PRELIMINARY CONSTRUCTION PROGRAMME FOR MTPC NEW FACTORY PROJECT

Rev04 ‐ 12 July 2017

ID Task Name Duration Start Finish %  June July August September October November December January F
Complete E B M E B M E B M E B M E B M E B M E B M E B M E B
1 MTPC ‐ CONSTRUCTION PROGRAMME 223 days Fri 16‐06‐17 Thu 25‐01‐18 25%
2 SIGNING CONTRACT 1 day Fri 16‐06‐17 Sat 17‐06‐17 100% SIGNING CONTRACT
3 SITE PREPARATION 8 days Fri 16‐06‐17 Sat 24‐06‐17 100%
4 Site Clearance 5 days Fri 16‐06‐17 Wed 21‐06‐17 100% Site Clearance
5 Site Installation 5 days Mon 19‐06‐17 Sat 24‐06‐17 100% Site Installation
6 ALL PILING WORKS 30 days Fri 16‐06‐17 Sun 16‐07‐17 100% ALL PILING WORKS
7 MAIN BUILDING (PHASE A) 212 days Sat 17‐06‐17 Mon 15‐01‐18 43%
8 Shop drawing for concrete work 60 days Sat 01‐07‐17 Wed 30‐08‐17 100% Shop drawing for concrete work
9 SUBSTRUCTURE 126 days Sun 16‐07‐17 Sun 19‐11‐17 65%
10 Pile cutting off 10 days Sun 16‐07‐17 Wed 26‐07‐17 100% Pile cutting off
11 Excavation 30 days Sun 16‐07‐17 Tue 15‐08‐17 100% Excavation
12 Lean concrete under pile cap 25 days Mon 17‐07‐17 Fri 11‐08‐17 100% Lean concrete under pile cap
13 Pile caps 30 days Sun 16‐07‐17 Tue 15‐08‐17 100% Pile caps
14 Back filling 30 days Tue 01‐08‐17 Thu 31‐08‐17 100% Back filling
15 Excavation for ground beam 21 days Thu 10‐08‐17 Thu 31‐08‐17 80% Excavation for ground beam
16 Lean concrete under ground beam 15 days Tue 15‐08‐17 Wed 30‐08‐17 80% Lean concrete under ground beam
17 Ground beam 20 days Wed 02‐08‐17 Mon 21‐08‐17 80% Ground beam
18 Sand & crush stone back filling 39 days Fri 01‐09‐17 Tue 10‐10‐17 0% Sand & crush stone back filling
19 Ground slab 40 days Tue 10‐10‐17 Sun 19‐11‐17 0% Ground slab
20 SUPERSTRUCTURE 7 days Tue 10‐10‐17 Tue 17‐10‐17 0%
21 Mezzanine Slab 7 days Tue 10‐10‐17 Tue 17‐10‐17 0% Mezzanine Slab
22 STEEL STRUCTURE 212 days Sat 17‐06‐17 Mon 15‐01‐18 18%
23 ENGINEERING 62 days Sat 17‐06‐17 Fri 18‐08‐17 62%
24 Approval/Engineering drawings with  15 days Sat 17‐06‐17 Sun 02‐07‐17 100% Approval/Engineering drawings with BOQ, Reaction Load Calculation
25 Shop drawings and approval 47 days Sun 02‐07‐17 Fri 18‐08‐17 50% Shop drawings and approval
26 PRODUCTION 15 days Fri 18‐08‐17 Sat 02‐09‐17 0% PRODUCTION
27 DELIVERY 7 days Sat 02‐09‐17 Sat 09‐09‐17 0% DELIVERY
28 ERECTION WORKS 114 days Sun 16‐07‐17 Tue 07‐11‐17 29%
29 Setting up anchor bolts, and waiting for 25 days Sun 16‐07‐17 Thu 10‐08‐17 100% Setting up anchor bolts, and waiting for casting concrete of foundation
30 Main Frame 27 days Wed 06‐09‐17 Tue 03‐10‐17 0% Main Frame
31 Roof Sheeting, Insulation, and Liner 12 days Wed 04‐10‐17 Mon 16‐10‐17 0% Roof Sheeting, Insulation, and Liner
32 Wall Sheeting, Insulation, and Liner 15 days Mon 16‐10‐17 Tue 31‐10‐17 0% Wall Sheeting, Insulation, and Liner
33 Finishing works 7 days Tue 31‐10‐17 Tue 07‐11‐17 0% Finishing works
34 ARCHITECTURAL WORKS 87 days Fri 20‐10‐17 Mon 15‐01‐18 0%
35 Ground Floor 87 days Fri 20‐10‐17 Mon 15‐01‐18 0%
36 Wall partitions 14 days Fri 20‐10‐17 Fri 03‐11‐17 0% Wall partitions
37 Plastering 14 days Fri 27‐10‐17 Fri 10‐11‐17 0% Plastering
38 Ceiling finishes 14 days Fri 10‐11‐17 Fri 24‐11‐17 0% Ceiling finishes
39 Door & window installation 7 days Fri 17‐11‐17 Fri 24‐11‐17 0% Door & window installation
40 Wall tiles & skirting 7 days Fri 24‐11‐17 Fri 01‐12‐17 0% Wall tiles & skirting
41 Floor finishes 20 days Fri 01‐12‐17 Thu 21‐12‐17 0% Floor finishes
42 Painting 25 days Thu 21‐12‐17 Mon 15‐01‐18 0% Painting
43 Mezzanine Floor 62 days Fri 03‐11‐17 Thu 04‐01‐18 0%
44 Wall partitions 14 days Fri 03‐11‐17 Fri 17‐11‐17 0% Wall partitions
45 Plastering 7 days Fri 10‐11‐17 Fri 17‐11‐17 0% Plastering
46 Ceiling finishes 14 days Fri 17‐11‐17 Fri 01‐12‐17 0% Ceiling finishes
47 Door & window installation 7 days Fri 24‐11‐17 Fri 01‐12‐17 0% Door & window installation
48 Wall tiles & skirting 7 days Fri 01‐12‐17 Fri 08‐12‐17 0% Wall tiles & skirting
49 Floor finishes 15 days Fri 08‐12‐17 Sat 23‐12‐17 0% Floor finishes
50 Painting 14 days Thu 21‐12‐17 Thu 04‐01‐18 0% Painting
51 EXTERNAL WORKS (PHASE A) 174 days Wed 26‐07‐17 Tue 16‐01‐18 11%
52 MAIN GATE 55 days Wed 26‐07‐17 Tue 19‐09‐17 45%
53 Structural Works 22 days Wed 26‐07‐17 Thu 17‐08‐17 100%
54 Pile cutting off 2 days Wed 26‐07‐17 Fri 28‐07‐17 100% Pile cutting off
55 Excavation 2 days Thu 27‐07‐17 Sat 29‐07‐17 100% Excavation
56 Pile caps 5 days Fri 28‐07‐17 Wed 02‐08‐17 100% Pile caps
57 Excavation for ground beam 2 days Tue 01‐08‐17 Thu 03‐08‐17 100% Excavation for ground beam
58 Back filling 3 days Mon 07‐08‐17 Thu 10‐08‐17 100% Back filling
59 Ground beam & slab, concrete slope 15 days Wed 02‐08‐17 Thu 17‐08‐17 100% Ground beam & slab, concrete slope
60 Architectural Works 33 days Thu 17‐08‐17 Tue 19‐09‐17 0%
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline
Split External Tasks Inactive Summary Manual Summary Progress
Project: MTPC NEW FACTORY PROJECT
Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

