Escolar Documentos
Profissional Documentos
Cultura Documentos
COST ESTIMATION
300
CHAPTER 7
COST ESTIMATION
operating at 270 days/year, the total capital investment reached an amout of Php
fixed capital investment was determined from the total direct production cost and
indirect production cost. The total direct production cost consist of 21.93%
control, 6.80% piping system, 2.19% electrical system, 6.36% building, 2.63% yard
improvement, 12.06% service facilities and the total indirect cost which is
0.88% legal expenses,4.17% contractor’s fee and 27.64% contingency. The Fixed
Capital Investment which represents the amount necessary for the complete cost
and installation of the process equipment I computed based on the major equipment
Crystallizer, Decanter Centrifuge, and Freeze Drier. It is assumed that the cost of
the other equipment is 20% of the cost of these four major equipment. The working
301
capital necessary to finance plant operation was computed and added to the fixed
The selling prices of the designed equipment are obtained from trusted
Chemical Engineering resources and textbooks. Present costs are computed based
on Marshall and Swift Indexes to take into consideration the economic impact to
302
II. Total Production Cost
necessary in order to know if the given design will yield a considerate amount of
profit. It is determined from the manufacturing cost, which may also be referred to
charges, and plant overhead cost, and from the general expenses. Considering one
kilogram of collagen, the calculated total production cost is Php 288.57 which was
obtained from adding the manufacturing cost and the general expenses.
In the manufacturing cost, the calculated amount of the total direct cost is
Php 196.88 which is the sum of cost of the raw materials amounting to Php 146.45,
operating labor of Php 24.08, direct supervisory and clerical labor of Php 3.62,
utilities of Php 9.25, maintenance and repair of Php 8.58, operating supplies of Php
1.29, and laboratory charges of Php 3.61. The fixed charges calculated is Php 16.49
which is obtained by adding the depreciation worth of Php 11.92, local taxes of Php
3.58 and insurance of Php1.00. The plant overhead cost is also included and it
The General Expenses amount to Php 53.43. This amount is the summation
of the administrative cost of Php 7.26, Distribution and Marketing cost of Php 31.74
303
The current selling price of a 92% purity food grade hydrolyzed collagen in
USA, is 36 USD or Php 1,800 per kilogram. Since the computed TPC is lower than
the current selling price, henxce, it is safe to say that the proposed plant will be
profitable.
304
III. SUMMARY OF COST ESTIMATION
A. Direct cost
Cost (Php) Exhibit %
Purchased Equipment Delivered Php 54,058,419.63 A 21.93%
Installation Php 21,082,783.66 B 8.55%
Instrumentation and Control Php 14,055,189.10 C 5.70%
Piping System Php 16,758,110.09 D 6.80%
Building Php 15,676,941.69 E 6.36%
Electrical System Php 5,405,841.96 F 2.19%
Yard Improvement Php 6,487,010.36 G 2.63%
Service Facilities Php 29,732,130.80 H 12.06%
Total Direct Cost Php 163,256,427.28 66.24%
B. Indirect cost
305
IV. Total Production Cost (TPC)
B. Fixed Charges BB
Depreciation Php 11.92 BB-1 4.13%
Local Taxes Php 3.58 BB-2 1.24%
Insurance Php 1.00 BB-3 0.35%
Total Fixed Charges Php 16.49 5.72%
306
IV. EXHIBIT A
Schedule
Pepsin Digester Php 7,115,702.56 A-1
Salt-Out Tank Php 3,788,752.90 A-2
Decanter Centrifuge Php 7,988,966.73 A-3
Freeze Drier Php 17,145,524.23 A-4
Other Equipment Php 7,207,789.28 A-5
Total Php 43, 246,735.70
= (𝑃ℎ𝑝 43,246,735.70)(1.25)
307
V. SCHEDULE A-1 (PEPSIN DIGESTER)
Cost of Reactor:
From Plant Design and Economics for Chemical Engineers by Peters and
604
Present Cost of Reactor2019 = ($60,000) ( )
390.4
Cost of Insulation:
From Plant Design and Economics for Chemical Engineers by Peters and
308
Computing for the purchased cost of insulation for a 13.0 m2 heat transfer area,
604
Present cost of insulation = ($1313) ( ) = $2,031.38
390.4
Cost of Impeller:
From Plant Design and Economics for Chemical Engineers by Peter and
For stainless steel and rotational speed of 125 rpm, adjustment factor is 1.85.
