Você está na página 1de 6

REFRIGRATION ASSEMBLY PROCESS

Issue 1 SCH-PSF-REFAS-PRO- 001 Date Nov, 25, 2018

Revision 0 Page 1

REFIRGRATION ASSEMBLY PROCESS


Reviewed By
Prepared By Industrial Approved by
Rev. No. Commercial
Director General manager
Manager
3 Name
Date Signature

2 Name
Date Signature

1 Name
Date Signature

0 Name
Date: Signature
/ /2018

Distribution Log
Sr Position Name Signature
1 General Manager Eng. Ahmed Samir

2 Commercial Manager Eng. Ahmed Ghandour

3 Operation Manager DR. Samir El Bahtity

Issue: 1 Refrigeration Assembly Process Date: Nov, 25, 2018 Revision : 0 Page 1
REFRIGRATION ASSEMBLY PROCESS
Issue 1 SCH-PSF-REFAS-PRO- 001 Date Nov, 25, 2018

Revision 0 Page 2

INDEX

1- ACTIVITY PURPOSE

2- ACTIVITY SCOPE

3- RESPONSIBILITIES ABBREVATION AND DIFINETIONS

4- PROCEDURE

5- ATTACHMENTS ( DELIVERABLES )

6- RISKS AND OPPORTUNITIES

Issue: 1 Refrigeration Assembly Process Date: Nov, 25, 2018 Revision : 0 Page 2
REFRIGRATION ASSEMBLY PROCESS
Issue 1 SCH-PSF-REFAS-PRO- 001 Date Nov, 25, 2018

Revision 0 Page 3

1- ACTIVITY PURPOSE:

This process was developed to describe the process of industrial refrigeration


Process

2- ACTIVITY SCOPE:
Industrial refrigeration Process and it related

3- RESPONSIBILITIES ABBREVATION AND DEFINITIONS


OPM Operation Manager
TOM Technical office manager
QM Quality Manager
PM Production Manager
COM Commercial Manager

Issue: 1 Refrigeration Assembly Process Date: Nov, 25, 2018 Revision : 0 Page 3
REFRIGRATION ASSEMBLY PROCESS
Issue 1 SCH-PSF-REFAS-PRO- 001 Date Nov, 25, 2018

Revision 0 Page 4

4- PROCEDURE:

Activity Description Process owner Approval

5.1 Receiving requirement from the client. Client


COM

5.2 Calculating cooling loads. TOM


OPM

5.3 Specifying and selecting the required TOM


equipment for the calculated cooling loads. PM OPM

5.4 Manufacturing process:

a. Manufacturing the chassis.


b. Manufacturing the receiver tank.
PM
c. Manufacturing the accumulator. QM
d. Manufacturing the water condenser if
required.
e. Manufacturing the evaporator if required.

5.5 Collecting the pre manufactured items:

a. Gauges, High/Low pressure switch, Solenoid PM


QM
valve, Sight glass and hand valves.
b. Copper/steel piping material.

5.6 Installing all items into one assembled


product:

a. Installing compressors. PM
QM
b. Installing tanks and condensers.
c. Installing piping and instrumentation.
d. Installing control panel.

5.7 Product is ready to be delivered. OPM


Client

Issue: 1 Refrigeration Assembly Process Date: Nov, 25, 2018 Revision : 0 Page 4
REFRIGRATION ASSEMBLY PROCESS
Issue 1 SCH-PSF-REFAS-PRO- 001 Date Nov, 25, 2018

Revision 0 Page 5

5- Attachments (Deliverables):

SCH-PSF-REFAS-CL-F-001 Refrigeration assembly checklist

6- RISKS AND OPPORTUNITIES:


Risk/Opportunity Effect Severity Action
Neglecting the Quality of the Inspecting the Finished
finished product like gauges and Negative High products before assembling
Solenoid. it is mandatory

Issue: 1 Refrigeration Assembly Process Date: Nov, 25, 2018 Revision : 0 Page 5
REFRIGRATION ASSEMBLY PROCESS
Issue 1 SCH-PSF-REFAS-PRO- 001 Date Nov, 25, 2018

Revision 0 Page 6

Issue: 1 Refrigeration Assembly Process Date: Nov, 25, 2018 Revision : 0 Page 6