Você está na página 1de 13

SPE

Society of Petroleum Engineers

SPE 25339

Simulation of Rapid Depressurization and Blowdown of an Offshore Oil Pipeline


B. M. Zagalai,* Unocallndonesia, Ltd., D. W. Montgomery,* Unocal, U.K. Ltd., C. L. Redus,*Texaco Exploration
& Production Technology, and T. K. Tan, Scientific Software-Intercomp (U.K.) Ltd.
*SPE Member

Copyright 1993. Society of Petroleum Engineers. Inc.

This ~ was prepared for presentation at the SPE Asia Pacific Oil &. Gas Conferance held in Singapore. 8-10 Fabruary 1993.

This papar w_ selected for presentation by en SPE Program Committea following raviaw of information contained in en abstract submitted by tha authorlsl. Contents of tha
~ as presented, have not been reviawed by the Society of Petroleum Engine.,s end ..a subject to correction by the authorlsl. Tha matarial, _ presented, does not
necessarily reflect any position of the Society of Patrolaum Engina.,s, its officers, or mambars. Papers presented at SPE meetings lII'e subject to publication review by Editorial
Committees of tha Society of Petroleum Engineers. Permission to copy is restricted to an abstract of not more than 300 words, illustrations may not ba copied. Tha abstrect
should contain conspicuous aclcnowIedgment of wh.,e end by whom the pap. is presented. Write Ubrarian, SPE, POBox 833836. Richardson, TX 15083-3836 U.S.A. Telex
130989 SPEOAL

ABSTRACT effects are compared to the installation of a sub-sea


isolation valve. A blowdown system on Heather
A practical investigation is reported of rapid platform was shown to be effective when the leak is
depressurization and blowdown in case of riser from a hole with a diameter of less than 2 inch
rupture of an offshore pipeline exporting live oil at (50 mm).
high pressure. This work was performed to assess
the environmental and safety consequences of not INTRODUCTION
installing sub-sea isolation valves on the Heather-
Ninian pipeline. The Heather Field is close to its Simulation of rapid depressurization in case of riser
economic limit, consequently, the overriding objective rupture is becoming an important part of the North
was to evaluate changes in operating procedure Sea pipeline environmental and safety studies. If the
which would provide an equivalent level of safety to pipeline is not fitted with a sub-sea isolation
that of installing a sub-sea isolation valve. valve (SSIV), hazards may result from the high leak
rates and the large cumulative release.
Three methods - simple analytical. approximate and
rigorous numerical simulation were used to predict Heather Ninian Pipeline
leak rates in case of riser rupture. To build
confidence in the predictions, a blowdown test to the The Heather Field is located in the UK Block 2/5,
separators on the exporting platform was performed. 90 miles northwest of the Shetland Islands. The field
The test results are in good agreement with the model was first discovered in 1973 with first production
predictions. commencing in October 1978. Currently there are
26 actively producing wells and 10 water injectors.
The oil was found to have a bubble point pressure Peak oil production of 40,000 B/D occurred in 1982
near the threshold pressure at which riser rupture and has been followed by steady decline over the last
could cause sustained hydrocarbon release due to decade to about 12,000 B/D. Crude oil and
solution gas drive in the sub-sea pipeline. As a result, condensate are exported via the Heather-Ninian
the process facility on the exporting platform was 16 inch pipeline to Ninian Central Platform (NCP),
modified to lower the bubble point pressure. The (Fig. 1). It is then further exported to Sullom Voe

References and figures at end of paper.