Purchased Cost of Impeller (2019) = $𝟏𝟔, 𝟎𝟎𝟎 (𝟏. 𝟖𝟓) = $𝟐𝟗, 𝟔𝟎𝟎
604
Present Cost of One (1) Impeller = $29,600 (390.4) = $45,795.08
𝑃ℎ𝑝 50.59
Total Present Cost of J-3 = $140,654.33 ( )
1 𝑈𝑆𝐷
309
Cost of Reactor:
From Figure 15-17 of Peters and Timmerhaus 5th Ed.: Commented [KB1]:
310
Cost of Insulation:
311
Cost of Impeller:
For SS316 and rotational speed of 125 rpm, adjustment factor is 1.85
312
SUMMARY OF FIGURES USED IN SCHEDULE A-1
(PEPSIN DIGESTER)
313
VI. SCHEDULE A-2 (VACUUM CRYSTALLIZER)
Cost of Crystallizer:
1990. (PD&E for ChE, Peters, Timmerhaus, & West 4th Ed.; Fig. 14-76, p561).
314
𝑃𝑟𝑒𝑠𝑒𝑛𝑡 𝑃𝑢𝑟𝑐ℎ𝑎𝑠𝑒𝑑 𝐶𝑜𝑠𝑡 𝑜𝑓 𝐶𝑟𝑦𝑠𝑡𝑎𝑙𝑙𝑖𝑧𝑒𝑟
315
Cost of Pump:
Pressure Drop:
∆𝑃 = 𝜌𝑠𝑙𝑢𝑟𝑟𝑦 𝑔ℎ𝑇𝐷𝐻
𝑘𝑔 𝑁−𝑚
∆𝑃 = (1,257.70 ) (9.889 ) = 12,437 𝑃𝑎 = 1.80 𝑝𝑠𝑖
𝑚3 𝑘𝑔
𝑙𝑏 𝑙𝑏
𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝐹𝑎𝑐𝑡𝑜𝑟 = 𝑔𝑝𝑚 𝑥 = (72.34 𝑔𝑝𝑚)(1.80 𝑝𝑠𝑖) = 130.21 𝑔𝑝𝑚
𝑖𝑛2 𝑖𝑛2
𝑙𝑏
Present cost of centrifugal pump with capacity factor of 122.43 𝑔𝑝𝑚 is $1500
𝑖𝑛2
as of January 1990. (PD&E for ChE, Peters, Timmerhaus, & West 4th Ed.; Fig. 14-
41, p527)
316
𝑃𝑟𝑒𝑠𝑒𝑛𝑡 𝑃𝑢𝑟𝑐ℎ𝑎𝑠𝑒𝑑 𝐶𝑜𝑠𝑡 𝑜𝑓 𝐶𝑒𝑛𝑡𝑟𝑖𝑓𝑢𝑔𝑎𝑙 𝑃𝑢𝑚𝑝 (1990)
𝑙𝑏 0.60
130.21 𝑔𝑝𝑚 604
= ($1,500) ( 𝑖𝑛2 ) ( ) = $748.98
𝑙𝑏 356
1000 𝑔𝑝𝑚 2
𝑖𝑛
317
Cost of Insulation:
From PD&E for ChE, Peters, Timmerhaus, & West 5th Edition, Fig. 15-17, p797
$155 2)
0.0063 m 0.60 604
𝑃𝑟𝑒𝑠𝑒𝑛𝑡 𝐶𝑜𝑠𝑡 𝑜𝑓 𝐼𝑛𝑠𝑢𝑙𝑎𝑡𝑖𝑜𝑛 = (2.97 𝑚 ( ) ( )
𝑚2 0.026 m 390.4
= $𝟑𝟎𝟑. 𝟑𝟖
318
For Insulation thickness of 6.34mm for Cooling Condenser:
= $𝟑𝟎𝟒. 𝟐𝟓
319
SUMMARY OF FIGURES USED IN SCHEDULE A-2
(SALT OUT CRYSTALLIZER)
320
VII. SCHEDULE A-3 (DECANTER CENTRIFUGE)
Solid Liquid = 1
January 2002.
(PD&E for ChE, Peters, Timmerhaus, & West 5th Ed.; Fig. 15-43, p866).
