Escolar Documentos
Profissional Documentos
Cultura Documentos
Table 1. Separating the 39 Processes Belonging to the Nine Knowledge Areas by Planning Processes and Other Processes
be identified for each planning process. For example, the major based on the learning curve theory, which has proved ongoing
product of the scope definition process is the work breakdown improvement as a function of the number of repetitions
structure (WBS). Table 2 lists the major products for all plan- (Griffith, 1996; Snead & Harrell, 1994; Yiming & Hao, 2000;
ning processes. Watson & Behnke, 1991).
Participants in the study were project managers and others
The Study who are involved in project management activities. The 282
A field study was conducted to evaluate the extent of the pro- participants came from different project management work-
ject manager’s involvement in the planning processes and to shops administered as part of internal or external training sem-
evaluate their quality. A major problem in designing this study inars. The portion of the questionnaire that they were asked to
was to establish a way to evaluate the extent to which planning complete, which served as the database for this study, appears
processes were used in projects and their quality level. For this in Appendix 1.
purpose, the following assumption was made: The quality of a The following scale was used for evaluating the intensity of
process is a function of the frequency with which it is used to use of the different products:
obtain the major product of the process. This assumption is ■ 5 = The product is always obtained;
■ 4 = The product is obtained quite frequently; ■ Medium quality areas, to which cost, quality, and procure-
■ 3 = The product is obtained frequently; ment belong. The score for this group is around 3;
■ 2 = The product is seldom obtained; ■ Poor quality areas, to which risk and communications
■ 1 = The product is hardly ever obtained; belong. The score of both is around 2.3.
■ 9 = The product is irrelevant to the projects I am involved in;
■ 0 = I do not know whether the product is being obtained. Analysis and Discussion
Table 3 summarizes the results. As may be seen from Table Assuming that for successful completion of a project, all
3, the quality of the processes ranges from a low of 2.0 for processes in the nine knowledge areas should be high quali-
qualitative risk analysis up to 4.2 for activity duration estimat- ty, we should discuss ways to improve the poor performance
ing. In other words, qualitative risk analysis is hardly practiced. areas. Performance in a specific area is a function of the pro-
There is a high correlation among the quality of products ject manager’s know-how of that area, the know-how of
belonging to the same knowledge area; that is, they are either other professionals, such as functional managers, who are
low or high. For example, the quality of all risk processes is involved in the specific process, and with the project manag-
below 2.9, whereas the quality of all the scope processes is er’s ability to affect the area and its attendant processes.
above 3.5. The quality of each knowledge area is calculated by In general, functional managers are accountable for the
the average quality of the processes belonging to it, as present- proper execution of the specific work packages assigned to
ed in Table 3, and charted in descending order in Figure 1. them, whereas the project manager is responsible for integra-
The three groups of knowledge areas identified in Figure 1 are: tion and infrastructure-related work packages and activities. For
■ High quality areas, to which integration, scope, time, and example, a project manager is heavily involved with the process
human resources belong. The score for this group is around 4; of establishing the WBS for the whole project and is directly
Table 3. Quality of Major Planning Processes Within the Different PMBOK® Guide Knowledge Areas
accountable for it. However, a process such as quantitative risk within the same organization, much care is taken to include all
analysis, which must be done separately for each individual relevant expectations in the contract, to ensure that the external
work package, requires heavy involvement of the functional suppliers follows all requirements. The combination of employ-
manager and those of his employees who are responsible for ees working on a work package without the relevant know-how
executing the work package (assuming a matrix organization). in relevant risk management processes, and a project manager
Therefore, to perform the process properly, all the involved par- without the ability to endow them with this knowledge makes
ties should possess know-how of risk management methods. it unrealistic to expect effective implementation of project man-
Process know-how means being familiar with the required agement processes. In other words, if a certain process is to be
inputs, the tools and techniques used, and the desired outputs carried out in an appropriate manner, the people involved in the
of the process. If this is not the case, then risk management or process need the relevant know-how.
