Escolar Documentos
Profissional Documentos
Cultura Documentos
SSM-SU-5003-B
Welding and Inspection Requirements for Subsea Pipelines
and Risers
This document is the confidential property of Chevron U.S.A. Inc. and its affiliates. When made available to
any contractor providing services to Chevron U.S.A. Inc. or its affiliates, the contractor’s use of this
document shall be governed by the confidentiality provisions of the applicable contract or bid package.
Without limiting the foregoing, neither the whole nor any part of this document may be disclosed by the
contractor to any third party, other than an affiliate of the contractor that requires this information for
purposes of the contract with the Chevron entity, without the prior written consent of the Chevron entity
that has disclosed this document to the contractor. When requested by Chevron U.S.A. Inc. or its disclosing
affiliate, the contractor must return all copies of this document to the Chevron entity requesting such return
and delete any electronic copies from the contractor’s systems.
Any and all modifications (changes, amendments, etc.) to this document must follow approved
Chevron Engineering Standards governance processes.
December 2016 © 2007-2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 1 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
Summary of Changes
Revised technical content may be marked with change bars in the right margin as directed by Author.
The Author denotes the following technical changes to this revision as detailed below:
Added requirements throughout specification for projects which plan to use acid stimulation.
Added requirements throughout specification for projects which plan to use reeling installation method.
Added references to new CES specification for ECA and inspection acceptance criteria SSM-SU-6152.
5.0 Added Section 5.0 ‘Supplemental Pipeline Design Requirements for Sour Service’.
6.0 Added baseline weld flaw UT acceptance criteria.
20.0 Updated requirements for maximum interpass temperature.
App. B Added baseline fatigue sensitive weld flaw UT acceptance criteria.
Added Appendix C ‘Qualification Testing Requirements for Reeled Risers and Pipelines in Sour and HCAS
App. C
Service’.
App. D Added Appendix D ‘Requirements for Welding Corrosion Resistant Alloy Clad and Corrosion Resistant
Alloy Lined Pipe’.
App. E Former Appendix C is now Appendix E.
N/a
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 2 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
Contents
1.0 Scope............................................................................................................................................... 5
2.0 References ...................................................................................................................................... 5
2.1 Owner Documents .............................................................................................................. 5
2.2 Industry Codes and Standards ........................................................................................... 6
2.3 Conflict Resolution .............................................................................................................. 7
3.0 Acronyms ........................................................................................................................................ 8
4.0 Quality Control ............................................................................................................................. 10
5.0 Supplemental Pipeline Design Requirements for Sour Service ............................................. 11
6.0 Engineering Critical Assessment ............................................................................................... 11
7.0 Pipeline Materials ......................................................................................................................... 12
8.0 Welding Equipment, Tools, Resources, and Supplies ............................................................. 14
9.0 Welding Processes ...................................................................................................................... 15
10.0 Welding Consumables (Electrodes, Filler Metals, Fluxes, and Shield Gasses) .................... 16
10.1 Production Welding Batch Testing .................................................................................... 18
10.2 Storage and Handling of Consumables ............................................................................ 19
10.3 Shielding Gasses .............................................................................................................. 20
11.0 Welding Procedure Qualifications ............................................................................................. 21
12.0 Mainline Procedure Qualification ............................................................................................... 25
13.0 Repair Welding Qualifications .................................................................................................... 29
13.1 Through Thickness Repair Qualification ........................................................................... 29
13.2 Partial Wall Repair Qualification ....................................................................................... 29
13.3 Cap Repair Qualification ................................................................................................... 29
14.0 Welder and Welding Operator Qualification.............................................................................. 30
15.0 Production Welding Requirements ............................................................................................ 32
16.0 Pipe Material Handling, Shipping, and End Protection ............................................................ 34
17.0 Marking of Welds ......................................................................................................................... 35
18.0 Jointing of Pipe ............................................................................................................................ 36
18.1 Multiple Jointing ................................................................................................................ 36
18.2 Spool Base Jointing .......................................................................................................... 36
19.0 Weld Bevel Preparation and Inspection .................................................................................... 37
20.0 Joint Alignment, Clamps, Clamp Release, and Pipe Movement ............................................. 38
21.0 Preheat, Interpass, and Postheat ............................................................................................... 41
22.0 Back Welding ................................................................................................................................ 41
23.0 Arc Strikes .................................................................................................................................... 42
24.0 Proximity of Weld Joints ............................................................................................................. 42
25.0 Girth Weld Inspection and Testing............................................................................................. 43
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 3 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 4 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
1.0 Scope
1. The main body of this specification applies to onshore and offshore welding activities for
subsea pipelines and risers that will not be subjected to fatigue sensitive service.
2. Appendix B of this specification applies to pipelines and steel catenary risers (SCRs) that are
in fatigue sensitive service of up to API 5L X65 grade.
3. This specification includes specific requirements for reeled pipelines and pipelines installed
by conventional S-lay and J-lay practices.
4. Pipe materials to be welded per the main body of this specification are limited to
API 5L grades up to and including X70 and in sizes of 3-inch (76.2-mm) and greater
diameters. This specification does not apply to reeled coil tubing used for subsea pipelines.
5. Appendix C of this specification applies to reeled pipelines and risers in sour or hydrogen
charging acid stimulation (HCAS) service.
6. Appendix D of this specification applies to welding corrosion resistant alloy (CRA) clad pipe
and CRA lined pipe.
2.0 References
1. The latest editions of the following specifications, national or industry codes and standards,
including all parts and amendments current at the date of order placement, shall apply to the
work defined in this specification.
2. Supplier shall comply with all applicable jurisdiction requirements (e.g., U.S. Code of
Federal Regulations for the Gulf of Mexico).
3. In case of any conflict between this specification and the requirements of these codes,
standards, or specifications, the more stringent requirements shall apply.
4. Refer to Appendix E for additional references not cited in the text of this specification.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 5 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 6 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 7 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
3.0 Acronyms
1GR One G Rotated (Welding Position Term)
ASA Aged-Strained-Aged
AUT Automated Ultrasonic Testing
AWMT All Weld Metal Tensile
AYS Actual Yield Strength
BM Base Metal
CE Carbon Equivalent
CRA Corrosion Resistant Alloy
CSWIP Certification Scheme for Welding Inspection Personnel
CT Compact Tension Specimen
CTOD Crack Tip Opening Displacement
CVN Charpy V-Notch
CWI Certified Welding Inspector
DSAW Double Submerged Arc Welded
ECA Engineering Critical Assessment
FBE Fusion Bonded Epoxy
FCAW Flux Cored Arc Welding
FL Fusion Line
FSFL Fatigue Sensitive Flow Line
GMAW Gas Metal Arc Welding
GMAW-P Gas Metal Arc Welding Pulsed
GTAW Gas Tungsten Arc Welding
H&D Hurter-Driffield
HAZ Heat Affected Zone
HCAS Hydrogen Charging Acid Stimulation
HV Vickers Hardness Number
ID Inside Diameter
IIW International Institute of Welding
J-R J Integral Resistance (fracture mechanics term)
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 8 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
K1SSC Stress Intensity Value to Prevent Initiation of a Sulfide Stress Corrosion Crack
MDT Minimum Design Temperature
MPI Magnetic Particle Inspection
MT Magnetic Particle Testing
MTR Material Test Report
NDE Nondestructive Examination
OD Outside Diameter
Pcm Critical Metal Parameter
PCN Personnel Certification in Nondestructive Testing
PQR Procedure Qualification Record
PSL Product Specification Level
PT Penetrant Test
PWHT Post-Weld Heat Treatment
pWPS Preliminary Welding Procedure Specification
QA Quality Assurance
QC Quality Control
QUTE Qualification of Ultrasonic Testing Examiners
RMS Root Mean Square
RT Radiographic Testing
SAW Submerged Arc Welding
SCR Steel Catenary Riser
SENB Single-Edge Notched Bend
SENT Single-Edge Notched Tensile
SMAW Shielded Metal Arc Welding
SMTS Specified Minimum Tensile Strength
SMYS Specified Minimum Yield Strength
SSC Sulfide Stress Cracking
TOFD Time of Flight Diffraction
UT Ultrasonic Testing
UTS Ultimate Tensile Strength
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 9 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 10 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
5. The minimum standard of weld acceptance for radiographic testing (RT), magnetic particle
testing (MT), liquid penetrant testing, and ultrasonic testing (UT) shall be as defined in the
API 1104 section ‘Acceptance Standards for NDT’ (Section 9).
6. Automated ultrasonic testing (AUT) examinations may be used provided that the
requirements of PPL-PU-5312 are met. AUT examinations shall be used for sour, hydrogen
charging acid stimulation (HCAS) or fatigue sensitive service.
7. For reeled pipelines, the rules of BSI BS 7910 shall apply as modified per Section 7.0 of this
specification.
8. An inspection matrix identifying hold, witness, monitor, and review points shall be submitted
to Owner for review and acceptance a minimum of 6 weeks prior to the start of welding
procedure qualification.
9. Key inspection witness points shall include subsea assembly fabrication inspections,
touchdown point, firing line inspection points, mobilization/demobilization checks, etc. See
examples in Appendix A.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 11 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
5. Supplier shall provide the necessary weld coupons for single-edge notched tensile (SENT)
specimens to develop the required J integral resistance (J-R) curves and perform segment
tests to validate the J-R curve methodology.
6. SENT testing and segment test validation shall be required for any change in welding
procedure, pipe manufacturer, pipe grade, pipe OD, or pipe thickness.
7. All ECA-related testing shall be performed by Owner-reviewed and-accepted laboratory
using qualified, skilled personnel.