321
𝑃𝑟𝑒𝑠𝑒𝑛𝑡 𝑃𝑢𝑟𝑐ℎ𝑎𝑠𝑒𝑑 𝐶𝑜𝑠𝑡 𝑜𝑓 𝐷𝑒𝑐𝑎𝑛𝑡𝑒𝑟 𝐶𝑒𝑛𝑡𝑟𝑖𝑓𝑢𝑔𝑒
₱50.59
$157,915.93 × [ ] = ₱𝟕, 𝟗𝟖𝟖, 𝟗𝟔𝟔. 𝟕𝟑
$1
322
SUMMARY OF FIGURES USED IN SCHEDULE A-3
(DECANTER CENTRIFUGE)
323
VIII. SCHEDULE A-4 (FREEZE-DRIER)
Equipment: Freeze-drier
Equipment code: T-2
Type: Vacuum, Freeze-drier
Material of Construction: AIS SS316L
From Equipment Design:
Capacity: 1.34 m3
No. of Units 1
Cost of Dryer:
From Plant Design and Economics for Chemical Engineers by Peter and
604
Present cost of dryer2019 (based on total shelf area) = $100,700 (309.4) =
$196,583.06
Php 50.59
$196,583.06(1 unit) ( ) = 𝐏𝐡𝐩𝟗, 𝟗𝟒𝟓, 𝟏𝟑𝟕. 𝟐𝟏
1USD
324
Cost of Compressor:
From Plant Design and Economics for Chemical Engineers by Peter and
Cost2002= $85,000
Computing for the cost of the compressor with a power requirement of 85.45kW
85.45 0.6
Cost2002= $85,000 ( ) = $85,269.71
85
604
Cost2019=$85,269.71 ( ) = $131,923.43
390.4
Php 50.59
$171,152.82(1 unit) ( ) = 𝐏𝐡𝐩𝟔, 𝟔𝟒𝟕, 𝟎𝟎𝟔. 𝟒𝟏
1USD
From Plant Design and Economics for Chemical Engineers by Peter and
Cost2002=$10,000
325
Computing for the cost of the shell and tube heat exchanger with a heating area of
0.5732 0.6
Cost2002=$10,000( ) = $481.32
90
604
Cost2019=$481.67 ( ) = $744.67
390.4
50.59Php
$1561.93(1 unit)( ) = 𝟑𝟕, 𝟔𝟕𝟐. 𝟗𝟖𝐏𝐡𝐩
1USD
From Plant Design and Economics for Chemical Engineers by Peter and
Cost2002=$10,000
Computing for the cost of the shell and tube heat exchanger with a heating area of
1.53 0.6
Cost2002=$10,000( ) = $867.5
90
604
Cost2019=$867.5 (390.4) = $1,342.13
326
Present cost in Philippine currency:
50.59Php
$1,342.13(1 unit) ( ) = 𝟔𝟕, 𝟖𝟗𝟖. 𝟔𝟓𝐏𝐡𝐩
1USD
Cost of Insulation:
From Plant Design and Economics for Chemical Engineers by Peter and
$102
Cost2002= m2
$102
Cost2002= (52.71𝑚2 ) = $5,376.42
m2
604
Cost2019= $5,376.42 (390.4) = $8,318.03
50.59Php
$9107.62(1unit) ( ) = 𝟒𝟐𝟎, 𝟖𝟎𝟖. 𝟗𝟖𝐏𝐡𝐩
1USD
+ 420,808.98Php
= Php 17,145,524.23
327
Cost of Freeze-Drier:
From Plant Design and Economics for Chemical Engineers by Peter and
328
Cost of Reciprocating Compressor:
From Plant Design and Economics for Chemical Engineers by Peter and
= $85,000
329
Cost of Shell and Tube Heat Exchanger:
From Plant Design and Economics for Chemical Engineers by Peter and
Purchased Cost of Shell and Tube Heat Exchanger2002 with a heating area of 90 m2
= $10,000
330
Cost of Insulation:
From Plant Design and Economics for Chemical Engineers by Peter and
331
SUMMARY OF FIGURES USED IN SCHEDULE A-4
(FREEZE DRIER)
332
IX. SCHEDULE A-5
The four equipment previously designed are the major equipment and much
expensive compared to the others. Therefore, assuming 20% of the total cost of the
333
X. EXHIBIT B
Installation Cost
The installation cost of purchased equipment includes the cost for manpower,
foundations, flat forms, supports, construction expenses and other factors directly
From Exhibit A:
334
XI. EXHIBIT C
The major constituents of the instrument and control cost are the instruments cost
installation-labor costs, and the expenses for auxiliary and material. These
auxiliaries are composed of the pressure and temperature gauges and flow
251)
From Exhibit A:
335
XII. EXHIBIT D
Piping Cost
The cost of piping encompasses the labor cost, cost of piping materials, valves,
fittings, supports and other item related necessary for the pipe installation and
251)
From Exhibit A:
336
XIII. EXHIBIT E
offices and other buildings connected in the plant. This also includes other building
251)
From Exhibit A:
337
XIV. EXHIBIT F
The electrical system cost is primarily consists of installation labor and materials
for power and lightning. It is consistof major components such as wiring, power,
lighting, instrument and control wiring, transformation and other electrical related
251)
From Exhibit A:
338
XV. EXHIBIT G
Yard Improvement
251)
From Exhibit A:
339
XVI. EXHIBIT H
Service Facilities
equipment in a production plant such as utilities for supplying steam, water, power,
compressed air, and fuel. The cost of service facilities includes waste disposal, fire
251)
From Exhibit A:
340
XVII. EXHIBIT I
communications, and home office expense including overhead constitute the capital
251)
From Exhibit A:
341
XVIII. EXHIBIT J
Construction Expenses
The construction expenses cover all the construction labor cost and construction
expenses such as construction tools, materials, rentals, and payrolls, taxes and
251)
From Exhibit A:
342
XIX. EXHIBIT K
Legal Expenses
Legal cost includes the expenditures in the processing of equipment and land
measures.
