Escolar Documentos
Profissional Documentos
Cultura Documentos
FILING NO __________
CASE NO __________
AND
1
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
of Manipur, and the Manipur State Power Company Limited (MSPCL) responsible
for generation and transmission functions in the State of Manipur.
2. As per JERC (Multi Year Tariff) Regulations, 2014, the ARR and tariff of
transmission and distribution are to be determined separately. In the Tariff Order
for FY 2014-15, the Hon’ble Commission has also issued a directive for filing
separate Petitions for Transmission Business and Distribution and Retail Supply
Business. The two restructured Companies had filed separate ARR Petitions for
Distribution and Transmission for the first time at the time of tariff determination
for FY 2017-18, and the Hon’ble Commission issued separate Orders for
Transmission and Distribution.
3. The present Petition is for Limited Provisional True up of FY 2017-18 and Tariff
Determination for FY 2019-20 based on the ARR approved by the Hon’ble
Commission for FY 2019-20 in the MYT Order for MSPDCL dated 12 March, 2018
in Petition (ARR & Tariff) No. 1 of 2018.
4. In accordance with the Electricity Act, 2003, MSPDCL is required to submit its
Annual Revenue Requirement (ARR) and Tariff Petition as per procedures
outlined in Sections 61, 62 and 64 of the Electricity Act, 2003 and the governing
Regulations thereof.
5. MSPDCL hereby submits its Petition for approval of Limited Provisional True up
for FY 2017-18 and Tariff Determination for FY 2019-20 in accordance with the
principles specified in the JERC (Multi Year Tariff) Regulations, 2014, notified by
the Hon’ble Commission.
6. MSPDCL prays to the Hon’ble Commission to admit the enclosed Petition for
Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-
20, and grant the specific reliefs prayed for.
2
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Contents
1. Chapter 1: Introduction ............................................................................................................... 6
1.1 Historical Background......................................................................................................... 6
1.2 Power Profile of MSPDCL .................................................................................................. 7
1.3 Background of Regulatory Setup ....................................................................................... 8
1.4 Contents of this Petition ...................................................................................................... 9
2. Chapter 2: Overall Approach for Present Filing .................................................................... 10
2.1 Approach for Filing ........................................................................................................... 10
3. Chapter 3: Limited Provisional true up of FY 2017-18.......................................................... 13
3.1 Energy Sales ........................................................................................................................ 13
3.2 Distribution Loss ................................................................................................................ 14
3.3 Energy Requirement .......................................................................................................... 17
3.4 Energy Availability ............................................................................................................ 18
3.5 Power Purchase Cost ......................................................................................................... 19
3.6 Transmission Charges ....................................................................................................... 21
3.7 Operation and Maintenance Expenses............................................................................ 21
3.7.1 Employee Expenses ................................................................................................... 22
3.7.2 R&M Expenses............................................................................................................ 22
3.7.3 A&G Expenses ............................................................................................................ 23
3.8 Capitalisation ...................................................................................................................... 24
3.9 Interest on Working Capital ............................................................................................. 25
3.10 Gross Fixed Assets and Depreciation .............................................................................. 26
3.11 Interest on Loan .................................................................................................................. 27
3.12 Return on Equity ................................................................................................................ 28
3.13 Write off of Bad Debts ....................................................................................................... 28
3.14 Non-Tariff Income ............................................................................................................. 28
3.15 Aggregate Revenue Requirement .................................................................................... 29
3.16 Revenue from sale of power ............................................................................................. 30
3.17 Revenue Gap....................................................................................................................... 30
4. Chapter 4: Tariff Determination for FY 2019-20 .................................................................... 31
4.1 Aggregate Revenue Requirement .................................................................................... 31
4.2 Revenue at Existing Tariff ................................................................................................. 33
4.3 Revenue Gap for FY 2019-20 at Existing Tariff .............................................................. 35
4.4 Recovery of Revenue Gap for FY 2019-20....................................................................... 36
4.5 Tariff Proposal for FY 2019-20 .......................................................................................... 46
3
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
4
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
List of Tables
Table 1: Category-wise Energy Sales (MU) for FY 2017-18 .......................................................... 14
Table 2: Actual Distribution Losses for FY 2017-18 ....................................................................... 14
Table 3: Approved Losses upto 33 kV level in other States ......................................................... 16
Table 4: Distribution Losses and AT&C losses approved by Different SERCs ......................... 17
Table 5: Energy Requirement for FY 2017-18 (MU) ...................................................................... 17
Table 6: Energy Drawal for FY 2017-18 (MU) ................................................................................ 18
Table 7: Actual Power Purchase Cost for FY 2017-18 ................................................................... 19
Table 8: Transmission Charges for FY 2017-18 (Rs. Crore) .......................................................... 21
Table 9: Employee Expenses for FY 2017-18 (Rs. Crore) .............................................................. 22
Table 10: R&M Expenses for FY 2017-18 (Rs. Crore)..................................................................... 22
Table 11: A&G Expenses for FY 2017-18 (Rs. Crore) ..................................................................... 23
Table 12: Actual O&M Expenses for FY 2017-18 (Rs. Crore) ....................................................... 24
Table 13: Capitalisation for FY 2017-18 (Rs. Crore) ....................................................................... 25
Table 14: Interest on Working Capital for FY 2017-18 (Rs. Crore) .............................................. 26
Table 15: Depreciation for FY 2017-18 (Rs. Crore) ......................................................................... 26
Table 16: Interest on Loan for FY 2017-18 (Rs. Crore) ................................................................... 27
Table 17: Return on Equity for FY 2017-18 (Rs. Crore) ................................................................. 28
Table 18: Non-Tariff Income for FY 2017-18 (Rs. Crore) .............................................................. 29
Table 19: Aggregate Revenue Requirement for FY 2017-18 (Rs. Crore) ..................................... 29
Table 20: Revenue Gap for FY 2017-18 (Rs. Crore) ........................................................................ 30
Table 21: Combined ARR approved for FY 2019-20 (Rs. Crore) ................................................. 31
Table 22: Power Purchase Expenses as a proportion of the ARR in other States (Rs. Crore) . 32
Table 23: Category-wise Revenue from Sale of Power in FY 2019-20 at Existing Tariff of FY
2018-19 (Rs. Crore) ............................................................................................................................. 34
Table 24: Revenue Gap for FY 2019-20 at Existing Tariff (Rs. Crore) ......................................... 35
Table 25: Average Cost of Supply & Average Realisation ........................................................... 35
Table 26: Comparative Average Cost of Supply & Average Billing Rate Approved by
different SERC’s for FY 2018-19 ....................................................................................................... 37
Table 27: Comparison of Domestic Tariff of selected States ........................................................ 40
Table 28: Increase in MSPCL approved ARR over last four years (Rs. Crore) .......................... 43
Table 29: State Government Subsidy for MSPDCL over five years (Rs. Crore) ........................ 43
Table 30: Average Tariff Increase Required ................................................................................... 45
Table 31: Existing & Proposed Category-wise Tariffs for FY 2019-20 ........................................ 48
Table 32: ARR for Wires Business for FY 2019-20 ......................................................................... 51
Table 33: Proposed Wheeling Charges for FY 2019-20 ................................................................. 52
5
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
1. Chapter 1: Introduction
To evacuate the power generated from the captive micro hydel power station (100 +
56) kW at Leimakhong to specific load centres of Palace Compound and main bazar
area of Imphal, the 20 km long, 11 kV line between Imphal and Leimakhong was
constructed for the first time in Manipur in 1930. The State was then having 26 km of
11 kV lines and 45 km of domestic lines to serve very few consumers in 7
villages/Leikais. The line and generating stations were owned by the then Manipur
State HE Board, constituted under the ex-officio Chairmanship of the Political Agent.
Subsequently, electricity was kept under the administrative control of the Public
Works Department, Government of Manipur. It was separated from the State PWD
and started functioning as an independent Department since February 1970.
The peak load demand of Manipur in 1971 was 3.6 MW only, which was met from the
State’s own generating stations and power purchased from the neighbouring
States/Electricity Boards at low voltage. The per capita consumption of energy was
4.84 kWh. The scenario abruptly changed after the purchase of bulk power from
Assam with the commissioning of 132 kV inter-State transmission line from Imphal to
Dimapur and 6.3 MVA, 132/33 kV sub-station at Yurembam in December 1981. The
situation improved further with the commissioning of Loktak Hydro Electric Project
having a capacity of 3x35 MW on 4 August, 1984.
6
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
During the years from 1984 to 1996, a number of Central Sector Power Projects, mostly
hydel projects, were commissioned in the North Eastern Region. Manipur State has a
share of about 7-8% in every project. Because of the power availability from such
projects, the peak demand of the State has increased gradually and in FY 2018-19, it
has increased to more than 200 MW.
After the enactment of Electricity Act 2003, various reforms have been initiated in the
power sector including restructuring of integrated State Electricity Boards into
separate Companies. With effect from 1 February, 2014, the Electricity Department of
Manipur (EDM) was restructured and separated into two different entities, viz., (1)
Manipur State Power Distribution Company Limited (MSPDCL), and (2) Manipur
State Power Company Limited (MSPCL).
Accordingly, MSPDCL is submitting the tariff filing for Wheeling and Retail Supply
Business to the Hon’ble Commission.
7
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
For the purpose of evacuating power from different sources in the North-Eastern
Region, the inter-State transmission network owned and maintained by PGCIL as well
as the intra-State transmission network owned by the Manipur State Power
Corporation Limited (MSPCL) is utilised. The existing intra-state transformation
capacity of 132 kV Substations in Manipur is 417 MVA and the length of the 132 kV
lines is 472.7 km of single circuit lines and 87.9 km of double circuit lines.
EDM filed the Tariff Petition for FY 2013-14 before Hon’ble JERC in April 2013 but the
same was not admitted by the Hon’ble Commission because of delay in filing of the
Petition and since the Order had to be issued before the start of the year. The Petition
for FY 2013-14 was kept by JERC for reference and record purposes. The Petition for
FY 2014-15 was filed by EDM by November 2013 and the Order was issued in
February 2014. The first Petition for approval for ARR and tariff for FY 2015-16 for
MSPDCL was filed by November 2014 and the Order was issued on 27 February, 2015.
The next Petition for Multi Year ARR approval for FY 2016-17 to FY 2017-18 and Tariff
Petition for FY 2016-17 was filed by MSPDCL by November 2015 and the Order was
issued on 29 February, 2016. The Petition for approval of Limited Provisional True up
of FY 2016-17 and determination of ARR and Tariff for the second MYT Control Period
from FY 2018-19 to FY 2022-23 was filed by MSPDCL in January 2018 and the Order
was issued on 12 March, 2018.
8
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
JERC (Multi Year Tariff) Regulations, 2014 requires the Licensees to submit the Tariff
Petition for the ensuing financial year before 30th November of the previous year. To
fulfil this statutory requirement, MSPDCL is filing the present Petition for approval of
Limited Provisional True up of FY 2017-18 and determination of Tariff for FY 2019-20
before 31st December 2018, in accordance with the JERC (MYT) Regulations, 2014, to
enable the issue of the Tariff Order for FY 2019-20, before the start of FY 2019-20.
