only )
Door 1X 2.25 X 1.20 X 2.00 = 5.40 Sqm
Window 1X 2.75 X 0.90 X 1.20 = 2.97 Sqm
Grill 1X 1.25 X 1.80 X 1.20 = 2.70 Sqm
Total = 11.07 Sqm
@ Rs. 28.54 Per Sqm Rs
16 Cost of Paint
Qty = 1.38 Litre
@ Rs. 145.00 Per Litre Rs
17 Cost of Sign board ( 1.20X1.50 ) mtr. Size 1 No with Photograph Charges Rs
18 Add for Cess 1% Rs
Grand Total Rs.
Limitted to Rs.
(Rupees Sixty Thousand O
Technically Sanctioned for Rs.60,000/-
(Rupees Sixty Thousand Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
Administratively approved for Rs.60,000/-
(Rupees Sixty Thousand Only)
SARAPANCH
SANAMASIGAM GRAMPANCHAYAT
Say Rs.
Junior Engineer
Nabarangpur Block
Junior Engineer
Nabarangpur Block
Sarapanch
Badakumuli GP
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF PATIENT CABIN AT DISTRICT HEAD QUARTER HOSPITAL
CAMPUS,NABARANGPUR."
Est.Cost:- Rs.6,00,0
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Pillar 9X 1.20 X 1.20 X 1.20 = 15.55 Cum
Long Wall 3X 6.46 X 0.60 X 0.60 = 6.98 Cum
Short Wall 2X 3.66 X 0.60 X 0.60 = 2.64 Cum
1X 2.63 X 0.60 X 0.60 = 0.95 Cum
1X 5.06 X 0.60 X 0.60 = 1.82 Cum
3X 1.13 X 0.60 X 0.60 = 1.22 Cum
Septic Tank 1X 4.50 X 3.00 X 3.00 = 40.50 Cum
Soak Pit 1X 3.00 X 1.50 X 1.50 = 6.75 Cum
Total = 76.40 Cum
@ Rs. 4721.40 Per 100 Cum Rs
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Pillar 9X 1.20 X 1.20 X 0.10 = 1.30 Cum
Long Wall 3X 6.46 X 0.60 X 0.10 = 1.16 Cum
Short Wall 2X 3.66 X 0.60 X 0.10 = 0.44 Cum
1X 2.63 X 0.60 X 0.10 = 0.16 Cum
1X 5.06 X 0.60 X 0.10 = 0.30 Cum
3X 1.13 X 0.60 X 0.10 = 0.20 Cum
Septic Tank 1X 4.50 X 3.00 X 0.10 = 1.35 Cum
Soak Pit 1X 3.00 X 1.50 X 0.10 = 0.45 Cum
Total = 5.36 Cum
@ Rs. 208.21 Per Cum Rs
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Pillar 9X 1.20 X 1.20 X 0.15 = 1.94 Cum
Long Wall 3X 6.46 X 0.60 X 0.15 = 1.74 Cum
Short Wall 2X 3.66 X 0.60 X 0.15 = 0.66 Cum
1X 2.63 X 0.60 X 0.15 = 0.24 Cum
1X 5.06 X 0.60 X 0.15 = 0.46 Cum
3X 1.13 X 0.60 X 0.15 = 0.31 Cum
Room 2X 3.98 X 3.38 X 0.10 = 2.69 Cum
Toilet 2X 1.78 X 1.28 X 0.10 = 0.46 Cum
Ver 1X 8.41 X 1.78 X 0.10 = 1.50 Cum
Septic Tank 1X 4.50 X 3.00 X 0.15 = 2.03 Cum
Total = 12.01 Cum
@ Rs. 2085.29 Per Cum Rs
4 RR stone massonary in CM (1:6) to the F&P including all
cost,conveyance,royality etc. complete.
1st footing Long Wall 3X 8.40 X 0.60 X 0.35 = 5.29 Cum
Short Wall 2X 5.60 X 0.60 X 0.35 = 2.35 Cum
1X 3.60 X 0.60 X 0.35 = 0.76 Cum
1X 4.60 X 0.60 X 0.35 = 0.97 Cum
3X 1.13 X 0.60 X 0.35 = 0.71 Cum
2nd footing Long Wall 3X 8.40 X 0.45 X 0.45 = 5.10 Cum
Short Wall 2X 5.60 X 0.45 X 0.45 = 2.27 Cum
1X 3.60 X 0.45 X 0.45 = 0.73 Cum
1X 4.45 X 0.45 X 0.45 = 0.90 Cum
3X 1.28 X 0.45 X 0.45 = 0.78 Cum
Total = 19.86 Cum
@ Rs. 1419.53 Per Cum Rs
5 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Pillar 9X 1.20 X 1.20 X 0.30 = 3.89 Cum
9 X (1+0.23)/2 X (1+0.23)/2 X 0.45 = 1.53 Cum
9X 0.23 X 0.23 X 3.95 = 1.88 Cum
Ver Col. above Plinth 2X 0.23 X 0.23 X 3.95 = 0.42 Cum
Plinth Beam 1X 49.19 X 0.23 X 0.23 = 2.60 Cum
Lintel Bend 1X 28.39 X 0.23 X 0.15 = 0.98 Cum
Ver Beam 1X 7.94 X 0.23 X 0.23 = 0.42 Cum
2X 2.00 X 0.23 X 0.23 = 0.21 Cum
Chujja 2X 1.20 X 0.50 X 0.06 = 0.07 Cum
1X 9.10 X 0.50 X 0.06 = 0.27 Cum
Slab 1X 9.40 X 6.60 X 0.10 = 6.20 Cum
1X 5.00 X 1.88 X 0.10 = 0.94 Cum
Septic Tank & Soak Pit 1X 6.00 X 3.00 X 0.10 = 1.80 Cum
Total = 21.22 Cum
@ Rs. 3317.48 Per Cum Rs
6 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Total 18.04 Qtl
@ Rs. 4110.80 Per Qtl Rs
7 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Pillar 9X 2 X (1+0.23)/2 X 0.45 = 4.98 Sqm
Plinth bend 1X 2 X 49.19 X 0.23 = 22.63 Sqm
Total = 27.61 Sqm
@ Rs. 60.93 Per Sqm Rs
ii) Lintel Bend 1X 2 X 28.39 X 0.15 = 8.52 Sqm
Total = 8.52 Sqm
@ Rs. 141.47 Per Sqm Rs
iii) Column,beam 11 X 1 X 3.95 X 0.92 = 39.97 Sqm
1X 1 X 9.94 X 0.69 = 6.86 Sqm
Total = 46.83 Sqm
@ Rs. 278.27 Per Sqm Rs
iv) Slab & Chajja 2 X 1 X 1.20 X 0.50 = 1.20 Sqm
1 X 1 X 9.10 X 0.50 = 4.55 Sqm
1 X 1 X 6.60 X 9.40 = 62.04 Sqm
1 X 1 X 5.00 X 1.88 = 9.40 Sqm
1 X 1 X 6.00 X 3.00 = 18.00 Sqm
Total = 95.19 Sqm
@ Rs. 192.14 Per Sqm Rs
8 WBCB in CM (1:6) in superstructure including all cost, conveyance
royality etc complete.
Long Wall 3X 8.40 X 0.23 X 2.95 = 17.10 Cum
Short Wall 3X 3.60 X 0.23 X 2.95 = 7.33 Cum
1X 2.00 X 0.23 X 2.95 = 1.36 Cum
1X 4.69 X 0.23 X 2.95 = 3.18 Cum
3X 1.50 X 0.23 X 2.95 = 3.05 Cum
Soak Pit 2X 3.00 X 0.23 X 1.50 = 2.07 Cum
2X 1.04 X 0.23 X 1.50 = 0.72 Cum
Septic Tank 2X 4.50 X 0.23 X 3.00 = 6.21 Cum
3X 2.50 X 0.23 X 3.00 = 5.18 Cum
Total = 46.19 Cum
Deduction
Door Opening 2 X 1.20 X 0.23 X 2.00 = 1.10 Cum
2 X 0.75 X 0.23 X 2.00 = 0.69 Cum
Opening of Front Ver Wall 1 X 7.94 X 0.23 X 1.25 = 2.28 Cum
Gate ( Mini ) 2 X 0.90 X 0.23 X 0.75 = 0.31 Cum
Vantilator 12 X 0.30 X 0.23 X 0.30 = 0.25 Cum
Window Opening 4 X 0.90 X 0.23 X 1.20 = 0.99 Cum
Total = 5.63 Cum
Net Qty = 40.56 Cum
@ Rs. 1947.29 Per Cum Rs
9 2.50 CM thick grading concreete (1:2:2) using 6 mm size cbg
chips on roof slab.
Roof 1X 6.60 X 9.40 = 62.04 Sqm
1X 5.00 X 1.88 = 9.40 Sqm
Total = 62.04 Sqm
@ Rs. 133.39 Per Sqm Rs
10 16 mm CP in CM (1:6) to the Super structure
Out side 1 X 1 X 50.10 X 3.10 = 155.31 Sqm
Inside 2 X 2 X 4.20 X 3.10 = 52.08 Sqm
2 X 2 X 3.60 X 3.10 = 44.64 Sqm
2 X 2 X 2.00 X 3.10 = 24.80 Sqm
2 X 2 X 1.50 X 3.10 = 18.60 Sqm
Septic Tank 2 X 1 X 4.50 X 3.00 = 27.00 Sqm
2 X 1 X 2.50 X 3.00 = 15.00 Sqm
Total = 337.43 Sqm
Deduction
Door Opening 2 X 2 X 1.20 X 2.00 = 9.60 Sqm
2 X 2 X 0.75 X 2.00 = 6.00 Sqm
Opening of Front Ver Wall 1 X 2 X 7.94 X 1.25 = 19.85 Sqm
Gate ( Mini ) 2 X 2.00 X 0.90 X 0.75 = 2.70 Cum
Vantilator 12 X 2 X 0.30 X 0.30 = 2.16 Sqm
Window Opening 4 X 2 X 0.90 X 1.20 = 8.64 Sqm
Total = 48.95 Sqm
Net Qty = 288.48 Sqm
@ Rs. 67.51 Per Sqm Rs
11 Finishing wall surface with water proofing cement paint
of approved shade of 2 coats to give an even shade excluding
cost of paint.
Qty as per Item No 9 i.e = 288.48 Sqm
Add for ceiling = 95.19 Sqm
Total = 383.67 Sqm
@ Rs. 14.76 Per Sqm Rs
12 Cost of Iron Door & Window
Total 105.00 Kg
@ 50.00 Per Kg Rs
Vantilator 12 Nos @ 1000.00/No Rs
13 Providing,fitting,fixing of Alluminium door with OEL anodized Alluminium
door section of 9202 as vertical member & 9200 as bottom & middle
member & 6 mm plain glass in top portion with 12 mm thick pre-laminated
board in bottom portion fixed on door frame by means of tappered clip No.
4660 & the frame to be completed by means of jointing angle No. 1855
including all cost,hire charges of drilling machine etc complete.
Door 2X 1.20 X 2.00 = 4.80 Sqm
Window 4X 0.75 X 2.00 = 6.00 Sqm
Total = 10.80 Sqm
@ Rs. 3678.60 Per Sqm Rs
14 Fixing Tiles in floor,treads ,steps & laying in 25 mm thick bed of cement mortar
( 1:1) jointed with neat slurrymixed with pigment to match the shade of the
tiles including rubbing & polishing complete excluding cost of precast tiles.
Room 2X 4.20 X 3.60 = 30.24 Sqm
Toilet 2X 2.00 X 1.50 = 6.00 Sqm
Ver 1X 8.63 X 2.20 = 18.99 Sqm
Total = 55.23 Sqm
@ Rs. 266.60 Per Sqm Rs
15 Fixing Tiles in dados skirting& risers of steps on 12 mm thick cement plaster
( 1:3) jointed with neat slurrymixed with pigment to match the shade of the
tiles including rubbing & polishing complete excluding cost of precast tiles.
Room 2X 2 X 4.20 X 0.20 = 3.36 Sqm
2X 2 X 3.60 X 0.20 = 2.88 Sqm
Ver 1X 2 X 8.63 X 0.20 = 3.45 Sqm
Toilet 2X 2 X 2.00 X 1.50 = 12.00 Sqm
2X 2 X 1.50 X 1.50 = 9.00 Sqm
Total = 30.69 Sqm
Deduction
Door Opening 2X 1 X 0.75 X 1.50 = 2.25 Sqm
2X 2 X 1.20 X 0.20 = 0.96 Sqm
Ver 1X 1 X 8.64 X 0.20 = 1.73 Sqm
Total = 2.25 Sqm
Net Qty = 28.44 Sqm
@ Rs. 237.06 Per Sqm Rs
16 Cost of Precast Tiles
Floor Tiles 55.23 Sqm @ 355.00 Per Sqm Rs
Wall Tiles 28.44 Sqm @ 320.00 Per Sqm Rs
17 Painting 2 coats with any approved Paint ( Labour Only )
Door 2X 2.25 X 0.75 X 2.00 = 6.75 Sqm
Total = 6.75 Sqm
@ Rs. 28.54 Per Sqm Rs
18 Cost of Paint
Qty = 0.84 Say 1 Litre
@ Rs. 150.00 Per Litre Rs
19 Cost of Electrical Fittings (Taking10% of Civil Works) Rs
20 Cost of PHD Fittings (Taking10% of Civil Works) Rs
21 Cost of 02 Nos Of Air Conditioner ( 1.50 ton ) LS ( To be Paid as Per Actual ) Rs
22 Cost of Sign board ( 1.50X1.80 ) mtr. Size 1 No with photograph Rs
Grand Total Rs.
Say Rs.
(Rupees Six Lakhs O
DETAILED ESTIMATE FOR THE WORK:-"RENOVATION OF PALLAVI SHOW ROOM AT BLOCK OFFICE PREMISE
Est.Cost:- Rs.20,00
1 WBCB in CM (1:6) to the super structure
Wall 6 X 0.60 X 0.23 X 0.60 = 0.50
Total 0.50 Cum
@ Rs. 1947.29 Per Cum Rs
2 16 mm CP in CM (1:6) to the Super structure
2 X 8.50 X 3.00 = 51.00
2 X 3.00 X 3.00 = 18.00
2 X 2.26 X 3.00 = 13.56
2 X 1.96 X 3.00 = 11.76
2 X 1.50 X 1.55 = 4.65
2 X 1.50 X 1.55 = 4.65
Total 103.62 Sqm
@ Rs. 67.51 Per Sqm Rs
Junior Engineer
Asst. Engineer Nabarangpur Block
Nabarangpur Block
Est.Cost:- Rs.1,06,0
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
1X 58.50 X 3.00 X 0.150 = 26.33 Cum
Total = 26.33 Cum
@ Rs. 4721.40 Per 100 Cum Rs
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
1X 58.50 X 3.00 X 0.150 = 26.33 Cum
Total = 26.33 Cum
@ Rs. 208.21 Per Cum Rs
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
1X 58.50 X 3.00 X 0.15 = 26.33 Cum
Total = 26.33 Cum
@ Rs. 2085.29 Per Cum Rs
4 CC (1:2:4) using 12 mm size hbg chips including all cost,conveyance
royality etc.complete
1X 58.50 X 3.00 X 0.075 = 13.16 Cum
Total = 13.16 Cum
@ Rs. 3219.24 Per Cum Rs
5 Cost of Signboard & Photograph Rs
6 Cess 1% Rs
Grand Total Rs.
Limit to Say Rs.
(Rupees One Lakh & six Thousand O
Junior Engineer
Asst. Engineer Nabarangpur Block
Nabarangpur Block
DEDUCTION
Column Trench 18 X 0.75 X 0.75 X 0.15 = 1.52 Cum
Net Quantity = 30.41 Cum
E) Chajja
2X 1.80 X 0.45 X 0.075 = 0.12 Cum
8X 1.20 X 0.45 X 0.075 = 0.32 Cum
Total = 0.45 Cum
E) Staircase
Waist 2 X 2.75 X 0.90 X 0.20 = 0.99 Cum
Step 0.5 X 18.00 X 0.30 X 0.175 X 0.900 = 0.43 Cum
Landing 1 X 2.00 X 0.90 X 4.57 X 0.200 = 1.65 Cum
3.06 Cum
G Slab
1X 20.43 X 7.77 X 0.125 = 19.84 Cum
Less S/C 1X 2.44 X 4.57 X 0.100 = 1.12 Cum
Less S/C back 1X 1.80 X 2.44 X 0.100 = 0.44 Cum
septic tank 3.55 X 1.42 X 0.10 = 0.50 Cum
3.14/4 X 0.91*0.91 X 0.10 = 0.07 Cum
TOTAL = 18.85 Cum
DEDUCTION
D 2 X 2.00 X 1.06 X 0.230 X 2.100 = 2.05 Cum
2 X 3.00 X 0.90 X 0.230 X 2.100 = 2.61 Cum
2 X 1.00 X 0.75 X 0.230 X 2.100 = 0.72 Cum
2 X 1.50 X 0.23 X 1.350 X = 0.93 Cum
2 X 5.00 X 0.90 X 0.230 X 1.350 = 2.79 Cum
2 X 1.00 X 0.60 X 0.230 X 0.450 = 0.12 Cum
1 X 2.44 X 0.23 X 2.100 = 1.18 Cum
10.41 Cum
54.41 Cum
7 12mm thick CP (1:6) over brick masonary
including cost, conveyancy, curring, royalty etc Complete.
As per item No. avobe Qunatity 550.16 Sqm
Door D 4Nos.
D1 6Nos.
D2 2Nos.
Window
W 2Nos.
W1 10 Nos.
Ventilator
V 2Nos.
Collapsible
Gate 1 No.
12 Finishing wall sur face of wall with Acrylic wall putty ( Water based)
of approved make & finished smooth & even surface to receive
painting including cost of scaffolding staging charges etc complete.
3411.5
2 x 15.0 x 15.0 = 264.00
2 x 12.0 x 11.0 = 96.00
2 x 12.0 x 4.0 = 12.00
2 x 8.0 x 15.0 = 128.00
2 x 8.0 x 8.0 = 194.72
2 x 12.2 x 8.0 = 96.00
898.72
Or 442.24 sqm
DEDUCTION
D1 1X 0.9 X 0.23 X 2.1 = 0.43 Cum
Window 1X 1.5 X 0.23 X 2.44 = 0.84 Cum
Total = 1.28 Cum
Net Quantity = 16.58 Cum
13 Finishing wall sur face of wall with Acrylic wall putty ( Water based)
of approved make & finished smooth & even surface to receive
painting including cost of scaffolding staging charges etc complete.
DEDUCTION
D1 1X 0.9 X 0.23 X 2.1 = 0.43 Cum
Window 1X 1.5 X 0.23 X 2.44 = 0.84 Cum
Total = 1.28 Cum
Net Quantity = 16.58 Cum
21379.38
10944.66
6471.70
1481.40
40277.14
40000.00
(Rupees Forty Thousand Only)
Junior Engineer
Nabarangpur Block
NST. OF GUARD WALL AND CULVERT ON THE ROAD FROM PILIKA
RILIAMBAGUDA IN TARAGAM GP ".
Est.Cost:- Rs.5,00,000/-
7714.87
2726.95
370943.48
24289.91
32204.89
39947.6
11838.78
9558.33
1300.00
500524.80
500000.00
-"CONST. OF GUARD WALL AT BHATIGAM IN BAGHSIUNIGP."
Est.Cost:- Rs.2,50,000/-
4118.2
1466.1
192733.87
34685.82
7183.08
8924.78
1300
250411.86
250000
RENOVATION OF SHOW ROOM CUM WSHG TRAINING CENTRE AT
PITAL PREMISES , NABARANGPUR".
Est.Cost:- Rs.2,00,000/-
472.14
16265.28
1415.00
2564.33
14315.94
4179.53
7791.32
6054.58
3773.27
12709.76
13102.90
9308.27
18825.42
6915.06
21398.16
6904.53
822.88
4018.74
2390.58
2077.65
15000.00
30000.00
200305.33
200000.00
(Rupees Two Lakh Only)
:-"IMPV. OF ROAD FROM DONGRIGUDA TO TELENGAGUDA."
Est.Cost:- Rs.2,00,000/-
3341.83
701.76
213029.78
14473.12
3082.22
5166.88
1500.00
241295.58
200000.00
(Rupees Two Lakhs Only)
Junior Engineer
Nabarangpur Block
K:-"CONST. OF TUBE WELL PLATFORM AT ."
Est.Cost:- Rs.4,000/-
2586.08
1430.54
4016.62
4000.00
(Rupees Four thousand Only)
Junior Engineer
Nabarangpur Block
WORK:-"Impv. Of road at Taragam Kumbhar Sahi road ."
Est.Cost:- Rs.10,000/-
8925.30
1540.00
10465.30
10000.00
(Rupees Ten thousand Only)
Junior Engineer
Nabarangpur Block
CONST. OF TRAINING CUM PRODUCTION CENTRE AT PILLIKA."
Est.Cost:- Rs.32,58,000/-
3349.74
8473.30
47833.55
33252.12
153019.44
170650.16
7474.60
2030.00
32038.48
21437.17
51501.36
15524.96
8424.66
4848.24
32281.20
1524.23
1001.25
40000.00
2000.00
636664.46
3258000.00
(Rupees Three Lakhs Only)
CIAL REPAIR TO OLD HOSPITAL QUARTERS AT NABARANGPUR."
Est.Cost:- Rs.2,27,500/-
1130.83
251.41
5034.42
7932.82
25539.73
14622.32
2388.59
2663.80
1383.42
51278.03
15542.59
95976.41
27668.43
1000.00
252412.79
227500.00
(Rupees Two Lakhs twenty seven thousand five hundred Only)
Junior Engineer
Nabarangpur Block
IAL REPAIR TO STAFF QUARTER & CONST. OF GENERAL TOILET AT
BLOCK PREMISES."
Est.Cost:- Rs.1,00,000/-
487.25
12478.42
7662.98
13002.94
8237.63
5332.35
8874.46
101.93
40.09
1967.03
20412.36
7499.98
2886.24
5786.46
214.65
908.00
2236.96
3374.00
101503.72
100000.00
(Rupees One Lakh Only)
Junior Engineer
Nabarangpur Block
THE WORK:- " IMPV. OF MIP AT BIKRAMPUR ".
500000.00
170541.41
4981.08
310063.37
4256.05
16889.57
3458.54
8957.19
9434.27
24941.04
6954.96
2500.00
562977.49
500000.00
JUNIOR ENGINEER
NABARANGPUR BLOCK
ORK:-"CONST. OF AWC BUILDING AT TELENGAGUDA."
Est.Cost:- Rs.3,00,000/-
1716.75
4667.13
23709.15
25215.70
69168.43
63717.32
1809.51
1779.17
13592.70
14973.55
49526.45
18292.15
2363.34
21805.00
400.00
1053.85
692.26
7306.87
1500.00
323289.33
300000.00
(Rupees Three Lakhs Only)
JUNIOR ENGINEER
NABARANGPUR BLOCK
9761.24
4438.78
198470.17
74352.63
140573.86
148061.14
11321.63
4128.76
22836.97
30616.13
136293.41
19362.33
31514.52
27671.76
10857.31
52111.08
8000.00
69525.54
30785.21
18668.18
40992.38
25200.00
840.04
551.81
80000.00
80000.00
135000.00
1000.00
56000.00
1468934.88
1400000.00
(Rupees Forteen Lakhs Only)
CIAL REPAIR & ADDITION TO THE ANM CENTRE AT BADAKUMULI
DER BADAKUMULI GP ."
Est.Cost:- Rs.1,60,000/-
1072.73
974.71
1144.98
2177.75
1218.01
22494.59
6442.91
28170.65
6881.12
45257.96
15075.74
6806.24
5488.77
1043.76
3449.17
1953.59
6140.10
920.21
604.48
4000.00
15000.00
10000.00
1500.00
187817.44
160000.00
(Rupees One Lakh & Sixty thousand Only)
Junior Engineer
Nabarangpur Block
Nabarangpur
Est.Cost:- Rs.25,000/-
363.31
1602.15
22286.56
1910.13
820.96
688.11
2000.00
29671.23
25000.00
(Rupees Twenty Five Thousand Only)
Nabarangpur Block
PV. OF ROAD FROM BADAMASIGAM VILLAGE TO TEMPLE ROAD."
Est.Cost:- Rs.20,000/-
17894.40
2765.76
20660.16
20000.00
(Rupees Twenty Thousand Only)
Nabarangpur Block
E WORK:-"CONST. OF CC ROAD FROM RD ROAD TO MOULIBANDH IN
TARAGAM GP".
Est.Cost:- Rs.1,50,000/-
444.58
3279.88
93871.92
85953.63
1500.00
184605.43
150000.00
(Rupees One Lakh & Fifty thousand Only)
Junior Engineer
Nabarangpur Block
Nabarangpur
T. OF MARKET SHED AT ."
Est.Cost:- Rs.2,50,000/-
1661.29
4100.38
20391.65
27135.81
75900.99
75241.08
1716.65
23674.11
15923.69
7084.67
1479.04
1223.02
5984.11
2000.00
263516.47
250000.00
(Rupees Two Lakhs & Fifty Thousand Only)
Junior Engineer
Nabarangpur Block
6000.13
2141.32
56635.45
59473.61
182063.27
111215.04
270850.01
3297.67
3819.78
39245.89
39274.77
3742.74
32586.54
34652.74
127373.05
90695.43
37630.11
37698.70
11242.78
10979.52
109909.80
5000.00
29575.94
18808.41
8306.69
35203.45
14787.30
7530.85
14880.74
4196.33
2756.53
70000.00
66000.00
50000.00
1597574.58
1500000.00
(Rupees Fifteen Lakhs Only)
Est.Cost:- Rs.9,75,000/-
5632.61
29491.64
49161.17
214129.70
186917.79
7368.48
10967.53
44204.82
52999.52
161181.17
33340.32
12663.12
130000.00
1000.00
18473.10
15000.00
3000.00
975530.96
975000.00
(Rupees Nine Lac seventy five thousand Only)
-"CONST. OF RESIDENTIAL BUILDING CUM SHOPPING
RAIGHAR OVER KHATA NO PLOT NO
Est.Cost:- Rs.5,36,000/-
113647.94
127341.29
46075.29
48093.68
93559.54
28641.54
10949.25
25000.00
11236.72
17074.71
15000.00
536619.95
536000.00
(Rupees Five Lac & Thirty six thousand Only)
K:-"CONST. OF CC ROAD AT MANTRIGUDA PUJARIGUDIA SAHI".
Est.Cost:- Rs.1,06,000/-
Head of Account:- TFC
1104.81
4872.03
48795.83
56497.61
2639.52
455.43
1500.00
115865.23
106000.00
(Rupees One Lakh six thousand Only)
Junior Engineer
Nabarangpur Block
66443.26
64887.10
1794.02
25289.95
15560.65
8879.98
97449.62
29039.41
7791.67
35314.56
22779.75
7564.46
42636.56
13466.02
14347.20
2000.00
10000.00
26000.00
20000.00
10000.00
2000.00
523244.21
500000.00
(Rupees Five Lacs Only)
Junior Engineer
Nabarangpur Block
"CONST. OF STORAGE GODOWN OF NABARANGPUR LAMPCS."
Est.Cost:- Rs.5,00,000/-
1814.01
12846.96
47547.16
67272.28
50238.50
61661.93
1804.23
1949.78
230.57
76802.82
24661.18
5391.16
9800.00
6000.00
414.24
272.11
14021.95
6201.50
34540.00
93000.00
15000.00
531470.39
500000.00
(Rupees Five Lakhs Only)
JUNIOR ENGINEER
NABARANGPUR BLOCK
12434.31
18894.00
3260.04
1200.00
35788.35
40000.00
(Rupees Forty thousand Only)
Junior Engineer
Nabarangpur Block
NST. OF KITCHEN CUM STORE ROOM AT ."
Est.Cost:- Rs.60,000/-
278.71
626.86
4118.12
8483.52
9276.34
9195.68
217.88
505.91
3209.45
1235.58
624.38
12679.84
3817.65
1047.87
905.59
6000.00
315.98
200.64
1500.00
600.00
64839.99
60000.00
(Rupees Sixty Thousand Only)
Junior Engineer
Nabarangpur Block
HE WORK:-"CONST. OF SHG BUILDING AT URDI."
Est.Cost:- Rs.5,00,000/-
3424.07
1264.39
33015.76
46927.13
99584.37
104888.46
2203.67
2500.68
17417.33
23622.47
77644.38
17769.42
14316.24
7276.34
18865.00
4000.00
12000.00
1100.00
1057.54
694.69
9139.18
1679.61
2133.51
2236.50
2880.00
20000.00
8000.00
1500.00
537140.74
500000.00
(Rupees Five Lakhs Only)
BLOCK DEV.OFFICER
NABARANGPUR BLOCK
WORK:-"CONST. OF GP BUILDING AT SANAMASIGAM."
Est.Cost:- Rs.5,00,000/-
2937.83
34073.25
49067.61
97702.90
90800.10
2276.92
2707.80
15417.93
25719.42
100356.89
30406.46
10025.05
8377.74
23000.00
6000.00
12000.00
1300.00
1352.11
888.19
2225.29
2160.00
3324.24
3408.00
10368.00
2600.00
538495.72
500000.00
(Rupees Five Lakhs Only)
JUNIOR ENGINEER
NABARANGPUR BLOCK
1381.97
18454.83
21367.69
1500.00
42704.49
40000.00
Junior Engineer
Nabarangpur Block
NST. OF PATIENT CABIN AT DISTRICT HEAD QUARTER HOSPITAL
MPUS,NABARANGPUR."
Est.Cost:- Rs.6,00,000/-
3607.28
1116.57
25049.24
28187.15
70398.73
74148.33
1682.19
1204.93
13031.96
18289.90
78985.55
8275.73
19474.04
5661.96
5250.00
12000.00
39728.88
14723.50
6742.35
19605.23
9101.44
192.67
126.56
45646.00
36517.00
80000.00
1000.00
619747.19
600000.00
(Rupees Six Lakhs Only)
Cum
967.41
6994.94
Cum
822.18
799.14
645.48
2050.83
6500.00
1500.00
20279.98
20000.00
(Rupees Twenty Thousand Only)
5435.05
22483.40
29580.67
59947.66
63140.61
1545.59
1892.91
11264.24
9710.61
47856.99
9763.63
13093.41
5889.82
5418.59
40126.13
4753.66
978.97
643.08
33537.00
25000.00
33288.00
45000.00
21000.00
4914.00
1500.00
4978.00
499613.51
500000.00
(Rupees Five Lakhs Only)
Junior Engineer
Nabarangpur Block
THE WORK:-"CONST. OF HAT MANDAP AT CHATTAHANDI."
Est.Cost:- Rs.4,20,000/-
2063.74
9020.33
32609.90
33717.48
116577.78
122786.97
2877.26
0.00
14592.31
26023.89
18743.65
18067.03
5650.23
3233.95
10867.03
4148.00
420979.54
420000.00
(Rupees Four Lakh Twenty Thousand Only)
HE WORK:-"CONST. OF OPEN TOILET NEAR HAT MANDAP AT
CHATTAHANDI." Est.Cost:- Rs.70,000/-
493.08
912.07
5244.30
9177.43
2996.78
3156.39
480.39
599.48
17791.62
4919.82
1075.52
1663.61
6151.61
2215.20
8304.00
5000.00
647.00
70828.30
70000.00
(Rupees Seventy Thousand Only)
THE WORK:-"CONST. CC ROAD & DRAIN AT SANKUSUMI."
Est.Cost:- Rs.1,06,000/-
1242.91
5481.04
54895.31
42373.21
1000.00
1060.00
106052.46
106000.00
(Rupees One Lakh & six Thousand Only)
WORK:-"CONST. OF LIVESTOCK AID CENTRE AT
CHATTAHANDI."
Est.Cost:- Rs.4,25,000/-
1401.40
4926.38
18167.22
21039.37
51561.57
57502.43
1534.01
1710.41
10445.02
11456.48
55301.71
4544.61
18030.10
4821.46
36000.00
1000.00
4531.55
1152.59
757.13
30000.00
30000.00
45000.00
2000.00
4250.00
417133.44
425000.00
(Rupees Four Lakhs & Twenty Five Thousand Only)
Junior Engineer
Nabarangpur Block
(-)
(-)
(-)
(-)
(-)
(-)
(-)
(-)
(-)
(-)
DETAILED ESTIMATE FOR THE WORK:-"IMPV OF ROAD FROM EKAMBA TO NUAGAM ROAD."
Est.Cost:- Rs.3,00,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Guard wall 1 X 87.00 X 1.05 X 1.05 = 95.92 Cum
Total = 95.92 Cum
@ Rs. 4721.40 Per 100 Cum Rs 4528.65
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Guard wall 1 X 87.00 X 1.05 X 0.05 = 4.57 Cum
Total = 4.57 Cum
@ Rs. 208.21 Per Cum Rs 950.98
3 CC (1:4:8) using 40 mm size cbg metal including all cost,conveyance
royality etc.complete
Guard wall 1 X 87.00 X 1.05 X 0.15 = 13.70 Cum
1 X 87.00 X (1.05+0.50 X 2.05 = 138.22 Cum
Total = 151.92 Cum
@ Rs. 1701.52 Per Cum Rs 258501.30
4 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Guard wall 1 X 2 X 87.00 X 2.05 = 356.70 Sqm
Total = 356.70 Sqm
@ Rs. 58.48 Per Sqm Rs 20859.82
5 12 mm CP in CM (1:6) to the Super structure
Guard wall 1 X 2 X 87.00 X 1.20 = 208.80 Sqm
Total = 208.80 Sqm
@ Rs. 48.01 Per Sqm Rs 10024.41
6 PCC (1:2:4) using 12 mm size cbg chips including all complete.
Guard wall 1 X 87.00 X 0.50 X 0.05 = 2.18 Cum
Total = 2.18 Cum
@ Rs. 2577.56 Per Cum Rs 5606.19
7 Provision for work Transperancy board (1.50X1.80) mtr size & Photograph Rs 1500.00
Grand Total Rs. 301971.35
Say Rs. 300000.00
(Rupees Three Lakhs Only)
Technically Sanctioned for Rs.3,00,000/-
(Rupees Three Lakhs Only)
Est.Cost:- Rs.1,50,000/-
royality etc.complete
Est.Cost:- Rs.2,00,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Pillar 6 X 1.20 X 1.20 X 1.20 = 10.37 Cum
Long Wall 2 X 3.46 X 0.75 X 0.75 = 3.89 Cum
1 X 1.88 X 0.75 X 0.75 = 1.06 Cum
1 X 2.48 X 0.75 X 0.75 = 1.40 Cum
Short Wall 3 X 4.06 X 0.75 X 0.75 = 6.85 Cum
Latrine 2 X 0.83 X 0.75 X 0.75 = 0.93 Cum
1 X 2.63 X 0.75 X 0.75 = 1.48 Cum
Septic Tank 1 X 1.50 X 2.00 X 2.00 = 6.00 Cum
Total = 31.98 Cum
@ Rs. 4721.40 Per 100 Cum Rs 1509.78
2 Sand filling to the foundation & plinth with watering , ramming
Pillar 6 X 1.20 X 1.20 X 0.10 = 0.86 Cum
Long Wall 2 X 3.46 X 0.75 X 0.10 = 0.52 Cum
1 X 1.88 X 0.75 X 0.10 = 0.14 Cum
1 X 2.48 X 0.75 X 0.10 = 0.19 Cum
Short Wall 3 X 4.06 X 0.75 X 0.10 = 0.91 Cum
Latrine 2 X 0.83 X 0.75 X 0.05 = 0.06 Cum
1 X 2.63 X 0.75 X 0.05 = 0.10 Cum
Septic Tank 1 X 1.50 X 2.00 X 0.05 = 0.15 Cum
Total = 2.93 Cum
@ Rs. 208.21 Per Cum Rs 610.96
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Pillar 6 X 1.20 X 1.20 X 0.15 = 1.30 Cum
Long Wall 2 X 3.46 X 0.75 X 0.15 = 0.78 Cum
1 X 1.88 X 0.75 X 0.15 = 0.21 Cum
1 X 2.48 X 0.75 X 0.15 = 0.28 Cum
Short Wall 3 X 4.06 X 0.75 X 0.15 = 1.37 Cum
Latrine 2 X 0.83 X 0.75 X 0.10 = 0.12 Cum
1 X 2.63 X 0.75 X 0.10 = 0.20 Cum
Septic Tank 1 X 1.50 X 2.00 X 0.10 = 0.30 Cum
Total = 4.56 Cum
@ Rs. 2085.29 Per Cum Rs 9502.68
4 RR stone massonary in CM (1:6) to the F&P including all
cost,conveyance,royality etc. complete.