251)
From Exhibit A:
343
XX. EXHIBIT L
Contractor’s Fee
The contractor’s fee is the payment given to the architectural and construction
company responsible for the construction of the production plant and all other fees
251)
From Exhibit A:
344
XXI. EXHIBIT M
Contingency
Contingency cost is usually incorporated in the estimation of the cost for a project
charges which may inevitably raise the cost of establishing the production plant.
Natural forces such as floods and storms, price hikes, and strikes, and other
in the cost estimation must have their own proper appropriation in the cost
estimation.
251)
From Exhibit A:
345
XXII. EXHIBIT N
Working Capital
designated to: (1) Raw materials, (2) Expenses for labors, and (3) Utilities
346
XXIII. SCHEDULE N-1
Raw material is one of the major costs in a production operation. Raw Materials
are the unprocessed materials that are used to produce goods and manufacture
products. These stored raw materials will be good for 60 days of operation.
Source: https://www.ceicdata.com/en/philippines/farmgate-price-selected-
agricultural-commodities/farmgate-price-fishery-yellowfin-tuna
From the material balance, the amount of yellowfin tuna skin is 12,000kg/day.
Basis: Yellowfin tuna skin constitutes 10% of the total live weight of the yellowfin
tuna (Chapter 4)
𝑃𝑟𝑖𝑐𝑒 (𝑃ℎ𝑝)
⁄𝑘𝑔 𝑦𝑒𝑙𝑙𝑜𝑤𝑓𝑖𝑛 𝑡𝑢𝑛𝑎 𝑠𝑘𝑖𝑛 = (𝑃ℎ𝑝106.45)(0.10) = 𝑃ℎ𝑝10.65
347
SUMMARY OF FIGURES USED IN SCHEDULE N-1
348
B. Hydrochloric acid:
From Material Balance: The required daily total amount of Hydrochloric Acid is
850.04 kilograms.
349
SUMMARY OF FIGURES USED IN N-1
HYDROCHLORIC ACID
Hydrochloric Acid Price, per kg Php 10.12
Amount of Hydrochloric Acid
850.04 kg/day
Required
Days of Operation 60 days
Cost of Hydrochloric Acid Php 516,144.29
350
C. Sodium hydroxide:
https://www.alibaba.com/product-detail/Pure-white-flakes-
caustic-soda-
Source:
99_60737755868.html?spm=a2700.7724857.normalList.42.
720a29e7BRGT2B
From Material Balance: The required daily total amount of sodium hydroxide is
808.89 kilograms
351
SUMMARY OF FIGURES USED IN SCHEDULE N-1
SODIUM HYDROXIDE
Sodium Hydroxide Price, per kg Php 25.30
Amount of Sodium Hydroxide Required 808.89kg/day
Days of Operation 60 days
Cost of Sodium Hydroxide Php 1,227,895.02
352
D. Pepsin:
Grade
Standar Pharmaceutical Grade, Food Grade
d:
Referenc
Alibaba Globe Trade
e:
https://www.alibaba.com/product-detail/Manufacture-supply-
Pepsin-1-10000-
Source:
NF_62297606583.html?spm=a2700.7724857.normalList.27.776849
db1uW081&s=p
From Material Balance: The required daily total amount of pepsin is 47.83
kilograms
Cost of Pepsin:
353
SUMMARY OF FIGURES USED IN SCHEDULE N-1
PEPSIN
Pepsin Price, per kg Php 607.08
Amount of Pepsin Required 46.41kg/day
Days of Operation 60 days
Cost of Pepsin Php 1,690,474.97
354
E. Acetic Acid:
From Material Balance: The required daily total amount of acetic acid is 1611.37
kilograms.