2 Simulation of Rapid Depressurization and Blowdown of an Offshore Oil Pipeline SPE 25339

terminal. The 16 inch (406 mm) pipeline is 20 miles mass flow rate is assumed to be the same in every
(32 km) long with risers at Heather and NCP of element of the pipeline at a given time).
541 feet (165 m) and 518 feet (158 m), respectively
(Fig. 2). At the average operating rate of 14,000 B/D Ellul 2 used a more rigorous pipeline transient flow
(25 kg/s), the inlet pressure and temperature are simulator (OLGA) to simulate pipeline riser rupture.
725 Psia (50.5 bara) and 131 -F (55 -C), and at the The code 3 is a one- dimensional, two-phase, transient
NCP outlet are 695 Psia (48 bara) and 50 -F (10 -C). flow in multi-branch pipeline networks. The model
The pipeline is operated at high pressure to facilitate solves three mass conservation equations; one for the
entry to the 36 inch main export line at NCP where it gas, one for the liquid droplets and one for the liquid
joins with fluids from four additional fields. Under film on the pipewall; two momentum conservation
steady-state conditions, the flow is single-phase liquid. equations; one for the gas oil liquid droplets and one
for the liquid film. Finally, one energy equation for the
The primary technical objective was to determine mixture is solved, assuming equal temperature and
whether a rupture of either riser would lead to: pressure for all three fractions (gas, liquid droplets
and liquid film). The model calculates pressure,
(1) sustained hydrocarbon release due to solution temperature, holdup and velocity for the individual
gas drive in the sub-sea pipeline and with its phases along the pipeline and at the point of the leak.
large inventory released, or
(2) a small fraction of the inventory released due to We have first used a simple analytical method and
liquid expansion only, with the liquid head in the then adapted a compositional, isothermal reservoir
riser maintaining a pressure at the base of the simulator to solve the problem while investigating a
riser above the bubble point pressure of the fluid more rigorous approach such as OLGA. The reservoir
in the sub-sea pipeline. simulator approximate solution is shown to be in good
agreement with OLGA's. We are not suggesting that
With the pipeline inventory of about 49,000 BBLS pipeline modeling may be done using a reservoir
(6,700 Tonnes), the cumulative hydrocarbon released simulator. For this type of problem, the depletion
for the first scenario would be about 7,300 BBLS performance is more controlled by the phase behavior
(1,000 Tonnes; 15% depletion) and for the latter would than the two-phase fluid dynamics in the riser and the
be about 220 BBLS (30 Tonnes; 0.5% depletion). The reservoir simulator provided a reasonable
cumulative release under the first scenario could be approximation.
reduced from 7,300 to 110-220 BBLS (1,000 to
15-30 Tonnes) by installation of SSIVs, depending on Heather Export Fluid
the time to fully activate the valve.
The export fluid consists of about 12,000 BID of stock
An approach was needed to predict leak rates and tank crude and 2,000 BID of condensate. The crude
cumulative release in case of riser rupture from small without the condensate has a bubble point pressure
hole size to full-bore. The effects of including SSIVs of 40 Psia, and with the condensate spike it increases
and blowdown to the separators can then be to 145 Psia at 50 -F (10 -C). The condensate has a
analyzed. saturation pressure of 415 Psia at 72 -F. Flashing of
the pipeline feed at atmospheric pressure and 50-F
METHODOLOGY (10 -C) resulted in a GOR of 80 SCF/STB and liquid
gravity of 32 -API. PVT experimental data was used
Richardson 1 reported on a computer program which to calibrate the Peng-Robinson equation of state and
can be used to simulate the emergency blowdown of generate required fluid properties as functions of
a pipeline containing hydrocarbons. Richardson pressure and temperature. Table 1 shows the
assumed homogeneous two-phase flow (no slip predicted bubble point pressure for the temperature
between the gas and liquid phase, where the range in the pipeline for the original export fluid and
two co-exist, gas and liquid phases move at the same after modification of the process facility which is
axial velocity) and the flow is pseudo-steady state (the discussed in a later section.
SPE 25339 B. M. Zagalai, D. W. Montgomery, C. L. Redus, and T. K. Tan 3

Under steady-state conditions the flow is single-phase Depressurization due to liquid expansion would be
and the pressure drop across the pipeline is only very rapid and all of the fluid produced from the initial
20 psi. The pipeline is operated at high pressure pressure of 900 Psia to a pressure of about 200 Psia
facilitating its entry to the export line of NCP. would be due to liqUid compressibility. Flashing
would occur at the ruptured end at NCP as well as
Steady-state flow calculations show the pressure and topside the riser of the intact end at Heather. Pipeline
temperature at the base of the riser at Heather are friction losses result in a pressure differential between
925 Psia and 127 -F (53 -C) and at base of the riser at the intact and ruptured end. Whether flashing would
NCP are 908 Psia and 50 -F (10 -C). The pressure occur in the sub-sea pipeline would depend on the
and temperature at mid-point of the sub-sea pipeline pressure at the base of the riser due to the
are 918 Psia and 68 -F (20 -C). The corresponding gravitational head, when the topside ruptured end is
bubble point pressures at the base of each riser were near atmospheric pressure. Determining that requires
200 Psia at Heather and due to seabed cooling the simultaneous solution of mass, momentum and
145 Psia at NCP. energy conservation equations. If the pressure falls
below the bubble point at the base of the risers at
Conceptualization of Flow NCP, gas begins to evolve over the entire sub-sea
in the Riser After Rupture pipeline. Depletion of the pipeline continues under
pseudo-steady state flow until the top of the riser
The most extreme condition of rupture from a fluid reaches atmospheric pressure.
flow perspective would involve leaks at NCP from
holes or full-bore at the sea level splash zone. For ANALYTICAL METHODS
sub-sea leaks, the ambient pressure due to the sea
water hydrostatic head at the seabed is about Pressure Profile in the Riser
215 Psia which would result in minimum degassing of
the Heather riser with low leak rates due to higher Assuming homogeneous two-phase flow and
backpressure. Rupture at topside the platform is neglecting pressure losses due to friction and
slightly contained by the liquid head from sea level to acceleration, the relationship between the riser topside
topside. pressure (P,) and the pressure at the base (P ~ is
analogous to static fluid column in a wellbore 4 and is
First consider a riser rupture at NCP. This is the given by the integral equation
platform with the higher risk due to the potential
escalation impact on an additional eight risers. Also, rpz v dp = -g~z (1)
)p,
if the pressure at the base of NCP riser falls below the
bubble point, the entire sub-sea pipeline would fall
below the bubble point pressure, because the bubble where, v is the specific volume of the two-phase
point pressure is lowest at NCP. mixture.