1st footing Long Wall 2 X 5.40 X 0.60 X 0.45 = 2.92 Cum
1 X 2.03 X 0.60 X 0.45 = 0.55 Cum
1 X 2.63 X 0.60 X 0.45 = 0.71 Cum
Short Wall 3 X 5.03 X 0.60 X 0.45 = 4.07 Cum
Latrine 2 X 0.93 X 0.50 X 0.45 = 0.42 Cum
1 X 2.53 X 0.50 X 0.45 = 0.57 Cum
2nd footing Long Wall 2 X 5.40 X 0.45 X 0.45 = 2.19 Cum
1 X 2.18 X 0.45 X 0.45 = 0.44 Cum
1 X 2.78 X 0.45 X 0.45 = 0.56 Cum
Short Wall 3 X 5.03 X 0.45 X 0.45 = 3.06 Cum
Latrine 2 X 0.98 X 0.45 X 0.45 = 0.40 Cum
1 X 2.48 X 0.45 X 0.45 = 0.50 Cum
Total = 16.38 Cum
@ Rs. 1419.53 Per Cum Rs 23255.48
5 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Pillar 6 X 1.00 X 1.00 X 0.30 = 1.80 Cum
6 X (1+0.23)/2 X (1+0.23)/2 X 0.45 = 1.02 Cum
6 X 0.23 X 0.23 X 3.95 = 1.25 Cum
Plinth Beam 1 X 35.95 X 0.23 X 0.15 = 1.24 Cum
Lintel Bend 1 X 32.95 X 0.23 X 0.15 = 1.14 Cum
Ver Beam 1 X 3.00 X 0.23 X 0.23 = 0.16 Cum
1 X 1.80 X 0.23 X 0.23 = 0.10 Cum
Chujja 6 X 1.20 X 0.50 X 0.06 = 0.22 Cum
1 X 4.20 X 0.50 X 0.06 = 0.13 Cum
1 X 1.80 X 0.50 X 0.06 = 0.05 Cum
Slab 1 X 6.40 X 5.80 X 0.10 = 3.71 Cum
1 X 2.56 X 1.58 X 0.10 = 0.40 Cum
Septic Tank 1 X 1.50 X 2.00 X 0.10 = 0.30 Cum
Total = 11.52 Cum
@ Rs. 3317.48 Per Cum Rs 38212.01
6 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Total 8.64 Qtl
@ Rs. 4110.80 Per Qtl Rs 35512.30
7 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Pillar 6 X 2 X (1+0.23)/2 X 0.45 = 3.32 Sqm
Plinth bend 1 X 2X 35.95 X 0.23 = 16.54 Sqm
Total = 19.86 Sqm
@ Rs. 60.93 Per Sqm Rs 1209.93
ii) Lintel Bend 1 X 2X 32.95 X 0.15 = 9.89 Sqm
Total = 9.89 Sqm
@ Rs. 141.47 Per Sqm Rs 1398.46
iii) Column,beam 6 X 1 X 3.95 X 0.92 = 21.80 Sqm
1 X 1 X 3.00 X 0.69 = 2.07 Sqm
1 X 1 X 1.80 X 0.69 = 1.24 Sqm
Total = 25.12 Sqm
@ Rs. 278.27 Per Sqm Rs 6988.95
iv) Slab & Chajja 6 X 1 X 1.20 X 0.50 = 3.60 Sqm
1 X 1 X 3.00 X 0.50 = 1.50 Sqm
1 X 1 X 1.80 X 0.50 = 0.90 Sqm
1 X 1 X 6.40 X 5.80 = 37.12 Sqm
1 X 1 X 2.56 X 1.58 = 4.04 Sqm
1 X 1X 1.50 X 2.00 = 3.00 Sqm
Total = 50.16 Sqm
@ Rs. 192.14 Per Sqm Rs 9638.72
8 WBCB in CM (1:6) in superstructure including all cost, conveyance
royality etc complete.
Long Wall 2 X 5.40 X 0.23 X 2.85 = 7.08 Cum
1 X 3.00 X 0.23 X 2.85 = 1.97 Cum
1 X 1.80 X 0.23 X 2.85 = 1.18 Cum
Short Wall 3 X 5.03 X 0.23 X 2.85 = 9.89 Cum
Wall above Verandah 1 X 3.00 X 0.23 X 0.60 = 0.41 Cum
1 X 1.80 X 0.23 X 0.60 = 0.25 Cum
Latrine 1 X 2.26 X 0.23 X 2.85 = 1.48 Cum
2 X 1.20 X 0.23 X 2.85 = 1.57 Cum
2 X 1.04 X 0.23 X 2.00 = 0.96 Cum
2 X 2.00 X 0.23 X 2.00 = 1.84 Cum
Total = 26.63 Cum
Deduction
Ver Opening 1 X 3.00 X 0.23 X 2.00 = 1.38 Cum
Door Opening 4 X 1.20 X 0.23 X 2.00 = 2.21 Cum
1 X 0.75 X 0.23 X 2.00 = 0.35 Cum
Window Opening 6 X 0.90 X 0.23 X 1.20 = 1.49 Cum
Total = 4.04 Cum
Net Qty = 22.59 Cum
@ Rs. 1947.29 Per Cum Rs 43984.87
9 12 mm CP in CM (1:6) to the Super structure
Out side 2 X 1X 6.09 X 3.00 = 36.54 Sqm
2 X 1X 5.50 X 3.00 = 33.00 Sqm
Inside 2 X 1X 3.00 X 3.00 = 18.00 Sqm
2 X 1X 1.80 X 3.00 = 10.80 Sqm
1 X 2X 3.00 X 3.00 = 18.00 Sqm
1 X 2X 3.00 X 3.00 = 18.00 Sqm
2 X 2X 2.40 X 3.00 = 28.80 Sqm
2 X 2X 2.40 X 3.00 = 28.80 Sqm
Latrine 1 X 2X 1.43 X 3.00 = 8.58 Sqm
1 X 1X 2.26 X 3.00 = 6.78 Sqm
1 X 2X 1.20 X 3.00 = 7.20 Sqm
1 X 1X 1.80 X 3.00 = 5.40 Sqm
Septic Tank 1 X 2X 1.04 X 2.00 = 4.16 Sqm
1 X 2X 2.00 X 2.00 = 8.00 Sqm
Total = 232.06 Sqm
Deduction
Ver Opening 1 X 2 X 3.00 X 2.00 = 12.00 Sqm
Door Opening 4 X 2 X 1.20 X 2.00 = 19.20 Sqm
1 X 2 X 0.75 X 2.00 = 3.00 Sqm
Window Opening 6 X 2 X 0.90 X 1.20 = 12.96 Sqm
Total = 35.16 Sqm
Net Qty = 196.90 Sqm
@ Rs. 48.01 Per Sqm Rs 9453.09
10 Finishing wall surface with water proofing cement paint
of approved shade of 2 coats to give an even shade excluding
cost of paint.
Qty as per Item No 9 i.e = 196.90 Sqm
Add for ceiling = 44.16 Sqm
Total = 241.06 Sqm
@ Rs. 14.76 Per Sqm Rs 3557.48
11 Cost of Iron Door & Window
Total 450.00 Kg
@ 49.00 Per Kg Rs 22050.00
Vantilator 10 Nos @ 50.00/No Rs 500.00
12 Painting 2 coats with any approved Paint ( Labour Only )
Door 4 X 2.25 X 1.20 X 2.00 = 21.60 Sqm
Window 6 X 2.75 X 0.90 X 1.20 = 17.82 Sqm
Total = 39.42 Sqm
@ Rs. 28.54 Per Sqm Rs 1125.19
13 Cost of Paint
Qty = 4.93 Litre
@ Rs. 150.00 Per Litre Rs 739.13
14 2.50 CmM thick AS flooring in CC (1:2:4) using 12 mm size hbg
Chips including all cost , conveyance , royality etc. complete
Room 1 X 3.00 X 1.80 = 5.40 Sqm
1 X 3.00 X 3.00 = 9.00 Sqm
1 X 1.80 X 1.20 = 2.16 Sqm
2 X 2.40 X 2.40 = 11.52 Sqm
Total = 28.08 Sqm
@ Rs. 120.74 Per Sqm Rs 3390.51
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
Administratively approved for Rs.2,50,000/-
(Rupees Two Lakh & Fifty thousand Only)
6 Cess1% Rs 1150.00
Grand Total Rs. 126759.16
Say Rs. 115000.00
(Rupees One Lakh & Fifteen thousand Only)
Technically Sanctioned for Rs.1,15,000/-
(Rupees One Lakh & Fifteen thousand Only)
Junior Engineer
Nabarangpur Block
Junior Engineer
Nabarangpur Block
Administratively approved for Rs.1,15,000/-
(Rupees One Lakh & Fifteen thousand Only)
Sarapanch
Chattahandi GP
DETAILED WORK DONE ESTIMATE FOR THE WORK:-"CONST. OF CC ROAD AT VILLAGE
ATAKABEDA IN BADAKUMULI GP".
Est.Cost:- Rs.2,50,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Mandap 1 X 19.00 X 0.30 X 0.30 = 1.71 Cum
Wall 2 X 45.00 X 0.23 X 0.23 = 4.76 Cum
2 X 49.00 X 0.23 X 0.23 = 5.18 Cum
Road 2 X 28.00 X 0.23 X 0.23 = 2.96 Cum
Total = 14.62 Cum
@ Rs. 4721.40 Per 100 Cum Rs 690.16
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Mandap 2 X 4.75 X 2.00 X 0.35 = 6.65 Cum
2 X 2.75 X 2.00 X 0.35 = 3.85 Cum
Road 1 X 28.00 X 3.54 X 0.05 = 4.96 Cum
Total = 15.46 Cum
@ Rs. 208.21 Per Cum Rs 3218.04
3 CC (1:4:8) using40 mm size cbg metal including all cost,conveyance
royality etc.complete
Mandap 1 X 19.00 X 0.30 X 0.75 = 4.28 Cum
1 X 19.00 X 2.00 X 0.10 = 3.80 Cum
Road 1 X 45.00 X (4.10+3.7)/2 X 0.10 = 17.55 Cum
1 X 49.00 X (5.20+3.85)/2 X 0.10 = 22.17 Cum
Wall 2 X 45.00 X 0.23 X 0.23 = 4.76 Cum
2 X 49.00 X 0.23 X 0.23 = 5.18 Cum
Road 1 X 28.00 X 4.00 X 0.10 = 11.20 Cum
Road 2 X 28.00 X 0.23 X 0.23 = 2.96 Cum
Total = 71.91 Cum
@ Rs. 2208.17 Per Cum Rs 158778.83
3 CC (1:2:4) using 12 mm size cbg Chips including all cost, conveyance
royality etc complete.
Mandap 1 X 19.00 X 2.00 X 0.075 = 2.85 Cum
Road 1 X 45.00 X (4.10+3.7)/2 X 0.075 = 13.16 Cum
1 X 49.00 X (5.2+3.85)/2 X 0.075 = 16.63 Cum
Road 1 X 28.00 X 4.00 X 0.075 = 8.40 Cum
Total = 41.04 Cum
@ Rs. 3380.34 Per Cum Rs 138735.37
4 Provision for work Transperancy board (1.50X1.80) mtr size Rs 2000.00
Grand Total Rs. 302732.24
Say Rs. 250000.00
(Rupees Two Lakh & Fifty thousand Only)
Technically Sanctioned for Rs.2,50,000/-
(Rupees Two Lakh & Fifty thousand Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
Block Dev. Officer
Nabarangpur
Administratively approved for Rs.2,50,000/-
(Rupees Two Lakh & Fifty thousand Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
Block Dev. Officer
Nabarangpur
Administratively approved for Rs.2,50,000/-
(Rupees Two Lakh & Fifty thousand Only)
Est.Cost:- Rs.2,50,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Guard wall 1 X 41.70 X 1.05 X 1.05 = 45.97 Cum
Culvert ( U/S cutt-off) 1 X 8.40 X 1.20 X 1.20 = 12.10 Cum
Culvert ( D/S cutt-off) 1 X 8.40 X 1.20 X 1.50 = 15.12 Cum
Abutment 2 X 3.80 X 1.20 X 1.20 = 10.94 Cum
Bed 1 X 3.80 X 1.70 X 0.45 = 2.91 Cum
Total = 87.04 Cum
@ Rs. 4721.40 Per 100 Cum Rs 4109.57
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Guard wall 1 X 41.70 X 1.05 X 0.05 = 2.19 Cum
Culvert ( U/S cutt-off) 1 X 8.40 X 1.20 X 0.15 = 1.51 Cum
Culvert ( D/S cutt-off) 1 X 8.40 X 1.20 X 0.15 = 1.51 Cum
Abutment 2 X 3.80 X 1.20 X 0.15 = 1.37 Cum
Bed 1 X 3.80 X 1.70 X 0.15 = 0.97 Cum
Total = 7.55 Cum
@ Rs. 208.21 Per Cum Rs 1572.01
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Guard wall 1 X 41.70 X 1.05 X 0.15 = 6.57 Cum
1 X 41.70 X (1.05+0.50)/2 X 1.85 = 59.79 Cum
Culvert ( U/S cutt-off) 1 X 8.40 X 1.20 X 0.15 = 1.51 Cum
1 X 8.40 X (1.00+0.75)/2 X 0.90 = 4.73 Cum
Culvert ( D/S cutt-off) 1 X 8.40 X 1.20 X 0.15 = 1.51 Cum
1 X 8.40 X (1.00+0.75)/2 X 0.90 = 4.73 Cum
Abutment 2 X 3.80 X 1.20 X 0.30 = 2.74 Cum
2 X 3.80 X (1.00+0.75)/2 X 0.75 = 4.99 Cum
2 X 6.00 X (0.75+0.0.50)/2 X 1.15 = 8.63 Cum
Wing wall 4 X 2.00 X (0.75+0.0.50)/2 X 1.15 = 5.75 Cum
Bed 1 X 4.50 X 2.00 X 0.30 = 2.70 Cum
Parapet 2 X 3.00 X 0.45 X 0.45 = 1.22 Cum
Total = 104.84 Cum
@ Rs. 2085.29 Per Cum Rs 218627.49
4 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Slab 1 X 6.00 X 3.00 X 0.25 = 4.50 Cum
Total = 4.50 Cum
@ Rs. 3317.48 Per Cum Rs 14928.66
5 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 4.05 Qtl
@ Rs. 4110.80 Per Qtl Rs 16648.72
6 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Guard wall 1 X 2 X 41.70 X 1.85 = 154.29 Sqm
Culvert ( U/S cutt-off) 1 X 2 X 8.40 X 0.90 = 15.12 Sqm
Culvert ( D/S cutt-off) 1 X 2 X 8.40 X 0.90 = 15.12 Sqm
Abutment 2 X 2 X 3.80 X 0.75 = 11.40 Sqm
2 X 2 X 6.00 X 1.00 = 24.00 Sqm
Wing wall 4 X 2 X 2.00 X 1.15 = 18.40 Sqm
Parapet 2 X 2 X 3.00 X 0.45 = 5.40 Sqm
Total = 243.73 Sqm
@ Rs. 60.93 Per Sqm Rs 14850.27
ii) Slab 1 X 1 X 6.00 X 3.00 = 18.00 Sqm
@ Rs. 192.14 Per Sqm Rs 3458.54
7 12 mm CP in CM (1:6) to the Super structure
Guard wall 1 X 2 X 41.70 X 1.00 = 83.40 Sqm
Abutment 2 X 1 X 6.00 X 1.00 = 12.00 Sqm
Wing wall 4 X 1 X 2.00 X 1.15 = 9.20 Sqm
Parapet 2 X 2 X 3.00 X 0.45 = 5.40 Sqm
Total = 110.00 Sqm
@ Rs. 48.01 Per Sqm Rs 5281.06
8 PCC (1:2:4) using 12 mm size hbg chips including all complete.
Guard wall 1 X 41.70 X 0.50 X 0.05 = 1.04
Cum
Pier Cap 2 X 6.00 X 0.50 X 0.075 = 0.45
Cum
Bed 1 X 6.00 X 2.00 X 0.075 = 0.90
Cum
Wing wall 4 X 2.00 X 0.50 X 0.05 = 0.20
Cum
Parapet 2 X 3.00 X 0.45 X 0.05 = 0.14
Cum
Total = 2.73
Cum
@ Rs. 3219.24 Per Cum Rs 8780.47
9 Provision for work Transperancy board (1.50X1.80) mtr size Rs 2000.00
10 Provision for Contigency(1%) Rs 2500.00
Grand Total Rs. 292756.77
Say Rs. 250000.00
(Rupees Two Lakh & Fifty thousand Only)
Technically Sanctioned for Rs.2,50,000/-
(Rupees Two Lakh & Fifty thousand Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
Administratively approved for Rs.2,50,000/-
(Rupees Two Lakh & Fifty thousand Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
Block Dev. Officer
Nabarangpur
Administratively approved for Rs.2,50,000/-
(Rupees Two Lakh & Fifty thousand Only)
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM BHATRA TO SEUNI WITH CD WORK ".
Est.Cost:- Rs.2,50,000/-
1 Providing , laying, spreading & compacting stone aggregates
of specific sizes to WBM specification including spreading uniform
thickness,hand packing,rolling with 3-wheeled steel rollers
8-10 tonnes in stages to proper grade & camber applying & brooming requisites
type of coarse aggregates,watering & compacting to the required density as per clause
404 of MoSRT&H specification for road & bridge works.
Grade-II ( Road ) 1 X 557.00 X 3.00 X 0.075 = 125.33 Cum
@ Rs. 1101.22 Per Cum Rs 138010.10
2 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Road(Flank Dressing 2 X 557.00 X 0.60 X 0.30 = 200.52 Cum
@ Rs. 3947.40 Per 100 Cum Rs 7915.33
3 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Culvert-1
Culvert ( U/S cutt-off) 1 X 8.40 X 1.20 X 1.20 = 12.10 Cum
Culvert ( D/S cutt-off) 1 X 8.40 X 1.20 X 1.50 = 15.12 Cum
Abutment 2 X 3.80 X 1.20 X 1.20 = 10.94 Cum
Bed 1 X 3.80 X 1.70 X 0.45 = 2.91 Cum
Total = 41.07 Cum
@ Rs. 4721.40 Per 100 Cum Rs 1938.94
4 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Culvert-1
Culvert ( U/S cutt-off) 1 X 8.40 X 1.20 X 0.15 = 1.51 Cum
Culvert ( D/S cutt-off) 1 X 8.40 X 1.20 X 0.15 = 1.51 Cum
Abutment 2 X 3.80 X 1.20 X 0.15 = 1.37 Cum
Bed 1 X 3.80 X 1.70 X 0.15 = 0.97 Cum
Total = 5.36 Cum
@ Rs. 208.21 Per Cum Rs 1116.19
5 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Culvert-1
Culvert ( U/S cutt-off) 1 X 8.40 X 1.20 X 0.15 = 1.51 Cum
1 X 8.40 X (1.00+0.75)/2 X 0.90 = 4.73 Cum
Culvert ( D/S cutt-off) 1 X 8.40 X 1.20 X 0.15 = 1.51 Cum
1 X 8.40 X (1.00+0.75)/2 X 0.90 = 4.73 Cum
Abutment 2 X 3.80 X 1.20 X 0.30 = 2.74 Cum
2 X 3.80 X (1.00+0.75)/2 X 0.75 = 4.99 Cum
2 X 6.00 X (0.75+0.0.50)/2 X 1.15 = 8.63 Cum
Wing wall 4 X 2.00 X (0.75+0.0.50)/2 X 1.15 = 5.75 Cum
Bed 1 X 4.50 X 2.00 X 0.30 = 2.70 Cum
Parapet 2 X 3.00 X 0.45 X 0.45 = 1.22 Cum
Total = 38.49 Cum
@ Rs. 2085.29 Per Cum Rs 80257.68
6 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Slab-1 1 X 6.00 X 3.00 X 0.25 = 4.50 Cum
Total = 4.50 Cum
@ Rs. 3317.48 Per Cum Rs 14928.66
7 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 4.05 Qtl
@ Rs. 4110.80 Per Qtl Rs 16648.72
8 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
Slab-1
i) Culvert ( U/S cutt-of 1 X 2 X 8.40 X 0.90 = 15.12 Sqm
Culvert ( D/S cutt-off) 1 X 2 X 8.40 X 0.90 = 15.12 Sqm
Abutment 2 X 2 X 3.80 X 0.75 = 11.40 Sqm
2 X 2 X 6.00 X 1.00 = 24.00 Sqm
Wing wall 4 X 2 X 2.00 X 1.15 = 18.40 Sqm
Parapet 2 X 2 X 3.00 X 0.45 = 5.40 Sqm
Total = 89.44 Sqm
@ Rs. 60.93 Per Sqm Rs 5449.51
Slab-1 1 X 1 X 6.00 X 3.00 = 18.00 Sqm
Total = 18.00 Sqm
@ Rs. 192.14 Per Sqm Rs 3458.54
9 12 mm CP in CM (1:6) to the Super structure
Slab-1
Abutment 2 X 1 X 6.00 X 1.00 = 12.00 Sqm
Wing wall 4 X 1 X 2.00 X 1.15 = 9.20 Sqm
Parapet 2 X 2 X 3.00 X 0.45 = 5.40 Sqm
Total = 26.60 Sqm
@ Rs. 48.01 Per Sqm Rs 1277.06
10 PCC (1:2:4) using 12 mm size hbg chips including all complete.
Slab-1
Pier Cap 2 X 6.00 X 0.50 X 0.075 = 0.45 Cum
Bed 1 X 6.00 X 2.00 X 0.075 = 0.90 Cum
Wing wall 4 X 2.00 X 0.50 X 0.05 = 0.20 Cum
Parapet 2 X 3.00 X 0.45 X 0.05 = 0.14 Cum
Total = 1.69 Cum
@ Rs. 3219.24 Per Cum Rs 5424.41
11 Provision for Signboard & Photograph Rs 2000.00
Total Rs 278425.13
Say Rs. 250000.00
(Rupees Two Lakh & Fifty thousand Only)
Technically Sanctioned for Rs.2,50,000/-
(Rupees Two Lakh & Fifty thousand Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
Block Dev. Officer
Nabarangpur
Administratively approved for Rs.2,50,000/-
(Rupees Two Lakh & Fifty thousand Only)
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM URDI TO BAGH-SEUNI NADIGHAT IN
BADAKUMULI GP".
Est.Cost:- Rs.2,50,000/-
1 Providing , laying, spreading & compacting stone aggregates
of specific sizes to WBM specification including spreading uniform
thickness,hand packing,rolling with 3-wheeled steel rollers
8-10 tonnes in stages to proper grade & camber applying & brooming requisites
type of coarse aggregates,watering & compacting to the required density as per clause
404 of MoSRT&H specification for road & bridge works.
Grade-II ( Road ) 1 X 1040.00 X 3.00 X 0.075 = 234.00 Cum
@ Rs. 1101.22 Per Cum Rs 257684.93
2 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Road(Flank Dressing 2 X 1040.00 X 0.60 X 0.30 = 374.40 Cum
@ Rs. 3947.40 Per 100 Cum Rs 14779.07
3 Provision for Signboard & Photograph Rs 2000.00
Total Rs 274464.00
Say Rs. 250000.00
(Rupees Two Lakh & Fifty thousand Only)
Technically Sanctioned for Rs.2,50,000/-
(Rupees Two Lakh & Fifty thousand Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
Block Dev. Officer
Nabarangpur
Administratively approved for Rs.2,50,000/-
(Rupees Two Lakh & Fifty thousand Only)
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM URDI TO BAGH-SEUNI NADIGHAT IN
BADAKUMULI GP ".
Est.Cost:- Rs.2,50,000/-
1 Collecting , conveying,supplying of good quality hard metal
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road 1 X 793.00 X 3.00 X 0.10 = 237.90 Cum
@ Rs. 414.40 Per Cum Rs 98585.76
2 Collecting , conveying,supplying of good quality murrom or gravel
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road Sub base 1 X 793.00 X 3.00 X 0.15 = 356.85 Cum
Add for metal Consolidation 25% of metal Qty. = 59.48 Cum
Total = 416.33 Cum
@ Rs. 188.00 Per Cum Rs 78269.10
3 Labour for laying sub-base in layers not exceeding
150 mm thick watering,compacting to the required density in OMC
with PRR but excluding cost & conveyance of Sub-base materials
Road 1 X 793.00 X 3.00 X 0.15 = 356.85 Cum
@ Rs. 87.23 Per Cum Rs 31128.48
4 Labour for spreading metal & packing the voids with small stones
& hand packing the same to proper camber including conveying , spreading
of filler material & filling the interstics by spreading the same over the surface
watering & consolidation with PRR including hire & running charges of PRR
but excluding the cost of metal & filler material.
Road 1 X 793.00 X 3.00 X 0.10 = 237.90 Cum
@ Rs. 191.92 Per Cum Rs 45657.43
5 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Road 2 X 793.00 X 0.60 X 0.25 = 237.90 Cum
Total = 237.90 Cum
@ Rs. 3947.40 Per 100 Cum Rs 9390.86
6 Provision for Work Sign board & Photograph Rs. 2000.00
Grand Total Rs. 265031.63
Say Rs. 250000.00
(Rupees Two Lakh & Fifty thousand Only)
Technically Sanctioned for Rs.2,50,000/-
(Rupees Two Lakh & Fifty thousand Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
Block Dev. Officer
Nabarangpur
Administratively approved for Rs.2,50,000/-
(Rupees Two Lakh & Fifty thousand Only)
DETAILED WORK DONE ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM RD ROAD TO
BADMASIGAM GP OFFICE".
Est.Cost:- Rs.1,00,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Road 1 X 66.00 X 3.00 X 0.10 = 19.80 Cum
Total = 19.80 Cum
@ Rs. 4721.40 Per 100 Cum Rs 934.84
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Road 1 X 66.00 X 3.00 X 0.10 = 19.80 Cum
Total = 19.80 Cum
@ Rs. 208.21 Per Cum Rs 4122.49
3 CC (1:4:8) using40 mm size cbg metal including all cost,conveyance
royality etc.complete
Road 1 X 66.00 X 3.00 X 0.10 = 19.80 Cum
Total = 19.80 Cum
@ Rs. 2208.17 Per Cum Rs 43721.81
4 CC (1:2:4) using 12 mm size cbg Chips including all cost, conveyance
royality etc complete.
Road 1 X 66.00 X 3.00 X 0.075 = 14.85 Cum
Total = 14.85 Cum
@ Rs. 3380.34 Per Cum Rs 50198.00
5 Provision for work Transperancy board (1.50X1.80) mtr size Rs 2000.00
Grand Total Rs. 100042.30
Say Rs. 100000.00
(Rupees One Lakh Only)
Technically Sanctioned for Rs.1,00,000/-
(Rupees One Lakh Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
Est.Cost:- Rs.5,00,000/-
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur Block
288.88886383609
1.7632376943121
1 E/W in slushy soil in water up to 0.60 mtr depth requiring the aid of pans
Junior Engineer
Nabarangpur Block
Junior Engineer
Nabarangpur Block
Sarapanch
Badamasigamgam GP.
DETAILED ESTIMATE FOR THE WORK:-"REPAIR OF GODOWN OF KOSAGUMUDA LAMP".
Est.Cost:- Rs.9,800/-
from floor including stacking the useful materials for reuse & removing the debries
The estimate has been prepared basing on S/R 2008 & enhanced labour rate on request.
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF OVERHEAD TANK AT NURSERY,
NABARANGPUR
Est.Cost:- Rs.2,60,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"RENOVATION OF ALEKH MAHIMA PRAYER HALL AT KUKUDABAI
Est.Cost:- Rs.50,000/-
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF BOUNDARY WALL OF DFO OFFICE,
NABARANGPUR
Est.Cost:- Rs.1,58,040/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF BOUNDARY WALL OF DFO OFFICE,
NABARANGPUR
Est.Cost:- Rs.80000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF STORAGE GODOWN OF DFO OFFICE,
NABARANGPUR
Est.Cost:- Rs.1,20,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Long wall 3X 4.73 X 0.90 X 0.90 = 11.49
Cr. Wall 1X 2.33 X 0.90 X 0.90 = 1.89
1X 1.13 X 0.90 X 0.90 = 0.92
Total = 14.30 Cum
@ Rs. 5084.20 Per 100 Cum Rs 726.86
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Long wall 3X 4.73 X 0.90 X 0.15 = 1.92
Cr. Wall 1X 2.33 X 0.90 X 0.15 = 0.31
1X 1.13 X 0.90 X 0.15 = 0.15
Total = 2.38 Cum
@ Rs. 181.00 Per Cum Rs 431.28
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Long wall 3X 1.20 X 1.20 X 0.30 = 1.30
Cr. Wall 2X 1.73 X 0.60 X 0.15 = 0.31
2X 3.30 X 0.60 X 0.15 = 0.59
1X 5.18 X 2.48 X 0.10 = 1.28
Total = 3.49 Cum
@ Rs. 1622.80 Per Cum Rs 5657.15
4 Rcc (1:1.5:3) uing 12 mm ize hbg chip including ll complete.
Ground Floor
Long wall 3X 1.20 X 1.20 X 0.30 = 1.30
3 X (1.20+0.23)/2X(1.20+0.30)/2 X 0.45 = 0.72
3X 0.30 X 0.23 X 3.75 = 0.78
Grade beam 2X 5.40 X 0.30 X 0.23 = 0.75
2X 2.70 X 0.30 X 0.23 = 0.37
Beam 2X 5.40 X 0.30 X 0.23 = 0.75
2X 2.70 X 0.30 X 0.23 = 0.37
1X 2.70 X 0.30 X 0.30 = 0.24
Chuzza 2X 1.50 X 0.60 X 0.07 = 0.13
Slab 1X 6.16 X 3.46 X 0.10 = 2.13
Total = 7.53 Cum
@ Rs. 3023.45 Per Cum Rs 22773.07
5 Supplying,fitting,fixing of HYSD Bar reinforcement etc. complete.
Qty 8.00 Qtl @ Rs. 5000.00 per Qtl Rs 40000.00
6 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
Long wall 3 X 4X 1.20 X 0.30 = 4.32
3 X 2 X (1.20+0.30)/ X 0.45 = 2.03
3 X 2 X (1.20+0.23)/ X 0.45 = 1.93
Grade beam 2 X 2X 5.40 X 0.30 = 6.48
2 X 2X 2.70 X 0.30 = 3.24
Total = 18.00 Sqm
@ Rs. 54.90 Per Sqm Rs 987.95
Beam 2X 5.40 X 0.83 = 8.96
2X 2.70 X 0.83 = 4.48
2X 2.70 X 0.90 = 4.86
Long wall 9X 1.06 X 3.75 = 35.78
Total = 54.08 Sqm
@ Rs. 235.70 Per Sqm Rs 12746.89
Slab 1X 6.16 X 3.46 = 21.31
Chuzza 2X 1.50 X 0.60 = 1.80
Total = 23.11 Sqm
@ Rs. 179.30 Per Sqm Rs 4144.27
7 RRHGSM in CM (1:6) to the F&P
1st Footing
2 X 4.20 X 0.50 X 0.35 = 1.47
2 X 3.60 X 0.50 X 0.35 = 1.26
2nd Footing
2 X 4.20 X 0.45 X 0.45 = 1.70
2 X 3.60 X 0.45 X 0.45 = 1.46
Total = 5.89 Cum
@ Rs. 1117.25 Per Cum Rs 6579.49
8 2.50 cm thick A flooring in CC (1:2:4) uing 12 mm ize hbg chip
1X 3.60 X 4.20 = 15.12 Sqm
@ Rs. 92.40 Per Sqm Rs 1397.09
9 WBCB in CM (1:6) to the super structure
2 X 4.20 X 0.23 X 3.00 = 5.80
2 X 3.60 X 0.23 X 3.00 = 4.97
Total 10.76 Cum
Deduction
Door 1 X 1.20 X 0.23 X 2.00 = 0.55
Window 1 X 0.90 X 0.23 X 1.20 = 0.25
Total 0.80 Cum
Net Qty = 9.96 Cum
@ Rs. 1398.25 Per Cum Rs 13931.60
10 16 mm CP in CM (1:6) to the Super structure
2X 3.16 X 3.00 = 18.96
2X 5.86 X 3.00 = 35.16
Total 54.12 Sqm
Deduction
Door 2X 1.20 X 2.00 = 4.80
Window 2X 0.90 X 1.20 = 2.16
Total 6.96 Sqm
Net Qty = 47.16 Sqm
@ Rs. 52.00 Per Sqm Rs 2452.32
11 20 mm CP in CM (1:4) to the grading plaster to the
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"RENOVATION. OF OUT HOUSEOF DFO RES.