356
SUMMARY OF RAW MATERIAL COSTS
Yellowfin Tuna Skin Php 7,668,000.00
Hydrochloric Acid Php 526,624.56
Sodium Hydroxide Php 1,227,895.02
Pepsin Php 1,742,198.19
Acetic Acid Php 1,223,029.83
TOTAL RAW MATERIAL COST Php 12,387,747.60
357
XXIV. SCHEDULE N-2
A. Labor cost
Estimating labor requirements as a function of plant capacity is based on
adding the various principal processing steps on the flow sheet. In this method, a
process step is defined as any unit operation, unit process, or combination thereof
that takes place in one or more units of grinding, extracting, fermenting, filtering,
distilling, etc.
plant is 1,400kg.
Using Figure 6-9 page 265 of Plant Design and Economics for Ch.E., 5th
Ed. by Peters, Timmerhaus, and West, the operating labor by using line B (average
conditions) is,
17 𝑒𝑚𝑝𝑙𝑜𝑦𝑒𝑒 ∙ ℎ𝑜𝑢𝑟𝑠
𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝐿𝑎𝑏𝑜𝑟 =
𝑑𝑎𝑦 ∙ 𝑝𝑟𝑜𝑐𝑒𝑠𝑠 𝑠𝑡𝑒𝑝
By adapting the minimum wage per day of Php 311.00 (Source: DOLE
𝑃ℎ𝑝 38.88
=
𝑒𝑚𝑝𝑙𝑜𝑦𝑒𝑒 ∙ ℎ𝑜𝑢𝑟
358
The plant operation is 24 hours per day with 3 shifts wherein the employees
359
SUMMARY OF FIGURES USED IN SCHEDULE N-2
360
XXV. SCHEDULE N-3
Utilities
The basic utilities in a production plant that usually contribute in the cost
estimation are cooling water and electricity which may vary directly depending on
SUMMARY OF UTILITIES
Water Php 112, 205.49
Electricity Php 357,778.11
Steam Php 388,182.17
TOTAL COST OF UTILITIES Php 858,165.77
361
A. Water
The water consumption listed under utilities are used as process water and
cooling water.
PROCESS WATER
EQUIPMENT
REQUIREMENT (per day)
Alkali Pretreatment (J-1) 2,931.75 kg 2.93175 cu. m.
Neutralization Tank (J-2) 663.03 kg 0.66303 cu. m.
Pepsin Digester (J-3) 3,227.29 kg 3.22729 cu. m.
Dialyzer Ultra-Filter (K-6) 5,048.89 kg 5.04889 cu. m.
TOTAL WATER
11,870.96 kg 11.87096 cu. m.
REQUIREMENT
= 𝑃ℎ𝑝 30,769.53
362
From Energy Balance,
= 𝑃ℎ𝑝 350.70
363
SUMMARY OF FIGURES USED IN SCHEDULE N-3
WATER
Water Price of Industrial Use Php 43.20/cu. m.
Total Process Water Requirements 11.87096 cu. m.
Days of Operation 60 days
Total Cooling Water Requirements 8.11785 cu. m.
Total Cost of Water Php 31,120.23
364
B. Electricity
365
Electricity Cost for Decanter Centrifuge
Assuming 40% of the total electricity cost of the four major equipment as the
electricity cost of the other equipment.