It was assumed that in case of a leak, the Heather oil At the end of the leak period, the pressure at the
exporting pumps will be shut-down instantaneously. topside of the riser is equal to atmospheric pressure.
For the OLGA simulations the pump shut-down period The final sub-sea pipeline pressure (Eq. 1) at the
lasts 30 seconds. At the instant of the rupture the flow base of the riser at NCP would be 100 Psia. This
is single phase liquid. The initial leak rate would pressure is below the bubble point pressure of
depend on the size of the hole. The pressure wave 145 Psia. When the analytical approach was first used
moves from the ruptured end to the intact end of the the pipeline fluid was estimated to have a bubble
other riser at the local speed of sound, after which the point pressure of 86 Psia (6 bara) based on
pressure there begins to fall. For a leak from a large recombined composition of crude/condensate sample.
hole, an acceleration wave begins to propagate due In that case the final pressure of 100 Psia is above the
to higher fluid velocity at the ruptured end. bubble pressure and the cumulative release would be
only 16 Tonnes. With the numerical integration of
4 Simulation of Rapid Depressurization and Blowdown of an Offshore Oil Pipeline SPE 25339

equation 1 the calculated final pressure can be under Cumulative Release


estimated if not enough steps are taken to account for
the substantial drop in the two-phase fluid density as By assuming a horizontal sub-sea pipeline and
the pressure drops from 30 Psia to atmospheric. For neglecting frictional pressure losses, the sub-sea
example, with a pressure step of 15 Psia, the final pipeline is treated as a tank with uniform pressure and
pressure at the base of the riser was 57 Psia (4 bara) temperature. The riser at Heather is ignored. The
which is lower than the bubble point pressure of 86 average pressure of the sub-sea pipeline is assumed
Psia and the cumulative release is 930 Tonnes. In an to be equal to the pressure at the base of the riser at
intermediate run with a final pressure of 76 Psia (5 the ruptured end. The temperature is assumed to
bara), the cumulative release was 335 Tonnes. remain constant at 10 ·C.

Leak Rate Cumulative release when the pressure drops from


initial pressure to a pressure above the bubble point
The leak from the topside NCP riser initially would be is given by:
single phase liquid until the pressure at the top of the
riser falls below 145 Psia. The usual formula for the (4)
flow rate through an orifice is used to calculate the
leak rate, when the flow is subcritical. Using an oil compressibility of 5x1 0 -6t /Psi, the
cumulative release with depressurization from 900 to
145. Psia is 0.38% of the pipeline inventory of 6684
Tonnes or 25 Tonnes. For a given pressure
decrement, total mass release is calculated using
Assuming a discharge coefficient of 0.8, the initial equation (4), pressure topside the riser is calculated
instantaneous leak rate for hole sizes 10, 50 and using equation (1) and the leak rate using equation
100 mm (0.4", 2", and 4") would be 6, 115, 350 kg/s, (2). The time step corresponding to the pressure step
(3,300, 65,000 and 195,000 B/D) respectively. For a is calculated assuming the rate to remain constant
full-bore rupture the initial leak rate would be over the pressure step.
1250 kg/s (700,000 B/D).
Once the pressure in the sub-sea pipeline falls below
For two-phase flow, it is assumed that the fluid the bubble point pressure, the change in the mass
behaves as a homogeneous mixture with the average content of the pipeline is calculated using the average
two-phase density used in equation 2. density of the two-phase homogenous mixture. The
liquid/gas saturations are determined from the phase
Critical Flow behavior predicted by the equation of state.