MSPDCL being a utility undertaking distribution and retail supply function, the cost
and expenses of distribution and retail supply functions have been considered
together as approved by the Hon’ble Commission, and the Tariff Petition has been
filed for seeking approval of the Wheeling Charges and Retail Supply Tariff after
allocation of the total ARR of MSPDCL for FY 2019-20 into Wires ARR and Supply
ARR based on the Allocation Matrix specified in the JERC (MYT) Regulations, 2014.
In view of the above, MSPDCL hereby submits its Petition for Limited Provisional
True up of FY 2017-18, and determination of Tariff for FY 2019-20.
9
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
MSPDCL is filing the petition for the Petition for Limited Provisional True up of FY
2017-18, and determination of Tariff for FY 2019-20.
“4.2 The Multi-Year Tariff framework shall be based on the following elements, for
determination of Aggregate Revenue Requirement and expected revenue from tariff and
charges for Generating Company, Transmission Licensee, Distribution Wires Business
and Retail Supply Business:
…
(iii) Truing up of previous year's expenses and revenue based on Audited Accounts
vis-à-vis the approved forecast and categorisation of variation in performance as
those caused by factors within the control of the applicant (controllable factors) and
those caused by factors beyond the control of the applicant (uncontrollable factors),
shall be undertaken by the Commission:
…
(iv) The mechanism for pass-through of approved gains or losses on account of
uncontrollable factors as specified by the Commission in these Regulations;
(v) The mechanism for sharing of approved gains or losses on account of controllable
factors as specified by the Commission in these Regulations;
(vi) Annual determination of tariff for Generating Company, Transmission
Licensee, Distribution Wires Business and Retail Supply Business, for each
financial year within the Control Period, based on the approved forecast
and results of the truing up exercise.”(emphasis added)
10
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Thus, in accordance with the JERC (MYT) Regulations, 2014, MSPDCL is supposed to
submit final true up petition for FY 2017-18. MSPDCL respectfully submits that due
to unbundling of EDM in 2014, various structural, organizational, commercial,
financial and administrative aspects have had to be segregated in separate books for
the unbundled utilities. These processes were time consuming, which caused delay in
preparation of the Balance Sheet of MSPDCL for FY 2014-15. This delay has also
caused to postpone the finalization of the accounts for FY 2015-16, FY 2016-17, and FY
2017-18 and getting it audited by a statutory auditor.
Thus, due to aforesaid reasons, the annual accounts for FY 2017-18 could not be
finalized, hence, MSPDCL is unable to submit the True up Petition for FY 2017-18 in
accordance with the JERC (MYT) Regulations, 2014. As and when the accounts of FY
2017-18 are audited, MSPDCL shall file its final true up petition.
However, it is important to consider the actual data for past years because it forms the
base for future projections. Hence, MSPDCL is submitting the actual sales and power
purchase data for FY 2017-18, as well as the actual O&M expenses and finance related
costs for FY 2017-18. Based on the above, a limited provisional True up Petition has
been prepared for FY 2017-18. As only limited provisional True up for FY 2017-18 is
being claimed, MSPDCL has not requested for pass through of the provisional
Revenue Gap of FY 2017-18 and consequent sharing of gains and losses for FY 2017-
18 along with this Petition, and the same shall be claimed at the time of seeking final
true-up for FY 2017-18 based on audited accounts.
The JERC (MYT) Regulations, 2014 do not contain any provision for filing of Annual
Performance Review (APR) for the ongoing year, i.e., FY 2018-19. Hence, MSPDCL is
not filing any request for APR of FY 2018-19 along with this Petition.
Regulation 4.2 (vi) of the JERC (MYT) Regulations, 2014 reproduced above, clearly
specifies that the tariff for Distribution Wires Business and Retail Supply Business
shall be determined annually, for each financial year within the Control Period, based
on the approved forecast and results of the truing up exercise. As stated above,
MSPDCL has not requested for pass through of the provisional Revenue Gap of FY
2017-18 and consequent sharing of gains and losses for FY 2017-18 along with this
Petition, as only provisional true-up for FY 2017-18 has been claimed in this Petition.
The Hon’ble Commission has already approved the ARR for FY 2019-20 in the MYT
11
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Order dated 12 March, 2018 in Petition (ARR & Tariff) No. 1 of 2018. Hence, in
accordance with Regulation 4.2 (vi) of the JERC (MYT) Regulations, 2014, MSPDCL
has filed this Petition for determination of Tariff for FY 2019-20 based on the ARR
approved for FY 2019-20 in the above-referred MYT Order.
However, it is clarified that the actual sales and power purchase expenses as well as
other expenses like O&M expenses and capital related expenses in FY 2019-20 will be
different from that approved by the Hon’ble Commission in the above-referred MYT
Order. MSPDCL will claim the difference between the approved and actual amounts
in the true-up Petition for FY 2019-20, at the appropriate time.
12
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
MSPDCL is a Distribution Licensee, which fulfils the need for electricity of the
consumers in the State of Manipur. As explained earlier, MSPDCL is required to
submit the request for true-up for FY 2017-18 in this Petition, but since the audited
financial accounts of FY 2017-18 are not ready at the time of filing this Petition,
MSPDCL is unable to submit the final true up Petition. Hence, MSPDCL hereby
submits a limited provisional true-up of FY 2017-18 based on the actual sales, power
purchase quantum and costs, O&M expenses and capitalisation for FY 2017-18. As and
when the accounts of FY 2017-18 are audited, MSPDCL shall file its final true up
Petition. As only limited provisional True up for FY 2017-18 is being claimed,
MSPDCL has not requested for pass through of the provisional Revenue Gap of FY
2017-18 and consequent sharing of gains and losses for FY 2017-18 along with this
Petition, and the same shall be claimed at the time of seeking final true-up for FY 2017-
18 based on audited accounts. The main objective of this limited provisional true-up
Petition is to update the Commission regarding the Revenue Gap for FY 2017-18 based
on the actual expenses and revenue and after considering the actual State Government
Subsidy received for FY 2017-18, as compared to the ARR and Revenue Gap approved
by the Hon’ble Commission in the Tariff Order dated 28 February, 2017 for FY 2017-
18 in Petition (ARR & Tariff) No.2 of 2016. It may be noted that the true-up Petition is
not based on the comparison of the actual expenses and revenue for FY 2017-18 with
the expenses and revenue considered by the Hon’ble Commission in the Annual
Performance Review (APR) of FY 2017-18 in the MYT Order dated 12 March, 2018, as
in this Order, the Hon’ble Commission has not passed through the impact of the APR,
and has merely captured the values as they are the base values for the MYT period.
13
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Sl.
Category Approved Actual
No.
1 Kutir Jyoti 7 18.17
2 LT Domestic 372 336.57
3 LT Commercial 42 47.33
4 HT Commercial 6 0.00
5 Public Lighting 5 3.67
6 LT Public Water-works 4 1.24
7 HT Public Water-works 15 19.83
8 LT Agri & Irrigation 1 1.29
9 HT Agri & Irrigation 1 0.83
10 LT Small Industry 18 19.25
11 HT Bulk 95 106.63
12 Temporary - 0.14
13 HT Medium Industry 4 3.73
14 HT Large Industry 6 5.31
TOTAL 576 563.98
The actual energy sold by MSPDCL in FY 2017-18 was 563.98 MU, which is slightly
lower than the approved sales of 576 MU. MSPDCL requests the Hon’ble Commission
to approve the actual category-wise sales of 563.98 MU, as shown in the Table above.
Sl.
Particulars Unit Approved Actuals
No.
1 Total Power Purchase MU 1067.95 1056.38
Inter-State transmission loss in NER
2 for FY 2017-18 MU 28.30 27.68
14
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Sl.
Particulars Unit Approved Actuals
No.
3 Net Power Purchase (1-2) MU 1040.33 1028.70
4 UI Overdrawal MU 6.02
5 UI Underdrawal MU 13.34
6 Sale of Surplus Power MU 297 207.74
Net power available at State
7 periphery MU 1040.33 813.64
8 Intra-State Transmission Loss MU 37.45 81.36
Net Energy requirement at DISCOM
9 periphery for sale within State MU 1002.88 732.28
10 Energy Sales within the State MU 576 563.98
11 Distribution loss MU 129.88 168.29
Distribution Losses w.r.t. Energy
12 Input at DISCOM periphery % 22.98%
Distribution Losses w.r.t. Energy
18.40% 20.68%
13 Input at State periphery %
The actual surplus energy available and sold by MSPDCL in the Indian Energy
Exchange (IEX) in FY 2017-18 was 207.74 MU as compared to the surplus quantum of
297 MU approved by the Hon’ble Commission in the Tariff Order for FY 2017-18.
MSPDCL respectfully submits that the actual Distribution Losses are slightly higher
than the approved figures, on account of Manipur having a hilly terrain and
characterized by population spread throughout the State. The distribution system
network in the State consists of long length of distribution and LT lines. In recent
years, majority of the new connections through various schemes are in the LT
category, which inherently incurs higher Distribution Losses.
MSPDCL wishes to bring to the attention of the Hon’ble Commission that in the
above-said Order, the Distribution Losses have been calculated with reference to the
15
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
energy injected at the State Periphery, as the Distribution Losses for FY 2017-18 have
been considered as equal to the arithmetical difference between T&D Losses and
Transmission Losses of 3.6% approved by the Hon’ble Commission (i.e., 22% - 3.6% =
18.40%). Hence, for the purposes of Limited True-up for FY 2017-18, MSPDCL has also
calculated the Distribution Loss with reference to the energy injected at State
periphery, which works out to 20.68%. The corresponding Distribution Loss with
reference to the energy injected into the distribution system works out to 22.98%.
The inter-State Transmission loss has been considered as 2.62%, based on the Interstate
transmission loss in North-Eastern Region for FY 2017-18, and has been deducted
from the total Power Purchase quantum. Further MSPDCL has added the UI
Overdrawal and subtracted UI Underdrawal and Surplus sales from the Net Power
Purchase to compute the Net Power available at State Periphery for sale within the
State of Manipur.
MSPDCL has considered the intra-State Transmission (MSPCL) loss of 10% for
computing the power available at the DISCOM periphery. The Hon’ble Commission
has been allowing intra-State Transmission losses of only 3.6%. MSPDCL respectfully
submits that in other States, 33 kV system is part of the distribution network, whereas,
in Manipur, the 33 kV system is part of MSPCL network, and the distribution network
is from 11 kV and below voltages. Thus, when other SERCs have approved intra-State
Transmission Losses of around 3 to 4%, the 33 kV losses have also been separately
approved as around 5-6%, which works out to total losses of around 10% upto 33 kV
level. The relevant data from some selected States, based on data available in the
public domain, is given in the Table below:
Hence, the intra-State Transmission (MSPCL) loss of 10% considered by MSPDCL for
computing the Energy Balance is appropriate and needs to be allowed.
