IMPROVEMENTS TO SECTION OF GAMPAHA DISTRICT SECRETARIAT OFFICE PREMISES ROAD -Asphalt Laying -850 m2
Rate Rs.
Item No Description Unit Qty Amount Rs. Cts. Remarks
Cts.
1.00 Mobilization & Demobilization of Contractor's facilities and plant/Equipment item
1 560,000.00 560,000.00 Already rated
ROAD WAY EXCAVATION -
2.00 Excavation in hard soil-exsisting asphalt etc (Cutting measurement)- transportation 3
m
excavated soil to dump site should be done by client -Width 7m 775.00 3,192.78 2,474,404.50 Additional item
3.00 Prepare sub grade in cut areas 2
m 1,491.00 146.05 217,760.55 Additional item
GRANULAR PAVEMENT -
4.00 Sub base as compacted in position-7m width ,200mm thickness m3 372.75 4,122.42 1,536,632.06 Additional item
5.00 Laying ,cutting Leveling & Compacting 200mm thick Dense graded aggregate base 2
m 1,491.00 200.00 298,200.00 Already rated
PRIME COAT AND TACK COAT -
6.00 Bituminous Prime Coat using 2 860.00 180.00 154,800.00 Already rated
m
7.00 Bituminous Tack Coat 2
m 860.00 90.00 77,400.00 Already rated
8.00 Brushing and cleaning road surface for tack coat 860.00 10.16 8,737.60 Additional item
BITUMINOUS SURFACING -
9.00 Asphalt concrete in wearing course 50mm compacted thickness with necessary Mt 105.00 9,500.00 997,500.00 Already rated
bituminous coatings -
10.00 50 mm thick Asphalt concrete in binder/ Correction course Mt 105.00 9,500.00 997,500.00 Additional item
Page 1 of 1