The flow through an orifice is at critical (choked) Fig. 3 shows the leak rate and cumulative release
condition when the downstream pressure is from a 100 mm hole for a pressure step of 15 and 1
apprOXimately 0.55 or less of the upstream pressure. Psi. The rate declines from 350 to 50 kg/s in about
Under these conditions the flow rate is a function only two minutes due to liquid expansion and gradually
of the upstream pressure and is given by: declines once the pressure falls below the bubble
point in the sub-sea pipeline. The sensitivity to the
dm=C.,A~ dp (3) pressure integration step is shown in Fig. 3.
dt dv
The analytical approach was biased toward under
estimating the final pressure at the base of the riser
The expansion wave moves at the local speed of and hence could be used a screening tool prior to a
sound of about 4600 ft/sec and reaches the intact end rigorous study. It also highlighted the need for
of the 20 mile (32 km) pipeline at about 20 seconds. accurate PVT data. SUbsequent laboratory PVT
characterization showed that the fluid had a bubble
SPE 25339 B. M. Zagalai, D. W. Montgomery, C. L. Redus, and T. K. Tan 5

point pressure of 145 Psia and in this case the leak ceased after 15 minutes with a cumulative release
analytical method would show flashing in the sub-sea of 160 BBlS (25 Tonnes).
pipe and cumulative release of about 900 Tonnes.
At the end of the leak, the sub-sea pipeline pressure
was 165 Psia which is above the bubble point
Approximate Numerical Solutions pressure. The riser fluid at NCP was consequently
liquid at saturation pressure. However, due to gas
In reservoir engineering terminology, the simplified prOduction, the bubble point pressure was no longer
analytical approach discussed may be classified as a constant.
black-oil tank type problem, under pseudo-steady
state flow with an explicit source term. While preparing OLGA SIMULATIONS
for use of a rigorous multi-phase transient pipeline
flow simulator, we adapted a compositional reservoir OLGA is a 1-0, transient, two-component, two-phase
simulator to model the pipeline inventory depletion. flow simulator for pipeline networks. Compositional
The use of the reservoir simulator allows relaxation of effects are accounted for by table look-up of fluid
the assumptions of pseudo-steady state flow and properties as functions of pressure and temperature.
static fluid column in the riser. The tables are generated using a pvr pre-processor.
The pipeline is divided into a number of elements and
The pipeline was divided axially into 91 grid blocks, mass, momentum and energy balances are performed
with the sub-sea pipeline represented with for each element. The model calculates pressure,
geometrically increasing increments toward its center. temperature, liquid holdup and velocity of the
The risers are represented with grid blocks of equal individual phases in each element. The model is first
size. An equivalent well prOductivity index was initialized to arrive at steady-state operating
assigned based on the initial mass rate calculated conditions. A restart run is made by changing the
from equation (2) and used to represent the leak boundary conditions and specifying the leak point at
point. An absolute permeability of 1 billion Darcys a particular element.
resulted in a match of the pressure drop across the
pipeline under steady-state flow. A relative Case Studies: Rupture at NCP
permeability of 1 was used for both oil and gas
independent of saturation. The entire pipeline was Case studies were performed with a rupture point at
assumed to be at constant temperature. topside the NCP riser. The boundary condition at
topside Heather was changed to flux specified with
For a 50 mm rupture at topside of the NCP riser, the rate decreasing to zero over a period of 30 seconds
initial mass rate was 125 kg/s (70,000 B/D). The to account for shut-down of the operating pumps.
simulated rate declined rapidly due to
depressurization above the bubble point (Fig. 4). The Threshold Pressure
rate was 740 B/D after 15 minutes from rupture.
Because the pressure drop across the pipeline is not For each fluid and pipeline-riser configuration, there
significant, the pressure drop in the ruptured end is exists a threshold pressure. If the fluid has a bubble
transmitted to the intact end at Heather. As a result, point pressure above that threshold, then degassing
gas continues to evolve at the intact end and migrates will occur in the sub-sea pipeline. For the Heather-
to the top of the riser to form a free gas column. The Ninian pipeline, the threshold pressure was estimated
rapid gravity segregation due to the very high at 150 Psia. Sensitivity runs were performed with
permeability causes stability problems for the reservoir modified pvr data for fluids with bubble point
simulator which by its very nature is not designed to pressure of 230, 145 and 90 Psia. For a fluid with
solve this type of problem. The gas migration results 230 Psia bubble point pressure at 50 -F, a leak from
in continuous flow at the low rate of 700 B/D. When a 4" (100 mm) diameter hole lasted for 6.7 hours with
the model was reconfigured without the Heather riser, a cumulative release of 5,500 BBlS (750 Tonnes).
For a bubble point pressure of 90 Psia at 50 -F, the
6 Simulation of Rapid Depressurization and Blowdown of an Offshore Oil Pipeline SPE 25339