NABARANGPUR
Est.Cost:- Rs.50,000/-
1 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
1X 11.60 X 3.80 X 0.10 = 4.41
Total = 4.41 Cum
@ Rs. 1622.80 Per Cum Rs 7153.30
2 2.50 cm thick A flooring in CC (1:2:4) uing 12 mm ize hbg chip
1X 11.60 X 3.80 = 44.08 Sqm
@ Rs. 92.40 Per Sqm Rs 4072.99
3 WBCB in CM (1:6) to the super structure
2 X 3.80 X 0.23 X 3.00 = 5.24
1 X 11.60 X 0.23 X 3.00 = 8.00
Total 13.25 Cum
Deduction
Door 1 X 1.20 X 0.23 X 2.00 = 0.55
Window 3 X 0.90 X 0.23 X 1.20 = 0.75
Total 1.30 Cum
Net Qty = 11.95 Cum
@ Rs. 1398.25 Per Cum Rs 16710.21
4 16 mm CP in CM (1:6) to the Super structure
4X 3.80 X 3.00 = 45.60
2X 11.60 X 3.00 = 69.60
Total 115.20 Sqm
Deduction
Door 2X 1.20 X 2.00 = 4.80
Window 6X 0.90 X 1.20 = 6.48
Total 11.28 Sqm
Net Qty = 103.92 Sqm
@ Rs. 52.00 Per Sqm Rs 5403.84
5 Cot of Door & Window Rs 14000.00
6 Cost of whitewahing & painting Rs 3000.00
Grand Total Rs. 50340.34
Say Rs. 50000.00
(Rupees Fifty thousand Only)
The estimate has been prepared basing on S/R 2007 & enhanced labour rate
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"EXTENSION OF SLAB NEAR STORAGE GODOWN OF DFO
OFFICE,NABARANGPUR
Est.Cost:- Rs.44,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Long wall 1X 6.10 X 0.75 X 0.45 = 2.06
Cr. Wall 1X 1.50 X 0.75 X 0.45 = 0.51
Total = 2.57 Cum
@ Rs. 5084.20 Per 100 Cum Rs 130.41
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Long wall 1X 6.10 X 0.75 X 0.05 = 0.23
Cr. Wall 1X 1.5 X 0.75 X 0.05 = 0.06
Space 1x 7.62 X 1.20 X 0.30 = 2.74
Total = 3.03 Cum
@ Rs. 181.00 Per Cum Rs 548.10
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Space 1x 7.62 X 1.20 X 0.30 = 2.74
Total = 2.74 Cum
@ Rs. 1622.80 Per Cum Rs 4451.66
4 Rcc (1:1.5:3) uing 12 mm ize hbg chip including ll complete.
Beam 2X 6.70 X 0.23 X 0.23 = 0.71
Slab 1X 6.40 X 2.63 X 0.10 = 1.68
1X 3.65 X 2.10 X 0.10 = 0.77
Total = 3.16 Cum
@ Rs. 3023.45 Per Cum Rs 9549.75
5 Supplying,fitting,fixing of HYSD Bar reinforcement etc. complete.
Qty 3.00 Qtl @ Rs. 5000.00 per Qtl Rs 15000.00
6 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
Beam 2X 6.70 X 0.83 = 11.12
Total = 11.12 Sqm
@ Rs. 235.70 Per Sqm Rs 2621.46
Slab 1X 6.40 X 2.63 = 16.83
1X 3.65 X 2.10 = 7.67
Total = 24.50 Sqm
@ Rs. 179.30 Per Sqm Rs 4392.31
7 RRHGSM in CM (1:6) to the F&P
Long wall 1X 6.10 X 0.70 X 0.45 = 1.92
Cr. Wall 1X 1.50 X 0.70 X 0.45 = 0.47
Total = 2.39 Cum
@ Rs. 1117.25 Per Cum Rs 2674.70
8 2.50 cm thick A flooring in CC (1:2:4) uing 12 mm ize hbg chip
1X 7.60 X 1.20 = 9.12 Sqm
@ Rs. 92.40 Per Sqm Rs 842.69
9 WBCB in CM (1:6) to the super structure
1 X 6.10 X 0.23 X 0.30 = 0.42
1 X 6.10 X 0.23 X 0.45 = 0.63
Pillar 2 X 2.85 X 0.23 X 0.35 = 0.46
Total 1.51 Cum
@ Rs. 1398.25 Per Cum Rs 2112.90
10 16 mm CP in CM (1:6) to the Super structure
2X 6.10 X 0.30 = 3.66
2X 6.10 X 0.45 = 5.49
Pillar 4X 2.85 X 0.23 = 2.62
4X 2.85 X 0.35 = 3.99
Total 15.76 Sqm
@ Rs. 52.00 Per Sqm Rs 819.62
11 20 mm CP in CM (1:4) to the grading plaster to the
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF ROOM INSIDE OVER HEAD TANK AT
NURSERY,NABARANGPUR
Est.Cost:- Rs.25,000/-
1 WBCB in CM (1:6) to the super structure
2 X 2.70 X 0.23 X 2.85 = 3.54
2 X 5.10 X 0.23 X 2.85 = 6.69
Total 10.23 Cum
Deduction
Door 1 X 1.20 X 0.23 X 2.00 = 0.55
Window 1 X 0.90 X 0.23 X 1.20 = 0.25
Total 0.80 Cum
Net Qty = 9.43 Cum
@ Rs. 1398.25 Per Cum Rs 13179.07
2 16 mm CP in CM (1:6) to the Super structure
2X 3.16 X 3.00 = 18.96
2X 5.86 X 3.00 = 35.16
Total 54.12 Sqm
Deduction
Door 2X 1.20 X 2.00 = 4.80
Window 2X 0.90 X 1.20 = 2.16
Total 6.96 Sqm
Net Qty = 47.16 Sqm
@ Rs. 52.00 Per Sqm Rs 2452.32
3 Rcc (1:1.5:3) uing 12 mm ize hbg chip including ll complete.
1st Floor
Lintel 2X 2.70 X 0.23 X 0.15 = 0.19
2X 5.10 X 0.23 X 0.15 = 0.35
Chuza 2X 1.50 X 0.50 X 0.06 = 0.09
Total = 0.63 Cum
@ Rs. 3080.90 Per Cum Rs 1935.42
4 Supplying,fitting,fixing of HYSD Bar reinforcement etc. complete.
Qty 0.60 Qtl @ Rs. 5000.00 per Qtl Rs 3000.00
Junior Engineer
Nabarangpur Block
The estimate has been prepared for the work" Completion of incomplete SHG Conference building at "
Nabarangpur amounting to Rs.1,32,000/- ( Rupees One Lakh Thirty Two Thousand Only) to meet the
probableexpenditure out of infrastructure development of SHG fund for the Year 2008-09 of Nabarangpur .
Block.Previously the said building was construted out of Infrastructure Development fund placed specially
to this Block. But due to short of fund some items of the building was left incomplete during construction .
Now following provision are made to complete the incomplete building.
1. Const. Of Septic tank for the building.
2. Extension of Slab over stair case to prevent rain water.
3. 16 mm CP (1:6) to the brick wall.
4. Installation of electric supply to the building.
5. Installation of water supply to the building.
The estimate has been prepared basing on Shedule of Rates 2007 & enhanced Labour rate.
The minimum wages to the unskilled labourer is Rs.70.00 per 7 Hrs of work per day.
The wages will be provided equal to the both man & woman un skilled labour. The ODSS
will be followed strictly during execution of the work.
Est.Cost:- Rs.2,00,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Long Wall 1X 7.31 X 0.75 X 0.75 = 4.11 Cum
Short Wall 3X 2.48 X 0.75 X 0.75 = 4.19 Cum
Total = 8.30 Cum
@ Rs. 5084.20 Per 100 Cum Rs 421.83
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Long Wall 1X 7.31 X 0.75 X 0.05 = 0.27 Cum
Short Wall 3X 2.48 X 0.75 X 0.05 = 0.28 Cum
Room 1X 2.48 X 3.08 X 0.45 = 3.44 Cum
1X 2.48 X 1.88 X 0.45 = 2.10 Cum
Total = 6.09 Cum
@ Rs. 181.00 Per Cum Rs 1102.02
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Long Wall 1X 7.31 X 0.75 X 0.15 = 0.82 Cum
Short Wall 3X 2.48 X 0.75 X 0.15 = 0.84 Cum
Room 1X 2.48 X 3.08 X 0.10 = 0.76 Cum
1X 2.48 X 1.88 X 0.10 = 0.47 Cum
Total = 2.89 Cum
@ Rs. 1622.80 Per Cum Rs 4689.01
4 RRHGSM in CM (1:6) to the F&P including all cost,conveyance
royality etc complete.
Long Wall 1X 7.21 X 0.60 X 0.55 = 2.38 Cum
3X 2.58 X 0.60 X 0.55 = 2.55 Cum
1X 7.16 X 0.45 X 0.45 = 1.45 Cum
3X 2.63 X 0.45 X 0.45 = 1.60 Cum
Total = 7.98 Cum
@ Rs. 1117.25 Per Cum Rs 8916.91
5 WBCB in CM (1:6) to the super structure
Long Wall 1 X 6.69 X 0.23 X 3.00 = 4.62
Short Wall 3 X 3.00 X 0.23 X 3.00 = 6.21
Total 21.85 Cum
Deduction
Door 2 X 1.20 X 0.23 X 2.00 = 1.10
Window 1 X 0.90 X 0.23 X 1.20 = 0.25
Vantilator 2 X 0.30 X 0.23 X 0.30 = 0.04
Total 1.39 Cum
Net Qty 20.46 Cum
@ Rs. 1398.25 Per Cum Rs 28609.66
5 16 mm CP in CM (1:6) to the Super structure
Inside of room 2X 2.40 X 3.00 = 14.40
2X 3.00 X 3.00 = 18.00
2X 3.60 X 3.00 = 21.60
2X 3.00 X 3.00 = 18.00
Out side room 2X 3.46 X 3.00 = 20.76
1X 6.70 X 3.00 = 20.10
Total 112.86 Sqm
Deduction
Door 2 X 2X 1.20 X 2.00 = 9.60
Window 1 X 2X 0.90 X 1.20 = 2.16
Vantilator 2 X 2X 0.30 X 0.30 = 0.36
Total 12.12 Sqm
Net Qty = 100.74 Sqm
@ Rs. 52.00 Per Sqm Rs 5238.48
6 Rcc (1:1.5:3) uing 12 mm ize hbg chip including ll complete.
Plinth 1X 15.55 X 0.45 X 0.15 = 1.05
Lintel 1X 15.72 X 0.23 X 0.15 = 0.54
Chuza 1X 1.20 X 0.50 X 0.06 = 0.04
Slab 1X 7.00 X 3.60 X 0.10 = 2.52
Total = 4.15 Cum
@ Rs. 3080.90 Per Cum Rs 12779.47
7 Supplying,fitting,fixing of HYSD Bar reinforcement etc. complete.
Qty 3.73 Qtl @ Rs. 4993.45 per Qtl Rs 18641.39
8 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
Slab 1X 7.00 X 3.60 = 25.20
Total = 25.20 Sqm
@ Rs. 179.30 Per Sqm Rs 4518.36
Plinth 2X 15.55 X 0.15 = 4.67 Sqm
@ Rs. 54.90 Per Sqm Rs 256.11
Lintel 2X 15.72 X 0.15 = 4.72 Sqm
@ Rs. 130.95 Per Sqm Rs 617.56
9 Finishing wall surface with water proof cement paint to the newly
plastered surface to give an even shade with all cost etc complete
Qty as per item No.5 I.e = 100.74 Sqm
Add for ceiling = 25.20
Total 125.94 Sqm
@ Rs. 13.35 Per Sqm Rs 1681.30
10 Supplying,fitting & fixing of vetrified tiles in floors of size 600 mm X600 mm
of approved make with application of polymer modified cement based water
resistant adhesive bed of required thickness of 10 mm & filling joints with
epoxy grout of approved quality including cost of materials etc complete.
Room 1X 2.50 X 3.00 = 7.50
1X 3.60 X 3.00 = 10.80
Total = 18.30 Sqm
@ Rs. 993.00 Per Sqm Rs 18171.90
11 Providing,fitting & fixing of false ceiling with Alluminium anodised T-section
No. 3215 with 2' C/C,L-section No.1705 up to 15 micron on 4 walls to be
fixed by means of steel screws & PVC plug and the Alluminium grid
2'00"X2'00" suspended from ceiling etc complete.
Room 1X 3.60 X 3.00 = 10.80
Total = 10.80 Sqm
@ Rs. 1138.40 Per Sqm Rs 12294.72
12 Providing,fitting,fixing of Alluminium door with OEL anodized Alluminium
door section of 9202 as vertical member & 9200 as bottom & middle
member & 6 mm plain glass in top portion with 12 mm thick pre-laminated
board in bottom portion fixed on door frame by means of tappered clip No.
4660 & the frame to be completed by means of jointing angle No. 1855
including all cost,hire charges of drilling machine etc complete.
Door 2X 1.20 X 2.00 = 4.80
Total = 4.80 Sqm
@ Rs. 3678.60 Per Sqm Rs 17657.28
13 Cost of MS Iron Window & Vantilator Rs 2500.00
14 Cost of Electic supply to the room with 3 Phase line L.S (To be paid as per actual) Rs. 62000.00
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF LATRINE WITH SEPTIC TANK AT RESIDENTIAL QUARTER OF
SMT.ULAMPA BHATRA,Sr.CLERK OF NABARANGPUR BLOCK".
Est.Cost:- Rs.43,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Latrine 2X 2.63 X 0.60 X 0.60 = 1.89 Cum
2X 1.13 X 0.60 X 0.60 = 0.81 Cum
Septic tank 1X 1.50 X 1.50 X 1.80 = 4.05 Cum
Total = 6.76 Cum
@ Rs. 5084.20 Per 100 Cum Rs 343.55
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Septic tank 1X 1.50 X 1.50 X 0.10 = 0.23 Cum
Latrine 2X 2.63 X 0.60 X 0.05 = 0.16 Cum
2X 1.13 X 0.60 X 0.05 = 0.07 Cum
1X 1.43 X 1.13 X 0.45 = 0.73 Cum
Total = 1.18 Cum
@ Rs. 181.00 Per Cum Rs 213.17
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Septic tank 1X 1.50 X 1.50 X 0.15 = 0.34 Cum
Latrine 2X 2.63 X 0.60 X 0.15 = 0.47 Cum
2X 1.13 X 0.60 X 0.15 = 0.20 Cum
1X 1.43 X 1.13 X 0.10 = 0.16 Cum
Total = 1.18 Cum
@ Rs. 1622.80 Per Cum Rs 1908.23
4 RRHGSM in CM (1:6) to the F&P including all cost,conveyance
royality etc complete.
Latrine 2X 2.53 X 0.50 X 0.40 = 1.01 Cum
2X 1.23 X 0.50 X 0.40 = 0.49 Cum
2X 2.48 X 0.45 X 0.45 = 1.00 Cum
2X 1.28 X 0.45 X 0.45 = 0.52 Cum
Total = 3.03 Cum
@ Rs. 1117.25 Per Cum Rs 3381.69
5 WBCB in CM (1:6) to the super structure
Septic tank 2 X 1.50 X 0.23 X 1.55 = 1.07
2 X 1.04 X 0.23 X 1.55 = 0.74
Latrine 2 X 2.26 X 0.23 X 3.00 = 3.12
2 X 1.50 X 0.23 X 3.00 = 2.07
Total 11.55 Cum
Deduction
Door 1 X 0.75 X 0.23 X 2.00 = 0.35
Vantilator 2 X 0.30 X 0.23 X 0.30 = 0.04
Total 0.39 Cum
Net Qty 11.16 Cum
@ Rs. 1398.25 Per Cum Rs 15608.69
5 16 mm CP in CM (1:6) to the Super structure
Inside of room 2X 1.80 X 3.00 = 10.80
2X 1.50 X 3.00 = 9.00
Out side room 2X 2.26 X 3.00 = 13.56
2X 1.96 X 3.00 = 11.76
Tank 2X 1.50 X 1.55 = 4.65
2X 1.50 X 1.55 = 4.65
Total 54.42 Sqm
Deduction
Door 1 X 2X 0.75 X 2.00 = 3.00
Vantilator 2 X 2X 0.30 X 0.30 = 0.36
Total 3.36 Sqm
Net Qty = 51.06 Sqm
@ Rs. 52.00 Per Sqm Rs 2655.12
6 Rcc (1:1.5:3) uing 12 mm ize hbg chip including ll complete.
Plinth 1X 7.52 X 0.45 X 0.10 = 0.34
Lintel 1X 7.52 X 0.23 X 0.10 = 0.17
Chuza 1X 1.20 X 0.50 X 0.06 = 0.04
Slab 1X 2.56 X 2.26 X 0.10 = 0.58
1X 2.00 X 2.00 X 0.075 = 0.30
Total = 1.43 Cum
@ Rs. 3080.90 Per Cum Rs 4393.12
7 Supplying,fitting,fixing of HYSD Bar reinforcement etc. complete.
Qty 1.28 Qtl @ Rs. 4993.45 per Qtl Rs 6408.23
8 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
Slab 1X 2.56 X 2.56 = 6.55
1X 2.00 X 2.00 = 4.00
Total = 10.55 Sqm
@ Rs. 179.30 Per Sqm Rs 1892.26
Plinth 2X 7.52 X 0.15 = 2.26 Sqm
@ Rs. 54.90 Per Sqm Rs 123.85
Lintel 2X 7.52 X 0.15 = 2.26 Sqm
@ Rs. 130.95 Per Sqm Rs 295.42
9 Finishing wall surface with water proof cement paint to the newly
plastered surface to give an even shade with all cost etc complete
Qty as per item No.5 I.e = 51.06 Sqm
Add for ceiling = 2.70
Total 53.76 Sqm
@ Rs. 13.35 Per Sqm Rs 717.70
10 2.50 CM thick AS flooring in CC (1:2:4) using 12 mm size hbg chips
including all complete.
Room 1X 1.50 X 1.80 = 2.70
1X 1.50 X 1.50 = 2.25
Total = 4.95 Sqm
@ Rs. 92.40 Per Sqm Rs 457.38
11 Cost of Door & Vantilator Rs 2500.00
12 Cost of Latrine Pan 1 Nos including fitting @ Rs.1000 Per No Rs. 1000.00
13 Cost of Sanitary Pipes L.S ( To be paid as per actual ) Rs 1000.00
14 Cost of Paintings including paint etc complete. Rs 500.00
G.Total Rs. 43398.43
Say Rs. 43000.00
(Rupees Forty Three thousand Only)
Technically Scrutinised for Rs.43,000/-
(Rupees Forty Three thousand Only)
Est.Cost:- Rs.1,00,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Long wall 1X 7.95 X 0.75 X 0.75 = 4.47 Cum
1X 6.17 X 0.75 X 0.75 = 3.47 Cum
Short wall 1X 3.12 X 0.75 X 0.75 = 1.76 Cum
Total = 9.70 Cum
@ Rs. 4721.40 Per 100 Cum Rs 457.86
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Long wall 1X 7.95 X 0.75 X 0.05 = 0.30 Cum
1X 6.17 X 0.75 X 0.05 = 0.23 Cum
Short wall 1X 3.12 X 0.75 X 0.05 = 0.12 Cum
Total = 0.65 Cum
@ Rs. 208.21 Per Cum Rs 134.61
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Long wall 1X 7.95 X 0.75 X 0.15 = 0.89 Cum
1X 6.17 X 0.75 X 0.15 = 0.69 Cum
Short wall 1X 3.12 X 0.75 X 0.15 = 0.35 Cum
Total = 1.94 Cum
@ Rs. 2085.29 Per Cum Rs 4044.42
4 RRHGSM in CM (1:6) to the F&P including all cost,conveyance
royality etc complete.
Long wall 1X 7.80 X 0.60 X 0.55 = 2.57 Cum
Long wall 1X 7.65 X 0.45 X 0.45 = 1.55
1X 6.02 X 0.60 X 0.55 = 1.99 Cum
1X 5.87 X 0.45 X 0.45 = 1.19 Cum
Short wall 1X 3.27 X 0.60 X 0.55 = 1.08 Cum
1X 3.42 X 0.45 X 0.45 = 0.69
Total = 9.07 Cum
@ Rs. 1419.53 Per Cum Rs 12875.24
5 RCC work of M-20 grade with 20 down grade black hard granite
cruser broken stone chips icluding hoisting &laying .
Plinth 1X 16.94 X 0.45 X 0.15 = 1.14
Lintel 1X 16.94 X 0.23 X 0.15 = 0.58
Chuza 3X 1.20 X 0.50 X 0.06 = 0.11
Beam 1X 4.10 X 0.30 X 0.30 = 0.37
Slab 1X 7.70 X 4.40 X 0.10 = 3.39
1X 2.00 X 1.20 X 0.075 = 0.18
Total = 5.77 Cum
@ Rs. 3317.48 Per Cum Rs 19151.41
6 WBCB in CM (1:6) to the super structure
2 X 7.40 X 0.23 X 3.00 = 10.21
1 X 3.64 X 0.23 X 3.00 = 2.51
Total 12.72 Cum
Deduction
Door 1 X 1.20 X 0.23 X 2.00 = 0.55
Window 2 X 0.90 X 0.23 X 1.20 = 0.50
Total 1.05 Cum
Net Qty 11.67 Cum
@ Rs. 1947.29 Per Cum Rs 22734.23
7 16 mm CP in CM (1:6) to the Super structure
Inside of room 2X 7.20 X 3.00 = 43.20
2X 3.90 X 3.00 = 23.40
Out side room 2X 7.66 X 3.00 = 45.96
Total 112.56 Sqm
Deduction
Door 1 X 2X 1.20 X 2.00 = 4.80
Vantilator 2 X 2X 0.90 X 1.20 = 4.32
Total 9.12 Sqm
Net Qty = 103.44 Sqm
@ Rs. 67.51 Per Sqm Rs 6982.79
8 Supplying,fitting,fixing of HYSD Bar reinforcement etc. complete.
Qty 4.91 Qtl @ Rs. 4110.80 per Qtl Rs 20171.46
9 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
Slab 1X 7.70 X 4.40 = 33.88
1X 2.00 X 1.20 = 2.40
Chuza 3X 1.20 X 0.60 = 2.16
Total = 38.44 Sqm
@ Rs. 192.14 Per Sqm Rs 7385.90
Plinth 2X 16.94 X 0.15 = 5.08 Sqm
@ Rs. 60.93 Per Sqm Rs 309.64
Lintel 2X 7.52 X 0.15 = 2.26 Sqm
@ Rs. 141.47 Per Sqm Rs 319.16
Beam 1X 4.10 X 0.90 = 3.69 Sqm
@ Rs. 278.27 Per Sqm Rs 1026.80
10 Finishing wall surface with water proof cement paint to the newly
plastered surface to give an even shade with all cost etc complete
Qty as per item No.7 I.e = 103.44 Sqm
Add for ceiling = 38.44
Total 141.88 Sqm
@ Rs. 14.76 Per Sqm Rs 2093.77
11 2.50 CM thick AS flooring in CC (1:2:4) using 12 mm size hbg chips
including all complete.
Room 1X 7.20 X 3.90 = 28.08
Total = 28.08 Sqm
@ Rs. 120.74 Per Sqm Rs 3390.51
12 Cost of Door & Vantilator Rs 6000.00
13 Cost of Paintings including paint etc complete. Rs 1500.00
G.Total Rs. 108577.82
Say Rs. 100000.00
(Rupees One Lakh Only)
Junior Engineer
Nabarangpur Block
Junior. Engineer
Nabarangpur Block
SARAPANCH
BAGHSEUNI GP
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF RESIDENTIAL SINGLE STORIED BUILDING OF SRI AMAR
SINGH BISSOI AT DRDA BACK SIDE COLONY,NABARANGPUR OVER PLOT NO. ,KHATA NO.
MOUZA
Est.Cost:- Rs.9,00,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Pillar 20 X 1.20 X 1.20 X 1.20 = 34.56
Long Wall 3X 8.92 X 0.60 X 0.60 = 9.63
1X 8.67 X 0.60 X 0.60 = 3.12
Sh. Wall 5X 5.07 X 0.60 X 0.60 = 9.13
4X 2.03 X 0.60 X 0.60 = 2.92
2X 1.73 X 0.60 X 0.60 = 1.25
Total = 60.61 Cum
@ Rs. 5084.20 Per 100 Cum Rs 3081.51
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Pillar 20 X 1.20 X 1.20 X 0.10 = 2.88
Long Wall 3X 8.92 X 0.60 X 0.10 = 1.61
1X 8.67 X 0.60 X 0.10 = 0.52
Sh. Wall 5X 5.07 X 0.60 X 0.10 = 1.52
4X 2.03 X 0.60 X 0.10 = 0.49
2X 1.73 X 0.60 X 0.10 = 0.21
Room 2X 3.65 X 4.26 X 0.50 = 15.55
Kit 2X 3.65 X 2.10 X 0.50 = 7.67
Dinning 2X 3.30 X 4.26 X 0.50 = 14.06
Drawing 2X 3.05 X 3.96 X 0.50 = 12.08
Toilet 4X 1.60 X 2.10 X 0.50 = 6.72
Stair 1X 3.05 X 3.65 X 0.50 = 5.57
Total = 68.86 Cum
@ Rs. 181.00 Per Cum Rs 12463.27
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Pillar 20 X 1.20 X 1.20 X 0.15 = 4.32
Long Wall 3X 8.92 X 0.60 X 0.15 = 2.41
1X 8.67 X 0.60 X 0.15 = 0.78
Sh. Wall 5X 5.07 X 0.60 X 0.15 = 2.28
4X 2.03 X 0.60 X 0.15 = 0.73
2X 1.73 X 0.60 X 0.15 = 0.31
Room 2X 3.65 X 4.26 X 0.10 = 3.11
Kit 2X 3.65 X 2.10 X 0.10 = 1.53
Dinning 2X 3.30 X 4.26 X 0.10 = 2.81
Drawing 2X 3.05 X 3.96 X 0.10 = 2.42
Toilet 4X 1.60 X 2.10 X 0.10 = 1.34
Stair 1X 3.05 X 3.65 X 0.10 = 1.11
Total = 23.16 Cum
@ Rs. 1622.80 Per Cum Rs 37583.48
4 RCC work of M-20 grade with 20 down grade black hard granite
cruser broken stone chips icluding hoisting &laying .
Pillar 20 X 1.20 X 1.20 X 0.30 = 8.64
20 X (1.20+0.23)/2X(1.20+0.30)/2 X 0.45 = 4.83
20 X 0.30 X 0.23 X 3.80 = 5.24
Plinth beam 3X 12.80 X 0.23 X 0.40 = 3.53
1X 11.58 X 0.23 X 0.40 = 1.07
5X 7.01 X 0.23 X 0.40 = 3.22
2X 1.60 X 0.23 X 0.40 = 0.29
4X 3.04 X 0.23 X 0.40 = 1.12
Lintel 3X 12.80 X 0.23 X 0.15 = 1.32
1X 11.58 X 0.23 X 0.15 = 0.40
5X 7.01 X 0.23 X 0.15 = 1.21
2X 1.60 X 0.23 X 0.15 = 0.11
4X 3.04 X 0.23 X 0.15 = 0.42
Grade beam 3X 12.80 X 0.23 X 0.23 = 2.03
1X 11.58 X 0.23 X 0.23 = 0.61
5X 7.01 X 0.23 X 0.23 = 1.85
2X 1.60 X 0.23 X 0.23 = 0.17
4X 3.04 X 0.23 X 0.23 = 0.64
Steps 20 X 1.20 X 0.30 X 0.125 = 0.90
Landing 1X 3.05 X 1.20 X 0.125 = 0.46
Chuzza 10 X 1.50 X 0.60 X 0.07 = 0.63
Slab 1X 14.25 X 7.85 X 0.10 = 11.19
1X 10.36 X 3.43 X 0.10 = 3.55
Total = 53.45 Cum
@ Rs. 3023.45 Per Cum Rs 161595.68
5 Supplying,fitting,fixing of HYSD Bar reinforcement etc. complete.
Qty 45.43 Qtl @ Rs. 5000.00 per Qtl Rs 227151.65
6 Rigid & smooth centering,shuttering for RCC work & dismanteling
them after casting etc. complete.
Pillar 4 X 20 X 1.20 X 0.30 = 28.80
4 X 20 X (1.20+0.30)/ X 0.45 = 27.00
4 X 20 X (1.20+0.23)/ X 0.45 = 25.74
Plinth beam 3 X 2X 12.80 X 0.40 = 30.72
1 X 2X 11.58 X 0.40 = 9.26
5 X 2X 8.53 X 0.40 = 34.12
2 X 2X 1.60 X 0.40 = 2.56
4 X 2X 3.04 X 0.40 = 9.73
Total = 167.93 Sqm
@ Rs. 54.90 Per Sqm Rs 9219.47
Lintel 3 X 2 X 12.80 X 0.15 = 11.52
1 X 2 X 11.58 X 0.15 = 3.47
5 X 2 X 7.01 X 0.15 = 10.52
2 X 2 X 1.60 X 0.15 = 0.96
4 X 2 X 3.04 X 0.15 = 3.65
Total = 30.12 Sqm
@ Rs. 130.95 Per Sqm Rs 3943.82
Grade beam 3 X 2 X 12.80 X 0.23 = 17.66
1 X 2 X 11.58 X 0.23 = 5.33
5 X 2 X 7.01 X 0.23 = 16.12
2 X 2 X 1.60 X 0.23 = 1.47
4 X 2 X 3.04 X 0.23 = 5.59
Total = 46.18 Sqm
@ Rs. 235.70 Per Sqm Rs 10884.48
Slab 1 X 14.25 X 7.85 = 111.86
1 X 10.36 X 3.43 = 35.53
Steps 20 X 1.20 X 0.30 = 7.20
20 X 1.20 X 0.15 = 3.60
Landing 1 X 3.05 X 1.20 = 3.66
Chuzza 10 X 1.50 X 0.60 = 9.00
Total = 170.86 Sqm
@ Rs. 179.30 Per Sqm Rs 30634.71
7 RRHGSM in CM (1:6) to the F&P
1st Footing
3 X 12.80 X 0.50 X 0.35 = 6.72
1 X 10.97 X 0.50 X 0.35 = 1.92
5 X 7.01 X 0.50 X 0.35 = 6.13
4 X 3.65 X 0.50 X 0.35 = 2.56
2nd Footing
3 X 12.80 X 0.45 X 0.30 = 5.18
1 X 10.97 X 0.45 X 0.30 = 1.48
5 X 7.01 X 0.45 X 0.30 = 4.73
4 X 3.65 X 0.45 X 0.30 = 1.97
Total = 30.70 Cum
@ Rs. 1117.25 Per Cum Rs 34295.33
8 WBCB in CM (1:6) to the super structure
3 X 12.80 X 0.23 X 3.00 = 26.50
1 X 10.97 X 0.23 X 3.00 = 7.57
5 X 7.01 X 0.23 X 3.00 = 24.18
4 X 3.65 X 0.23 X 3.00 = 10.07
2 X 1.50 X 0.125 X 3.00 = 1.13
Total 69.45 Cum
Deduction
Door 6 X 1.20 X 0.23 X 2.00 = 3.31
Door 6 X 0.90 X 0.23 X 2.00 = 2.48
Window 10 X 0.90 X 0.23 X 1.20 = 2.48
Total 8.28 Cum
Net Qty = 61.17 Cum
@ Rs. 1398.25 Per Cum Rs 85529.27
9 16 mm CP in CM (1:6) to the Super structure
Qty 265.951 Sqm
@ Rs. 52.00 Per Sqm Rs 13829.47
10 20 mm CP in CM (1:4) to the grading plaster to the
Slab 1X 14.25 X 7.85 = 111.86 Sqm
1X 10.36 X 3.43 = 35.53 Sqm
Total = 147.40 Sqm
@ Rs. 65.50 Per Sqm Rs 9654.52
11 Finishing wall surface with water proof cement paint to the newly
plastered surface to give an even shade with all cost etc complete
Qty as per item No.9 I.e = 265.95 Sqm
Add for ceiling = 147.40
Total 413.35 Sqm
@ Rs. 13.35 Per Sqm Rs 5518.20
12 Supplying,fitting & fixing of vetrified tiles in floors of size 600 mm X600 mm
of approved make with application of polymer modified cement based water
resistant adhesive bed of required thickness of 10 mm & filling joints with
epoxy grout of approved quality including cost of materials etc complete.
Room 2X 3.65 X 4.20 = 30.66
2X 2.10 X 3.65 = 15.33
2X 3.30 X 4.20 = 27.72
2X 1.60 X 2.10 = 6.72
2X 1.60 X 1.35 = 4.32
2X 3.05 X 3.90 = 23.79
Total = 108.54 Sqm
@ Rs. 993.00 Per Sqm Rs 107780.22
13 Cot of Door & Window Rs 67000.00
14 Provision for water supply & sanitary fittings LS Rs 40000.00
15 Provision for electrification with all fittings etc. LS Rs 40000.00
Grand Total Rs. 900165.10
Say Rs. 900000.00
(Rupees Nine Lakh Only)
The estimate has been prepared basing on S/R 2009 & enhanced labour rate
Junior Engineer
Nabarangpur Block
10 Finishing wall surface with water proof cement paint to the newly
plastered surface to give an even shade with all cost etc complete
Qty as per item No.7 I.e = 67.13 Sqm
Add for ceiling = 19.62
Total 86.74 Sqm
@ Rs. 13.35 Per Sqm Rs 1158.03
11 2.50 CM thick AS flooring in CC (1:2:4) using 12 mm size hbg chips
including all complete.