16
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Further, MSPDCL respectfully submits that the Distribution Losses approved by the
other SERCs are generally higher than the Distribution Losses approved by the
Hon’ble Commission, as shown in the Table below:
Utility/ Approved by
State Particulars Order Reference
Department Commission
Arunachal AT&C Losses Department of Petition No. TP 01 44%
Pradesh for FY 2016- Power, of 2018, dated 31
17 Government of May, 2018
Arunachal
Pradesh
Meghalaya Distribution Meghalaya Power Case No. 1/2018, 21%
Losses for FY Distribution dated 25
2017-18 Corporation September, 2018
Bihar Distribution NBPDCL Case No. 40 of 2017 24%
Losses for FY
2017-18
Source: Latest Tariff Orders of respective SERCs
It is further submitted that MSPDCL has been incorporated in recent years and it has
taken significant steps over the years to reduce the Distribution Losses. Hence, in view
of all the above, MSPDCL requests the Hon’ble Commission to approve the actual
Distribution Losses of 20.68% for FY 2017-18.
Sl.
Particulars Approved Actuals
No.
1 Energy Sales 576 563.98
17
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Sl.
Particulars Approved Actuals
No.
2 Distribution Loss 18.40% 20.68%
3 Distribution loss Quantum 129.88 168.29
Energy Requirement at Distribution
4 Periphery for sale within the State 705.88 732.28
MSPDCL respectfully submits that the actual energy requirement was 732.28 MU,
which is slightly higher than the 705.88 MU approved by the Hon’ble Commission in
its Order dated 28 February, 2017. The higher energy requirement is attributable to
the higher actual Distribution Losses. As elaborated earlier, the Distribution Losses
approved by the Hon’ble Commission are lower and the actual Distribution Losses
are required to be allowed. Accordingly, MSPDCL requests the Hon’ble Commission
to approve the actual Energy Input in the Limited True-up for FY 2017-18.
18
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
As can be seen from the above Table, the actual power purchase quantum in FY 2017-
18 was 1056.38 MU, which is slightly lower than the approved quantum of 1067.95
MU. The reason for this deviation may be attributed to lower purchase of power from
NTPC Bongaigaon and Baramura GBPP Unit IV and V, and non-availability of power
from the projected new source of Kameng HEP. MSPDCL requests the Hon’ble
Commission to approve the actual power purchase quantum of 1056.38 MU in the
Limited provisional truing up for FY 2017-18.
Approved Actual
Sl. Total Average Total Average
Plant
No Cost (Rs Rate Cost (Rs Rate
Crore) (Rs/kWh) Crore) (Rs/kWh)
A Own Generation
1 Leimakhong - Micro Hydel
2 Various Diesel Generating plants 1.19
B CGS – NEEPCO
1 Kopili -I HE 6.21 0.97 8.91 1.17
19
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Approved Actual
Sl. Total Average Total Average
Plant
No Cost (Rs Rate Cost (Rs Rate
Crore) (Rs/kWh) Crore) (Rs/kWh)
2 Kopili-II HE 1.25 1.84 0.96 1.25
3 Khandong HE 2.83 2.64 2.91 1.76
4 Ranganadi HE Project 31.51 2.96 25.81 2.21
5 Doyang HE Project 7.85 4.33 10.03 4.90
6 Assam GBPP 52.66 3.96 39.69 3.37
7 AGTPP 32.16 4.36 15.50 2.88
C CGS – NHPC
1 Loktak HE (Purchased) 52.76 2.93 66.29 2.68
2 Free Power 0 0 0 0
D Others
1 Baramura GBPP Unit IV and V 25.37 3.1 12.43 3.00
2 OTPC Pallatana 62.10 2.82 72.29 3.25
3 NTPC Bongaigaon Thermal PP 25.86 3.09 49.46 *
4 Kameng HEP Stage I 4.69 2.55
5 Renewable Solar 1.02
6 Non-Solar 11.06
7 IEX 3.04
317.33 2.97 307.31 2.88
Total
1 UI Overdrawal 1.574
2 UI Underdrawal 2.304
3 NERLDC Charges 0.64
4 Arrears/Supplementary Bills 25.37
5 Reimbursement 4.68
6 Total Power Purchase Excluding
Transmission Charges
337.26
Note: * MSPDCL has surrendered part of the power entitlement of NTPC Bongaigaon, as the Energy
Charges were on the higher side and MSPDCL was unable to earn that much amount through sale of
surplus power on the Exchange. However, Fixed Charges are still payable, unless NTPC is able to find
a buyer for the surrendered power. The actual average Energy Charges of NTPC Bongaigaon in FY
2017-18 was Rs. 2.993/kWh, while the Fixed Charges paid to NTPC Bongaigaon were Rs. 40.55 crore in
FY 2017-18.
20
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
The total actual power purchase cost including UI over-drawal and under-drawal,
NERLDC Charges, and arrears /supplementary bills in FY 2017-18 was thus, Rs.
337.26 Crore as compared to the approved figure at Rs. 317.33 Crore. These power
purchase costs are payable by MSPDCL as they are determined by CERC and
MSPDCL has no control over the same. MSPDCL requests the Hon’ble Commission
to approve the actual power purchase costs for FY 2017-18, as shown above.
21
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
The actual employee expenses are lower than the employee expenses approved by the
Hon’ble Commission for FY 2017-18. MSPDCL requests the Hon’ble Commission to
approve the actual Employee Expenses of Rs. 74.20 Crore for FY 2017-18.
22
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
MSPDCL requests the Hon’ble Commission to approve the actual R&M expenses of
Rs. 8.91 Crore for FY 2017-18.
The Commission approved A&G Expenses of Rs. 2.65 Crore in the Tariff Order for FY
2017-18. MSPDCL has actually incurred A&G expenses of Rs. 7.31 Crore in FY 2017-
18, as shown in the Table below:
23
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
The actual A&G expenses in FY 2017-18 are significantly lower than the actual A&G
expenses in FY 2016-17 (Rs. 10.98 crore), as approved by the Hon’ble Commission in
the Limited Provisional true-up for FY 2016-17. MSPDCL requests the Hon’ble
Commission to approve the actual A&G expenses of Rs. 7.31 Crore for FY 2017-18.
The total O&M expenses incurred in FY 2017-18 are shown in the Table below:
The actual O&M expenses are thus, lower than the O&M expenses approved by the
Hon’ble Commission in the Tariff Order for FY 2017-18. MSPDCL requests the
Hon’ble Commission to approve the actual O&M expenses of Rs. 90.42 Crore for FY
2017-18.
3.8 Capitalisation
MSPDCL undertakes capital expenditure to meet the growing demand for electricity
in the State and for system augmentation and strengthening. MSPDCL receives
significant grant from the State Government for creation of capital asset, as well as
consumer contribution for capital works, with the balance funding sourced from
loans.
The details of actual capitalization achieved in FY 2017-18 vis-à-vis the capitalisation
approved by the Hon’ble Commission in the Tariff Order for FY 2017-18, is shown in
the Table below:
24
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
25
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
(d) Amount held as security deposits under clause (a) and clause (b) of sub-section (1) of
Section 47 of the Act from consumers except the security deposits held in the form of Bank
Guarantees;
(ii) Interest shall be allowed at a rate equal to the State Bank Advance Rate (SBAR) as on
1st April of the financial year in which the Petition is filed.”
The computation of normative Interest on Working Capital (IoWC) for MSPDCL for
FY 2017-18, in accordance with the above-reproduced Regulations, is shown in the
Table below:
MSPDCL requests the Hon’ble Commission to approve the IoWC of Rs 4.89 Crore for
FY 2017-18.
26
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
MSPDCL respectfully submits that since 10% of the capital cost of every scheme is
financed by MSPDCL, either through loan or equity, depreciation has been claimed
equal to 10% of Gross Depreciation, as depreciation cannot be claimed on assets
funded by Government Grants and Consumer Contribution.
MSPDCL requests the Hon’ble Commission to approve the Depreciation of Rs. 1.96
Crore, as sought by MSPDCL.
27
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
MSPDCL requests the Hon’ble Commission to kindly approve the actual interest on
loan of Rs. 6.70 Crore for FY 2017-18.
MSPDCL requests the Hon’ble Commission to approve the Return on Equity of Rs.
1.95 Crore for FY 2017-18.
28
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
MSPDCL requests the Hon’ble Commission to approve the actual Non-Tariff Income
of Rs. 5.35 Crore for FY 2017-18.
29
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
The ARR for FY 2017-18 is Rs. 540.37 Crore, which is very close to the ARR of Rs.
540.04 Crore approved by the Hon’ble Commission for FY 2017-18 in its Tariff Order
dated 28 February, 2017. MSPDCL requests the Hon’ble Commission to approve the
same.
As can be seen from the above Table, the Unmet Revenue Gap for FY 2017-18 is Rs.
34.43 Crore, largely because the State Government has provided revenue subsidy of
Rs 213.06 Crore. The actual revenue gap can only be finalized during the actual Truing
up process for FY 2017-18, and MSPDCL shall seek pass through of such amounts with
associated carrying cost and sharing of efficiency gains and losses at that time.
30
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
As can be seen from the above Table, power purchase cost including Transmission
inter-State and intra-State Charges contribute 81% of the approved ARR of MSPDCL.
MSPDCL has no control over these costs, as these are levied by Central Sector entities
31
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
regulated by CERC whose tariffs are approved by CERC, while the intra-State
Transmission Charge of MSPCL is approved by the Hon’ble Commission.
Power purchase expenses generally contribute around 70% to 90% of the ARR of
Distribution Licensees in the country as shown in the Table below, and in case of
MSPDCL also, it is around 81%.
Table 22: Power Purchase Expenses as a proportion of the ARR in other States (Rs.
Crore)
Sl. Amount
State/Utility Particulars % of Total
No.
Power Purchase Expenses 3234.7 58.03%
Assam Transmission Charges
1 1160.64 20.82%
(APDCL) NERLDC/SLDC charges
Total Power Purchase Expenses 78.85%
Power Purchase Expenses 5476.4 77.71%
PGCIL & Other Transmission
charges 390.46 5.54%
Bihar
2 BSPTCL Transmission charges 549.41 7.80%
(NBPDCL)
BGCL charges 127.07 1.80%
SLDC 1.97 0.03%
Total Power Purchase Expenses 92.88%
Power purchase cost 11021.51 79.57%
Inter-State transmission charges - -
Haryana Intra-State transmission charges and
3
(DHVNL) SLDC charges 901.50 6.51%
SLDC charges 2.86 0.02%
Total Power Purchase Expenses 86.10%
Power Purchase Expenses 47901.00 70.74%
Inter-State transmission charges 2688.00 3.97%
Maharashtra
4
(MSEDCL) Intra-State transmission charges and
MSLDC Charges 4303.00 6.35%
Total Power Purchase Expenses 81.07%
Power Purchase Expenses 18720.13 66.92%
Transmission charges payable to
5 Punjab
PSTCL 1281.99 4.58%
Total Power Purchase Expenses 71.50%
Power Purchase Expenses 23473.41 78.19%
6 Telangana
Inter-State transmission charges 922.72 3.07%
32
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Sl. Amount
State/Utility Particulars % of Total
No.
