Escolar Documentos
Profissional Documentos
Cultura Documentos
Group 4
JACULINE STEPHEN-051753
The first issue is whether the ABC Builders can discharge the contract under the
doctrine of frustration.
1
Pacific Forest Industries Sdn Bhd & Anor v. Lin Wen-Chih & Anor [2009] 6 MLJ 293.
performance arising after the contract was made’. The contract will ‘become void’ once
it is held to be frustrated. Section 57(2) of the Contracts Act 1950 also provides the
doctrine of frustration. In the case of Guan Aik Moh (KL) Sdn Bhd v. Selangor
Properties Bhd [2007] 4 MLJ 201, CA, Gopal Sri Ram JCA stated that there are 3
elements for the doctrine of frustrated incorporated within the meaning of Section 57
of Contracts Act 1950, namely:
(1) The event upon which the promisor relies as having frustrated the contract must
have been one for which no provision has been made in the contract. If
provision has been made then the parties must be taken to have allocated the
risk between them.
(2) The event relied upon by the promisor must be one for which he or she is not
responsible. Put shortly, self induced frustration is ineffective.
(3) The event which is said to discharge the promise must be such that renders it
radically different from that which was undertaken by the contract. The court
must find it practically unjust to enforce the original promise.
In the case of Pacific Forest Industries Sdn Bhd & Anor v. Lin Wen-Chih & Anor
[2009] 6 MLJ 293, the court held that any of the above elements must be fulfilled to
establish the frustration under s57.
The sub-issue is whether the facts of the present case fulfilled any of the
elements stated above. It is clear that the first element as stated above does not
relevant to the present case as the facts was silent on this matter. With regards to the
second element and the third element, it is submitted that ABC builder could not rely
on it. In this case, the event occurred was the intermittent strikes by the worker and
cause the delay of the construction and directly increases the cost of construction.
However, under the second element, it is stated that self-induced frustration is
ineffective. It is assumed that the aroseness of the strike by the workers was due to
the self-management system of the ABC Builders which is within its own control.
Besides, merely the increases of the cost of construction does not rendered the
performance of the contract by ABC Builders to be radically different from what was
undertaken by the contract and make it practically unjust to enforce it.
This view can be supported by the case of Davis Contractors Ltd v. Fareham
Urban District Council [1956] AC 696, where the appellants agreed to build 78
houses within 8 months for the respondents for the fixed sum of £94,000. Owing to
unexpected shortage of skilled labour and certain materials, the period construction
was forced to extend and the cost also increased. The appellants contended that there
was frustration of the contract and claimed quantum meruit for the actual cost incurred.
The HOL held that there was no frustration. The fact that the contract becomes more
onerous or expensive to the appellants did not discharge the agreement. The thing
that undertaken was not, when performed, different from the contract.
By above reasons, it can be concluded that ABC Builders could not discharge
from the contract by claiming the doctrine of frustration.
The second issue is whether ABC Builders can claim for the excess cost of
construction on a quantum meruit basis.
In the current case, the construction of a girl’s hostel and a swimming pool with
UNISZA was contracted on RM10m. However due to the intermittent strikes by the
workers, the construction was completed only after a year later and the cost of
construction also rose from Rm10m to Rm15m. Since the ABC Builders cannot
discharge the contract, applying Section 66 of the Contracts Act 1950, ABC Builders
cannot claim for the excess cost of construction on a quantum meruit basis.
In a nutshell, ABC Builders could not discharge from the contract by claiming
the doctrine of frustration and cannot claim for the excess cost of construction on a
quantum meruit basis.