Você está na página 1de 6

This reading describes the concepts, tools, and techniques used to determine

strategies for managing positive and negative risks, as well as planning and
implementing response actions.

The objective of the Plan Risk Responses process is to THE INPUTS


select the strategies and actions that should be imple-
mented to manage prioritized risks in the most efficient To start this Plan Responses process we need seve-
manner. ral documents that contain information, which we will
have to analyze.
The main benefit of this process is that it appropriately
allocates resources and introduces agreed-upon acti- The Risk Matrix, which records risks according to their
vities into the Project management plan and other Pro- prioritization, and states which risks have to be included
ject documents, to improve opportunities and reduce in the Response Plan.
threats to the Project’s objectives . 2

The Risk Management Plan, which records when and


The objective of the Implement Responses process is how to carry out the Plan Responses process and who
that response actions for managing risks be executed should carry it out. It also includes, among other elements,
as planned. a template for documenting the Response Plan for prio-
ritized risks.
Figure 1 – Structure of the Plan Responses Process
The Project Schedule and Budget, which we will have to
The main elements that make up the Plan Risk Respon- analyze to correctly include planned risk response ac-
ses process are as follows: tions, so that they can be executed like the rest of the Pro-
ject’s activities.

The Responsibility Assignment Matrix, in which there is


information related to the use of human resources. It is
important to remember that, as is the case with all other
activities, implementing risk management actions requi-
res capital, time, and human resources.

Created in-house, based on A Guide to the Project


Mana­gement Body of Knowledge (PMBOK® Guide) /
Project Management Institute, Sixth Edition.

1 PMBOK Guide, Sixth Edition.


2 Ibid.

1
THE TOOLS AND TECHNIQUES organization has capacities that the executing agen-
cy does not have, it may be prudent to contractually
How do we analyze and transform input information transfer responsibility for the execution of a Project
to achieve the objective of this process? product or component to that organization, along with
its corresponding risks. We may also want to transfer
Response Strategies for Threats and Opportunities: A an activity’s risks to a supplier or contractor through
response strategy is a course of action that enables the use of fixed-price contracts.
the Project Team to manage a risk’s potential impact
on the Project’s expected results. There are five respon- D. Accept. It involves not acting preventively on the
se strategies for positive risks and five for negative risks. risk but waiting to see if it materializes. This strategy is
These strategies are described below and summarized adopted when none of the other strategies are appli-
in Figure 2. cable or the cost of undertaking them is greater than
their potential benefits. Acceptance can be active or
1. Threat (Negative Risk) Response Strategies: passive. Passive acceptance does not require any ac-
tion, except documenting and justifying the strategy
A. Avoid. It consists of acting to eliminate the threat or and letting the Project Team address the risks as they
to protect the Project from its impact. It usually invol- arise. Active acceptance requires establishing a Con-
ves changing Project planning in order to complete- tingency Reserve that includes the amount of (human
ly eliminate the threat, isolate Project objectives from and financial) resources necessary to address the risk
the risk’s impact, or even change the objective that is if it materializes. Although accepted risks do not have
threatened. Examples include extending the schedu- a response action, they must be recorded in the Risk
le, changing the intervention strategy, or reducing the Matrix so they can be monitored throughout the life of
scope. Some risks that arise in the early stages of the the Project.
Project can be avoided by adjusting the Project’s de-
sign, clarifying its requirements, obtaining information, E. Escalate. It involves assigning the threat so that it is
improving communications, or acquiring experience. managed at a higher level, be it at the Program, Port-
folio, or organizational level. It is advisable to escalate a
B. Mitigate. It involves adopting actions to reduce a risk when its management at a higher level will gene-
risk’s probability and/or impact to a tolerable level. Miti- rate economies of scale, when it affects more than one
gation strategies can focus on reducing the probability project, or when the risk could impact an objective out-
that the risk will materialize (e.g., adopting a less com- side the scope of the Project, e.g., a Portfolio objective.
plex process, training staff, or selecting a more reliable
provider) or they can be aimed at minimizing the risk’s 2. Opportunity (Positive Risk) Response Strategies:
impact (e.g., adding resources to a component or ex-
tending the Project’s schedule). A. Exploit. It seeks to eliminate the uncertainty asso-
ciated with the materialization of a positive risk (an
C. Transfer. It seeks to shift a risk’s impact, and the res- opportunity), ensuring that the opportunity is definitely
ponsibility to act on it if it materializes, to a third party. realized. Some examples of direct exploitation respon-
Transferring a risk simply assigns the responsibility for ses involve including new planning activities to take
its management to a third party, but it does not elimi- advantage of the executing agency’s strengths, as-
nate or mitigate the risk. Transferring responsibility for a signing the most talented resources to the Project to
risk is more effective when dealing with exposure to fi- reduce the time to completion, or using new technolo-
nancial risks. Transferring a risk almost always involves gies or technological improvements to reduce the cost
paying a risk premium to the party that undertakes it. and time required to achieve the Project’s objectives.
Transfer tools can be quite diverse and include, among
others, the use of insurance, performance guaran- B. Enhance. It consists of adopting actions to increa-
tees, warranties, guarantee certificates, etc. Contracts se the probability and/or positive impacts of a risk
or agreements can be used to transfer responsibility (opportunity). Enhancing strategies seek to facilitate
for specific risks to a third party. For example, when an or strengthen the cause of the opportunity to increase