Room 1X 3.00 X 3.60 = 10.80
Total = 10.80 Sqm
@ Rs. 92.40 Per Sqm Rs 997.92
12 Cost of Door, window & Vantilator Rs 7000.00
13 Cost of Paintings including paint etc complete. Rs 1500.00
G.Total Rs. 60027.17
Say Rs. 60000.00
Technically Scrutinised for Rs.60,000/- (Rupees Sixty Thousand ) Only
(Rupees One Lakh & Fifty thousand Only)
Addl PD ( Tech)
DRDA,Nabarangpur
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF CONFERENCE HALL AT DFO OFFICE , NABARANGPUR,
Est.Cost:- Rs.2,50,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Pillar 8X 1.20 X 1.20 X 1.20 = 13.82
Cr. Wall 1X 5.55 X 0.60 X 0.60 = 2.00
2X 4.90 X 0.60 X 0.60 = 3.53
Total = 19.35 Cum
@ Rs. 4721.40 Per 100 Cum Rs 913.59
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Pillar 8X 1.20 X 1.20 X 0.15 = 1.73
Cr. Wall 1X 5.55 X 0.60 X 0.10 = 0.33
2X 4.90 X 0.60 X 0.10 = 0.59
Room 1X 9.15 X 6.10 X 0.60 = 33.49
Total = 36.14 Cum
@ Rs. 208.21 Per Cum Rs 7524.17
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Pillar 8X 1.20 X 1.20 X 0.15 = 1.73
Cr. Wall 1X 5.55 X 0.60 X 0.15 = 0.50
2X 4.90 X 0.60 X 0.15 = 0.88
1X 1.80 X 0.60 X 0.15 = 0.16
Room 1X 9.15 X 6.10 X 0.15 = 8.37
Total = 11.64 Cum
@ Rs. 2208.17 Per Cum Rs 25711.40
4 RRHGSM in CM (1:6) to the F&P
1st Footing 1X 8.55 X 0.50 X 0.45 = 1.92
2X 6.10 X 0.50 X 0.45 = 2.75
2nd Footing 1X 8.55 X 0.45 X 0.60 = 2.31
2X 6.10 X 0.45 X 0.60 = 3.29
Step 1X 1.50 X 0.90 X 0.30 = 0.41
1X 1.50 X 0.60 X 0.15 = 0.14
1X 1.50 X 0.30 X 0.15 = 0.07
Total = 10.68 Cum
@ Rs. 1419.53 Per Cum Rs 15155.30
5 WBCB in CM (1:6) to the super structure
1X 9.75 X 0.23 X 2.60 = 5.83
2X 5.60 X 0.23 X 3.00 = 7.73
4X 0.30 X 0.20 X 2.90 = 0.70
Total 14.25 Cum
Deduction
Door 1X 0.75 X 0.23 X 2.00 = 0.35
Window 2X 1.20 X 0.23 X 0.90 = 0.50
Vantilator 3X 1.20 X 0.23 X 0.30 = 0.25
Total 1.09 Cum
Net Qty = 13.16 Cum
@ Rs. 1947.29 Per Cum Rs 25634.72
6 RCC (1:1.5:3) uing 12 mm ize hbg chip including ll complete.
Pillar 8X 1.20 X 1.20 X 0.30 = 3.46
8 X (1.20+0.23)/2X(1.20+0.30)/2 X 0.45 = 1.93
8X 0.35 X 0.30 X 3.90 = 3.28
Grade beam 1X 9.75 X 0.15 X 0.23 = 0.34
1X 6.10 X 0.15 X 0.23 = 0.21
Lintel 1X 9.75 X 0.23 X 0.15 = 0.34
2X 6.10 X 0.15 X 0.23 = 0.42
Beam 4X 6.10 X 0.30 X 0.40 = 2.93
Slab 1X 10.00 X 6.80 X 0.10 = 6.80
Chujja 3X 1.05 X 0.45 X 0.06 = 0.09
Total = 19.78 Cum
@ Rs. 3967.47 Per Cum Rs 78475.19
5 Supplying,fitting,fixing of HYSD Bar reinforcement etc. complete.
Qty 18.40 Qtl @ Rs. 4000.00 per Qtl Rs 73580.30
6 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
Pillar 8 X 4X 1.20 X 0.30 = 11.52
8 X 2 X (1.20+0.30)/ X 0.45 = 5.40
8 X 4 X (1.20+0.23)/ X 0.45 = 10.30
Grade beam 1 X 2X 9.75 X 0.30 = 5.85
2 X 2X 6.10 X 0.30 = 7.32
Total = 40.39 Sqm
@ Rs. 60.93 Per Sqm Rs 2460.69
Pillar 8X 1.30 X 3.90 = 40.56
Beam 4X 6.10 X 1.20 = 29.28
Total = 69.84 Sqm
@ Rs. 278.27 Per Sqm Rs 19434.16
Lintel 2 X 2X 6.10 X 0.15 = 3.66
1 X 2X 9.75 X 0.15 = 2.93
Total = 6.59 Sqm
@ Rs. 141.47 Per Sqm Rs 931.60
Slab,chajja 1 X 1X 10.00 X 6.80 = 68.00
1 X 3X 1.05 X 0.45 = 1.42
Total = 69.42 Sqm
@ Rs. 141.47 Per Sqm Rs 9820.72
7 16 mm CP in CM (1:6) to the Super structure
1X 9.45 X 3.30 = 31.19
3X 2.85 X 3.30 = 28.22
4X 6.30 X 3.30 = 83.16
2X 0.75 X 3.30 = 4.95
2X 1.30 X 3.00 = 7.80
2X 1.20 X 6.00 = 14.40
Total 169.71 Sqm
Deduction
Door 2X 0.75 X 2.00 = 3.00
Window 4X 1.20 X 0.90 = 4.32
6X 0.30 X 1.20 = 2.16
Vantilator 4X 0.30 X 0.60 = 0.72
Total 10.20 Sqm
Net Qty = 159.51 Sqm
@ Rs. 67.51 Per Sqm Rs 10767.83
8 20 mm CP in CM (1:4) to the grading plaster to the
Slab 1X 10.00 X 6.80 = 68.00 Sqm
Total = 68.00 Sqm
@ Rs. 85.49 Per Sqm Rs 5813.06
9 Finishing wall surface with water proof cement paint to the newly
plastered surface to give an even shade with all cost etc complete
Total Qty = 159.51 Sqm
Add for ceiling = 68.00
Total = 227.51 Sqm
@ Rs. 14.76 Per Sqm Rs 3357.45
10 Cost of MS door & window
Window ( 0.90X1.20)mtr-2Nos Rs 5000.00
Grand Total Rs. 284580.17
Say Rs. 250000.00
(Rupees Two Lakh & Fifty thousand Only)
The estimate has been prepared basing on S/R 2008 & enhanced labour rate
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"COMPLETION OF CONFERENCE HALL AT DFO OFFICE ,
NABARANGPUR,
Est.Cost:- Rs.1,64,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Pillar 2X 1.20 X 1.20 X 1.20 = 3.46
Cr. Wall 1X 3.9 X 0.60 X 0.60 = 1.40
2X 3.30 X 0.60 X 0.60 = 2.38
Total = 7.24 Cum
@ Rs. 4721.40 Per 100 Cum Rs 341.64
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Pillar 2X 1.20 X 1.20 X 0.15 = 0.43
Room 1X 9.15 X 3.60 X 0.60 = 19.76
Total = 20.20 Cum
@ Rs. 208.21 Per Cum Rs 4204.94
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Pillar 2X 1.20 X 1.20 X 0.15 = 0.43
Cr. Wall 1X 3.90 X 0.60 X 0.15 = 0.35
2X 3.60 X 0.60 X 0.15 = 0.65
Room 1X 9.15 X 3.60 X 0.15 = 4.94
Total = 6.37 Cum
@ Rs. 2208.17 Per Cum Rs 14070.47
4 RRHGSM in CM (1:6) to the F&P
1st Footing 1X 3.90 X 0.50 X 0.45 = 0.88
2X 3.60 X 0.50 X 0.45 = 1.62
2nd Footing 1X 3.90 X 0.45 X 0.60 = 1.05
2X 3.60 X 0.45 X 0.60 = 1.94
Total = 5.49 Cum
@ Rs. 1419.53 Per Cum Rs 7799.63
5 WBCB in CM (1:6) to the super structure
1X 3.90 X 0.23 X 3.30 = 2.96
2X 3.60 X 0.23 X 3.15 = 5.22
Total 8.18 Cum
Deduction
Door 1X 1.20 X 0.23 X 2.00 = 0.55
Window 1X 1.50 X 0.23 X 1.20 = 0.41
1X 1.20 X 0.23 X 0.90 = 0.25
Total 1.21 Cum
Net Qty = 6.96 Cum
@ Rs. 1947.29 Per Cum Rs 13557.23
6 RCC (1:1.5:3) uing 12 mm ize hbg chip including ll complete.
Pillar 2X 1.20 X 1.20 X 0.30 = 0.86
2 X (1.20+0.23)/2X(1.20+0.30)/2 X 0.45 = 0.48
2X 0.23 X 0.23 X 3.90 = 0.41
Grade beam 2X 3.60 X 0.15 X 0.23 = 0.25
1X 3.90 X 0.15 X 0.23 = 0.13
Lintel 2X 3.60 X 0.23 X 0.15 = 0.25
1X 3.90 X 0.15 X 0.23 = 0.13
Beam 4X 3.90 X 0.23 X 0.30 = 1.08
Slab 1X 10.00 X 3.90 X 0.10 = 3.90
Chujja 1X 3.60 X 0.45 X 0.05 = 0.08
1X 1.65 X 0.45 X 0.05 = 0.04
1X 1.05 X 0.45 X 0.05 = 0.02
Total = 7.64 Cum
@ Rs. 3967.47 Per Cum Rs 30324.55
5 Supplying,fitting,fixing of HYSD Bar reinforcement etc. complete.
Qty 6.50 Qtl @ Rs. 4000.00 per Qtl Rs 25987.20
6 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
Pillar 2 X 4 X 1.20 X 0.30 = 2.88
2 X 4 X (1.20+0.23)/ X 0.45 = 2.57
Grade beam 2 X 2 X 3.60 X 0.30 = 4.32
1 X 2 X 3.90 X 0.30 = 2.34
Total = 12.11 Sqm
@ Rs. 60.93 Per Sqm Rs 738.10
Pillar 2X 0.92 X 3.90 = 7.18
Beam 4X 3.90 X 0.83 = 12.95
Total = 20.12 Sqm
@ Rs. 278.27 Per Sqm Rs 5599.84
Lintel 2 X 2X 3.60 X 0.15 = 2.16
1 X 2X 3.90 X 0.15 = 1.17
Total = 3.33 Sqm
@ Rs. 141.47 Per Sqm Rs 471.11
Slab,chajja 1 X 1X 10.00 X 3.90 = 39.00
1 X 1X 3.60 X 0.45 = 1.62
1 X 1X 1.70 X 0.45 = 0.77
1 X 1X 1.05 X 0.45 = 0.47
Total = 41.86 Sqm
@ Rs. 141.47 Per Sqm Rs 5921.72
7 16 mm CP in CM (1:6) to the Super structure
1X 3.90 X 4.20 = 16.38
2X 3.60 X 4.20 = 30.24
1X 3.90 X 3.60 = 14.04
2X 3.60 X 3.60 = 25.92
2X 3.60 X 0.70 = 5.04
Total 91.62 Sqm
Deduction
Door 2X 1.20 X 2.00 = 4.80
Window 4X 1.20 X 0.90 = 4.32
2X 1.50 X 1.20 = 3.60
Total 12.72 Sqm
Net Qty = 78.90 Sqm
@ Rs. 67.51 Per Sqm Rs 5326.20
8 20 mm CP in CM (1:4) to the grading plaster to the
Slab 1X 10.00 X 3.90 = 39.00 Sqm
Total = 39.00 Sqm
@ Rs. 85.49 Per Sqm Rs 3333.96
9 Finishing wall surface with water proof cement paint to the newly
plastered surface to give an even shade with all cost etc complete
Total Qty = 78.90 Sqm
Add for ceiling = 39.00
Total = 117.90 Sqm
@ Rs. 14.76 Per Sqm Rs 1739.89
10 CC (1:2:4) using 12 mm size hbg chips including all cost
conveyance , royality etc. complete
Hall 1X 9.00 X 6.00 X 0.075 = 4.05
1X 9.00 X 3.60 X 0.075 = 2.43
1X 3.00 X 1.80 X 0.075 = 0.41
Total = 6.89 Cum
@ Rs. 2527.00 Per Cum Rs 17398.40
10 Cost of MS door & window
Door(0.75X2.00) mtr Size -1No Rs 2500.00
Door(1.20X2.00) mtr Size -1No Rs 3500.00
Window ( 1.50X1.20)mtr-12No Rs 2000.00
Window ( 0.90X1.20)mtr-2Nos Rs 4000.00
Collapsable Gate- 1 No Rs 10000.00
11 Cost of Sanitary fittings LS Rs 3000.00
12 Cost of electrical fittings 10% of Civil Works Rs 30000.00
Total Rs 191814.88
Say Rs. 180000.00
(Rupees One Lakh & Eighty thousand Only)
The estimate has been prepared basing on S/R 2008 & enhanced labour rate
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF LATRINE AT NEW FOREST COLONY NEAR QR. OF NIGHT
WATCHER & SWEEPER
Est.Cost:- Rs.60,000/-
1 E/W in excavation in hard soil in Foundation with initial lead & lift
including rough dressing & breaking clods etc. complete.
Toilet-1 2X 1.80 X 0.45 X 0.60 = 0.97 Cum
1X 0.90 X 0.45 X 0.60 = 0.24 Cum
Toilet-2 3X 1.65 X 0.45 X 0.60 = 1.34 Cum
2X 1.05 X 0.45 X 0.60 = 0.57 Cum
Soak Pit 1X 0.90 X 1.80 X 1.05 = 1.70 Cum
Septic Tank 1X 2.40 X 3.60 X 2.80 = 24.19 Cum
Total = 29.01 Cum
@ Rs 4721.40 Per 100 Cum Rs 1369.75
2 CC (1:4:8) using 40 mm size hbg metal including all complete.
Toilet-1 2X 1.80 X 0.45 X 0.15 = 0.24 Cum
1X 0.90 X 0.45 X 0.15 = 0.06 Cum
Toilet-2 3X 1.65 X 0.45 X 0.15 = 0.33 Cum
2X 1.05 X 0.45 X 0.15 = 0.14 Cum
Toilet Room 3X 1.20 X 1.50 X 0.10 = 0.54 Cum
Soak Pit 1X 0.90 X 1.80 X 0.15 = 0.24 Cum
Septic Tank 1X 2.40 X 3.60 X 0.15 = 1.30 Cum
Total = 2.86 Cum
@ Rs 2085.29 Per 100 Cum Rs 5961.07
3 WBCB in CM (1:6) to the super structure
Toilet-1 Foundati 2X 1.80 X 0.35 X 0.60 = 0.76 Cum
1X 0.90 X 0.35 X 0.60 = 0.19 Cum
Toilet-2 3X 1.80 X 0.35 X 0.60 = 1.13 Cum
2X 0.90 X 0.35 X 0.60 = 0.38 Cum
Toilet-1 Room 2X 1.80 X 0.23 X 2.55 = 2.11 Cum
1X 1.80 X 0.23 X 1.20 = 0.50 Cum
1X 1.20 X 0.23 X 2.55 = 0.70 Cum
Toilet-2 3X 1.80 X 0.23 X 2.55 = 3.17 Cum
2X 1.05 X 0.23 X 2.55 = 1.23 Cum
2X 1.20 X 0.23 X 2.10 = 1.16 Cum
1X 3.00 X 0.23 X 1.20 = 0.83 Cum
Septic Tank 2X 3.45 X 0.23 X 2.70 = 4.28 Cum
3X 1.80 X 0.23 X 2.70 = 3.35 Cum
Soak Pit 1X 2.25 X 0.23 X 0.90 = 0.47 Cum
2X 0.90 X 0.23 X 0.90 = 0.37 Cum
Total 20.63 Cum
Deduction
Door 3X 0.75 X 0.23 X 2.10 = 1.09
Total 1.09 Cum
Net Qty = 19.54 Cum
@ Rs. 1947.29 Per Cum Rs 38059.51
4 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Slab 1X 4.50 X 2.25 X 0.10 = 1.01 Cum
Total = 1.01 Cum
@ Rs. 3317.48 Per Cum Rs 3358.95
5 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 0.91 Qtl
@ Rs. 4000.00 Per Qtl Rs 3645.00
6 Rigid & smooth centering , shuttering for RCC work
& dismanteling them after casting.
Toilet 3X 1.20 X 1.50 = 5.40 Sqm
Septic Tank 2X 1.80 X 1.50 = 5.40 Sqm
Total = 10.80 Sqm
@ Rs. 192.14 Per Sqm Rs 2075.12
7 12 mm CP in CM (1:6) to the superstructure
Qty = 169.96 Sqm @ 38.03 Per Sqm Rs 6463.40
8 2.50 CmM thick AS flooring in CC (1:2:4) using 12 mm size hbg
Chips including all cost , conveyance , royality etc. complete
Toilet 3X 1.20 X 1.50 = 5.40 Sqm
Septic Tank 2X 1.80 X 1.50 = 5.40 Sqm
Total = 10.80 Sqm
@ Rs. 95.79 Per Sqm Rs 1034.53
9 Cost of Latrine Door 03 Nos Rs 2400.00
10 Cost of Sanitary Fittings Rs 5300.00
Total Rs 69667.32
Say Rs. 60000.00
(Rupees Sixty thousand Only)
The estimate has been prepared basing on S/R 2008 & enhanced labour rate
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF LATRINE OF CONFERENCE HALL AT DFO OFFICE ,
NABARANGPUR.
Est.Cost:- Rs.30,000/-
1 E/W in excavation in hard soil in Foundation with initial lead & lift
including rough dressing & breaking clods etc. complete.
Toilet-1 1X 1.80 X 0.60 X 0.60 = 0.65 Cum
@ Rs 4721.40 Per 100 Cum Rs 30.59
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Room 1X 1.80 X 3.00 X 0.60 = 3.24 Cum
@ Rs. 208.21 Per Cum Rs 674.59
3 CC (1:4:8) using 40 mm size hbg metal including all complete.
Toilet-1 1X 1.80 X 0.60 X 0.15 = 0.16 Cum
Room 1X 1.80 X 3.00 X 0.15 = 0.81 Cum
Total = 0.97 Cum
@ Rs 2085.29 Per 100 Cum Rs 2026.90
4 RR stone massonary in CM (1:6) to the F&P including all
cost,conveyance,royality etc. complete.
1st Footings
Toilet-1 1X 1.80 X 0.50 X 0.45 = 0.41 Cum
2nd Footings
Toilet-1 1X 1.80 X 0.45 X 0.60 = 0.49 Cum
Total = 0.89 Cum
@ Rs. 1419.53 Per Cum Rs 1264.80
5 WBCB in CM (1:6) to the super structure
Toilet-1 1X 1.80 X 0.23 X 2.40 = 0.99 Cum
1X 1.80 X 0.23 X 2.00 = 0.83 Cum
1X 3.00 X 0.23 X 0.30 = 0.21 Cum
1X 1.80 X 0.23 X 0.30 = 0.12 Cum
Total 2.15 Cum
Deduction
Vantilator 2X 0.30 X 0.23 X 0.60 = 0.08
Total 0.08 Cum
Net Qty = 2.07 Cum
@ Rs. 1947.29 Per Cum Rs 4030.89
6 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Grade Beam 1X 1.80 X 0.23 X 0.15 = 0.06 Cum
Slab 1X 3.80 X 2.60 X 0.10 = 0.99 Cum
Total = 1.05 Cum
@ Rs. 3317.48 Per Cum Rs 3483.69
7 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 0.95 Qtl
@ Rs. 4000.00 Per Qtl Rs 3780.36
8 20 mm CP in CM (1:4) to the grading plaster to the
Slab 1X 3.80 X 2.60 = 9.88 Sqm
@ Rs. 85.49 Per Sqm Rs 844.60
9 12 mm CP in CM (1:6) to the superstructure
Qty = 21.00 Sqm @ 38.03 Per Sqm Rs 798.63
10 2.50 CmM thick AS flooring in CC (1:2:4) using 12 mm size hbg
Chips including all cost , conveyance , royality etc. complete
Toilet 1X 1.80 X 3.00 = 5.40 Sqm
@ Rs. 95.79 Per Sqm Rs 517.27
11 Cost of Latrine Door-1No Rs 3000.00
Vantilator with Glass fittings - 02 Nos @ 700.00 per No Rs 1400.00
12 Cost of PHD Fittings Rs 3000.00
13 Cost of Sanitary Fittings Rs 6500.00
14 Cost of Electric Fittings Rs 1000.00
Total Rs 32352.33
Say Rs. 30000.00
(Rupees Thirty thousand Only)
The estimate has been prepared basing on S/R 2008 & enhanced labour rate
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-REPAIR OF FOREST GUARD QUARTER AT NEW FOREST
COLONY,NABARANGPUR.
Est.Cost:- Rs.60,000/-
1 E/W in excavation in hard soil in Foundation with initial lead & lift
including rough dressing & breaking clods etc. complete.
Boundary wall 1X 13.10 X 0.60 X 0.60 = 4.72 Cum
@ Rs 4721.40 Per 100 Cum Rs 222.66
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Boundary wall 1X 13.10 X 0.60 X 0.05 = 0.39 Cum
@ Rs. 208.21 Per Cum Rs 81.83
3 CC (1:4:8) using 40 mm size hbg metal including all complete.
Boundary wall 1X 13.10 X 0.60 X 0.15 = 1.18 Cum
@ Rs 2085.29 Per 100 Cum Rs 2458.56
4 RR stone massonary in CM (1:6) to the F&P including all
cost,conveyance,royality etc. complete.
1st Footings
Boundary wall 1X 13.10 X 0.50 X 0.45 = 2.95 Cum
2nd Footings
Boundary wall 1X 13.10 X 0.45 X 0.45 = 2.65 Cum
Total = 5.60 Cum
@ Rs. 1419.53 Per Cum Rs 7949.74
5 WBCB in CM (1:6) to the super structure
Boundary wall 1X 13.10 X 0.23 X 1.50 = 4.52 Cum
12 X 0.35 X 0.12 X 1.50 = 0.76 Cum
Total 5.28 Cum
Deduction
Gate 1X 1.20 X 0.23 X 1.50 = 0.41
Total 0.41 Cum
Net Qty = 4.86 Cum
@ Rs. 1947.29 Per Cum Rs 9466.75
6 12 mm CP in CM (1:6) to the superstructure
Qty = 52.40 Sqm @ 38.03 Per Sqm Rs 1992.77
7 Cost of MS Door-7No Total 360 Kg @ Rs.49.00 Per Kg Rs 17640.00
Cost of MS window-5No Total 210 Kg @ Rs.49.00 Per Kg Rs 10290.00
Cost of grill gate-1No Total 40 Kg @ Rs.49.00 Per Kg Rs 1960.00
8 Cost of Electric Fittings Rs 6500.00
9 Dismanteling & removing doors & windows & vantilators including
removal of frame,hinges,fastening & stacking the same for reuse
& removing the debries within 50 mtr. Lead.
Door 5X 0.90 X 1.95 = 8.78 Sqm
2X 0.75 X 1.95 = 2.93 Sqm
Window 5X 0.90 X 1.20 = 5.40 Sqm
Total = 17.10 Sqm
@ Rs. 206.04 Per Sqm Rs 1808.00
10 Fixing,fitting of MS Door & Window LS Rs 2500.00
11 Cost of Paintings including paint etc complete. Rs 1500.00
Total Rs 64370.32
Say Rs. 60000.00
(Rupees Sixty thousand Only)
The estimate has been prepared basing on S/R 2008 & enhanced labour rate
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-CONST OF CHECK GATE BOUNDARY WALL WITH LATRINE AT
PAPADAHANDI..
Est.Cost:- Rs.60,000/-
1 E/W in excavation in hard soil in Foundation with initial lead & lift
including rough dressing & breaking clods etc. complete.
Boundary wall 1X 40.00 X 0.45 X 0.45 = 8.10 Cum
Septic Tank 1X 2.00 X 2.50 X 2.50 = 12.50 Cum
Total = 20.60 Cum
@ Rs 4721.40 Per 100 Cum Rs 972.61
2 CC (1:4:8) using 40 mm size hbg metal including all complete.
Septic Tank 1X 2.00 X 2.50 X 0.15 = 0.75 Cum
@ Rs 2085.29 Per 100 Cum Rs 1563.97
3 RR stone massonary in sand grouted using stone other than granite
in F & P including all cost , conveyance , royality etc. complete.
1st Footings
Boundary wall 1X 40.00 X 0.45 X 0.45 = 8.10 Cum
@ Rs. 772.58 Per Cum Rs 6257.90
4 RR stone massonary in CM (1:6) to the F&P including all
cost,conveyance,royality etc. complete.
2nd Footings
Boundary wall 1X 40.00 X 0.30 X 0.30 = 3.60 Cum
@ Rs. 1419.53 Per Cum Rs 5110.32
5 WBCB in CM (1:6) to the super structure
Septic Tank 2X 2.00 X 0.23 X 2.50 = 2.30 Cum
2X 2.00 X 0.23 X 2.50 = 2.30 Cum
Latrine 2X 1.20 X 0.23 X 2.50 = 1.38 Cum
2X 2.00 X 0.23 X 2.50 = 2.30 Cum
Boundary wall 1X 40.00 X 0.23 X 1.20 = 11.04 Cum
Pillar of Boundary 10 X 0.35 X 0.12 X 1.20 = 0.50 Cum
Total 19.82 Cum
Deduction
Gate 1X 2.00 X 0.23 X 1.20 = 0.55
Door Opening 1X 0.75 X 0.23 X 2.50 = 0.43
Total 0.98 Cum
Net Qty = 18.84 Cum
@ Rs. 1947.29 Per Cum Rs 36688.42
6 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Slab 1X 2.00 X 2.50 X 0.10 = 0.50 Cum
1X 2.10 X 3.00 X 0.10 = 0.63 Cum
Total = 1.13 Cum
@ Rs. 3317.48 Per Cum Rs 3748.75
7 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 1.02 Qtl
@ Rs. 4000.00 Per Qtl Rs 4068.00
8 20 mm CP in CM (1:4) to the grading plaster to the
Slab 1X 2.10 X 3.00 = 6.30 Sqm
@ Rs. 85.49 Per Sqm Rs 538.56
9 12 mm CP in CM (1:6) to the superstructure
Qty = 163.83 Sqm @ 38.03 Per Sqm Rs 6230.55
10 2.50 CmM thick AS flooring in CC (1:2:4) using 12 mm size hbg
Chips including all cost , conveyance , royality etc. complete
Toilet 1X 1.20 X 2.00 = 2.40 Sqm
1X 2.00 X 2.50 = 5.00 Sqm
Total = 7.40 Sqm
@ Rs. 95.79 Per Sqm Rs 708.85
11 Cost of Latrine Door-1No Rs 2500.00
12 Cost of Sanitary Fittings Rs 1500.00
13 Cost of White washing etc Rs 500.00
Total Rs 70387.93
Say Rs. 60000.00
(Rupees Sixty thousand Only)
The estimate has been prepared basing on S/R 2008 & enhanced labour rate
Junior Engineer
Nabarangpur Block
Est.Cost:- Rs.1,30,000/-
1 E/W in excavation in hard soil in Foundation with initial lead & lift
including rough dressing & breaking clods etc. complete.
Extension wall 1X 4.80 X 0.60 X 0.60 = 1.73 Cum
2X 1.62 X 0.60 X 0.60 = 1.17 Cum
Latrine Tank 1X 3.60 X 2.40 X 3.00 = 25.92 Cum
Latrine Room-1 2X 3.23 X 0.60 X 0.60 = 2.33 Cum
2X 1.43 X 0.60 X 0.60 = 1.03 Cum
Latrine Room-2 2X 3.23 X 0.60 X 0.60 = 2.33 Cum
2X 1.43 X 0.60 X 0.60 = 1.03 Cum
Total = 35.52 Cum
@ Rs 4721.40 Per 100 Cum Rs 1677.27
2 CC (1:4:8) using 40 mm size hbg metal including all complete.
Flooring 1X 4.80 X 1.80 X 0.10 = 0.86 Cum
2X 4.80 X 3.60 X 0.10 = 3.46 Cum
Latrine Tank 1X 3.60 X 2.40 X 0.10 = 0.86 Cum
Latrine Room-1 2X 3.23 X 0.60 X 0.10 = 0.39 Cum
2X 1.43 X 0.60 X 0.10 = 0.17 Cum
Latrine Room-2 2X 3.23 X 0.60 X 0.10 = 0.39 Cum
2X 1.43 X 0.60 X 0.10 = 0.17 Cum
Total = 6.30 Cum
@ Rs 2085.29 Per Cum Rs 13142.34
3 RR stone massonary in sand grouted using stone other than granite
in F & P including all cost , conveyance , royality etc. complete.
Extension wall 1X 4.80 X 0.60 X 0.60 = 1.73 Cum
2X 1.62 X 0.60 X 0.60 = 1.17 Cum
Total = 2.89 Cum
@ Rs. 772.58 Per Cum Rs 2236.16
4 RR stone massonary in CM (1:6) to the F&P including all
cost,conveyance,royality etc. complete.
Extension wall 1X 4.80 X 0.45 X 0.45 = 0.97 Cum
2X 1.62 X 0.46 X 0.45 = 0.67 Cum
Latrine Room-1 2X 3.13 X 0.50 X 0.50 = 1.57 Cum
2X 3.08 X 0.45 X 0.45 = 1.25 Cum
2X 1.53 X 0.50 X 0.50 = 0.77 Cum
2X 1.58 X 0.45 X 0.45 = 0.64 Cum
Latrine Room-2 2X 3.13 X 0.50 X 0.50 = 1.57 Cum
2X 3.08 X 0.45 X 0.45 = 1.25 Cum
2X 1.53 X 0.50 X 0.50 = 0.77 Cum
2X 1.58 X 0.45 X 0.45 = 0.64 Cum
Total = 10.08 Cum
@ Rs. 1419.53 Per Cum Rs 14305.04
5 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Plinth Bend 1X 9.32 X 0.23 X 0.15 = 0.32 Cum
Lintel Bend 1X 9.32 X 0.23 X 0.15 = 0.32 Cum
Slab 1X 4.06 X 2.86 X 0.10 = 1.16 Cum
Slab 2X 3.16 X 2.56 X 0.10 = 1.62 Cum
Total = 3.42 Cum
@ Rs. 3317.48 Per Cum Rs 11352.95
6 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 3.08 Qtl
@ Rs. 4000.00 Per Qtl Rs 12319.78
7 WBCB in CM (1:6) to the super structure
Extension wall 1X 4.80 X 0.23 X 2.50 = 2.76 Cum
2X 1.80 X (2.50+2.75)/2 X 0.23 = 2.17 Cum
Latrine Tank 1X 4.06 X 0.23 X 3.00 = 2.80 Cum
1X 2.40 X 0.23 X 3.00 = 1.66 Cum
Latrine Room-1 2X 2.86 X 0.23 X 2.40 = 3.16 Cum
2X 1.80 X 0.23 X 2.40 = 1.99 Cum
Latrine Room-2 2X 2.86 X 0.23 X 2.40 = 3.16 Cum
2X 1.80 X 0.23 X 2.40 = 1.99 Cum
Total 19.68 Cum
Deduction
Door 1X 0.90 X 0.23 X 2.00 = 0.41
2X 0.75 X 0.23 X 2.00 = 0.69
Total 1.10 Cum
Net Qty = 18.58 Cum
@ Rs. 1947.29 Per Cum Rs 36173.22
8 Rigid & smooth centering , shuttering for RCC work
& dismanteling them after casting.
i) Plinth Bend 2X 3.16 X 2.56 = 16.18 Sqm
Total = 16.18 Sqm
@ Rs. 60.93 Per Sqm Rs 985.79
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF SILAGE INSIDE PAPADAHANDI DEER PARK.
Est.Cost:- Rs.1,85,000/-
1 E/W in excavation in hard soil in Foundation with initial lead & lift
including rough dressing & breaking clods etc. complete.
Foundation 1X 3.46 X 7.15 X 1.80 = 44.53 Cum
@ Rs 5364.24 Per 100 Cum Rs 2388.71
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Foundation 1X 3.46 X 7.15 X 0.05 = 1.24 Cum
@ Rs. 196.79 Per Cum Rs 243.42
3 CC (1:4:8) using 40 mm size hbg metal including all complete.
Foundation 1X 3.46 X 7.15 X 0.15 = 3.71 Cum
Total = 3.71 Cum
@ Rs 1701.52 Per 100 Cum Rs 6314.09
4 WBCB in CM (1:6) to the super structure
Silage Long Wall 2X 7.15 X 0.23 X 3.00 = 9.87 Cum
Silage Short Wall 5X 3.00 X 0.23 X 3.00 = 10.35 Cum
Upstair 2X 7.15 X 0.23 X 2.40 = 7.89 Cum
5X 3.00 X 0.23 X 2.40 = 8.28 Cum
Parapet 1X 8.45 X 0.23 X 0.75 = 1.46 Cum
Total 37.85 Cum
Deduction
Door 8X 0.75 X 0.23 X 1.50 = 2.07
Vantilator 8X 0.30 X 0.23 X 0.60 = 0.33
Total 2.40 Cum
Net Qty = 35.45 Cum
@ Rs. 1540.87 Per Cum Rs 54619.26
5 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Grade Beam 8X 4.50 X 0.23 X 0.15 = 1.24 Cum
Stair Case 8X 1.00 X 0.30 X 0.10 = 0.24 Cum
8X 1.00 X 0.10 X 0.10 = 0.08 Cum
Slab 1X 7.45 X 4.76 X 0.10 = 3.55 Cum
Slab 1X 7.45 X 4.76 X 0.10 = 3.55 Cum
Total = 8.65 Cum
@ Rs. 3317.48 Per Cum Rs 28710.79
6 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 7.79 Qtl
@ Rs. 4000.00 Per Qtl Rs 31155.84
7 Rigid & smooth centering , shuttering for RCC work
& dismanteling them after casting.
i)Slab 2X 7.45 X 4.76 = 70.92 Sqm
Stair Case 8X 1.00 X 0.30 = 2.40 Cum
8X 1.00 X 0.10 = 0.80 Cum
Total = 74.12 Sqm
@ Rs. 177.17 Per Sqm Rs 13132.55
ii)Beam 8X 4.50 X 0.53 = 19.08 Sqm
Total = 19.08 Sqm
@ Rs. 278.27 Per Sqm Rs 5309.33
8 20 mm CP in CM (1:4) to the grading plaster to the
Slab 2X 7.45 X 4.76 = 70.92 Sqm
@ Rs. 85.49 Per Sqm Rs 6063.02
9 12 mm CP in CM (1:6) to the superstructure
Qty = 308.24 Sqm @ 38.03 Per Sqm Rs 11722.18
10 2.50 CmM thick AS flooring in CC (1:2:4) using 12 mm size hbg
Chips including all cost , conveyance , royality etc. complete
Room 8X 1.50 X 3.00 = 36.00 Sqm
@ Rs. 95.79 Per Sqm Rs 3448.44
11 Finishing wall surface with water proof cement paint to the newly
plastered surface to give an even shade with all cost etc complete
Total Qty = 308.24 Sqm
Add for ceiling = 74.12
Total = 382.36 Sqm
@ Rs. 14.76 Per Sqm Rs 5642.61
12 Painting 2 coats with any approved Paint ( Labour Only )
Door 8X 2.25 X 0.75 X 1.50 = 20.25 Sqm
Total = 20.25 Sqm
@ Rs. 22.15 Per Sqm Rs 448.54
13 Cost of Paint
Qty = ### Litre
@ Rs. 150.00 Per Litre Rs 379.69
14 Cost of Door-8No Rs 15000.00
Iron Stair Case 150 Kg @ 49.00 per Kg Rs 7350.00
Vantilator 8 Nos @ Rs 100.00 per No Rs 800.00
Total Rs 192728.45
Say Rs. 185000.00
(Rupees One Lakh Eighty Five thousand Only)
The estimate has been prepared basing on S/R 2008 & enhanced labour rate
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:- " CONST. OF TANK UNDER SCM AT PONDIKOTE MICRO WATERSHED ".
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"EXTENSION OF OLD REST SHED AT OLD DFO OFFICE ,
NABARANGPUR".
Est.Cost:- Rs.65,000/-
1 Dismanteling GCI or AC sheet roofing after carefully removing the bolts
& nuts including stacking the useful materials for reuse & removing the debries
within 50 mtr. Lead.
Roof 1X 6.70 X 3.05 = 20.44 Sqm
Total = 20.44 Sqm
@ Rs. 17.99 Per Sqm Rs 367.57
2 Labour for fixing GCI Sheet in roof drilling hole in wind ties including
fixing of ridges valleys windties etc excluding cost of fittings per 1 sqm.
Roof 1X 6.70 X 3.05 = 20.44 Sqm
Total = 20.44 Sqm
@ Rs. 40.95 Per Sqm Rs 836.81
3 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Angon 1X 8.53 X 9.14 X 0.05 = 3.90 Cum
1X 7.31 X 1.36 X 0.05 = 0.50 Cum
1X 3.05 X 1.36 X 0.05 = 0.21 Cum
Room 1X 6.10 X 2.40 X 0.15 = 2.20 Cum
Total = 6.80 Cum
@ Rs. 208.21 Per Cum Rs 1415.53
4 CC (1:4:8) using 40 mm size hbg metal including all complete.
Angon 1X 8.53 X 9.14 X 0.10 = 7.80 Cum
1X 7.31 X 1.36 X 0.10 = 0.99 Cum
1X 3.05 X 1.36 X 0.10 = 0.41 Cum
Room 1X 6.10 X 2.40 X 0.10 = 1.46 Cum
Total = 10.67 Cum
@ Rs 2085.29 Per Cum Rs 22248.77
5 WBCB in CM (1:6) to the super structure
Extension of wall 1X 6.10 X 0.23 X 1.20 = 1.68 Cum
2X 2.40 X 0.23 X 1.20 = 1.32 Cum
Pillar 5X 0.35 X 0.35 X 1.20 = 0.74 Cum
Door Close 1X 0.90 X 0.23 X 1.80 = 0.37 Cum
Deduction Total 4.12 Cum
Door 1X 0.90 X 0.23 X 1.20 = 0.25
Total 0.25 Cum
Net Qty = 3.87 Cum
@ Rs. 1947.29 Per Cum Rs 7531.34
6 2.50 CmM thick AS flooring in CC (1:2:4) using 12 mm size hbg
Chips including all cost , conveyance , royality etc. complete
Angon 1X 8.53 X 9.14 = 77.96 Sqm
1X 7.31 X 1.36 = 9.94 Sqm
1X 3.05 X 1.36 = 4.15 Sqm
Room 1X 6.10 X 2.40 = 14.64 Sqm
Total = 106.69 Sqm
@ Rs. 120.74 Per Sqm Rs 12882.72
7 12 mm CP in CM (1:6) to the superstructure
Qty = 120.00 Sqm @ 48.01 Per Sqm Rs 5761.15
8 Finishing wall surface with water proof cement paint to the newly
plastered surface to give an even shade with all cost etc complete
Total Qty = 120.00 Sqm
Total = 120.00 Sqm
@ Rs. 14.76 Per Sqm Rs 1770.88
9 Cost of Door-1No ### Kg @ 46.00 per Kg Rs 2760.00
Grill-4 Nos ### Kg @ 46.00 per Kg Rs 12880.00
10 Painting 2 coats with any approved Paint ( Labour Only )
Door 1X 2.25 X 0.90 X 1.80 = 3.65 Sqm
Grill-4 Nos 2X 1.25 X 2.40 X 1.20 = 7.20 Sqm
1X 1.25 X 2.70 X 1.20 = 4.05 Sqm
1X 1.25 X 1.80 X 1.20 = 2.70 Sqm
Total = 17.60 Sqm
@ Rs. 28.54 Per Sqm Rs 502.22
11 Cost of Paint
Qty = ### Litre
@ Rs. 150.00 Per Litre Rs 329.91
Total Rs 69286.92
Say Rs. 65000.00
(Rupees Sixty Five thousand Only)
The estimate has been prepared basing on S/R 2008 & enhanced labour rate
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF COW CATCHER & GATE AT DFO OFFICE ,
NABARANGPUR".
