Escolar Documentos
Profissional Documentos
Cultura Documentos
CONSTRUCTION PROJECTS
SEMINAR II
SEMINAR GUIDE: Prof (Dr) V Thiruvengdam
Prof. V D Deewan
In case of huge construction projects, speedy work and timely completion are very vital.
Mechanization of the most of the work and timely completion are very vital due to this reason
mechanization of the most of the work has been done in which, equipment and machinery play a
vital role. Proper use of the appropriate equipment contributes to the economy, quality, safety,
speed and timely completion of the project.
EQUIPMENT MANAGEMENT IN CONSTRUCTION PROJECTS I
CERTIFICATE
ACKNOWLEDGEMENT
I want to acknowledge with thanks the encouragement and generous help rendered by Dr. V.
Thiruvengadam and Prof. V D Deewan, my Thesis Guide and Professor of the Department of
Building Engineering and Management in selecting and guiding the work. It would have never
been possible for me to come to this stage without his Constructive Suggestions, Sustained
Interest and the Focused Guidance.
I also want to take this opportunity to express my gratitude towards Prof. Y K Jain, Professor and
presently the Head of the Department of Building Engineering and Management, School of
Planning and Architecture, New Delhi, for his valuable support.
Last but not the least; I want to thank my friends Princy Soni and Talha Khanfor the guidance,
help and materials they have given to me on the topic.
Shishupal Singh
Dec, 2012
EQUIPMENT MANAGEMENT IN CONSTRUCTION PROJECTS III
TABLE OF FIGURES:
Table of Contents
CHAPTER:1 INTRODUCTION .............................................................................................. 1-1
1.1 INTRODUCTION ......................................................................................................... 1-1
1.2 AIM ............................................................................................................................... 1-3
1.3 OBJECTIVE.................................................................................................................. 1-4
1.4 METHEDOLOGY ........................................................................................................ 1-4
1.5 CHAPTER STRUCTURE ............................................................................................ 1-6
CHAPTER:2 LITERATURE REVIEW ................................................................................... 2-1
2.1 INTENT OF THE CHAPTER ...................................................................................... 2-1
2.2 UNPUBLISHED SEMINAR AND THESIS WORKS - Dept. of BEM, SPA. .......... 2-1
2.2.1 MANAGEMENT OF CONSTRUCTION EQUIPMENTS IN BUILDING
PROJECTS .......................................................................................................................... 2-1
2.2.2 MECHANIZATION IN CONSTRUCTION AND ITS COST ANALYSIS ........ 2-2
2.3 PAPERS, JOURNALS AND ARTICLES .................................................................... 2-3
CHAPTER:3 CONSTRUCTION EQUIPMENT CLASSIFICATION ................................... 3-1
3.1 INTENT OF THE CHAPTER ...................................................................................... 3-1
3.2 CONSTRUCTION EQUIPMENT SECTOR IN INDIA .............................................. 3-1
3.2.1 SECTOR COMPOSITION AND SIZE ................................................................. 3-1
3.3 CLASSIFICATION OF CONSTRUCTION EQUIPMENT ........................................ 3-2
3.3.1 CLASSIFICATION ON THE BASIS OF WORK ................................................ 3-2
3.3.2 CLASSIFICATION ON THE BASIS MANUFACTURING PROCESS ............. 3-4
3.4 CONSTRUCTION EQUIPMENT TO BE COVERED IN SEMINAR ...................... 3-5
3.4.1 EXCAVATORS ..................................................................................................... 3-5
3.4.2 LIFTING EQUIPMENT - CRANE ....................................................................... 3-8
3.4.3 PILLING EQUIPMENT ...................................................................................... 3-18
3.4.4 BATCHING PLANT ........................................................................................... 3-21
3.4.5 FORMING SYSTEM .......................................................................................... 3-23
CHAPTER:4 COST OF OWNING AND PURCHASING OF CONSTRUCTION
EQUIPMENT 4-1
4.1 INTENT OF CHAPTER ............................................................................................... 4-1
4.2 TIME VALUE OF MONEY ......................................................................................... 4-1
EQUIPMENT MANAGEMENT IN CONSTRUCTION PROJECTS V
CHAPTER:1 INTRODUCTION
1.1 INTRODUCTION
Construction is the ultimate objective of a design, and the transformation of a design by
construction into a useful structure is accomplished by men and machines. Men and machines
transform a project plan into reality, and as machines evolve there is a continuing transformation
of how projects are constructed. This seminar report is explaining fundamental concepts of heavy
machine utilization, which economically match machine capability to specific project
construction requirements: The efforts of contractors and equipment manufacturers, daring to
develop new ideas, constantly push machine capabilities forward. As the array of useful
equipment expands, the importance of careful planning and execution of construction operations
increases.
In case of huge construction projects, speedy work and timely completion are very vital.
Mechanization of the most of the work and timely completion are very vital due to this reason
mechanization of the most of the work has been done in which, equipment and machinery play a
vital role. Proper use of the appropriate equipment contributes to the economy, quality, safety,
speed and timely completion of the project. A number of different types of equipment and
machinery are used in almost all types of the project such as highway projects, irrigation,
buildings, power projects etc. To obtain the best service and performance from the construction
industry, the Client should be closely involved at each step in the process. Successful
construction equipment procurement should result in a project delivered on time, to cost and to
the desired quality capable of performing the specific business function of that client. The
procurement process involves a wide range of skills for which training and development may be
required.
The main challenge in effective equipment management is the absence of linkages between the
stakeholders such as procurement, equipment department, accounts and project teams. Also, lack
of visibility on information related to equipment’s such as availability, productivity.
It has been estimated that about 15-30% of the project cost has been accounted towards
equipment and machinery. The financial aspects of the construction equipment are an important
matter particularly for construction firm.
When commercial manufacturing of heavy construction equipment began, the primary way to
acquire a new piece of equipment was outright purchase. Players in the construction industry
typically were wealthy and filled all of the primary roles — owner, designer, and contractor.
Without credit and financing, heavy equipment purchase probably would be limited today, much
like it was in the late 1800s. The proliferation of diverse equipment manufacturers around the
world has spawned great competition, not just for the purchase price of the equipment, but
financing, terms of use, and method of payment.
In the current construction marketplace, equipment manufacturers, used equipment brokers, and
rental companies provide a means for a user with proper credentials and competence to acquire
just about any heavy construction machine available on a temporary or permanent basis. There
are numerous options to consider when deciding on heavy equipment acquisition and financing.
Traditionally, the equipment purchase process was complete when the contractor selected a
specific make and model of machine from a dealer. The buyer received financing with a down
payment, often the trade-in of an older piece of equipment. The new piece of equipment was the
loan security. If the contractor defaulted on loan, then the lender could repossess the equipment.
This acquisition process today includes numerous financing options and scenarios that banks,
finance companies, leasing agencies, and manufacturers offer. All major heavy construction
equipment manufacturers offer a number of creative leasing, renting, and installment loan
products.
The equipment rental industry has leveled the playing field for contractors by minimizing the
risk associated with equipment purchase and utilization. Renting or leasing appropriate
equipment greatly increases the type and size of the projects that contractors and subcontractor
scan bid and execute. Contractors bid jobs today knowing they will rent every piece of heavy
equipment used on the project or subcontract any work requiring heavy equipment.
There are many aspects to be considered before planning and procuring of construction
equipment for projects. There will be different department will be involved in this exercise: the
design, planning, construction, mechanical, operation, maintenance, stores, space, personnel and
the most important of them finance. A decision made by several groups of people would result in
lesser problem regarding availability, utilization and productivity of equipment.
Operation research offers alternative plans for a problem so as to facilitate the management to
take proper decision. OR uses the mathematical logic and helps the management to solve the
complex problems to find optimum solutions. Many giant projects connected with railways,
highways, irrigation, mining, airports etc.; involves huge quantities of the earthwork, concreting
work and handling millions of cubic meter of the minerals and rock. Hence deployment of large
fleet of the construction equipment becomes necessary. Selection and efficiency is a crucial
factor. In such situations OR provides the management with powerful tools to quantify the
results of the different alternatives and help the management to understand and assess the
complex situation. Some of the commonly used OR techniques in system analysis of the
equipment management are briefly outlined:
OR TECHNIQUES APPLICATION
NETWORK SYSTEMS Allocation of available equipment’s,
procurement schedule, site selection,
installation and organizing heavy equipment
repairs.
WAITING LINE MODELS Study of equipment performance and sizing
and in sizing and matching of equipment.
ASSIGNEMENT MODELS Allocation of construction equipment among a
number of requirements.
TRANSPORTATION MODEL In deciding a procurement policy for different
pieces of equipment for several competing
sources of supply.
REPLACEMENT, MAINTENACE AND Decision making in selecting a suitable
RELIABILITY MODELS preventive maintenance scheme or replacement
policy
GAMING MODEL Helps to overcome unexpected occurrence
such as a major breakdown of the equipment
SIMULATION MODEL Helps in equipment matching
1.2 AIM
The aim of the seminar is to study different types of construction equipment, operations of
various construction equipment and fundamentals of equipment selection, cycle times,
production rates and costs.
The quality of performance is measured by matching the equipment spread's production against
its cost. Production is work done; it can be the volume or weight of material moved the number
of pieces of material cut, the distance traveled, or any similar measurement of progress. To
estimate the equipment component of project cost it is necessary to first determine machine
EQUIPMENT
COMPONENT OF
• Equipment Spreads PROJECT COST • Classify the
performance against equipment's.
its cost • Determining the
Productivity • Selecting heavy
• Production is Work equipments for the
Done • Different costs study.
associated with
productivity
MEASURE QUALITY PRACTICAL
PERFORMANCE APPLICATION
1.3 OBJECTIVE
Classify the construction equipment according to their use and understand operations of
various construction equipment.
Understanding of construction equipment selection, cycle times, production rates and
costs.
Estimate and Perform the analysis needed to determine costs and productions of given
construction equipment.
Enable selection of right equipment for a job with minimum cost.
1.4 METHEDOLOGY
IMPLEMENTING THE
METHODOLOGY DEVELOPED ON • CHAPTER 8: MONITORING AND CONTROLLING
THE EXISTING PROJECT AND
ANALYSING THE IMPACT ON THE OF CONSTRUCTION EQUIPMENT
FINACE OF THE PROJECT
CHAPTER 9 : CONCLUSION
In order to have a reasonable understanding of the topic, a comprehensive study has been carried
out to get the basic data, keywords, earlier records and information regarding works done. This
creates a base and builds a clear image of what has to be done further more in this subject.
c) Allocation Model.
d) Regression Model.
Study deals with the production estimate of equipment in a
particular condition for power shovel, back hoe, loader, and
dumper, batching plant and concrete pumps.
Study covers maintenance planning and maintenance program
for preventive maintenance.
The study includes the management aspects of construction
equipment regarding:
a) Layout of batching plant.
b) Operational Requirements.
c) Safety Considerations.
Outcome of the Work Recommendations for construction equipment planning for the
construction project to be considered were proposed.
Proposing points for selection of construction equipment.
Decision making on sourcing of the construction equipment.
Methods for productivity estimation of construction equipment.
Relevance to Current Methodology for estimation of productivity of construction
Work equipment.
Outcome of the Work Factors which govern the analysis of cost for the activity process, like
in concreting the decision to come over a conclusion of concreting
method.
Cost being the most important factor in deciding the method of
concreting so the cost analysis is being done for the different
concreting method
Relevance to Current Classification of construction equipment.
Work Procurement of Construction of construction equipment.
Cost analysis of construction equipment.
Imported used equipments, which include highend hydraulic mobile cranes, excavators, motor
graders, vibratory compactors comprise a negligible 0.4 per cent of the total construction
equipment market. The exports of Indian construction equipment industry were estimated at US$
35 million in 2004-05. The growth in exports in the period 2000-01 to 2004-05 was around 30
per cent. The potential exports market for construction equipment from India is projected to be
around US$ 100-120 million by 2010. Spare parts revenues range anywhere from
20–29 per cent of the total sales for representative companies and is predominant in tunneling
and drilling equipment’s. Services revenues have been higher for global players at around 11–20
per cent in comparison to 2–8 per cent of Indian players. The construction equipment industry in
India has more than 200 players; however, the top 6 players occupy about 60 per cent of the
market. The following are players and their contribution to the Indian construction equipment
industry.
Table 3-1Key Players of Construction Equipment Industry in India
• Earthmoving equipment
• Construction vehicles
The following is the industry structure and the categories involved in the construction equipment
industry:
In terms of size, earthmoving equipment constitutes the biggest segment, accounting for nearly
57 per cent of the overall equipment market. Material Handling equipment and tunneling and
drilling equipment follow with 13 per cent and 12 per cent respectively.