This programme is for estimation only. LBL International reserves the rights to change the programme to suit actual condition on site/ avaiability of materials, goods for construction drawing/ site construction/ etc... Page 1
PRELIMINARY CONSTRUCTION PROGRAMME FOR MTPC NEW FACTORY PROJECT
Rev04 ‐ 12 July 2017

ID Task Name Duration Start Finish %  June July August September October November December January F
Complete E B M E B M E B M E B M E B M E B M E B M E B M E B
61 Wall partitions 5 days Thu 17‐08‐17 Tue 22‐08‐17 0% Wall partitions
62 Plastering 5 days Tue 22‐08‐17 Sun 27‐08‐17 0% Plastering
63 Ceiling finishes 5 days Sun 27‐08‐17 Fri 01‐09‐17 0% Ceiling finishes
64 Door & window installation 2 days Wed 30‐08‐17 Fri 01‐09‐17 0% Door & window installation
65 Wall tiles & skirting 3 days Fri 01‐09‐17 Mon 04‐09‐17 0% Wall tiles & skirting
66 Floor finishes 5 days Mon 04‐09‐17 Sat 09‐09‐17 0% Floor finishes
67 Painting 10 days Sat 09‐09‐17 Tue 19‐09‐17 0% Painting
68 WATER TANK 25 days Thu 17‐08‐17 Mon 11‐09‐17 41%
69 Excavation 3 days Thu 17‐08‐17 Sun 20‐08‐17 100% Excavation
70 Sand and crush stone compaction 3 days Mon 21‐08‐17 Thu 24‐08‐17 100% Sand and crush stone compaction
71 Concrete for bottom slab 3 days Wed 23‐08‐17 Sat 26‐08‐17 100% Concrete for bottom slab
72 Concrete for wall 5 days Sun 27‐08‐17 Fri 01‐09‐17 0% Concrete for wall
73 Concrete for top slab 5 days Sat 02‐09‐17 Thu 07‐09‐17 0% Concrete for top slab
74 Back filling 3 days Fri 08‐09‐17 Mon 11‐09‐17 0% Back filling
75 SEPTIC TANK 10M3 27 days Mon 21‐08‐17 Sun 17‐09‐17 0%
76 Excavation 3 days Mon 21‐08‐17 Thu 24‐08‐17 0% Excavation
77 Sand and crush stone compaction 3 days Fri 25‐08‐17 Mon 28‐08‐17 0% Sand and crush stone compaction
78 Concrete for bottom slab 3 days Tue 29‐08‐17 Fri 01‐09‐17 0% Concrete for bottom slab
79 Concrete for wall 5 days Sat 02‐09‐17 Thu 07‐09‐17 0% Concrete for wall
80 Concrete for top slab 5 days Fri 08‐09‐17 Wed 13‐09‐17 0% Concrete for top slab
81 Back filling 3 days Thu 14‐09‐17 Sun 17‐09‐17 0% Back filling
82 SEPTIC TANK PREFABRICATE 6 days Sat 26‐08‐17 Fri 01‐09‐17 0%
83 Excavation 2 days Sat 26‐08‐17 Mon 28‐08‐17 0% Excavation
84 Septic tank installation 2 days Mon 28‐08‐17 Wed 30‐08‐17 0% Septic tank installation
85 Back filling 2 days Wed 30‐08‐17 Fri 01‐09‐17 0% Back filling
86 SUB GATE 10 days Tue 19‐09‐17 Fri 29‐09‐17 0%
87 Substructural works (Excavation,  5 days Tue 19‐09‐17 Sun 24‐09‐17 0% Substructural works (Excavation, compaction)
88 Concrete slope 5 days Sun 24‐09‐17 Fri 29‐09‐17 0% Concrete slope
89 CAR PARKING 16 days Fri 29‐09‐17 Sun 15‐10‐17 0%
90 Footing 7 days Fri 29‐09‐17 Fri 06‐10‐17 0% Footing
91 Concrete curb 7 days Fri 06‐10‐17 Fri 13‐10‐17 0% Concrete curb
92 Steel Structural Works 10 days Thu 05‐10‐17 Sun 15‐10‐17 0% Steel Structural Works
93 HARDSCAPE 34 days Sun 15‐10‐17 Sat 18‐11‐17 0%
94 Concrete curb & plinth 14 days Sun 15‐10‐17 Sun 29‐10‐17 0% Concrete curb & plinth
95 Rainwater bath and grating 5 days Tue 24‐10‐17 Sun 29‐10‐17 0% Rainwater bath and grating
96 Trees & Shrubs 20 days Sun 29‐10‐17 Sat 18‐11‐17 0% Trees & Shrubs
97 FLAT 10 days Mon 13‐11‐17 Thu 23‐11‐17 0%
98 Flat Foundation 5 days Mon 13‐11‐17 Sat 18‐11‐17 0% Flat Foundation
99 Flat pole installation 5 days Sat 18‐11‐17 Thu 23‐11‐17 0% Flat pole installation
100 ASPHALT ROAD WAY 40 days Thu 23‐11‐17 Tue 02‐01‐18 0%
101 Asphalt concrete 40 days Thu 23‐11‐17 Tue 02‐01‐18 0% Asphalt concrete
102 DECORATED FENCE 40 days Thu 23‐11‐17 Tue 02‐01‐18 0% DECORATED FENCE
103 SIMPLE FENCE 35 days Tue 05‐12‐17 Tue 09‐01‐18 0% SIMPLE FENCE
104 BACK FENCE 35 days Tue 12‐12‐17 Tue 16‐01‐18 0% BACK FENCE
105 INTERIOR WORKS (PHASE B) 132 days Tue 22‐08‐17 Mon 01‐01‐18 0%
106 Wall partitions 15 days Tue 22‐08‐17 Wed 06‐09‐17 0% Wall partitions
107 Ceiling finishes 15 days Wed 06‐09‐17 Thu 21‐09‐17 0% Ceiling finishes
108 Wall tiles & skirting 7 days Thu 21‐09‐17 Thu 28‐09‐17 0% Wall tiles & skirting
109 Floor finishes 35 days Thu 28‐09‐17 Thu 02‐11‐17 0% Floor finishes
110 Painting 15 days Thu 02‐11‐17 Fri 17‐11‐17 0% Painting
111 Curved green wall 45 days Fri 17‐11‐17 Mon 01‐01‐18 0% Curved green wall
112 CLOSE‐OUT 30 days Sun 17‐12‐17 Tue 16‐01‐18 0%
113 Snaging and Cleaning 30 days Sun 17‐12‐17 Tue 16‐01‐18 0% Snaging and Cleaning
114 MEP WORKS 209 days Fri 30‐06‐17 Thu 25‐01‐18 23%
115 Award, Mobilization and Pre engineering 10 days Fri 30‐06‐17 Mon 10‐07‐17 100%
116 MEP Award and Mobilisation  5 days Fri 30‐06‐17 Wed 05‐07‐17 100% MEP Award and Mobilisation 
117 Receipt of ACMV design drawings and  1 day Fri 30‐06‐17 Sat 01‐07‐17 100% Receipt of ACMV design drawings and specifications
118 Receipt of electrical design drawings and  1 day Fri 30‐06‐17 Sat 01‐07‐17 100% Receipt of electrical design drawings and specifications
119 Receipt of plumbing design drawings and  1 day Fri 30‐06‐17 Sat 01‐07‐17 100% Receipt of plumbing design drawings and specifications
120 Receipt of fire protection design drawings 1 day Fri 30‐06‐17 Sat 01‐07‐17 100% Receipt of fire protection design drawings and specifications 