Est.Cost:- Rs.56,000/-
1 E/W in excavation in hard soil in Foundation with initial lead & lift
including rough dressing & breaking clods etc. complete.
Foundation 1X 3.60 X 2.40 X 1.35 = 11.66 Cum
@ Rs 4721.40 Per 100 Cum Rs 550.70
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Foundation 1X 3.60 X 2.40 X 0.08 = 0.65 Cum
@ Rs. 208.21 Per Cum Rs 134.92
3 CC (1:4:8) using 40 mm size hbg metal including all complete.
Foundation 1X 3.60 X 2.40 X 0.15 = 1.30 Cum
2X 3.60 X (0.60+0.45)/2 X 1.20 = 4.54 Cum
Total = 5.83 Cum
@ Rs 2085.29 Per 100 Cum Rs 12161.42
4 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Pillar 2X 0.23 X 0.30 X 1.80 = 0.25 Cum
Total = 0.25 Cum
@ Rs. 3317.48 Per Cum Rs 824.06
5 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 0.25 Qtl
@ Rs. 4000.00 Per Qtl Rs 1000.00
6 Rigid & smooth centering , shuttering for RCC work
& dismanteling them after casting.
i)Beam 2X 1.80 X 0.86 = 3.10 Sqm
Total = 3.10 Sqm
@ Rs. 278.27 Per Sqm Rs 861.51
7 CC (1:2:4) using 12 mm size hbg chips including all cost
conveyance , royality etc. complete
Wall 2X 3.60 X 0.45 X 0.1 = 0.32
1X 3.60 X 1.20 X 0.05 = 0.22
Total = 0.54 Cum
@ Rs. 3219.24 Per Cum Rs 1738.39
8 WBCB in CM (1:6) to the super structure
Extension of wall 4X 0.23 X 0.10 X 1.80 = 0.17 Cum
4X 0.50 X 0.10 X 1.80 = 0.36 Cum
Total = 0.53 Cum
@ Rs. 1947.29 Per Cum Rs 1023.50
9 12 mm CP in CM (1:6) to the superstructure
Qty = 7.41 Sqm @ 48.01 Per Sqm Rs 355.75
10 Cost of MS Channel Rs 5000.00
11 Cost of MS Pipe 10 Nos @ Rs 2600.00 Per No Rs 26000.00
12 Cost of MS Signboard ( 6.10X0.70) mtr Size Rs 6000.00
13 Cost of Making & welding Charges Rs 2000.00
Total Rs 57650.26
Say Rs. 56000.00
(Rupees Fifty Six thousand Only)
The estimate has been prepared basing on S/R 2008 & enhanced labour rate
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF BOUNDARY WALL WITH BARBED WIRE FENCING FOR
DEVELOPMENT OF DEER PARK AT PAPADAHANDI ( TOTAL = 613.00 RMT )."
Est.Cost:- Rs.32,58,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Pillar 360 X 1.05 X 1.05 X 1.05 = 416.75 Cum
Boundary Wall 1X 530.00 X 0.75 X 0.75 = 298.13 Cum
Total = 714.87 Cum
@ Rs. 4721.40 Per 100 Cum Rs 33751.87
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Pillar 360 X 1.05 X 1.05 X 0.05 = 19.85 Cum
Boundary Wall 1X 530.00 X 0.75 X 0.05 = 19.88 Cum
Total = 39.72 Cum
@ Rs. 208.21 Per Cum Rs 8269.96
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Pillar 360 X 1.05 X 1.05 X 0.15 = 59.54 Cum
Boundary Wall 1X 530.00 X 0.75 X 0.15 = 59.63 Cum
Total = 119.16 Cum
@ Rs. 2085.29 Per Cum Rs 248483.39
4 RR stone massonary in CM (1:6) to the F&P including all
cost,conveyance,royality etc. complete.
Boundary Wall 1X 530.00 X 0.60 X 0.55 = 174.90 Cum
1X 530.00 X 0.45 X 0.45 = 107.33 Cum
Total = 282.23 Cum
@ Rs. 1419.53 Per Cum Rs 400627.95
5 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Pillar 360 X 1.05 X 1.05 X 0.30 = 119.07 Cum
360 X 0.35 X 0.25 X 4.00 = 126.00 Cum
Plinth 1X 530.00 X 0.45 X 0.15 = 35.78 Cum
Total = 280.85 Cum
@ Rs. 3317.48 Per Cum Rs 931697.48
6 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 150.00 Qtl
@ Rs. 4110.80 Per Qtl Rs 616619.25
7 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Plinth 1X 2 X 530.00 X 0.15 = 159.00 Sqm
Total = 159.00 Sqm
@ Rs. 60.93 Per Sqm Rs 9687.74
ii) Pillar 360 X 1 X 1.20 X 4.00 = 1728.00 Sqm
@ Rs. 192.14 Per Sqm Rs 332019.66
8 WBCB in CM (1:6) in superstructure including all cost, conveyance
royality etc complete.
Boundary Wall 1X 530.00 X 0.23 X 3.00 = 365.70 Cum
@ Rs. 1947.29 Per Cum Rs 712124.25
9 12 mm CP in CM (1:6) to the Super structure
Boundary Wall 1X 2 X 530.00 X 3.00 = 3180.00 Sqm
@ Rs. 48.01 Per Sqm Rs 152670.59
10 Labour for fixing barbed wire fencing & post by means of stapples
& straining hooks by means of tying with GI wires including cost of staples,hooks &
tying wires.
Barbed wire Fencing 5X 613.00 = 3065.00 RMT
Total = 3065.00 RMT
@ Rs. 500.00 Per 100 MT Rs 15325.00
11 Cost of Barbed Wire
Total 3065.00 RMt
@ 0.16 Kg per MT = 490.40 Kg
@ 47.00 Per Kg Rs 23048.80
12 Cost of MS angles to be fixed with barbed wire on the top of the
Buondary wall( 50mmX50mmX6 mm) size of 0.75 mtr height.
including drilling holes & placing in position etc complete.
Total 360 Nos @ 170.00 per No Rs 61200.00
Grand Total Rs. 3545525.95
Limitted to Rs. 3258000.00
(Rupees Thirty Two Lakhs & Fifty Eight Thousand Only)
Certified that the Estimate has been prepared basing on Schedule of rates 2008 & enhanced
labour rate as on 2008 & prepared on request
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"EXTENSION OF WALL INSIDE DEER PARK , PAPADAHANDI".
Est.Cost:- Rs.56,000/-
1 WBCB in CM (1:6) to the super structure
Extension of wall 2X 6.10 X 0.35 X 0.45 = 1.92 Cum
1X 17.75 X 0.35 X 0.45 = 2.80 Cum
2X 3.00 X 0.35 X 0.45 = 0.95 Cum
Pillar 11 X 0.35 X 0.35 X 1.60 = 2.16 Cum
Board 9X 0.23 X 0.80 X 1.60 = 2.65 Cum
2X 6.10 X 0.23 X 2.40 = 6.73 Cum
2X 3.00 X 0.35 X 2.40 = 5.04 Cum
Total = 22.24 Cum
Deduction
Door 1X 1.00 X 0.23 X 2.00 = 0.46
Window 2X 0.90 X 0.23 X 1.20 = 0.50
Total 0.46 Cum
Net Qty = 21.78 Cum
@ Rs. 1947.29 Per Cum Rs 42416.13
2 12 mm CP in CM (1:6) to the superstructure
Qty = 180.00 Sqm @ 48.01 Per Sqm Rs 8641.73
3 2.50 CmM thick AS flooring in CC (1:2:4) using 12 mm size hbg
Chips including all cost , conveyance , royality etc. complete
2X 6.10 X 2.40 = 29.28 Sqm
Total = 29.28 Sqm
@ Rs. 120.74 Per Sqm Rs 3535.41
4 Fixing Tiles in dados skirting& risers of steps on 12 mm thick cement plaster
( 1:3) jointed with neat slurrymixed with pigment to match the shade of the
tiles including rubbing & polishing complete excluding cost of precast tiles.
Pillar 11 X 1 X 0.70 X 1.60 = 12.32 Sqm
Total = 12.32 Sqm
@ Rs. 237.06 Per Sqm Rs 2920.53
5 Cost of Precast Tiles
Wall Tiles ### Sqm @ 320.00 Per Sqm Rs 3942.40
6 Finishing wall surface with water proof cement paint to the newly
plastered surface to give an even shade with all cost etc complete
Total Qty = 180.00 Sqm
Total = 180.00 Sqm
@ Rs. 14.76 Per Sqm Rs 2656.32
7 Painting 2 coats with any approved Paint ( Labour Only )
Door 1X 2.25 X 1.00 X 2.00 = 4.50 Sqm
Window 2X 2.75 X 0.90 X 1.20 = 5.94 Sqm
Grill Door 1X 1.25 X 0.90 X 1.60 = 1.80 Sqm
Grill 9X 1.25 X 1.60 X 0.60 = 10.80 Sqm
Total = 23.04 Sqm
@ Rs. 28.54 Per Sqm Rs 657.64
8 Cost of Paint
Qty = ### Litre
@ Rs. 150.00 Per Litre Rs 432.00
9 Cost of MS Grill,Door & Window 650 KG @ Rs.45.00 per Kg Rs 29250.00
Total Rs 94452.17
Say Rs. 88000.00
(Rupees Eighty Eight thousand Only)
The estimate has been prepared basing on S/R 2008 & enhanced labour rate
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:- " CONST. OF TANK UNDER SCM AT PONDIKOTE MICRO WATERSHED ".
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF CC ROAD AT DFO OFFICE NABARANGPUR".
Est.Cost:- Rs.1,01,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Road 1X 4.50 X (7.50+4.50)/2 X 0.15 = 4.05 Cum
Total = 4.05 Cum
@ Rs. 4721.40 Per 100 Cum Rs 191.22
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Road 1X 4.50 X (7.50+4.50)/2 X 0.05 = 1.35 Cum
2X 22.00 X (4.10+3.80)/2 X 0.05 = 8.69 Cum
1X 9.20 X (14.00+4.50)/2 X 0.05 = 4.26 Cum
Total = 14.30 Cum
@ Rs. 204.13 Per Cum Rs 2918.04
3 CC (1:4:8) using40 mm size cbg metal including all cost,conveyance
royality etc.complete
Road 1X 4.50 X (7.50+4.50)/2 X 0.10 = 2.70 Cum
2X 22.00 X (4.10+3.80)/2 X 0.10 = 17.38 Cum
1X 9.20 X (14.00+4.50)/2 X 0.10 = 8.51 Cum
Total = 28.59 Cum
@ Rs. 1904.81 Per Cum Rs 54458.52
4 CC (1:2:4) using 12 mm size cbg Chips including all cost, conveyance
royality etc complete.
Road 1X 4.50 X (7.50+4.50)/2 X 0.05 = 1.35 Cum
2X 22.00 X (4.10+3.80)/2 X 0.05 = 8.69 Cum
1X 9.20 X (14.00+4.50)/2 X 0.05 = 4.26 Cum
Total = 14.30 Cum
@ Rs. 2904.39 Per Cum Rs 41518.26
5 Collecting , conveying,supplying of good quality Murrom or Gravel
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 9.20 X (14.00+4.50)/2 X (0.05+0.15)/2 = 8.51 Cum
@ Rs. 188.00 Per Cum Rs 1599.88
6 Labour for spreading muroom or gravel including watering but excluding cost
& conveyance of Muroom
Road 1X 9.20 X (14.00+4.50)/2 X (0.05+0.15)/2 = 8.51 Cum
@ Rs. 32.44 Per Cum Rs 276.06
Grand Total Rs. 100961.97
Say Rs. 101000.00
(Rupees one Lakh & one thousand Only)
The estimate has been prepared basing on S/R 2008 & enhanced labour rate
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF LAWN AT DFO OFFICE NABARANGPUR".
Est.Cost:- Rs.42,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Barricode 1X 29.40 X 0.40 X 0.50 = 5.88 Cum
Total = 5.88 Cum
@ Rs. 4721.40 Per 100 Cum Rs 277.62
2 CC (1:4:8) using40 mm size cbg metal including all cost,conveyance
royality etc.complete
Barricode 1X 29.40 X 0.40 X 0.15 = 1.76 Cum
Total = 1.76 Cum
@ Rs. 1904.81 Per Cum Rs 3360.08
3 WBCB in CM (1:6) to the Sub structure & super Structure including all cost
royality etc complete.
Barricode 1X 29.40 X 0.35 X 0.35 = 3.60 Cum
2X 29.40 X 0.23 X 0.60 = 8.11 Cum
Deduction Total = 11.72 Cum
Door Opening 1X 0.75 X 0.23 X 0.60 = 0.10 Cum
Net Qty = 11.61 Cum
@ Rs. 1947.29 Per Cum Rs 22612.72
4 12 mm CP in CM (1:6) to the superstructure including all
cost , conveyance etc complete
2X 2 X (29.4-0.75) X 0.60 = 68.76 Sqm
Total = 68.76 Sqm
@ Rs. 48.01 Per Sqm Rs 3301.14
5 Painting 2 coats with new iron work with any approved paint
1X 1.25 X 29.40 X 0.60 = 22.05 Sqm
Total = 22.05 Sqm
@ Rs. 28.54 Per Sqm Rs 629.39
6 Cost of Paint = 22.05X1.25/10 = 2.76 Litre
@ Rs. 150.00 Per Litre Rs 413.44
7 Cost of MS Grill for Lawn Barricode Wall Total 29.40 RMT Rs 15000.00
Grand Total Rs. 45594.39
Say Rs. 42000.00
(Rupees Forty Two thousand Only)
The estimate has been prepared basing on S/R 2008 & enhanced labour rate
Junior Engineer
Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD WITH DRAIN AT BOXAGUDA VILLAGE ROAD."
Est.Cost:- Rs.3,00,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Drain 1X 235.00 X 1.20 X 0.75 = 211.50 Cum
@ Rs. 5395.57 Per 100 Cum Rs 11411.63
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Drain 1X 235.00 X 1.20 X 0.05 = 14.10 Cum
@ Rs. 209.71 Per Cum Rs 2956.94
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Drain 1X 235.00 X 1.20 X 0.10 = 28.20 Cum
2X 235.00 X 0.30 X 0.60 = 84.60 Cum
Total 112.80 Cum
@ Rs. 2138.32 Per Cum Rs 241202.72
4 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
Drain 2X 2X 235.00 X 0.60 = 564.00 Sqm
@ Rs. 62.46 Per Sqm Rs 35228.67
5 12 mm CP in CM (1:6) to the Super structure
Drain 2X 235.00 X 0.60 = 282.00 Sqm
@ Rs. 51.59 Per Sqm Rs 14548.27
6 PCC (1:2:4) using 12 mm size hbg chips including all complete.
Drain 2X 235.00 X 0.30 X 0.05 = 7.05 Cum
1X 235.00 X 0.60 X 0.05 = 7.05 Cum
Total = 14.10 Cum
@ Rs. 3289.62 Per Cum Rs 46383.63
7 Provision for rest shed , medicenes for laboureres etc. Rs 2000.00
8 Provision for remuneration of Gram Sathi 750 mandays @ 4.00 Rs 3000.00
9 Provision for Work Sign board & Photograph Rs. 1300.00
Grand Total Rs. 358031.87
Limitted to Rs. 300000.00
(Rupees Three Lakhs Only)
Technically Sanctioned for Rs.3,00,000/-
(Rupees Three Lakhs Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur
Administratively approved for Rs.5,00,000/-
(Rupees Five Lakhs Only)
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF PUCCA DRAIN WITH CULVERT AT BHATRA CHIKILI."
Est.Cost:- Rs.3,00,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Drain 1X 141.00 X 1.20 X 0.75 = 126.90 Cum
Culvert ( U/S cutt-off) 1X 8.40 X 1.20 X 1.20 = 12.10 Cum
Culvert ( D/S cutt-off) 1X 8.40 X 1.20 X 1.50 = 15.12 Cum
Abutment 2X 3.80 X 1.20 X 1.20 = 10.94 Cum
Bed 1X 3.80 X 1.70 X 0.45 = 2.91 Cum
Total = 167.97 Cum
@ Rs. 5395.57 Per 100 Cum Rs 9062.78
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Drain 1X 141.00 X 1.20 X 0.05 = 8.46 Cum
Culvert ( U/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
Culvert ( D/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
Abutment 2X 3.80 X 1.20 X 0.15 = 1.37 Cum
Bed 1X 3.80 X 1.70 X 0.15 = 0.97 Cum
Total = 13.82 Cum
@ Rs. 209.71 Per Cum Rs 2898.43
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Drain 1X 141.00 X 1.20 X 0.10 = 16.92 Cum
2X 141.00 X 0.30 X 0.60 = 50.76 Cum
Culvert ( U/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
1X 8.40 X (1.00+0.75)/2 X 0.90 = 4.73 Cum
Culvert ( D/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
1X 8.40 X (1.00+0.75)/2 X 0.90 = 4.73 Cum
Abutment 2X 3.80 X 1.20 X 0.30 = 2.74 Cum
2X 3.80 X (1.00+0.75)/2 X 0.75 = 4.99 Cum
2X 6.00 X (0.75+0.0.50)/2 X 1.15 = 8.63 Cum
Wing wall 4X 2.00 X (0.75+0.0.50)/2 X 1.15 = 5.75 Cum
Bed 1X 4.50 X 2.00 X 0.30 = 2.70 Cum
Parapet 2X 3.00 X 0.45 X 0.45 = 1.22 Cum
Total = 106.17 Cum
@ Rs. 2138.32 Per Cum Rs 227020.30
4 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Slab 1X 6.00 X 3.00 X 0.25 = 4.50 Cum
Total = 4.50 Cum
@ Rs. 3336.28 Per Cum Rs 15013.24
5 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 4.05 Qtl
@ Rs. 4125.86 Per Qtl Rs 16709.71
6 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Drain 2X 2X 141.00 X 0.60 = 338.40 Sqm
Culvert ( U/S cutt-off) 1X 2X 8.40 X 0.90 = 15.12 Sqm
Culvert ( D/S cutt-off) 1X 2X 8.40 X 0.90 = 15.12 Sqm
Abutment 2X 2X 3.80 X 0.75 = 11.40 Sqm
2X 2X 6.00 X 1.00 = 24.00 Sqm
Wing wall 4X 2X 2.00 X 1.15 = 18.40 Sqm
Parapet 2X 2X 3.00 X 0.45 = 5.40 Sqm
Total = 427.84 Sqm
@ Rs. 62.46 Per Sqm Rs 26723.82
ii) Slab 1X 1X 6.00 X 3.00 = 18.00 Sqm
@ Rs. 201.68 Per Sqm Rs 3630.23
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur
DETAILED ESTIMATE FOR THE WORK:-"CONST. OF GUARD WALL AT BODAMUNDA VILLAGE ROAD."
Est.Cost:- Rs.3,00,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Guard wall 1X 91.50 X 1.05 X 1.05 = 100.88 Cum
Total = 100.88 Cum
@ Rs. 5395.57 Per 100 Cum Rs 5442.99
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Guard wall 1X 91.50 X 1.05 X 0.05 = 4.80 Cum
Total = 4.80 Cum
@ Rs. 209.71 Per Cum Rs 1007.40
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Guard wall 1X 91.50 X 1.05 X 0.15 = 14.41 Cum
1X 91.50 X (1.05+0.50)/2 X 1.85 = 131.19 Cum
Total = 145.60 Cum
@ Rs. 2138.32 Per Cum Rs 311338.35
4 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Guard wall 1X 2X 91.50 X 1.85 = 338.55 Sqm
@ Rs. 62.46 Per Sqm Rs 21146.57
5 12 mm CP in CM (1:6) to the Super structure
Guard wall 1X 2X 91.50 X 1.00 = 183.00 Sqm
@ Rs. 51.59 Per Sqm Rs 9440.90
6 PCC (1:2:4) using 12 mm size hbg chips including all complete.
Guard wall 1X 91.50 X 0.50 X 0.05 = 2.29 Cum
@ Rs. 3289.62 Per Cum Rs 7525.00
7 Provision for rest shed , medicenes for laboureres etc. Rs 2000.00
8 Provision for remuneration of Gram Sathi 750 mandays @ 4.00 Rs 3000.00
9 Provision for Work Sign board & Photograph Rs. 1300.00
Grand Total Rs. 362201.21
Limitted to Rs. 300000.00
(Rupees Three Lakhs Only)
Technically Sanctioned for Rs.3,00,000/-
(Rupees Three Lakhs Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur
Administratively approved for Rs.3,00,000/-
(Rupees Three Lakhs Only)
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD AT SAN KUMULI HARIJAN SAHI WITH GUARD
WALL, STONE SOLING & CULVERT."
Est.Cost:- Rs.3,00,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Guard wall 1X 55.00 X 1.05 X 1.05 = 60.64 Cum
Culvert ( U/S cutt-off) 1X 8.40 X 1.20 X 1.20 = 12.10 Cum
Culvert ( D/S cutt-off) 1X 8.40 X 1.20 X 1.50 = 15.12 Cum
Abutment 2X 3.80 X 1.20 X 1.20 = 10.94 Cum
Bed 1X 3.80 X 1.70 X 0.45 = 2.91 Cum
Total = 101.70 Cum
@ Rs. 5395.57 Per 100 Cum Rs 5487.54
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Guard wall 1X 55.00 X 1.05 X 0.05 = 2.89 Cum
Culvert ( U/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
Culvert ( D/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
Abutment 2X 3.80 X 1.20 X 0.15 = 1.37 Cum
Bed 1X 3.80 X 1.70 X 0.15 = 0.97 Cum
Total = 8.25 Cum
@ Rs. 209.71 Per Cum Rs 1729.81
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Guard wall 1X 55.00 X 1.05 X 0.15 = 8.66 Cum
1X 55.00 X (1.05+0.50)/2 X 1.85 = 78.86 Cum
Culvert ( U/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
1X 8.40 X (1.00+0.75)/2 X 0.90 = 4.73 Cum
Culvert ( D/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
1X 8.40 X (1.00+0.75)/2 X 0.90 = 4.73 Cum
Abutment 2X 3.80 X 1.20 X 0.30 = 2.74 Cum
2X 3.80 X (1.00+0.75)/2 X 0.75 = 4.99 Cum
2X 6.00 X (0.75+0.0.50)/2 X 1.15 = 8.63 Cum
Wing wall 4X 2.00 X (0.75+0.0.50)/2 X 1.15 = 5.75 Cum
Bed 1X 4.50 X 2.00 X 0.30 = 2.70 Cum
Parapet 2X 3.00 X 0.45 X 0.45 = 1.22 Cum
Total = 126.01 Cum
@ Rs. 2138.32 Per Cum Rs 269441.94
4 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Slab 1X 6.00 X 3.00 X 0.25 = 4.50 Cum
Total = 4.50 Cum
@ Rs. 3336.28 Per Cum Rs 15013.24
5 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 4.05 Qtl
@ Rs. 4125.86 Per Qtl Rs 16709.71
6 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Guard wall 1X 2X 55.00 X 1.85 = 203.50 Sqm
Culvert ( U/S cutt-off) 1X 2X 8.40 X 0.90 = 15.12 Sqm
Culvert ( D/S cutt-off) 1X 2X 8.40 X 0.90 = 15.12 Sqm
Abutment 2X 2X 3.80 X 0.75 = 11.40 Sqm
2X 2X 6.00 X 1.00 = 24.00 Sqm
Wing wall 4X 2X 2.00 X 1.15 = 18.40 Sqm
Parapet 2X 2X 3.00 X 0.45 = 5.40 Sqm
Total = 292.94 Sqm
@ Rs. 62.46 Per Sqm Rs 18297.67
ii) Slab 1X 1X 6.00 X 3.00 = 18.00 Sqm
@ Rs. 201.68 Per Sqm Rs 3630.23
7 12 mm CP in CM (1:6) to the Super structure
Guard wall 1X 2X 55.00 X 1.00 = 110.00 Sqm
Abutment 2X 1X 6.00 X 1.00 = 12.00 Sqm
Wing wall 4X 1X 2.00 X 1.15 = 9.20 Sqm
Parapet 2X 2X 3.00 X 0.45 = 5.40 Sqm
Total = 136.60 Sqm
@ Rs. 51.59 Per Sqm Rs 7047.14
8 PCC (1:2:4) using 12 mm size hbg chips including all complete.
Guard wall 1X 55.00 X 0.50 X 0.05 = 1.38 Cum
Pier Cap 2X 6.00 X 0.50 X 0.075 = 0.45 Cum
Bed 1X 6.00 X 2.00 X 0.075 = 0.90 Cum
Wing wall 4X 2.00 X 0.50 X 0.05 = 0.20 Cum
Parapet 2X 3.00 X 0.45 X 0.05 = 0.14 Cum
Total = 3.06 Cum
@ Rs. 3289.62 Per Cum Rs 10066.23
9 Provision for rest shed , medicenes for laboureres etc. Rs 2000.00
10 Provision for remuneration of Gram Sathi 750 mandays @ 4.00 Rs 3000.00
11 Provision for Work Sign board & Photograph Rs. 1500.00
Grand Total Rs. 353923.52
Limitted to Rs. 300000.00
(Rupees Three Lakhs Only)
Technically Sanctioned for Rs.3,00,000/-
(Rupees Three Lakhs Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM AMALABHATA TO KUSUMI WITH CD WORK".
Est.Cost:- Rs.5,00,000/-
1 Collecting , conveying,supplying of good quality hard metal
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 1035.00 X 3.00 X 0.10 = 310.50 Cum
@ Rs. 414.40 Per Cum Rs 128671.20
2 Collecting , conveying,supplying of good quality murrom or gravel
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road Sub base 1X 1035.00 X 3.00 X 0.15 = 465.75 Cum
Add for metal Consolidation 25% of metal Qty. = 77.63 Cum
Total = 543.38 Cum
@ Rs. 188.00 Per 100 Cum Rs 87561.00
3 Labour for laying sub-base in layers not exceeding
150 mm thick watering,compacting to the required density in OMC
with PRR but excluding cost & conveyance of Sub-base materials
Road 1X 1035.00 X 3.00 X 0.15 = 465.75 Cum
@ Rs. 98.65 Per Cum Rs 45946.00
4 Labour for spreading metal & packing the voids with small stones
& hand packing the same to proper camber including conveying , spreading
of filler material & filling the interstics by spreading the same over the surface
watering & consolidation with PRR including hire & running charges of PRR
but excluding the cost of metal & filler material.
Road 1X 1035.00 X 3.00 X 0.10 = 310.50 Cum
@ Rs. 210.41 Per Cum Rs 65331.79
7 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Road 1X 1035.00 X 1.00 X 0.30 = 310.50 Cum
Road 2X 1035.00 X 0.60 X 0.25 = 310.50 Cum
Total = 621.00 Cum
@ Rs. 102.00 Per 2.83 Cum Rs 22382.33
8 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Culvert ( U/S cutt-off) 1X 10.70 X 1.20 X 1.20 = 15.41 Cum
Culvert ( D/S cutt-off) 1X 10.70 X 1.20 X 1.50 = 19.26 Cum
Abutment 2X 3.80 X 1.20 X 1.20 = 10.94 Cum
Bed 1X 3.80 X 1.70 X 0.45 = 2.91 Cum
Total = 48.52 Cum
@ Rs. 5395.57 Per 100 Cum Rs 2617.88
9 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Culvert ( U/S cutt-off) 1X 10.70 X 1.20 X 0.15 = 1.93 Cum
Culvert ( D/S cutt-off) 1X 10.70 X 1.20 X 0.15 = 1.93 Cum
Abutment 2X 3.80 X 1.20 X 0.15 = 1.37 Cum
Bed 1X 3.80 X 1.70 X 0.15 = 0.97 Cum
Total = 6.19 Cum
@ Rs. 209.71 Per Cum Rs 1297.91
10 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Culvert ( U/S cutt-off) 1X 10.70 X 1.20 X 0.15 = 1.93 Cum
1X 10.70 X (1.00+0.75)/2 X 0.90 = 6.02 Cum
Culvert ( D/S cutt-off) 1X 10.70 X 1.20 X 0.15 = 1.93 Cum
1X 10.70 X (1.00+0.75)/2 X 0.90 = 6.02 Cum
Abutment 2X 3.80 X 1.20 X 0.30 = 2.74 Cum
2X 3.80 X (1.00+0.75)/2 X 0.75 = 4.99 Cum
2X 6.00 X (0.75+0.0.50)/2 X 1.70 = 12.75 Cum
Wing wall 4X 5.00 X (0.75+0.0.50)/2 X 1.70 = 21.25 Cum
Bed 1X 4.50 X 2.00 X 0.30 = 2.70 Cum
Parapet 2X 3.00 X 0.45 X 0.45 = 1.22 Cum
Total = 61.53 Cum
@ Rs. 2138.32 Per Cum Rs 131566.68
11 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Slab 1X 6.00 X 3.00 X 0.25 = 4.50 Cum
Total = 4.50 Cum
@ Rs. 3336.28 Per Cum Rs 15013.24
12 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 4.05 Qtl
@ Rs. 4125.86 Per Qtl Rs 16709.71
13 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Culvert ( U/S cutt-off) 1X 2X 10.70 X 0.90 = 19.26 Sqm
Culvert ( D/S cutt-off) 1X 2X 10.70 X 0.90 = 19.26 Sqm
Abutment 2X 2X 3.80 X 0.75 = 11.40 Sqm
2X 2X 6.00 X 1.70 = 40.80 Sqm
Wing wall 4X 2X 5.00 X 1.70 = 68.00 Sqm
Parapet 2X 2X 3.00 X 0.45 = 5.40 Sqm
Total = 164.12 Sqm
@ Rs. 62.46 Per Sqm Rs 10251.29
ii) Slab 1X 1X 6.00 X 3.00 = 18.00 Sqm
@ Rs. 201.68 Per Sqm Rs 3630.23
14 12 mm CP in CM (1:6) to the Super structure
Abutment 2X 1X 6.00 X 1.70 = 20.40 Sqm
Wing wall 4X 1X 5.00 X 1.70 = 34.00 Sqm
Parapet 2X 2X 3.00 X 0.45 = 5.40 Sqm
Total = 59.80 Sqm
@ Rs. 51.59 Per Sqm Rs 3085.06
15 PCC (1:2:4) using 12 mm size hbg chips including all complete.
Pier Cap 2X 6.00 X 0.50 X 0.075 = 0.45 Cum
Bed 1X 6.00 X 2.00 X 0.075 = 0.90 Cum
Wing wall 4X 5.00 X 0.50 X 0.05 = 0.50 Cum
Parapet 2X 3.00 X 0.45 X 0.05 = 0.14 Cum
Total = 1.99 Cum
@ Rs. 3289.62 Per Cum Rs 6529.89
16 Provision for rest shed , medicenes for laboureres etc. Rs 3000.00
17 Provision for remuneration of Gram Sathi 1000 mandays @ 4.00 Rs 4000.00
18 Provision for Work Sign board & Photograph Rs. 2000.00
Grand Total Rs. 549594.22
Limitted to Rs. 500000.00
(Rupees Five Lakhs Only)
Technically Sanctioned for Rs.5,00,000/-
(Rupees Five Lakhs Only)
Junior Engineer
Tentulikhunti
Asst. Engineer
Tentulikhunti
Administratively approved for Rs.5,00,000/-
(Rupees Five Lakhs Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur
Administratively approved for Rs.5,00,000/-
(Rupees Five Lakhs Only)
DETAILED ESTIMATE FOR THE WORK:-"METALLING & MURROM WITH CD WORK FROM RD ROAD TO
SAGARMUNDA".
Est.Cost:- Rs.3,00,000/-
1 Collecting , conveying,supplying of good quality hard metal
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 257.00 X 3.00 X 0.10 = 77.10 Cum
@ Rs. 414.40 Per Cum Rs 31950.24
2 Collecting , conveying,supplying of good quality murrom or gravel
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road Sub base 1X 257.00 X 3.00 X 0.15 = 115.65 Cum
Add for metal Consolidation 25% of metal Qty. = 19.28 Cum
Total = 134.93 Cum
@ Rs. 188.00 Per 100 Cum Rs 21742.20
3 Labour for laying sub-base in layers not exceeding
150 mm thick watering,compacting to the required density in OMC
with PRR but excluding cost & conveyance of Sub-base materials
Road 1X 257.00 X 3.00 X 0.15 = 115.65 Cum
@ Rs. 98.65 Per Cum Rs 11408.81
4 Labour for spreading metal & packing the voids with small stones
& hand packing the same to proper camber including conveying , spreading
of filler material & filling the interstics by spreading the same over the surface
watering & consolidation with PRR including hire & running charges of PRR
but excluding the cost of metal & filler material.