8. The ECA shall be completed by personnel skilled in performing ECA according to
BSI BS 7910 and shall be performed by an organization reviewed and accepted by Owner.
9. Owner shall review and accept completed ECA prior to implementation for use on
production welds.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 12 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
5. Supplier shall check pipe and material quantity and condition upon receipt, and the following
shall apply:
a. All damages that are not noted at the time of receipt by Supplier shall be deemed to have
been accepted by Supplier as undamaged.
b. Damaged pipe shall be defined as that which does not meet the requirements of
API 5L, product specification level (PSL) 2, or project specifications under which the
pipe was originally manufactured, whichever is the most restrictive, with regards to
dents, gouges, straightness, bevel burrs and imperfections, and out-of-roundness.
c. For Owner-supplied pipe, Owner shall reserve the right to charge Supplier with the full
delivered cost of pipe and other Owner-furnished materials rendered unusable by acts of
Supplier.
d. When stock pipe is to be used, Purchaser and Supplier shall jointly determine any
required actions to be taken based on the condition of the pipe.
6. A gouge, groove, or dent shall not be repaired by insert patching or by pounding out.
7. Each gouge, groove, or dent that is removed from a length of pipe shall be removed by
cutting out the damaged portion as a cylinder.
8. Supplier shall use pipe in full joint lengths whenever it is practical.
9. Any gouges, grooves, or dents in the pipeline resulting from Supplier’s operations shall be
removed by Supplier, at no expense to Owner, and to the satisfaction of Owner’s
representative.
10. For coated pipe, Supplier shall determine the minimum and maximum coating cut back
distance from the open ends of the pipe for operations such as installation of orbital welding
equipment, preheating elements, welding grounds, AUT equipment, or field joint coating
equipment.
11. When pipe sorting is to be performed, both ends of pipe shall have the same coating cut back
distance, unless otherwise accepted by Owner, thus doubling the possible weld bevel end
sorting combinations.
12. Supplier shall advise Owner of minimum and maximum cut back distances with bid
submission.
13. For pipelines in sour or HCAS service, the following shall apply:
a. Supplier shall obtain pipe end dimensional survey data and submit an assembly sequence
based on the survey data for acceptance by Owner.
b. Prior to performance of the survey, Supplier shall submit the dimensional measurement
procedure and proposed Sub-Supplier, if any, for acceptance by Owner.
c. Supplier shall develop pipe sorting and Hi-Lo measurements for acceptance by Owner.
1) A minimum of 8 Hi-Lo measurements shall be recorded at each pipe weld end and as
close to the pipe end as possible.
2) Hi-Lo shall meet the fit tolerance of 1/16 inch (1.6 mm) at all weld ends in the
flowline.
Note: A more restrictive Hi-Lo may be required for steel catenary risers (SCRs) and a
more restrictive Hi-Lo may support a lower repair rate for pipelines in sour or
HCAS service.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 13 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 14 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 15 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
6. If Supplier proposes the use of an automatic (machine) pipeline welding process, a complete
description of the process, including examples of previously qualified welding procedures
and pipeline projects completed using the proposed process, shall be submitted for review
and acceptance by Owner prior to the award of the contract.
7. Welding processes or combinations of processes other than those listed in item 1 may be
submitted for Owner review and acceptance. As a minimum, Owner acceptance shall require
that the following conditions are met:
a. Owner shall have knowledge and previous satisfactory experience with the process or
system.
b. Supplier shall have a successful past history using the process or system, supported with
documentary evidence and shall be subject to Owner review.
8. Automatic orbital welding equipment shall be modern, fully programmable, and previously
proven on pipelines of similar size and material grade and shall meet the following
requirements:
a. The equipment shall be portable and suitable for use in the environmental conditions
prevailing at the welding station.
b. The operators of this equipment shall be fully trained, skilled, and experienced in the use
of such equipment.
9. Supplier shall develop and implement a contact tip QC and monitoring program to ensure
there is no copper contamination of the weld due to wire feed restrictions, contacting of the
tip to the bevel sidewall, etc.
a. Welds with copper contamination shall not be repaired.
b. The weld with copper contamination shall be cut out as a cylinder, pipe ends properly
re-beveled, and the joint re-welded.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 16 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
b. Welding consumables that produce a weld deposit containing more than 1 percent nickel
shall be acceptable only after successful weld sulfide stress cracking (SSC) qualification
in accordance with NACE MR0175/ISO 15156 and acceptance by the Owner.
c. For non-sour service, additional alloy shall be permitted provided the filler metal meets
AWS/ISO specifications and the following requirements unless otherwise reviewed and
accepted by the Owner:
1) Chromium (Cr), molybdenum (Mo), and copper (Cu) each shall not exceed
0.35 percent.
2) Nickel (Ni) shall not exceed 1.5 percent.
3) Vanadium (V) shall not exceed 0.04 percent.
d. For water injection systems, the root and hot pass shall be made using low alloy
consumables containing either of the following:
1) 0.8–1.0 percent Nickel (Ni).
2) 0.4–0.8 percent Copper (Cu) and 0.5–1.0 percent nickel (Ni).
7. For non-reeled pipe, the following shall apply:
a. Production welding procedure as-deposited yield strength (YS) of the welding
consumables shall overmatch base material SMYS by a minimum of 5 ksi (35 MPa).
b. The all weld metal as-deposited tensile strength shall overmatch the minimum specified
pipe base material ultimate tensile strength (UTS), but not by more than the lesser of
30 percent of base metal minimum specified UTS or 100 ksi (690 MPa).
8. For reeled pipe, the following shall apply:
a. Production welding procedure as-deposited YS of welding consumables shall be at least
equal to the actual yield strength (AYS) of the production pipe, but shall not be more
than 14.5 ksi (100 MPa) above the specified maximum YS for the base metal unless
otherwise agreed by Owner.
b. The all weld metal as-deposited tensile strength shall not exceed 100 ksi (690 MPa).
c. The YS, UTS, and percent elongation at failure shall be reported for the
aged-strained-aged (ASA) condition, as defined in Appendix C.
9. Filler materials used for sour or HCAS service welds shall be capable of providing deposited
weld metal with a maximum hardness of 250 Vickers hardness number (HV) 10. For reeled
pipe, maximum hardness of 250 HV10 shall apply to welds in the ASA condition.
10. Consumable manufacturers shall be subject to Owner review and acceptance, and the
following shall apply:
a. Manufacturers shall supply actual chemistry and mechanical property data sheets.
b. Actual chemical analysis shall report concentration of carbon (C), manganese (Mn),
silicon (Si), phosphorus (P,) sulfur (S,) nickel (Ni), chromium (Cr), copper (Cu),
micro-alloying elements, diffusible hydrogen (H), and all other intentionally added
elements.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 17 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
11. Brand name and manufacturer source of consumables used for procedure qualification shall
be the same as those used for production welding. Any change or variation shall require
re-qualification of welding procedure.
12. Batch testing of consumables shall meet the following requirements:
a. Batch testing shall be required for all filler metals to be used for production welding as
follows:
1) Supplier shall determine necessary filler metal and flux quantities including
sufficient overage to account for wastage or contamination of welding consumables
during production welding.
2) Sufficient quantities of each successfully-tested batch shall be purchased to
complete the work.
b. Consumable purchasing batch testing shall be required for each heat and lot of filler
metals as described in the following:
1) Batch testing of consumables shall be required as follows:
i. ‘Manufacturer/heat-lot/batch/diameter’ basis for SMAW electrodes.
ii. ‘Manufacturer/heat-lot’ basis for GTAW, GMAW, and FCAW filler.
iii. ‘Manufacturer/wire heat’ and ‘manufacturer/flux batch’ for SAW consumables.
2) For the SAW process, each electrode heat or lot (as defined by
AWS A5.01/A5.01M) with each flux lot shall be tested as a combination.
3) Heat or lot, as applicable, of welding filler metal and flux batch size shall be limited
to the smaller of 100,000 pounds (45,360 kg) or the maximum production quantity in
a 24-hour period. Supplier shall perform the tests and certify the results.
4) Electrode manufacturer or Supplier may perform the tests and certify the results.
5) Certification shall be to the applicable ASME BPVC, Section II, Part C, consumable
specification, or Owner-reviewed and -accepted AWS or ISO equivalent standard.
6) The mechanical and chemical test results shall be reported on the certification.
7) Manufacturer’s certificates shall be supplied for each batch of consumables.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 18 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 19 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
9. Coated electrodes and SAW flux shall be stored in the original unopened packages or
containers until issued for use.
a. Maximum exposure life and maintenance of covered electrodes shall be per
manufacturer’s recommendation.
b. Electrodes removed from storage shall be disposed of if not used within two hours after
removal from canister.
10. Cellulosic welding electrodes shall be stored in hermetically sealed canisters to minimize
absorption of moisture prior to use.
a. Cellulosic electrodes shall not be placed in heated storage ovens of any kind and shall not
be re-baked.
b. Cellulosic welding electrodes that are damaged or have excessive moisture shall be
discarded.
11. Reconditioning of moisture-contaminated coated electrodes or SAW flux shall not be
permitted.
12. Re-baking of low hydrogen electrodes, flux cored wires, and submerged arc fluxes shall not
be allowed.
13. Consumables that become wet, contaminated, or damaged shall be discarded per an
Owner-reviewed and -accepted waste management plan.