Table 3-2 Construction Equipment Industry Structure
II Hauling equipment
Hauling equipment: Transportation of materials by mobile units over highways or over project
roads is known as 'hauling'. The hauling is confined to movement of materials on roads or rails
only, such as with trucks, trailers or wagons.
IV Conveying Equipment
Conveying equipment: This involves moving the materials like loose and granular dug earth,
aggregates, sand concrete etc. along a stationary structure. It consists mainly of belt conveyor,
bucket conveyor, scrapper and screw conveyors, pneumatic conveyors etc. conveying is also
done by means of Ariel transportation through tramways, cable ways etc. the conventional
method of conveying is not only time consuming but also costly as compared to the use of
conveying equipment. The system solves the problem of manpower as it works automatically
and is even reliable.
V Pneumatic equipment
Pneumatic equipment’s: These equipment’s are very much useful for tunnelling and rock
excavation. They work on compressed air. Another use of air is done for the air motor used
for drill feed and hoisting. Compressed air acts like a motive force and important works like
driving of piles, power medium concrete vibrators, opening and closing of gates of aggregate
bins, sand blasting etc. are done.
type excavators are used primarily to excavate below the natural surface of the ground on which
the machine rests. The loader is a versatile piece of equipment designed to excavate at or above
wheel/track level. Unlike a shovel or hoe, a loader must maneuver and. Travel to position the
(Source: www.onlinecranes.com)
bucket to load or dump. Additionally, there are a variety of excavators available for specialty
applications.
The basic production formula is: Material carried per load X cycles per hour.
JCB 4D 0.5 37
POCLAIN 90 CK 0.83 61
(Source: www.onlinecranes.com)
BUCKETS
Buckets come in many shapes and sizes. Most can be easily replaced or changed quickly ‘‘on the
fly.’’ The shape of the bucket and the teeth or penetration edge is very much influenced by the
material that is to be excavated or moved. A bucket designed for moving loose gravel should not
be used to dig into hard material. As the material to be worked becomes harder, typically buckets
become slimmer and more elongated. Loaders, backhoes, and excavators typically have standard
buckets that can be used for a wide range of material types and uses. Buckets can have jaws or
apparatus for grasping irregularly shaped loads such as concrete chunks with rebar protruding or
jaws that can be used to cut structural members for demo. The size of the bucket and ultimate
payload must be matched to the power of the equipment. Buckets vary in width, depth, and
structure depending on the match to the power of the machine and the type of material that is
excavated or moved. Narrow sleek buckets with teeth are designed for penetration of a hard
digging surface. Narrow sleek buckets with teeth are designed for penetration of a hard digging
surface. The buckets used for moving material are typically wider and may not have teeth.
(Source: www.machineryjunctions.com)
of the growing construction industrialization witnessed in the last decades. Each type of crane is
designed and manufactured to work economically in specific site situations; modern-day sites
often employ more than one type of crane and more than one crane of the same type.
As the name suggests mobile cranes are movable (transportable) and tower crane are fixed on
ground.
I Mobile Cranes
They are further categorized into these group
Crawler
Telescoping-boom truck-mounted
Lattice-boom truck-mounted
Rough-terrain
All-terrain
CRAWLER CRANE
The full revolving superstructure of this type of unit
is mounted on a pair of continuous, parallel crawler
tracks. Units in the low to middle range of lift
capacity have good lifting characteristics and are
capable of duty cycle work such as handling a
concrete bucket. Machines of 100-short-ton capacity
and above are built for lift capability and do not have
the heavier components required for duty-cycle
work. The universal machines incorporate heavier
frames, have heavy-duty or multiple clutches and
brakes, and have more powerful swing systems. The Figure 3-5 Crawler Crane
crawlers provide the crane with good travel capability around the job site. The crawler tracks
provide such a large ground contact area that soil failure under these machines is only a problem
when operating on soils having a low bearing capacity. Before hoisting a load, the machine must
be leveled and ground settlement considered. If soil failure or ground settlement is possible, the
machine can be positioned and leveled on mats. When there are good supporting ground
conditions, a crawler crane can move with the hoisted load. This ability to carry a hoisted load
along with the crane's capacity to travel and work even in poor underfoot conditions is the main
advantage a crawler crane has over a wheeled (truck) crane. The distance between crawler tracks
affects stability and lift capacity. Some machines have the feature whereby the crawlers can be
extended.
TELESCOPING-BOOM TRUCK-MOUNTED
These are truck cranes that have a self-contained telescoping boom. Most of these units can
travel on public highways between projects under their own power with a minimum of
dismantling. Once the crane is leveled at the new worksite, it is ready to work without setup
delays. These machines, however, have higher initial cost per rated lift capability. If a job
requires crane utilization for a few hours to a couple of days, a telescoping truck crane should be
given first consideration because of its ease of movement and setup.
Telescoping-boom truck cranes have extendable outriggers for stability. In fact, many units
cannot be operated safely with a full reach of boom unless the outriggers are fully extended and
the machine is raised so that the tires are clear of the ground. Some models can operate on their
tires when there is firm, leveled ground, but their lifting capacity is markedly reduced (by 50%
and more, for 3° off level, depending on working radius) compared to working on outriggers. In
the case of the larger machines, the width of the outrigger vehicle may reach 40 ft, which
necessitates careful planning of the operation area. Additionally, these heavy machines transfer,
through the outriggers, extremely high loads to the ground. This high ground loading must be
considered vis-a-vis the soil-bearing capacity. Large-size timber or steel mats that are used to
spread the load over a larger ground area further increase the overall vehicle width. These
outrigger space considerations are also a concern when using large lattice-boom truck cranes.
LATTICE-BOOM TRUCK-MOUNTED
With the telescoping-boom truck crane, the lattice-boom truck crane has a fully revolving
superstructure mounted on a multi-axial truck/carder. The advantage of this machine is the lattice
boom. The lattice-boom structure is lightweight. This reduction in boom weight means additional
lift capacity, as the machine
predominately handles hoist load and
less weight of boom. The lattice boom
does take longer to assemble. The
lightweight boom will give a less
expensive lattice-boom machine the
same hoisting capacity as a larger
telescoping-boom unit.
The disadvantage of these units is the time and effort required to disassemble them for transport.
In the case of the larger units, it may be necessary to remove the entire superstructure.
Additionally, a second crane is often required for this task. Some newer models are designed so
that the machine can separate itself without the aid of another crane.
ROUGH-TERRAIN:
These cranes are mounted on two-axle carriers. The operator's cab may be mounted in the upper
works, enabling the operator to swing with the load. However, on many models, the cab is
located on the carrier. These units are equipped with unusually large wheels and closely spaced
axles to improve maneuverability at the job site. their high ground clearance, as well as the
ability of some models to move on slopes of up to 70%. Most units can travel on the highway but
have maximum speeds of only about 30 mph. In the case of long moves between projects, they
should be transported on low-bed trailers. Many units now have joystick controls. A joystick
enables the operator to manipulate four functions simultaneously. The most common models are
in the 20- to 50-ton capacity range and typically they are employed as utility cranes. They are
primarily lift machines but are capable of light, intermittent duty-cycle work.
ALL-TERRAIN CRANE:
This is designed with an undercarriage capable of long-distance highway travel. Yet the carrier
has all-axle drive and all-wheel steering, crab steering, large tires, and high ground clearance.
All-terrain cranes have dual cabs, a lower cab for fast highway travel, and a superstructure cab
that has both drive and crane controls. The machine can, therefore, be used for limited pick-and-
carry work. Because this crane
has both job-site mobility and
transit capability, it is an
appropriate machine when
multiple lifts are required at
scattered project sites or at
multiple work locations on a
single project. Because this
machine is a combination of two
features, it has a higher cost than
an equivalent capacity
telescoping truck crane or
rough-terrain crane. But an all-
terrain machine can be
positioned on the project without
the necessity of having other
construction equipment prepare
cranes would require. Source: Construction Equipment for Engineers, Estimators and Owners
II TOWER CRANE:
Tower cranes provide high lifting height and good working radius, while taking up a very limited
area. These advantages are achieved at the expense of low lifting capacity and limited mobility,
as compared to mobile cranes. The three common tower crane configurations are
Vertical tower with a jib kind of tower crane is the most commonly employed type. Tower
cranes of this type usually fall within one of two categories.
1. Top-slewing (fixed tower) tower cranes have a fixed tower and a swing circle ("slewing ring"
or "crown") mounted at the top, allowing only the jibs (main-jib and counter-jib), tower top, and
operator cab to rotate. The tower is assembled from modular sections, and hence the term
"sectional tower crane," often used in reference to this type of crane. The crane is stabilized
partly at its base (by ballasts or
other means of ground anchoring)
and partly by ballasts on the
counter-jib.
and both the tower and jib assembly Figure 3-10 Fixed Base Tower Crane
The main differences between these two categories are reflected in setup and dismantling
procedures and in lifting height.
foundation, either on fixing angles sunk in the base or Figure 3-11Travelling Tower Crane
on its ballasted chassis, which is bolted to the Source: www.onlinecranes.com
concrete base. On occasion, the tower may be
mounted on a ballasted static rail-mounted undercarriage. Usually, at the beginning of the
project, a large crawler or mobile crane is used to erect the tower crane to its full height;
however, many of these tower cranes have the capability to independently increase their tower
height by means of a climbing mechanism. For cranes with this ability, a smaller-size mobile
crane could be used as it is not necessary to initially erect the tower to its full height, because
additional tower sections (height) can be added later as the work progresses. There is a vertical
limit known as the maximum .free-standing height to which fixed-base cranes can safely rise
above a base, typically 200 ft for average-size top-slewing cranes, and up to 400 ft for the larger-
size cranes. If it is necessary to raise the tower above this limiting height, lateral bracing must be
provided. Guy ropes may be used to brace tower cranes, but in the majority of cases the towers
are tied to the structure being constructed using engineered steel brackets (anchorage frames).
The cost of bracing a crane to the structure rises sharply with the distance between them, which
must be taken into account when planning the exact location of the crane. Even when bracing is
provided, there is a maximum-braced height tower limit (although 1,000-ft-high top-slewing
cranes are not a particular exception). These limits are dictated by the structural capacity of the
tower frame and are machine-specific.
does not require extensive crane services in any given zone Source: www.onlinecranes.com
the mast employed. Taller the mast, the less frequent the climbing procedure. Vertical movement
of the climbing-type tower crane is by a system of hydraulically activated rams and latchings.
Normally, the crane is initially mounted on a fixed base, and as the work .progresses, it is
detached from its chassis and transfered to a climbing frame mounted on the structure. A typical
floor section cannot safely support the load imposed by the operating crane; therefore, it is
imperative for the structural designer to consider the loads imposed by the crane in the area of
this opening. If consideration for the crane loads is also taken into account in the building design,
it will usually be necessary to use shoring for several floors below the tower crane frame. To
avoid the pre-strengthening of the host building and the use of temporary shoring, the crane is
often placed for climbing inside the elevator shaft commonly serving as the building's structural
core. This location also has an advantage in that no openings are left in the floors for completion
after the crane has been raised. On the other hand, use of the elevator shaft for this purpose may
cause delays in elevator assembly, which is commonly on the critical Path of die project's
progress schedule. Additionally, it may limit the choice of the forming system for the concrete
shaft walls. At the end of construction, there will be a tower crane at the top of the structure with
no means of lowering itself. Removal must be by external methods, such as a mobile crane or by
use of a derrick. The mobile crane option may be limited by the height of the tower crane and the
confined access area next to the building. With a derrick, the tower crane to be dismantled first
lifts the derrick to the top of the building. The derrick is placed on the roof such that it can
dismantle the tower crane, and then it is dismantled itself with the use of hand tools, and its parts
are taken down in the building's elevator. Because of the heights involved and the possible
physical interference of the completed structure, the dismantling operation must be carefully
planned and given consideration as early as when project equipment is initially selected. If two
or more tower cranes were used on the project and there is overlapping hook coverage, it may be
possible to use the crane with the higher hook height to dismantle the lower crane. Under
circumstances where none of these techniques can be employed, an expensive solution is to use a
helicopter.
Usually bored piles are of replacement nature, formed in-situ using a non-percussion approach.
The consideration when forming a list of equipment to used in bored piles involves 3 main
factors:
1. How to form the bore (using what kind of machine and method to drill a hole in the ground)
2. How to protect the soil from collapsing into the bore hole during drilling (usually by inserting
a steel casing or using a drilling fluid)
3. How to take the spoil out from the bore hole during drilling (by a grasp, drilling fluid, or
compressor air)
Using small to medium sized in-situ concrete pile(Generally refers to piles ranging in size from
300mm to 900mm in diameter)
The use of drilling rigs of an appropriate capacity is required. Due to the possible collapse of
subsoil during drilling, the forming process usually required temporary protection by the use of
steel casings or some kind of drilling fluid such as bentonite slurry.