Road 1X 257.00 X 3.00 X 0.10 = 77.10 Cum
@ Rs. 210.41 Per Cum Rs 16222.48
5 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Road 2X 257.00 X 0.60 X 0.25 = 77.10 Cum
Total = 77.10 Cum
@ Rs. 102.00 Per 2.83 Cum Rs 2778.87
6 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Guard wall 1X 30.00 X 1.05 X 1.05 = 33.08 Cum
Culvert ( U/S cutt-off) 1 X 8.40 X 1.20 X 1.20 = 12.10 Cum
Culvert ( D/S cutt-off) 1 X 8.40 X 1.20 X 1.50 = 15.12 Cum
Abutment 2 X 3.80 X 1.20 X 1.20 = 10.94 Cum
Bed 1 X 3.80 X 1.70 X 0.45 = 2.91 Cum
Total = 74.14 Cum
@ Rs. 5395.57 Per 100 Cum Rs 4000.38
7 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Guard wall 1X 30.00 X 1.05 X 0.05 = 1.58 Cum
Culvert ( U/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
Culvert ( D/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
Abutment 2X 3.80 X 1.20 X 0.15 = 1.37 Cum
Bed 1X 3.80 X 1.70 X 0.15 = 0.97 Cum
Total = 6.94 Cum
@ Rs. 209.71 Per Cum Rs 1454.56
8 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Guard wall 1X 30.00 X 1.05 X 0.15 = 4.73 Cum
1X 30.00 X (1.05+0.50)/2 X 1.85 = 43.01 Cum
Culvert ( U/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
1X 8.40 X (1.00+0.75)/2 X 0.90 = 4.73 Cum
Culvert ( D/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
1X 8.40 X (1.00+0.75)/2 X 0.90 = 4.73 Cum
Abutment 2X 3.80 X 1.20 X 0.30 = 2.74 Cum
2X 3.80 X (1.00+0.75)/2 X 0.75 = 4.99 Cum
2X 6.00 X (0.75+0.0.50)/2 X 1.15 = 8.63 Cum
Wing wall 4X 2.00 X (0.75+0.0.50)/2 X 1.15 = 5.75 Cum
Bed 1X 4.50 X 2.00 X 0.30 = 2.70 Cum
Parapet 2X 3.00 X 0.45 X 0.45 = 1.22 Cum
Total = 86.23 Cum
@ Rs. 2138.32 Per Cum Rs 184376.81
9 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Slab 1X 6.00 X 3.00 X 0.25 = 4.50 Cum
Total = 4.50 Cum
@ Rs. 3336.28 Per Cum Rs 15013.24
10 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 4.05 Qtl
@ Rs. 4125.86 Per Qtl Rs 16709.71
11 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Guard wall 1X 2X 30.00 X 1.85 = 111.00 Sqm
Culvert ( U/S cutt-off) 1X 2X 8.40 X 0.90 = 15.12 Sqm
Culvert ( D/S cutt-off) 1X 2X 8.40 X 0.90 = 15.12 Sqm
Abutment 2X 2X 3.80 X 0.75 = 11.40 Sqm
2X 2X 6.00 X 1.00 = 24.00 Sqm
Wing wall 4X 2X 2.00 X 1.15 = 18.40 Sqm
Parapet 2X 2X 3.00 X 0.45 = 5.40 Sqm
Total = 200.44 Sqm
@ Rs. 62.46 Per Sqm Rs 12519.92
ii) Slab 1X 1X 6.00 X 3.00 = 18.00 Sqm
@ Rs. 201.68 Per Sqm Rs 3630.23
12 12 mm CP in CM (1:6) to the Super structure
Guard wall 1X 2X 30.00 X 1.00 = 60.00 Sqm
Abutment 2X 1X 6.00 X 1.00 = 12.00 Sqm
Wing wall 4X 1X 2.00 X 1.15 = 9.20 Sqm
Parapet 2X 2X 3.00 X 0.45 = 5.40 Sqm
Total = 86.60 Sqm
@ Rs. 51.59 Per Sqm Rs 4467.66
13 PCC (1:2:4) using 12 mm size hbg chips including all complete.
Guard wall 1X 30.00 X 0.50 X 0.05 = 0.75 Cum
Pier Cap 2X 6.00 X 0.50 X 0.075 = 0.45 Cum
Bed 1X 6.00 X 2.00 X 0.075 = 0.90 Cum
Wing wall 4X 2.00 X 0.50 X 0.05 = 0.20 Cum
Parapet 2X 3.00 X 0.45 X 0.05 = 0.14 Cum
Total = 2.44 Cum
@ Rs. 3289.62 Per Cum Rs 8010.22
14 Provision for rest shed , medicenes for laboureres etc. Rs 3000.00
15 Provision for remuneration of Gram Sathi 1000 mandays @ 4.00 Rs 4000.00
16 Provision for Work Sign board & Photograph Rs. 1300.00
Grand Total Rs. 342585.36
Limitted to Rs. 300000.00
(Rupees Three Lakhs Only)
Technically Sanctioned for Rs.3,00,000/-
(Rupees Three Lakhs Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur
Administratively approved for Rs.3,00,000/-
(Rupees Three Lakhs Only)
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM SARANPUR MAJHIGUDA CHHAKA TO PALPUR."
Est.Cost:- Rs.5,00,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Guard wall 1X 119.00 X 1.05 X 1.05 = 131.20 Cum
Total = 131.20 Cum
@ Rs. 5395.57 Per 100 Cum Rs 7078.86
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Guard wall 1X 119.00 X 1.05 X 0.05 = 6.25 Cum
Total = 6.25 Cum
@ Rs. 209.71 Per Cum Rs 1310.18
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Guard wall 1X 119.00 X 1.05 X 0.15 = 18.74 Cum
1X 119.00 X (1.05+0.50)/2 X 1.85 = 170.62 Cum
Total = 189.36 Cum
@ Rs. 2138.32 Per Cum Rs 404909.98
4 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Guard wall 1X 2X 119.00 X 1.85 = 440.30 Sqm
Total = 440.30 Sqm
@ Rs. 62.46 Per Sqm Rs 27502.10
5 12 mm CP in CM (1:6) to the Super structure
Guard wall 1X 119.00 X 0.50 X 0.05 = 2.98 Cum
Total = 2.98 Sqm
@ Rs. 51.59 Per Sqm Rs 153.48
6 PCC (1:2:4) using 12 mm size hbg chips including all complete.
Guard wall 1X 119.00 X 0.50 X 0.05 = 2.98 Cum
Total = 2.98 Cum
@ Rs. 3289.62 Per Cum Rs 9786.62
7 Providing , laying, spreading & compacting stone aggregates
of specific sizes to WBM specification including spreading uniform
thickness,hand packing,rolling with 3-wheeled steel rollers
8-10 tonnes in stages to proper grade & camber applying & brooming requisites
type of coarse aggregates,watering & compacting to the required density as per clause
404 of MoSRT&H specification for road & bridge works.
Road Gr-II 1X 500.00 X 3.00 X 0.075 = 112.50 Cum
@ Rs. 1110.23 Per Cum Rs 124900.50
8 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Road 2X 500.00 X 1.00 X 0.23 = 230.00 Cum
Total = 230.00 Cum
@ Rs. 102.00 Per 2.83 Cum Rs 8289.75
9 Provision for rest shed , medicenes for laboureres etc. Rs 2000.00
10 Provision for remuneration of Gram Sathi 750 mandays @ 4.00 Rs 3000.00
11 Provision for Work Sign board & Photograph Rs. 1300.00
Grand Total Rs. 590231.46
Limitted to Rs. 500000.00
(Rupees Five Lakhs Only)
Technically Sanctioned for Rs.5,00,000/-
(Rupees Five Lakhs Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur
Administratively approved for Rs.5,00,000/-
(Rupees Five Lakhs Only)
DETAILED ESTIMATE FOR THE WORK:-"METALLING OF ROAD FROM MAJHIGUDA TO RD ROAD ".
Est.Cost:- Rs.3,00,000/-
1 Collecting , conveying,supplying of good quality hard metal
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 257.00 X 3.00 X 0.10 = 77.10 Cum
@ Rs. 414.40 Per Cum Rs 31950.24
2 Collecting , conveying,supplying of good quality murrom or gravel
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road Sub base 1X 257.00 X 3.00 X 0.15 = 115.65 Cum
Add for metal Consolidation 25% of metal Qty. = 19.28 Cum
Total = 134.93 Cum
@ Rs. 188.00 Per Cum Rs 21742.20
3 Labour for laying sub-base in layers not exceeding
150 mm thick watering,compacting to the required density in OMC
with PRR but excluding cost & conveyance of Sub-base materials
Road 1X 257.00 X 3.00 X 0.15 = 115.65 Cum
@ Rs. 98.65 Per Cum Rs 11408.81
4 Labour for spreading metal & packing the voids with small stones
& hand packing the same to proper camber including conveying , spreading
of filler material & filling the interstics by spreading the same over the surface
watering & consolidation with PRR including hire & running charges of PRR
but excluding the cost of metal & filler material.
Road 1X 257.00 X 3.00 X 0.10 = 77.10 Cum
@ Rs. 210.41 Per Cum Rs 16222.48
5 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Road 2X 257.00 X 0.60 X 0.25 = 77.10 Cum
Total = 77.10 Cum
@ Rs. 102.00 Per 2.83 Cum Rs 2778.87
6 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Guard wall 1X 30.00 X 1.05 X 1.05 = 33.08 Cum
Culvert ( U/S cutt-off) 1X 8.40 X 1.20 X 1.20 = 12.10 Cum
Culvert ( D/S cutt-off) 1X 8.40 X 1.20 X 1.50 = 15.12 Cum
Abutment 2X 3.80 X 1.20 X 1.20 = 10.94 Cum
Bed 1X 3.80 X 1.70 X 0.45 = 2.91 Cum
Total = 74.14 Cum
@ Rs. 5395.57 Per 100 Cum Rs 4000.38
7 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Guard wall 1X 30.00 X 1.05 X 0.05 = 1.58 Cum
Culvert ( U/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
Culvert ( D/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
Abutment 2X 3.80 X 1.20 X 0.15 = 1.37 Cum
Bed 1X 3.80 X 1.70 X 0.15 = 0.97 Cum
Total = 6.94 Cum
@ Rs. 209.71 Per Cum Rs 1454.56
8 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Guard wall 1X 30.00 X 1.05 X 0.15 = 4.73 Cum
1X 30.00 X (1.05+0.50)/2 X 1.85 = 43.01 Cum
Culvert ( U/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
1X 8.40 X (1.00+0.75)/2 X 0.90 = 4.73 Cum
Culvert ( D/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
1X 8.40 X (1.00+0.75)/2 X 0.90 = 4.73 Cum
Abutment 2X 3.80 X 1.20 X 0.30 = 2.74 Cum
2X 3.80 X (1.00+0.75)/2 X 0.75 = 4.99 Cum
2X 6.00 X (0.75+0.0.50)/2 X 1.15 = 8.63 Cum
Wing wall 4X 2.00 X (0.75+0.0.50)/2 X 1.15 = 5.75 Cum
Bed 1X 4.50 X 2.00 X 0.30 = 2.70 Cum
Parapet 2X 3.00 X 0.45 X 0.45 = 1.22 Cum
Total = 86.23 Cum
@ Rs. 2138.32 Per Cum Rs 184376.81
9 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Slab 1X 6.00 X 3.00 X 0.25 = 4.50 Cum
Total = 4.50 Cum
@ Rs. 3336.28 Per Cum Rs 15013.24
10 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 4.05 Qtl
@ Rs. 4125.86 Per Qtl Rs 16709.71
11 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Guard wall 1X 2X 30.00 X 1.85 = 111.00 Sqm
Culvert ( U/S cutt-off) 1X 2X 8.40 X 0.90 = 15.12 Sqm
Culvert ( D/S cutt-off) 1X 2X 8.40 X 0.90 = 15.12 Sqm
Abutment 2X 2X 3.80 X 0.75 = 11.40 Sqm
2X 2X 6.00 X 1.00 = 24.00 Sqm
Wing wall 4X 2X 2.00 X 1.15 = 18.40 Sqm
Parapet 2X 2X 3.00 X 0.45 = 5.40 Sqm
Total = 200.44 Sqm
@ Rs. 62.46 Per Sqm Rs 12519.92
ii) Slab 1X 1X 6.00 X 3.00 = 18.00 Sqm
@ Rs. 201.68 Per Sqm Rs 3630.23
12 12 mm CP in CM (1:6) to the Super structure
Guard wall 1X 2X 30.00 X 1.00 = 60.00 Sqm
Abutment 2X 1X 6.00 X 1.00 = 12.00 Sqm
Wing wall 4X 1X 2.00 X 1.15 = 9.20 Sqm
Parapet 2X 2X 3.00 X 0.45 = 5.40 Sqm
Total = 86.60 Sqm
@ Rs. 51.59 Per Sqm Rs 4467.66
13 PCC (1:2:4) using 12 mm size hbg chips including all complete.
Guard wall 1X 30.00 X 0.50 X 0.05 = 0.75 Cum
Pier Cap 2X 6.00 X 0.50 X 0.075 = 0.45 Cum
Bed 1X 6.00 X 2.00 X 0.075 = 0.90 Cum
Wing wall 4X 2.00 X 0.50 X 0.05 = 0.20 Cum
Parapet 2X 3.00 X 0.45 X 0.05 = 0.14 Cum
Total = 2.44 Cum
@ Rs. 3289.62 Per Cum Rs 8010.22
14 Provision for rest shed , medicenes for laboureres etc. Rs 3000.00
15 Provision for remuneration of Gram Sathi 1000 mandays @ 4.00 Rs 4000.00
16 Provision for Work Sign board & Photograph Rs. 1300.00
Grand Total Rs. 342585.36
Limitted to Rs. 300000.00
(Rupees Three Lakhs Only)
Technically Sanctioned for Rs.3,00,000/-
(Rupees Three Lakhs Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM PILLIKA TO DEULA VIA DONGRIGUDA WITH
GUARD WALL BOTH SIDE OF ROAD."
Est.Cost:- Rs.10,00,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Guard wall 1X 308.40 X 1.05 X 1.05 = 340.01 Cum
@ Rs. 5890.32 Per 100 Cum Rs 20027.72
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Guard wall 1X 308.40 X 1.05 X 0.05 = 16.19 Cum
@ Rs. 206.86 Per Cum Rs 3349.21
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Guard wall 1X 308.40 X 1.05 X 0.15 = 48.57 Cum
1X 308.40 X (1.05+0.50)/2 X 1.85 = 442.17 Cum
Total = 490.74 Cum
@ Rs. 2043.85 Per Cum Rs 1003003.00
4 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Guard wall 1X 2X 308.40 X 1.85 = 1141.08 Sqm
@ Rs. 62.46 Per Sqm Rs 71274.35
5 12 mm CP in CM (1:6) to the Super structure
Guard wall 1X 308.40 X 1.00 = 308.40 Cum
@ Rs. 45.15 Per Sqm Rs 13924.14
6 PCC (1:2:4) using 12 mm size hbg chips including all complete.
Guard wall 1X 308.40 X 0.50 X 0.05 = 7.71 Cum
@ Rs. 3164.28 Per Cum Rs 24396.58
7 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Road 1X 308.40 X 1.00 X 1.00 = 308.40 Cum
@ Rs. 102.00 Per 2.83 Cum Rs 11115.48
8 Provision for rest shed , medicenes for laboureres etc. Rs 2000.00
9 Provision for remuneration of Gram Sathi 1500 mandays @ 4.00 Rs 6000.00
10 Provision for Work Sign board & Photograph Rs. 1500.00
Grand Total Rs. 1156590.46
Limitted to Rs. 1000000.00
(Rupees Ten Lakhs Only)
Technically Sanctioned for Rs.10,00,000/-
(Rupees Ten Lakhs Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur
Administratively approved for Rs.10,00,000/-
(Rupees Ten Lakhs Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur
Administratively approved for Rs.2,50,000/-
(Rupees Two Lakhs & Fifty thousand Only)
Block Dev. Officer
Nabarangpur
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM NH ROAD TARAGAM TO BAGH-SEUNI CHHAK VIA
GUMAGUDA-SANKUMULI."
Est.Cost:- Rs.10,00,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Guard wall 1X 304.30 X 1.05 X 1.05 = 335.49 Cum
@ Rs. 5395.57 Per 100 Cum Rs 18101.64
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Guard wall 1X 304.30 X 1.05 X 0.05 = 15.98 Cum
@ Rs. 209.71 Per Cum Rs 3350.31
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Guard wall 1X 304.30 X 1.05 X 0.15 = 47.93 Cum
1X 304.30 X (1.05+0.50)/2 X 1.85 = 436.29 Cum
Total = 484.22 Cum
@ Rs. 2138.32 Per Cum Rs 1035412.67
4 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Guard wall 1X 2X 304.30 X 1.85 = 1125.91 Sqm
@ Rs. 62.46 Per Sqm Rs 70326.79
5 12 mm CP in CM (1:6) to the Super structure
Guard wall 1X 304.30 X 1.00 = 304.30 Cum
@ Rs. 51.59 Per Sqm Rs 15698.72
6 PCC (1:2:4) using 12 mm size hbg chips including all complete.
Guard wall 1X 304.30 X 0.50 X 0.05 = 7.61 Cum
@ Rs. 3289.62 Per Cum Rs 25025.78
7 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Road 1X 304.30 X 1.00 X 1.00 = 304.30 Cum
@ Rs. 141.62 Per 2.83 Cum Rs 15227.90
8 Provision for rest shed , medicenes for laboureres etc. Rs 5000.00
9 Provision for remuneration of Gram Sathi 300 mandays @ 4.00 Rs 1200.00
10 Provision for Work Sign board & Photograph Rs. 2000.00
Grand Total Rs. 1191343.81
Limitted to Rs. 1000000.00
(Rupees Ten Lakhs Only)
Technically Sanctioned for Rs.10,00,000/-
(Rupees Ten Lakhs Only)
Junior Engineer
Nabarangpur Block
Asst. Engineer
Nabarangpur
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM PILLIKA BHATRA SAHI TO MASANI GHAT."
Est.Cost:- Rs.1,00,000/-
1 Collecting,Conveying supplying of good quality soling stone & stacking
on the road side with box heap of size (1.50X1.50X0.50) mtr to be
measured (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 350.00 X 3.00 X 0.15 = 157.50 Cum
@ Rs. 302.40 Per Cum Rs 47628.00
2 Collecting,Conveying supplying of good quality murrom or gravel & stacking
on the road side with box heap of size (1.50X1.50X0.50) mtr to be
measured (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 350.00 X 3.00 X 0.10 = 105.00 Cum
For Filling interstics of soling road taking 12.50% of soling quantity = 19.69 Cum
Total = 124.69 Cum
@ Rs. 188.00 Per Cum Rs 23441.25
3 Labour for spreading muroom or gravel including watering but excluding cost
& conveyance of Muroom
Total Qty = 124.69 Cum
@ Rs. 37.04 Per Cum Rs 4618.97
4 labour for Soling road surface with soling stone including filling
the interstics with earth & rolling with HRR excluding cost &
conveyance of soling stone.
Road 1X 350.00 X 3.00 X 0.15 = 157.50 Cum
@ Rs. 132.33 Per Cum Rs 20841.36
5 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Road 2X 350.00 X 0.60 X 0.30 = 126.00 Cum
@ Rs. 141.62 Per 2.83 Cum Rs 6305.34
6 Provision for rest shed , medicenes for laboureres etc. Rs 1000.00
7 Provision for remuneration of Gram Sathi 350 mandays @ 4.00 Rs 1400.00
8 Provision for Work Sign board & Photograph Rs. 1500.00
Grand Total Rs. 106734.92
Limitted to Rs. 100000.00
(Rupees One Lakh Only)
Technically Sanctioned for Rs.1,00,000/-
(Rupees One Lakh Only)
Sarapanch
Taragam GP
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM PILLIKA RD ROAD TO NADIGHAT."
Est.Cost:- Rs.1,00,000/-
1 Collecting,Conveying supplying of good quality soling stone & stacking
on the road side with box heap of size (1.50X1.50X0.50) mtr to be
measured (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 350.00 X 3.00 X 0.15 = 157.50 Cum
@ Rs. 302.40 Per Cum Rs 47628.00
2 Collecting,Conveying supplying of good quality murrom or gravel & stacking
on the road side with box heap of size (1.50X1.50X0.50) mtr to be
measured (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 350.00 X 3.00 X 0.10 = 105.00 Cum
For Filling interstics of soling road taking 12.50% of soling quantity = 19.69 Cum
Total = 124.69 Cum
@ Rs. 188.00 Per Cum Rs 23441.25
3 Labour for spreading muroom or gravel including watering but excluding cost
& conveyance of Muroom
Total Qty = 124.69 Cum
@ Rs. 37.04 Per Cum Rs 4618.97
4 labour for Soling road surface with soling stone including filling
the interstics with murrom or gravel & rolling with HRR excluding cost &
conveyance of soling stone.
Road 1X 350.00 X 3.00 X 0.15 = 157.50 Cum
@ Rs. 132.33 Per Cum Rs 20841.36
5 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Road 2X 350.00 X 0.60 X 0.30 = 126.00 Cum
@ Rs. 141.62 Per 2.83 Cum Rs 6305.34
6 Provision for rest shed , medicenes for laboureres etc. Rs 1000.00
7 Provision for remuneration of Gram Sathi 350 mandays @ 4.00 Rs 1400.00
8 Provision for Work Sign board & Photograph Rs. 1500.00
Grand Total Rs. 106734.92
Limitted to Rs. 100000.00
(Rupees One Lakh Only)
Technically Sanctioned for Rs.1,00,000/-
(Rupees One Lakh Only)
Sarapanch
Taragam GP
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM RD ROAD TO RATHAMAJHIGUDA WITH CD WORK."
Est.Cost:- Rs.284944/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Guard wall 1X 39.36 X 1.05 X 1.05 = 43.39 Cum
Culvert ( U/S cutt-off) 1X 9.40 X 1.20 X 1.20 = 13.54 Cum
Culvert ( D/S cutt-off) 1X 9.40 X 1.20 X 1.50 = 16.92 Cum
Abutment 2X 3.80 X 1.20 X 1.20 = 10.94 Cum
Bed 1X 3.80 X 2.70 X 0.45 = 4.62 Cum
Total = 89.41 Cum
@ Rs. 5395.57 Per 100 Cum Rs 4824.26
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Guard wall 1X 39.36 X 1.05 X 0.05 = 2.07 Cum
Culvert ( U/S cutt-off) 1X 9.40 X 1.20 X 0.15 = 1.69 Cum
Culvert ( D/S cutt-off) 1X 9.40 X 1.20 X 0.15 = 1.69 Cum
Abutment 2X 3.80 X 1.20 X 0.15 = 1.37 Cum
Bed 1X 3.80 X 2.70 X 0.15 = 1.54 Cum
Total = 8.36 Cum
@ Rs. 209.71 Per Cum Rs 1752.65
3 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Guard wall 1X 39.36 X 1.05 X 0.15 = 6.20 Cum
1X 39.36 X (1.05+0.50)/2 X 1.85 = 56.43 Cum
Culvert ( U/S cutt-off) 1X 9.40 X 1.20 X 0.15 = 1.69 Cum
1X 9.40 X (1.00+0.75)/2 X 0.90 = 5.29 Cum
Culvert ( D/S cutt-off) 1X 9.40 X 1.20 X 0.15 = 1.69 Cum
1X 9.40 X (1.00+0.75)/2 X 0.90 = 5.29 Cum
Abutment 2X 3.80 X 1.20 X 0.30 = 2.74 Cum
2X 3.80 X (1.00+0.75)/2 X 0.75 = 4.99 Cum
2X 6.00 X (0.75+0.0.50)/2 X 1.50 = 11.25 Cum
Wing wall 4X 2.00 X (0.75+0.0.50)/2 X 1.50 = 7.50 Cum
Bed 1X 4.50 X 3.00 X 0.30 = 4.05 Cum
Parapet 2X 4.00 X 0.45 X 0.45 = 1.62 Cum
Total = 108.73 Cum
@ Rs. 2138.32 Per Cum Rs 232508.52
4 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Pier Cap 2X 6.00 X 0.50 X 0.15 = 0.90 Cum
Slab 1X 6.00 X 4.00 X 0.25 = 6.00 Cum
Total = 6.90 Cum
@ Rs. 3336.28 Per Cum Rs 23020.31
5 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 6.21 Qtl
@ Rs. 4125.86 Per Qtl Rs 25621.56
6 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Guard wall 1X 2X 39.36 X 1.85 = 145.63 Sqm
Culvert ( U/S cutt-off) 1X 2X 9.40 X 0.90 = 16.92 Sqm
Culvert ( D/S cutt-off) 1X 2X 9.40 X 0.90 = 16.92 Sqm
Abutment 2X 2X 3.80 X 0.75 = 11.40 Sqm
2X 2X 6.00 X 1.50 = 36.00 Sqm
Wing wall 4X 2X 2.00 X 1.50 = 24.00 Sqm
Parapet 2X 2X 4.00 X 0.45 = 7.20 Sqm
Total = 258.07 Sqm
@ Rs. 62.46 Per Sqm Rs 16119.74
ii) Slab 1X 1X 6.00 X 4.00 = 24.00 Sqm
@ Rs. 201.68 Per Sqm Rs 4840.31
7 12 mm CP in CM (1:6) to the Super structure
Guard wall 1X 2X 39.36 X 1.00 = 78.72 Sqm
Abutment 2X 1X 6.00 X 1.50 = 18.00 Sqm
Wing wall 4X 1X 2.00 X 1.50 = 12.00 Sqm
Parapet 2X 2X 3.00 X 0.45 = 5.40 Sqm
Total = 114.12 Sqm
@ Rs. 51.59 Per Sqm Rs 5887.41
8 PCC (1:2:4) using 12 mm size hbg chips including all complete.
Guard wall 1X 39.36 X 0.50 X 0.05 = 0.98
Cum
Bed 1X 6.00 X 3.00 X 0.075 = 1.35
Cum
Wing wall 4X 2.00 X 0.50 X 0.05 = 0.20
Cum
Parapet 2X 4.00 X 0.45 X 0.05 = 0.18
Cum
Total = 2.71
Cum
@ Rs. 3289.62 Per Cum Rs 8928.03
9 Provision for rest shed , medicenes for laboureres etc. Rs 2000.00
10 Provision for remuneration of Gram Sathi 700 mandays @ 4.00 Rs 2800.00
11 Provision for Work Sign board & Photograph Rs. 2000.00
Grand Total Rs. 330302.77
Limitted to Rs. 284944.00
(Rupees Two Lakh Eighty four thousand & Nine hundred forty four Only)
Sarapanch
Agnipur GP
DETAILED ESTIMATE FOR THE WORK:-"IMPV, OF ROAD FROM MAHULPADAR PMGSY TO THAKURANI
MANDIR".
Est.Cost:- Rs.1,84,000/-
1 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Road 1X 360.00 X 6.00 X 0.75 = 1620.00 Cum
Total = 1620.00 Cum
@ Rs. 141.62 Per 2.83 Cum Rs 81068.69
2 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Culvert ( U/S cutt-off) 1X 7.40 X 1.20 X 1.20 = 10.66 Cum
Culvert ( D/S cutt-off) 1X 7.40 X 1.20 X 1.50 = 13.32 Cum
Abutment 2X 3.80 X 1.20 X 1.20 = 10.94 Cum
Bed 1X 3.80 X 0.70 X 0.45 = 1.20 Cum
Total = 36.12 Cum
@ Rs. 5395.57 Per 100 Cum Rs 1948.72
3 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Culvert ( U/S cutt-off) 1X 7.40 X 1.20 X 0.15 = 1.33 Cum
Culvert ( D/S cutt-off) 1X 7.40 X 1.20 X 0.15 = 1.33 Cum
Abutment 2X 3.80 X 1.20 X 0.15 = 1.37 Cum
Bed 1X 3.80 X 0.70 X 0.15 = 0.40 Cum
Total = 4.43 Cum
@ Rs. 209.71 Per Cum Rs 929.23
4 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Culvert ( U/S cutt-off) 1X 7.40 X 1.20 X 0.15 = 1.33 Cum
1X 7.40 X (1.00+0.75)/2 X 0.90 = 4.16 Cum
Culvert ( D/S cutt-off) 1X 7.40 X 1.20 X 0.15 = 1.33 Cum
1X 7.40 X (1.00+0.75)/2 X 0.90 = 4.16 Cum
Abutment 2X 3.80 X 1.20 X 0.30 = 2.74 Cum
2X 3.80 X (1.00+0.75)/2 X 0.75 = 4.99 Cum
2X 6.00 X (0.75+0.0.50)/2 X 1.15 = 8.63 Cum
Wing wall 4X 2.00 X (0.75+0.0.50)/2 X 1.15 = 5.75 Cum
Bed 1X 4.50 X 1.00 X 0.30 = 1.35 Cum
Parapet 2X 2.00 X 0.45 X 0.45 = 0.81 Cum
Total = 35.25 Cum
@ Rs. 2138.32 Per Cum Rs 75370.50
5 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Slab 1X 6.00 X 2.00 X 0.25 = 3.00 Cum
Total = 3.00 Cum
@ Rs. 2730.22 Per Cum Rs 8190.66
6 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 2.70 Qtl
@ Rs. 5033.35 Per Qtl Rs 13590.03
7 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Culvert ( U/S cutt-off) 1X 2X 7.40 X 0.90 = 13.32 Sqm
Culvert ( D/S cutt-off) 1X 2X 7.40 X 0.90 = 13.32 Sqm
Abutment 2X 2X 3.80 X 0.75 = 11.40 Sqm
2X 2X 6.00 X 1.00 = 24.00 Sqm
Wing wall 4X 2X 2.00 X 1.15 = 18.40 Sqm
Parapet 2X 2X 2.00 X 0.45 = 3.60 Sqm
Total = 84.04 Sqm
@ Rs. 59.67 Per Sqm Rs 5014.60
ii) Slab 1X 1X 6.00 X 2.00 = 12.00 Sqm
@ Rs. 184.57 Per Sqm Rs 2214.88
8 12 mm CP in CM (1:6) to the Super structure
Abutment 2X 1X 6.00 X 1.00 = 12.00 Sqm
Wing wall 4X 1X 2.00 X 1.15 = 9.20 Sqm
Parapet 2X 2X 2.00 X 0.45 = 3.60 Sqm
Total = 24.80 Sqm
@ Rs. 40.81 Per Sqm Rs 1012.10
9 PCC (1:2:4) using 12 mm size hbg chips including all complete.
Pier Cap 2X 6.00 X 0.50 X 0.075 = 0.45 Cum
Bed 1X 6.00 X 1.00 X 0.075 = 0.45 Cum
Wing wall 4X 2.00 X 0.50 X 0.05 = 0.20 Cum
Parapet 2X 2.00 X 0.45 X 0.05 = 0.09 Cum
Total = 1.19 Cum
@ Rs. 2632.28 Per Cum Rs 3132.41
10 Provision for rest shed , medicenes for laboureres etc. Rs 1500.00
11 Provision for remuneration of Gram Sathi 500 mandays @ 4.00 Rs 2000.00
12 Provision for Work Sign board & Photograph Rs. 2000.00
Grand Total Rs. 184169.72
Limitted to Rs. 184000.00
(Rupees One Lakh & Eighty four thousand Only)
Sarapanch
Sanmasigam GP
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM SEUNI DURKAGUDA TO BADAMASIGAM RD
ROAD ".
Est.Cost:- Rs.3,00,000/-
1 Collecting , conveying,supplying of good quality hard metal
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 910.00 X 3.00 X 0.10 = 273.00 Cum
@ Rs. 405.20 Per Cum Rs 110619.60
2 Collecting , conveying,supplying of good quality murrom or gravel
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road Sub base 1X 910.00 X 3.00 X 0.15 = 409.50 Cum
Add for metal Consolidation 25% of metal Qty. = 68.25 Cum
Total = 477.75 Cum
@ Rs. 186.40 Per Cum Rs 89052.60
3 Labour for laying sub-base in layers not exceeding
150 mm thick watering,compacting to the required density in OMC
with PRR but excluding cost & conveyance of Sub-base materials
Road 1X 910.00 X 3.00 X 0.15 = 409.50 Cum
@ Rs. 78.09 Per Cum Rs 31978.23
4 Labour for spreading metal & packing the voids with small stones
& hand packing the same to proper camber including conveying , spreading
of filler material & filling the interstics by spreading the same over the surface
watering & consolidation with PRR including hire & running charges of PRR
but excluding the cost of metal & filler material.
Road 1X 910.00 X 3.00 X 0.10 = 273.00 Cum
@ Rs. 177.47 Per Cum Rs 48448.10
5 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Road 2X 910.00 X 0.60 X 0.25 = 273.00 Cum
Total = 273.00 Cum
@ Rs. 141.62 Per 2.83 Cum Rs 13661.58
6 Provision for rest shed , medicenes for laboureres etc. Rs 1500.00
7 Provision for remuneration of Gram Sathi 750 mandays @ 4.00 Rs 3000.00
8 Provision for Work Sign board & Photograph Rs. 2000.00
Grand Total Rs. 300260.11
Limitted to Rs. 300000.00
(Rupees Three Lakhs Only)
Sarapanch
Bhatraseuni GP
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM BADGAM TO CHIRMAPONDI ".
Est.Cost:- Rs.2,00,000/-
1 Collecting , conveying,supplying of good quality hard metal
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 240.00 X 3.00 X 0.10 = 72.00 Cum
@ Rs. 405.20 Per Cum Rs 29174.40
2 Collecting , conveying,supplying of good quality murrom or gravel
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road Sub base 1X 240.00 X 3.00 X 0.15 = 108.00 Cum
Add for metal Consolidation 25% of metal Qty. = 18.00 Cum
Total = 126.00 Cum
@ Rs. 186.40 Per Cum Rs 23486.40
3 Labour for laying sub-base in layers not exceeding
150 mm thick watering,compacting to the required density in OMC
with PRR but excluding cost & conveyance of Sub-base materials
Road 1X 240.00 X 3.00 X 0.15 = 108.00 Cum
@ Rs. 78.09 Per Cum Rs 8433.82
4 Labour for spreading metal & packing the voids with small stones
& hand packing the same to proper camber including conveying , spreading
of filler material & filling the interstics by spreading the same over the surface
watering & consolidation with PRR including hire & running charges of PRR
but excluding the cost of metal & filler material.