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Split External Tasks Inactive Summary Manual Summary Progress
Project: MTPC NEW FACTORY PROJECT
Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

This programme is for estimation only. LBL International reserves the rights to change the programme to suit actual condition on site/ avaiability of materials, goods for construction drawing/ site construction/ etc... Page 2
PRELIMINARY CONSTRUCTION PROGRAMME FOR MTPC NEW FACTORY PROJECT
Rev04 ‐ 12 July 2017

ID Task Name Duration Start Finish %  June July August September October November December January F
Complete E B M E B M E B M E B M E B M E B M E B M E B M E B
121 Engineering review of design drawings 5 days Wed 05‐07‐17 Mon 10‐07‐17 100% Engineering review of design drawings
122 Engineering 56 days Mon 10‐07‐17 Mon 04‐09‐17 74%
123 Material submission and Approval 56 days Mon 10‐07‐17 Mon 04‐09‐17 77%
124 Submission 41 days Mon 10‐07‐17 Sun 20‐08‐17 85%
125 Submission of MVAC materials 11 days Mon 10‐07‐17 Fri 21‐07‐17 100%
134 Submission of Electrical  materials 25 days Mon 10‐07‐17 Fri 04‐08‐17 85%
135 HDPE pipe & Fittings 3 days Mon 10‐07‐17 Thu 13‐07‐17 100% HDPE pipe & Fittings
136 uPVC conduits & Fittings 3 days Mon 10‐07‐17 Thu 13‐07‐17 100% uPVC conduits & Fittings
137 Wireway 3 days Mon 10‐07‐17 Thu 13‐07‐17 100% Wireway
138 Earthing Suystem 7 days Fri 14‐07‐17 Fri 21‐07‐17 100% Earthing Suystem
139 LV Cable 7 days Fri 14‐07‐17 Fri 21‐07‐17 100% LV Cable
140 Lightning Protection systems 7 days Fri 14‐07‐17 Fri 21‐07‐17 100% Lightning Protection systems
141 Lighting Fixtures 7 days Fri 21‐07‐17 Fri 28‐07‐17 100% Lighting Fixtures
142 Wiring Devices 7 days Fri 21‐07‐17 Fri 28‐07‐17 0% Wiring Devices
143 LV Distribution Boards 7 days Fri 21‐07‐17 Fri 28‐07‐17 0% LV Distribution Boards
144 ELV Cables 1 day Thu 20‐07‐17 Fri 21‐07‐17 100% ELV Cables
145 Fire Alarm Systems 1 day Thu 20‐07‐17 Fri 21‐07‐17 100% Fire Alarm Systems
146 Telephone and Data Equipment 1 day Thu 20‐07‐17 Fri 21‐07‐17 100% Telephone and Data Equipment
147 Access control System 7 days Fri 21‐07‐17 Fri 28‐07‐17 100% Access control System
148 Instruction Alarm System 7 days Fri 21‐07‐17 Fri 28‐07‐17 100% Instruction Alarm System
149 Finger Print 7 days Fri 21‐07‐17 Fri 28‐07‐17 100% Finger Print
150 CCTV System 7 days Fri 28‐07‐17 Fri 04‐08‐17 100% CCTV System
151 Public Address Systems 7 days Fri 28‐07‐17 Fri 04‐08‐17 100% Public Address Systems
152 MATV 7 days Fri 28‐07‐17 Fri 04‐08‐17 100% MATV
153 Submission of Plumbing materials 41 days Mon 10‐07‐17 Sun 20‐08‐17 59%
154 HDPE pipe & Fittings 3 days Mon 10‐07‐17 Thu 13‐07‐17 100% HDPE pipe & Fittings
155 uPVC pipes &Fitings 3 days Mon 10‐07‐17 Thu 13‐07‐17 100% uPVC pipes &Fitings
156 PPR pipes &Fittings 3 days Mon 10‐07‐17 Thu 13‐07‐17 100% PPR pipes &Fittings
157 Valves (Gate valve, check valve,  7 days Fri 14‐07‐17 Fri 21‐07‐17 100% Valves (Gate valve, check valve, strainer, ball)
