VACCUM CIRCUIT
BREAKER
CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P2 of 10
Document No. Solution Centre India
SE-SCI-CON-S-62 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/06/2013
1.0 Introduction
The following test procedure has been prepared for the testing and commissioning of the Vaccum Circuit
Breaker at …………………………………………… project India.
All Testing and Commissioning documentation must be produced in accordance with all relevant codes of
practice of India and international standard.
The following test instrumentation & tools will be required to undertake the tests detailed within this
procedure:
A Megger (5KV)
B CRM Kit
C Timing Test Kit
D Gas Leakage Detector Test Kit
E Vaccum Bottle
CIRCUIT BREAKER
5.1.2 Procedure:
CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P5 of 10
Document No. Solution Centre India
SE-SCI-CON-S-62 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/06/2013
IR test of breaker is done using 5KV Megger. Meggering is generally done under specified conditions
namely, when CB is closed and when CB is opened. During these conditions, Megger value is noted
down for all the phases. The values thus measured are preferably in giga ohms.
The breaker closed condition R pole to Earth and Y pole to Earth and B pole to Earth.
The breaker open condition R pole to Earth and Y pole to Earth and B pole to Earth
The breaker open condition R-R pole and Y-Y pole and B-B pole. The above values are noted and
recorded on site register / test report. The value should be in Meg Ohms.
CIRCUIT
BREAKER
5.2.2 Procedure:
Contact resistance of the breaker R ph, Y ph and B ph pole is seen by injecting 100A dc current with
the help of CRM Kit and thus the corresponding resistance is displayed. The value thus shown should
ideally be less than 100 micro ohms.
Stationary & Moving Contacts are built from materials that provide good resistance from arcing.
However if contacts are not maintained on a regular basis, resistance due to repeated arcing builds
up resulting in the contacts disability to carry currents
5.3.2 Procedure:
It is necessary to time each breaker, in order to have its functional signature. Incorrect operation can
have disastrous consequences on the equipment or the substation personnel. Not to mention the out of
service losses of revenue and the repair costs. Timing tests are done first in the factory during the routine
tests and after installation, during the commissioning tests. They have to be done periodically in order to
validate the good working order and reliability of the breaker. Timing tests are also a powerful tool for
troubleshooting faulty breakers.
Data interpretation
Data analysis
CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P8 of 10
Document No. Solution Centre India
SE-SCI-CON-S-62 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/06/2013
5.4.1 Procedure:
The gas is filled in the gas leakage detector test kit and it is kept for 24hrs under observation. Then
after 24 hours the pipe joints are checked for any detection of leakage of gas
If the pressure drop is more than 1KV then the gas leakage detector detects it
5.5.1 Procedure:
High Voltage Test up to 18 KV is applied to the apparatus. If the apparatus trips then it is concluded
that the Vaccum Bottle is faulty & must be replaced
CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P9 of 10
Document No. Solution Centre India
SE-SCI-CON-S-62 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/06/2013
8.0 RECORDS