Source: www.onlinecranes.com
• Can carry a combined pile and hammer
mass of 19 T.
Power augur:
• Used for installing bored piles in clay soils
• Diameter up to 1.5m
• The hydraulic power pack drives 4 motors arranged around the ring gear. The latter can
be moved up and down a vertical guide frame mounted on the base machine.
• This is advantageous when drilling through a casing since the level of top of the casing be
allowed to vary.
• The augur is rotated at high rpm, hole is drilled and soil is removed by spinning them,
after withdrawal from the hole
Drilling Rig
Drilling rigs are able to adapt various boring arrangement.
Bucket Barrel.
Flight Auger
Drilling Shaft with drill bit
Various forms of the drilling rig for pile max up to 900mm dia.
Steel Casing
Steel Casing as temporary support during the boring process purpose of the casing serves also to
give the direction to the rig.
Carrier Tube
Carrier tube to take the mud out from the bore hole using drilling fluid (bentonite) Using of
drilling fluid to remove mud from bore hole.
Source www.onlinecranes.com
Source www.onlinecranes.com
Batchers: Batching is nothing but proportioning the ingredients of concrete such as cement, sand
aggregate and water for a particular mix of concrete by weighing each item separately. A batcher
shall consist of a suitable container for weighing an ingredient for concrete. A combination of
aggregates or a combination of cements (or cement and other cementitious materials) may each
be considered as a single ingredient. Aggregates and cement or cementitious materials shall not
be weighed in the same batcher. Each batcher shall be equipped with a scale and also with the
necessary mechanisms for its operation. The charging device shall be capable of stopping the
flow of material within the weighing tolerances specified in these Standards. Charging and
discharging devices shall not permit loss of materials when closed. The discharge device shall be
capable of controlling the rate of flow of the material. When furnished, vibrators, or other aids to
charging and discharging, shall be attached in such a manner that they will not affect accuracy of
weighing. The batcher shall be so designed and of such capacity that it will receive its rated load
without the weighed materials being in contact with the charging mechanism. The criteria to
qualify batchers for rating plates are based on minimum volumetric capacities. Volumetric
capacities may exceed the minimum requirements. In use, the rated batcher capacity may be
exceeded providing the load does not:
Concrete Mixers: The concrete mixers are used to mix all the ingredients of concrete to make
mix of specified consistency. The advantage of using concrete mixer fast mixing and also mixing
will be done properly. The important factors which govern the production from mixer are:
There are two main types of concrete mixers (i) Drum Type (ii) Pan Type
I. Drum Type. There are two main types of mixers a) tilting, b) non-tilting
(a) Tilting Mixer: Tilting mixers are useful for large construction works. Mixing of concrete in
tilting mixer occurs through rolling of material from end to center and upon itself. The tilting
mixers are easy to clean and can discharge the mix quickly and with minimum of the
segregation. Tilting mixers consist of a drum with a cast base and steel plate top, rotating on
tapered roller bearings through a driving opinion meshing with a large ring gear around the
periphery.
(b) Non-Tilting Mixer: The non-tilting mixers are useful for aggregate size upto 80mm. Mixing
of the concrete in non-tilting mixer occurs through both rolling as well as falling from the
buckets fitted inside the mixing drum. The non-tilting mixer consists of a drum rotating
about the horizontal axis. The drum is supported on rollers and is commonly driven by a
pinion meshing with a ring gear on the drum periphery.
II. Pan Type. The pan type mixers consists of an open pan with a rotating star of blades
moving in the direction opposite to that of the star and with lesser speed. These mixers
are very efficient in working especially with stiff mixes but due to its huge construction,
it is difficult to maintain and transport. In some models the pan may be stationary and
only the blades moving.
III. Truck Mixer. These are used to supply the freshly mixed concrete to the required places
from the site of batching and mixing the plant. Fully or partly mixed concrete are
transported in the truck and mixing may takes place also during the transportation. The
mixed concrete is kept in plastic state and saved from segregation through continuous
agitation of the drum.
IV. Transfer of Concrete. The transfer of mixed concrete from the mixing plant to the site
of placement is usually done in buckets usually carried on trucks or rail- road cars or
dump trucks and even belt conveyors.
V. Concrete Pumps. Concrete pumps are heavy direct acting pumps which act both as a
transfer agent as well as a placing unit for plastic concrete. These are used where the
concrete is to be placed in sites which are not readily accessible. Concrete pumps may be
mounted on trucks or trailers. The truck mounted pump and boom combination is
particularly efficient and cost effective in saving labour and eliminating the need for
pipelines to carry the concrete.
VI. Pneumatic Concrete Placer. It is done using compressed air to push the concrete
through a pipeline and can be used for placing concrete in inaccessible places. It consists
of a pressure vessel with opening at top and a conical bottom. The bottom has opening on
both the sides which are connected to the discharge pipe and the other to compressed air
pipe. When concrete is placed in the vessel by closing the air gate valve, the air pressure
is applied by opening the gate valve. Before this operation, the chamber has to be closed
totally by pulling the cone upwards. So, when the air pressure is applied, the concrete
moves through the discharge pipeline and discharge at the required place.
VII. Concrete Vibrator. Compacting of concrete is important to improve the characteristics
of concrete. Vibrators are used for compaction of concrete after placement. There are two
types of vibrator:
a) Internal Vibrator
b) External Vibrator
Internal vibrator is used in freshly placed concrete, while the external vibrator is used on the
formwork or the surface of the concrete, through which the vibrations are conveyed to the
interior of the mass. Internal vibrators are more efficient, easier to handle and manipulate in
difficult positions and used for mass concreting works, while external vibrators are used only for
construction of pavements, precast work or canal lining.
F=A*[(1+i)n-1+(1+i)n-2+(1+i)n-3+......(1+i)+1]
Or F=A*[(1+i)n-1]/i
Or A=F*[i/{(1+i)n-1}]where,
A=uniform end-of-period payments or receipts continuing for a duration of n periods
The relationship i/{(1+i)n-1}] is known as the uniform series sinking fund factor (USSFF)
because it determines the uniform end-of-period investment A that must be made to provide an
amount F at the end of n periods. To determine the equivalent uniform period series required to
replace a present value of P,
P=A*[{(1+i)n-1}/{i*(1+i)n}] Uniform series present worth factor (USPWF)
Or A=P*{i*(1+i)n}/{(1+i)n-1} Uniform series capital recovery factor(USCRF)
Cash-flow diagram of above equation is shown below. Cash flow diagrams are drawings where
the horizontal line represents time and the vertical arrows represent cash flows at specific times
In order to determine the most economical time to replace equipment, accurate records of
maintenance and repair costs and downtime must be kept for each machine. The owner must
consider all costs related to ownership and operation of the equipment. Also consider the impact
of continuous use of the machine on these costs. Hourly working rate of construction equipment
comprises of the following components:
Owning Cost.
Operating Cost.
Investment Cost
Depreciation
Salvage value
Major repairs and overhauls
Taxes
Insurance'
Storage and miscellaneous
I INVESTMENT
Investment cost (or interest) represents the annual cost (converted to an hourly cost) of the capital
invested in equipment is purchased from company assets, an interest rate should be charged
equal to the rate of return on company investments. Thus investment cost is computed as the
product of an interest rate multiplied by the value of the equipment machine. If borrowed funds
are utilized, it is simply the interest charge on these funds. However, if the item of, then
converted to cost per hour. The true investment cost for a specific year of ownership is properly
calculated using the average value of the equipment during that year. However, the average
hourly investment cost may be more easily calculated using
1+𝑛
𝐼𝑓 𝑆 = 0; 𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡 = ×𝑃
2𝑛
𝑆(𝑛 − 1) + 𝑃(𝑛 + 1)
𝐼𝑓 𝑆 ≠ 0 ; 𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝑖𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡 =
2𝑛
Where, S= Salvage Value
n= useful life in years
P= capital cost
II DEPRICIATION
Depreciation represents the decline in market value of an item of equipment due to age, wear,
deterioration, and obsolescence. In accounting for equipment costs, however, depreciation is
used for two separate purposes: (1) evaluating tax liability, and (2) determining the depreciation
component of the hourly equipment cost. Note that it is possible (and legal) to use different
depreciation schedules for these two purposes. For tax purposes many equipment owners
depreciate equipment as rapidly as possible to obtain the maximum reduction in tax liability
during the first few years of equipment life. However, the result is simply the shifting of tax
liability between tax years, because current tax rules of the U.S. Internal Revenue Service (IRS)
treat any gain (amount received in excess of the equipment's depreciated or book value) on the
sale of equipment as ordinary income. The depreciation methods explained in the following
pages are those commonly used in the construction equipment industry. When the methods of
engineering economics are used, the depreciation and investment components of equipment
owning costs will be calculated together as a single cost factor. In calculating depreciation, the
initial cost of an item of equipment should be the full delivered price, including transportation,
taxes, and initial assembly and servicing. For rubber-tired equipment, the value of tires should be
subtracted from the amount to be depreciated because tire cost will be computed separately as an
element of operating cost. Equipment salvage value should be estimated as realistically as
possible based on historical data. The equipment life used in calculating depreciation should
correspond to the equipment's expected economic or useful life. The IRS guideline life for
general construction equipment is currently 5 years, so this depreciation period is widely used by
the construction industry. The most commonly used depreciation methods are the straight-line
method, the sum-of-the-years'-digits method, the double-declining balance method, and IRS-
prescribed methods. Procedures for applying each of these methods are explained below.
Straight-Line Method
The straight-line method of depreciation produces a uniform depreciation for each year of
equipment life. Annual depreciation is thus calculated as the amount to be depreciated divided by
the equipment life in years. The amount to be depreciated consists of the equipment's initial cost
less salvage value (and less tire cost for rubber-tired equipment).
𝐶𝑜𝑠𝑡 − 𝑆𝑎𝑙𝑣𝑎𝑔𝑒(−𝑇𝑖𝑟𝑒)
𝐷𝑛 =
𝑁
Where, Dn= Depreciation
n= year of life
N= Life of Equipment
denominator of the depreciation factor is the sum of the years' digits for the depreciation period.
The numerator of the depreciation factor is simply the particular year digit taken in inverse order.
Thus for the first year of a 5-year life, 5 would be used as numerator.
𝑌𝑒𝑎𝑟 𝐷𝑖𝑔𝑖𝑡
𝐷𝑛 = × 𝐴𝑚𝑜𝑢𝑛𝑡 𝑡𝑜 𝑏𝑒 𝐷𝑒𝑝𝑟𝑖𝑐𝑖𝑎𝑡𝑒𝑑
𝑆𝑢𝑚 𝑜𝑓 𝑌𝑒𝑎𝑟 ′ 𝑠 𝐷𝑖𝑔𝑖𝑡
2
𝐷𝑛 = × 𝐵𝑜𝑜𝑘 𝑉𝑎𝑙𝑢𝑒 𝑎𝑡 𝑡ℎ𝑒 𝑏𝑒𝑔𝑖𝑛𝑖𝑛𝑔 𝑜𝑓 𝑡ℎ𝑒 𝑦𝑒𝑎𝑟
𝑁
IRS- Prescribed Method
Since the Internal Revenue Service tax rules change frequently, always consult the latest IRS
regulations for the current method of calculating depreciation for tax purposes. The Modified
Accelerated Cost Recovery System (MACRS) has been adopted by the Internal Revenue Service
for the depreciation of most equipment placed in service after 1986. This depreciation method is
also referred to as the General Depreciation System (GDS) by the IRS. Under the MACRS
system, depreciation for all property except real property is spread over a 3-year, 5-year, 7-year,
or 10-year period. Most vehicles and equipment, including automobiles, trucks, and general
construction equipment, are classified as 5-year property. The yearly deduction for depreciation
is calculated as a prescribed percentage of initial cost (cost basis) for each year of tax life without
considering salvage value. For 5-year property, annual depreciation percentages are 20%, 32%,
19.2%, 11.52%, 11.52%, and 5.76% for years 1 through 6, respectively. Notice that regardless of
the month of purchase; only one-half of the normal double-declining-balance depreciation is
taken in the year of purchase. The remaining cost basis is spread over a period extending through
the year following the recovery life. Thus, depreciation for 5-year property actually extends over
a 6-year period. This procedure is referred to by the IRS as using the "half-year convention."