14. If the SAW process is used for 1GR welds, the following shall apply:
a. The moisture content of the flux shall be provided on the actual mechanical property data
sheet and all weld metal diffusible hydrogen analysis shall be determined and provided
for each lot of flux.
b. Re-use of flux that has been melted and solidified shall not be permitted.
c. If recycling of flux is being used, the ratio of new to re-used flux shall be greater than
75 percent.
15. Each tin or packet of electrodes, reel of filler wire, and bag of flux shall be clearly marked
with the respective batch number, heat, and lot.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 20 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
b. For argon shielding gas, oxygen content shall not exceed 10 ppm (with approximate dew
point of −77°F [−60°C]).
c. Argon shielding gas shall be of a minimum purity content of 99.995 percent.
d. Final gas composition used in production welding shall not vary more than ±2.5 percent
from nominal shielding gas composition during qualification. Examples of
compositional limits are as follows:
1) Nominal: 75 percent argon, 25 percent CO2.
2) Upper limits: 77.5 percent argon, 22.5 percent CO2.
3) Lower limits: 72.5 percent argon, 27.5 percent CO2.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 21 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 22 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
c. MT acceptance criteria shall be that no linear indications shall exist on the weld cap
reinforcement, cap toes, or pipe wall for a distance of 1 inch (25 mm) from the toes of
the weld.
11. Supplier shall submit all NDE procedures to Owner for review and acceptance.
12. If inspections indicate the presence of flaws exceeding levels permitted in this specification,
the reason for such flaws shall be investigated and explained to the satisfaction of Owner
before re-welding a test piece to the same (or any other) procedure.
13. In addition to the requirements of API 1104, fillet welds in sour service application shall be
qualified with a hardness survey in accordance with NACE MR0175/ISO 15156 as follows:
a. A minimum of two weld passes shall be used.
b. Maximum hardness shall not exceed 250 HV10.
14. The welding procedure qualification process (WPQP) (i.e., welding of pipe test coupons)
shall begin no later than 60 days prior to start of production welding (90 days if CTOD
fracture toughness testing is required). The following shall apply:
a. Supplier shall provide a detailed schedule listing procedures to be qualified and expected
times to accomplish the following individual tasks:
1) Preliminary WPS generation.
2) Equipment set up.
3) Pipe cutting and weld prepping, fit-up, and welding.
4) NDE.
5) Lab testing.
6) Procedure qualification record (PQR) generation.
7) Expected WPS submittal dates.
b. This schedule shall be kept current by Supplier.
15. Supplier shall submit detailed preliminary welding procedure specifications (pWPS),
including any required weld repair procedures, for Owner review and acceptance prior to
commencing procedure qualification testing, and the following shall apply:
a. All welding consumables shall be defined in the pWPS.
b. A register of proposed and accepted welding procedures shall be maintained current by
Supplier and shall be submitted with each submittal of welding procedures for Owner
review and acceptance.
16. Following review and acceptance of the pWPS, Supplier shall carry out qualification tests
demonstrating that welds having the required mechanical properties (strength, ductility,
toughness, hardness, etc.) can be achieved by the procedure.
17. The PQR testing cycle of the WPQP shall be completed a minimum of 30 days before start of
production welding.
18. Each weld procedure shall be uniquely identified, performed, and documented by Supplier
and witnessed by Owner.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 23 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
19. Qualification of proposed procedure(s) shall comply, at a minimum, with the API 1104
section ‘Qualification of Welding Procedure for Welds Containing Filler Metal Additives’
(Section 5) or ‘Mechanized Welding with Filler Metal Addition’ (Section 12).
20. For welds subject to ECA as permitted by this specification, welding procedures shall be
qualified per the following requirements:
a. API 1104 annex ‘Alternate Acceptance Standard for Girth Welds’ (Annex A) or
BSI BS 7910 (non-reeled) – Qualify per API 1104 annex ‘Alternate Acceptance
Standard for Girth Welds’, and this specification.
b. DNV-RP-F108 (reeled) – Qualify per the API 1104 section ‘Qualification of Welding
Procedure for Welds Containing Filler Metal Additives’ (Section 5) or ‘Mechanized
Welding with Filler Metal Addition’ (Section 12), and this specification.
21. Separate welding procedure qualifications shall be required for each pipe diameter and wall
thickness to be welded.
22. For procedures qualified in accordance with the API 1104 annex ‘Alternate Acceptance
Standard for Girth Welds’ (Annex A), the additional mechanical testing, as required by the
API 1104 annex, shall be accomplished.
23. Detailed WPS shall be provided for each type of joint and nominal size to be joined, and shall
meet the following requirements:
a. Each WPS shall clearly identify all of the essential variables, materials, and
specifications, as well as consumables by trade name and classification, in addition to
normal standard ‘code’ requirements.
b. A key requirement of each WPS shall be to indicate the minimum and maximum number
of passes permitted for particular joint thickness and the welding conditions to be used
for each pass or group of passes.
24. Supplier shall review each WPS and PQR to confirm that Owner requirements have been met
before submittal to Owner.
a. Supplier shall submit the qualified WPS(s) and original documentation supporting
acceptability of each procedure and the PQR(s) for review and acceptance by Owner.
b. The following shall be submitted as a minimum:
1) Welding procedure register.
2) WPS(s).
3) WPS(s) for repairs.
4) PQR(s).
5) All PQR lab test results, base metal and filler metal certifications, NDE results, and
chemical analysis.
6) Arc burn inspection and repair procedure.
7) Weld repair limitations (i.e., depth and length of repair for repairs made aft of
tensioners).
c. Owner shall retain a written record of each welding procedure.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 24 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 25 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
2) For manual and semiautomatic welding, heat inputs of ±20 percent from the
anticipated midline shall be acceptable.
3) A high heat input weld and a low heat input weld shall both be fully qualified for
each pipe size and wall thickness.
4) The permitted range for production welding shall be within the high and low
qualified values.
5) In defining the heat input range, Supplier may elect to use the measured range of
average heat inputs per pass or maximum/minimum values per pass.
6) Supplier shall state their heat input basis on each pWPS and fully qualified WPS.
h. A change beyond ±20 percent from the nominal shielding gas flow rate qualified and
recorded on the supporting welding procedure qualification.
i. Any decrease in preheat from that recorded during weld procedure qualification.
j. Increase in preheat of greater than 100°F (55°C), subject to maximum interpass
temperature limitations.
k. Any change in the following:
1) Minimum number of weld passes.
2) Weld bevel configuration for procedures that are to be AUT inspected in production
welding.
3) Number of root run welders.
4. Mainline procedures shall simulate a root pass burn through and repair as part of the
qualification process and shall include the following:
a. Burn-through locations shall be properly ground to feather the ends of the repair cavity
for re-welding.
b. Re-welding may be done manually or by automatic processes.
5. All procedure qualification test welds not in sour or HCAS service shall meet the
requirements of Section 11.0, item 9 above. All procedure qualification test welds in sour or
HCAS service shall meet the requirements of Section 11.0, item 10 above.
6. As a minimum, API 1104-required mechanical test specimens shall be removed from the
qualification welds at the specified API 1104 clock positions and shall meet the following
requirements:
a. NDE results shall not be used to locate and remove mechanical test specimens.
b. Hardness testing shall also be performed as part of the welding procedure qualification as
follows:
1) Three trans weld Vickers microhardness surveys shall be performed in accordance
with NACE MR0175/ISO 15156 on all test welds.
2) For welds in sour service, additional hardness tests shall be required. Refer to
Figure 1 for additional hardness testing locations.
3) For 5G welding position, samples shall be taken close to the 12, 3, and 6 o’clock
positions.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 26 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
4) Cross-sections for hardness testing shall be ground and polished (diamond paste
finished) and etched to show the weld metal and heat affected zone (HAZ)
micro-structures.
5) Load used in Vickers hardness test shall not exceed 10 kg.
6) Maximum hardness shall not exceed 250 HV10 for sour service and 325 HV10 for
non-sour service.
7) Photomicrographs showing the indent locations shall be submitted with the
welding PQR.
8) Retest shall be allowed only if a single hardness point has a value above the
requirement. For welds in sour service, a single point may exceed 250 HV10, but
shall not exceed 265 HV10.
i. The entire specimen shall be repolished and the full hardness survey shall be
conducted again.
ii. If every point meets the acceptance criteria, the weld shall be accepted.
iii. Only one retest shall be allowed.
Figure 1: Weld Hardness Survey
2 4 5 6
1 8
4 mm
3 7
1 mm
18
17 19
4 mm
1 mm
11 15
10 14
9 16
12 13
1.5 ±0.5 mm
NACE REQUIRED
ADDITIONAL OWNER HARDNESS TEST
Notes:
1. Shaded area represents the weld HAZ.
2. The top line of survey shall be positioned so that the impressions in the HAZ coincide with the final layer or change
in profile of the fusion line associated with the final layer.
3. Impressions in the HAZ shall be entirely within the HAZ and located as close as possible to the fusion line, normally
within 0.25 mm of the fusion line.
4. Additional Owner required hardness test shown are taken every 0.15 in. (4 mm), starting from the surface.
Impressions on the top two lines of the survey (2, 3, 4, 5, 6, and 7) are identified as cap hardness.
December 2016 © 20072016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 27 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
7. Charpy impact tests shall be run as part of the welding procedure qualification and shall meet
the following requirements:
a. For 5G weld position, test sets of three specimens from weld metal, fusion line (FL), and
base metal shall be taken from the 12, 3, and 6 o’clock positions as follows:
1) Center of weld.
2) FL.
