Você está na página 1de 1

VONLAN CONSTRUCTIONS

IMPROVEMENTS TO SECTION OF GAMPAHA DISTRICT SECRETARIAT OFFICE PREMISES ROAD -Asphalt Laying -850 m2

Rate Rs.
Item No Description Unit Qty Amount Rs. Cts. Remarks
Cts.
1.00 Mobilization & Demobilization of Contractor's facilities and plant/Equipment item
1 560,000.00 560,000.00 Already rated
ROAD WAY EXCAVATION -
2.00 Excavation in hard soil-exsisting asphalt etc (Cutting measurement)- transportation 3
m
excavated soil to dump site should be done by client -Width 7m 775.00 3,192.78 2,474,404.50 Additional item
3.00 Prepare sub grade in cut areas 2
m 1,491.00 146.05 217,760.55 Additional item
GRANULAR PAVEMENT -
4.00 Sub base as compacted in position-7m width ,200mm thickness m3 372.75 4,122.42 1,536,632.06 Additional item
5.00 Laying ,cutting Leveling & Compacting 200mm thick Dense graded aggregate base 2
m 1,491.00 200.00 298,200.00 Already rated
PRIME COAT AND TACK COAT -
6.00 Bituminous Prime Coat using 2 860.00 180.00 154,800.00 Already rated
m
7.00 Bituminous Tack Coat 2
m 860.00 90.00 77,400.00 Already rated
8.00 Brushing and cleaning road surface for tack coat 860.00 10.16 8,737.60 Additional item
BITUMINOUS SURFACING -
9.00 Asphalt concrete in wearing course 50mm compacted thickness with necessary Mt 105.00 9,500.00 997,500.00 Already rated
bituminous coatings -
10.00 50 mm thick Asphalt concrete in binder/ Correction course Mt 105.00 9,500.00 997,500.00 Additional item

Special Discount (410,000.00)


Total Amount 6,912,934.71

Transportation of Excavated Soil to dumping site by Sanken


Supply of sub base matrial by Vonlan
Supply of ABC by Sanken
Drawings and specifications should be provided by Sanken-Design CS etc