EQUIPMENT SCRAPER
SPECIFICATIONS
Power KW (HP) 150 (201)
Investment (Cost) Rs 2,200,000.00
Useful Life years 6
Tyre Cost Rs 250,000.00
Life of Tyre
Working Hrs/ Years 2000
Information about the project
Repair cost of Tractor 72% of initial cost Rs 1,584,000.00
Salvage Value of Tractor 10% of initial cost Rs 220,000.00
Scrap Value of Tractor 10% of initial cost Rs 220,000.00
DEPRECIATION SCRAPER
DEPRECIATION SCRAPER
DEPRECIATION SCRAPER
0 Rs 2,200,000.00
1 Rs 650,000.0 Rs 650,000.0 Rs 1,550,000.0
2 Rs 433,333.3 Rs 1,083,333.3 Rs 1,116,666.7
3 Rs 288,888.9 Rs 1,372,222.2 Rs 827,777.8
4 Rs 192,592.6 Rs 1,564,814.8 Rs 635,185.2
5 Rs 128,395.1 Rs 1,693,209.9 Rs 506,790.1
6 Rs 85,596.7 Rs 1,778,806.6 Rs 421,193.4
Total Book Value Rs 7,257,613.17
From graph it can be clearly seen from the graph that in case of double declining balance method
depreciation in early years is higher in comparison to other two methods and then goes on
decreasing in the coming years. Similarly, in case of the sum of years digit method depreciation
decreases with time but the depreciation is less as compared to the double decline balance
method. Straight line method is represented by a straight line showing the same rate of
depreciation every year.
Rs1,600,000.0
Rs1,400,000.0
Rs1,200,000.0
Double Decline
Rs1,000,000.0
Balance
Rs800,000.0 Sum of years digit
method
Rs600,000.0
Straight Line Method
Rs400,000.0
Rs200,000.0
Rs-
1 2 3 4 5 6
Figure 4-2 Comparison of Depreciation Rates by Straight Line Method, Sum of the Year Method and Double- Declining
Method
V TAXES
In this context, taxes refer to those equipment ownership taxes that are charged by any
government subdivision, They are commonly assessed at a percentage rate applied against the
book value of the machine, Depending on location, property taxes can range up to about 4.5% of
assessed machine value. In many locations, there will be no property tax on equipment. Over the
service life of the machine, they will decrease in magnitude as the book value decreases.
VI INSURANCE
Insurance, as considered here, includes the cost to cover fire, theft, and damage to the equipment.
Annual rates can range from I to 3%. This cost can be actual premium payments to insurance
companies, or it can represent allocations to a self-insurance fund maintained by the equipment
owner.
Fuel Cost
Service Cost
Repair Cost
Tire Cost
Special Item
Operator
I FUEL COST
The hourly cost of fuel is simply fuel consumption per hour multiplied by the cost per unit of fuel
(gallon or liter). Actual measurement of fuel consumption under similar job conditions provides
the best estimate of fuel consumption. However, when historical data are not available, fuel
consumption may be estimated from manufacturer's data or by the use of Table 4-l. Table.4-1
provides approximate fuel consumption factors in liters per horsepower per hour for major types
of equipment under light, average, and severe load conditions.
Table 4-1 Fuel Consumption Factors (litre/HP/hr)
0.5×𝐵𝐻𝑃×𝐶``×4.5
Optimum fuel consumption = 𝑖𝑛 𝑙𝑖𝑡𝑟𝑒𝑠/ ℎ𝑟
8.26
II SERVICE COST
Service cost represents the cost of oil, hydraulic fluids, grease, and filters as well as the labor
required to perform routine maintenance service. Equipment manufacturers publish consumption
data or average cost factors for oil, lubricants, and filters for their equipment under average
conditions. Using such consumption data, multiply hourly consumption (adjusted for operating
conditions) by cost per unit to obtain the hourly cost of consumable items. Service labor cost
may be estimated based on prevailing wage rates and the planned maintenance program.
Since service cost is related to equipment size and severity of operating conditions, a rough
estimate of service cost may be made based on the equipment’s fuel cost
Table 4-2 Service Cost Factors (% of hourly fuel consumption)
This method of prorating repair costs is essentially the reverse of the sum-of the- years'-digits
method of depreciation explained earlier, because the year digit used in the numerator of the
equation is now used in a normal sequence (i.e., 1 for the first year, 2 for the second year, etc.)
Table 4-3 Typical Life Time Repair Cost (% initial cost less tire cost)
IV TIRE COST
Tire cost represents the cost of tire repair and replacement. Among operating costs for rubber-
tired equipment, tire cost is usually exceeded only by repair cost. Tire cost is difficult to estimate
because of the difficulty in estimating tire life. As always, historical data obtained under similar
operating conditions provide the best basis for estimating tire life. However, Table 4-4 may be
used as a guide to approximate tire life. Tire repair will add about 15% to tire replacement cost.
Following equation may be used to estimate tire repair and replacement cost.
𝐶𝑜𝑠𝑡 𝑜𝑓 𝑆𝑒𝑡 𝑜𝑓 𝑇𝑖𝑟𝑒𝑠(𝑅𝑠)
Tire cost = 1.15 × 𝐸𝑥𝑝𝑒𝑐𝑡𝑒𝑑 𝑇𝑖𝑟𝑒 𝐿𝑖𝑓𝑒 (𝐻𝑟)
Operating Condition
Type of Equipment Favorable Average Severe
Dozers and loaders 3200 2100 1300
Motor Grader 5000 3200 1900
Scraper
Conventional 4600 3300 2500
Twin Engine 4000 3000 2300
Push-Pull and Elevating 3600 2700 2100
Trucks and Wagon 3500 2100 1100
V SPECIAL ITEMS
The cost of replacing high-wear items such as dozer, grader, and scraper blade cutting edges and
end bits, as well as ripper tips, shanks, and shank protectors, should be calculated as a separate
item of operating expense. As usual, unit cost is divided by expected life to yield cost per hour.
VI OPERATOR
The final item making up equipment operating cost is the operator's wage. Care must be taken to
include all costs, such as worker's compensation insurance, Social Security taxes, overtime or
premium pay, and fringe benefits in the hourly wage figure. The crew charges are worked as per
actual annual cost over the operational hours during the year. The crew charges could be worked
out for various categories as follows:
𝑚𝑜𝑛𝑡ℎ𝑙𝑦 𝑠𝑎𝑙𝑎𝑟𝑦 ×12
Hourly Cost Worker= 𝐴𝑛𝑛𝑢𝑎𝑙 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑜𝑛𝑎𝑙 𝑐𝑜𝑛𝑠𝑡𝑟𝑢𝑐𝑡𝑖𝑜𝑛 ℎ𝑜𝑢𝑟𝑠 𝑜𝑓 𝑡ℎ𝑒 𝑚𝑎𝑐ℎ𝑖𝑛𝑒
I EXCAVATORS: Adopting a Time Value Approach for Calculating the Ownership Cost
The cost of a back hoe excavator-JCB is Rs 2400000/- and to have useful life of 7 years and have
salvage value of 10% of the cost of the equipment. Taking rate of interest 12%. Taxes, insurance,
and storage should amount to an additional 8%, which results in an overall cost of money of 12 +
8, or 20%. What are the uniform annual equivalents of estimated ownership costs?
II TOWER CRANE: Adopting a Time Value Approach for Calculating the Ownership
Cost
The cost of a tower crane is Rs 80000000/- and to have useful life of 7 years and have salvage
value of 10% of the cost of the equipment. Taking rate of interest 12%. Taxes, insurance, and
storage should amount to an additional 8%, which results in an overall cost of money of 12 + 8,
or 20%. What are the uniform annual equivalents of estimated ownership costs?
Cost Rs 8,000,000.00
Rate of Interest 20%
Salvage Value Rs 800,000.00
Useful Life (years) 7
Use Rate (hr/year) 1000
uniform annual equivalents of estimated ownership cost
III BATCHING PLANT: : Adopting a Time Value Approach for Calculating the Ownership
Cost
Determining the ownership cost of the batching plant of capacity 20.0 m³ which is electrically
operated. Initial cost of the batching plant Rs 30,00,000.00 which includes erection of the
batching plant at the site
Investment cost is computed as the product of the interest rate multiplied by the value of the
equipment, which is then converted into cost per hour of operation. The average annual cost of
interest should be based on the average value of the equipment during its life. The average value
of the equipment may be determined from the following equation:
𝐼𝐶(𝑛 + 1)
𝑃=
2
Where, P= the average value, IC = investment cost, n= number of use life of the equipment
𝐼𝐶(𝑛 + 1) + 𝑆(𝑛 − 1)
𝑃=
2𝑛
I EXCAVATOR: Using Average Annual Invest Method for Calculating the Ownership
Cost
The cost of a back hoe excavator-JCB is Rs 2400000/- and to have useful life of 7 years and have
salvage value of 10% of the cost of the equipment. Taking rate of interest 12%. Taxes, insurance,
and storage should amount to an additional 8%, which results in an overall cost of money of 12 +
8, or 20%. What are the uniform annual equivalents of estimated ownership costs?
Cost of Equipment Rs 2,400,000.00
Rate of Interest 20%
Salvage Value Rs 240,000.00
Useful Life (years) 10
Use Rate hr/ year 1000
AAI
AAI Rs 1,428,000.00
Investment Cost/ hr Rs 285.60
Depriciation/ hr Rs 216.00
Operator Charges/hr Rs 100.00
Owning Cost/ hr Rs 601.60
II TOWER CRANE: Using Average Annual Invest Method for Calculating the Ownership
Cost
The cost of a tower crane is Rs 1800000/- and to have useful life of 7 years and have salvage
value of 10% of the cost of the equipment. Taking rate of interest 12%. Taxes, insurance, and
storage should amount to an additional 8%, which results in an overall cost of money of 12 + 8,
or 20%. What are the uniform annual equivalents of estimated ownership costs?
AAI
AAI Rs 4,760,000.00
Investment Cost/ hr Rs 952.00
Depriciation/ hr Rs 720.00
Operator Charges/hr Rs 42.31
Owning Cost/ hr Rs 1,714.31
III BATCHING PLANT: Using Average Annual Invest Method for Calculating the
Ownership Cost
Determining the ownership cost of the batching plant of capacity 20.0 m³ which is electrically
operated. Initial cost of the batching plant Rs 30,00,000.00 which includes erection of the
batching plant at the site
the Corps of Engineers method and Peurifoy method. Three methods are described below which
are generally used:
Caterpillar Method
Associated General Contractor of America (AGC) Method
Peurifoy/ Schexnayder Method
1. No prices for any item are provided. For reliable estimates these must be obtained locally.
2. Calculations are based on complete machine. Separate estimate are not necessary for the
basic machine like dozer, control, etc.
3. The multiplier factor will work equally well in any currency expressed in decimals.
4. Because of the standards of comparison, what may seem to sever application to one
machine owner may appear only average to another. Therefore, in order to better describe
machine use, the operating condition and applications are defined in zones.
Ownership costs are calculated as a sum of costs incurred due to depreciation, interest, insurance
and taxes. Usually depreciation is done to zero value with straight line method, which is not
based on tax consideration but resale or residual value at replacement may be included for
depreciation or tax incentive purposes
Fuel Cost
Filter, Oil, and grease Cost
Repair Cost
Tire Cost
Special Item
Operator
Repair Cost
Life Time Repair Cost Factor X Initial Cost
Rs 8,041,000.00 Rs 574.36
Tyres Cost 1.15X(Cost Set for Tyres/Expected Life In Rs 47.92
hours)
Operator Cost 12 X monthly Salary / Operational Hr Rs 150.00
Operator @ Rs 25000/month
HOURLY OWNING COST Rs 222.51
HOURLY OPERATING COST Rs2,140.58
TOTAL HOURLY COST Rs 2,363.09
EQUIPMENT CRANE
SPECIFICATIONS Tower Crane
Power KW (HP) 150 (201)
Cost Rs 8,000,000.00
Useful Life Hrs 8,000
Working Hrs 1,000
Useful Life (Years) 8
DEPRICIATION Crane
0 Rs 8,000,000.00
Repair Cost
Life Time Repair Cost Factor X Initial Cost
Rs 1,300,000.00 Rs 162.50
Operator Cost 12 X monthly Salary / Operational Hr Rs 132.00
Operator @ Rs 11000/month
HOURLY OWNING COST Rs 1,494.00
HOURLY OPERATING COST Rs 3,283.95
TOTAL HOURLY COST Rs 4,777.95
0 Rs 2,000,000.00
1 Rs 100,000.0 Rs 100,000.0 Rs 1,900,000.0
2 Rs 100,000.0 Rs 200,000.0 Rs 1,800,000.0
3 Rs 100,000.0 Rs 300,000.0 Rs 1,700,000.0
4 Rs 100,000.0 Rs 400,000.0 Rs 1,600,000.0
5 Rs 100,000.0 Rs 500,000.0 Rs 1,500,000.0
6 Rs 100,000.0 Rs 600,000.0 Rs 1,400,000.0
7 Rs 100,000.0 Rs 700,000.0 Rs 1,300,000.0
8 Rs 100,000.0 Rs 800,000.0 Rs 1,200,000.0
9 Rs 100,000.0 Rs 900,000.0 Rs 1,100,000.0
10 Rs 100,000.0 Rs 1,000,000.0 Rs 1,000,000.0
11 Rs 100,000.0 Rs 1,100,000.0 Rs 900,000.0
LABOUR COST
Ownership Cost
The ownership cost considered in this method is the same as described in the Caterpillar method:
however, replacement cost of escalation is also considered. Depreciation is calculated by the
straight line method and includes the purchase price, sales tax, freight and erection cost with an
assumed salvage value of 10% Average economic life in hours and average annual operating
hours are shown for each size range. Replacement cost escalation of 7% is designed to augment
the capital recovery and to offset the inflation and machine price increase. Interest on the
investment is assumed to be 7%, where taxes and insurance, and storage is taken as 4.5%.