3) FL+3/32 inch (2 mm) in the parent material.
b. For 1GR, 2G, and 6G weld positions, test sets of three specimens from weld metal, FL,
and FL +3/32 inch (2 mm) shall be taken 120 degrees apart.
c. For material exceeding 3/4-inch (19 mm) thickness, impact tests shall also be taken from
the root region in center of weld, FL, and FL+3/32 inch (2 mm) locations.
d. The CVN impact test temperature shall be +32°F (0°C) or project minimum design
temperature (MDT), whichever is lower.
e. Each set of full-size specimens shall have minimum average impact energy of
37 ft-lbs (50 Joules) with no single value less than 30 ft-lbs (41 Joules).
8. For non-reeled pipelines of X60 and higher strength, one AWMT test shall be required from
each procedure qualification in accordance with ASTM A370 as follows:
a. YS shall exceed pipe SMYS by 5 ksi (34.5 MPa) to a maximum of 30 ksi (206.5 MPa).
b. Maximum tensile strength shall not exceed 1.3 × specified minimum tensile strength
(SMTS) of specified pipe grade, and in no case more than 100 ksi (690 MPa) tensile
strength.
9. For reeled pipelines, two all weld metal tests shall be required from each procedure
qualification in accordance with ASTM 370.
a. One tensile specimen shall be tested in the as-welded condition (no additional aging or
straining) and one specimen shall be tested after age-strain aging is performed.
b. As-deposited YS of weld metal shall be at least equal to the AYS of the production pipe,
but shall not be more than 14.5 ksi (100 MPa) above specified maximum YS for the base
metal unless otherwise agreed by Owner.
c. The all weld metal as-deposited tensile strength shall not exceed 100 ksi (690 MPa).
10. For any pipeline on which an ECA is to be performed, destructive testing in accordance with
DNV-OS-F101, Appendix C E300 shall be performed in addition to any other required
testing.
a. CTOD testing shall be required of weld metal and HAZ.
b. Test temperature shall be +32°F (0°C) or at MDT, whichever is lower.
c. Minimum CTOD shall be 0.015 inch (0.38 mm) or higher as determined by ECA
analysis.
11. For pipelines in sour or HCAS service, environmental fracture toughness shall be measured
using CTOD testing as described in Appendix C.5. For non-reeled pipelines, specimens
shall be tested in the as-welded condition, rather than ASA.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 28 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 29 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
c. Cap repairs may be completed in a single pass or multiple passes, except for welds in
sour service as follows:
1) Single pass and multiple pass shall be individually qualified.
2) Cap repairs for sour service applications shall be qualified and completed in
production with a multiple pass technique with the last weld pass completed on weld
metal only.
2. A previously welded mainline procedure test coupon shall be used, excavating to desired
depth, then replacing weld using the mainline procedure or similar welding technique to
repair the weld joint.
3. Testing requirements shall be limited to one hardness test only as follows:
a. One microhardness traverse shall be required across the weld and shall be located
0.04 to 0.08 inch (1 to 2 mm) below the pipe surface.
b. Test results shall meet requirements of Section 12.0, item 6b, number 6).
4. Welding consumables and processes used for cap repair that have not been previously
qualified per Section 12.0 shall require full qualification to Section 12.0 in addition to cap
repair qualification testing.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 30 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 31 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
b. The record shall include welder’s name, date of test, and WPS used.
c. A certified copy of these records shall be furnished to Owner upon completion of the job.
15. Owner may require retesting of, or have removed from the job, any welder or welding
operator who, in the judgment of Owner inspector, is responsible for an excessive number of
defects or who is not performing to an acceptable level of workmanship.
16. No welder shall work on any phase of the pipeline for which he has not been tested and
accepted by Owner.
17. Each welder or welding operator shall be given a unique number that shall be marked in paint
against all welds produced by him. Paint type, quality, and lettering style shall be previously
agreed with Owner.
18. Supplier shall keep a list of qualified personnel up to date and available for inspection.
a. List of qualified personnel shall, as a minimum, include the following:
1) Welder’s name.
2) Unique identification number issued by Supplier.
3) Date of qualification for the procedure.
b. Should a welder leave, his/her number shall not be duplicated.
19. Supplier shall keep a separate list of each qualified welding procedure reviewed and accepted
by Owner.
20. Arc-air gouging and grinding shall be carried out by personnel who have previously satisfied
Owner that they are competent to do so and in accordance with a Owner-accepted procedure
by qualification according to Owner-accepted repair welding procedure for full or partial
penetration repairs.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 32 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
5. Immediately prior to alignment with pipeline, each joint of pipe shall be swabbed along its
full length as follows:
a. Swab may be air-driven.
b. Swabbing shall remove all dirt, mill scale, and other foreign substances inside the pipe.
c. Swab shall incorporate a steel disc, minimum 1/4 inch (6 mm) thick, with a diameter of
90 percent of nominal pipe ID or 1/8 inch (3 mm) less than nominal pipe ID, whichever
is smaller.
d. In the event that the steel disc will not pass through a joint with the plane of the disc at
right angles to pipe wall, that joint shall not be installed in the pipeline.
e. Each rejected joint of pipe shall be clearly marked as a reject, and shall be removed from
job site.
6. Working clearance shall meet the following requirements:
a. Working clearance shall be such as to afford the welder maximum comfort during
welding.
b. Minimum clear space shall be 16 inch (406 mm) at any point around outside surface of
pipeline and 40 inches (1 m) along length of pipeline centered on the weld joint.
7. Weather protection shall meet the following requirements:
a. Applicable welding procedures reviewed and accepted by Owner shall be strictly
adhered to at all times with regard to welding parameters and environmental conditions.
b. Welding shall not be done when, in the judgment of Owner representative, the quality of
the completed weld could be impaired by prevailing weather conditions.
1) These conditions shall include airborne moisture, dirt particles, and high winds at a
minimum.
2) Weather protection devices shall be used where necessary.
3) Owner representative shall be the sole authority in determining whether conditions
are acceptable to perform production welding.
8. Weld cleaning shall meet the following requirements:
a. Weld spatter shields shall be placed on top of pipe to protect pipe coating from weld
spatter damage.
b. Following completion of each weld pass and before the succeeding pass is initiated, weld
shall be cleaned as follows:
1) Hand chisels, power chisels, grinders, brushes, and slag hammers may be used to
clean the surface of welds completed with the SMAW, FCAW, or SAW processes.
2) Before applying the next bead or between weld passes, all scale, oxides, dirt, slag,
silicate, coatings, and other impurities shall be completely removed from each pass
with the use of a powered steel brush, except the root pass where grinding shall be
acceptable.
3) Power wire brushing shall be used to clean the hot pass immediately after
completion.
4) When mechanized welding is used, succeeding beads shall be cleaned as necessary.
c. Weld shall receive a final cleaning after the cap pass is complete to provide a suitable
surface for NDE and subsequent coating.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 33 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 34 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
4. Pipe shall be stacked in such a manner so as to prevent damage to pipe and coating.
5. Supplier shall submit a proposed stacking arrangement, including stacking heights with
calculations, to Owner for review and acceptance prior to use.
6. During transportation on pipe haul vessels and storage on the pipe lay vessel, stacking of
concrete-coated and fusion bonded epoxy (FBE) or other coated pipe shall conform to the
requirements of API 5LW and shall not exceed the static load as specified for the individual
coating systems.
a. In any event, Supplier shall ensure that stacking methods do not damage pipe or pipe
coatings.
b. Bottom layer shall be supported by bearing strips or wooden wedges spaced along its
length to prevent displacement or rolling.
7. When transporting pipe, valves, or other material, a means for tie-down support shall always
be used.
8. Cradles, padding, or other strapping necessary to protect materials during transportation
(including transport of pipe on cargo barges in heavy sea conditions) shall be designed and
placed in such a manner as to prevent the possibility of shifting loads or other potential
motion.
9. Pipe ends shall be adequately protected during transportation, handling, fabrication, and
installation in accordance with Owner project specifications.
10. End covers, where provided, shall remain in place until pipe is added to string rack or when
fabrication commences.
11. On completion of stage fabrication or end of work day or shift, end covers and desiccant shall
be replaced as necessary.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 35 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
Note: Supplier is advised that higher strength grades of pipe become difficult to source
acceptable filler metals for reeled pipelines.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 36 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
8. Tie-in welds stalk-to-stalk shall be done using mainline procedure to the extent possible.
9. All tie-in welds that cannot be welded with the mainline procedure shall be separately
qualified, including applying reeling and installation strain to the test welds before
mechanical testing.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 37 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
b. Burrs, small nicks, or irregularities on the beveled welding edge shall be removed,
subject to dimensional tolerance limits, with the aid of files or buffing wheels.
c. Grinding disks shall not be used.
12. Immediately prior to line-up, Supplier shall visually inspect the uncoated pipe ends internally
and externally for nicks, dents, general damage, laminations, or other surface defects.
13. Should laminations or split ends be discovered in the pipe, defective end shall be cut off and
re-beveled, and the new end shall be ultrasonically inspected for laminations for a minimum
of 8 inches (203 mm) from the bevel prior to installation.
14. All foreign materials such as mud, oil, grease, shop paint, etc., except internal or external
coating applied for permanent protection of pipe, shall be removed by Supplier from both
internal and external surfaces to a distance of 8 inch (203 mm) from each side of the proposed
weld.