366
SUMMARY OF FIGURES USED IN SCHEDULE N-3
ELECTRICITY
SOCOTECO II Rate Php 7.12239/kWh
Change-out Period 60 days
Power Requirement of Pepsin Digester 7.457kW
Operating hours of Pepsin Digester 1.69 hours
No. of Digester Units 1 unit
Electricity Cost for Pepsin Digester Php 5,386.65
Power Requirement of Salt-out Tank 0.559275kW
Operating hours of Salt-out Tank 22.5 hours
No. of Salt-out Tank Units 1 unit
Electricity Cost for Salt-out Tank Php 5,378.70
Power Requirement of Decanter Centrifuge 5.2199kW
Operating hours of Decanter Centrifuge 24 hours
No. of Decanter Centrifuge Units 1 unit
Electricity Cost for Decanter Centrifuge Php 53,547.91
Power Requirement of Freeze Drier 149.14kW
Operating hours of Freeze Drier 3 hours
No. of Freeze Drier Units 1 unit
Electricity Cost for Freeze Drier Php 191,242.53
40% of Major Equipment
Electricity Cost for Other Equipment
Total Electricity Cost
Total Electricity Cost Php 357,778.11
367
C. Steam
From Energy Balance,
𝑷𝒉𝒑 𝟒𝟐𝟑. 𝟒𝟖
𝑹𝒂𝒘 𝑴𝒂𝒕𝒆𝒓𝒊𝒂𝒍 𝑪𝒐𝒔𝒕 = ⁄𝒅𝒂𝒚
𝒍𝒃 𝒔𝒕𝒆𝒂𝒎
𝑺𝒕𝒆𝒂𝒎 𝑪𝒂𝒑𝒂𝒄𝒊𝒕𝒚 = 𝟖𝟗𝟖. 𝟓𝟕
𝒉𝒐𝒖𝒓
(From PD & E, 5th Edition by Peters & Timmerhaus, Figure B-3, p. 809)
For 900 lb/hr and 265 psi, Purchased Cost of Boiler = $11,408.98
(From PD & E, 5th Edition by Peters & Timmerhaus, Table 7-8, p. 310)
𝑷𝒉𝒑𝟐𝟏𝟑𝟕. 𝟕𝟏
𝑪𝒐𝒔𝒕 𝒐𝒇 𝑫𝒆𝒑𝒓𝒆𝒄𝒊𝒂𝒃𝒍𝒆 𝑩𝒐𝒊𝒍𝒆𝒓 = ⁄𝒅𝒂𝒚
𝑘𝑔 𝑠𝑡𝑒𝑎𝑚 1 𝑑𝑎𝑦
𝑆𝑡𝑒𝑎𝑚 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 = (9,802.12 )( )
𝑑𝑎𝑦 86400 𝑠𝑒𝑐
𝑘𝑔 𝑠𝑡𝑒𝑎𝑚⁄
= 0.1135 𝑠𝑒𝑐
𝑘𝑔 𝑠𝑡𝑒𝑎𝑚
1 𝐵𝑜𝑖𝑙𝑒𝑟 𝐻𝑜𝑟𝑠𝑒𝑝𝑜𝑤𝑒𝑟 = 𝑒𝑛𝑒𝑟𝑔𝑦 𝑛𝑒𝑒𝑑𝑒𝑑 𝑟𝑜 𝑝𝑟𝑜𝑑𝑢𝑐𝑒 15.65
ℎ𝑟
369
Hence,
𝑃ℎ𝑝 0.66
𝑆𝑡𝑒𝑎𝑚 𝐶𝑜𝑠𝑡 = ⁄𝑘𝑔 𝑠𝑡𝑒𝑎𝑚
Therefore,
370
SUMMARY OF FIGURES USED IN SCHEDULE N-3
STEAM
Water Price for Industrial Use Php 43.20/ cu. m
Total Steam Requirement for Processes 9802.58kg/day
Density of Water 1000 kg/ cu. m
Mass Unit Conversion Factor 2.2 lb/kg
Time Unit Conversion Factor 24 hours/day
Steam Cost per day Php6469.71
Steam Capacity 900lb/hr
Purchased Cost of Boiler for 900 lb/hr and 265 psi $11,408.98
Recovery Period for Industrial Steam Generation 22 years
Annual Days of Operation 270 days/year
371
XXVI. EXHIBIT AA-1
372
XXVII. SCHEDULE AA – 5
operating condition of the manufacturing plant. It includes the cost for labor,
6% (Purchased Equipment Delivered) from Peters and Timmerhaus 5th Ed., Table
6-18, p. 273
𝑃ℎ𝑝 8.58
𝑀𝑎𝑖𝑛𝑡𝑒𝑛𝑎𝑛𝑐𝑒 𝑎𝑛𝑑 𝑅𝑒𝑝𝑎𝑖𝑟 = ⁄𝑘𝑔 𝑐𝑜𝑙𝑙𝑎𝑔𝑒𝑛
373
SUMMARY OF FIGURES IN SCHEDULE AA-5
374
XXVIII. SCHEDULE AA – 6
A. Operating supplies
Operating supplies are those miscellaneous items that cannot be considered
as raw materials or maintenance and repairs materials but are necessary to keep the
process functionality efficient. These include items such as charts, lubricants, test
15% (Maintenance and Repair) from Peters and Timmerhaus 5th Ed., Table 6-18,
p. 273
𝑃ℎ𝑝 8.58
𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑆𝑢𝑝𝑝𝑙𝑖𝑒𝑠 = 0.15 ( )
𝑘𝑔 𝑐𝑜𝑙𝑙𝑎𝑔𝑒𝑛
𝑃ℎ𝑝 1.29
𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑆𝑢𝑝𝑝𝑙𝑖𝑒𝑠 = ⁄𝑘𝑔 𝑐𝑜𝑙𝑙𝑎𝑔𝑒𝑛
375
SUMMARY OF FIGURES USED IN SCHEDULE AA-6
376
XXIX. SCHEDULE AA-7
Laboratory charges
Laboratory charges are the costs of various laboratory tests for control
operating labor.