158 Irrigation pump &Transfer Pump 28 days Fri 21‐07‐17 Fri 18‐08‐17 100% Irrigation pump &Transfer Pump
159 Irrigation Sprinkler 30 days Fri 21‐07‐17 Sun 20‐08‐17 0% Irrigation Sprinkler
160 Submission of Fire Fighting   39 days Mon 10‐07‐17 Fri 18‐08‐17 100%
165 Approval 53 days Thu 13‐07‐17 Mon 04‐09‐17 72%
166 Approval of MVAC materials 23 days Thu 13‐07‐17 Sat 05‐08‐17 100%
167 PVC Condensate Pipes &Fitting 15 days Thu 13‐07‐17 Fri 28‐07‐17 100% PVC Condensate Pipes &Fitting
168 Copper pipes 15 days Thu 13‐07‐17 Fri 28‐07‐17 100% Copper pipes
169 Closed Cell Rubber Insulation 15 days Thu 13‐07‐17 Fri 28‐07‐17 100% Closed Cell Rubber Insulation
170 Galvanized Air Duct 15 days Thu 13‐07‐17 Fri 28‐07‐17 100% Galvanized Air Duct
171 MPS Evaporative Cooler and Air  15 days Fri 21‐07‐17 Sat 05‐08‐17 100% MPS Evaporative Cooler and Air Circulating Fan
172 Grilles and Diffusers & Damper 15 days Fri 21‐07‐17 Sat 05‐08‐17 100% Grilles and Diffusers & Damper
173 Ventilation Fans 15 days Fri 21‐07‐17 Sat 05‐08‐17 100% Ventilation Fans
174 AC units 7 days Fri 21‐07‐17 Fri 28‐07‐17 100% AC units
175 Approval of Electrical  materials 37 days Thu 13‐07‐17 Sat 19‐08‐17 67%
176 HDPE pipe & Fittings 15 days Thu 13‐07‐17 Fri 28‐07‐17 100% HDPE pipe & Fittings
177 uPVC conduits & Fittings 15 days Thu 13‐07‐17 Fri 28‐07‐17 100% uPVC conduits & Fittings
178 Wireway 15 days Thu 13‐07‐17 Fri 28‐07‐17 100% Wireway
179 Earthing Suystem 15 days Fri 21‐07‐17 Sat 05‐08‐17 100% Earthing Suystem
180 LV Cable 15 days Fri 21‐07‐17 Sat 05‐08‐17 100% LV Cable
181 Lightning Protection systems 15 days Fri 21‐07‐17 Sat 05‐08‐17 100% Lightning Protection systems
182 Lighting Fixtures 15 days Fri 28‐07‐17 Sat 12‐08‐17 0% Lighting Fixtures
183 Wiring Devices 15 days Fri 28‐07‐17 Sat 12‐08‐17 0% Wiring Devices
184 LV Distribution Boards 15 days Fri 28‐07‐17 Sat 12‐08‐17 0% LV Distribution Boards
185 ELV Cables 15 days Fri 21‐07‐17 Sat 05‐08‐17 100% ELV Cables
186 Fire Alarm Systems 15 days Fri 21‐07‐17 Sat 05‐08‐17 100% Fire Alarm Systems
187 Telephone and Data Equipment 15 days Fri 21‐07‐17 Sat 05‐08‐17 0% Telephone and Data Equipment
188 Access control System 15 days Fri 28‐07‐17 Sat 12‐08‐17 0% Access control System
189 Instruction Alarm System 15 days Fri 28‐07‐17 Sat 12‐08‐17 0% Instruction Alarm System
190 Finger Print 15 days Fri 28‐07‐17 Sat 12‐08‐17 100% Finger Print
191 CCTV System 15 days Fri 04‐08‐17 Sat 19‐08‐17 100% CCTV System
192 Public Address Systems 15 days Fri 04‐08‐17 Sat 19‐08‐17 100% Public Address Systems

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Split External Tasks Inactive Summary Manual Summary Progress
Project: MTPC NEW FACTORY PROJECT
Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

This programme is for estimation only. LBL International reserves the rights to change the programme to suit actual condition on site/ avaiability of materials, goods for construction drawing/ site construction/ etc... Page 3
PRELIMINARY CONSTRUCTION PROGRAMME FOR MTPC NEW FACTORY PROJECT
Rev04 ‐ 12 July 2017