any other relevant processes can’t be effectively handled on a Table 4 divides the planning processes according to the
work package level or on the integrated level. A project man- individual who expends most effort in properly executing a
ager functioning in a matrix environment gets work packages process (the project manager or the functional manager), keep-
done by “contracting out” to internal suppliers, who are the ing in mind that the project manager is held responsible for all
functional managers in the organization, and purchasing other processes. In general, in a matrix organization, a functional
work packages from external sources via procurement process- manager is responsible for carrying single work package relat-
es. Because procurement requires the signing of formal docu- ed activities, whereas a project manager deals with work pack-
ments, as compared to working with functional managers ages that are integrated in nature. For example, a functional
4.0
3.9
4 3.8
3.7
3 2.9
Planning Quality
2.3 2.3
0
s
ns
n
st
ity
sk
e
t
en
ce
ag
io
op
Co
tio
al
Ri
at
em
ur
Ti
er
Sc
Qu
ica
gr
so
Av
ur
te
un
Re
oc
In
m
Pr
an
m
Co
m
Hu
Knowledge Areas
manager carries the major responsibility for activity definition, The situation is not the same for the communications
whereas the project manager has to integrate all project activi- area, because its only planning process—communications
ties into activity sequencing, and so on. planning—is an integrated work package with which the pro-
Keep in mind that a project manager is regarded as a func- ject manager is the most heavily involved. Although other
tional manager when he or she works on the professional work professionals, such as functional mangers, must be involved
packages that fall within his or her direct area of accountabili- in the communications planning process, the project manag-
ty. For example, the project manager is directly accountable for er should lead the overall effort and have a strong command
the scope-definition process, the major output of which is the of the relevant tools and techniques. Therefore, lack of know-
WBS. However, the project manager will not be able to execute how on the part of the functional manager is not the main
this process out without the cooperation and the know-how of reason for poor performance in this area. The explanation has
functional managers. The same holds true for all processes, to be sought elsewhere.
regardless of the manager who is directly accountable. According to the PMBOK® Guide, “Communications
Further, the two areas that belong to the “poor quality” group, planning determines the information and communications
that is, risk management and communications, displayed poor needs for the stakeholders: Who needs what information,
results. Because risk management is part of the PMBOK® Guide when they will need it, and how it will be given to them”
and, therefore, also part of the Project Management Professional (p.119). This area is probably the most difficult for the
(PMP®) examination, one may assume that project managers are project manager to plan, because it requires getting present
familiar with it. However, functional managers do not have any and future information needs from all the stakeholders. Very
formal risk management training, and one may assume that they few formal tools and techniques are available to the project
suffer from lack of the requisite know-how with regard to risk manager for supporting the communications area. PMBOK®
management processes. It is therefore not surprising that func- Guide offers only one unstructured tool, namely, stakeholder
tional managers are of little help in performing risk management analysis. The lack of proper and easily accessible tools cou-
processes. The project manager is thus left alone to struggle with pled with the difficult task of identifying future information
it, with limited success according to the results of this study and needs of stakeholders makes communication a very difficult
others (Ibbs & Kwak, 2000; Mullaly, 1997). process to plan.
Table 4. Mapping of the 21 PMBOK® Guide Planning Processes According to the Individual (Project or Functional
Manager) Who Performs Most of the Activities Required to Execute the Planning Process
The areas that belong to the middle quality group are cost, tional manager also should get intensive but adapted project
quality, and procurement. From Table 4, we can identify management training. The agent for such a fundamental
the manager who needs most of the know-how required change in the organizational culture can’t be the project man-
to properly execute each of the processes. While the project ager alone. It is essential that it be sponsored at a high level
manager leads the process in the quality area and the func- of the organization and even treated as a project by itself.
tional manager in the procurement area, both are involved in
the cost area. Therefore, the key to success in these areas is References
different tailor-made training modules for the project and the Cleland, D.I. (1994). Project management: Strategic design
functional manager. and implementation. New York: McGraw-Hill.
Fleming, Q.W., & Koppelman, J.M. (1994). The earned
Conclusion value concept: Back to the basics. PM Network, 8 (11), 27–29.
As the person who is fully accountable for the success of the Griffith, T.L. (1996). Negotiating successful technology
project as a whole, the project manager is responsible for implementation: A motivation perspective. Journal of
overcoming the difficulties encountered in guaranteeing Engineering & Technology Management, 13 (1), 29–53.
that all planning processes are properly executed. To resolve Ibbs, C.W., & Kwak, Y.H. (2000). Assessing project man-
the problems, the project manager should identify the agement maturity. Project Management Journal, 31, 32–43.
events that have a negative impact on the successful com- Kimmons, R.L. (1990). Project management basics.
pletion of the project and develop explicit mitigating plans Houston, TX: Kimmons-Asaro Group Ltd. Inc.
to accommodate them. Mullaly, M. (1998). 1997 Canadian project management
In some areas, such as communications and quality, the baseline study. Proceedings of the Project Management
project management community should develop better tools Institute’s 29th Annual Symposium, Long Beach, CA. Newtown
and techniques to support the project manager’s efforts. In Square, PA: PMI, 375–384.
other areas, such as risk and cost, more emphasis should be PMI Standards Committee. (2000). A guide to the project
placed on the training of functional managers in the use of management body of knowledge. Newtown Square, PA: Project
the relevant tools and techniques. In other words, the func- Management Institute.