2
the probability that it will materialize (e.g., adding re- Figure 2 - Risk Response Strategies

sources to an activity to finish earlier), or they may be


directed at increasing the Project’s susceptibility to the
opportunity (e.g., extending the Project’s schedule to
take advantage of more favorable weather conditions
that can reduce costs).

C. Share. It involves assigning ownership of an oppor-


tunity to a better trained third party so as to seize the
positive impacts for the benefit of the Project. Some
examples of risk sharing actions include establishing
temporary joint ventures or partnerships for the ex-
press purpose of taking advantage of an opportunity.

D. Accept. It consists of being willing to take advantage


of a positive risk if it occurs, but without actively seeking
it. Although accepted risks do not have a response ac-
tion, they must be recorded in the Risk Matrix so they
can be monitored throughout the life of the Project.

E. Escalate. It involves assigning the opportunity so


that it is managed at a higher level, be it at the Pro-
gram, Portfolio, or organizational level. It is advisable to
escalate a positive risk when its management at a hi-
gher level can generate benefits beyond the Project at Created in-house, based on A Guide to the Project
lower cost or when it impacts an objective outside the Mana­gement Body of Knowledge (PMBOK® Guide) /
Project Management Institute, Sixth Edition.
scope of the Project.

Cost-Benefit Analysis: Response actions must be adap-


ted to the importance of the risk, i.e., there must be a
balance between the cost of developing the response
and the impact that the risk would have if it were to
materialize. If the risk’s impact has been quantified in
monetary terms, the different response actions iden-
tified can be analyzed by dividing the impact by the
cost of implementing the response action. The higher
the result, the more efficient the response.

Alternatives Analysis: It allows for establishing the most


appropriate response by comparing the characteris-
tics and requirements of the identified response op-
tions. Once the response strategy for a particular risk
has been identified, we must plan the concrete actions
to be implemented so as to achieve the objective of
the selected strategy, be it avoiding, mitigating, trans-
ferring, escalating, or actively accepting the risk. Risk
responses must be realistic within the context of the
Project and they must be agreed upon among all the
parties involved.

3
THE OUTPUTS EXAMPLE

The main output of this process, after analyzing the input Risk: If the equipment is delivered to local vendors at
information using the techniques introduced, is the Res- their current locations, vendors may not want to move to

ponse Plan, a document that updates the Risk Register the newly built dock, which would prevent meeting the goal
of having xx (number) local entrepreneurs established on
(which includes all identified risks) and the Risk Matrix
the dock by Year 4.
(which includes all analyzed and prioritized risks) with ad-
ditional information.
Action: 1) Prioritizing the start of the construction of the
docks based on the areas where the greatest investments
Only those risks that have been prioritized will appear in
in equipment will be made. 2) Delaying equipment acqui-
the Response Plan; those that have not been prioritized sition.
will be recorded for subsequent monitoring. If, throu-
ghout the life of the Project, nonprioritized risks chan- Trigger: 1) When the results of the mapping of invest-
ge risk levels, they will be prioritized and included in the ments in equipment are available. 2) At the beginning of
Response Plan. the construction works of the new dock.

