OUTLET: BASIN / TUNNEL OUTLET MONITORING TABLE

CURRENT PREVIOUS WEEK THIS WEEK


ITEM NO. DESCRIPTION UOM BOQ QTY RATE AMOUNT EARNED % EARNED AMOUNT EARNED % EARNED AMOUNT EARNED % EARNED AMOUNT
4.1 Outlet: Basin/Tunnel Outlet

4.1.1 Clearing and Grubbing sq.m. 2,040.00 674.66 1,376,298.71 100.00% 1,376,298.71 100.00% 1,376,298.71 0.00% -

4.1.2 Common Excavation cu.m. 400.00 2,193.29 877,314.30 100.00% 877,314.30 100.00% 877,314.30 0.00% -

4.1.3 Rock Excavation cu.m. 2,300.00 4,926.27 11,330,419.99 100.00% 11,330,419.99 100.00% 11,330,419.99 0.00% -

4.1.4 Common Backfill cu.m. 500.00 3,649.28 1,824,642.27 100.00% 1,824,642.27 100.00% 1,824,642.27 0.00% -

4.1.5 Gravel Fill cu.m. 15.00 8,424.77 126,371.51 100.00% 126,371.51 100.00% 126,371.51 0.00% -

4.1.6 Lean Concrete cu.m. 15.00 45,168.42 677,526.23 100.00% 677,526.23 100.00% 677,526.23 0.00% -

4.1.7 Structural Concrete cu.m. 90.00 49,817.76 4,483,598.64 39.95% 1,791,330.82 0.00% - 39.95% 1,791,330.82

Transition Tunnel cu.m. 29.23 49,817.76 1,455,953.86 23.21% 337,911.70 0.00% - 23.21% 337,911.70
Foundation slab cu.m. 6.78 49,817.76 337,911.70 100.00% 337,911.70 - 100.00% 337,911.70
Walls cu.m. 6.88 49,817.76 342,917.79 - - 0.00% -
Cirved Roof / Arch cu.m. 15.56 49,817.76 775,124.37 - - -
Transition Basin cu.m. 60.77 49,817.76 3,027,644.78 48.00% 1,453,419.13 0.00% - 48.00% 1,453,419.13
Foundation shear key/slab cu.m. 29.17 49,817.76 1,453,419.13 100.00% 1,453,419.13 - 100.00% 1,453,419.13
Walls cu.m. 31.60 49,817.76 1,574,225.65 - - 0.00% -
4.1.8 Waterstop lm 52.00 18,445.01 959,140.48 - - 0.00% -
4.1.9 Reinforcing Steel kg 9,000.00 487.62 4,388,544.45 37.72% 1,655,415.66 37.72% 1,655,415.66 0.00% -

Transition Tunnel kg 3,194.69 487.62 1,557,781.05 15.69% 244,367.38 15.69% 244,367.38 0.00% -
Foundation slab kg 501.15 487.62 244,367.38 100.00% 244,367.38 100.00% 244,367.38 0.00% -
Walls kg 1,536.78 487.62 749,359.71 - - 0.00% -
Cirved Roof / Arch kg 1,156.76 487.62 564,053.95 - - 0.00% -
Transition Basin kg 5,805.31 487.62 2,830,763.41 49.85% 1,411,048.28 49.85% 1,411,048.28 0.00% -
Foundation shear key/slab kg 2,893.77 487.62 1,411,048.28 100.00% 1,411,048.28 100.00% 1,411,048.28 0.00% -
Walls kg 2,911.54 487.62 1,419,715.13 - - 0.00% -
4.1.10 Shotcrete with wiremesh sq.m. 600.00 9,744.01 5,846,408.60 100.00% 5,846,408.60 100.00% 5,846,408.60 0.00% -

4.1.11 Rock Anchors pcs 130.00 48,235.73 6,270,644.77 100.00% 6,270,644.77 100.00% 6,270,644.77 0.00% -

4.1.12 Handrail pcs 20.00 46,248.26 924,965.20 - - 0.00% -

4.1.13 Steel Grating sq.m. 14.20 80,934.47 1,149,269.45 - - 0.00% -


4.1.14 Formwork sq.m. 200.00 11,229.10 2,245,820.66 12.57% 282,235.55 12.57% 282,235.55 0.00% -

Transition Tunnel sq.m. 70.18 11,229.10 788,077.08 11.30% 89,053.64 11.30% 89,053.64 0.00% -
Foundation slab sq.m. 7.93 11,229.10 89,053.64 100.00% 89,053.64 100.00% 89,053.64 0.00% -
Walls sq.m. 28.07 11,229.10 315,155.77 - - -
Cirved Roof / Arch sq.m. 34.19 11,229.10 383,867.68 - - -
Transition Basin sq.m. 129.82 11,229.10 1,457,743.57 13.25% 193,181.91 13.25% 193,181.91 0.00% -
Foundation shear key/slab sq.m. 17.20 11,229.10 193,181.91 100.00% 193,181.91 100.00% 193,181.91 0.00% -
Walls sq.m. 112.61 11,229.10 1,264,561.66 - - 0.00% -
SUB-TOTAL 42,480,965.27 75.47% 32,058,608.41 71.25% 30,267,277.59 4.22% 1,791,330.82