leak lasted only 7 minutes with cumulative release of and decreases to 90 Psia after 2 minutes from rupture.
230 BBLS (31.5 Tonnes). The sub-sea pipeline average pressure follows the
trend of the ruptured end and remains above the
Heather export fluid had a bubble point pressure of bubble point pressure of 104 Psia with a final pressure
145 Psia at 50 -F. Due to its proximity to the of 145 Psia. The liquid holdup follows a similar trend.
threshold pressure, simulation was sensitive to small A column of free gas forms very early at the intact
changes in the input fluid property tables used in end. The leak ends when a free liquid level forms and
OLGA. Slight variations resulted in a cumulative the riser loads up. A slight differential in pressure top
release between 90 Tonnes to 185 Tonnes, and leak side the Heather and NCP risers exists at the end of
duration from 35 to 85 minutes for 100 mm hole. the leak due to higher density of the cooler liquid
Although the riser loads up in both cases, simulations column at NCP.
were near to the balance point, and the leak could
continue for 7 hours with cumulative release of Blowdown to The Heather Separators
750 Tonnes.
To model blowdown to the Heather separators in case
Process Modification to Lower the of rupture of NCP riser, the pipeline configuration was
Bubble Point Pressure changed to account for flow through a "3" backflow
line to the main production separators. The
Reducing the bubble point pressure from 145 Psia to equivalent length of the 3" pipe after accounting for
about 100 Psia was thought to provide a good safety bends and valves is 82 m. At 2 minutes from rupture,
margin. The target was achieved by lowering the the boundary condition at Heather was altered from
operating pressure of the condensate stabilization zero flux to a constant pressure of 60 Psig, this being
vessel from 415 Psia to 300 Psia prior to spiking into the normal operating condition of the production
the oil stream. A PVT sampling program was initiated separator's first stage. It is assumed that backflow
to ensure the export fluid remained within the target would not result in pressurizing the separator. The
pressure. Laboratory PVT results were in excellent two separators have an operating volume of 480
agreement with predictions performed using the BBLS each, which is considerably larger than the
equation of state. Table 1 shows the bubble point of expected liquid back flow due to liquid expansion.
the modified export fluid as a function of temperature.
Sensitivity runs were performed for a rupture topside For a 10 mm hole, the blowdown rate was much
the riser at NCP for hole sizes of 0.4, 2 and 4 inch larger than the leak rate (Fig. 7). Backflow to the
(10, 50 and 100 mm). The results are summarized in separator was 109 BBLS (15 Tonnes) and cumulative
Table 2. release at NCP is reduced from 167 BBLS to 25 BBLS
(23 to 3.5 Tonnes). The backflow rate to the
The flow rate in the pipe prior to rupture was 14,000 separator is smaller than the leak rate from 50 and
BID (25 kg/s). The leak rate (Figure 5) shows the fluid 100 mm holes. For the 50 mm hole, about 10 BBLS
accelerating to its maximum flow rate of 210,000 BID (1.4 Tonnes) backflowed, while almost no backflow
(380 kg/s) and 67,000 BID (120 kg/s) for the 100 and was observed for the 100 mm hole. Lowering the
50 mm hole, respectively, in 3 seconds. The leak rate separator back pressure from 60 Psig to atmospheric
from the 10 mm hole is 3,300 BID (6 kg/s). The increases the backflow modestly to 2.9 and .4 Tonnes
cumulative release of 250 and 204 BBLS (34 and 28 for the 50 and 100 mm holes, respectively.
Tonnes) and duration of 8,15 minutes for 100 and 50
mm hole, and 167 BBLS (23 Tonnes) and duration of Case Studies: Rupture of Riser at Heather
2.6 hours for the 10 mm hole (Fig. 5).
Because of the higher temperature at the Heather
The pressure at the point of rupture (NCP) begins to end, the bubble point pressure was 160 Psia at the
drop at the instant of rupture and gradually decreases base of the Heather riser and 115 Psia at about half
to atmospheric pressure (Fig. 6). The pressure at the way in the sub-sea pipeline, compared to 104 Psia at
intact end at Heather begins to drop after 20 seconds the NCP end. The bubble point pressure at Heather
SPE 25339 B. M. Zagalai, D. W. Montgomery, C. L Redus, and T. K. Tan 7

is slightly higher than the threshold pressure Figure 11 shows the liquid holdup at the base of
established from simulation of rupture at NCP. Heather.

