2 Actuators
1B95080 - 08/2019-2
Fitting and Re-fitting
Figure 2
Figure 3
Figure 1
Green
Grey
Blue
Grey
Blue
Grey
Blue
Green
Feedback signal
0-10V DC
actuator remains in the final failsafe position until
Close Open
charging mode is reached (max. 60 sec). Here-
Power 24V AC/DC after the actuator will return to normal operation
Ground/common
mode.
Feedback ground
0V DC
#3 %
% Normally Open %
% % 3
% %
% Normally Closed
2
#2 Control signal 2-10V Control signal 0-10V
1
#1 Auto cycle ON Auto cycle OFF
LED Status
The LED indicator is visible through the dark colored transparent connection cover. The LED indica-
tion will give the following statuses.
FN.0.2 FN.0.4 FN.1.2
FlowCon International assumes no responsibility for mistakes, if any, in any printed material.
Flushing:
Water must always be suitable treated, clean recommends 4-6 rounds of tape applied tightly
and free of debris (according to VDI 2035 re- in clockwise rotation. WHEN USING HEMP AS
commendation). PIPE SEALANT, ENSURE NO STRANDS ARE
In case of an insert-based valve, system is re- LEFT IN THE VALVE OR PIPING.
commended to be flushed before the insert is in-
stalled in the valve body. A suitable flushing cap For threaded connections including sealing O-
is available. In case of a one-unit-valve, system ring or sealing gasket additional sealing is not
is recommended to be flushed before the valve required. Please make sure the O-ring / gasket
is installed. If not possible, flush the system at is properly placed. After finger tightening O-ring
maximum flow setting equal to fully open valve. sealing requires 2-5 Nm torque.
Ensure that the valve is not in the fully closed
position when filling the system with water. EuroCone fittings will seal with FlowCon UniQ®
It is recommended that a strainer be installed and FlowCon Mini By-Pass without additional
prior to the valve body to prevent damage or sealing.
blockage due to debris.
O-rings:
Installation: Any O-ring (on valve, insert or accessory) is
INSTALL THE VALVE HOUSING WITH THE re-commended to be greased with silicone oil
FLOW DIRECTIONAL ARROW POINTING IN before installation. IMPORTANT: Never use mine-
THE CORRECT DIRECTION. Valves must be ral oil or petrol-based grease or oil on the O-
installed avoiding unnecessary pull or twist in rings.
the valve housing.
Pressure:
Thread Sealing: It is recommended to make some type of over-
For threaded connections please clear threads pressure limitation to avoid the inlet pressure
on both valve and piping of debris. FlowCon re- never exceeds the maximum operating pres-
commends thread sealant (Permabond A1044 sure. The valves shall be inspected for damage
or equivalent). When using Teflon tape, FlowCon after any overpressure condition.
WARRANTY:
Following recommendations will prolong valve Warranty is voided using other actuators than
life and give better functionality. supplied or recommended by FlowCon Interna-
tional.
Failure to abide by all recommendations as per
this General Instruction will void warranty. For any supplementary warranty obligations, plea-
se see the relevant product specific installation
and operation instruction.
Two different types of pressure/temperature fit- Capillary tube for PIM-DP (F212)
tings (p/t plugs) are available upon request for Capillary tube is supplied with fixed angled
valves with body tappings, i.e. p/t plugs with- 1/4” NPT fitting (F4039-14) at one end going
out collar and p/t plugs with collar. Suitable to the FlowCon Partner Globe with an adaptor
p/t plug choice will depend on the valve. Alterna- (ACC6584). The other tube end is to be as-
tive to p/t plugs, the valve body can be ordered sembled in the 1/4” NPT fitting already mounted
with plugs for the body tappings. Extended p/t on the FlowCon PIM-DP. Thread sealing is de-
plugs (without collar) are standard included with scribed elsewhere in this General Instruction.
FlowCon AHU and FlowCon Wafer.
FlowCon International assumes no responsibility for mistakes, if any, in any printed material.