15. In the event that pipe is multiple jointed in Supplier’s yard, a swabbing operation with a steel
disc shall be performed prior to multiple jointing the pipe as follows:
a. Just prior to installing multiple joints into the pipeline, the entire length of the multiple
joint shall be blown out using compressed air.
b. Compressed air cleaning shall be performed so that the entire joint length is free of loose
particles and debris.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 38 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
5. Details of alignment clamps to be used shall be submitted to Owner for review and
acceptance.
a. Use of internal line-up clamps shall be mandatory for pipe sizes 8 inches (203 mm) and
larger, and shall be preferred for all pipe diameters.
b. Internal clamps shall not be removed until root pass has been 100 percent completed.
c. Internal line-up clamps shall be pneumatic and shall be equipped with fiber or rubber
rollers so that internal coating on pipe, if so furnished, will not be scratched or marred in
any way.
d. For pipe sizes of 8 inches (203 mm) and smaller, a no-clamp fitup procedure may be
used.
1) When a no-clamp fitup procedure is permitted, a written procedure shall be required
that includes ID and OD Hi-Lo measurements before root pass welding and OD
Hi-Lo measurements after root pass welding to confirm that the Hi-Lo values have
not changed significantly during the welding of the root pass.
2) This procedure shall require review and acceptance by Owner.
6. For welds on pipe diameters less than 8 inches (203 mm), for tie-in welds, and for welds
joining valves, flanges, or fittings where an internal line-up clamp cannot be used, an
external line-up clamp shall be used and shall remain in place until 50 percent of root pass,
uniformly distributed around circumference, has been completed.
7. Use of internal clamps shall be shown not to induce undue stress into weld joint.
8. Force shall not be used to correct misalignment other than the nominal forces associated with
use of conventional clamps.
9. The maximum misalignment, Hi-Lo, or offset shall be as follows:
a. For reeled pipelines of X60 and greater strength pipe, not more than 1/16 inch (1.6 mm).
b. For pipelines of X52 and lesser strength pipe, not more than 1/8 inch (3.2 mm).
c. For non-reeled pipelines using X70 and lesser strength pipe on which an ECA is
performed, equal to 1/16 inch (1.6 mm).
d. For non-reeled pipelines using X70 and lesser strength pipe on which an ECA is NOT
performed, equal to 1/8 inch (3.2 mm).
e. For sour or HCAS service, 1/16 inch (1.6 mm).
f. Abutting ends of each pipe joint accurately aligned to minimize Hi-Lo between surfaces.
g. Alignment of abutting ends to minimize offset between surfaces.
h. If an offset larger than 1/16 inch (1.6 mm) for reeled X60 and stronger pipe or 1/8 inch
(3 mm) for non-reeled X52 and weaker pipe is caused by dimensional variations, equally
distributed around circumference of pipe.
10. If a wall thickness offset is encountered that exceeds 3/32 inch (2.4 mm), it shall be made by
tapering the inside wall of the thicker pipe to a maximum 30-degree angle and a minimum
14-degree angle so that misalignment is not greater than 1/16 inch (1.6 mm).
a. Supplier shall furnish internal tapering machine and perform the tapering work.
b. At its option, Owner may provide or direct Supplier to provide transition pieces.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 39 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
11. For reeled pipelines, if a wall thickness OD offset is encountered that exceeds
0.100 inch (2.5mm), the thicker wall pipe shall be removed from the flowline. No tapering
shall be done.
12. Each pipe joint element shall be properly aligned to preceding pipe joint prior to being
welded.
a. Correction of misalignment by use of steel hammers shall not be permitted.
b. Longitudinal welded pipe seams shall be located in the top quarter of pipeline.
c. Longitudinal seams in adjacent sections of pipe shall be on opposite sides of the top
center and shall be staggered by not less than 20 degrees.
d. In all bends, the longitudinal seam shall be in a plane at right angles to the bend.
e. Pipe joints shall be rotated to prevent adjacent joints having aligned longitudinal weld
seams.
13. Where the welding procedure requires a root gap for a full penetration weld, spacing tools
shall be used in conjunction with line-up clamps to ensure proper joint spacing.
14. Pipes on both sides of the joint shall not be raised, lowered, or otherwise moved, until both
the root run and the second run (hot pass) have been completed, unless Supplier can
demonstrate to the satisfaction of Owner that the root run alone is adequate to resist
deformation and cracking.
15. Unless otherwise reviewed and accepted by Owner, Supplier shall clean and contour grind
the root weld pass to remove undercutting, rough surfaces, and other defects as follows:
a. A 5/32-inch (4-mm) or 3/16-inch (5-mm) thick grinding wheel shall be used to grind the
root pass when the root pass is welded with the CO2 GMAW process or when using
SMAW (stick) electrodes with a diameter greater than 1/8 inch (3.2 mm).
b. A 1/8 inch (3.2 mm) thick grinding wheel shall be used to grind the root pass when stick
electrodes, 1/8 inch (3.2 mm) diameter or less, are used for welding the root pass.
c. Grinding shall be required for all starts, stops, and convex surfaces when the root pass is
made using the CO2 GMAW process.
d. Burn through areas shall be feathered before repair by welding.
16. After the root pass has been completed, the hot pass shall be applied in the same welding
station as the root pass.
17. In the case of mechanized welding, the hot pass may be applied in another welding station
provided the root pass is at least 3/16 inch (5 mm) in thickness or 25 percent of nominal pipe
wall, whichever is greater.
18. Time delay between completion of the root pass and starting of the hot pass shall be the same
as or less than that qualified during weld procedure qualification.
19. Succeeding beads may be applied in other welding stations as follows:
a. Before applying the next bead, all scale, slag, and coatings shall be completely removed
from each pass with the use of a powered steel brush, except the root pass where grinding
is acceptable.
b. Power wire brushing shall be used to clean the hot pass immediately after completion.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 40 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
20. No two succeeding passes (i.e., hot and filler passes or filler and cap passes) shall start or stop
at the same point in the circumference.
21. End-to-end spacing between starts or stops shall be a minimum of approximately one weld
bead width.
22. In the case of pipe lay vessel manual welding, the vessel shall not be moved until root and hot
passes are complete.
23. Movement of the pipe during root pass welding shall be prohibited except as reviewed and
accepted in advance by Owner.
24. Hammering on pipe shall be prohibited.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 41 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
4. Back welding shall be prohibited for welds in sour service, HCAS service, or fatigue service.
5. Back welding shall be permitted only upon written acceptance by Owner and when no other
reasonable alternative is feasible.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 42 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 43 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 44 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
3. Each weld shall be visually examined and shall meet acceptance criteria in the API 1104
sections ‘Qualification of Welders’ (Section 6) and ‘Acceptance Standards for NDT’
(Section 13.9) plus the following criteria:
a. Weld cap reinforcement shall be plainly visible and shall not exceed 3/16 inch (5 mm).
b. Weld cap reinforcement shall be reasonably smooth with no large ripples or undulations.
c. No slag or heavy oxides shall be present.
d. For automatic gas metal arc pipeline and flowline welds, maximum cap pass height shall
be 3/32 inch (2.5 mm) or as otherwise specified by Owner.
4. For welds in sour or HCAS reeled service, the VT acceptance criteria shall meet the
following requirements:
a. When measured, weld root reinforcement shall not exceed 1/16 inch (1.6 mm).
b. Weld cap reinforcement shall not exceed 3/32 inch (2.5 mm).
c. At no point shall the weld surface lie below the adjacent base metal surface.
d. Hi-Lo fit-up measurements shall be recorded and verified to be within the specified
maximum of 1/16 inch (1.6 mm).
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 45 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 46 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
c. Minimum experience considered for primary operator shall be at least 2000 girth welds
to the criteria in item 1 above.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 47 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
15. Test details, including a notation of all defects along with a hard copy recording of the
inspection, shall be submitted to Owner for review and acceptance.
16. Owner shall notify Supplier of acceptance of each procedure and technique validated.
17. Upon acceptance from Owner, the procedure shall become a mandatory requirement and
changes shall only be permitted with further acceptance from Owner.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 48 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 49 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
4. X-ray machines shall have the capability of being accurately positioned and actuated
remotely.
5. Crawler-type internal x-ray machines furnished by Supplier shall have at least two (2) fail
safe devices such as the following:
a. Stop trolley.
b. Anti-runaway.
6. Retrieval equipment shall be furnished by Supplier and shall be available at all times at any
work site location or aboard pipe lay vessel.
7. Qualification of radiographers shall be in accordance with the ASNT SNT-TC-1A
supplement for qualification of radiographers.
8. RT procedures shall include film brand and type. Film substitutions shall require Owner
review and acceptance, and the following shall apply:
a. All film used shall be fresh stock.
b. Outdated or expired film emulsions shall not be permitted.
c. With radioactive isotope sources, a fine grain film, acceptable to Owner, shall be used.
9. Prior to commencement of production welding, Supplier shall demonstrate that each RT
procedure will produce images that meet or exceed requirements of the API 1104 section
‘Procedures for NDT’ (Section 11) as follows:
a. Either x-ray machines or radioactive isotopes may be used as sources of radiation.
1) For sour, HCAS, or fatigue sensitive service, x-ray machines shall be used.
2) Gamma radiography shall only be permitted with written Owner acceptance.
b. Source of radiation may be located either inside or outside of the pipe as specified in
API 1104.
10. Unless otherwise specified by Owner, radiographic sensitivity shall be 1 percent or better in
the welded area, which may require longer exposure. This shall conform to the ASME
BPVC, Section V.
11. Supplier shall be responsible for protection and monitoring of all personnel working with or
operating near x-ray or gamma radiation.
a. Protection and monitoring shall comply with all applicable local, state, and federal
regulations.
b. Total tolerance or dosage shall not exceed 0.1 roentgen per week.
c. Where radioactive materials are used, the area affected by radiation shall be surveyed
and the limits of hazards shall be posted.