Intra-State Transmission charges 1408.07 4.69%
SLDC charges 34.49 0.11%
Total Power Purchase Expenses 86.07%
Power Purchase Expenses (including
Inter-State Transmission charges,
7 Delhi Intra-State Transmission charges and
SLDC charges)
5015.94 77.09%
As power purchase expenses comprise a large part of the ARR, other SERCs have been
approving tariffs such that the Distribution Licensees is able to recover the
major/entire portion of its ARR. This highlights the fact that there is an urgent need
to upwardly revise the tariffs charged by MSPDCL, so that it is able to recover the
power purchase expenses as well as other expenses, as the revenue from existing
tariffs are very low, as discussed below.
1. Revenue from sale of power for FY 2019-20 at existing tariff has been determined
based on the category-wise energy sales approved by the Hon’ble Commission in
the MYT Order for FY 2019-20 and the category-wise tariff approved by the
Hon’ble Commission in the MYT Order for FY 2018-19.
2. Revenue from sale of power at existing tariff is estimated to be Rs 310.71 crore for
FY 2019-20.
3. For FY 2019-20, while approving the Energy Balance, the Hon’ble Commission has
approved quantum of surplus power to be sold by MSPDCL, as 375.12 MU. As the
actual distribution losses as well as the intra-State losses in Manipur are much
higher than that approved by the Hon’ble Commission, the actual quantum of
surplus power that would be available to MSPDCL for sale, would be significantly
33
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
lower. However, for the purposes of this Petition, MSPDCL has considered the
same quantum of surplus power to be sold, as the ARR approved by the Hon’ble
Commission for FY 2019-20 is being considered in totality.
4. MSPDCL has sold surplus power in the IEX at an average rate of Rs. 2.65/kWh in
FY 2017-18 and at an average rate of Rs. 2.65/kWh in the first half of FY 2018-19
(April to September). Accordingly, MSPDCL has considered that it will be selling
the surplus power at Rs 2.65/kWh in FY 2019-20. The impact of the difference in
the quantum of surplus power and the rate for sale of surplus power, shall be
claimed at the time of true-up for FY 2019-20. The estimated revenue from sale of
surplus power in FY 2019-20 based on the approved quantum of surplus power
and the expected rate for sale of surplus power, thus works out to Rs. 99.41 crore.
5. The Table below summarizes the category-wise revenue from sale of power at
existing tariff for FY 2019-20:
34
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Table 24: Revenue Gap for FY 2019-20 at Existing Tariff (Rs. Crore)
Thus, MSPDCL has estimated that it will face a Revenue Gap of Rs. 331.38 crore in FY
2019-20, based on the approved ARR and expected revenue from existing tariff.
The projected Average Cost of Supply and Average Realisation from sale of power for
FY 2019-20 are shown in the Table below:
FY 2019-
Legend/ Formula Units
Sl. Particulars 20
1 Net Revenue Requirement A Rs. Crore 741.49
2 Revenue from existing tariff B Rs. Crore 310.71
3 Revenue from sale of surplus power C Rs. Crore 99.41
4 Total Revenue D=B+C Rs. Crore 410.11
5 Revenue Gap E=A-D Rs. Crore 331.38
6 Energy Sales F MU 600.00
7 Surplus Power to be sold G MU 375.12
8 Total Sales H=F+G MU 975.12
9 Average Cost of Supply I = (A x 10)/H Rs/kWh 7.60
10 Average Realisation from sale of power J = (B x 10)/F Rs/kWh 5.18
11 Average Rate for Sale of surplus power K = (C x 10)/G Rs/kWh 2.65
35
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
FY 2019-
Legend/ Formula Units
Sl. Particulars 20
12 Average Rate for sale of all power L = (B + C) x 10/H Rs/kWh 4.21
13 Average rate for Unmet Revenue Gap M = (E x 10)/H Rs/kWh 3.40
The method proposed by MSPDCL to recover the above estimated Revenue Gap is
discussed in the following paragraphs.
Regulation 4.2 (vi) of the JERC (MYT) Regulations, 2014 is reproduced below again for
reference:
Thus, in accordance with the above Regulations, it is expected that the Hon’ble
Commission shall determine the category-wise tariffs in such a manner that the entire
approved ARR of MSPDCL is recovered from the category-wise tariffs.
Further, the State Government subsidy referred to in the Electricity Act, 2003 and JERC
(MYT) Regulations, 2014 is category-wise subsidy with respect to category-wise tariff
approved by the Hon’ble Commission, i.e., targeted subsidy. Regulation 21.1 of the
JERC (MYT) Regulations, 2014 is reproduced below for reference:
“21.1 With effect from the first day of April 2015, if the State Government requires the grant
of any subsidy to any consumer or class of consumers in the tariff determined by the
Commission, the State Government shall, notwithstanding any direction which may
be given under Section 108 of the Act, pay in advance the amount to compensate the
Distribution Licensee/person affected by the grant of subsidy, as a condition for the
Licensee or any other person concerned to implement the subsidy provided for by the
State Government, in the manner specified in these Regulations:
36
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Provided that no such direction of the State Government shall be operative if the
payment is not made in accordance with the provisions contained in these Regulations
and the tariff fixed by the Commission shall be applicable from the date of issue of
orders by the Commission in this regard.”
Thus, the Hon’ble Commission is required to determine full cost tariffs in such a
manner that the entire approved ARR of MSPDCL is recovered from the approved
category-wise tariffs, and if the State Government desires to subsidise any specific
category, it may do so in accordance with the provisions of the Electricity Act, 2003
and JERC (MYT) Regulations, 2014, and compensate MSPDCL for the corresponding
loss of revenue.
MSPDCL has compiled data from Tariff Orders issued by other SERCs, which clearly
shows that the SERCs are generally issuing Tariff Orders where the Average Billing
Rate (ABR) matches the Average Cost of Supply (ACoS). Even in States where there is
a gap between the ACoS and ABR, the gap is much lesser than that being approved
by the Hon’ble Commission, as shown in the Table below:
Table 26: Comparative Average Cost of Supply & Average Billing Rate Approved
by different SERC’s for FY 2018-19
ACoS-ABR %
State Utilities ABR ACoS
Gap Variation
Punjab 6.34 6.55 0.21 -3.15%
Chhattisgarh 6.20 6.20 0.00 -0.04%
Maharashtra 6.63 7.25 0.62 -8.55%
Himachal Pradesh 5.59 5.59 0.00 0.00%
Madhya Pradesh 6.03 6.03 0.00 0.00%
Assam 7.35 7.35 0.00 0.00%
Manipur 5.12 7.42 2.30 -31.00%
Further, the Hon’ble Commission, while approving the ARR of MSPDCL, has already
factored in the desired efficiency improvements and approves only the expenses that
are considered to be legitimately recoverable from the consumers, in the opinion of
the Hon’ble Commission. The Hon’ble Commission is well aware that the actual
Distribution Losses and intra-State Transmission Losses of MSPCL are significantly
higher than that being approved by the Hon’ble Commission on normative basis.
37
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Thus, there is no further scope for meeting any part of the approved ARR through
efficiency improvements, and the entire approved ARR has to be met either through
tariff payable by the consumers.
Further, it needs to be appreciated that the existing revenue from sale of electricity
does not even meet the power purchase cost from different sources, leave alone power
purchase cost including inter-State and intra-State Transmission Charges. The
Revenue from sale of power at existing tariff for FY 2019-20 is estimated at Rs. 310.71
crore, whereas the approved cost of power purchase cost including inter-State and
intra-State Transmission Charges for FY 2019-20 is itself Rs. 601.06 crore, i.e., Revenue
from sale of electricity can meet only 51.69% of the power purchase cost including
inter-State and intra-State Transmission Charges. The remaining 48.31% of the power
purchase cost, and other expenses, viz., O&M expenses, interest expenses, etc., have
to be met through some other sources.
It may be noted that generally, some of the categories are subsidising consumers, i.e.,
their Average Billing Rate (ABR) is higher than the ACoS, and such subsidising
consumers cross-subsidise the subsidised consumers, whose ABR is lower than the
ACoS. However, in case of MSPDCL, as the ABR of all categories is lower than the
ACoS, i.e., all the categories are subsidised, and there is no subsidising consumer
category. This highlights the fact that the tariffs of MSPDCL are at very low levels,
which is unsustainable, and there is an urgent need to rationalise the tariffs of all
consumer categories.
Further, in the MYT Order, the Hon’ble Commission has relied upon the trajectory of
technical performance parameters agreed in the tri-partite UDAY MoU signed
between MSPDCL, Government of Manipur, and Government of India. However, the
same UDAY MoU also lays down the following financial parameters:
a. The gap between ACoS and ABR has to be eliminated by FY 2018-19; however,
MSPDCL is able to recover less than 50% of the ARR approved by the Hon’ble
Commission through the tariffs approved by the Hon’ble Commission.
b. The tariff should have been increased as per the following trajectory:
38
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Average Tariff Rs. 4.12/kWh Rs. 4.46/kWh Rs. 5.13/kWh Rs. 6.00/kWh
(UDAY)
As can be seen from the above Table, the Hon’ble Commission has increased
the tariffs by only 5.6% in FY 2017-18 and 7.23% in FY 2018-19, though the
average tariff increase as per UDAY and as sought by MSPDCL were much
higher.
The financial aspects of the UDAY MoU cannot be separated from the technical
aspects, and in the absence of adequate tariff increases, MSPDCL cannot be expected
to achieve the technical performance parameters. Hence, adequate tariff increases are
essential and MSPDCL requests the Hon’ble Commission to approve the appropriate
and adequate tariff increase.
MSPDCL has also provided a comparison of the tariff for the domestic category
prevailing in selected States, which clearly shows that the tariff in Manipur is
significantly low and there is lot of scope for upwardly revising the tariffs of all
categories including the domestic category.
39
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Domestic A-below 5 kW
BPL 20 1.06
Unmetered 350
Metered
40
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Demand Based
Category III
41
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
upto 100
kVA
Above 100
All Units 70/kVA 6.44/kVAh
kVA
LT I (B)(ii): Above 200 units/Month
0-200 5.00
201-300 7.20
6 Telangana
301-400 8.50
401-800 9.00
Above 800 Units 9.50
Rs.125/kW
Upto 2 kW /month
0-200 Units-Rs.
Rs.140/kW
3.00,
>2kW and ≤5kW /month
201-400 Units-
Rs.175/kW
Rs. 4.50,401-
>5kW and ≤15 kW /month
800 Units-Rs.
Rs.200/kW
6.50,801-1200
Delhi >15 kW and ≤25 kW /month
7 Units-Rs. 7.00,
(TPDDL)
Above 1200
Rs.250/kW Units-Rs. 7.75
>25 kW
/month
Rs.