Operating Cost
Maintenance and repair costs are calculated based on hourly percentage rate times the acquisition
cost. It is a level regardless of the age of the machine. This method includes field and shop
repairs, overhaul, and replacement of tires and tracks, etc. Fuel, oil and grease costs are not
included in this method
Depreciation 15%
Replacement cost Escalation 7%
Interest on Investment 7%
Taxes, Insurance & Storage 4.50%
Ownership Expense 33.5%
Repair & Maintenance 19.40%
Salvage Value 10%
Depreciation 15%
Replacement cost Escalation 7%
Interest on Investment 7%
Taxes, Insurance & Storage 4.50%
Ownership Expense 33.5%
Repair & Maintenance 19.40%
Salvage Value 10%
Determining the owning and operating cost of the batching plant of the capacity 30 m³/hr and 45
m³/hr, those are electrically operated particulars are given below:
LABOUR COST
LABOUR COST
COMPONENT OF
COST BATCHING PLANT AP-30 (Inline) BATCHING PLANT AP-45 (Inline)
DETAILS HOURLY COST DETAILS HOURLY COST
(A) OWNING COST
Rs Rs
Capital Cost
2,700,000.00 3,150,000.00
Useful Life
3,000,000 -
Ownership Expense total ownership/ annual Rs 452.25 total ownership/ Rs 527.63
Ownership Cost
This method assumes the straight-line method for depreciation. The value of equipment is
depreciated to be zero at the end of useful life of the equipment. The ownership cost is based on
an average investment cost that is taken as 60% of the initial cost of the equipment. Usually
equipment owners charge an annual fixed rate of interest against the full purchase of the
equipment. This gives an annual interest cost which is higher than the normal. As the cost of
depreciation has already been claimed, it’s more realistic to base the annual cost of investment
on the average value of equipment during its life. This value can be obtained by taking an
average values at the beginning of each year that the equipment will be used. The cost of
investment is taken as 15% of the average investment.
Operating Cost
As the tire life is different from that of the equipment, its costs are treated differently. The
maintenance cost is taken as 50% of the annual depreciation, the fuel and the FOG costs
included, whereas the operator wages are no included.
Depreciation 15.00%
Interest on Investment 6.75%
Taxes, Insurance & Storage 3.75%
Repair & Maintenance 19.40%
Salvage Value 20.00%
Tire Repair cost 16.00%
Equipment under load 30% of the operating time
Carrier under load 10% of the operating time
Use 50-min productive hour
Depreciation 15.00%
Interest on Investment 6.75%
Taxes,Insurance & Storage 3.75%
Repair & Maintenance 19.40%
Salvage Value 20.00%
Tire Repair cost 16.00%
Equipment under load 30% of the operating time
Carrier under load 10% of the operating time
Use 50-min productive hour
Depreciation 15.00%
Interest on Investment 6.75%
Taxes, Insurance & Storage 3.75%
Repair & Maintenance 37.00%
Salvage Value 20.00%
Tire Repair cost 16.00%
Equipment under load 30% of the operating time
Carrier under load 10% of the operating time
Use 50-min productive hour
LABOUR COST
Plant Capacity (cum/day) 120
Buy, rent or lease decision is the way of procurement of construction equipment. This is a
financial investment decision and also a matter of concern to how to use the equipment to make
out of it as much as possible. Second aspect is the replacement of the construction equipment. It
is very necessary to do the accurate calculation for finding the economic life of the equipment.
This is necessary to find because one might replace equipment before the actual replacement life
of the equipment and lose the benefits on the other hand if equipment is used beyond the
economic life owner of the equipment will lose money as well as time. Loss will occur due to the
increased maintenance cost, repair charges and reduction in the productivity which will lead to
an increase in the time for completing the work.
Equipment Life: Determining the economic useful life for a given piece of equipment.
Replacement Analysis: Analytical tools to compare alternatives to replace a piece of
equipment that has reached the end of its useful life.
Replacement Equipment Selection: Methods to make a logical decision as to which
alternative furnishes the most promising solution to the equipment replacement decision.
Equipment life can be mathematically defined in three different ways: physical life, profit life
and economic life. All three aspects are defined and calculated when considering equipment life
because they furnish three important means to approach replacement analysis and ultimately to
Physical Life
Physical life is the age at which machine is worn out and is no longer reliably produce. At this
point, it usually be abandoned or scrapped. As construction equipment ages, maintenance and
operating costs increases.
Profit Life
Profit life is the life over which the equipment can earn the profit. Retention beyond that point
will create an operating loss. This essentially is the point where machine seemingly spends more
time in the workshop than on the project site.
Economic Life
Economic life equates to the time period that maximizes profits over equipment’s life. It is prime
objective to maximize production and minimize the operating cost.
the accelerated cost of the equipment minus the depreciation occurred in that year. Considering
the salvage is 10% of the initial cost of the equipment.
EXCAVATOR 3CX
END OF YEAR REPLACEMENT COST BOOK VALUE LOSS ON REPLACEMENT CUMULATIVE USE (h) CUMULATIVE COST /Hour
0 Rs 2,200,000.00 Rs 2,200,000.00 Rs - 0
1 Rs 2,310,000.00 Rs 1,767,500.00 Rs 542,500.00 2000 Rs 271.25
2 Rs 2,420,000.00 Rs 1,396,785.71 Rs 1,023,214.29 4000 Rs 255.80
3 Rs 2,530,000.00 Rs 1,087,857.14 Rs 1,442,142.86 6000 Rs 240.36
4 Rs 2,640,000.00 Rs 840,714.29 Rs 1,799,285.71 8000 Rs 224.91
5 Rs 2,750,000.00 Rs 655,357.14 Rs 2,094,642.86 10000 Rs 209.46
6 Rs 2,860,000.00 Rs 531,785.71 Rs 2,328,214.29 12000 Rs 194.02
7 Rs 2,970,000.00 Rs 470,000.00 Rs 2,500,000.00 14000 Rs 178.57
EQUIPMENT CRANE
SPECIFICATIONS Tower Crane
Power KW (HP) 150 (201)
Cost Rs 8,000,000.00
Useful Life Hrs 8,000
END OF YEAR REPLACEMENT COST BOOK VALUE LOSS ON REPLACEMENT CUMULATIVE USE (h) CUMULATIVE COST /Hour
0 Rs 8,000,000.00 Rs 8,000,000.00 Rs - 0
1 Rs 8,400,000.00 Rs 6,400,000.00 Rs 2,000,000.00 1000 Rs 2,000.00
2 Rs 8,800,000.00 Rs 5,000,000.00 Rs 3,800,000.00 2000 Rs 1,900.00
3 Rs 9,200,000.00 Rs 3,800,000.00 Rs 5,400,000.00 3000 Rs 1,800.00
4 Rs 9,600,000.00 Rs 2,800,000.00 Rs 6,800,000.00 4000 Rs 1,700.00
5 Rs 10,000,000.00 Rs 2,000,000.00 Rs 8,000,000.00 5000 Rs 1,600.00
6 Rs 10,400,000.00 Rs 1,400,000.00 Rs 9,000,000.00 6000 Rs 1,500.00
7 Rs 10,800,000.00 Rs 1,000,000.00 Rs 9,800,000.00 7000 Rs 1,400.00
8 Rs 11,200,000.00 Rs 800,000.00 Rs 10,400,000.00 8000 Rs 1,300.00
BATCHING PLANT
END OF YEAR REPLACEMENT COST BOOK VALUE LOSS ON REPLACEMENT CUMULATIVE USE (h) CUMULATIVE COST /Hour
0 Rs 2,000,000.00 Rs 2,000,000.00 Rs - 0
1 Rs 2,100,000.00 Rs 1,810,526.32 Rs 289,473.68 1000 Rs 289.47
2 Rs 2,200,000.00 Rs 1,631,578.95 Rs 568,421.05 2000 Rs 284.21
3 Rs 2,300,000.00 Rs 1,463,157.89 Rs 836,842.11 3000 Rs 278.95
4 Rs 2,400,000.00 Rs 1,305,263.16 Rs 1,094,736.84 4000 Rs 273.68
5 Rs 2,500,000.00 Rs 1,157,894.74 Rs 1,342,105.26 5000 Rs 268.42
6 Rs 2,600,000.00 Rs 1,021,052.63 Rs 1,578,947.37 6000 Rs 263.16
7 Rs 2,700,000.00 Rs 894,736.84 Rs 1,805,263.16 7000 Rs 257.89
8 Rs 2,800,000.00 Rs 778,947.37 Rs 2,021,052.63 8000 Rs 252.63
9 Rs 2,900,000.00 Rs 673,684.21 Rs 2,226,315.79 9000 Rs 247.37
10 Rs 3,000,000.00 Rs 578,947.37 Rs 2,421,052.63 10000 Rs 242.11
11 Rs 3,100,000.00 Rs 494,736.84 Rs 2,605,263.16 11000 Rs 236.84
12 Rs 3,200,000.00 Rs 421,052.63 Rs 2,778,947.37 12000 Rs 231.58
13 Rs 3,300,000.00 Rs 357,894.74 Rs 2,942,105.26 13000 Rs 226.32
14 Rs 3,400,000.00 Rs 305,263.16 Rs 3,094,736.84 14000 Rs 221.05
15 Rs 3,500,000.00 Rs 263,157.89 Rs 3,236,842.11 15000 Rs 215.79
16 Rs 3,600,000.00 Rs 231,578.95 Rs 3,368,421.05 16000 Rs 210.53
17 Rs 3,700,000.00 Rs 210,526.32 Rs 3,489,473.68 17000 Rs 205.26
18 Rs 3,800,000.00 Rs 200,000.00 Rs 3,600,000.00 18000 Rs 200.00
DUMPER
END OF YEAR REPLACEMENT COST BOOK VALUE LOSS ON REPLACEMENT CUMULATIVE USE (h) CUMULATIVE COST /Hour
0 Rs 1,200,000.00 Rs 1,200,000.00 Rs - 0
1 Rs 1,260,000.00 Rs 1,010,000.00 Rs 250,000.00 2000 Rs 125.00
2 Rs 1,320,000.00 Rs 858,000.00 Rs 462,000.00 4000 Rs 115.50
3 Rs 1,380,000.00 Rs 736,400.00 Rs 643,600.00 6000 Rs 107.27
4 Rs 1,440,000.00 Rs 639,120.00 Rs 800,880.00 8000 Rs 100.11
5 Rs 1,500,000.00 Rs 561,296.00 Rs 938,704.00 10000 Rs 93.87
6 Rs 1,560,000.00 Rs 499,036.80 Rs 1,060,963.20 12000 Rs 88.41
7 Rs 1,620,000.00 Rs 449,229.44 Rs 1,170,770.56 14000 Rs 83.63
8 Rs 1,680,000.00 Rs 409,383.55 Rs 1,270,616.45 16000 Rs 79.41
9 Rs 1,740,000.00 Rs 377,506.84 Rs 1,362,493.16 18000 Rs 75.69
10 Rs 1,800,000.00 Rs 352,005.47 Rs 1,447,994.53 20000 Rs 72.40
II INFLATION
Like every product, equipment replacement costs are affected by economic and industrial
inflation. Economic inflation is defined as the loss in buying power of the national currency, and
industrial inflation is the change in construction costs due to long- and short-term fluctuations in
commodity pricing. While the inflation should always be considered in equipment replacement
decision making, its effect can be ignored because inflation will equally affect rest of the
alternatives.