ID Task Name Duration Start Finish %  June July August September October November December January F
Complete E B M E B M E B M E B M E B M E B M E B M E B M E B
193 MATV 15 days Fri 04‐08‐17 Sat 19‐08‐17 100% MATV
194 Approval of Plumbing materials 53 days Thu 13‐07‐17 Mon 04‐09‐17 62%
195 HDPE pipe & Fittings 15 days Thu 13‐07‐17 Fri 28‐07‐17 100% HDPE pipe & Fittings
196 uPVC pipes &Fitings 15 days Thu 13‐07‐17 Fri 28‐07‐17 100% uPVC pipes &Fitings
197 PPR pipes &Fittings 15 days Thu 13‐07‐17 Fri 28‐07‐17 100% PPR pipes &Fittings
198 Valves (Gate valve, check valve,  15 days Fri 21‐07‐17 Sat 05‐08‐17 0% Valves (Gate valve, check valve, strainer, ball)
199 Roof drain, Floor drain, Vent  15 days Fri 21‐07‐17 Sat 05‐08‐17 100% Roof drain, Floor drain, Vent cap&floor clean
200 Irrigation pump &Transfer Pump 7 days Fri 18‐08‐17 Fri 25‐08‐17 0% Irrigation pump &Transfer Pump
201 Irrigation Sprinkler 15 days Sun 20‐08‐17 Mon 04‐09‐17 0% Irrigation Sprinkler
202 Approval of Fire Fighting  materials 43 days Thu 13‐07‐17 Fri 25‐08‐17 58%
203 Steel pipes & Fittings 15 days Thu 13‐07‐17 Fri 28‐07‐17 100% Steel pipes & Fittings
204 Fire fighting Valves 15 days Fri 28‐07‐17 Sat 12‐08‐17 0% Fire fighting Valves
205 Fire Hose reels 15 days Tue 18‐07‐17 Wed 02‐08‐17 100% Fire Hose reels
206 Fire Pumps 7 days Fri 18‐08‐17 Fri 25‐08‐17 0% Fire Pumps
207 Shop Drawing approval and Submittals 50 days Mon 10‐07‐17 Tue 29‐08‐17 63%
208 Submission 35 days Mon 10‐07‐17 Mon 14‐08‐17 80%
209 Submission of MVAC drawings 25 days Mon 10‐07‐17 Fri 04‐08‐17 100% Submission of MVAC drawings
210 Submission of Electrical drawings 35 days Mon 10‐07‐17 Mon 14‐08‐17 40% Submission of Electrical drawings
211 Submission of Plumbing drawings 25 days Mon 10‐07‐17 Fri 04‐08‐17 95% Submission of Plumbing drawings
212 Submission of Fire fighting drawings 25 days Mon 10‐07‐17 Fri 04‐08‐17 100% Submission of Fire fighting drawings
213 Approval 25 days Fri 04‐08‐17 Tue 29‐08‐17 33%
214 Approval of MVAC drawings 15 days Fri 04‐08‐17 Sat 19‐08‐17 0% Approval of MVAC drawings
215 Approval of Electrical drawings 15 days Mon 14‐08‐17 Tue 29‐08‐17 10% Approval of Electrical drawings
216  Approval of Plumbing drawings 15 days Fri 04‐08‐17 Sat 19‐08‐17 20% Approval of Plumbing drawings
217 Approval of Fire fighting drawings 15 days Fri 04‐08‐17 Sat 19‐08‐17 100% Approval of Fire fighting drawings
218 Procurement and delivery 123 days Fri 28‐07‐17 Tue 28‐11‐17 3%
219 ELECTRICAL MATERIAL 90 days Fri 28‐07‐17 Thu 26‐10‐17 4%
220 HDPE pipe & Fittings 30 days Fri 28‐07‐17 Sun 27‐08‐17 100% HDPE pipe & Fittings
221 uPVC conduits & Fittings 30 days Fri 28‐07‐17 Sun 27‐08‐17 40% uPVC conduits & Fittings
222 Wireway 40 days Fri 28‐07‐17 Wed 06‐09‐17 0% Wireway
223 Earthing System 25 days Sat 05‐08‐17 Wed 30‐08‐17 0% Earthing System
224 LV Cable 60 days Sat 05‐08‐17 Wed 04‐10‐17 0% LV Cable
225 Lightning Protection systems 30 days Sat 05‐08‐17 Mon 04‐09‐17 0% Lightning Protection systems
226 Lighting Fixtures 45 days Sat 12‐08‐17 Tue 26‐09‐17 0% Lighting Fixtures
227 Wiring Devices 60 days Sat 12‐08‐17 Wed 11‐10‐17 0% Wiring Devices
228 LV Distribution Boards 75 days Sat 12‐08‐17 Thu 26‐10‐17 0% LV Distribution Boards
229 ELV Cables 70 days Sat 05‐08‐17 Sat 14‐10‐17 0% ELV Cables
230 Fire Alarm Systems 70 days Sat 05‐08‐17 Sat 14‐10‐17 0% Fire Alarm Systems
231 Telephone and Data Equipment 75 days Sat 05‐08‐17 Thu 19‐10‐17 0% Telephone and Data Equipment
232 Access control System 60 days Sat 12‐08‐17 Wed 11‐10‐17 0% Access control System
233 Instruction Alarm System 60 days Sat 12‐08‐17 Wed 11‐10‐17 0% Instruction Alarm System
234 Finger Print 60 days Sat 12‐08‐17 Wed 11‐10‐17 0% Finger Print
235 CCTV System 55 days Sat 19‐08‐17 Fri 13‐10‐17 0% CCTV System
236 Public Address Systems 60 days Sat 19‐08‐17 Wed 18‐10‐17 0% Public Address Systems
237 MATV 60 days Sat 19‐08‐17 Wed 18‐10‐17 0% MATV
238 MVAC MATERIALS 83 days Fri 28‐07‐17 Thu 19‐10‐17 0%
239 PVC Condensate Pipes &Fitting 20 days Fri 28‐07‐17 Thu 17‐08‐17 0% PVC Condensate Pipes &Fitting
240 Copper pipes 20 days Fri 28‐07‐17 Thu 17‐08‐17 0% Copper pipes
241 Closed Cell Rubber Insulation 20 days Fri 28‐07‐17 Thu 17‐08‐17 0% Closed Cell Rubber Insulation
242 Galvanized Air Duct 30 days Fri 28‐07‐17 Sun 27‐08‐17 0% Galvanized Air Duct
243 MPS Evaporative Cooler and Air  75 days Sat 05‐08‐17 Thu 19‐10‐17 0% MPS Evaporative Cooler and Air Circulating Fan
244 Grilles and Diffusers & Damper 55 days Sat 05‐08‐17 Fri 29‐09‐17 0% Grilles and Diffusers & Damper
245 Ventilation Fans 60 days Sat 05‐08‐17 Wed 04‐10‐17 0% Ventilation Fans
246 AC units 75 days Fri 28‐07‐17 Wed 11‐10‐17 0% AC units
247 FIRE SYSTEMS MATERIALS 123 days Fri 28‐07‐17 Tue 28‐11‐17 0%
248 Steel pipes & Fittings 30 days Fri 28‐07‐17 Sun 27‐08‐17 0% Steel pipes & Fittings
249 Fire fighting Valves 60 days Sat 12‐08‐17 Wed 11‐10‐17 0% Fire fighting Valves
250 Fire Hose reels 90 days Fri 25‐08‐17 Thu 23‐11‐17 0% Fire Hose reels
251 Fire Pumps 95 days Fri 25‐08‐17 Tue 28‐11‐17 0% Fire Pumps
252 PLUMBING MATERIALS 123 days Fri 28‐07‐17 Tue 28‐11‐17 3%
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline
Split External Tasks Inactive Summary Manual Summary Progress
Project: MTPC NEW FACTORY PROJECT
Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

