1.0 PROPOSE 3
2.0 SCOPE 3
4.0 ACTIVITIES 4
5.0 ATTACHMENTS 5
2.0 SCOPE
Project:
Main Contractor:
Sub Contractor:
4.1 Before starting the work, the Project Manager shall assign
the Supervisor to compile the relevant document and shall
submit to the Client for review, if required.
4.2 The Contractor shall prepare the inspection and test plan,
using specific forms to set all hold points/witness points
according to the contractual requirements, project
specifications and statutory codes.
4.3 QC manager and the Site Supervisor shall review the proposed
inspection and test plans and compile the relevant
inspection and test items to form a complete set of
Inspection and Test Plan. It should be submitted for
approval.
4.4 The approved Inspection and Test Plan shall be handed over
to the responsible appointed QC Manager.
5.0 ATTACHMENTS