12. API 1104 penetrameters shall be used in conformance with the API 1104 section ‘Procedures
for NDT’ (Section 11).
13. Thickness of penetrameter shall be in accordance with the requirements for penetrameters in
the paragraphs on radiographic inspection in API 1104 section ‘Procedures for NDT’
(Section 11).
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 50 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
14. A standard test radiograph shall be made in accordance with API 1104 to establish limits for
production radiography in situations where the penetrameter cannot be placed inside the pipe
and must be placed on the exposure holder.
15. Before commencing inspection, Supplier shall make three radiographs of a weld using source
side and film side penetrameters with each penetrameter identified as to its location.
Radiographs shall be made of welds of the same diameter group and wall thickness group
and of radiographically similar material to that which will be used during production.
16. Defects noted from the radiographs shall be recorded on the same RT report form to be used
during production inspection.
a. Three copies of this RT report, together with copies of the test radiographs, shall be
submitted to Owner.
b. Owner’s representative shall decide whether the procedure is satisfactory.
17. Film shall be exposed so that the average Hurter-Driffield (H&D) density shall not be less
than 2.5. Therefore, the density through thickest portion of weld metal shall not be less than
1.8 in accordance with API 1104.
18. When requested by Owner, film or other imaging media shall be processed, handled, and
stored so that images are interpretable for at least 3 years after they are produced.
19. Radiographs shall be free from all artifacts caused by bending, dirt, faulty screen, static
marks, light leakage, and handling.
20. At the option of Owner’s representative, any film containing artifacts interfering with
interpretation of the radiograph shall be discarded and the weld shall again be radiographed
at no additional cost to Owner.
21. A densitometer or film comparison strip shall be kept at the site when radiographic
interpretation is being performed and made available upon request of Owner.
22. All interpretations of radiographs shall be made in accordance with appropriate paragraphs
under the API 1104 section ‘Acceptance Standards for NDT’ (Section 9).
23. Owner’s representative shall have the option of examining radiographs immediately
following their development.
24. In any case, no weld shall be coated or pipe lowered until radiographs are reviewed and
accepted by Owner’s representative.
25. Supplier shall use a high intensity viewer to inspect radiographs.
26. Films shall be clearly identified by lead numbers, letters, and markers so that location of the
weld and any discontinuity in the weld may be accurately located and evaluated.
27. Supplier shall consecutively number all radiographic films taken to correspond with the field
joint welds.
28. Supplier shall keep a logbook to record by station numbers the following information:
a. Number of girth welds made.
b. Number of girth welds nondestructively tested.
c. Disposition of rejected welds.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 51 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
29. Supplier shall mark a set of Owner drawings to show all film numbers and corresponding
welds on the drawing.
30. The set of Owner’s marked-up drawings and film numbers shall be made a part of the
radiographic film logbook.
31. Radiographic film logbook shall be furnished by Supplier and shall be hardback bound,
8-1/2 × 11 inches (216 mm × 280 mm) in size, and of sufficient capacity to include all
required data in one volume.
32. Upon completion of the job, Supplier shall present radiographic film logbook along with the
film negatives to Owner.
33. Minimum acceptability standards for penetration, fusion, burned through areas, slag
inclusion, gas pockets, discontinuities, and undercutting shall be in accordance with the
API 1104 section ‘Acceptance Standards for NDT’ (Section 9), and ASME B31.4 and
ASME B31.8 as applicable.
31.0 Repairs
1. When welds fail to comply wholly or in part with the requirements of this specification, all
defects shall be removed by arc gouging, grinding, or machining.
a. As an option, Supplier may elect to cut out the entire weld.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 52 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
b. Entire removal of a weld shall entail cutting out a section of pipe as a cylinder containing
the weld or, at a minimum, cutting through the existing weld and machining back on both
sides of the weld at least 1/4 inch (6 mm) from the toe of the weld cap.
2. Repair and removal of defects shall be done in accordance with the API 1104 section ‘Repair
and Removal of Defects’ (Section 13.10) and any additional requirements of this
specification.
3. No weld shall be repaired without the prior review and acceptance of Owner.
4. Weld repairs shall only be performed in accordance with the appropriate qualified repair
weld procedure, and the following shall apply:
a. Only a single repair shall be attempted on any weld defect.
b. Supplier may qualify and submit re-repair procedures for Owner’s review and
acceptance.
c. If Supplier’s re-repair procedure qualification is accepted by Owner, use of the
procedure shall be at the discretion of Owner’s representative.
5. Repairs of cracks shall not be permitted.
6. If a crack is present in any weld, the entire weld shall be removed.
7. When machining, gouging, or grinding is necessary to remove a subsurface defect, care shall
be taken that the entire defect be removed to clean metal before repair welding is started.
a. Sides and ends of the repair groove shall be properly sloped to permit a sound weld repair
to be made.
b. MPI of the excavation shall be performed to ensure that the defect has been completely
removed prior to repair welding.
8. Minimum physical length of any repair weld shall be 2 inches (50 mm) plus adequate run in
and run out transition lengths that are dependent on the depth of the repair cavity.
9. Weld repairs aft of the pipe tensioners or in the curved portion of the pipelay ramp shall only
be accomplished after Supplier performs an engineering analysis to determine how much
weld metal may be safely removed before the weld metal is subject to cracking or failure.
a. This analysis shall be submitted to Owner for review.
b. If Owner accepts this repair procedure, after review of the analysis, such acceptance shall
not relieve Supplier of the responsibility for the weld.
10. Repaired welds shall be subjected to the same NDE requirements and acceptance criteria as
the original weld.
32.0 Records
Supplier shall maintain comprehensive records for all welding and inspection activities that shall
include the following at a minimum:
1. Welding PQRs.
2. Welder qualification certificates.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 53 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
3. Pipe and weld numbers and location within pipeline or piping system.
4. Details of all weld repairs.
5. PWHT records.
6. NDE inspection records.
7. Nondestructive personnel qualification certificates.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 54 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 55 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
Levels of Criticality
No. Activities Comments
A1 A2 A3
14 Post-Weld Heat Treatment V X
15 Supplier Inspection Reports X
Levels of Criticality
(1) Witness/Verify by Owner Rep
(2) Review Documentation by Owner Rep.
(3) Obtain Certification/Test Documents
Notes:
X - Required
O - Observe
V - Verify
W - Witness (Hold Point)
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 56 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 57 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
3. CTOD testing shall be required for each welding procedure qualification with testing in weld
metal and HAZ.
a. B X 2B specimens shall be required unless otherwise accepted by Owner.
b. Test temperature shall be +32°F (±0°C) or at MDT, whichever is lower.
c. Minimum CTOD shall be 0.015 inch (0.38 mm) or higher as determined by the ECA.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 58 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
5. Every heat or lot (batch) of welding consumables to be used in production, other than those
used during PQR welding procedure qualification, shall be batch tested by Supplier using
welding parameters that shall be used in production.
a. Welding shall be completed by Supplier with mechanical testing and chemical analysis
by Owner-accepted third-party laboratory.
b. Batch testing shall include chemical analysis of bare filler metal or deposited weld metal,
all weld metal diffusible hydrogen content, tensile (yield, ultimate, elongation, and
reduction in area), Charpy impact test (energy, lateral expansion, and percent shear), and
fracture toughness (CTOD) testing to the requirements of this specification and project
requirements.
c. For SAW process, each heat of electrode shall be batch tested with the lot of SAW flux
that will be used in production welding.
1) Welding of test coupon for batch test mechanical properties shall be completed
within the range of the qualified welding procedure that will be used in production
for the welding consumables being batch tested.
2) Certification of welding consumable batch testing shall follow the basic
requirements of the appropriate ASME BPVC, Section II, Part C welding
consumable specification, with modification of testing requirements of this
specification, including this appendix and any additional project specification
requirements.
6. Additional welding filler metal requirements shall be as follows:
a. Production welding procedure as-deposited weld strength of welding consumables shall
be greater than the AYS of base metal (based on material test reports [MTRs] for each
pipe), but shall not be more than 14.5 ksi (100 Mpa) above the specified maximum YS of
the base metal, unless otherwise agreed by Owner.
b. Minimum AWMT strength elongation shall not be less than 18 percent.
c. Maximum all weld metal as manufactured diffusible hydrogen content for all welding
consumables shall be 5 ml/100g per AWS A4.3 or ISO 3690.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 59 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
3. Qualification of welding procedures shall comply as a minimum with the following three
requirements:
a. The API 1104 section ‘Qualification of Welding Procedures for Welds Containing Filler
Metal Additives’ (Section 5) or section ‘Mechanized Welding with Filler Metal
Additions’ (Section 12), as applicable.
b. API 2RD.
c. This specification, including this appendix.
4. Each WPS shall contain all non-essential and essential variable requirements of API 1104
and additional requirements of this specification.
5. After machining the bevel, all pipe coupons to be used for weld qualification or fatigue
testing shall be inspected for planar type defects per the following:
a. Bevel face shall be inspected by MT for any linear defects.
b. Pipe body within 4 inches (100 mm) of OD bevel shall be inspected by manual UT
(straight beam) for any lamination type defects.
6. Minimum, maximum, and average heat inputs for each weld pass for each weld qualification
test (minimum, maximum, heat input, and fatigue test welds) shall be electronically
measured and recorded using a weld data logger as follows:
a. Weld data logging equipment used shall allow as a minimum the sampling of at least
voltage, amperage, and travel speed for each pass.
b. For mechanized (automatic) welding, the oscillation parameters such as amplitude,
frequency, and dwell time shall be recorded and shall be listed in the welding procedure
qualification documentation and specified in the WPS.
c. For pulsed procedures, the effective heat input shall be calculated on the basis of simple
average values and, in all cases, the manufacturer and model of equipment shall be an
essential variable of the qualification.