This programme is for estimation only. LBL International reserves the rights to change the programme to suit actual condition on site/ avaiability of materials, goods for construction drawing/ site construction/ etc... Page 4
PRELIMINARY CONSTRUCTION PROGRAMME FOR MTPC NEW FACTORY PROJECT
Rev04 ‐ 12 July 2017

ID Task Name Duration Start Finish %  June July August September October November December January F
Complete E B M E B M E B M E B M E B M E B M E B M E B M E B
253 HDPE pipe & Fittings 20 days Fri 28‐07‐17 Thu 17‐08‐17 0% HDPE pipe & Fittings
254 uPVC pipes &Fitings 20 days Fri 28‐07‐17 Thu 17‐08‐17 40% uPVC pipes &Fitings
255 PPR pipes &Fittings 20 days Fri 28‐07‐17 Thu 17‐08‐17 0% PPR pipes &Fittings
256 Valves (Gate valve, check valve,  60 days Sat 05‐08‐17 Wed 04‐10‐17 0% Valves (Gate valve, check valve, strainer, ball)
257 Roof drain, Floor drain, Vent cap&floor  50 days Sat 05‐08‐17 Sun 24‐09‐17 0% Roof drain, Floor drain, Vent cap&floor clean
258 Irrigation pump &Transfer Pump 95 days Fri 25‐08‐17 Tue 28‐11‐17 0% Irrigation pump &Transfer Pump
259 Irrigation Sprinkler 35 days Mon 04‐09‐17 Mon 09‐10‐17 0% Irrigation Sprinkler
260 Installation of MEP sevices 161 days Thu 17‐08‐17 Thu 25‐01‐18 0%
261 LV Services 148 days Wed 30‐08‐17 Thu 25‐01‐18 0%
262 1st fix 85 days Wed 30‐08‐17 Thu 23‐11‐17 0%
263 Ground Floor 85 days Wed 30‐08‐17 Thu 23‐11‐17 0%
264 Install Earthing systems 15 days Wed 30‐08‐17 Thu 14‐09‐17 0% Install Earthing systems
265 Install Lightning System  15 days Mon 16‐10‐17 Tue 31‐10‐17 0% Install Lightning System 
266 Installation of conduits 20 days Fri 03‐11‐17 Thu 23‐11‐17 0% Installation of conduits
267 Installation of cable tray 15 days Tue 17‐10‐17 Wed 01‐11‐17 0% Installation of cable tray
268 Mezzanine 36 days Tue 17‐10‐17 Wed 22‐11‐17 0%
269 Installation of conduits 5 days Fri 17‐11‐17 Wed 22‐11‐17 0% Installation of conduits
270 Installation of cable tray 10 days Tue 17‐10‐17 Fri 27‐10‐17 0% Installation of cable tray
271 2nd fix 15 days Thu 23‐11‐17 Fri 08‐12‐17 0%
272 Ground Floor 15 days Thu 23‐11‐17 Fri 08‐12‐17 0%
273 Wiring , Cabling and Termination 15 days Thu 23‐11‐17 Fri 08‐12‐17 0% Wiring , Cabling and Termination
274 Mezzanine 10 days Thu 23‐11‐17 Sun 03‐12‐17 0%
275 Wiring , Cabling and Termination 10 days Thu 23‐11‐17 Sun 03‐12‐17 0% Wiring , Cabling and Termination
276 3rd fix  55 days Fri 01‐12‐17 Thu 25‐01‐18 0%
277 Ground Floor 48 days Fri 08‐12‐17 Thu 25‐01‐18 0%
278 Installation of wiring devices and  10 days Mon 15‐01‐18 Thu 25‐01‐18 0% Installation of
279 Installation of Light Fixture and  10 days Mon 15‐01‐18 Thu 25‐01‐18 0% Installation of
280 Installation of DB including  15 days Fri 08‐12‐17 Sat 23‐12‐17 0% Installation of DB including termination
281 Mezzanine 39 days Fri 01‐12‐17 Tue 09‐01‐18 0%
282 Installation of wiring devices and  5 days Thu 04‐01‐18 Tue 09‐01‐18 0% Installation of wiring device
283 Installation of Light Fixture and  5 days Fri 01‐12‐17 Wed 06‐12‐17 0% Installation of Light Fixture and termination
284 ELV Service 54 days Fri 03‐11‐17 Wed 27‐12‐17 0%
285 1st Fix 29 days Fri 03‐11‐17 Sat 02‐12‐17 0%
286 Ground Floor 15 days Fri 03‐11‐17 Sat 18‐11‐17 0%
287 Install support and Conduit 15 days Fri 03‐11‐17 Sat 18‐11‐17 0% Install support and Conduit
288 Mezzanine 10 days Wed 22‐11‐17 Sat 02‐12‐17 0%
289 Install support and Conduit 10 days Wed 22‐11‐17 Sat 02‐12‐17 0% Install support and Conduit
290 2nd fix 19 days Sat 18‐11‐17 Thu 07‐12‐17 0%
291 Ground Floor 10 days Sat 18‐11‐17 Tue 28‐11‐17 0%
292 Installation of wiring devices  and  10 days Sat 18‐11‐17 Tue 28‐11‐17 0% Installation of wiring devices  and termination
293 Mezzanine 5 days Sat 02‐12‐17 Thu 07‐12‐17 0%
294 Installation of wiring devices  and  5 days Sat 02‐12‐17 Thu 07‐12‐17 0% Installation of wiring devices  and termination
295 3rd fix  20 days Thu 07‐12‐17 Wed 27‐12‐17 0%
296 Ground Floor 10 days Thu 07‐12‐17 Sun 17‐12‐17 0%
297 Install Access Control 5 days Thu 07‐12‐17 Tue 12‐12‐17 0% Install Access Control
298 Install Instrusion 5 days Thu 07‐12‐17 Tue 12‐12‐17 0% Install Instrusion
299 Install Fire Alarm  5 days Thu 07‐12‐17 Tue 12‐12‐17 0% Install Fire Alarm 
300 Install CCTV 5 days Thu 07‐12‐17 Tue 12‐12‐17 0% Install CCTV
301 Install MATV 5 days Tue 12‐12‐17 Sun 17‐12‐17 0% Install MATV
302 Install PA 5 days Tue 12‐12‐17 Sun 17‐12‐17 0% Install PA
303 Install Finger Print 5 days Tue 12‐12‐17 Sun 17‐12‐17 0% Install Finger Print
304 Install Telephone and Data 5 days Tue 12‐12‐17 Sun 17‐12‐17 0% Install Telephone and Data
305 Mezzanine 10 days Sun 17‐12‐17 Wed 27‐12‐17 0%
306 Install Access Control 5 days Sun 17‐12‐17 Fri 22‐12‐17 0% Install Access Control
307 Install Instrusion 5 days Sun 17‐12‐17 Fri 22‐12‐17 0% Install Instrusion
308 Install Fire Alarm  5 days Sun 17‐12‐17 Fri 22‐12‐17 0% Install Fire Alarm 
309 Install Fire Alarm  5 days Sun 17‐12‐17 Fri 22‐12‐17 0% Install Fire Alarm 
310 Install CCTV 5 days Fri 22‐12‐17 Wed 27‐12‐17 0% Install CCTV
311 Install MATV 5 days Fri 22‐12‐17 Wed 27‐12‐17 0% Install MATV
312 Install PA 5 days Fri 22‐12‐17 Wed 27‐12‐17 0% Install PA