Road 1X 240.00 X 3.00 X 0.10 = 72.00 Cum
@ Rs. 177.47 Per Cum Rs 12777.52
5 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Road 2X 240.00 X 0.60 X 0.25 = 72.00 Cum
Total = 72.00 Cum
@ Rs. 141.62 Per 2.83 Cum Rs 3603.05
6 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Culvert ( U/S cutt-off) 1 X 8.40 X 1.20 X 1.20 = 12.10 Cum
Culvert ( D/S cutt-off) 1 X 8.40 X 1.20 X 1.50 = 15.12 Cum
Abutment 2 X 3.80 X 1.20 X 1.20 = 10.94 Cum
Bed 1 X 3.80 X 1.70 X 0.45 = 2.91 Cum
Total = 41.07 Cum
@ Rs. 5890.32 Per 100 Cum Rs 2418.98
7 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Culvert ( U/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
Culvert ( D/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
Abutment 2X 3.80 X 1.20 X 0.15 = 1.37 Cum
Bed 1X 3.80 X 1.70 X 0.15 = 0.97 Cum
Total = 5.36 Cum
@ Rs. 201.10 Per Cum Rs 1078.11
8 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Culvert ( U/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
1X 8.40 X (1.00+0.75)/2 X 0.90 = 4.73 Cum
Culvert ( D/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
1X 8.40 X (1.00+0.75)/2 X 0.90 = 4.73 Cum
Abutment 2X 3.80 X 1.20 X 0.30 = 2.74 Cum
2X 3.80 X (1.00+0.75)/2 X 0.75 = 4.99 Cum
2X 6.00 X (0.75+0.0.50)/2 X 1.15 = 8.63 Cum
Wing wall 4X 2.00 X (0.75+0.0.50)/2 X 1.15 = 5.75 Cum
Bed 1X 4.50 X 2.00 X 0.30 = 2.70 Cum
Parapet 2X 3.00 X 0.45 X 0.45 = 1.22 Cum
Total = 38.49 Cum
@ Rs. 1742.76 Per Cum Rs 67074.38
9 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Slab 1X 6.00 X 3.00 X 0.25 = 4.50 Cum
Total = 4.50 Cum
@ Rs. 2730.22 Per Cum Rs 12286.00
10 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 4.05 Qtl
@ Rs. 5033.35 Per Qtl Rs 20385.05
11 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
Culvert ( U/S cutt-off) 1X 2X 8.40 X 0.90 = 15.12 Sqm
Culvert ( D/S cutt-off) 1X 2X 8.40 X 0.90 = 15.12 Sqm
Abutment 2X 2X 3.80 X 0.75 = 11.40 Sqm
2X 2X 6.00 X 1.00 = 24.00 Sqm
Wing wall 4X 2X 2.00 X 1.15 = 18.40 Sqm
Parapet 2X 2X 3.00 X 0.45 = 5.40 Sqm
Total = 89.44 Sqm
@ Rs. 59.67 Per Sqm Rs 5336.81
ii) Slab 1X 1X 6.00 X 3.00 = 18.00 Sqm
@ Rs. 184.57 Per Sqm Rs 3322.32
12 12 mm CP in CM (1:6) to the Super structure
Abutment 2X 1X 6.00 X 1.00 = 12.00 Sqm
Wing wall 4X 1X 2.00 X 1.15 = 9.20 Sqm
Parapet 2X 2X 3.00 X 0.45 = 5.40 Sqm
Total = 26.60 Sqm
@ Rs. 40.81 Per Sqm Rs 1085.56
13 PCC (1:2:4) using 12 mm size hbg chips including all complete.
Pier Cap 2X 6.00 X 0.50 X 0.075 = 0.45
Cum
Bed 1X 6.00 X 2.00 X 0.075 = 0.90
Cum
Wing wall 4X 2.00 X 0.50 X 0.05 = 0.20
Cum
Parapet 2X 3.00 X 0.45 X 0.05 = 0.14
Cum
Total = 1.69
Cum
@ Rs. 2632.28 Per Cum Rs 4435.39
14 Provision for rest shed , medicenes for laboureres etc. Rs 1500.00
15 Provision for remuneration of Gram Sathi 500 mandays @ 4.00 Rs 2000.00
16 Provision for Work Sign board & Photograph Rs. 2000.00
Grand Total Rs. 200397.79
Limitted to Rs. 200000.00
(Rupees Two Lakhs Only)
Technically Sanctioned for Rs.2,00,000/-
(Rupees Two Lakhs Only)
Asst. Engineer Block Dev. Officer Junior Engineer
Nabarangpur Nabarangpur Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM DONGRIGUDA BHAIRAVI MANDIR TO
TELIGUDA ".
Est.Cost:- Rs.2,00,000/-
1 Collecting , conveying,supplying of good quality hard metal
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 545.00 X 3.00 X 0.10 = 163.50 Cum
@ Rs. 405.20 Per Cum Rs 66250.20
2 Collecting , conveying,supplying of good quality murrom or gravel
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road Sub base 1X 545.00 X 3.00 X 0.15 = 245.25 Cum
Add for metal Consolidation 25% of metal Qty. = 32.70 Cum
Total = 277.95 Cum
@ Rs. 186.40 Per Cum Rs 51809.88
3 Labour for laying sub-base in layers not exceeding
150 mm thick watering,compacting to the required density in OMC
with PRR but excluding cost & conveyance of Sub-base materials
Road 1X 545.00 X 3.00 X 0.15 = 245.25 Cum
@ Rs. 78.09 Per Cum Rs 19151.80
4 Labour for spreading metal & packing the voids with small stones
& hand packing the same to proper camber including conveying , spreading
of filler material & filling the interstics by spreading the same over the surface
watering & consolidation with PRR including hire & running charges of PRR
but excluding the cost of metal & filler material.
Road 1X 545.00 X 3.00 X 0.10 = 163.50 Cum
@ Rs. 177.47 Per Cum Rs 29015.62
5 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Road 2X 545.00 X 0.60 X 0.25 = 163.50 Cum
Total = 163.50 Cum
@ Rs. 141.62 Per 2.83 Cum Rs 23154.87
6 CC (1:2:4) using 12 mm size hbg chips including all complete.
Slab of culvert 1X 5.80 X 1.20 X 0.125 = 0.87 Cum
@ Rs. 2632.28 Per Cum Rs 2290.08
7 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 0.78 Qtl
@ Rs. 5033.35 Per Qtl Rs 3941.11
8 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
ii) Slab 1X 1X 5.80 X 1.20 = 6.96 Sqm
@ Rs. 184.57 Per Sqm Rs 1284.63
9 Provision for remuneration of Gram Sathi 500 mandays @ 4.00 Rs 2000.00
10 Provision for Work Sign board & Photograph Rs. 1200.00
Grand Total Rs. 200098.19
Limitted to Rs. 200000.00
(Rupees Two Lakhs Only)
Technically Sanctioned for Rs.2,00,000/-
(Rupees Two Lakhs Only)
Sarapanch
Bikrampur GP
DETAILED ESTIMATE FOR THE WORK:- " CONST. OF COMMUNITY POND AT PATRAMUNDA ".
BLOCK DEV.OFFICER
NABARANGPUR BLOCK
DETAILED ESTIMATE FOR THE WORK:- " RENOVATION OF TANK AT MOHULPADAR ".
ESTIMATED COST :- Rs. 700000.00
1 E/W in ordinary soil with initial lead & lift including rough dressing
breaking the clods & deposited the soil on the embankment of the Tank as directed
by the EIC. 1st Footing
Tank 1X 76.40 X 76.40 X 0.60 = 3502.18 Cum
@ Rs 102.00 Per 2.83 Cum Rs 126226.84
2 E/W in hard soil with initial lead & lift including rough dressing
breaking the clods & deposited the soil on the embankment of the Tank as directed
by the EIC. 1st Footing
Tank 1X 74.40 X 74.40 X 0.60 = 3321.22 Cum
Tank 1X 72.40 X 72.40 X 0.30 = 1572.53 Cum
Total = 4893.74 Cum
@ Rs 137.70 Per 2.83 Cum Rs 238116.09
3 E/W in hard soil with one extra lift over initial lead & lift including rough dressing
breaking the clods & deposited the soil on the embankment of the Tank as directed
by the EIC. 2nd Footing
Tank 1X 72.40 X 72.40 X 0.30 = 1572.53 Cum
Tank 1X 70.40 X 70.40 X 0.60 = 2973.70 Cum
Tank 1X 68.40 X 68.40 X 0.60 = 2807.14 Cum
Total = 5780.83 Cum
@ Rs 145.82 Per 2.83 Cum Rs 297866.05
4 Fine dressing & turfing to the embankment of the tank with compact
dub grass including all cost,conveyance with all lead & lift
etc complete.
Embankment area 1X 4X 98.40 X 3.00 = 1180.80 Sqm
1X 4X 78.40 X 3.00 = 940.80 Sqm
Total = 2121.60 Sqm
@ Rs. 673.93 Per 100 Sqm Rs 7957.77
5 Remuneration of Gram Sathi
For 6000 Mandays
@ Rs. 4.00 Per Mandays Rs 24000.00
6 Provision for Labour rest shed,drinking water facility & medicene etc Rs 4000.00
7 Provision for work sign board with lettering,painting & Photograph Rs 2500.00
G.TOTAL Rs 700666.75
Limitted Rs 700000.00
ASST. ENGINEER
NABARANGPUR BLOCK
Administratively Approved for Rs.7,00,000/-
( Rupees Seven Lakhs Only)
BLOCK DEV.OFFICER
NABARANGPUR BLOCK
DETAILED ESTIMATE FOR THE WORK:- " CONST. OF CHECK - DAM AT CHHELIKANARI SINGARI JODI
NALLAH IN CHATTAHANDI GP ".
ESTIMATED COST :- Rs. 1000000.00
1 E/W in excavation in hard soil in Foundation with initial lead & lift
including rough dressing & breaking clods etc. complete.
U/S Cut-off 1X 17.00 X 1.00 X 1.50 = 25.50 Cum
D/S Cut-off 1X 17.00 X 1.00 X 2.10 = 35.70 Cum
Abutment 2X 12.00 X 1.20 X 1.50 = 43.20 Cum
Head Wall 1X 10.00 X 1.00 X 1.00 = 10.00 Cum
Bed 1X 10.00 X 7.00 X 0.45 = 31.50 Cum
Protection wall 1X 91.20 X 1.20 X 1.50 = 164.16 Cum
Total = 310.06 Cum
@ Rs 5395.57 Per 100 Cum Rs 16729.51
2 CC (1:4:8) using 40 mm size hbg metal including all complete.
U/S Cut-off 1X 17.00 X 1.00 X 0.15 = 2.55 Cum
1X 17.00 X (1.00+0.75)/2 X 1.35 = 20.08 Cum
D/S Cut-off 1X 17.00 X 1.00 X 0.15 = 2.55 Cum
1X 17.00 X (1.00+0.75)/2 X 1.95 = 29.01 Cum
Abutment 2X 12.00 X 1.20 X 0.15 = 4.32 Cum
1X 13.20 X (1.20+0.60)/2 X 3.30 = 39.20 Cum
Wing Wall 4X 3.00 X (0.75+0.60)/2 X 1.95 = 15.80 Cum
Head Wall 1X 10.00 X 1.00 X 1.00 = 10.00 Cum
4X 1.25 X (1.00+0.60)/2 X 1.50 = 6.00 Cum
Bed 1X 10.00 X 7.00 X 0.45 = 31.50 Cum
Protection wall 1X 91.20 X 1.20 X 0.15 = 16.42 Cum
1X 91.20 X (1.20+0.60)/2 X 2.85 = 233.93 Cum
Total = 411.35 Cum
@ Rs. 2138.32 Per Cum Rs 879599.82
3 12 mm Cp In CM (1:6) to the wall including all complete.
Abutment 2X 13.20 X 1.95 = 51.48 Sqm
Wing Wall 4X 3.00 X 1.95 = 23.40 Sqm
Head Wall 2X 1.20 X 1.50 = 3.60 Sqm
2X 1.00 X 1.50 = 3.00 Sqm
Protection wall 1X 91.20 X 1.50 = 136.80 Cum
Total = 218.28 Sqm
@ Rs. 51.59 Per Sqm Rs 11260.98
4 Rigid & smooth centering,shuttering for PCC & RCC work including
false work & dismanteling them after casting etc complete.
U/S Cut-off 2X 17.00 X 1.35 = 45.90 Sqm
D/S Cut-off 2X 17.00 X 2.10 = 71.40 Sqm
Abutment 4X 13.00 X 3.30 = 171.60 Sqm
Wing Wall 8X 3.00 X 1.95 = 46.80 Sqm
Head Wall 4X 1.25 X 1.50 = 7.50 Sqm
4X 1.00 X 1.50 = 6.00 Sqm
Protection wall 2X 91.20 X 2.85 = 519.84 Cum
Total = 869.04 Sqm
@ Rs. 62.46 Per Sqm Rs 54282.13
5 RCC of M-20 grade using 20 mm & down grade hard granite
Cbg Chips 12 mm size including all cost , conveyance
royality etc. complete.
Bed 1X 13.00 X 8.00 X 0.15 = 15.60 Cum
Total = 15.60 Cum
@ Rs. 3336.28 Per Cum Rs 52045.91
6 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Qty required 85% of RCC qty 13.26 Qtl
@ Rs. 4125.86 Per Qtl Rs 54708.84
BLOCK DEV.OFFICER
NABARANGPUR BLOCK
DETAILED ESTIMATE FOR THE WORK:- " COMPLETION. OF INCOMPLETE CHECK - DAM AT BAGDORI IN
BASINI GP ".
ESTIMATED COST :- Rs. 7,00,000/-
1 E/W in excavation in hard soil in Foundation with initial lead & lift
including rough dressing & breaking clods etc. complete.
D/S Cut-off 1X 26.50 X 1.00 X 1.50 = 39.75 Cum
Wing wall 4X 3.50 X 1.20 X 1.20 = 20.16 Cum
Bed (D/S Appron ) 1X 26.50 X 7.00 X 0.45 = 83.48 Cum
Protection wall 1X 40.00 X 1.20 X 1.20 = 57.60 Cum
Total = 200.99 Cum
@ Rs 5395.57 Per 100 Cum Rs 10844.29
2 CC (1:4:8) using 40 mm size hbg metal including all complete.
D/S Cut-off 1X 26.50 X 1.00 X 0.15 = 3.98 Cum
1X 26.50 X (1.00+0.60)/2 X 1.35 = 28.62 Cum
Wing Wall 4X 3.50 X 1.80 X 0.15 = 3.78 Cum
4X 3.50 X (1.20+0.60)/2 X 3.50 = 44.10 Cum
Bed 1X 26.50 X 7.00 X 0.45 = 83.48 Cum
Protection wall 1X 40.00 X 1.50 X 0.15 = 9.00 Cum
1X 40.00 X (1.20+0.60)/2 X 2.70 = 97.20 Cum
Total = 270.15 Cum
@ Rs. 2138.32 Per Cum Rs 577667.69
3 12 mm Cp In CM (1:6) to the wall including all complete.
Abutment 2X 15.00 X 4.00 = 120.00 Sqm
Wing Wall 8X 3.50 X 2.50 = 70.00 Sqm
Protection wall 1X 40.00 X 1.50 = 60.00 Cum
Total = 250.00 Sqm
@ Rs. 51.59 Per Sqm Rs 12897.41
4 Rigid & smooth centering,shuttering for PCC & RCC work including
false work & dismanteling them after casting etc complete.
D/S Cut-off 2X 26.50 X 1.50 = 79.50 Sqm
Wing Wall 8X 3.50 X 3.50 = 98.00 Sqm
Protection wall 2X 40.00 X 2.70 = 216.00 Cum
Total = 393.50 Sqm
@ Rs. 62.46 Per Sqm Rs 24578.87
5 CC (1:2:4) using 12 mm size hg chips including all cost
conveyance , royality etc complete.
Abutment 2X 15.00 X 0.75 X 0.05 = 1.13 Cum
Wing Wall 4X 3.50 X 0.60 X 0.05 = 0.42 Cum
Head Wall 1X 26.50 X 0.80 X 0.05 = 1.06 Cum
Bed 1X 26.50 X 22.00 X 0.062 = 36.15 Cum
Protection wall 1X 40.00 X 0.60 X 0.05 = 1.20 Cum
Total = 39.95 Cum
@ Rs. 3289.62 Per Cum Rs 131423.57
6 E/W in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Back Filling 2X 15.00 X 3.00 X 3.00 = 270.00 Cum
Over burden 2X 10.00 X 3.00 X 3.00 = 180.00 Cum
Total = 450.00 Cum
@ Rs 4511.05 Per 100 Cum Rs 20299.73
7 Remuneration of Gram Sathi For 505 Mandays
@ Rs. 4.00 Per Mandays Rs 2020.00
8 Cost of MS gate (1.00X1.50 ) mtr size with rubber bidding 06 Nos @ Rs.6000 per No Rs 36000.00
9 Cost of dewatering,cupper dam & unforseen item LS Rs 8000.00
10 Provision for Labour rest shed,drinking water facility & medicene etc Rs 3500.00
11 Provision for work sign board with lettering,painting & Photograph Rs 2500.00
G.TOTAL Rs 829731.55
Limitted Rs 700000.00
( Rupees Seven Lakhs Only)
ASST. ENGINEER
NABARANGPUR BLOCK
Administratively Approved for Rs.7,00,000/-
( Rupees Seven Lakhs Only)
BLOCK DEV.OFFICER
NABARANGPUR BLOCK
DETAILED WORK DONE ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM PILLIKA BHATRA SAHI TO
MASANI GHAT".
Est.Cost:- Rs.1,00,000/-
1 Collecting , conveying,supplying of good quality Soling stone
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 176.00 X 3.10 X 0.15 = 81.84 Cum
@ Rs. 297.68 Per Cum Rs 24362.13
2 Collecting , conveying,supplying of good quality murrom or gravel
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 176.00 X 3.10 X 0.15 = 81.84 Cum
Total = 81.84 Cum
@ Rs. 186.40 Per 100 Cum Rs 15254.98
3 Conveying from stacks & soling road surface with soling stone
with all cost etc complete.
Road 1X 176.00 X 3.10 X 0.15 = 81.84 Cum
@ Rs. 102.90 Per Cum Rs 8421.34
4 Labour for spreading murrom on the road surface
including all cost etc complete.
Road 1X 176.00 X 3.10 X 0.15 = 81.84 Cum
@ Rs. 28.81 Per Cum Rs 2357.81
5 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Culvert -1 1X 5.00 X 1.60 X 0.60 = 4.80 Cum
Culvert-2 1X 5.10 X 1.80 X 0.75 = 6.89 Cum
G.Wall 1X 3.00 X 0.75 X 0.75 = 1.69 Cum
Total = 13.37 Cum
@ Rs. 5890.32 Per 100 Cum Rs 787.68
6 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Culvert -1 1X 5.00 X 1.60 X 0.15 = 1.20 Cum
2X 5.00 X 0.40 X 0.60 = 2.40 Cum
Culvert-2 1X 5.10 X 1.80 X 0.15 = 1.38 Cum
2X 5.10 X 0.40 X 0.75 = 3.06 Cum
G.Wall 1X 3.00 X 0.75 X 0.15 = 0.34 Cum
1X 3.00 X (0.75+0.45)/2 X 1.20 = 2.16 Cum
Parapet 1X 5.90 X 3.30 X 0.10 = 1.95 Cum
Total = 12.48 Cum
@ Rs. 1742.76 Per Cum Rs 21752.26
7 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Slab-1 1X 5.00 X 1.60 X 0.15 = 1.20 Cum
Slab-2 1X 5.10 X 1.80 X 0.20 = 1.84 Cum
Total = 3.04 Cum
@ Rs. 2730.22 Per Cum Rs 8288.95
8 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 1.47 Qtl
@ Rs. 5033.35 Per Qtl Rs 7399.02
9 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Slab-1 1X 1X 5.00 X 1.60 = 8.00 Sqm
ii) Slab-2 1X 1X 5.10 X 1.80 = 9.18 Sqm
Total = 17.18 Sqm
@ Rs. 184.57 Per Sqm Rs 3170.91
10 12 mm CP in CM (1:6) to the Super structure
i) Slab-1 1X 2X 5.00 X 0.60 = 6.00 Sqm
ii) Slab-2 1X 2X 5.10 X 0.75 = 7.65 Sqm
Total = 13.65 Sqm
@ Rs. 40.81 Per Sqm Rs 557.06
11 PCC (1:2:4) using 12 mm size hbg chips including all complete.
road 1X 5.90 X 3.30 X 0.070 = 1.36 Cum
Bed of Slab 1X 5.00 X 0.80 X 0.050 = 0.20 Cum
Bed of Slab 1X 5.10 X 1.00 X 0.05 = 0.26 Cum
Total = 1.82 Cum
@ Rs. 2632.28 Per Cum Rs 4785.22
12 Provision for remuneration of Gram Sathi 260 mandays @ 4.00 Rs 1040.00
13 Provision for Work Sign board & Photograph Rs. 2000.00
Grand Total Rs. 100177.36
Limitted to Rs. 100000.00
(Rupees One Lakh Only)
Technically Sanctioned for Rs.1,00,000/-
(Rupees One Lakh Only)
Junior Engineer
Nabarangpur
Junior Engineer
Nabarangpur
Administratively approved for Rs.1,00,000/-
(Rupees One Lakh Only)
Sarapanch
Taragam GP
DETAILED WORK DONE ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM PILLIKA RD ROAD TO NADI
GHAT".
Est.Cost:- Rs.1,00,000/-
1 Collecting , conveying,supplying of good quality Soling stone
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 210.00 X 3.10 X 0.15 = 97.65 Cum
@ Rs. 297.68 Per Cum Rs 29068.45
2 Collecting , conveying,supplying of good quality murrom or gravel
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 210.00 X 3.10 X 0.15 = 97.65 Cum
@ Rs. 186.40 Per 100 Cum Rs 18201.96
3 Conveying from stacks & soling road surface with soling stone
with all cost etc complete.
Road 1X 210.00 X 3.10 X 0.15 = 97.65 Cum
@ Rs. 102.90 Per Cum Rs 10048.19
4 Labour for spreading murrom on the road surface
including all cost etc complete.
Road 1X 210.00 X 3.10 X 0.15 = 97.65 Cum
@ Rs. 28.81 Per Cum Rs 2813.30
5 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Cause way 2X 4.95 X 0.90 X 0.90 = 8.02 Cum
2X 2.85 X 0.90 X 0.90 = 4.62 Cum
Total = 12.64 Cum
@ Rs. 5890.32 Per 100 Cum Rs 744.30
6 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Cause way 2X 4.95 X 0.90 X 0.15 = 1.34 Cum
2X 4.85 X (0.90+0.45)/2 X 1.05 = 6.87 Cum
2X 2.85 X 0.90 X 0.15 = 0.77 Cum
2X 2.85 X (0.90+0.45)/2 X 1.35 = 5.19 Cum
Bed 1X 4.00 X 3.30 X 0.15 = 1.98 Cum
Total = 16.16 Cum
@ Rs. 1742.76 Per Cum Rs 28154.29
7 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Cause way wall 2X 2 X (1.35+0.75)/2 X 4.85 = 20.37 Sqm
2X 2X 2.85 X 1.35 = 15.39 Sqm
Total = 35.76 Sqm
@ Rs. 59.67 Per Sqm Rs 2133.80
8 PCC (1:2:4) using 12 mm size hbg chips including all complete.
Bed of Cause way 1X 4.85 X 4.20 X 0.070 = 1.43 Cum
@ Rs. 2632.28 Per Cum Rs 3753.37
9 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Road ( Berm) 2X 210.00 X 0.45 X 0.30 = 56.70 Cum
@ Rs. 141.62 Per 2.83 Cum Rs 2837.40
10 Provision for remuneration of Gram Sathi 300 mandays @ 4.00 Rs 1200.00
11 Provision for Work Sign board & Photograph Rs. 2000.00
Grand Total Rs. 100955.05
Limitted to Rs. 100000.00
(Rupees One Lakh Only)
Technically Sanctioned for Rs.1,00,000/-
(Rupees One Lakh Only)
Junior Engineer
Nabarangpur
Junior Engineer
Nabarangpur
Administratively approved for Rs.1,00,000/-
(Rupees One Lakh Only)
Sarapanch
Taragam GP
DETAILED REVISED ESTIMATE FOR THE WORK:- " RENOVATION OF RANDHARI TANK AT SIRISI ".
ASST. ENGINEER
NABARANGPUR BLOCK
DETAILED ESTIMATE FOR THE WORK:- " CONST. OF CROSS BANDH AT ".
1 E/W in hard soil with initial lead & lift including rough dressing breaking the clods
& deposited the soil on the embankment of the Cross bandh as directed
by the EIC.
Tank 1X 32.00 X (15.00+5.00)/2 X 1.20 = 384.00 Cum
@ Rs 137.70 Per 2.83 Cum Rs 18684.38
2 Remuneration of Gram Sathi
For 327 Mandays
@ Rs. 4.00 Per Mandays Rs 1308.00
3 Provision for work Photography Rs 400.00
G.TOTAL Rs 20392.38
Limitted Rs 20000.00
ASST. ENGINEER
NABARANGPUR BLOCK
BLOCK DEV.OFFICER
NABARANGPUR BLOCK
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM AMBADOLLA BHAURIKHANDI TO NADIGHAT
".
Est.Cost:- Rs.2,00,000/-
1 Collecting , conveying,supplying of good quality hard metal
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 450.00 X 3.00 X 0.10 = 135.00 Cum
@ Rs. 414.40 Per Cum Rs 55944.00
2 Collecting , conveying,supplying of good quality murrom or gravel
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road Sub base 1X 450.00 X 3.00 X 0.15 = 202.50 Cum
Add for metal Consolidation 25% of metal Qty. = 27.00 Cum
Total = 229.50 Cum
@ Rs. 188.00 Per Cum Rs 43146.00
3 Labour for laying sub-base in layers not exceeding
150 mm thick watering,compacting to the required density in OMC
with PRR but excluding cost & conveyance of Sub-base materials
Road 1X 450.00 X 3.00 X 0.15 = 202.50 Cum
@ Rs. 98.65 Per Cum Rs 19976.52
4 Labour for spreading metal & packing the voids with small stones
& hand packing the same to proper camber including conveying , spreading
of filler material & filling the interstics by spreading the same over the surface
watering & consolidation with PRR including hire & running charges of PRR
but excluding the cost of metal & filler material.
Road 1X 450.00 X 3.00 X 0.10 = 135.00 Cum
@ Rs. 210.41 Per Cum Rs 28405.13
5 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
& deposited the earth on the berm of the road.
Road 2X 450.00 X 0.80 X 0.60 = 432.00 Cum
Total = 432.00 Cum
@ Rs. 137.70 Per 2.83 Cum Rs 59486.40
6 Provision for remuneration of Gram Sathi 621 mandays @ 4.00 Rs 2484.00
7 Provision for Work Sign board & Photograph Rs. 1500.00
Grand Total Rs. 210942.05
Limitted to Rs. 200000.00
(Rupees Two Lakhs Only)
Technically Sanctioned for Rs.2,00,000/-
(Rupees Two Lakhs Only)
Sarapanch
Bikrampur GP
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM MALEKOTE TO SARANGIA CHHAKA ".
Est.Cost:- Rs.2,00,000/-
1 Collecting , conveying,supplying of good quality Murrom or Gravel
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 2380.00 X 3.00 X 0.10 = 714.00 Cum
@ Rs. 188.00 Per Cum Rs 134232.00
2 Labour for spreading muroom or gravel including watering but excluding cost
& conveyance of Muroom
Road 1X 2380.00 X 3.00 X 0.10 = 714.00 Cum
@ Rs. 37.04 Per Cum Rs 26449.69
3 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
& deposited the earth on the berm of the road.
Road 2X 2380.00 X 0.60 X 0.30 = 856.80 Cum
@ Rs. 141.62 Per 2.83 Cum Rs 42876.33
4 Provision for remuneration of Gram Sathi 709 mandays @ 4.00 Rs 2836.00
5 Provision for Work Sign board & Photograph Rs. 1500.00
Grand Total Rs. 207894.02
Limitted to Rs. 200000.00
(Rupees Two Lakhs Only)
Technically Sanctioned for Rs.2,00,000/-
(Rupees Two Lakhs Only)
Sarapanch
Chatahandi GP
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM BOXAGUDA TO BIRIGUDA CHHAKA ".
Est.Cost:- Rs.2,00,000/-
1 Collecting , conveying,supplying of good quality Murrom or Gravel
& stacking on the road side with box heap of size (1.50X1.50X0.50) mtr
to be measured as (1.50X1.50X0.44) mtr as 1 Cum
Road 1X 270.00 X 3.00 X 0.10 = 81.00 Cum
@ Rs. 186.40 Per Cum Rs 15098.40
2 Labour for spreading muroom or gravel including watering but excluding cost
& conveyance of Muroom
Road 1X 270.00 X 3.00 X 0.10 = 81.00 Cum
@ Rs. 28.81 Per Cum Rs 2333.61
3 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
& deposited the earth on the berm of the road.
Road 2X 270.00 X 0.60 X 0.30 = 97.20 Cum
2X 200.00 X 4.50 X 0.60 = 1080.00 Cum
Total = 1177.20 Cum
@ Rs. 141.62 Per 2.83 Cum Rs 58909.92
4 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Culvert ( U/S cutt-off) 1X 8.40 X 1.20 X 1.20 = 12.10 Cum
Culvert ( D/S cutt-off) 1X 8.40 X 1.20 X 1.50 = 15.12 Cum
Abutment 2X 3.80 X 1.20 X 1.20 = 10.94 Cum
Bed 1X 3.80 X 1.70 X 0.45 = 2.91 Cum
Total = 41.07 Cum
@ Rs. 5395.57 Per 100 Cum Rs 2215.80
5 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Culvert ( U/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
Culvert ( D/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
Abutment 2X 3.80 X 1.20 X 0.15 = 1.37 Cum
Bed 1X 3.80 X 1.70 X 0.15 = 0.97 Cum
Total = 5.36 Cum
@ Rs. 209.71 Per Cum Rs 1124.27
6 CC (1:4:8) using40 mm size hbg metal including all cost,conveyance
royality etc.complete
Culvert ( U/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
1X 8.40 X (1.00+0.75)/2 X 0.90 = 4.73 Cum
Culvert ( D/S cutt-off) 1X 8.40 X 1.20 X 0.15 = 1.51 Cum
1X 8.40 X (1.00+0.75)/2 X 1.20 = 6.30 Cum
Abutment 2X 3.80 X 1.20 X 0.30 = 2.74 Cum
2X 3.80 X (1.00+0.75)/2 X 0.75 = 4.99 Cum
2X 6.00 X (0.75+0.0.50)/2 X 1.15 = 8.63 Cum
Wing wall 4X 2.00 X (0.75+0.0.50)/2 X 1.15 = 5.75 Cum
Bed 1X 4.50 X 2.00 X 0.30 = 2.70 Cum
Parapet 2X 3.00 X 0.45 X 0.45 = 1.22 Cum
Total = 40.06 Cum
@ Rs. 2138.32 Per Cum Rs 85666.53
7 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Slab 1X 6.00 X 3.00 X 0.25 = 4.50 Cum
Total = 4.50 Cum
@ Rs. 3336.28 Per Cum Rs 15013.24
8 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Taking 90% of RCC Qty I.e 4.05 Qtl
@ Rs. 4125.86 Per Qtl Rs 16709.71
9 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Culvert ( U/S cutt-off) 1X 2X 8.40 X 0.90 = 15.12 Sqm
Culvert ( D/S cutt-off) 1X 2X 8.40 X 0.90 = 15.12 Sqm
Abutment 2X 2X 3.80 X 0.75 = 11.40 Sqm
2X 2X 6.00 X 1.00 = 24.00 Sqm
Wing wall 4X 2X 2.00 X 1.15 = 18.40 Sqm
Parapet 2X 2X 3.00 X 0.45 = 5.40 Sqm
Total = 89.44 Sqm
@ Rs. 62.46 Per Sqm Rs 5586.62
ii) Slab 1X 1X 6.00 X 3.00 = 18.00 Sqm
@ Rs. 201.68 Per Sqm Rs 3630.23
10 12 mm CP in CM (1:6) to the Super structure
Abutment 2X 1X 6.00 X 1.00 = 12.00 Sqm
Wing wall 4X 1X 2.00 X 1.15 = 9.20 Sqm
Parapet 2X 2X 3.00 X 0.45 = 5.40 Sqm
Total = 26.60 Sqm
@ Rs. 51.59 Per Sqm Rs 1372.28
11 PCC (1:2:4) using 12 mm size hbg chips including all complete.
Pier Cap 2 X 6.00 X 0.50 X 0.075 = 0.45
Cum
Bed 1 X 6.00 X 2.00 X 0.075 = 0.90
Cum
Wing wall 4 X 2.00 X 0.50 X 0.05 = 0.20
Cum
Parapet 2 X 3.00 X 0.45 X 0.05 = 0.14
Cum
Total = 1.69
Cum
@ Rs. 3289.62 Per Cum Rs 5543.01
12 Provision for remuneration of Gram Sathi 893 mandays @ 4.00 Rs 3572.00
13 Provision for Work Sign board & Photograph Rs. 1500.00
Grand Total Rs. 218275.62
Limitted to Rs. 200000.00
(Rupees Two Lakhs Only)
Technically Sanctioned for Rs.2,00,000/-
(Rupees Two Lakhs Only)
Sarapanch
Chatahandi GP
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD FROM DONGRIGUDA TO TELENGAGUDA."
Est.Cost:- Rs.15,00,000/-
1 E/W excavation in foundation with initial lead of 50 mtr.& initial
lift of 1.50 mtr including rough dressing & breaking the clods &
deposited the soil as directed by the EIC.
Culvert No.1
Culvert ( U/S cutt-off) 1X 16.00 X 1.50 X 1.50 = 36.00 Cum
Culvert ( D/S cutt-off) 1X 16.00 X 1.50 X 2.00 = 48.00 Cum
Abutment 2X 4.50 X 1.50 X 1.50 = 20.25 Cum
Pier 2X 4.50 X 1.50 X 1.50 = 20.25 Cum
Bed 2X 4.50 X 1.40 X 0.45 = 5.67 Cum
1X 4.50 X 1.10 X 0.45 = 2.23 Cum
Culvert No.2
Culvert ( U/S cutt-off) 1X 13.30 X 1.50 X 1.50 = 29.93 Cum
Culvert ( D/S cutt-off) 1X 13.30 X 1.50 X 2.00 = 39.90 Cum
Abutment 2X 4.50 X 1.50 X 1.50 = 20.25 Cum
Pier 1X 4.50 X 1.50 X 1.50 = 10.13 Cum
Bed 2X 4.50 X 1.40 X 0.45 = 5.67 Cum
Culvert No.3
Culvert ( U/S cutt-off) 1X 11.10 X 1.50 X 1.50 = 24.98 Cum
Culvert ( D/S cutt-off) 1X 11.10 X 1.50 X 2.00 = 33.30 Cum
Abutment 2X 4.50 X 1.50 X 1.50 = 20.25 Cum
Bed 1X 4.50 X 2.10 X 0.45 = 4.25 Cum
Total = 321.05 Cum
@ Rs. 5395.57 Per 100 Cum Rs 17322.21
2 Sand filling to the foundation & plinth with watering , ramming
including all cost,conveyance,royality etc. complete
Culvert No.1
Culvert ( U/S cutt-off) 1X 16.00 X 1.50 X 0.15 = 3.60 Cum
Culvert ( D/S cutt-off) 1X 16.00 X 1.50 X 0.15 = 3.60 Cum
Abutment 2X 4.50 X 1.50 X 0.15 = 2.03 Cum
Pier 2X 4.50 X 1.50 X 0.15 = 2.03 Cum
Bed 2X 4.50 X 1.40 X 0.10 = 1.26 Cum
1X 4.50 X 1.10 X 0.10 = 0.50 Cum
Culvert No.2
Culvert ( U/S cutt-off) 1X 13.30 X 1.50 X 0.15 = 2.99 Cum
Culvert ( D/S cutt-off) 1X 13.30 X 1.50 X 0.15 = 2.99 Cum
Abutment 2X 4.50 X 1.50 X 0.15 = 2.03 Cum
Pier 1X 4.50 X 1.50 X 0.15 = 1.01 Cum
Bed 2X 4.50 X 1.40 X 0.10 = 1.26 Cum
Culvert No.3
Culvert ( U/S cutt-off) 1X 11.10 X 1.50 X 0.15 = 2.50 Cum
Culvert ( D/S cutt-off) 1X 11.10 X 1.50 X 0.15 = 2.50 Cum
Abutment 2X 4.50 X 1.50 X 0.15 = 2.03 Cum
Bed 1X 4.50 X 2.10 X 0.10 = 0.95 Cum
Total = 31.25 Cum
@ Rs. 209.71 Per Cum Rs 6554.02
3 CC (1:3:6) using 40 mm size hbg metal including all cost,conveyance
royality etc.complete
Culvert No.1
Culvert ( U/S cutt-off) 1X 13.00 X 1.50 X 0.30 = 5.85 Cum
1X 13.00 X (1.20+0.90)/2 X 1.05 = 14.33 Cum
Culvert ( D/S cutt-off) 1X 13.00 X 1.50 X 0.30 = 5.85 Cum
1X 13.00 X (1.20+0.90)/2 X 1.05 = 14.33 Cum
Pier 2X 7.20 X 1.50 X 0.30 = 6.48 Cum
Abutment 2X 4.50 X 1.50 X 0.30 = 4.05 Cum
2X 4.50 X (1.20+0.90)/2 X 0.75 = 7.09 Cum
2X 7.20 X (0.90+0.60)/2 X 1.85 = 19.98 Cum
Wing wall 4X 3.10 X (0.90+0.50)/2 X 1.85 = 16.06 Cum
Bed 3X 4.50 X 2.00 X 0.25 = 6.75 Cum
Culvert No.2
Culvert ( U/S cutt-off) 1X 11.80 X 1.50 X 0.30 = 5.31 Cum
1X 11.80 X (1.20+0.90)/2 X 1.05 = 13.01 Cum
Culvert ( D/S cutt-off) 1X 11.80 X 1.50 X 0.30 = 5.31 Cum
1X 11.80 X (1.20+0.90)/2 X 1.05 = 13.01 Cum
Pier 1X 4.50 X 1.50 X 0.30 = 2.03 Cum
Abutment 2X 4.50 X 1.50 X 0.30 = 4.05 Cum
2X 4.50 X (1.20+0.90)/2 X 0.75 = 7.09 Cum
2X 7.20 X (0.90+0.60)/2 X 1.85 = 19.98 Cum
Wing wall 4X 3.10 X (0.90+0.50)/2 X 1.85 = 16.06 Cum
Bed 2X 4.50 X 2.00 X 0.25 = 4.50 Cum
Culvert No.3
Culvert ( U/S cutt-off) 1X 11.10 X 1.50 X 0.30 = 5.00 Cum
1X 11.10 X (1.20+0.90)/2 X 1.05 = 12.24 Cum
Culvert ( D/S cutt-off) 1 X 11.10 X 1.50 X 0.30 = 5.00 Cum
1 X 11.10 X (1.20+0.90)/2 X 1.05 = 12.24 Cum
Abutment 2 X 4.50 X 1.50 X 0.30 = 4.05 Cum
2 X 4.50 X (1.20+0.90)/2 X 0.75 = 7.09 Cum
2 X 7.20 X (0.90+0.60)/2 X 1.85 = 19.98 Cum
Wing wall 4 X 3.10 X (0.90+0.50)/2 X 1.85 = 16.06 Cum
Bed 1 X 4.50 X 2.40 X 0.25 = 2.70 Cum
Total = 275.45 Cum
@ Rs. 2454.05 Per Cum Rs 675969.15
4 RCC of M-20 grade using 20 mm & down grade black hard granite
crusher broken stone chips including hoisting & laying etc complete.
