Escolar Documentos
Profissional Documentos
Cultura Documentos
d. Typical-bay Method
Plinth area is the covered built-up area measured at the floor level of any storey or at the floor
level of the basement. Plinth area is also called as built-up area and is the entire area occupied
by the building including internal and external walls. Plinth area is generally 10-20% more than
carpet area.
Carpet area the covered area of the usable spaces of rooms at any floor. It is measured
between walls to walls within the building and is the sum of the actual areas of the
rooms where you can carpet.
You can see the bricks should be burnt thoroughly without being vitrified and
have deep red, cherry and copper color.
Bricks should have regular and uniform in shape and size with sharp and square
edges and parallel faces.
Bricks should give a clear ringing sound on being struck together and are free
from flaws, cracks, chops, stones and lime.
Bricks should not absorb water more than 20% of its own dry weight after 24
hours, immersion in cold water.
Bricks should have a minimum crushing strength of 105 kg per sq. cm when
tested according to the specification.
Bricks should not show appreciable sign of efflorescence either in dry state or
subsequent to soaking in water.
Long answer
TYPES OF ESTIMATES
There are eight different types of stimate:
I. Detailed estimate
V. Supplementary estimate
I. DETAILED ESTIMATE
A detailed estimate provides schedule of all the possible items and an amount which is
very near to the final amount of the structure and the above is prepared for the following
two purpose.
a. Execution process
The whole project is subdivided into various stages, the stages broken up into various
items of work having same specifications and rates.
The detailed estimate comprises the cost as follows:
1. Total cost of various items of work
4. Estimated amount for the service charges like water supply, drainage, sanitary
arrangement and electrical installation.
2) Specifications
3) Detailed drawings showing plans, elevation, sections, key plan, drainage layout,
electrical drawings, structural drawings, etc.
4. It is the basis of which percentage tenders are called after excluding the amounts of
contingencies.
5. The bills of work done are also prepared on the basis of abstract of estimate.
7. The nomenclature of item provides concise description of the nature of the work,
name of the materials & quantities, workmanship, period of curing, consideration of land
& lift, scaffolding, shuttering, dewatering operation including all transport, tools and
plants.
3. Damp-proof course.
4. Brickwork in superstructure.
11. Painting & colour washing (Doors, windows, ventilators, grills and cemented
surfaces)
13. Electrification
14. Miscellaneous (Overhead tank, sump, elevation finishes, platform, septic tank,
compound wall gate, etc)
Important factors for detailed estimate:
1. Availability of local labour
2. Availability of materials
3. Location of site
4. Transportation of materials
5. Quantity of materials
2. Investment
3. Financial aspect
4. Tax schedule
5. Insurance
2. Fix up the unit cost by studying the actual cost of similar existing structure
constructed in near past.
The approximate cost of a building can be found by the use of any one of
following six methods:
a. Unit area or Service Unit Method
d. Typical-bay Method
3. Material deviations.
V. SUPPLEMENTARY ESTIMATE
Some changes or additional works due to material deviation or a structural nature from
the originally approved design maybe thought necessary when the work is in progress,
for all such items a detailed estimate is prepared. It is to be attached with a detailed
report describing the reasons for new additional work.