EXCAVATOR 3CX
YEAR INVESTMENT START DEPRECIATION INVESTMENT END OF YEAR INVESTMENT COST CUMULATIVE INVESTMENT CUMULATIVE USE (h) CUMULATIVE COST /Hour
1 Rs 2,200,000.00 Rs 432,500.00 Rs 1,767,500.00 Rs 330,000.00 Rs 330,000.00 2000 Rs 165.00
2 Rs 1,767,500.00 Rs 370,714.29 Rs 1,396,785.71 Rs 265,125.00 Rs 595,125.00 4000 Rs 148.78
3 Rs 1,396,785.71 Rs 308,928.57 Rs 1,087,857.14 Rs 209,517.86 Rs 804,642.86 6000 Rs 134.11
4 Rs 1,087,857.14 Rs 247,142.86 Rs 840,714.29 Rs 163,178.57 Rs 967,821.43 8000 Rs 120.98
5 Rs 840,714.29 Rs 185,357.14 Rs 655,357.14 Rs 126,107.14 Rs 1,093,928.57 10000 Rs 109.39
6 Rs 655,357.14 Rs 123,571.43 Rs 531,785.71 Rs 98,303.57 Rs 1,192,232.14 12000 Rs 99.35
7 Rs 531,785.71 Rs 61,785.71 Rs 470,000.00 Rs 79,767.86 Rs 1,272,000.00 14000 Rs 90.86
Investment cost for the tower crane is assumed to increase by 15% of the initial cost every year.
Cumulative investment is divided by the cumulative use of the equipment to get cumulative
investment per hour.
BATCHING PLANT
YEAR INVESTMENT START DEPRECIATION INVESTMENT END INVESTMENT CUMULATIVE CUMULATIVE CUMULATIVE
OF YEAR COST INVESTMENT USE (h) COST /Hour
1 Rs 2,000,000.00 Rs 189,473.68 Rs 1,810,526.32 Rs 300,000.00 Rs 300,000.00 1000 Rs 300.00
2 Rs 1,810,526.32 Rs 178,947.37 Rs 1,631,578.95 Rs 271,578.95 Rs 571,578.95 2000 Rs 285.79
3 Rs 1,631,578.95 Rs 168,421.05 Rs 1,463,157.89 Rs 244,736.84 Rs 816,315.79 3000 Rs 272.11
4 Rs 1,463,157.89 Rs 157,894.74 Rs 1,305,263.16 Rs 219,473.68 Rs 1,035,789.47 4000 Rs 258.95
5 Rs 1,305,263.16 Rs 147,368.42 Rs 1,157,894.74 Rs 195,789.47 Rs 1,231,578.95 5000 Rs 246.32
6 Rs 1,157,894.74 Rs 136,842.11 Rs 1,021,052.63 Rs 173,684.21 Rs 1,405,263.16 6000 Rs 234.21
7 Rs 1,021,052.63 Rs 126,315.79 Rs 894,736.84 Rs 153,157.89 Rs 1,558,421.05 7000 Rs 222.63
8 Rs 894,736.84 Rs 115,789.47 Rs 778,947.37 Rs 134,210.53 Rs 1,692,631.58 8000 Rs 211.58
9 Rs 778,947.37 Rs 105,263.16 Rs 673,684.21 Rs 116,842.11 Rs 1,809,473.68 9000 Rs 201.05
10 Rs 673,684.21 Rs 94,736.84 Rs 578,947.37 Rs 67,368.42 Rs 1,876,842.11 10000 Rs 187.68
11 Rs 578,947.37 Rs 84,210.53 Rs 494,736.84 Rs 57,894.74 Rs 1,934,736.84 11000 Rs 175.89
12 Rs 494,736.84 Rs 73,684.21 Rs 421,052.63 Rs 49,473.68 Rs 1,984,210.53 12000 Rs 165.35
13 Rs 421,052.63 Rs 63,157.89 Rs 357,894.74 Rs 42,105.26 Rs 2,026,315.79 13000 Rs 155.87
14 Rs 357,894.74 Rs 52,631.58 Rs 305,263.16 Rs 35,789.47 Rs 2,062,105.26 14000 Rs 147.29
15 Rs 305,263.16 Rs 42,105.26 Rs 263,157.89 Rs 30,526.32 Rs 2,092,631.58 15000 Rs 139.51
16 Rs 263,157.89 Rs 31,578.95 Rs 231,578.95 Rs 26,315.79 Rs 2,118,947.37 16000 Rs 132.43
17 Rs 231,578.95 Rs 21,052.63 Rs 210,526.32 Rs 23,157.89 Rs 2,142,105.26 17000 Rs 126.01
18 Rs 210,526.32 Rs 10,526.32 Rs 200,000.00 Rs 21,052.63 Rs 2,163,157.89 18000 Rs 120.18
DUMPER
END OF LOSS ON CUMULATIVE USE CUMULATIVE COST
REPLACEMENT COST BOOK VALUE
YEAR REPLACEMENT (h) /Hour
Rs
0 Rs 1,200,000.00 Rs 1,200,000.00 0
-
1 Rs 1,260,000.00 Rs 1,010,000.00 Rs 250,000.00 2000 Rs 125.00
Type of equipment
Age of equipment
Operating Conditions
Daily care by the operator
Maintenance department
Frequency and level of maintenance
crane perform also, on the policies of the company. Here example of the tower crane is
explained.
Table 5-10 TOWER CRANE: Maintenance and Repair Cost
BATCHING PLANT
ANNUAL MAINTENANCE AND CUMULATIVE COST
CUMULATIVE COST PER
YEAR REPAIR COST CUMULATIVE USE (h)
HOUR
1 Rs 10,526.32 Rs 10,526.32 1000 Rs 10.53
2 Rs 21,052.63 Rs 31,578.95 2000 Rs 15.79
3 Rs 31,578.95 Rs 63,157.89 3000 Rs 21.05
4 Rs 42,105.26 Rs 105,263.16 4000 Rs 26.32
5 Rs 52,631.58 Rs 157,894.74 5000 Rs 31.58
6 Rs 63,157.89 Rs 221,052.63 6000 Rs 36.84
7 Rs 73,684.21 Rs 294,736.84 7000 Rs 42.11
8 Rs 84,210.53 Rs 378,947.37 8000 Rs 47.37
9 Rs 94,736.84 Rs 473,684.21 9000 Rs 52.63
10 Rs 105,263.16 Rs 578,947.37 10000 Rs 57.89
11 Rs 115,789.47 Rs 694,736.84 11000 Rs 63.16
12 Rs 126,315.79 Rs 821,052.63 12000 Rs 68.42
13 Rs 136,842.11 Rs 957,894.74 13000 Rs 73.68
14 Rs 147,368.42 Rs 1,105,263.16 14000 Rs 78.95
15 Rs 157,894.74 Rs 1,263,157.89 15000 Rs 84.21
DUMPER
ANNUAL MAINTENANCE AND CUMULATIVE COST
REPAIR COST CUMULATIVE COST PER
YEAR CUMULATIVE USE (h)
HOUR
V DOWNTIME
Downtime is the time when equipment does not work due to repairs or mechanical adjustments.
Downtime tends to increase as equipment usage increases. Availability, the portion of the time
equipment is actually available for the production or is in actual production, is the opposite of
downtime. For example, if the equipment’s downtime is 10% then its availability is 90%. The
downtime cost includes the ownership cost, operating cost, operator cost, and productivity loss
caused by the loss of equipment availability. In availability affects the productivity and increases
the cost of the operation.
OPERATING DOWNTIME COST DOWNTIME COST CUMULATIVE CUMULATIVE CUMULATIVE PRODUCTIVITY PRODUCTIVITY ADJUSTED
YEAR DOWNTIME
COST PER HOUR PER YEAR DOWNTIME COST USE (h) COST PER HOUR FACTOR CUMULATIVE COST / HOUR
1 3% Rs 703.82 Rs 21.11 Rs 42,229.20 Rs 42,229.20 2000 Rs 21.11 1 Rs 21.11
2 6% Rs 703.82 Rs 42.23 Rs 84,458.40 Rs 126,687.60 4000 Rs 31.67 0.99 Rs 31.36
3 9% Rs 703.82 Rs 63.34 Rs 126,687.60 Rs 253,375.20 6000 Rs 42.23 0.98 Rs 41.38
4 11% Rs 703.82 Rs 77.42 Rs 154,840.40 Rs 408,215.60 8000 Rs 51.03 0.96 Rs 48.99
5 13% Rs 703.82 Rs 91.50 Rs 182,993.20 Rs 591,208.80 10000 Rs 59.12 0.95 Rs 56.16
6 15% Rs 703.82 Rs 105.57 Rs 211,146.00 Rs 802,354.80 12000 Rs 66.86 0.94 Rs 62.85
7 17% Rs 703.82 Rs 119.65 Rs 239,298.80 Rs 1,041,653.60 14000 Rs 74.40 0.93 Rs 69.20
BATCHING PLANT
OPERATING DOWNTIME COST DOWNTIME COST CUMULATIVE CUMULATIVE CUMULATIVE PRODUCTIVITY PRODUCTIVITY ADJUSTED
YEAR DOWNTIME
COST PER HOUR PER YEAR DOWNTIME COST USE (h) COST PER HOUR FACTOR CUMULATIVE COST / HOUR
1 3% Rs 388.52 Rs 11.66 Rs 11,655.60 Rs 11,655.60 1000 Rs 11.66 1 Rs 11.66
2 5% Rs 388.52 Rs 19.43 Rs 19,426.00 Rs 31,081.60 2000 Rs 15.54 0.99 Rs 15.39
3 6% Rs 388.52 Rs 23.31 Rs 23,311.20 Rs 54,392.80 3000 Rs 18.13 0.98 Rs 17.77
4 8% Rs 388.52 Rs 31.08 Rs 31,081.60 Rs 85,474.40 4000 Rs 21.37 0.96 Rs 20.51
5 9% Rs 388.52 Rs 34.97 Rs 34,966.80 Rs 120,441.20 5000 Rs 24.09 0.95 Rs 22.88
6 10% Rs 388.52 Rs 38.85 Rs 38,852.00 Rs 159,293.20 6000 Rs 26.55 0.94 Rs 24.96
7 11% Rs 388.52 Rs 42.74 Rs 42,737.20 Rs 202,030.40 7000 Rs 28.86 0.93 Rs 26.84
8 12% Rs 388.52 Rs 46.62 Rs 46,622.40 Rs 248,652.80 8000 Rs 31.08 0.92 Rs 28.60
9 14% Rs 388.52 Rs 54.39 Rs 54,392.80 Rs 303,045.60 9000 Rs 33.67 0.9 Rs 30.30
10 16% Rs 388.52 Rs 62.16 Rs 62,163.20 Rs 365,208.80 10000 Rs 36.52 0.89 Rs 32.50
11 18% Rs 388.52 Rs 69.93 Rs 69,933.60 Rs 435,142.40 11000 Rs 39.56 0.88 Rs 34.81
12 20% Rs 388.52 Rs 77.70 Rs 77,704.00 Rs 512,846.40 12000 Rs 42.74 0.87 Rs 37.18
13 23% Rs 388.52 Rs 89.36 Rs 89,359.60 Rs 602,206.00 13000 Rs 46.32 0.86 Rs 39.84
14 24% Rs 388.52 Rs 93.24 Rs 93,244.80 Rs 695,450.80 14000 Rs 49.68 0.85 Rs 42.22
15 25% Rs 388.52 Rs 97.13 Rs 97,130.00 Rs 792,580.80 15000 Rs 52.84 0.84 Rs 44.38
16 26% Rs 388.52 Rs 101.02 Rs 101,015.20 Rs 893,596.00 16000 Rs 55.85 0.81 Rs 45.24
17 32% Rs 388.52 Rs 124.33 Rs 124,326.40 Rs 1,017,922.40 17000 Rs 59.88 0.79 Rs 47.30
18 34% Rs 388.52 Rs 132.10 Rs 132,096.80 Rs 1,150,019.20 18000 Rs 63.89 0.77 Rs 49.20
DUMPER
OPERATING DOWNTIME COST DOWNTIME COST CUMULATIVE CUMULATIVE CUMULATIVE PRODUCTIVITY PRODUCTIVITY ADJUSTED
YEAR DOWNTIME
COST PER HOUR PER YEAR DOWNTIME COST USE (h) COST PER HOUR FACTOR CUMULATIVE COST / HOUR
1 2% Rs 658.73 Rs 13.17 Rs 26,349.20 Rs 26,349.20 2000 Rs 13.17 1 Rs 13.17
2 3% Rs 658.73 Rs 19.76 Rs 39,523.80 Rs 65,873.00 4000 Rs 16.47 0.98 Rs 16.14
3 4% Rs 658.73 Rs 26.35 Rs 52,698.40 Rs 118,571.40 6000 Rs 19.76 0.96 Rs 18.97
4 5% Rs 658.73 Rs 32.94 Rs 65,873.00 Rs 184,444.40 8000 Rs 23.06 0.93 Rs 21.44
5 6% Rs 658.73 Rs 39.52 Rs 79,047.60 Rs 263,492.00 10000 Rs 26.35 0.89 Rs 23.45
6 7% Rs 658.73 Rs 46.11 Rs 92,222.20 Rs 355,714.20 12000 Rs 29.64 0.87 Rs 25.79
7 8% Rs 658.73 Rs 52.70 Rs 105,396.80 Rs 461,111.00 14000 Rs 32.94 0.85 Rs 28.00
8 9% Rs 658.73 Rs 59.29 Rs 118,571.40 Rs 579,682.40 16000 Rs 36.23 0.81 Rs 29.35
9 10% Rs 658.73 Rs 65.87 Rs 131,746.00 Rs 711,428.40 18000 Rs 39.52 0.79 Rs 31.22
10 11% Rs 658.73 Rs 72.46 Rs 144,920.60 Rs 856,349.00 20000 Rs 42.82 0.77 Rs 32.97
VI OBSOLESCENSE
Obsolescence is the reduction in value and marketability due to the competition between newer
and more productive models. Obsolescence can be subdivided into two types: technological and
market preference. Technological obsolescence can be measured in terms of productivity. Over
the short term, technological obsolescence has typically occurred at a fairly constant. Market rate
preference obsolescence occurs as a function of the customers taste.