Culvert No.1
Slab 1X 8.40 X 7.20 X 0.23 = 13.91 Cum
Pier Cap 4X 7.20 X 0.60 X 0.15 = 2.59 Cum
Pier 2X 7.20 X 1.20 X 0.60 = 10.37 Cum
2X 7.20 X 0.60 X 2.60 = 22.46 Cum
Culvert No.2
Slab 1X 5.80 X 7.20 X 0.23 = 9.60 Cum
Pier Cap 3X 7.20 X 0.60 X 0.15 = 1.94 Cum
Pier 1X 7.20 X 1.20 X 0.60 = 5.18 Cum
1X 7.20 X 0.60 X 2.60 = 11.23 Cum
Culvert No.3
Slab 1X 3.60 X 7.20 X 0.23 = 5.96 Cum
Pier Cap 2X 7.20 X 0.60 X 0.15 = 1.30 Cum
Total = 84.56 Cum
@ Rs. 3336.28 Per Cum Rs 282104.85
5 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Total Quantity LS 60.00 Qtl
@ Rs. 4125.86 Per Qtl Rs 247551.30
6 Rigid & smooth centering,shuttering for PCC work & dismanteling
them after casting etc. complete.
i) Culvert No.1
Abutment 2X 2X 7.20 X 1.85 = 53.28 Sqm
Wing wall 4X 2X 3.10 X 1.85 = 45.88 Sqm
Culvert No.2
Abutment 2X 2X 7.20 X 1.85 = 53.28 Sqm
Wing wall 4X 2X 3.10 X 1.85 = 45.88 Sqm
Culvert No.3
Abutment 2X 2X 7.20 X 1.85 = 53.28 Sqm
Wing wall 4X 2X 3.10 X 1.85 = 45.88 Sqm
Total = 297.48 Sqm
@ Rs. 62.46 Per Sqm Rs 18581.25
ii) Culvert No.1
Pier 2X 2X 8.40 X 2.60 = 87.36 Sqm
Culvert No.2
Pier 1X 2X 8.40 X 2.60 = 43.68 Sqm
Total = 131.04 Sqm
@ Rs. 298.71 Per Sqm Rs 39142.54
Sarapanch
Badakumuli GP
DETAILED ESTIMATE FOR THE WORK:-"IMPV. OF ROAD AT CHIKILI HARIJAN SAHI."
Est.Cost:- Rs.1,00,000/-
1 Collecting,conveying & supplying of good quality gravel & stacking
on the road side with box heap of size ( 1.50X1.50X0.50) mtr to
be measured as 1 Cum.
For Sub-base of Road 1X 407.00 X 3.00 X 0.15 = 183.15 Cum
@ Rs. 188.00 Per Cum Rs 34432.20
2 Labour for laying sub-base in layers not exceeding
100 mm thick watering,compacting to the required density in OMC
with PRR but excluding cost & conveyance of Sub-base materials
For Sub-base of Road 1X 407.00 X 3.00 X 0.15 = 183.15 Cum
@ Rs. 37.04 Per Cum Rs 6784.68
3 E/W in Ordinary type of soil with initial lead & lift including
rough dressing & levelling the bed breaking clods maximum
up to 30 cm & depositedthe soil on the embankment of the
road as directed by the EIC.
Road 2X 407.00 X 2.25 X 0.60 = 1098.90 Cum
@ Rs. 141.62 Per 2.83 Cum Rs 54991.60
4 Provision for remuneration of Gaon Sathi for 505 Mandays @ 4.00 Rs 2020.00
5 Provision for work Transperancy board with photograph charges LS Rs 2000.00
Grand Total Rs. 100228.47
Say Rs. 100000.00
(Rupees One Lakhs Only)
Technically Sanctioned for Rs.1,00,000/-
(Rupees One Lakhs Only)
Sarapanch
Badakumuli GP
Name of the Work: IMPV. OF ROAD AT HARIJAN CHIKILI."
MATERIAL & LABOUR STATEMENT ( NREGS WORK )
Sand / Stone Masson Labour
Sl No Item Qty Unit Cement
Moorum Product 1st 2nd skilled un skilled
1 E/W in ordinary soil 1098.90 2.83 Cum 431.27
2 E/W in hard soil 0.00 100 Cum 0.00
3 E/W in Foundation 0.00 100 Cum 0.00
4 Sand filling 0.00 Cum 0.00 0.00
5 CC (1:4:8) 0.00 Cum 0.00 0.00 0.00 0.00 0.00
6 CC (1:3:6) 0.00 Cum 0.00 0.00 0.00 0.00 0.00
7 RRSM in CM (1:6) 0.00 Cum 0.00 0.00 0.00 0.00 0.00 0.00
8 RCC of M-20 grade 0.00 Cum 0.00 0.00 0.00 0.00 0.00
9 CC (1:2:4) 0.00 Cum 0.00 0.00 0.00 0.00 0.00
10 CC (1:1.5:3) 0.00 Cum 0.00 0.00 0.00 0.00 0.00
Supplying,fitting,fixing of HYSD bar
11 reinforcement 0.0000 Qtl 0.00 0.00
Labour for painting 2 coats with any
12 approved paint only 0.00 litre 0.00 0.00
13 WBCB in CM (1:6) 0.00 Cum 0.00 0.00 0.00 0.00 0.00
Rigid & smooth centering & shuttering
Plinth,mass concreete 0.00 Sqm 0.00 0.00
14 lintel band 0.00 Sqm 0.00 0.00
beam 0.00 Sqm 0.00 0.00
Slab / Chajja 0.00 Sqm 0.00 0.00
15 12 mm CP in CM (1:6) 0.00 Sqm 0.00 0.00 0.00 0.00
16 16 mm CP in CM (1:6) 0.00 Sqm 0.00 0.00 0.00 0.00
17 20 mm CP in CM (1:4) 0.00 Sqm 0.00 0.00 0.00 0.00
Distempering wall Surface two coats
18 including all complete. 0.00 Sqm 0.00 0.00
19 2.50 CM thick ASF in CC (1:2:4) 0.00 Sqm 0.00 0.00 0.00 0.00 0.00
20 Collection of Soling Stone 0.00 Cum 0.00
21 Collection of Murrom 183.15 Cum 183.15
22 Spreading Murrom 183.15 Cum 73.91
23 Spreading Metal (Grade-II) 0.00 Cum 0.00 0.00 0.00 0.00
24 Collection of Hard Metal 0.00 Cum 0.00
25 Labour for Sub base 0.00 Cum 0.00
26 Spreading Metal (Grade-I) 0.00 Cum 0.00 0.00 0.00 0.00
27 Labour for Soling road Surface 0.00 Cum 0.00 0.00
Total 0.00 183.15 0.00 0.00 0.00 0.00 505.18
Say 0 Cum Cum 0 0 0 505
Bags Nos Nos Nos Nos
Cost of Material & Royality Statement
Sl Name of Materials Total Qty Unit Basic Conveyance Royality Total VAT 4% on Total VAT Net Rate of Net Value of
executed Rate per per Unit per Cum Royality Basic Rate per Value in materials in Materials in
No. Cum Cum Rs Rs Rs
1 Sand for mortar 0.00 Cum 47.00 134.00 14.00 0.00 1.88 0.00 179.12 0.00
2 Sand for filling 0.00 Cum 41.00 134.00 14.00 0.00 1.64 0.00 173.36 0.00
3 Murrom 183.15 Cum 40.00 134.00 14.00 2564.10 1.60 293.04 172.40 31575.06
4 Bricks 0.00 Cum 708.00 131.84 14.00 0.00 28.32 0.00 811.52 0.00
5 Earth 1098.90 Cum 0.00 0.00 14.00 15384.60 0.00 0.00 0.00 0.00
6 40 mm size hbg metal 0.00 Cum 430.00 134.00 50.40 0.00 17.20 0.00 546.80 0.00
7 40 mm size cbg metal 0.00 Cum 480.00 134.00 50.40 0.00 19.20 0.00 594.80 0.00
8 12 mm size hbg chips 0.00 Cum 625.00 134.00 50.40 0.00 25.00 0.00 734.00 0.00
9 12 mm size cbg chips 0.00 Cum 820.00 134.00 50.40 0.00 32.80 0.00 921.20 0.00
10 20 mm size cbg chips 0.00 Cum 770.00 134.00 50.40 0.00 30.80 0.00 873.20 0.00
11 10 mm size cbg chips 0.00 Cum 850.00 134.00 50.40 0.00 34.00 0.00 950.00 0.00
12 6 mm size cbg chips 0.00 Cum 575.00 134.00 50.40 0.00 23.00 0.00 686.00 0.00
13 Hard Metal 0.00 Cum 230.00 134.00 50.40 0.00 9.20 0.00 354.80 0.00
14 Rod 0.00 Qtl 3450.00 13.90 0.00 0.00 0.00 0.00 3463.90 0.00
15 Soling Stone 0.00 Cum 118.00 134.00 50.40 0.00 4.72 0.00 247.28 0.00
Total 17948.70 293.04 31575.06
Mustor Roll Say 17949.00 293.00 31575.00
1 Masson 1st Class 0 Nos @ 129.00 = 0.00
2 Masson 2nd Class 0 Nos @ 116.00 = 0.00
3 Semiskilled Labour 0 Nos @ 103.00 = 0.00
4 Un-Skilled Labour 505 Nos @ 90.00 = 45450.00
505 Nos Total 45450.00
Summary
1 Cement 0 Bags @ 240.00 Rs 0.00
2 Conveyance of Cement 0 Bags @ 6.95 Rs 0.00
3 Cost of Material Rs 31575.00
4 Mustor Roll Rs 45450.00
5 Gaon Sathi 505 Mandays @ 4.00 Rs 2020.00
6 Royality Rs 17949.00
Rest shed , Drinking water , Medicene
7 etc. Rs 0.00
8 Sign Board , Photograph Rs 2000.00
9 Cost of MS gate Rs 0.00
10 PRR Charges Rs 0.00
11 Water Tanker Charges Rs 0.00
10 VAT Rs 293.00
11 T&P & centering Materials & Others Rs 713.00
Total Rs 100000.00
Bill Summary
No of Labour Per Day 42 Nos.
Total Mandays in Thousand 0.50500 Thoudands
Cost of Skilled Labour 0.00000 Lakhs
Cost of Unskilled Labour 0.45450 Lakhs
Cost of Materials 0.54550 Lakhs Junior Engineer
Total 1.00000 Lakhs Nabarangpur Block
DETAILED ESTIMATE FOR THE WORK:- " CONSTRUCTION OF
COMPOSITE TANK AT KESHARIGUDA".
Sl
Name of Items Unit Cost Total Estimated Cost
No
Total 2000000.00
( Rupees Twenty Lakhs) Only
Addl PD ( Tech )
DRDA , NABARANGPUR
DETAILED ESTIMATE FOR THE WORK:- " CONST. OF COMMUNITY POND AT OLD BOXAGUDA".
JUNIOR ENGINEER
NABARANGPUR BLOCK
ASST. ENGINEER
NABARANGPUR BLOCK
BLOCK DEV.OFFICER
NABARANGPUR BLOCK
DETAILED ESTIMATE FOR THE WORK:- " IMPV. OF MIP AT MANTRIGUDA".
ESTIMATED COST :- Rs.3,00,000/-
1 E/W in hard soil with one extra lift over initial lead & lift including rough dressing
breaking the clods & deposited the soil on the embankment of the Tank as directed
by the EIC.
2nd Footing
Ponding Area 1 X 40.00 X 40.00 X 1.50 = 2400.00 Cum
Total = 2400.00 Cum
@ Rs 4323.78 Per 100 Cum Rs 103770.72
2 E/W in excavation in foundation with initial lead & lift including
rough dressing & levelling the bed & deposited the soil as
directed by the EIC.
Protection wall 1 X 39.60 X 1.20 X 1.20 = 57.02 Cum
@ Rs 4736.88 Per 100 Cum Rs 2701.16
3 CC (1:3:6) using 40 mm size hbg metal including all complete.
Protection wall 1 X 39.60 X 1.20 X 0.30 = 14.26 Cum
1 X 39.60 X (1.00+0.50)/2 X 2.10 = 62.37 Cum
Total 76.63 Cum
@ Rs 2401.02 Per Cum Rs 183980.18
4 Rigid & smooth centering, shuttering for PCC work
& dismanteling them after casting etc complete.
Protection wall 1 X 2 X 39.60 X 2.10 = 166.32 Sqm
@ Rs 60.93 Per Cum Rs 10133.74
5 CC (1:2:4) using 12 mm size hbg chips including all complete.
Protection wall 1 X 39.60 X 0.50 X 0.05 = 0.99 Cum
@ Rs 3219.24 Per 100 Cum Rs 3187.04
6 Fine dressing & turfing to the embankment of the tank with compact
dub grass including all cost,conveyance with all lead & lift
etc complete.
Embankment area 2 X 2 X 70.00 X 3.50 = 980.00 Sqm
@ Rs 832.47 Per 100 Sqm Rs 8158.24
7 Add for Work Contigency 1% Rs 3000.00
8 Provision for work sign board with lettering,painting & Photograph Rs 2000.00
G.TOTAL Rs 316931.08
Limitted Rs 300000.00
( Rupees Three Lakhs Only)
Technically Scrutinised for Rs.3,00,000/-
( Rupees Three Lakhs Only)
JUNIOR ENGINEER
NABARANGPUR BLOCK
ASST. ENGINEER
NABARANGPUR BLOCK
Const of Surplus
1 E/W in excavation in foundation with initial lead & lift including
rough dressing & levelling the bed & deposited the soil as
directed by the EIC.
Abutment Wall 1 X 4.00 X 0.75 X 0.75 = 2.25 Cum
U/S Cutoff Wall 1 X 4.00 X 0.75 X 0.75 = 2.25 Cum
U/S Wing Wall 2 X 2.00 X 0.75 X 0.75 = 2.25 Cum
D/S Cutoff Wall 1 X 4.00 X 0.75 X 0.75 = 2.25 Cum
D/S Wing Wall 2 X 2.00 X 0.75 X 0.75 = 2.25 Cum
Total = 9.00 Cum
@ Rs 4721.40 Per 100 Cum Rs 424.93
2 CC (1:4:8) using 40 mm size hbg metal including all complete.
Abutment Wall 1 X 14.50 X 0.75 X 0.15 = 1.63 Cum
1 X 14.50 X (0.75+0.45)/2 X 1.75 = 15.23 Cum
U/S Cutoff Wall 1 X 4.00 X 0.75 X 0.15 = 0.45 Cum
1 X 4.00 X (0.75+0.45)/2 X 0.60 = 1.44 Cum
U/S Wing Wall 2 X 2.00 X 0.75 X 0.15 = 0.45 Cum
2 X 2.00 X (0.75+0.45)/2 X 1.75 = 4.20 Cum
D/S Cutoff Wall 1 X 4.00 X 0.75 X 0.15 = 0.45 Cum
1 X 4.00 X (0.75+0.45)/2 X 0.60 = 1.44 Cum
D/S Wing Wall 2 X 2.00 X 0.75 X 0.15 = 0.45 Cum
2 X 2.00 X (0.75+0.45)/2 X 1.75 = 4.20 Cum
Total = 25.74 Cum
@ Rs 2085.29 Per Cum Rs 53667.60
3 Rigid & smooth centering, shuttering for PCC work
& dismanteling them after casting etc complete.( Mass Concreete )
Abutment Wall 1 X 2 X 14.50 X 1.75 = 50.75 Sqm
U/S Cutoff Wall 1 X 2 X 4.00 X 0.60 = 4.80 Sqm
U/S Wing Wall 2 X 2 X 2.00 X 1.75 = 14.00 Sqm
D/S Cutoff Wall 1 X 2 X 4.00 X 0.60 = 4.80 Sqm
D/S Wing Wall 2 X 2 X 2.00 X 1.75 = 14.00 Sqm
Total = 88.35 Sqm
@ Rs 60.93 Per Sqm Rs 5383.09
4 CC (1:2:4) using 12 mm size hbg chips including all complete.
Abutment Wall 2 X 14.50 X 0.45 X 0.05 = 0.65 Cum
Wing Wall 4 X 2.00 X 0.45 X 0.05 = 0.18 Cum
Total = 0.83 Cum
@ Rs 3219.24 Per Cum Rs 2680.01
5 Fine dressing & turfing to the embankment of the tank with compact
dub grass including all cost,conveyance with all lead & lift
etc complete.
Embankment area 2 X 2 X 70.00 X 3.50 = 980.00 Sqm
@ Rs 0.00 Per 100 Sqm Rs 0.00
DATA FOR DESIGN OF CULVERT = 2 Nos.
0.90 0.90
0.64 0.64
0.37 Mtr. 0.37 Mtr.
5.87 Mtrs.
49 Nos
7.42 Mtrs.
40 Nos
5.87 Mtrs.
0.37 38 Nos 0.37
0.52
0.48
0.10
Cement 387.07 Bags 0.58
. MS RODS
Abutement caps
10 mm rods Main 51 X 7.40 X 0.617 = 232.856 Kgs.
8 mm rods Rings 202 X 2.40 X 0.395 = 191.496 Kgs.
Deck slab
16 mm rods Crank-main 50 X 6.11 X 1.578 = 481.737 Kgs.
16 mm rods Plain-main 49 X 5.87 X 1.578 = 453.880 Kgs.
16 mm rods Plain-Dist 40 X 7.42 X 1.578 = 468.350 Kgs.
10 mm rods Top-main 38 X 6.61 X 0.617 = 154.978 Kgs.
10 mm rods Top-Dist 40 X 8.16 X 0.617 = 201.389 Kgs.
16mm rods Chairs 6 X 2.00 X 1.578 = 18.936 Kgs.
Total = 2203.622 Kgs.
Constn. of R.C.C. culvert on the road from
6.25
5.95
DECK SLAB IN RCC (1:1.5:3) 0.45
0.15 0.15
0.65 0.65
5.00
2.25
2.25
♣♣♣ NSL NSL ♣♣♣
1.35 1.35
1.35 1.35
4.00 4.00
5.00
6.60 7.50 6.60
5.95
4.00 4.00
TOP PLAN
b. Earth work excavation in stoney earth with initial lead & lift
1X 30.00 X 1.50 X 0.90 = 40.50 Cum
@ Rs. 253.82 Per 2.83 Cum = Rs 3632.41
5 Earth excavation in hard soil with initial lead & lift for foundation wall
1X 48.00 X 0.90 X 0.90 = 38.88 Cum
@ Rs. 7093.26 Per 100 Cum Rs 2757.86
1 E/W in Ordinary type of soil with initial lead & lift including
1 E/W in Ordinary type of soil with initial lead & lift including
be measured as 1 Cum.
8-10 tonnes in stages to proper grade & camber applying & brooming requisites
type of coarse aggregates,watering & compacting to the required density as per clause
1 E/W in Ordinary type of soil with initial lead & lift including
be measured as 1 Cum.
be measured as 1 Cum.
E/W in ordinary type of Soil with initial lead & lift including
rough dressing & levelling the bed breaking clods
1 maximum up to 5 CM to 7 CM & deposited the soil on the 5342.04 2.83 Cum 162.02 305836.51
embankment of the road as directed by EIC.
E/W in excavation in hard Soil with initial lead & lift
2 including dressing & levelling the bed & deposited the soil 85.08 100 Cum 4721.40 4016.83
as directed by EIC.
Sand filling to the F&P including all cost,conveyance ,
3 12.49 Cum 208.21 2599.98
royality etc complete
CC ( 1:4:8) using 4 cm size hbg metal including all
4 118.60 Cum 1904.81 225904.28
cost,conveyance,royality etc complete.
RCC of M-20 grade using 20 mm & down grade chips
5 21.94 Cum 2982.99 65439.34
including all cost,conveyance , royality etc complete.
Supplying , fitting , fixing of HYSD bar reinforcement etc
6 19.74 Cum 3795.80 74943.33
complete.
Rigid & smooth centering shuttering for PCC & RCC work
including dismanteling them after casting etc complete.
7
Mass Concreete 315.48 Sqm 60.93 19222.20
Slab 87.75 Sqm 192.14 16860.29
12 mm CP in CM (1:6) to the superstructure including all
8 cost , conveyance royality etc complete. 97.26 Sqm 45.85 4459.37
1 Sand for mortar 71.88 Cum 47.00 134.00 14.00 1006.36 0.00 0.00 167.00 12004.40
2 Sand for filling 12.49 Cum 41.00 134.00 14.00 174.83 0.00 0.00 161.00 2010.49
3 Murrom 175.73 Cum 40.00 134.00 14.00 2460.15 0.00 0.00 160.00 28116.00
4 Bricks 0.00 Cum 708.00 131.84 14.00 0.00 0.00 0.00 825.84 0.00
5 Earth 5427.12 Cum 0.00 0.00 14.00 75979.64 0.00 0.00 0.00 0.00
6 40 mm size hbg metal 113.85 Cum 430.00 134.00 50.40 5738.19 17.20 1958.27 513.60 58474.84
7 IRC Grade -I metal 0.00 Cum 480.00 134.00 50.40 0.00 19.20 0.00 563.60 0.00
8 12 mm size hbg chips 7.25 Cum 625.00 134.00 50.40 365.44 25.00 181.27 708.60 5137.95
9 12 mm size cbg chips 0.00 Cum 820.00 134.00 50.40 0.00 32.80 0.00 903.60 0.00
10 20 mm size cbg chips 11.85 Cum 770.00 134.00 50.40 597.05 30.80 364.86 853.60 10111.96
11 10 mm size cbg chips 7.90 Cum 850.00 134.00 50.40 398.03 34.00 268.52 933.60 7373.11
12 6 mm size cbg chips 0.00 Cum 575.00 134.00 50.40 0.00 23.00 0.00 658.60 0.00
13 Hard Metal 0.00 Cum 230.00 134.00 50.40 0.00 9.20 0.00 313.60 0.00
14 Rod 19.74 Qtl 3450.00 13.90 0.00 0.00 0.00 0.00 0.00 0.00
15 Hard Stone 0.00 Cum 140.00 134.00 50.40 0.00 5.60 0.00 223.60 0.00
Total 86719.68 2772.92 123228.74
Say 86720.00 2773.00 123229.00
Mustor Roll New Rate
1 Masson 1st Class 6 Nos @ 129.00 = 774.00
2 Masson 2nd Class 128 Nos @ 116.00 = 14848.00
3 Semiskilled Labour 73 Nos @ 103.00 = 7519.00
4 Un-Skilled Labour 3250 Nos @ 90.00 = 292500.00
3457 Nos Total 315641.00
Summary
1 Cement 619 Bags @ 244.00 Rs 151036.00
2 Cement 0 Bags @ 214.00 Rs 0.00
3 Cost of Material Rs 123229.00
4 Mustor Roll Rs 315641.00
5 Gaon Sathi 3457 Mandays @ 4.00 Rs 13828.00
6 Gram Sanjoyak 60 Days @ 103.00 Rs 6180.00
7 Royality Rs 86720.00
8 Rest shed , Drinking water , Medicene etc. Rs 5000.00
9 Sign Board , Photograph Rs 2500.00
10 Cost of MS gate,Door,Window & Grill Rs 0.00
11 PRR Charges Rs 0.00
12 Water Tanker Charges Rs 0.00
13 VAT Rs 2773.00
14 Cess Rs 8000.00
15 Cost of MS Rod 19.74 Qtl @ 3450.00 Rs 68116.00
16 T&P & centering Materials & Others Rs 16977.00
Total Rs 800000.00
No of Labour Per Day 58 Nos.
Total Mandays in Thousand 3.45700 Thoudands
Cost of Skilled Labour 0.23141 Lakhs
Cost of Unskilled Labour 2.92500 Lakhs 31.56 %
Cost of Materials 6.84359 Lakhs 68.44 % Junior Engineer
Total 10.00000 Lakhs Nabarangpur Block
Analysis of Rates 2009 for 8 hour of work.
1 E/W in excavation in hard soil with initial lead & lift
including rough dressing & breaking clods etc. complete.
Data for 100 Cum
Man Mulia 21.50 Nos @ 90.00 Per No Rs 1935.00
Woman mulia 21.50 Nos @ 90.00 Per No Rs 1935.00
T & P , Sundries 2% Rs 77.40
Grand Total Rs 3947.40 Per 100 Cum
Royality of Earth for 100 Cum 100.00 Cum @ 14.00 Per Cum Rs 1400.00
Grand Total Rs. 5347.40 Per 100 Cum
2 E/W in ordinary soil with initial lead & lift
including rough dressing & breaking clods max. up to 5 cm to 7 cm
& deposited the soil as directed by EIC etc. complete.
Data for 2.83 Cum
Rate for Ordinary Soil Rs 120.00
T & P , Sundries 2% Rs 2.40
Total Rs 122.40 Per 2.83 Cum
Royality of Earth for 2.83 Cum 2.83 Cum @ 14.00 Per Cum Rs 39.62
Grand Total Rs 162.02 Per 2.83 Cum
3 E/W in excavation in hard soil in Foundation with initial lead & lift
including rough dressing & breaking clods etc. complete.
Data for 100 Cum
Rate as per Item No.1 I.e Rs. 3947.40
Add 20% extra Lbour for excavation of Foundation Rs. 774.00
Royality of Earth for 100 Cum 100.00 Cum @ 14.00 Per Cum Rs 1400.00
Grand Total Rs. 6121.40 Per 100 Cum
4 Filling the foundation & the plinth with excavated earth well
watered & rammed completely 2/3rd rate of the earth work in hard soil Rs. 2631.60 Per 100 Cum
5 Filling the Foundation & plinthwith sandwith well watered & rammed
etc. complete.
Filling Sand 1.00 Cum @ 193.00 Per Cum Rs. 193.00
Man Mulia 0.1236 Nos @ 90.00 Per No Rs. 11.12
T & P , Sundries 2% Rs. 4.08
Grand Total Rs. 208.21 Per Cum
6 CC (1:4:8) using 4 cm size hbg metal including all cost, conveyance
royality etc complete.
Materials
Hbg metal 40 mm size 0.96 Cum @ 694.40 Per Cum Rs 666.62
Sand for Mortar 0.48 Cum @ 196.00 Per Cum Rs 94.08
Cement 1.72 Qtl @ 553.90 Per Qtl Rs 952.71
Labour
Masson 2nd Class 0.18 Nos @ 116.00 Per No Rs 20.88
Man Mulia 2.50 Nos @ 90.00 Per No Rs 225.00
Woman Mulia 1.40 Nos @ 90.00 Per No Rs 126.00
Grand Total Rs. 2085.29 Per Cum
7 CC (1:2:4) using 12 mm size hbg Chips including all cost, conveyance
royality etc complete.
Materials
Hbg Chips 12 mm size 0.90 Cum @ 809.40 Per Cum Rs 728.46
Sand for Mortar 0.45 Cum @ 195.00 Per Cum Rs 87.75
Cement 3.23 Qtl @ 493.90 Per Qtl Rs 1595.30
Labour
Masson 2nd Class 0.68 Nos @ 116.00 Per No Rs 78.88
Man Mulia 3.20 Nos @ 90.00 Per No Rs 288.00
Woman Mulia 1.40 Nos @ 90.00 Per No Rs 126.00
Grand Total Rs. 2904.39 Per Cum
8 RCC of M-20 grade using 20 mm & down grade hard granite
Cbg Chips 12 mm size including all cost , conveyance
royality etc. complete.( Data for 15 Cum )
Materials
Cbg Chips 20 mm size 8.10 Cum @ 954.40 Per Cum Rs 7730.64
Cbg Chips 10 mm size 5.40 Cum @ 1034.40 Per Cum Rs 5585.76
Sand for Mortar 6.75 Cum @ 195.00 Per Cum Rs 1316.25
Cement 52.10 Qtl @ 493.90 Per Qtl Rs 25732.19
Labour
Masson 2nd Class 1.50 Nos @ 116.00 Per No Rs 174.00
Man Mulia 20.00 Nos @ 90.00 Per No Rs 1800.00
Machinery
Concreete Mixer ( Cap 0.40 / 0.28 Cum )
6.00 Hrs @ 161.00 Hr Rs 966.00
Generator 33 KVA 6.00 Hrs @ 240.00 Hr Rs 1440.00
Grand Total Rs. 44744.84 Per Cum
Rate per 1 Cum Rs 2982.99 Per Cum
9 12 mm CP in CM (1:6) including all cost , conveyance , royality
etc. complete.
Materials
Sand for Mortar 0.02 Cum @ 195.00 Per Cum Rs 2.93
Cement 0.04 Qtl @ 493.90 Per Qtl Rs 17.68
Labour
Masson 2nd Class 0.14 Nos @ 116.00 Per No Rs 16.24
Man Mulia 0.05 Nos @ 90.00 Per No Rs 4.50
Woman Mulia 0.05 Nos @ 90.00 Per No Rs 4.50
Grand Total Rs. 45.85 Per Sqm
10 Supplying , fitting & fixing uncoated HYSD bar reinforcement
including all complete.
Materials
HYSD bar including 5% extra for overlap & wastage
1.05 Qtl @ 3463.90 per Qtl Rs. 3637.10
Binding wire 0.80 Kg @ 60.00 per Kg Rs. 48.00
Labour
Black smith 1st Class 0.30 Nos @ 129.00 Per No Rs 38.70
Man Mulia 0.80 Nos @ 90.00 Per No Rs 72.00
Grand Total Rs. 3795.80 Per Qtl
11 Labour for laying sub-base in layers not exceeding
100 mm thick watering,compacting to the required density in OMC
with PRR but excluding cost & conveyance of Sub-base materials
Data for 2.83 Cum
Labour
Man mulia for removing from stacks,spreading & rolling
1.00 No @ 90.00 Per No Rs 90.00
Woman mulia for watering & conveyance etc.
1.50 Nos @ 90.00 Per No Rs 135.00
Machinery
Add hire & running charges of PRR for consolidation considering
425 Cum of out turn with PRR per day ( 8.00 Hrs)
0.05 Hrs @ 320.00 Per Hr Rs 17.02
Add 2% for T&P, sundries Rs 4.84
Grand Total Rs. 246.86
Rate per 1 cum Rs 87.23 Per Cum
12 Providing , laying, spreading & compacting stone aggregates
of specific sizes to WBM specification including spreading uniform
thickness,hand packing,rolling with 3-wheeled steel rollers
8-10 tonnes in stages to proper grade & camber applying & brooming requisites
type of coarse aggregates,watering & compacting to the required density as per clause
404 of MoSRT&H specification for road & bridge works.
Taking out put 360 Cum
A)Grade-I (using muroom or gravel )
Materials
Grading-I 90 mm to 45 mm @ 1.21 Cum per 10 Sqm for compacted thickness
of 100 mm thick 435.60 Cum @ 664.40 per Cum Rs 289412.64
Muroom or Gravel @ 0.30 Cum per 10 Sqm
108.00 Cum @ 188.00 per Cum Rs 20304.00
Cost of water 144.00 KL @ 10.00 Per KL Rs 1440.00
Labour
Skilled Mulia 2.00 Nos @ 103.00 Per No Rs 206.00
Mulia 250.00 Nos @ 90.00 Per No Rs 22500.00
Machinery
Smoth 3-wheeled steel rollers @ 30 Cum per Hour
12.00 Hrs @ 320.00 Per Hr Rs 3840.00
Water tanker 6.00 KL cap. 24.00 Hrs @ 506.00 Per Hr Rs 12144.00
Grand Total Rs. 349846.64 Per 360 Cum
Rate per 1 Cum Rs. 971.80 Per Cum
13 Labour for spreading muroom or gravel including watering but excluding cost
& conveyance of Muroom
Data for 2.83 Cum
Labour
Man Mulia 1.00 Nos @ 90.00 Per No Rs 90.00
Add 2% for T&P, Sundries Rs 1.80
Grand Total Rs. 91.80 Per 2.83 Cum
Rate per 1 Cum Rs. 32.44 Per Cum
14 Labour for spreading metal & packing the voids with small stones
& hand packing the same to proper camber including conveying , spreading
of filler material & filling the interstics by spreading the same over the surface
watering & consolidation with PRR including hire & running charges of PRR
but excluding the cost of metal & filler material.
Data for 2.83 Cum
Labour
Man mulia for removing from stacks,spreading metal to proper camber & turfedging
1.00 No @ 90.00 Per No Rs 90.00
Woman mulia for watering & conveyance etc.
3.00 Nos @ 90.00 Per No Rs 270.00
Machinery
Add hire & running charges of PRR for consolidation considering
42 Cum of out turn with PRR per day ( 8.00 Hrs)
0.54 Hrs @ 320.00 Per Hr Rs 172.48
Add 2% for T&P, sundries Rs 10.65
Grand Total Rs. 543.13 Per 2.83 Cum
Rate per 1 cum Rs 191.92 Per Cum
JUNIOR ENGINEER
NABARANGPUR BLOCK
Technically Sanctioned for Rs.1000000.00
( Rupees Ten Lakhs Only)
ASST. ENGINEER,
NABARANGPUR BLOCK
BLOCK DEV.OFFICER
NABARANGPUR BLOCK
Detail Estimate for the work, " Estimate of BNRGSK at Block level
JUNIOR ENGINEER
NABARANGPUR BLOCK
Technically Sanctioned for Rs.2500000.00