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Split External Tasks Inactive Summary Manual Summary Progress
Project: MTPC NEW FACTORY PROJECT
Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

This programme is for estimation only. LBL International reserves the rights to change the programme to suit actual condition on site/ avaiability of materials, goods for construction drawing/ site construction/ etc... Page 5
PRELIMINARY CONSTRUCTION PROGRAMME FOR MTPC NEW FACTORY PROJECT
Rev04 ‐ 12 July 2017

ID Task Name Duration Start Finish %  June July August September October November December January F
Complete E B M E B M E B M E B M E B M E B M E B M E B M E B
313 Install Telephone and Data 5 days Fri 22‐12‐17 Wed 27‐12‐17 0% Install Telephone and Data
314 MVAC SERVICES 41 days Tue 17‐10‐17 Mon 27‐11‐17 0%
315 1st fix 12 days Tue 17‐10‐17 Sun 29‐10‐17 0%
316 Ground Floor 10 days Tue 17‐10‐17 Fri 27‐10‐17 0%
317 Install Supports  & Copper Pipes 10 days Tue 17‐10‐17 Fri 27‐10‐17 0% Install Supports  & Copper Pipes
318 Install Support &  Ducts 10 days Tue 17‐10‐17 Fri 27‐10‐17 0% Install Support &  Ducts
319 Install Support & Condensate  5 days Tue 17‐10‐17 Sun 22‐10‐17 0% Install Support & Condensate Drain pipe
320 Mezzanine Floor 12 days Tue 17‐10‐17 Sun 29‐10‐17 0%
321 Install Support & Copper Pipes 12 days Tue 17‐10‐17 Sun 29‐10‐17 0% Install Support & Copper Pipes
322 Install Support &  Ducts 5 days Tue 17‐10‐17 Sun 22‐10‐17 0% Install Support &  Ducts
323 Install Support & Condensate  5 days Tue 17‐10‐17 Sun 22‐10‐17 0% Install Support & Condensate Drain pipe
324 2nd fix 22 days Tue 17‐10‐17 Wed 08‐11‐17 0%
325 Ground Floor 12 days Fri 27‐10‐17 Wed 08‐11‐17 0%
326 Install fans & Plenum Box c/w  12 days Fri 27‐10‐17 Wed 08‐11‐17 0% Install fans & Plenum Box c/w Flexible Duct
327 Install AC Unit ( Cassette ) 5 days Fri 27‐10‐17 Wed 01‐11‐17 0% Install AC Unit ( Cassette )
328 Mezzanine Floor 10 days Tue 17‐10‐17 Fri 27‐10‐17 0%
329 Install Fans & Plenum Box c/w  5 days Sun 22‐10‐17 Fri 27‐10‐17 0% Install Fans & Plenum Box c/w Flexible Duct
330 Install AC Unit ( Cassette)  10 days Tue 17‐10‐17 Fri 27‐10‐17 0% Install AC Unit ( Cassette) 
331 3rd fix  31 days Fri 27‐10‐17 Mon 27‐11‐17 0%
332 Ground Floor 3 days Fri 24‐11‐17 Mon 27‐11‐17 0%
333 Install Grilles and Diffusers 3 days Fri 24‐11‐17 Mon 27‐11‐17 0% Install Grilles and Diffusers
334 Install AC Unit Cover ( Cassette) 3 days Fri 24‐11‐17 Mon 27‐11‐17 0% Install AC Unit Cover ( Cassette)
335 Mezzanine Floor 3 days Fri 27‐10‐17 Mon 30‐10‐17 0%
336 Install Grilles and Diffusers 3 days Fri 27‐10‐17 Mon 30‐10‐17 0% Install Grilles and Diffusers
337 Install AC Unit Cover ( Cassette) 3 days Fri 27‐10‐17 Mon 30‐10‐17 0% Install AC Unit Cover ( Cassette)
338 FIRE SERVIVES 47 days Tue 17‐10‐17 Sun 03‐12‐17 0%
339 1st fix 20 days Tue 17‐10‐17 Mon 06‐11‐17 0%
340 Install Support & FF pipes 20 days Tue 17‐10‐17 Mon 06‐11‐17 0% Install Support & FF pipes
341 2nd fix 5 days Mon 06‐11‐17 Sat 11‐11‐17 0%
342 FF Pipe Pressure Testing 5 days Mon 06‐11‐17 Sat 11‐11‐17 0% FF Pipe Pressure Testing
343 3rd fix  10 days Thu 23‐11‐17 Sun 03‐12‐17 0%
344 Install Hose Reel 10 days Thu 23‐11‐17 Sun 03‐12‐17 0% Install Hose Reel
345 PLUMBING SERVICES 121 days Thu 17‐08‐17 Sat 16‐12‐17 0%
346 1st fix 81 days Thu 17‐08‐17 Mon 06‐11‐17 0%