Single Point Delivery supply at 11 kV for 150/kW/m
GHS onth Rs.4.50/kWh
8 Manipur Kutir Jyothi
Domestic
Further, the Hon’ble Commission will appreciate that MSPDCL’s own contribution to
its ARR is only Rs. 140.43 crore, after excluding cost of power purchase and
transmission charges, which are payable to other agencies based on regulated tariffs,
and are hence, uncontrollable for MSPDCL. Thus, MSPDCL’s contribution is only 19%
42
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
of the approved ARR of Rs. 741.49 crore, which works out to Rs. 1.44 per kWh,
considering the total energy handled by MSPDCL. In comparison, the approved ARR
of MSPCL for FY 2019-20, which is a much smaller organisation, is Rs. 86.57 crore
which is completely passed through to MSPDCL and contributes Rs. 0.90 per kWh to
MSPDCL’s Average Cost of Supply of Rs. 7.62/kWh. Further, the ARR approved for
MSPCL in recent years has increased steeply, by 79% and 26% in FY 2017-18 and FY
2018-19, as shown in the Table below:
Table 28: Increase in MSPCL approved ARR over last four years (Rs. Crore)
Sl. Particulars
No. FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20
Approved ARR of
1 MSPCL 36.08 64.54 81.49 86.57
2 Annual Increase (%) 79% 26% 6%
Thus, it needs to be appreciated that the estimated Revenue Gap of Rs. 331.38 crore is
higher than the Revenue from sale of power at existing tariff, i.e., Rs. 310.71 crore. In
other words, if the entire Revenue Gap has to be recovered from the revised tariff,
then the average tariff increase would amount to 107%, which is impractical and
would amount to a tariff shock. Hence, for some years at least, the dependence on
revenue subsidy support from the State Government would have to continue.
However, there is an urgent need to steeply increase the category-wise tariffs to be
charged by MSPDCL, so that the recovery of the ARR through tariffs is increased
significantly, and MSPDCL’s dependence on State Government subsidy is reduced
significantly and eventually eliminated in the next 3-4 years.
The revenue subsidy provided by the State Government over the last 5 years is shown
in the Table below:
Table 29: State Government Subsidy for MSPDCL over five years (Rs. Crore)
43
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
It is seen from the above Table that the revenue subsidy has reduced from Rs. 258.29
crore in FY 2014-15 to Rs. 220 crore (Budget Estimate) in FY 2018-19. The reduction in
subsidy support is primarily for the bigger account heads of power purchase subsidy,
which has reduced from Rs. 170 crore in FY 2014-15 to Rs. 120 crore in FY 2018-19.
Further, for FY 2018-19, out of a total committed subsidy of Rs. 120.00 Crore for power
purchase, so far the State Government has released only 30 Crore (only 25%). This
non-release of subsidy will affect the payment capacity of MSPDCL towards the
Power Generators (CPSU Bills) and the outstanding bills along with the applicable
surcharge will be carried forward (apportioned) in the next Year.
It should be noted that the State’s tax base is very narrow and more than 90% of the
State’s total revenue receipts comes from Central transfers. More than 80% of the
State’s total expenditure in a year are financed out of Central receipts, whereas the
balance is met out of the State’s own revenue receipts and borrowings.
During FY 2018-19, there has been a huge shortfall in receipts from share in Central
taxes, a major central receipt, vis-à-vis the amount assessed by the 14th Finance
Commission (FC). Cumulative gap during the first 3 years of the 14th FC award period
(FY 2015-16 to FY 2017-18) has been Rs 1431 crore. In addition, the current trend of
devolution points towards the shortfall in FY 2018-19 as well. The trend shows that
during FY 2018-19, total devolution will be around Rs 4148 crore only against the
assessment of Rs 5522 crore by the 14th Finance Commission. This may leave a huge
gap of about Rs 1374 crore during this year alone, taking the total gap between the
assessment by the 14th Finance Commission and the actual devolution of Central taxes
during the first 4 years of the period 2015-20 to a staggering level of Rs 2805 crore.
Further, during the current year, due to shortfall in provision for committed
expenditures, mainly salary and pension expenditures, realization of lesser than
estimated receipts and high estimates of opening balance, there is an estimated
shortfall of Rs. 1900 crore (approx.) in the current year’s Budgetary outlay. Over and
above these, there are other committed liabilities of Rs 2600 crore (approx.) for which
resources have to be met out of current year’s budgetary resources.
As a result of the shortfall in Central revenue transfers and budgetary resources, and
ballooning committed liabilities, the State Government is passing through a period of
44
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
severe resource crunch. This has led to shrinking fiscal space for capital and
developmental expenditure, as substantial portion of these transfers are pre-empted
by committed revenue expenditures like salary, pension, repayment liabilities,
interest payments and grant-in-aid to different bodies including subsidies for power
purchase. The magnitude of the gap has widened to such an extent that a complete
ban on encashment of bills have been imposed in Treasuries and Banks except those
relating to salary and pension bills.
In order to deal with the severe resource crunch, the State Government has taken up
various expenditure rationalization measures. An important aspect of these measures
will be to cut down subsidy support to different State parastatal bodies including State
power utilities and make them self- sustainable. In this regard, there is an urgent need
to arrest the increasing Revenue Gap of the State power utilities, which is
unsustainable. The Revenue Gap has ranged around Rs 218 crore to Rs. 293 crore in
the last 2-3 years. With periodic increase in the unit cost of power purchase, the
Revenue Gap is expected to widen even further. Given such a situation and the current
state of State’s finances, unless the Revenue Requirement of the Utilities is
substantially covered up by increase in the electricity tariff, the State Government will
not be in a position to further subsidize the power utilities and the power scenario in
the State could deteriorate, as MSPDCL will be unable to pay its power purchase bills,
with possibilities of return to the load shedding days.
The latest figure of Revenue Subsidy to be provided by the State Government is Rs.
220 crore for FY 2018-19. In view of all the above, MSPDCL has considered that the
State Government would provide revenue subsidy support in FY 2019-20 to the extent
of Rs. 220 crore, in addition to any Grants for creation of capital assets.
The balance Revenue Gap of Rs. 111.38 crore would thus, have to be recovered from
the consumers through an average tariff increase of 36%, as shown in the Table below:
45
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
2. The provisions of the Section 61 (g) of the Electricity Act, 2003 state that the
Appropriate Commission should be guided by the objective that the tariff
progressively reflects the efficient and prudent cost of supply of electricity. In
line with the above provision, the Tariff Policy also stipulates that the tariffs
should be within ± 20 % of the Average Cost of Supply (ACoS). However, in
the present scenario, all the tariff categories are subsidised w.r.t. the ACoS.
Hence, it is impractical to burden the consumers with a tariff shock in order to
revise their tariffs within ± 20 % of the ACoS straightaway. Considering these
limitations, MSPDCL has formulated its tariff proposal with an endeavour to
progressively reduce the cross-subsidies, without giving any tariff shock to the
consumers.
3. As such MSPDCL has proposed an average Tariff increase of 36% for FY 2019-
20 to partially meet the approved ARR and estimated Revenue Gap and ACoS.
It may be noted that subsidy support of Rs. 220 crore from the State
Government has been considered for meeting the balance Revenue Gap.
46
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
7. MSPDCL has proposed a lower tariff increase for the first and second slab of
LT domestic category, in order to minimise the tariff shock to the lower end
consumers, and on account of the telescopic tariffs, all the domestic category
consumers will benefit from the lower tariffs of the first two slabs, i.e., 0-30 and
31-100 units units per month. The tariff for the higher consumption slabs in the
domestic category has been increased at a higher rate, in order to generate the
desired revenue, as domestic category comprises more than 60% of the total
consumption of MSPDCL.
8. The tariff increase for the Public Utilities, i.e., Public Lighting and Public Water
Works, has also been proposed lower than the average tariff increase of 36%,
as the Public Utilities are providing essential services to the common
population of the State, which should not suffer.
10. It is proposed to retain the tariff of small industries lower than that of
commercial category.
47
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
11. MSPDCL has also attempted to maintain the cross-subsidy between consumer
categories within the range of +20% stipulated by the Tariff Policy, though for
some categories, this has not been possible despite significant tariff increases.
12. Accordingly, the MSPDCL requests the Hon’ble Commission to revise the tariff
structure as summarized below:
Note: In the existing Tariff Schedule, the first consumption slab is 0-100 units/month, but
shown as two slabs of 0-30 units/month and 31-100 units/month with same tariff for both
48
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
slabs, in order to show the comparison with proposed tariffs. Modifications proposed to the
Tariff Schedule
While implementing the Tariff Schedule approved by the Hon’ble Commission for FY
2018-19 in the MYT Order, MSPDCL has faced certain difficulties. MSPDCL has also
observed certain inconsistencies between the approved Tariff Schedule and the JERC
Supply Code, 2013. Accordingly, MSPDCL requests the Hon’ble Commission to
modify the following clauses of the Tariff Schedule, based on the justification
provided:
“1.13 Billing demand: The billing demand shall be the maximum recorded demand or 75% of
the contracted demand whichever is higher.”
However, in the JERC (Electricity Supply Code) Regulations, 2013, the Billing Demand
is defined as under:
As can be seen from the above extracts, the definition of Contract Demand in the Tariff
Schedule is inconsistent with the definition of Contract Demand as per the JERC
Supply Code Regulations, as the Tariff Schedule states one of the clauses as 75% of
Contract Demand, whereas the JERC Supply Code stipulates the related clause as
Contract Demand. Hence, MSPDCL requests the Hon’ble Commission to modify the
definition Contract Demand in the Tariff Schedule to make it consistent with the
definition of Contract Demand as per the JERC Supply Code Regulations, and
stipulate the relevant clause as “contract demand” rather than “75% of contract
demand”.
49
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
In clause 1.7 of the Tariff Schedule, sub-clauses a) to f), the applicability of Power
Factor Incentive/Surcharge is stipulated under different conditions and for different
levels of Power Factor. However, from the wording, it may be interpreted that the
Power Factor Incentive/Surcharge is applicable to all consumer categories. However,
the Power Factor Incentive/Surcharge is applicable only for HT consumers and LT 3-
phase consumers and LT Industrial consumers. Hence, MSPDCL requests the Hon’ble
Commission to kindly modify sub-clauses a) to f) of clause 1.7 of the Tariff Schedule,
to state that “If the average monthly power factor of the HT consumer or LT 3-phase
consumer or LT Industrial consumer…” rather than “If the average monthly power
factor of the consumer…”
In Annexure 11.19 of the JERC Supply Code, the assessment formula for calculation
of the consumption due to theft of electricity has been specified as under:
50
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
“
MSPDCL has interpreted the above clause as under:
Wires Retail
Total Business Supply Wires Supply
Sl. Particulars ARR (%) Business (%) ARR ARR
A Expenditure
51
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Wires Retail
Total Business Supply Wires Supply
Sl. Particulars ARR (%) Business (%) ARR ARR
1 Cost of power purchase 452.66 0% 100% 0.00 452.66
Inter-State Transmission
0% 100%
2 charges 61.12 0.00 61.12
Intra-State Transmission
0% 100%
3 charges 86.57 0.00 86.57
4 NERLDC Charges 0.71 0% 100% 0.00 0.71
5 O&M Expenses 123.82 75.65 48.17
Employee Expenses 106.68 60% 40% 64.01 42.67
Repair & Maintenance
90% 10%
Expenses 7.69 6.92 0.77
Administrative & General
50% 50%
Expenses 9.45 4.73 4.73
6 Depreciation 0.31 90% 10% 0.28 0.03
7 Interest on Loan 5.17 90% 10% 4.65 0.52
8 Interest on Working Capital 6.59 10% 90% 0.66 5.93
9 Provision for bad debts 3.00 0% 100% 0.00 3.00
Total Cost 739.95 81.24 660.01
B Add: Return on Equity 1.95 90% 10% 1.76 0.20
Add: Income Tax 0.00 90% 10% 0.00 0.00
B: Total 1.95 1.76 0.20
C Total ARR: A+B 741.90 83.00 660.20
D Less (Non-Tariff Income) 0.41 10% 90% 0.04 0.37
Sub-total (D) 0.41 0.04 0.37
Net Aggregate Revenue
Requirement (C-D) 741.49 82.96 658.53
The proposed Wheeling Charges for FY 2019-20 have been computed based on the
methodology adopted by the Hon’ble Commission for determining the Wheeling
Charges for FY 2018-19 in the MYT Order dated March 12, 2018, as shown in the Table
below:
52
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
5. Tariff Schedule
5.1.1 Rebate for advance payment: For payment of energy bill in advance, a
rebate of 1% shall be allowed on the rate of charge of the applicable Tariff.