7. The WPS shall be qualified by making welds within a heat input range that has been qualified
by mechanical testing and by testing of fatigue samples welded at the midline of the qualified
low and heat input range.
8. In defining the heat input per pass, Supplier may elect to use measured range of average heat
input per pass or recorded maximum and minimum values per pass.
9. The maximum range of welding heat input shall not exceed ±15 percent from anticipated
mid-line heat input that will be used to weld fatigue samples and production welding.
a. Supplier shall establish production heat input range for each weld pass by welding a
complete weld qualification at the low heat input values and a complete weld at high heat
input values. See Appendix B.5, item 1.
1) These welds shall meet mechanical, fracture toughness (CTOD), and NDE
requirements as specified in this specification and this appendix.
2) Maximum and minimum heat inputs and range of heat inputs for each weld pass
shall be measured and recorded.
3) During weld procedure qualification, electronic weld data logging equipment shall
be used sampling at least the voltage, amperage, and travel speed of each weld pass.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 60 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 61 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
1) Full-size CVN impact specimens shall be required unless pipe wall thickness is less
than 0.43 in (11 mm).
2) CVN impact specimens (set of three at each notch location) shall have minimum
average impact energy as shown in Table 4.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 62 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
i. There shall be no provision for retests, unless it can be shown that a welding
defect, base metal lamination or segregation, or specimen machining error or test
machine problem interfered with the test.
ii. Retests shall be accomplished in a complete set of three specimens at the notch
location requiring retesting.
iii. Retests shall only be completed when reviewed and accepted by Owner.
3) For double submerged arc welded (DSAW) pipe, two additional sets of three Charpy
impact tests shall be conducted using samples so that the specimens are completed at
FL and FL+3/32 inch (2 mm) associated with the circumferential (girth) weld
intersection and the pipe longitudinal weld seam.
4) FL and HAZ being tested shall be the longitudinal seam weld metal.
5) Absorbed energy, lateral expansion, and fracture appearance (percent shear) shall be
reported for all CVN tests.
b. Vickers hardness tests shall be completed per the locations and hardness locations
specified in Section12.0, item 6b of this specification and as follows:
1) For sour service, maximum hardness in weld metal, HAZ, and parent material shall
be per NACE MR0175/ISO 15156 requirements.
2) For welds not in sour service, maximum hardness shall be 275 HV10 in weld metal
and HAZ.
3) Photomicrographs showing the indent locations shall be submitted with each
welding PQR.
c. Cross-sections used for Vickers hardness testing shall be ground and polished (diamond
paste finish) and etched to reveal the weld metal and HAZs. These polished
cross-sections shall be visually examined and shall meet the following requirements:
1) No cracks.
2) Complete fusion at root, between layers of weld metal, and between weld metal and
base metal at the bevel interface.
3) No undercut of the cap pass with the base metal.
4) ID reinforcement of 1/16 inch (1.6 mm) maximum and OD reinforcement of
1/8 inch (3.2 mm) maximum.
5) No point on ID and OD weld surfaces lies below (is thinner than) adjacent base
metal.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 63 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
6) Weld reinforcement blends smoothly with adjacent base metal with a target
re-entrant angle of 165 degrees (unless weld surfaces are to be ground flush).
7) Surface condition used in fatigue testing is the condition used in production.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 64 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 65 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
7. During fit-up for welds subject to fatigue sensitive service, end measurements shall be taken
as required to calculate and document internal alignment at a minimum of eight equidistant
locations around pipe circumference.
a. This measurement shall be made using the top of the vertical land as the reference point.
b. Supplier shall prepare a procedure for calculation of misalignment and Hi-Lo and shall
submit to Owner for review and acceptance.
c. Fit-up information shall be available for NDE interpretation.
8. Arc strikes less than 4 inches (100 mm) from weld bevel shall be cut out as a cylinder. No
repairs shall be permitted.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 66 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
b. Arc strikes more than 4 inches (100 mm) from the toe of the weld cap may be removed
(repaired) by grinding with review and acceptance of Owner.
c. Repair of arc strikes shall not reduce the wall thickness by more than 5 percent below the
adjacent wall thickness or below the minimum allowed, whichever thickness is greater.
d. All repaired arc strike areas shall, at a minimum, be inspected for cracking using liquid
penetrant testing or MT and for any remaining HAZ using a 20 percent solution of
ammonium persulfate test.
e. No cracking or residual HAZ shall be acceptable.
f. Arc strike repairs and subsequent testing shall be witnessed by Owner.
7. Every ID production weld shall be examined by remote video camera inspection using a
system and procedure reviewed and accepted by Owner.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 67 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 68 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
>0.5−1.0 13 >1.0−2.0 13
>1.0−1.5 7 >2.0−3.0 7
>1.5 0 >3.0 0
*Buried flaws shall be defined as flaws that are more than 3 mm from the nearest free surface,
i.e., ligament > 3 mm.
3. For FSFL and SCR welds made in a fabrication yard onshore, and for offshore welds, the
following requirements shall apply:
a. Any crack shall be unacceptable and the weld shall be cut out and re-welded.
b. Planar weld flaws shall be accepted according to the criteria listed in Table 5, for both
surface breaking root or cap flaws and buried flaws.
c. Volumetric flaws shall be evaluated by the same method as planar flaws.
d. In all cases, defect and surface interaction shall be considered in defining flaw height and
length as defined in the Owner’s AUT specification requirements and the API 1104
annex ‘Alternate Acceptance Standard for Girth Welds’ (Annex A).
1) Because the criteria are influenced by the welding process to be used on the FSFLs
and SCRs and the mechanical properties of these welds, a specific AUT qualification
shall be qualified for each welding process used on each diameter and wall thickness
of pipe to be welded in production.
2) After a welding process has been defined and qualified, full-scale fatigue samples
shall be manufactured and tested to verify the fracture mechanics predictions.
3) Based on the results of the mechanical testing and the performance during fatigue
testing, the production weld acceptance criteria shall be defined.
e. Lack of fusion or lack of penetration shall not be allowed in the root region.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 69 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
4. Supplier shall use MPI to inspect 100 percent of the final weld surface of all FSFL and SCR
welds after all grinding or sanding has been completed.
5. In addition, MPI shall be performed on all qualification and fatigue test welds.
6. MPI procedure shall include the following, as a minimum:
a. Type of magnetization.
b. Type of equipment.
c. Surface preparation.
d. Wet or dry method.
e. Make and type of magnetic particles and contrast paint
f. Magnetizing current.
g. Demagnetization.
h. Description of testing technique.
i. MPI areas demagnetized after inspection, if required.
7. MPI acceptance criteria shall be such that no linear indications from MPI shall be permitted
on the weld cap reinforcement, cap toes, or pipe wall for a distance of 1 inch (25 mm) from
the toes of the weld.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 70 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 71 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 72 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
2. Weld hardness surveys at the extrados, 12 o’clock, and 6 o’clock welding positions.
a. Hardness surveys shall be as shown in Figure 1.
b. Owner shall review and accept laboratory procedure to ensure that FL indents are as
close to the FL as possible.
c. All individual hardness measurements shall be below 250 HV10.
3. Charpy impact tests as per Section 12.0, item 7 for non-fatigue-sensitive pipe, or as per
Appendix B.6, item 4 for fatigue-sensitive pipe.
4. CTOD testing of as-welded (not ASA) SENT samples to develop the required J-R curves and
segment tests to validate the J-R curve methodology.
a. Testing shall be as described in Section 6.0 and the project ECA specification.
b. Six SENT specimens shall be required.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 73 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 74 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
Note: This series of tests establishes the fatigue crack growth rate over a range of stress
intensity factors. The crack growth model is used as an input to the ECA to establish
allowable initial defect sizes for inspection.
1. The appropriate crack growth data for the project-specific solution shall be established.
2. For the onshore mainline procedure, CT specimens shall be extracted from ASA samples,
centered on the girth weld. Fatigue crack growth rate testing shall not be required for all other
welding procedures.
a. Specimens shall be extracted in the L-C or NP orientation.
b. Specimens shall be extracted half from the intrados and half from the extrados.
3. A frequency scan shall be performed to determine the loading frequency with the fastest
crack growth rate as follows:
a. Scans of two specimens shall be performed, one from the intrados and one from the
extrados.
b. Scans shall take place in the project-specific solution.
c. ΔK and Kmax shall be maintained by continual monitoring and shedding the applied load
range as crack length increases during the test.
d. Loading frequency shall be decreased from 1 Hz down to 0.001 Hz in steps as follows:
1) Steps of 1.0, 0.33, 0.1, 0.033, 0.01, 0.001 Hz.
2) After each 0.039-inch (1-mm) of crack incremental growth.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 75 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
4. Paris Law fatigue crack growth rate tests shall be performed as follows:
a. Two specimens shall be tested, one from the intrados and one from the extrados.
b. Scans shall take place in the project-specific solution.
c. Specimens shall be tested at the fastest growth rate frequency from the frequency scan, or
the operational fatigue rate (whichever is lower).
d. Fatigue crack growth rate tests shall be performed as a function of ΔK with a constant
Kmax.
5. In-air crack growth tests shall be performed as follows:
a. Two specimens shall be tested, one from the intrados and one from the extrados.
b. Tests may be performed at a relatively high frequency (5−10 Hz) in air.
c. Tests shall be performed as a function of ΔK with a constant Kmax.