15% (Operating Labor) from Peters and Timmerhaus 5th Ed., Table 6-18, p.
273.
𝑃ℎ𝑝 24.08
𝐿𝑎𝑏𝑜𝑟𝑎𝑡𝑜𝑟𝑦 𝐶ℎ𝑎𝑟𝑔𝑒𝑠 = 0.15 ( )
𝑘𝑔 𝑐𝑜𝑙𝑎𝑔𝑒𝑛
𝑃ℎ𝑝 3.62
𝐿𝑎𝑏𝑜𝑟𝑎𝑡𝑜𝑟𝑦 𝐶ℎ𝑎𝑟𝑔𝑒𝑠 =
𝑘𝑔 𝑐𝑜𝑙𝑙𝑎𝑔𝑒𝑛
377
SUMMARY OF FIGURES USED IN SCHEDULE AA-7
378
XXX. EXHIBIT-BB
Fixed charges
Fixed charges are expenses which are always incorporated in an industrial plant
whether or not the manufacturing process is in operation. These expenses are direct
function of the capital investment. These include costs for depreciation, local
379
Cost (Php)/kg collagen Schedule
Depreciation Php 11.92 BB-1
Local Taxes Php 3.58 BB-2
Insurance Php 1.00 BB-3
Total Fixed Charges Php 16.49
380
XXXI. SCHEDULE BB-1
Depreciation
throughout the usual life of the material. Depreciation rates are very important in
𝐷𝑒𝑝𝑟𝑒𝑐𝑖𝑎𝑡𝑖𝑜𝑛
𝑃ℎ𝑝 11.92
𝐷𝑒𝑝𝑟𝑒𝑐𝑖𝑎𝑡𝑖𝑜𝑛 = ⁄𝑘𝑔 𝑐𝑜𝑙𝑙𝑎𝑔𝑒𝑛
381
SUMMARY OF FIGURES USED IN SCHEDULE BB-1
382
XXXII. SCHEDULE BB-2
Local taxes
the plant and the regional laws. Annual property taxes for plants in highly populated
areas are ordinarily in the range of 1%-4% of the fixed capital investment.
2.5% (Purchased Equipment Delivered) from Peters and Timmerhaus 5th Ed.,
𝑃ℎ𝑝 3.58
𝐿𝑜𝑐𝑎𝑙 𝑇𝑎𝑥𝑒𝑠 = ⁄𝑘𝑔 𝑐𝑜𝑙𝑙𝑎𝑔𝑒𝑛
383
SUMMARY OF FIGURES USED IN SCHEDULE BB-2
384
XXXIII. SCHEDULE BB-3
Insurance
Insurance rates are independent on the type of process being carried out in
These rates amount to about 0.7% of the fixed capital investment per year.
0.70% (Purchased Equipment Delivered) from Peters and Timmerhaus 5th Ed.,
𝑃ℎ𝑝 1.00
𝐼𝑛𝑠𝑢𝑟𝑎𝑛𝑐𝑒 = ⁄𝑘𝑔 𝑐𝑜𝑙𝑙𝑎𝑔𝑒𝑛
385
SUMMARY OF FIGURES USED IN SCHEDULE BB-3
386
XXXIV. EXHIBIT CC
Plant overhead cost covers expenditures required for routine plant services
but is necessary for many of the general plant services such as non-manufacturing
machinery, equipment, and building, the fixed charges and the direct costs for these
items, and all the labor cost directly connected to production operation. The plant
overhead cost may range from 50%-70% of the total costs for operating labor, direct
60% (Operating Labor + Direct Supervisory & Clerical Labor + Maintenance &
Repair) from Peters and Timmerhaus 5th Ed., Table 6-18, p. 274.