Model case studies were performed for Heather riser Sub-Sea Isolation Valves
rupture from 10, 50, 100 mm holes and full-bore 375
mm at sea level (Table 2). For the 10 mm hole, the Assuming that a sub-sea valve closes at 1 minute after
riser loads up after 2.5 hours with cumulative release riser rupture, the cumulative release from a full-bore
of 17 Tonnes. The temperature at the base of the rupture would be reduced to 28 Tonnes. However, for
riser decreased from 54·C to 35·C due to sea-bed the riser rupture at NCP, reducing the bubble point
cooling. For the 50 mm hole the riser loads up at pressure from 146 to 104 Psia also resulted in a
about 30 minutes with cumulative release of 29 cumulative release of about 30 Tonnes. For a series
Tonnes. As with the 10 mm hole, the pressure in the of ruptures at the Heather end of the pipeline, only
sub-sea pipeline remains above the bubble point with rupture sizes of 50 mm or less result in releases of
final pipeline pressure of 145 Psia. less than 30 Tonnes. The 100 mm and full-bore
rupture result in releases of 180 and 750 Tonnes
For the 100 mm hole, the riser loads up in 2.5 hours respectively. Currently these values are being input
with cumulative release of 180 Tonnes which was into further safety studies for assessing the risk of
higher than the 30 Tonnes expected from liquid rupture.
expansion only. However, the cumulative release was
much less than the 750 Tonnes expected from BLOWDOWN TEST
complete degassing of the sub-sea pipeline. Because
of the decrease in bubble point pressure With distance To build confidence in the model predictions, a
away from the Heather riser due to lower fluid blowdown test was instigated at near normal pipeline
temperature, the pressure remains above the bubble operating conditions. After close of the ESDV at NCP,
point in most of the sub-sea pipeline. This results in the line was pressurized to 745 Psig topside Heather,
partial and diminishing gas drive as the Heather end following which the shutdown valve for 3" line to the
cools down, and when coupled with the decrease in separator was opened. After 17 minutes the
leak rate, results in loading up of the riser. The leak pipeline-separator system had equilibrated to the
rate and cumulative release are shown in Figure 8, separator pressure of 35 Psig. Table 3 compares key
and the liquid holdup at the base of Heather riser in model results to field measurements. The calculated
Figure 9. For the smaller hole, the back pressure on cumulative oil released over the duration of backflow
top of the riser prevents propagation of the two-phase (20 Tonnes and 16 minutes) are in very good
region and riser loads up quickly. The liquid holdup agreement with the measured data (18 Tonnes and 17
profile for 100 mm hole ( Fig. 10) shows the minutes). The calculated pressure at the top of
propagation of the flashing zone to a distance of Heather riser was also in good agreement with
about 5 km. measured pressures. It should be kept in mind that
no model parameters were adjusted to obtain this
In simulation of full-bore rupture, the model grid was match. This is strictly prediction and is dissimilar to
refined by adding an additional 30 grid blocks in order that of reservoir history matching.
to model extreme conditions due to the very high leak
rate. Furthermore, the portion of the riser above sea CONCLUSIONS
level (22 m) was eliminated from the model grid.
Simulation of full-bore rupture results in a initial rate of (1) For each fluid and pipeline-riser configuration,
700,000 BID (1250 kg/s) and resulted in gas flashing there exists a threshold pressure; if the fluid has
over the entire sub-sea pipeline with cumulative a bubble point pressure above it, then degassing
release at 1 hour of over 400 Tonnes. The leak rate will occur in the sub-sea pipeline.
at run termination is 80 kgls and would continue until
the maximum depletion, estimated at 750 Tonnes. (2) Use of a simple analytical method which assumes
homogenous gas-oil mixture and pseudo-steady
8 Simulation of Rapid Depressurization and Blowdown of an Offshore Oil Pipeline SPE 25339

