2
CURRENT DESIGN STATUS
3
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
• Construction of new drainage, median concrete barrier wall and pavement replacement on I-95 between
NW 17 Street and NW 29 Street (Ongoing)
• Ongoing full NB and SB I-95 closures for overhead sign structure including two DMS
4
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
5
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
6
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
7
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
Ongoing work on eastbound SR 836 from NW 17 Avenue to the Miami River and from NW 12
Avenue to I-95 for bridge widening.
9
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
10
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
11
ONGOING LANE THREE MONTH LOOK
CLOSURES AHEAD
12
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
2 • Ongoing demolition of
outside I-395 on-ramp that
was closed as part of the
NE 12 Street Closure 1
13
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
14
UPCOMING & ONGOING I-395 BRIDGE WORK
CONSTRUCTION ACTIVITIES
3 1. Demolition of median separator between the
eastbound I-395 mainline and local road
connector (Ongoing)
15
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
16
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
18
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
19
UPCOMING CONSTRUCTION THREE MONTH LOOK
ACTIVITIES AHEAD
21
TRAFFIC MANAGEMENT SYSTEM Smart Work Zone Management
System (SWZMS) - The project is
N implementing a SWZMS that will
utilize Intelligent Transportation
System (ITS) devices such as traffic
cameras, data collection devices
and portable message signs to:
22
COMMUNITY OUTREACH
PROJECT WEBSITE
• www.i-395miami.com
• Calendar of events
STAKEHOLDER MEETINGS
• Ongoing individual stakeholder meetings and presentations
• Next stakeholder meeting – November 18, 2019
23