Escolar Documentos
Profissional Documentos
Cultura Documentos
Five-Day Delivery
Transition Management
Status
Sam Pulcrano
Mailers Technical Advisory
Committee -- November 18, 2010
FDD Timeline
Pre-PRC Post-PRC Planning Pre-Approval PlanningImplementation Five Day
MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP
Deadline to File Interrogatories (8/18) GAO Report (Jan.)
PRC/GAO Response
Program Mgmt &
Ready to Launch
Implementation &
Review existing plans and identify gaps Integrate the plans together Resolve issues, fill remaining gaps,
and obtain sign-off for final plan
8/9 8/16 8/23 8/30 9/6 9/13 9/20 9/27 10/4 10/11 10/18 10/25 11/1 11/8
FDD TMO Kick Off Checkpoint Checkpoint Mid-Point Review Implementation Plan Final Implementation Submission
(complete 8/10) #1 #2 (Bolger 9/16) Ready for Submission to Plan Review to GAO
GAO & Sr. Mgmt Session 11/8/2010
10/15/2010 10/21/2010
INPUTS: INPUTS:
•Existing FDD workgroup materials • Draft gap assessment
•Global Postal Industry Operating Model • Re-baselined implementation plans for each workstream
• Baseline USPS processes by workstream
INPUTS:
•Draft Integrated Implementation Plan
KEY ACTIVITIES:
•Integrated USPS Operating Model /
•Initial support sessions / KEY ACTIVITIES:
Impact Assessment
checkpoints with implementation •Continue support sessions / checkpoints
plan owners with implementation plan owners
•Validate Operating Model with plan •Facilitate compilation of individual KEY ACTIVITIES:
owners workstream plans to consolidated FDD • Finalize compilation of workstream
implementation plan plans to consolidated FDD
implementation plan
OUTPUTS: OUTPUTS: • Final VP sign-off of Integrated
•Draft gap assessment • Draft Integrated Implementation Plan for submission Implementation Plan
•Re-baselined implementation plans for to Senior Management
each workstream • Comprehensive implementation plans with for each
•Baseline USPS processes with impacts by workstream OUTPUTS:
workstream • Draft Integrated USPS Operating Model / Impact •Final Integrated Implementation Plan for
Assessment submission to GAO
•Final USPS Operating Model / Impact
Assessment
3
FDD Implementation Plan Owners & Reviewers
Work Group Implementation Plan Section Implementation Plan Owner(s) VP / Review Authority 1
Delivery Work Group City Delivery P. Knoll, V. Rouse Granholm
Rural Delivery J. Boldt Granholm
HCR and Contract Delivery B. McKain Brownell
Post Office Operations Work Post Office Operations A. Raney Granholm
Group
Network Operations Work Mail Processing Operations E. Lichorat Williams
Group Transportation F. Rigel Williams
BMEU and DMU Operations A. VanGorder, L. Zalewski Mehra
Maintenance and Engineering A. Hall Sigmon
Global Business R. Middlebrooks Shah
Service Performance Measurement M. Clarke, R. Creamer, E. Ryan Killette
Facilities U. Tamaskar No FDD Impacts / No Implementation
Plan
Communications Work Communications G. McKiernan, T. Knupp Betman
Group
Mailing & Shipping Services Advertising J. Carrier Vogel
Work Group Consumers & Small Business Mgmt M. Clarke, D. Nichols, P. Mason, G. Vogel
Thuro, S. Felix
Customer Account Mgmt T. Knupp Plonkey
Retail Equipment K. Mastervich Healy
Retail Partners D. Kelly Healy
Express and Priority Mail K. Key Tasks Integrated into Other Plans / No
Separate Implementation Plan
Human Resources / Labor People Movement Plan B. Brenker, A. Moore, M. Gandhi Giannoni-Jackson (HR), Tulino (LR)
Relations Work Group Training T. Link LaChance
Manuals A. Moore, K. Coleman Tulino
IT and Finance Systems IT M. Goldman Edgar
Work Group Finance R. Langevin DeVito
1 Additional Reviewers (Products): Steve Monteith (Transactions and Correspondence), Tom Foti (Marketing Mail), Nan McKenzie (Special Services), Gary
Thuro (Marketing Retail), Karen Mastervich (Retail Systems / POS)
4
Work Groups for Implementation Planning
Delivery 1 Communications 4
Work Group Lead: Van Rouse Work Group Lead: Gerry McKiernan
City Delivery Communications
Rural Delivery
Mailing & Shipping Services 5
HCR and Contract Delivery
Work Group Leads: Bob Michelson & Terry Knupp
Post Office Operations 2 Advertising
Work Group Lead: Annette Raney Consumers & Small Business Management
Post Office Operations Customer Account Management
Retail Equipment
Network Operations 3a/3b Retail Partners
Work Group Lead: Ed Lichorat Express & Priority Mail 2
Mail Processing Operations
Transportation Human Resources / Labor Relations 6
BMEU & DMU Operations (incl. FAST) Work Group Leads: Mangala Gandhi & Alan Moore
People Movement
Maintenance & Engineering Training
Global Business Manuals
Service Performance Measurement
IT and Finance Systems 7
Facilities 1
Work Group Lead: Mike Goldman
¹Facilities has no FDD Impacts / No Implementation Plan IT
²Express & Priority Mail tasks will be distributed into other Operations
plans / no separate Implementation Plan Finance
New Workstream 5
Manual and Handbook Updates Summary
Corporate Publishing
Updates Updates Finalized Between LR LR Review
VP Total Identified Provided to LR Scheduled
Needed Completed and Originator Completion Date
Completion Date
Deborah Giannoni-
5 3 3 3 3 10/1/2010 1/1/2011
Jackson
Total 76 33 33 33 33
6
FDD IT Status
User
Delivery Sales and Network Customer Shipping Human
Finance Applications Engineering
and Retail Marketing Operations Relations and Mailing Resources & Reports
IRT
Inform Customer 90 WebFarm, Variance, Mail History Tracking
Days Prior to Delivery System, EDW
8
FDD Area-Level Planning Schedule
11/8/10 11/15 11/22 11/29 12/6 12/13 12/20 12/27 1/3/11 1/10 1/17 1/24 1/31 2/7 2/14
Create outline and key topics by section for Guidebook (HQ Final Area-Level
Core Team) –for MOS Meeting 11/30 - 12/1 Guidebook Briefing
Complete impact assessment of HQ Implementation Plan using Date TBD
products and services catalog
If any – Identify additional detail related to functional workstreams,
products / services, or IT systems to enhance HQ Implementation
Plan
Your Questions?