EXCAVATOR: OBSOLESCENSE
Obsolescence cost for excavator cost is determined by multiplying the obsolescence factor to the
hourly operating cost of the excavator. Hourly obsolescence cost is equal to the cumulative
obsolescence cost divided by cumulative use of the excavator.
Table 5-17 EXCAVATOR: Obsolescence
EXCAVATOR 3CX
OBSOLESCENSE OBSOLESCENCE COST OBSOLESCENCE COST CUMULATIVE CUMULATIVE COST
YEAR OPERATING COST CUMULATIVE USE (h)
FACTOR PER HOUR PER YEAR DOWNTIME COST PER HOUR
1 0 Rs 703.82 Rs - Rs - Rs - 2000 Rs -
2 0.06 Rs 703.82 Rs 42.23 Rs 84,458.40 Rs 84,458.40 4000 Rs 21.11
3 0.11 Rs 703.82 Rs 77.42 Rs 154,840.40 Rs 239,298.80 6000 Rs 39.88
4 0.15 Rs 703.82 Rs 105.57 Rs 211,146.00 Rs 450,444.80 8000 Rs 56.31
5 0.2 Rs 703.82 Rs 140.76 Rs 281,528.00 Rs 731,972.80 10000 Rs 73.20
6 0.26 Rs 703.82 Rs 182.99 Rs 365,986.40 Rs 1,097,959.20 12000 Rs 91.50
7 0.32 Rs 703.82 Rs 225.22 Rs 450,444.80 Rs 1,548,404.00 14000 Rs 110.60
BATCHING PLANT
OBSOLESCENSE OBSOLESCENCE COST OBSOLESCENCE COST CUMULATIVE CUMULATIVE COST
YEAR OPERATING COST CUMULATIVE USE (h)
FACTOR PER HOUR PER YEAR DOWNTIME COST PER HOUR
1 0 Rs 388.52 Rs - Rs - Rs - 1000 Rs -
2 0.06 Rs 388.52 Rs 23.31 Rs 23,311.20 Rs 23,311.20 2000 Rs 11.66
3 0.09 Rs 388.52 Rs 34.97 Rs 34,966.80 Rs 58,278.00 3000 Rs 19.43
4 0.11 Rs 388.52 Rs 42.74 Rs 42,737.20 Rs 101,015.20 4000 Rs 25.25
5 0.15 Rs 388.52 Rs 58.28 Rs 58,278.00 Rs 159,293.20 5000 Rs 31.86
6 0.2 Rs 388.52 Rs 77.70 Rs 77,704.00 Rs 236,997.20 6000 Rs 39.50
7 0.26 Rs 388.52 Rs 101.02 Rs 101,015.20 Rs 338,012.40 7000 Rs 48.29
8 0.32 Rs 388.52 Rs 124.33 Rs 124,326.40 Rs 462,338.80 8000 Rs 57.79
9 0.34 Rs 388.52 Rs 132.10 Rs 132,096.80 Rs 594,435.60 9000 Rs 66.05
10 0.35 Rs 388.52 Rs 135.98 Rs 135,982.00 Rs 730,417.60 10000 Rs 73.04
11 0.36 Rs 388.52 Rs 139.87 Rs 139,867.20 Rs 870,284.80 11000 Rs 79.12
12 0.38 Rs 388.52 Rs 147.64 Rs 147,637.60 Rs 1,017,922.40 12000 Rs 84.83
13 0.41 Rs 388.52 Rs 159.29 Rs 159,293.20 Rs 1,177,215.60 13000 Rs 90.56
14 0.42 Rs 388.52 Rs 163.18 Rs 163,178.40 Rs 1,340,394.00 14000 Rs 95.74
15 0.45 Rs 388.52 Rs 174.83 Rs 174,834.00 Rs 1,515,228.00 15000 Rs 101.02
16 0.46 Rs 388.52 Rs 178.72 Rs 178,719.20 Rs 1,693,947.20 16000 Rs 105.87
17 0.48 Rs 388.52 Rs 186.49 Rs 186,489.60 Rs 1,880,436.80 17000 Rs 110.61
18 0.52 Rs 388.52 Rs 202.03 Rs 202,030.40 Rs 2,082,467.20 18000 Rs 115.69
DUMPER
OBSOLESCENSE OBSOLESCENCE COST OBSOLESCENCE COST CUMULATIVE CUMULATIVE COST
YEAR OPERATING COST CUMULATIVE USE (h)
FACTOR PER HOUR PER YEAR DOWNTIME COST PER HOUR
1 0 Rs 658.73 Rs - Rs - Rs - 2000 Rs -
2 0.04 Rs 658.73 Rs 26.35 Rs 52,698.40 Rs 52,698.40 4000 Rs 13.17
3 0.05 Rs 658.73 Rs 32.94 Rs 65,873.00 Rs 118,571.40 6000 Rs 19.76
4 0.08 Rs 658.73 Rs 52.70 Rs 105,396.80 Rs 223,968.20 8000 Rs 28.00
5 0.1 Rs 658.73 Rs 65.87 Rs 131,746.00 Rs 355,714.20 10000 Rs 35.57
6 0.11 Rs 658.73 Rs 72.46 Rs 144,920.60 Rs 500,634.80 12000 Rs 41.72
7 0.13 Rs 658.73 Rs 85.63 Rs 171,269.80 Rs 671,904.60 14000 Rs 47.99
8 0.14 Rs 658.73 Rs 92.22 Rs 184,444.40 Rs 856,349.00 16000 Rs 53.52
9 0.15 Rs 658.73 Rs 98.81 Rs 197,619.00 Rs 1,053,968.00 18000 Rs 58.55
10 0.16 Rs 658.73 Rs 105.40 Rs 210,793.60 Rs 1,264,761.60 20000 Rs 63.24
EXCAVATOR 3CX
YEAR DEPRECIATION & REPLACEMENT INVESTMENT MAINTENANCE & REPAIRS DOWNTIME OBSOLESCENSE TOTAL
1 Rs 271.25 Rs 165.00 Rs 35.36 Rs 21.11 Rs - Rs 492.72
2 Rs 255.80 Rs 148.78 Rs 36.06 Rs 31.36 Rs 21.11 Rs 493.12
3 Rs 240.36 Rs 134.11 Rs 36.77 Rs 41.38 Rs 39.88 Rs 492.50
4 Rs 224.91 Rs 120.98 Rs 37.48 Rs 48.99 Rs 56.31 Rs 488.66
5 Rs 209.46 Rs 109.39 Rs 38.19 Rs 56.16 Rs 73.20 Rs 486.40
6 Rs 194.02 Rs 99.35 Rs 38.89 Rs 62.85 Rs 91.50 Rs 486.61
7 Rs 178.57 Rs 90.86 Rs 39.60 Rs 69.20 Rs 110.60 Rs 488.82
Rs600.00
Rs500.00
DEPRECIATION &
REPLACEMENT
Rs400.00 INVESTMENT
TOTAL COST
DOWNTIME
Rs200.00
OBSOLESCENSE
Rs100.00
TOTAL
Rs-
0 2 4 6 8
LIFE OF EQUIPMENT (YEARS)
YEAR DEPRECIATION & REPLACEMENT INVESTMENT MAINTENANCE & REPAIRS DOWNTIME OBSOLESCENSE TOTAL
Rs3,500.00
Rs3,000.00
Rs2,500.00
DEPRECIATION & REPLACEMENT
TOTAL COST
Rs2,000.00 INVESTMENT
MAINTENANCE & REPAIRS
Rs1,500.00
DOWNTIME
Rs1,000.00 OBSOLESCENSE
Rs500.00 TOTAL
Rs-
0 2 4 6 8 10
LIFE OF EQUIPMENT (YEAR)
BATCHING PLANT
YEAR DEPRECIATION & REPLACEMENT INVESTMENT MAINTENANCE & REPAIRS DOWNTIME OBSOLESCENSE TOTAL
1 Rs 289.47 Rs 300.00 Rs 10.53 Rs 11.66 Rs - Rs 611.66
2 Rs 284.21 Rs 285.79 Rs 15.79 Rs 15.39 Rs 11.66 Rs 612.83
3 Rs 278.95 Rs 272.11 Rs 21.05 Rs 17.77 Rs 19.43 Rs 609.30
4 Rs 273.68 Rs 258.95 Rs 26.32 Rs 20.51 Rs 25.25 Rs 604.72
5 Rs 268.42 Rs 246.32 Rs 31.58 Rs 22.88 Rs 31.86 Rs 601.06
6 Rs 263.16 Rs 234.21 Rs 36.84 Rs 24.96 Rs 39.50 Rs 598.67
7 Rs 257.89 Rs 222.63 Rs 42.11 Rs 26.84 Rs 48.29 Rs 597.76
8 Rs 252.63 Rs 211.58 Rs 47.37 Rs 28.60 Rs 57.79 Rs 597.97
9 Rs 247.37 Rs 201.05 Rs 52.63 Rs 30.30 Rs 66.05 Rs 597.41
10 Rs 242.11 Rs 187.68 Rs 57.89 Rs 32.50 Rs 73.04 Rs 593.23
11 Rs 236.84 Rs 175.89 Rs 63.16 Rs 34.81 Rs 79.12 Rs 589.81
12 Rs 231.58 Rs 165.35 Rs 68.42 Rs 37.18 Rs 84.83 Rs 587.36
13 Rs 226.32 Rs 155.87 Rs 73.68 Rs 39.84 Rs 90.56 Rs 586.26
14 Rs 221.05 Rs 147.29 Rs 78.95 Rs 42.22 Rs 95.74 Rs 585.26
15 Rs 215.79 Rs 139.51 Rs 84.21 Rs 44.38 Rs 101.02 Rs 584.91
16 Rs 210.53 Rs 132.43 Rs 89.47 Rs 45.24 Rs 105.87 Rs 583.54
17 Rs 205.26 Rs 126.01 Rs 94.74 Rs 47.30 Rs 110.61 Rs 583.92
18 Rs 200.00 Rs 120.18 Rs 100.00 Rs 49.20 Rs 115.69 Rs 585.06
Rs700.00
Rs600.00
Rs400.00
MAINTENANCE & REPAIRS
Rs300.00 DOWNTIME
OBSOLESCENSE
Rs200.00
TOTAL
Rs100.00
Rs-
0 5 10 15 20
LIFE OF EQUIPMENT (YEAR )
DUMPER
YEAR DEPRECIATION & REPLACEMENT INVESTMENT MAINTENANCE & REPAIRS DOWNTIME OBSOLESCENSE TOTAL
1 Rs 125.00 Rs 120.00 Rs 7.55 Rs 13.17 Rs - Rs 265.72
2 Rs 115.50 Rs 110.50 Rs 11.32 Rs 16.14 Rs 13.17 Rs 266.63
3 Rs 107.27 Rs 102.27 Rs 15.09 Rs 18.97 Rs 19.76 Rs 263.36
4 Rs 100.11 Rs 95.11 Rs 18.86 Rs 21.44 Rs 28.00 Rs 263.52
5 Rs 93.87 Rs 85.67 Rs 22.64 Rs 23.45 Rs 35.57 Rs 261.20
6 Rs 88.41 Rs 76.07 Rs 26.41 Rs 25.79 Rs 41.72 Rs 258.40
7 Rs 83.63 Rs 68.77 Rs 30.18 Rs 28.00 Rs 47.99 Rs 258.57
8 Rs 79.41 Rs 62.98 Rs 33.95 Rs 29.35 Rs 53.52 Rs 259.22
9 Rs 75.69 Rs 58.26 Rs 37.73 Rs 31.22 Rs 58.55 Rs 261.46
10 Rs 72.40 Rs 54.32 Rs 41.50 Rs 32.97 Rs 63.24 Rs 264.43
Rs300.00
Rs250.00
Rs200.00
DEPRECIATION & REPLACEMENT
TOTAL COST
INVESTMENT
Rs150.00
MAINTENANCE & REPAIRS
DOWNTIME
Rs100.00
OBSOLESCENSE
Rs50.00 TOTAL
Rs-
0 2 4 6 8 10 12
LIFE OF EQUIPMENT (YEAR)
Considering a situation in which the a contractor who does only earthwork owns excavator JCB-
3D of cost Rs 22,00,000/- . This excavator is one year old annual operation and maintenance cost
is Rs 70,000/- for first year and increases by Rs 3000/- every year. The rental charges for the
JCB 3D is Rs 750/- which is operated for 2000 hours per year and hence revenue generated
every year is Rs 15,00,000/- . The revenue generated will not remain same and will decrease at
the rate of Rs 1,50,000/- per year thereafter. The contractor came to know about new backhoe
loader JCB 3X sitemaster of cost Rs 24,00,000/- of same size with additional bucket capacity
options. The operation and maintenance cost of the new loader is Rs 70,000/- for the first year
and increases by Rs 2500/- per year. This construction firm uses double declining balance
method for calculating the depreciation.