state results in overestimation of cumulative ACKNOWLEDGEMENTS


release from riser rupture of Heather-Ninian
pipeline. The simple approach could be used as The authors thank the management of the operating
a screening tool prior to a rigorous study. company, Unocal U.K., and the Heather Field group
partners for the opportunity to present this paper, with
(3) Adaption of a reservoir simulator provided a first special thanks to Texaco U.K. for their support.
order approximation for prediction of leak rate Access to the OLGA simulator was provided by
and inventory depletion. Texaco Exploration & Production Technology,
Houston and Scientific Software-Intercomp (U.K.) Ltd.
(4) Rigorous simulation work demonstrated that a
slight change in operating procedure and
process design would provide an equivalent level
of safety to that of installing a sub-sea isolation REFERENCES
valve.
1. Richardson, S. M. and Saville, G.: "Blowdown of
(5) The combination of simple analytical method, Pipelines," SPE Paper 23070 Presented at
approximate and rigorous simulation improved Offshore Europe Conference, Aberdeen, 3-6
understanding of the physical process during September 1991.
riser rupture. The matching of the blowdown field
test builds a level of confidence in the model 2. .Rygg, O. B. and Ellul, I. R., ''The Dynamic
predictions. Two-Phase Modelling of Offshore Uve Crude
Unes Under Rupture Conditions," Paper OTC
NOMENCLATURE 6747 Presented at 23rd Annual Offshore
Technology Conference, Houston, May 1991.
A = hole area (m 1
Cd = discharge coefficient 3. Bendiksen, K., Brandt, I., Fuchs, H., Maines, D.,
Co = Oil compressibility, psr' and Moe, R.: "1986, Two-phase Flow Research at
g = gravitational constant (9.8 m/s 1 SINTEF and IFE, Some Experimental Results and
m = mass, kg a Demonstration of the Dynamic Two- phase
P, = upstream pressure of rlWtured end (N/m 1 Flow Simulator OLGA," Presented at The
Pa = ambient pressure (N/m j Offshore North Sea 1986 Conference, Stavanger,
Pi = Initial sub-sea pipeline pressure (N/m 1 Aug 28, 1986.
p = density, kg/s
t = time, seconds 4. Bradley, H. B.:"Petroleum Engineering Handbook"
v = specific volume of mixture (m 3/kg) Society of Petroleum Engineering (1987).

v =Xv g+(1-X)v I

V = Pipeline Volume (m ~
X = mass fraction of gas phase
z = vertical distance from topside to sea floor (m)

Subscripts

g = gas
I = liquid
SPE 25339 B. M. Zagalai, D. W. Montgomery, C. L. Redus, and T. K. Tan 9

Table 1
Properties of Heather Export Oil

Oil Gravity 32.2 °API


Solution Gas-Oil Ratio 80 SCF/STB
Gas Gravity 1.29
Oil Compressibility 5X1O- 6 l/psi

Bubble Point Pressure as a Function of Temperature

Bubble Point Pressure


Temperature Original Fluid Modified Fluid
of Psia Psia

32 131 92
34 133 93
41 139 98
50 146 104
59 154 110
68 161 117
n 169 123
86 177 130
95 185 137
104 194 144
113 202 151
122 211 159
131 220 167
141 230 175
149 288 183

Table 2
OLGA Case Studies

At NCP At Heather

Hole Size. in 0.4 2.0 4.0 0.4 2.0 4.0 14.7


(mm) 10 50 100 10 50 100 375

Initial Leak Rate


K9/s 6 115 335 6 115 335 1250
(B/D) 3.300 65.000 188.000 33.000 65.000 188.000 700,000

Cumulative Release. Tonnes


at 1 Minute 0.3 7.0 15.0 0.3 6.9 14.5 28.2
at 2 Minutes 0.6 12.6 21.7 0.6 12.4 21.7 47.7

Leak Duration.
Minutes 156 15 8 160 32 160

Final Cumulative Release.


Tonnes 22.6 27.5 33.8 16.6 28.9 182 412*
*at 48 minutes
10 Simulation of Rapid Depressurization and Slowdown of an Offshore Oil Pipeline SPE 25339

Table 3
Comparison to Result from Blowdown Test

Simulated Top Riser Measured Top Riser


Time Backflow Pressure Backflow Pressure
(Minutes) Kgjs BID Psia BID Psia

1 64 36.000 580 46.000 620


2 53 30.000 420 32.000 440
3 42 24,000 301 16.000 265
4 33 18,000 219 5.500 165
7 15 8,000 108 2.700 105
10 9 5.000 78 5.500 84
15 3.6 2.000 56 5,500 50
17 0 0 50 0 50
Cumulative
Backflow 20.7 Tonnes 18 Tonnes

1m!~~I'fIIIIIIIIH_E_A_T_H_Er-R"_-r _ _~.- 61 oN

~ LYELL
~~ NINIAN CENTRAL
~A.
.... ·Vli)· PLATFORM
.!Q11 76" Pi .
Ninia.!!.-Su!!f> Voe 36" PiQeIineP... me_
- - - - -

MERALD

Figure 1 Heather Location Map


en
"'0
NINIAN CENTRAL m
I\)
01
P =695 Psla c.>
HEATHER ALPHA =
T 50°F c.>
<D
14,000 BID
=
P 725 Psla Hl~!"I
T_=_13_1_oF_.. "l,NM'Ilo~SEA LEVEL
...

