Monthly Stakeholder Meeting Presentation

October 21, 2019


This PowerPoint presentation was prepared by the Florida Department of
Transportation (FDOT) staff and has been made available to the public as part of
public records access. Any dissemination of this presentation by anyone or entity
other than FDOT staff is not official. Any questions can be sent to FDOT-
D6PIO@dot.state.fl.us.

This presentation may not be altered.

2
CURRENT DESIGN STATUS

OVERALL DESIGN STATUS

• Roadway - 90% • Structures – 45% • Maintenance of Traffic (MOT) – 55%

MAJOR DESIGN SUBMITTALS TO DATE:

• Roadway plans for I-95 north segment (segment 2A) complete


• Roadway plans for I-95 south segment (segment 2B) 90% complete
• Roadway plans for I-395 complete
• Surface street plans complete
• Phase I TCP plans complete for I-95, I-395 and SR 836
• Phase 2 and 3 TCP plans for I-95, 90% complete
• 60% signature bridge plans
• TCP generic plans and detour routes complete

3
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES

* This schedule does not reflect days added to the contract for
holidays, weather days or special events

• Construction of new drainage, median concrete barrier wall and pavement replacement on I-95 between
NW 17 Street and NW 29 Street (Ongoing)

• Ongoing full NB and SB I-95 closures for overhead sign structure including two DMS

4
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES

* This schedule does not reflect days added to the contract for
holidays, weather days or special events

5
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES

* This schedule does not reflect days added to the contract for
holidays, weather days or special events

6
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES

* This schedule does not reflect days added to the contract for
holidays, weather days or special events

7
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES

* This schedule does not reflect days added to the contract for
holidays, weather days or special events

Foundation work on northbound I-95 bridge approaching ramp to I-195 (Ongoing)


8
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES

Ongoing work on eastbound SR 836 from NW 17 Avenue to the Miami River and from NW 12
Avenue to I-95 for bridge widening.
9
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES

10
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES

11
ONGOING LANE THREE MONTH LOOK
CLOSURES AHEAD

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

ANTICIPATED NIGHTTIME LANE CLOSURES ON SR 836 CORRIDOR:


• Lane closures along eastbound and westbound SR 836
• NW 17 Avenue under SR 836
• Eastbound SR 836 ramp to NW 17 Avenue
• Eastbound SR 836 ramp to northbound I-95
• Arterial Roads under SR 836

12
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES

1 • Implemented a traffic shift


on westbound I-395 from 2
NE 1 Avenue to I-95.
Traffic has been shifted to
the left

2 • Ongoing demolition of
outside I-395 on-ramp that
was closed as part of the
NE 12 Street Closure 1

13
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES

* This schedule does not reflect days added to the contract for
holidays, weather days or special events

14
UPCOMING & ONGOING I-395 BRIDGE WORK
CONSTRUCTION ACTIVITIES
3 1. Demolition of median separator between the
eastbound I-395 mainline and local road
connector (Ongoing)

Concrete closure pour between the


eastbound I-395 mainline and local road
2 connector (Ongoing)

2.Removal of median separator between the


4 eastbound I-395 mainline and the westbound
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
mainline (November)

3. Begin construction on westbound outside,


local road lanes. Foundations will begin at
NE 2 Avenue and move towards the west
(October/November)
1
4. Begin construction on eastbound, local road
lanes. Foundations will begin at NW 1
Avenue and move towards the west
(November)

15
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES

* This schedule does not reflect days added to the contract for
holidays, weather days or special events

16
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES

* This schedule does not reflect days added to the contract for
holidays, weather days or special events

Auger Cast Pile Load Testing Scheduled - Ongoing


17
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES

* This schedule does not reflect days added to the contract for
holidays, weather days or special events

18
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES

* This schedule does not reflect days added to the contract for
holidays, weather days or special events

19
UPCOMING CONSTRUCTION THREE MONTH LOOK
ACTIVITIES AHEAD

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

Bridge foundation work for westbound Signature Bridge (December)


20
ONGOING LANE THREE MONTH LOOK
CLOSURES AHEAD

SR 836 UPCOMING CONSTRUCTION ACTIVITIES


ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR:
• Southbound I-95 and northbound I-95 ramps to eastbound I-395
• Lane closures along I-395 mainline and connector road
• Lane closures along Biscayne Boulevard
• Arterial roads under I-395
• Shift traffic on eastbound I-395 mainline to the right from I-95 to
approximately NW 1 Avenue to allow for the removal of the eastbound
and westbound traffic separator (late October)

21
TRAFFIC MANAGEMENT SYSTEM Smart Work Zone Management
System (SWZMS) - The project is
N implementing a SWZMS that will
utilize Intelligent Transportation
System (ITS) devices such as traffic
cameras, data collection devices
and portable message signs to:

• Provide drivers with real-time


travel information;

• Encourage motorists to take


alternate routes;

• Clear incidents more quickly,


thereby reducing secondary
incidents; and

• Make work zones safer for


highway workers and motorists.

22
COMMUNITY OUTREACH

PROJECT WEBSITE

• www.i-395miami.com

• Sign-up for project alerts/updates


Lane closure information
Upcoming construction activities
Presentations

• Calendar of events

OUTREACH OFFICE IN THE OVERTOWN COMMUNITY

• 1035 NW 3 Avenue, Miami, Florida 33136

STAKEHOLDER MEETINGS
• Ongoing individual stakeholder meetings and presentations
• Next stakeholder meeting – November 18, 2019

23
THANK YOU!
www.i-395miami.com