347 Underground Work 20 days Thu 17‐08‐17 Wed 06‐09‐17 0%
348 Install Sawage pipe  20 days Thu 17‐08‐17 Wed 06‐09‐17 0% Install Sawage pipe 
349 Install HDPE pipe  20 days Thu 17‐08‐17 Wed 06‐09‐17 0% Install HDPE pipe 
350 Ground Floor 15 days Tue 17‐10‐17 Wed 01‐11‐17 0%
351 Installation Support & Pipes 15 days Tue 17‐10‐17 Wed 01‐11‐17 0% Installation Support & Pipes
352 Mezzanine Floor 5 days Wed 01‐11‐17 Mon 06‐11‐17 0%
353 Install Support & Pipe 5 days Wed 01‐11‐17 Mon 06‐11‐17 0% Install Support & Pipe
354 2nd fix 25 days Tue 17‐10‐17 Sat 11‐11‐17 0%
355 Ground Floor 20 days Tue 17‐10‐17 Mon 06‐11‐17 0%
356 Installation of valves and  15 days Tue 17‐10‐17 Wed 01‐11‐17 0% Installation of valves and accessories
357 Pressure testing and gravity tests 5 days Wed 01‐11‐17 Mon 06‐11‐17 0% Pressure testing and gravity tests
358 Mezzanine Floor 10 days Wed 01‐11‐17 Sat 11‐11‐17 0%
359 Installation of valves and  5 days Wed 01‐11‐17 Mon 06‐11‐17 0% Installation of valves and accessories
360 Pressure testing and gravity tests 5 days Mon 06‐11‐17 Sat 11‐11‐17 0% Pressure testing and gravity tests
361 3rd fix  15 days Fri 01‐12‐17 Sat 16‐12‐17 0%
362 Ground Floor 15 days Fri 01‐12‐17 Sat 16‐12‐17 0%
363 Installation of sanitary wares 15 days Fri 01‐12‐17 Sat 16‐12‐17 0% Installation of sanitary wares
364 Mezzanine Floor 5 days Fri 08‐12‐17 Wed 13‐12‐17 0%
365 Install Sanitary Wares 5 days Fri 08‐12‐17 Wed 13‐12‐17 0% Install Sanitary Wares
366 Installation of Plant and Equipments 8 days Mon 27‐11‐17 Tue 05‐12‐17 0%
367 Electrical services 7 days Tue 28‐11‐17 Tue 05‐12‐17 0%
368 Installation of MV panels,  7 days Tue 28‐11‐17 Tue 05‐12‐17 0% Installation of MV panels, Equipment Panel
369 MVAC Services 5 days Mon 27‐11‐17 Sat 02‐12‐17 0%
370 Install Outdoor Units 5 days Mon 27‐11‐17 Sat 02‐12‐17 0% Install Outdoor Units
371 Fire Fighting Service 7 days Tue 28‐11‐17 Tue 05‐12‐17 0%
372 Installation of Fire Pumps 7 days Tue 28‐11‐17 Tue 05‐12‐17 0% Installation of Fire Pumps

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Split External Tasks Inactive Summary Manual Summary Progress
Project: MTPC NEW FACTORY PROJECT
Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

This programme is for estimation only. LBL International reserves the rights to change the programme to suit actual condition on site/ avaiability of materials, goods for construction drawing/ site construction/ etc... Page 6
PRELIMINARY CONSTRUCTION PROGRAMME FOR MTPC NEW FACTORY PROJECT
Rev04 ‐ 12 July 2017

ID Task Name Duration Start Finish %  June July August September October November December January F
Complete E B M E B M E B M E B M E B M E B M E B M E B M E B
373 Plumbing Services 7 days Tue 28‐11‐17 Tue 05‐12‐17 0%
374 Install Pumps 7 days Tue 28‐11‐17 Tue 05‐12‐17 0% Install Pumps
375 Testing and Commissioning 14 days Tue 09‐01‐18 Tue 23‐01‐18 0%
376 Testing and Commsioning of MEP  14 days Tue 09‐01‐18 Tue 23‐01‐18 0% Testing and Com

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Split External Tasks Inactive Summary Manual Summary Progress
Project: MTPC NEW FACTORY PROJECT
Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

This programme is for estimation only. LBL International reserves the rights to change the programme to suit actual condition on site/ avaiability of materials, goods for construction drawing/ site construction/ etc... Page 7