M
....N
OJ

470' ~
Co co
CJI iii N
-----I n>
(Q
n>
~.
0

SEAFLOOR
~
~

Figure 2
20m es

Heather-NinJan Pipeline
---~l-197'

-0
:J
(Q
0
3(I)
~
600 200 100 1000 a
r
500 ::II
Ic 80 800 ~ (I)
150 c ~ ID
lD
0-
C
400 ~ ::E W en
.;. rn
iii W 60 600
rn
c( n>
~
-e !C
a:
W :J
0-
100 w
iii 300 oJ
oJ w :-I
~ w
a:
:ill:
c( a:
a: w w
~ w oJ
40 400 > ?'
-e >
~
200 ~
w
oJ
5 oJ n>
:J
100 .-._ ........
",-p=lf!L-----9- ::I
::E
::I
0
20 200
:J
::E
:J
0

0
--------------.
0 0.2 0.4 0.6 0.8
0.20 0.40 0.60 0.80 1.0
TIME (Hours)
TIME (Hours)

Figure 3 Leak Rate and Cumulative Figure 4 Leak Rate and Cumulative
Release from 100 mm Hole Release from 50 mm Hole
(Analytical Method) (Reservoir Simulator) ......
......
103 r - - - - - - - - - - - - - - - - - -__---., 40 1000

III .......................
102
'\
5Q 1'l}!1\••••••••••
..... tI
C
C
SOO
TOPSIDE HEATHER
...........................
30
~ .... .... ' ....... en
~ ui .! .... .... 3'
~ In
oC
III 600 ...... ••••••••••$UB-SEA PIPELINE
... c
~ 10 20
W
..J
W
A.
ui
a::
..... .... . . e
o'
a::
w
a:: :::l
In 400
.... .... :l
~
oC > In
W
.... ' . o
.....
W ~ a::
..J
10 :5:::l A. TOPSIDE NCP :D
lU
::E 200 ""0
:::l
U a:
oCD
10.1 L--...L-_-L-_---J..._----l._<::::..-'----_-'-=_.LI-_---C.<_--' 0 0 ""0
....
10.5 10-4 10.3 10.2 10.1 10 103 10-8 10.3 10-2 10 CD
(J)
TIME (Minutes) TIME (Minutes) (J)
c
....
Figure 5 Leak Rate and Cumulative N'
Release from 10, 50 and 100 mm
Figure 6 Pressure at NCP. Heather and e
Sub-Sea for 100 mm hole at NCP o'
:l
Diameter Hole at NCP
lU
:l
0.
OJ

102.--------------------,
102
~0.
o
:E
•! :l
c o
.....
~ lU
~ 10 10 ui :l
~
......... ~ o
•..... l~I(~T W ~

.•.••.........:::::::::::::~~- ,.::::::::::. :::::::::::::::::::...


..J (J)
W
a:: ::T
w o
....
1-
> CD

5
:::l
Q
::E ::Po
:::l
U ""0
~
10.1 S·
CD
5 10 15 20
TIME (Minutes)
en
-0
Figure 7 Leak Rate at NCP from 10 mm m
Hole with Slowdown to Heather I\)
(11
(,,)
(,,)
(0
III
en
"1l
400 200 !c m
..
)300
{!.
150 ~ D.
I\)
(]I
c..>
c.l
ce ::) 1.0 <0
u.i W
.... C
~ 100 ~
.J
0
a: 200 ::I:
0.9
lllI: w
i3.... ~ c
100 50 5
:)
5
a
:J
0.8
:::E OJ
:)
0.7
CJ
60 120 180 240 300
s:
60 120 180 N
ll)
(Q
TIME (Minutes) TIME (Minutes) ll)

~.
0
Figure 8 Leak Rate and Cumulative Figure 9 Liquid Holdup at Base of Heather ~
Release for 100 mm Hole at Riser for 100 mm Hole at Heather
s:
Heather 0
::J
r+
(Q
0
3
CI>
-<
0
1.0 - r
D. 1.0 :D
0.8 t- ::) CD
Q, 0-
:)
c
c 0.8 c
.J
.... 0.6 - 0
(J)

0 ll)
::c ::I: 0.6 ::J
c 0.4 - C a.
5
a 5 0.4 :-f
::::i -
a
0.2 :J 0.2 ?'
-f
I I I ll)
::J
10 20 30 10 20 30 40 50 60
DISTANCE, km
TIME (Minutes)

Figure 10 Liquid Holdup Profile at 30 Figure 11 Liquid Holdup at Base of Heather


Minutes After Rupture of Riser for Full-Bore Rupture of
Heather for 100 mm Hole Heather
.....
c.l

Você também pode gostar