5.3.1 BUY
Buying or financing the equipment is most sensible if the equipment is essential to construction
company core fleet and expected to provide service life for long time. If the sufficient funds are
available to the company for purchase or for down payment large enough to reduce the monthly
finance payments to an acceptable level then firm should buy the equipment. Owning equipment
can provide long term tax benefits- principally from deduction of interest expense and
depreciation of equipment. By deducting the equipment’s purchases price on tax return each
year, some recovery of the equipment price can be made. This situation is applicable if the
construction firm does not have real estate or office equipment that provide additional
opportunity depreciation deductions.
5.3.2 RENTAL
The rental of a machine is a short-term alternative to direct equipment ownership. With a rental,
a company can pick the machine that is exactly suited for the job at hand. This is particularly
advantageous if the job is of short duration or if the company does not foresee a continuing need
for the particular type of machine in question. Rentals are very beneficial to a company in such
situations, even though the rental charges are higher than normal direct ownership expense. The
advantage lies in the fact that direct ownership costing assumes a continuing need and utilization
of the machine. If that assumption is not valid, a rental should be considered. Another important
point to consider is the fact that with a rental, the company loses the tax depreciation shield of
machine ownership but gains a tax deduction because rental payments are treated as an expense.
It must be remembered that rental companies only have a limited number of machines and,
during the peak work season, all types are not always available. Furthermore, many specialized
or custom machines cannot be rented. Firms many times use rentals as a way to test a machine
prior to a purchase decision. A rental provides the opportunity for a company to operate a
specific make or model machine under actual project conditions. The profitability of the
machine, based on the company's normal operating procedures, can then be evaluated before a
major capital expenditure is approved to purchase the machine.
The general practice of the industry is to price rental rates for equipment on either a daily (8 hr),
weekly (40 hr), or monthly (176 hr) basis. In the case of larger pieces of equipment, rentals may
be available only on a monthly basis. Cost per hour usually is less for a longer-term rental (Le.,
the monthly rate figured on a per hour basis would be less than the daily rate on an hourly basis).
Responsibility for repair cost is stated in the rental contract. Normally, on tractor-type
equipment, the renter is responsible for all repairs. If it is a pneumatic-tired machine (on rubber),
the renting company will measure tread wear and charge the renter for tire wear. In the case of
cranes and shovels, the renting company usually bears the cost of normal wear and tear. The user
must provide servicing of the machine while it is being used. The renter is almost always
responsible for fuel and lubrication expenses. Industry practice is that rentals are payable in
advance. The renting company will require that the user furnish certificates of insurance before
the machine is shipped to the job site. Equipment cost is very sensitive to changes in use hours.
Fluctuations in maintenance expenses or purchase price barely affect cost per hour. But a
decrease in use hours per year can make the difference between cost-effective machine
ownership and renting. The basic cost considerations that need to be examined when considering
a possible rental can be illustrated by a simple set of circumstances.
5.3.3 LEASE
A lease is a long-term agreement for the use of an asset. It provides an alternative to direct
ownership, During the lease term, the leasing company (lessor) always owns the equipment and
the user (lessee) pays the owner to use the equipment. The lessor must retain ownership rights
for the contract to be considered a true lease by the Internal Revenue Service, The lessor will
receive lease payments in return for providing the machine, The lease payments do not have to
be uniform across the lease period. The payments can be structured in the agreement to best fit
the situation of the lessee or the lessor. In the lessee's case, cash flow at the beginning may be
low, so the lessee wants payments that are initially low, Because of tax considerations, the lessor
may agree to such a payment schedule. Lease contracts are binding legal documents, and most
equipment leases are non-cancellable by either party. A lease pays for the use of a machine
during the most reliable years of a machine's service life. Sometimes the advantage of a lease is
that the lessor provides the equipment management and servicing. This frees the contractor from
hiring mechanics and service personnel and enables the company to concentrate on the task of
building,
Long-term, when used in reference to lease agreements, is a period of time that is long relative to
the life of the machine in question. An agreement that is for a very short period of time, as
measured against the expected machine life, is a rental. A conventional-true-Iease will have one
of three different endof-lease options:
As in the case of a rental, a lessee loses the tax depreciation shield of machine ownership but
gains a tax deduction because lease payments are treated as an expense. The most important
factor contributing to a decision to lease is reduced cost. Under specific conditions, the actual
cost of a leased machine can be less than the ownership cost of a purchased machine. This is
caused by the different tax treatments for owning and leasing an asset. An equipment user must
make a careful examination of the cash flows associated with each option to determine which
results in the lowest total cost.
A commonly cited advantage of leasing is that working capital is notified up in equipment. This
statement is only partly true. It is true that when a company borrows funds to purchase a
machine, the lender normally requires that the company establish an equity position in the
machine, a down payment, Additionally, the costs of delivery and initial servicing are not
included in the loan and must be paid by the new owner. Corporate funds are therefore tied up in
these up-front costs of a purchase, Leasing does not require these cash outflows and is often
considered as 100% financing. However, most leases require an advance lease payment. Some
even require security deposits and charge other up-front costs.
Still another argument is that because borrowed funds are not used, credit capacity is preserved.
Leasing is often referred to as off-balance-sheet financing. A lease is considered an operating
expense, not a liability, as is the case with a bank loan. With an operating lease (used when the
lessee does not ultimately want to purchase the equipment), leased assets are expensed.
Therefore, such assets do not appear on the balance sheet. Standards of accounting, however,
require disclosure of lease obligations. It is hard to believe that lenders would be so naive as to
not consider all of a company's fixed obligations, including both loans and leases. But the off-
balance-sheet lease typically will not hurt bonding capacity, which is important to a company's
ability to bid work.
Before entering into a contract with a construction company, most owners require that the
company post a bond guaranteeing that it will complete the project. A third-party surety
company secures this bond. The surety closely examines the construction company's financial
position before issuing the bond. Based on the financial strength of the construction company,
the surety typically restricts the total volume of worle that the construction company can have
under contract at anyone time. This restriction is known as bonding capacity. It is the total dollar
value of work under contract that a surety company will guarantee for a construction company.
Owners should make a careful examination of the advantages of a lease situation. The cash
flows, which should be considered when evaluating the cost of a lease, include
These costs all occur at different points in time, so present-value computations must be made
before the costs can be summed. The total present value of the lease option should be compared
to the minimum ownership costs, as determined by a time-value replacement analysis. In most
lease agreements, the lessee is responsible for maintenance. If, for the lease in question,
maintenance expense is the same as for the case of direct ownership, then the maintenance
expense factor can be dropped from the analysis. A leased machine would exhibit the same aging
and resulting reduced availability as a purchased machine.
Analyze the cost of renting, leasing, and purchasing an item of construction equipment under the
conditions described. Evaluate total net after-tax cash flow and its present value.
Cost Rs 2,400,000.00
Rate of Interest 20%
Salavage Value Rs 240,000.00
Useful Life (year) 10
Use Rate (hr/ year) 1000
Total Rs(3,942,464.08)
Loan Details
Downpayment Rs480,000.00
Duration (yearly) 5
DEPRECIATION EXCAVATOR
Lease Details
PURCHASE COST
LEASE COST
RENT COST
Rs4,500,000.00
Rs4,000,000.00
Rs3,500,000.00
ANNUAL COST
Rs3,000,000.00
Rs2,500,000.00
Rs2,000,000.00
Rs1,500,000.00
Rs1,000,000.00
Rs500,000.00
Rs-
1 2 3 4 5 6 7 8 9 10
RENT COST Rs713,209 Rs713,209 Rs713,209 Rs713,209 Rs713,209 Rs713,209 Rs713,209 Rs713,209 Rs713,209 Rs713,209
LEASE COST Rs4,726,7 Rs2,248,1 Rs1,424,5 Rs1,014,7 Rs577,789 Rs- Rs- Rs- Rs- Rs-
PURCHASE COST Rs902,457 Rs410,551 Rs248,315 Rs168,446 Rs121,483 Rs25,290. Rs16,431. Rs10,209. Rs5,723.5 Rs2,434.8
Figure 5-6 Comparison of different options Buying, Renting or Owning for Acquisition of Equipment
It can be seen from the graph that the renting cost will remain same throughout the life of the
equipment. Purchase cost is higher in first year but decreases in the beginning of the second year.
Leasing option is too much costly cannot be considered. It would be preferred to purchase the
equipment
1. Estimate the total quantity of the work to be done (such as cft, cyd, cum of earthwork or
concrete placement). For earthwork use bank volume.
2. From construction schedule find probable working time available (such as working hours
or working days to complete the quantity found in step 1).
3. From the step 1 and 2 above, find average rate of production per unit of time (such as X
cum per hour) required to complete the work by dividing quantity found in step 1 by time
as estimated in step 2.
4. Select a suitable size, and find its cycle time and from this cycle time the number of
cycles performed/ hour. Then ideal output of the machine per hour = machine capacity X
no. of cycles per hour. Consult production tables of machine, if available.
5. Scale down the ideal production as calculated in step 4 to probable value which would be
actually realized by using the suitable efficiency factors.
6. Find the average number of machine required to achieve the target production by
dividing the quantity found in step 3 by quantity found in step 5.
7. Add 10to 20% additional capacity for peaking requirement.
8. Add stand by capacity of 10 to 30% to serve during break downs, contingencies etc.
The cost of production as a result of using the specific size and number of machines as calculated
by above procedure should then be estimated. A second trial should be made using alternative
size of machine, and cost of production resulting from its use should be calculated. Several trials
can be made if it’s necessary. A comparison of the unit production rates of the different
machines for which trials have been made would reveal the economically advantageous size to
be used.
Mr. Frank A. Nirik of USA after a close study of these factors grouped them into a matrix as
shown below
Two shift working operations are considered to be economical and should be employed wherever
possible. Three shift working results in frequent breakdowns and low availability, thus
necessitating more standbys and increasing the cost. Single shift should be used where works are
located in difficult terrain, subjected to vagaries of nature or scattered over long distance.
Schedule working hours with 200 working days available in a year should be as follows under
average working conditions:
Applying the job and management factor for good management and good working condition at
site to be 0.75
Applying the job and management factor for good management and good working condition at
site to be 0.75
Bulldozers
Front-end loaders
Motor graders
Scrapers
Trucks
Time required by excavator to load the dumper (assuming the bucket fill capacity factor to be
0.85)
Number of cycles required to load the truck = 8.5/ (1.0X 0.85)= 10 cycles per truck load
= 10 cycles X 1X0.85
9.33
Number of TATA dumper truck of capacity 8.5 m³ supported by JCB 3D= 3.33 = 2.8 ℎ𝑎𝑢𝑙𝑒𝑟𝑠
Batching Plant
Concrete Pump
7.1 INTRODUCTION
In this chapter
7.2.3 EXCAVATION
Quantity of the earthwork = 109998.164 m³
Excavator = 4 JCB-3D
= 8 months
Applying the job and management factor for good management and good working condition at
site to be 0.75
JCB 3D equipped with 1.0 m³ of back hoe bucket and cycle time of 3 per minute is to be used to
load a dumper of TATA of capacity 8.5 m³ cycle time 7 per hour and travel time 6 minute.
Time required by excavator to load the dumper (assuming the bucket fill capacity factor to be
0.85)
Number of cycles required to load the truck = 8.5/ (1.0X 0.85)= 10 cycles per truck load
= 10 cycles X 1X0.85
9.33
Number of TATA dumper truck of capacity 8.5 m³ supported by JCB 3D= 3.33 = 2.8 ℎ𝑎𝑢𝑙𝑒𝑟𝑠