This will be applicable only for all consumers provided with prepaid
meters.
5.1.2 Rebate/surcharge for availing supply at voltage higher/lower than base
voltage: Those who avail supply at higher voltage than the classified
supply voltage for corresponding load as per Clause 3.2 of the JERC for
Manipur and Mizoram (Electricity Supply Code) Regulations, 2013, shall
be allowed rebate and those availing supply at lower voltage than the
specified voltage shall be levied surcharge as detailed below:
i) For consumers having contracted load up to 50 kW – If the supply is
given at HV/EHV, a rebate of 5 % would be admissible on the rate of
Energy Charge and Fixed Charge of the applicable tariff.
ii) For consumers having contracted load above 50 kW – If supply is given
at voltage lower than the base voltage for corresponding load as per
the Clause mentioned above, the consumer shall be required to pay an
extra charge of 10 % on the bill amount (Energy Charge + Fixed Charge)
calculated at the applicable tariff.
iii) All voltages mentioned above are nominal rate voltages as per Clause
3.2 of the JERC for Manipur & Mizoram (Electricity Supply Code)
Regulations, 2013.
5.2 Payment: All payments shall be made by way of Cash (up to the amount as
acceptable to the Licensee), Banker’s Cheque, Demand Draft or Money Order
or e-transfer on-line. Cheques and Demand Drafts shall be payable at any
branch of a scheduled commercial bank that is a member of the clearing house
for the area where the concerned Sub Divisional Office is located.
However, part payment is subjected to acceptance by the competent authority.
53
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
For each 0.01 by which his One percent (1%) of the total amount of
average monthly power factor the bill under the head ‘Energy Charge’.
falls below 0.90 up to 0.85
54
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
For each 0.01 by which his Two percent (2%) of the total
average monthly power factor amount of the bill under the head
falls below 0.85 ‘Energy Charge’.
consumer and all HT consumers falls below 0.70, then the utility shall
have the right to disconnect supply to consumer’s installation after
serving a notice of 15 days. Supply may be restored only after steps are
taken to improve the power factor to the satisfaction of the Utility. This
is, however, without prejudice to the levy of surcharge for low power
factor in the event of supply not being disconnected.
e) For this purpose, the “average monthly power factor” is defined as the
ratio of total ‘kilo Watt hours’ to the total ‘kilo Volt Ampere hours’
recorded during the month. This ratio will be rounded off to two figures
after decimal. Figure 5 or above, in the third place after decimal, shall be
rounded off to the next higher figure in the second place after decimal.
f) Notwithstanding the above, if the average monthly power factor of a
5.7 Transformation loss: The consumers getting their supply at HT and metered
on the LT side shall be charged transformation loss in kWh as per Clause 5.7 of
JERC for Manipur and Mizoram (Electricity Supply Code) Regulations, 2013.
The same is reproduced for convenience sake:
1. The average losses in the transformer shall be calculated as follows and added
to the energy consumption indicated by the meter:
55
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
730 x 1.0 x C
Average transformer loss = ------------------------ = kVAh per month
100
where C = kVA rating of the transformer. For conversion of kVAh to kWh or
vice-versa, latest power factor as per JERC (M&M) (Electricity Supply Code)
Regulations, 2013 with latest amendment is to be used.
2. The transformer loss arrived at by the above formula shall be added to the
energy consumption, even when the recorded energy* consumption is nil.
3. 1% of the transformer capacity for transformer above 63 kVA will be added to
the recorded maximum demand on the Low-Tension side to arrive at the
equivalent High-Tension demand.
* Note: - In case of un-metered supply, consumed energy computed as per Clause 5(1) of
this Tariff Schedule shall be taken as recorded energy consumption.
56
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Supply of Electricity to the consumers at voltage above 400 Volts as per Clause 3.2
of JERC for Manipur and Mizoram (Electricity Supply Code) Regulations, 2013 with
up to date amendment.
5.11.1 The Maximum Demand means the highest load measured in average kVA
or kW at the point of supply of a consumer during any consecutive period of 30
(thirty) minutes during the month or the maximum demand recorded by the MDI
during the month.
5.11.12Billing Demand: The billing demand means the highest of the following:
(i) the contract demand, or
(ii) the maximum demand indicated by the meter during the billing cycle, or
(iii) the sanctioned load wherever contract demand has not been provided in the
supply agreement.
57
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
The tariff does not include any tax or duty, etc., on electrical energy that may be
payable at any time in accordance with any law / State Government Rules in force.
Such charges, if any, shall be payable by the consumer in addition to tariff charges.
5.13 Contingency: - In case of any inconsistency between this Tariff Schedule and
the prevailing JERC for Manipur and Mizoram (Electricity Supply Code)
Regulations, 2013, the provision, meaning and contents of the said Code shall
prevail.
5.14 LT Supply:-
Tariff Rates:
58
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
C) Un-Metered Supply:
The energy (kWh) so computed as per Clause 5(1) of this Tariff Schedule shall be
charged at the same rate for metered tariff given above to arrive at the cost of
energy consumed.
Note: If any part of the domestic connection is utilized for any use other than
dwelling purpose like commercial, industrial, etc., a separate connection should be
taken for such loads under appropriate category, failing which the entire
consumption shall be treated as the case may be, in the corresponding category with
applicable tariff.
Applicability:
This tariff is applicable to all lights, all types of fans, heating devices, Television,
VCR/VCP, Radio, Refrigerator, Air Conditioner, lift motors, pump and all other
appliances for the purpose of private gain including other small power. This tariff
includes power loads for non-domestic purposes like Government/semi-
government/non-government offices, shops, hospitals, nursing homes, clinics,
dispensaries, health centres, restaurants, bars, hotels, clubs, guest houses, circuit
houses/rest houses, tourist lodges, picnic spots, resorts, farm/garden houses, clubs,
markets, optical houses, public buildings, community halls, stadiums,
meeting/conference halls, religious premises like churches, temples, mosques,
gurudwaras, religious offices, all types of studios, tea stalls, professional chambers
(like Advocates, chartered Accountants, consultants, Doctors, etc.), private trusts,
marriage halls, public halls, show rooms, centrally air-conditioning units,
commercial establishments, X- ray plants, diagnostic centers, pathological labs,
carpenters and furniture makers, repair workshops, laundries, typing institutes,
internet cafes, STD/ISD PCO’s, FAX/photocopy shops, tailoring shops,
Government/Non-Government Institutions, schools, colleges, libraries, research
institutes, boarding/lodging houses, railway stations, fuel/oil stations/pumps,
bottling or filling stations /plants, service stations, Railway/Bus stations/terminals,
59
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Tariff Rates:
The energy (kWh) so computed as per Clause 5(1) of this Tariff Schedule shall be
charged at the same rate for metered tariff given above to arrive at the cost of energy
consumed.
Tariff Rates:
60
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Un-Metered Supply:
The energy (kWh) so computed as per Clause 5(1) of this Tariff Schedule shall be
charged at the same rate for metered tariff given above to arrive at the cost of
energy consumed.
Applicability: Applicable to all public water supply system and sewerage system.
Tariff Rates:
61
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Tariff Rates:
Un-metered Supply:
The energy (kWh) so computed as per Clause 5(1) of this Tariff Schedule shall
be charged at the same rate for metered tariff given above to arrive at the cost
of energy consumed.
5.20 LT Category-6: Small Industry
Tariff Rates:
62
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
2. Un-Metered Supply:
The energy (kWh) so computed as per Clause 5(1) of this Tariff Schedule shall
be charged at the same rate for metered tariff given above to arrive at the cost
of energy consumed.
5.20 HT Supply Tariffs: The tariffs are applicable for Consumer availing supply at
voltage above 400 V irrespective of connected load/contracted demand. It is
mandatory to supply with voltage above 400 V, to consumer having a
Contracted Load of above 50 kW or Contract Demand of above 59 kVA, as per
Clause 3.2 of JERC for M&M (Electricity Supply Code) Regulations, 2013.
5.20.1 HT Category-1: Commercial
Tariff Rates:
A) Demand Charge: Rs. 115.00 per month per kVA of Billing Demand
B) Energy charge per month
Metered Supply:
Un-metered Supply : The energy (kWh) so computed as per Clause 5(1) of this
Tariff Schedule shall be charged at the same rate for metered tariff given above
to arrive at the cost of energy consumed.
63
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Tariff Rates:
A) Demand Charge: Rs. 115.00 per month per kVA of Billing Demand.
B) Energy charge per month:
Metered Supply:
Un-metered Supply: The energy (kWh) so computed as per Clause 5(1) of this
Tariff Schedule shall be charged at the same rate for metered tariff given above
to arrive at the cost of energy consumed.
5.22 HT Category-3: Irrigation & Agriculture
Tariff Rates:
A) Demand Charge: Rs. 115.00 per month per kVA of billing demand
B) Energy charge per month:
Metered Supply:
64
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Tariff Rates:
A) Demand Charge: Rs. 115.00 per month per kVA of Billing Demand.
B) Energy Charge per month:
Metered Supply:
Un-metered Supply:
The energy (kWh) so computed as per Clause 5(1) of this Tariff Schedule shall
be charged at the same rate for metered tariff given above to arrive at the cost
of energy consumed.
Applicability:
This Tariff is applicable for supply of power to industrial consumers having licence
from designated authority of appropriate Government and not covered under any
other category, at a single point for industrial purposes with Contract Demand
above 125 kVA or Contracted Load above 100 kW.
Tariff Rates:
A) Demand Charge: Rs. 115.00 per month per kVA of Billing Demand.
65
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Metered Supply:
Un-metered Supply:
The energy (kWh) so computed as per Clause 5(1) of this Tariff Schedule shall
be charged at the same rate for metered tariff given above to arrive at the cost
of energy consumed.