= 0.60(𝑂𝑝𝑒𝑟𝑎𝑖𝑛𝑔 𝐿𝑎𝑏𝑜𝑟
𝑃ℎ𝑝 21.77
𝐼𝑛𝑠𝑢𝑟𝑎𝑛𝑐𝑒 = ⁄𝑘𝑔 𝑐𝑜𝑙𝑙𝑎𝑔𝑒𝑛
387
SUMMARY OF FIGURES USED IN SCHEDULE CC
388
XXXV. EXHIBIT DD
General Expenses
expenses, and (3) research and development expenses. General expenses may
389
SUMMARY OF GENERAL EXPENSES
Cost (Php)/
Schedule
kg Collagen
Administrative Cost Php 7.26 DD-1
Distribution and Marketing Cost Php 31.74 DD-2
Research and Development Cost Php 14.43 DD-3
390
XXXVI. SCHEDULE DD-1
Administrative Cost
administrative activities. These covers the salaries and wages for administrators,
secretaries, accountants, and other similar workers, along with cost for office
20% (OL+DS&CL+M&R) from Peters and Timmerhaus 5th Ed., Table 6-18, p.
274.
𝐴𝑑𝑚𝑖𝑛𝑖𝑠𝑡𝑟𝑎𝑡𝑖𝑣𝑒 𝐶𝑜𝑠𝑡
= 0.20(𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝐿𝑎𝑏𝑜𝑟
𝑃ℎ𝑝 7.26
𝐴𝑑𝑚𝑖𝑛𝑖𝑠𝑡𝑟𝑎𝑡𝑖𝑣𝑒 𝐶𝑜𝑠𝑡 = ⁄𝑘𝑔 𝐶𝑜𝑙𝑙𝑎𝑔𝑒𝑛
391
SUMMARY OF FIGURES USED IN SCHEDULE DD-1
392
XXXVII. SCHEDULE DD-2
selling and distributing the finish products. These expenses vary widely from
different types of plants depending on the particular material being produced, other
product sold by the company, plant location, and company policies. These costs
11% (Total Product Cost) from Peters and Timmerhaus 5th Ed., Table 6-18, p. 274.
𝐺𝑒𝑛𝑒𝑟𝑎𝑙 𝐸𝑥𝑝𝑒𝑛𝑠𝑒𝑠
+ [𝐴𝑑𝑚𝑖𝑛𝑖𝑠𝑡𝑟𝑎𝑡𝑖𝑣𝑒 𝐶𝑜𝑠𝑡
393
𝑇𝑜𝑡𝑎𝑙 𝑃𝑟𝑜𝑑𝑢𝑐𝑡 𝐶𝑜𝑠𝑡(𝑇𝑃𝐶)
𝑃ℎ𝑝 288.57
𝑇𝑜𝑡𝑎𝑙 𝑃𝑟𝑜𝑑𝑢𝑐𝑡 𝐶𝑜𝑠𝑡 (𝑇𝑃𝐶) =
𝑘𝑔 𝑐𝑜𝑙𝑙𝑎𝑔𝑒𝑛
𝑃ℎ𝑝 288.57
𝐷𝑖𝑠𝑡𝑟𝑖𝑏𝑢𝑡𝑖𝑜𝑛 𝑎𝑛𝑑 𝑀𝑎𝑟𝑘𝑒𝑡𝑖𝑛𝑔 = 0.11 ( )
𝑘𝑔 𝑐𝑜𝑙𝑙𝑎𝑔𝑒𝑛
𝑃ℎ𝑝 31.74
𝐷𝑖𝑠𝑡𝑟𝑖𝑏𝑢𝑡𝑖𝑜𝑛 𝑎𝑛𝑑 𝑀𝑎𝑟𝑘𝑒𝑡𝑖𝑛𝑔 =
𝑘𝑔 𝑐𝑜𝑙𝑙𝑎𝑔𝑒𝑛
394
SUMMARY OF FIGURES USED IN SCHEDULE DD-2
395
XXXVIII. SCHEDULE DD-3
prevent from being overtaken by competitors, they allot a certain amount for
research and development expenses. These encompass salaries and wages for all
personnel directly connected with this type of work, fixed and operating expenses
for all machinery and equipment involved, cost for materials and supplies, direct
0.05% (Total Product Cost) from P&T 5th Ed., Table 6-18, p. 274.
𝑃ℎ𝑝 288.57
𝑅𝑒𝑠𝑒𝑎𝑟𝑐ℎ 𝑎𝑛𝑑 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 = 0.05 ( )
𝑘𝑔 𝑐𝑜𝑙𝑙𝑎𝑔𝑒𝑛
𝑃ℎ𝑝 14.43
𝑅𝑒𝑠𝑒𝑎𝑟𝑐ℎ 𝑎𝑛𝑑 𝐷𝑒𝑣𝑒𝑙𝑜𝑝𝑚𝑒𝑛𝑡 =
𝑘𝑔 𝑐𝑜𝑙𝑎𝑔𝑒𝑛
396
SUMMARY OF FIGURES USED IN SCHEDULE DD-3
397