In addition to the strategy and response action for The Plan Risk Responses process generates a second
each prioritized risk, the Response Plan must include, at Output: Updated Project Planning Documents. Respon-
least, the following elements:3 se actions may require that the following documents,
among others, be adjusted:
Party Responsible for the Response: A person, unit, or
team (also called risk action owner or response owner) A. Adjustments to the Execution Mechanism. Respon-
that will ensure the correct and timely implementation se actions to risks that arise from the execution system
of the agreed-upon action. may require changes to the Project execution mecha-
nism. For example, consultations with beneficiaries may
Allocation of financial and/or physical resources be added as part of the Project intervention approval
necessary for implementing the response, and their scheme or a formal coordination space among the
source of funding. organizations involved may be created by consensus.
Changes that are generated in the risk response pro-
Response Trigger: Some actions are short term and, cess will be included in different Project documents
due to their immediacy, they can be associated with according to the stage of the Project at that moment.
a specific date or known event, such as, for example,
a Project milestone or product. Other actions, on the B. Adjustments to the Results Matrix (RM). Respon-
other hand, are designed to be implemented when se actions to risks that significantly affect the achie-
certain events or conditions occur. These events or vement of the Project’s expected results may require
conditions are related the effectiveness of the respon- changes to Project products or results. This is the case,
se. Most risk responses will meet their objectives to a for example, of institutional strengthening activities
greater or lesser extent depending on when they are that may require an additional component or product
implemented. Executing a response action when the to be included as part of the scope of the Project, if they
appropriate conditions have not been met can be ex- are numerous and important enough to the Project’s
cessively costly and/or delayed and, therefore, not im- results. The risk analysis and the responses identified
pact the risk. to manage them can also involve reviewing indicators,
baselines, goals, or sources of verification.

3 See the Response Plan template.

4
C. Adjustments to the Pluriannual Execution Plan (PEP).
Response actions to risks associated with a specific
product of the operation are considered activities of
said product and, as such, must be part of the Project’s
PEP. The Project Team must take into account the ti-
ming and cost of these actions within the framework
of product activities, to ensure that the risk is mana-
ged on time and the product is delivered correctly and
in a timely manner. Response actions may also invol-
ve changes in the execution logic, which may require
reviewing the network schedule, adding floats into the
budget or schedule of activities or chains, or on the
contrary, compressing the schedule4.

D. Adjustments to the Procurement Plan. Like any ac-


tivity in a project, a risk response may require the pur-
chase of products or services, which will have to be
managed following the same procurement policies
and modalities as other Project purchases. It is also
very common for risk responses to involve actions re-
lated to procurement management, either through the
inclusion of contract clauses or through contract ad-
ministration.

CONCLUSIONS

A project’s risks are identified, recorded, and analyzed


to be managed. Risk management involves establi-
shing a strategic objective (planning the response
strategy) and implementing the actions necessary to
achieve it (response actions).

Like any action in a project, it requires the allocation


of resources and assignment of responsible parties.
Moreover, the risk response must be cost-effective, so
the Alternatives Analysis and the comparison between
the cost of the response and the benefit that it would
generate on the risk’s level is part of a good respon-
se planning exercise. Identifying the appropriate con-
ditions for implementing the response (the trigger)
is also essential to obtain the greatest benefit at the
lowest cost.

4 For references on the concepts of budget and schedule management, please consult the Glossary.

5
MAIN TERMS AND DEFINITIONS Risk Avoidance. A risk response strategy whereby the
IN THIS READING project team acts to eliminate the threat or protect the
project from its impact.

Acquisition. Obtaining human and material resour- Risk Mitigation. A risk response strategy whereby the
ces necessary to perform project activities. Acquisition project team acts to decrease the probability of occu-
implies a cost of resources and is not necessarily finan- rrence or impact of a threat.
cial.
Risk Transference. A risk response strategy whereby
Alternatives Analysis. A technique used to evalua- the project team shifts the impact of a threat to a third
te identified options in order to select the options or party, together with ownership of the response.
approaches to use to execute and perform the work of
the project. Trigger Condition. An event or situation that indicates
that a risk is about to occur.
Contingency. An event or occurrence that could
affect the execution of the project that may be accoun-
*Reading created in-house, based on A Guide to the Project
ted for with a reserve.
Management Body of Knowledge (PMBOK® Guide) / Project
Management Institute, Sixth Edition.
Contingency Reserve. The budget allocated in the
cost or performance measurement baseline for identi-
fied risks that are accepted and for which contingent or
mitigation responses are developed.

Corrective Action. An intentional activity that realig-


ns the performance of the project work with the project
management plan.

Cost-Benefit Analysis. A financial analysis tool used


to determine the benefits provided by a project against
its costs.

Plan Risk Responses. The process of developing op-


tions and actions to improve opportunities and reduce
threats to project objectives.

Preventive Action. An intentional activity that ensures


the future performance of the project work is aligned
with the project management plan.

Reserve. A provision in the project management plan


to mitigate cost and/or schedule risk. It is often used with
a modifier (e.g., management reserve, contingency re-
serve) to provide further detail on what types of risk are
meant to be mitigated.

Risk Acceptance. A risk response strategy whereby


the project team decides to acknowledge the risk and
not take any action unless the risk occurs.

Você também pode gostar