5.25 HT Category-6: Bulk Supply
Applicability:
This tariff is applicable for all installations, including mixed loads similar to LT
Category-1 and LT Category-2 such as private sector installation, educational
institution, defence installation, Government and Public Sector offices and
complexes and Hospital, etc., that arrange their own distribution system of power
within the premises with the approval of competent authority. This will not include
industrial complexes comprising mixed load of LT Category-1 and LT Category-2.
Tariff Rates:
A) Demand Charge: Rs. 115.00 per month per kVA of Billing Demand.
B) Energy Charge per month:
Metered Supply:
66
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Un-Metered Supply: The energy (kWh) so computed as per Clause 5(1) of this
Tariff Schedule shall be charged at the same rate for metered tariff given above
to arrive at the cost of energy consumed.
Applicability: Temporary power supply shall be given through correct meter and
carried out as per procedure laid down in Clause 4.56 to 4.70 of the JERC for
Manipur & Mizoram (Electricity Supply Code) Regulations, 2013 with latest
amendments. If the applicant provides the materials for service line, it shall be
treated as per Clause 4.133 of the JERC for Manipur & Mizoram (Electricity Supply
Code) Regulations, 2013 with latest amendments. If the licensee/Discom desires to
delegate power to various level of officers, it may be done through an Executive
Order within the licensee/Discom. However, in all cases, overall duration should
not violate the Supply Code mentioned above. If the service line is arranged by
consumer, it shall be treated as per Clause 4.133 of the JERC for Manipur & Mizoram
(Electricity Supply Code) Regulations, 2013 with latest amendments, and be
returned to the consumer after the period is over. Bill shall be served at the following
rates:
Tariff Rates:
A) Fixed / Demand charge: 1.5 times the rate of Fixed/Demand Charge of the
applicable tariff category for which power supply is given.
B) Energy charge per month: 1.5 times the rate of the highest rated slab of the
applicable tariff category for which energy is supplied.
67
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
(b) For street lights: -Total number of hours in a month during which power is
actually supplied to street lights through that feeder / through that DT
concerned. (12 Hrs per day in Gregorian calendar month or 365 hrs per month
on average basis). However, number of hours where power supply is not made
due to interruptions available shall be deducted.
F = Load Factor shall be as stipulated for theft cases in ANNEXURE 11.19 of the Joint
Electricity Regulatory Commission for Manipur & Mizoram (Electricity Supply
Code) Regulations, 2013, which is reproduced below for convenience sake:
S. No Particulars Load
1. Domestic (LT/HT) 40%
2. Non-domestic/Commercial (LT/HT) 50%
3. Industrial (LT/HT) 75%
4. Public Water supply (LT/HT) 50%
5. Bulk supply 50%
6. Agriculture/Irrigation (LT/HT) 50%
7. Street Light 50%
68
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
S. No Particulars Load
8. Direct theft-All Categories 100%
D = Demand factor which shall be taken as (1) 100 % in case of street lighting and (2)
45 % in case of other consumption.
2) Short period of unmetered supply: - For un-metered (meter not available) supply
as a result of defective, burnt, lost meter shall be treated as per Clause 6.11 – 6.13
of the JERC for Manipur and Mizoram (Electricity Supply Code) Regulations,
2013.
3) For Un-authorised consumer/theft (includes by-pass of meter)/pilferage and
cases cover by Section 135 of the Act: - The energy consumed shall be computed
as per Annexure 11.1.19 of the JERC for Manipur and Mizoram (Electricity Supply
Code) Regulations, 2013. The energy so computed shall be evaluated as follows: -
(a) Load less than 10 kW
i) First instance: - Three (3) times of the rate of the applicable tariff (fixed and
variable charges) for which the stolen energy was utilized.
ii) Second and subsequent instance: - Six (6) times of the rate of the applicable
tariff (fixed and variable charges) for which the stolen energy was utilized.
(b) Load exceeding 10 kW
69
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
First instance: - Three (3) times of the rate of the applicable tariff (fixed and
variable charges) for which the stolen energy was utilized.
Second and subsequent instance: - Six (6) times of the rate of the applicable tariff
(fixed and variable charges) for which the stolen energy was utilized.
Note: - Additional punishment of theft shall be as per Electricity Act 2003 (with latest
amendment) and as per the JERC for Manipur and Mizoram (Electricity Supply Code)
Regulations, 2013.
a) Meter Rent for non-prepaid meters: Monthly charges for hiring of the meter,
indicator payable shall be as follows:
i. AC single phase Energy meter, whole current: Rs. 10.00 per Month.
ii. AC, Three phase Energy meter, whole current: Rs. 20.00 per Month.
iii. AC, Three phase Energy meter, CT operated: Rs. 50.00 per Month
iv. AC, Three phase Energy meter, CT & PT operated: Rs. 500.00 per meter
per Month.
b) Meter Rent for Pre-Paid Meters: Monthly charges for hiring of the meter,
indicator payable shall be as follows:
i. AC, Single phase PP, Energy meter, whole current: Rs. 20.00 per month
ii. AC, Three phase PP, Energy meter, whole current: Rs. 40.00 per month
5.29 Other charges for meter:
a) Meter shifting
charge:
1. Rs. 100.00 per shifting if resulted from reconstruction/modification of
building and at consumer’s request.
2. Free of cost if shifting is done in the interest of licensee. Required
material to be borne by licensee.
Meter shifting shall be carried out as per Chapter -5 of the JERC for Manipur and
70
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
(i) For AC single phase LT energy meter: Rs. 50.00 per meter per
testing.
(ii) For AC three phase LT energy meter whole current: Rs. 75.00 per
meter per testing.
71
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
(iii) For AC three phase LT energy meter, CT operated: Rs. 100.00 per
meter per testing.
(iv) For energy meter AC three phase, CT & PT operated: Rs. 150.00 per
meter per testing.
In case the meter installed at the consumer premises is found to be defective from initial
installation, testing and replacement of meter shall be carried out as per Clause 5.31 to 5.50
of the JERC for Manipur and Mizoram (Electricity Supply Code) Regulations, 2013.
5.30 Testing of Consumer’s Installation:
The first test and inspection will be carried out free of cost as per Clause 4.47 of
the Joint Electricity Regulatory Commission for Manipur and Mizoram (Electricity
Supply Code) Regulations, 2013. Should any further test or inspection be
necessitated due to fault in the installation or due to non-compliance with the
condition of supply by the consumer, an extra charge of Rs. 100.00 per test,
payable in advance, shall be levied. In the event of the consumer failing to pay the
testing charge in advance within stipulated time, the Licensee will be at liberty to
disconnect the consumer’s premise from the supplier’s main.
Reconnection:
i. For AC single phase LT supply: Rs.80.00
ii. For AC three phase LT supply: Rs. 150.00
iii. For AC HT supply: Rs. 400.00
72
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Charges for change of category will be done as per Clause 4.72 to 4.80, Clause 4.85 to
4.86 and Clause 4.90 to 4.93 of the Joint Electricity Regulatory Commission for
Manipur & Mizoram (Electricity supply Code) Regulations, 2013.
Cost of replacement after initial fixation of connection wire, cut-out, fuses, etc., will be
borne by the consumers and shall be payable by the consumer in advance as per
purchase rate of the Licensee. The Licensee may supply the materials or the
consumer may arrange the required materials as per the required specifications of
the Licensee.
This charge is for meeting expenses toward spot verification of load and other
connected recording works. Fees for re-rating of the consumer’s installation at the
request of the consumer shall be Rs.100.00 per connection.
These charges shall be payable by the consumer in advance. The aforesaid charges do not
include the charges payable by the consumer for other works connected due to change of
connected load. Rerating shall be carried out as per Clause 4.94 to 4.107 of the JERC for
Manipur and Mizoram (Electricity Supply Code) Regulations, 2013.
73
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Security Deposit:
i) Load Security:
The amount of Security deposit for meter security shall normally be the price of the
meter as fixed by the licensee from time to time in line with Section 55 of Electricity
Act 2003.
For AC single phase LT or three phase LT without CT or with CT, the charge will be
as per Licensee’s purchase rate in case the energy meter box is replaced by the
Licensee from its store.
service connection will be as per Clause 4.2 read with Clause 5.10 of Joint
Electricity Regulatory Commission for Manipur and Mizoram (Electricity
Supply Code) Regulations, 2013.
ii) Cost of Service Connection: As stipulated in Clauses 4.37 and 4.131 of the
change. This shall be carried out as per Clause 4.81 to 4.84 of the Joint
Electricity Regulatory Commission for Manipur and Mizoram (Electricity
Supply Code) Regulations, 2013.
74
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
iv) Cost of Application Form: The Application Form shall be free of cost vide
Clause 4.14 of the Joint Electricity Regulatory Commission for Manipur and
Mizoram (Electricity Supply Code) Regulations, 2013.
v) Operation & Maintenance (O&M) Charge on dedicated assets: - The O&M
charge of assets created out of such amount received without any obligation to
return the same and no interest costs attached to such subvention, from
Consumer Contribution, Deposit work and any similar nature shall be as
follows: -
1) The completion costs shall be escalated at the rate of 4 % per annum from the
year of completion to arrive the costs of the assets for 2015-16 level.
2) The annual O&M charges/expenses shall be 5 % from the 2015-16 level costs.
3) The O&M charges/expenses for each subsequent year will be determined by
escalating the base charges/expenses determined above for 2015-16, at the
escalation factor of 5.72 % to arrive at possible O&M charges / expenses for
each year.
75
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
The Hon’ble Commission vide Tariff Order dated 12th March 2018 had issued a set of directives to be followed by MSPDCL to
comply with the JERC (Terms and Conditions of Determination of Tariff) Regulations, 2014.
MSPDCL has been taken several steps to comply with the directives. The purpose of this Chapter is to appraise the Hon’ble
Commission on progress made by MSPDCL on this matter since the issuance of the aforesaid Tariff Order.
Compliance of Directives
New Directives
Directive 29
MSPDCL was directed to ensure the installation and It is Submitted that MSPCL & MSPDCL to nominate nodal officers
energization of meters at all 11 kV feeders which is with minimum rank of DGM and co-ordinate the exercise of joint
the inter-company boundary and the energy injection feeder meter reading, every month and compile feeder wise energy
76
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
point from MSPCL to MSPDCL system for proper sent out / received by MSPCL / MSPDCL for energy audit.
energy accounting. The Commission also directed The joint meter readings are to be counter signed by the nodal
that there should be monthly joint reading of the officers. The Nodal Officer for joint metering from MSPDCL is
meters by MSPCL and MSPDCL. nominated. Meter readings subject to correction are taken in the
presence of the Substation Staff using CMRI.
Directive 30
MSPDCL and MSPCL were directed to conduct The Month wise feeder wise Energy received by MSPDCL from
monthly joint meter reading of the 11 kV incoming TRANSCOM periphery data has been prepared for the last quarter
meter (which is the injection point of energy from of 2017-18. The monthly wise feeder wise energy report is required
MSPCL to MSPDCL). to be reconciled with MSPCL and SLDC report.