Note: The knockdown factor quantifies the relative performance of the service
environment-exposed strip specimens to the in-air strip specimens. The knockdown
factor need only be determined for one weld procedure and then be applied to
full-scale fatigue performance for all weld procedures.
2. Longitudinal strip specimens shall be extracted from ASA samples, each containing at its
center a segment of the girth weld.
3. Fatigue resistance-enhancing treatment of the OD cap (e.g., grinding the cap and peening the
toes) may likely be required to ensure that the test quantifies the performance of the weld on
the ID (i.e., ensures that the OD performance does not drive the test result).
4. All strip specimens shall be taken from the extrados.
5. For in-air tests, six strip specimens shall be fatigue tested to failure (or run out) in air at three
stress levels (two specimens per stress level). In-air fatigue tests may be run at high
frequency, 5−10 Hz.
6. For in-situ tests, six strip specimens shall be fatigue tested to failure (or run out) in
project-specific solution at three stress levels (two specimens per stress level). The loading
frequency shall be determined by the frequency scan test detailed in Appendix C.6.1.
December 2016 © 2007−2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 76 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
Table 6: Weld Qualification Test Matrix for Reeling Installation in Sour/HCAS Service
Section No. of
Test Type Reasoning Environment Comments
No. Tests
To simulate coating prior to spoolbase welding, string heated to 482°F (250°C) for
Full Scale Simulate Coating, 1 hour prior to straining.
C.2.2 Reeling Reeling, and N/A N/A String subjected to maximum number of strain cycles allowed during installation.
Simulation Operating Lifetime After straining, string heated to 482°F (250°C) for 1 hour to simulate lifetime of
service at temperature.
2× extrados, 2× intrados, and 2× neutral axis.
Cross-Weld Mechanical
C.3 6 Air Full stress-strain curve (to 5 percent strain) to be recorded using extensometer and
Tensile Tests Properties
reported on graph with both axes fully labelled.
In accordance with Owner hardness map (see Figure 1).
Hardness Mechanical 1x extrados, 1x intrados, 1x neutral axis.
C.3 3 Air
Survey Properties Owner to review and accept hardness maps to ensure acceptable placement of FL
indents.
Specimen number shown is number of sets of three specimens required.
Specimens taken as per Section 12.0, item 7.
C.3 CVN Impact Toughness 9 Air
For material thicker than 3/4 inch (19 mm), similar number of specimens will be
required from root region of weld.
C.3 CTOD – SENT Reeling ECA Input 6 Air Performed on unstrained girth weld to test susceptibility to tearing during reeling.
Applied stress shall be 90 percent AYS of parent pipe, applied in axial direction
Project
C.4 Full Ring Test SSC Resistance 3 using hydraulic jacks.
Solution
Only two tests required for automatic welding procedures.
1 × WCL, 1 × HAZ, and 1× base metal (BM).
K1SSC – Fracture CT or SENB samples allowed (to match screening and validation tests).
C.5 3 Air
Calibration Toughness Calibration used to determine CTOD curve that will be used to calculate J values for
in-situ testing.
2× WCL, 2 × HAZ, and 2× BM.
K1SSC – Fracture Project CT or SENB samples allowed.
C.5 6
Screening Toughness Solution Step load or slow rising displacement test performed to determine approximate
K1SSC of each location.
Four samples to be taken from most severe location (lowest K1SSC) determined in
K1SSC – Fracture Project screening tests.
C.5 4
Validation Toughness Solution CT or SENB samples allowed.
Samples to be tested at constant load for 30-days to validate K1SSC.
December 2016 © 2007-2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 77 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
Section No. of
Test Type Reasoning Environment Comments
No. Tests
1× extrados, 1× intrados.
Fatigue Fatigue Testing Project CT samples.
C.6.1 2
Frequency Scan Frequency Solution Determines the loading frequency of most rapid crack growth for knockdown factor
and fatigue crack growth rate tests.
Fatigue Crack Paris Law Project 1× extrados, 1× intrados.
C.6.1 2 CT samples.
Growth Rate Determination Solution
Determines the fatigue crack growth rate in project-specific solution.
3× extrados and 3× intrados.
6 Air Control tests used to determine fatigue knockdown factor due to sour service
Fatigue S-N Knockdown exposure.
C.6.2
Segment Factor 3× extrados and 3× intrados.
Project
6 Loading frequency as determined by Appendix C.6.1.
Solution
Tests used to determine S-N fatigue knockdown factor.
Testing per SSM-SU-5414.
Full Scale 12 full weld samples required.
C.6.3 Fatigue Resistance 12 Air
Fatigue Where Supplier proposes production welds without removal of cap, Owner requires
additional tests with caps removed to demonstrate root performance.
Notes:
1. Extrados is taken to mean location of maximum initial tensile strain. Intrados is taken to mean location of maximum initial compressive strain.
2. If multiple sour/HCAS solutions are to be used during operations, additional equivalent testing must be performed in each solution.
3. Matrix shows the number of tests required for each weld procedure.
December 2016 © 2007-2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 78 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
D.2 Materials
1. Pipe used per this appendix shall be manufactured clad pipe or manufactured lined pipe
procured to a Owner or project technical specification for CRA clad or CRA lined pipe. The
carbon steel base pipe shall be of API 5LX grades 52 through X65.
2. The CRA material shall be of 0.120 inch (3 mm) minimum thickness unless otherwise
specified by the Owner.
3. The CRA material shall be one of the following alloys as specified by the Owner:
a. Alloy 625 (UNS N06625).
b. Alloy 825 (UNS N08825).
c. Alloy 316L (UNS S31603).
d. Duplex stainless steel (UNS 31803 or UNS S32205).
4. Pipe ends (clad and lined pipe) supplied for circumferential seam welding shall have the clad
or lining on ID ends cut back 1.5 inch (38 mm) minimum and weld overlayed with minimum
of two layers of type 625 (AWS classification ERNiCrMo-3/ENiCrMo-3) weld metal. This
overlay shall be machined to match the ID of the pipe and shall have a maximum 125 RMS
maximum surface roughness.
December 2016 © 2007-2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 79 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
4. The GTAW process, as a minimum, shall be required for the root and hot passes of all welds.
5. The following welding processes shall be acceptable for tie-in spool welding and yard
riser-welding:
a. Mechanized GTAW.
b. Mechanized GMAW-P.
c. Manual GTAW.
d. SMAW (fill and cap passes only).
6. Welding consumable requirements shall be as follows:
a. Alloy 625 (ERNiCrMo-3 / ENiCrMo-3) welding consumables shall be used for welding
the circumferential seams of all joints and materials from root pass through cap passes
for all CRA clad/CRA lined pipe listed.
b. Each welding procedure qualification with Alloy 625 weld metal shall be completed with
an all weld metal using largest size all weld metal tension test specimen possible,
reporting yield, ultimate strength, and percent elongation. The minimum YS reported
shall be 72.5 ksi (500 MPa).
7. Hardness shall be completed to the requirements/hardness indenture locations of
NACE MR0175/ISO 15156 with the following acceptance criteria:
a. 300 HV10 maximum in the carbon steel backing material and HAZ.
b. 350 HV10 maximum for Alloy 625/825 weldment, cladding material, and HAZ.
c. 250 HV10 maximum for Alloy 316L cladding material and HAZ.
d. 330 HV10 maximum for Alloy S31803/S32205 cladding and HAZ.
8. Corrosion testing meet the following requirements:
a. The main ‘firing line’ and root repair procedure welding procedure qualifications shall
be corrosion resistance ASTM G48, Method A tested when welding to Alloy 625 and
Alloy 825 CRAs, after the removal of all carbon steel backing base metal.
b. The maximum corrosion rate shall be 1 mmpy for Alloy 625 and 0.5 mmpy for
Alloy 825.
9. Fracture mechanics tests shall meet the following requirements:
a. When an ECA is required per Section 6.0, both weld metal and HAZ (course grain)
locations shall be tested at MDT or lower for the project.
b. Testing of the HAZ shall be with removal of the clad material from each test specimen.
The weld metal shall meet a minimum J value of 700 N/mm and the HAZ shall meet a
minimum CTOD values of 0.015 inch (0.38 mm).
c. J-integral test single-edge notch tensile (SENT specimens) shall be used in accordance
with DNV-0S-F101, Appendix A, Section E100, Table A100 and Appendix B,
Section A900.
December 2016 © 2007-2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 80 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007-2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 81 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
2. The repair WPS shall meet the requirements of this specification and shall contain the
following additional information:
a. Method for removal of defects.
b. Final preparation and method of inspection of the excavated area.
c. The minimum and maximum length of the section to be repaired.
d. Any limitation with regards to locations where the procedure can be used.
e. Sketch of excavation area showing position to original weld.
3. A weld repair qualification test shall be performed on each WPS that will have weld repairs
performed on it during production.
4. Single pass weld repairs shall be prohibited.
5. The minimum length of weld repair shall be 3 inches (75 mm).
6. Arc air gouging shall be followed with grinding to bright metal and remove all affected metal
using Owner-accepted procedure. All arc air gouging operators shall pass an
Owner-accepted qualification test.
7. Arc air gouging shall not be used on any portion of the CRA clad or lining material (i.e., root
repair).
8. Only one repair attempt shall be permitted on each defect location on a per weld joint basis.
December 2016 © 2007-2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 82 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007-2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 83 of 84
Integrity Critical
Welding and Inspection Requirements for Subsea Pipelines and Risers SSM-SU-5003-B
December 2016 © 2007-2016 Chevron U.S.A. Inc. All rights reserved. Confidential – Restricted Access 84 of 84