MSPDCL was directed to complete installation and At present, energy accounting through DT metering could not be
Energization of all 11 kV feeder meter by September, done due to the below reasons
2018 and calculate the energy injected by MSPCL to 100% DTR metering was not done under the scheme.
MSPDCL on monthly basis. MSPDCL was also Deactivation of GPRS connectivity for the installed modems
directed to complete the DT metering by September, attached to DTs due to unstable network.
2018 and conduct a case study of feeder-wise energy The exorbitant recurring charges for the installed systems
loss for all 11 kV lines. The Hon'ble Commission MSPDCL has been installing 11 KV feeder meters on priority basis.
further directed MSPDCL to come up with LT line It is expected that all meters will be installed by the end of FY 2018-
77
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
loss for individual DT fed LT lines. 19. The status report has been attached as Annexure-1
Directive 31 MSPDCL has been installing MDI meters for HT categories and LT
The Commission is of the view to introduce kVAH Categories consumers on priority Basis. It is further submitted to
billing in energy charges to all HT categories and LT Hon’ble Commission that once MSPDCL is able to achieve 100%
categories with contracted load of 20 kWh and above Implementation of MDI meters for HT and LT Categories
with effect from FY 2019-20 onwards. The licensee is Consumer it will introduce KVAH billing in the energy charges of
directed to see that all HT connections are provided all such consumer.
with trivector/MDI meters for such connections
without fail.
78
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
79
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Old Directives
Directive 2: MSPDCL is in the process of finalizing the financial statements of FY
Annual Statement of Accounts 2017-18 and will submit the same to the Hon’ble Commission once it
MSPDCL was directed to prepare separate Annual is finalized.
accounts statements such as balance sheet, profit and
loss Account and relevant schedules and statements,
every year for regulatory purpose and submit to the
Commission after duly getting them audited.
Directive 3: Asset and depreciation registers for FY 2015-16 and 2016-17 are
Maintenance of Asset & Depreciation Registers ready for submission.
MSPDCL was directed to update the asset register
and submit to the Commission soon.
80
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Directive 4: The MIS system is under progress and the database is being
Management Information System (MIS) prepared. The online payment portal for pre-paid recharge is
MSPDCL was directed to take appropriate steps to already active, where payments can be done through electronic
build up credible & accurate database and wallets.
management information system (MIS) and regularly
update the same for future record and reference.
Arrangement may also be made for “On-line
Payment” and “Payment through Bank” of the
electricity bills.
Directive 5: A major part of the total power sales is constituted by domestic
Revenue Arrears category consumers and hence, the revenue arrears are expected to
MSPDCL was directed to assess year-wise Revenue reduce through the actions initiated by MSPDCL.
Arrears due from consumers and submit a report by 1. Prepaid Consumer
30th September, 2011 to the Commission. The 2. Post Paid Consumer
MSPDCL was also further directed to initiate action MSPDCL deducts 20% on every recharge from the outstanding
to collect/ liquidate the arrears. arrears of the respective consumers. HT consumers including
hospitals have been sent disconnection warning notices for clearing
their outstanding dues. Other government consumers having
81
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Directive 10: Unauthorized Connection/ Theft of The unauthorized connections and connected load are being taken
power Cases & Directive 11: Detailed Survey & care of under the pre-paid metering plan. MSPDCL has already
Investigation achieved 100% pre-paid metering for EC-I. For EC-II and EC-III,
In the above two directives, the Commission had 100% per-paid metering will be achieved by the end of FY 2018-19.
directed to carryout detailed survey & Investigation
to –
1. Identify unauthorized connections.
2. Physical verification of the connected load of all
82
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
connections.
3. Physical verification of the categories under which
the consumers are availing supply.
4. Verification & updating of names of the consumers
etc. and
Regularize 30000 unauthorized consumers annually.
Directive 12: It is submitted that MSPDCL is allotting the New connection to the
Replacement of Defective Meters and Installation of consumer only after installation of the Meter.
Meters to Un-Metered Connections List of Replacement of Defective Meters and installation of Meters to
MSPDCL was directed to provide meters to all un Un-Metered Connection is under consideration & will be submitted
metered consumers and replace the defective meters once finalized.
within the time frame given in the Commission Order
No. 24012/2/5/09 – JERC dt 7.1.2011 on 100%
metering plan and submit quarterly report regularly.
Directive 13: The details of Physical and financial status of RAPDRP & RGGVY
Physical and Financial Status of RAPDRP & RGGVY Schemes are attached as Annexure-2.
Schemes
83
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Directive 14: MSPDCL has two security deposit accounts with State Bank of
Interest on Security Deposit Indian Paona Bazaar (i) Security Deposit A/C (Meter) No
MSPDCL was directed to furnish up to-date position 33810369620 (ii) Security Deposit A.C (Works) 34944027846.
of interest on security deposit as per Regulation MSPDCL does not have accurate database for security deposit of
6.10(5) of JERC (Supply Code) Regulations 2010. The consumers who were connected before the 31.01.2014 and the
above rule may be followed scrupulously database is under progress.
The security deposits of pre-paid consumers who have been
converted to post- paid have already been paid.
However, The summary of security deposit amount for FY 20117-18
is as attached as annexure-3.
84
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Directive 16: No Such Capital Investment Plan has been proposed form MSPDCL
Investment Plan and Capping of Capital expenditure own funds in the FY 2019-20
Annual Investment Plan shall be submitted to the
Commission and necessary approval of Commission
shall be obtained for all major capital works costing
Rs. 5.00 Crore and above before execution of the
works.
Directive 17: The process of MDI Metering to all high value connections are been
Maximum Demand Indicator Meters (MDI) to be done on priority basis by MSPDCL.
provided to all high value connections
Directive 18: In this regard it is submitted that MSPDCL is not allotting any new
As verified from the Tariff Schedule, it is observed connection without installation respective meters. Further it is
that unmetered categories are prevailing in all submitted that only 240 HT Consumer are left out of around 1200
categories including HT. Continuance of HT HT consumer whose meters are to be install. MSPDCL is making
connections without meters is highly irregular. As per every effort to do 100% Metering of HT consumer by FY 2018-19.
Electricity Act, 2003 no service connection be released
without meter. As such, the MSPDCL is directed to
provide HT meters to all unmetered HT connections
85
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
86
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Directive 20: MSPDCL would like to inform the Hon’ble Commission that there
In house development of IT enabled system has been progress in the in-house development of IT enabled system
MSPDCL is directed to take steps for development of in the last one year. Some in-house developed IT platforms are
in-house IT enabled system so that all software issues already in operation to improve administrative processes. A few
can be attended/solved departmentally instead of notable accomplishments are listed below.
depending on consultants →powernodue.com: It is a domain which has a database of all the
employees along with their connection status. It incorporates a
hassle free fast and efficient process of getting no-dues certificate.
→Indent: It is an IT enabled platform which facilitates and
streamlines the approval process for despatch from store to field.
→ Online prepaid recharge with e-wallets like NPCI Bharat Bill
Payment System.
Furthermore, MSPDCL would like to state that it has bought Virtual
Private Network and it is being planned to set up a physical server
in one year to go digital with all the files available on one electronic
87
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Directive 22:
Installation of meters to all 11 kV feeders and DT’s It is submitted that under RAPDRP Part-A 72 nos. of 11KV Feeder
MSPDCL should install meters for all 11 kV feeders meters and 925 nos. of DT meters were installed.
and DT’s in all RAPDRP covered towns by 30.06.2016.
Sample study should be conducted to know the
highest feeder loss and highest DT loss and report to
be submitted to the Commission by 30.09.2016
88
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Directive 23 The MYT Petition for the second Control Period was filed last year,
As per Regulations 2 (19) of JERC (M&M) (MYT) and the Hon’ble Commission has issued the MYT Order on 12th
Regulations, 2014 the Second Control Period shall be March, 2018. We would like to inform the Hon’ble Commission that
five years from 01.04.2018. The MSPDCL is directed the provisional balance sheet along with the audited balance sheet of
to submit the next ARR for Control Period from FY MSPDCL for FY 2015-16 and FY 2016-17 are still being prepared and
2018-19 to FY 2022-23 and Tariff Petition for FY 2018- will be made available soon.
19 and true up petitions for FY 2015-16 and FY 2016-
17 along with audited annual accounts for FY 2015-16
and FY 2016-17 invariably.
89
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Directive 25 MSPDCL has been installing MDI meters for HT categories and LT
The Commission is of the view to introduce kVAH Categories consumers on priority Basis. It is further submitted to
billing in energy charges to all HT categories and LT Hon’ble Commission that once MSPDCL is able to achieve 100%
categories with contracted load 20 kWh and above Implementation of MDI meters for HT and LT Categories
with effect from FY 2018-19 onwards. The licensee is Consumer it will introduce KVAH billing in the energy charges of
directed to see that all HT connections are provided all such consumer
with trivector/MDI meters for such connections
without fail.
Directive 26: Accounting of non-tariff income MSPDCL wishes to submit to the Hon'ble Commission that it has
As per Form No.11 of JERC (M&M) (MYT) segregated the Non-Tariff Income component wise as per directive
regulations, 2014, non-tariff income comprises : of the Hon'ble Commission and it has submitted the details
A Particulars accordingly in Provisional True-up Petition for FY 2017-18.
1 Income From Investments, Fixed and Call
Deposit
90
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
91
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Directive 27 MSPDCL has filed up all the forms relevant to MYT Regulations
MSPDCL is directed to fill up judiciously all Forms along with year wise, slab wise consumers, slab wise energy
relevant to MYT Regulations viz. Appendix C,D and consumed. MSPDCL has furnished all the data available as per the
also submit year wise slab wise consumers, slab wise Directive along with the MYT Petition filed last year, and the
92
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
energy consumed and category wise total contracted Hon’ble Commission has issued the MYT Order on 12th March, 2018.
load while submitting Tariff Petition for control
period FY 2018-19 to 2022-23 to avoid additional
information queries after submission of petition.
93
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
94
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
95
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
96
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
97
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
98
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
99
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
100
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
101
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
102
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
103
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
104
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
1 April 169,048
2 May 500,549
3 June 542,478
4 July 180,183
5 August 515,858
6 September 157,682
7 October 935,868
8 November 509,895
9 December 515,245
10 January 610,686
11 February 1,288,330
12 March 786,132
Total 6,711,954
105
MSPDCL Limited Provisional True up of FY 2017-18 and Tariff Determination for FY 2019-20
Chapter 7: Prayers
a. Admit the Petition for Limited Provisional True-up for FY 2017-18 and Tariff
Determination for FY 2019-20, as submitted herewith;
b. Approve the amounts claimed in the Limited Provisional True-up for FY 2017-18;
c. Approve the category-wise tariffs proposed by MSPDCL for FY 2019-20;
d. Condone any inadvertent omissions/ errors/ shortcomings and permit the
Petitioner to add/ change/ modify/ alter this filing and make further submissions
as may be required at a future date;
e. Permit submission of any additional information required by the Commission
during the processing of this Petition;
f. Pass such other and further orders as are deemed fit and proper in the facts and
circumstances of the case.
106