BROAD STATUS OF THERMAL POWER PROJECTS IN MAHARASHTRA

Sl. Capacity Commissioning Schedule Critical


No. PROJECT DETAILS (MW) Original Actual(A) / As Broad Status Areas
now Expected
Syn. COD Syn. COD
PROJECTS INCLUDED IN 11TH PLAN
I. PROJECTS COMMISSIONED
1. Paras TPP Expn.* 250
(Distt. Akola) Unit synchronized on 31.5.07.
MSPGCL Coal Firing completed on 18.10.07.
Unit is under shut down
w.e.f.11.02.08 to 21.02.08 for
interlinking.Full load operation
Uni-1* 250 11/06 01/07 05/07(A) 03/08(A) completed on10.03.08. Third mill is
expected to be ready by last week of
March08. COD achieved on 31.03.08..
Date of TEC : 13.06.2003
Date of Appl. by State Govt. : 9.9.2003
Org.Est.Proj.Cost : Rs. 102670lakhs
Latest Cost of Proj. : Rs. 146840akhs
Exp. Upto 03/06 : Rs.6459.04 lakhs
Exp. During 06-07(upto3/07) : Rs 44103 lakhs
Exp.During 7-08((Upto 7/07) : Rs.1788 lakhs
Cumulative Exp.(01/08) : Rs. 132856 Lakhs
Type of fuel :Coal
Financial closure : Achieved on Jan.04
Equity: GOMaharashtra Rs. 190.24
Crs.Loan: PFC Rs. 820 Crs.
Date of Main Plant Order : M/S BHEL on 25.5.04 (BTG)
* Slipped from 10TH Plan

II PROJECTS UNDER CONSTRUCTION

STATE SECTOR
1. New Parli TPP 250 1. Consultant appointed on 12.09.06. Supply of
(Distt. Beed) 2. All required clearances are available. Boiler & TG
MSPGCL 3. Financial closure achieved on 3.01.06. material.
4. The order for Civil Foundation is
Uni-2 250 04/09 06/09 04/09 06/09 placed on M/s Metcon on 16.3.07.
5. Orders of BOP packages are in
Date of TEC : Not Required progress.
Date of Approval by State : 12.05.06 Boiler
Govt. 1. MSPGCL have handed over Boiler
Est.Proj. cost. : 109100 Lakhs front to BHEL on 22.8.07.
Exp. Upto 03/08 : Rs.24038 Lakhs 2. Out of total 16661MT Boiler & ESP
material 10688MT received at site
Exp. During 08-09 : Rs. - Lakhs
and 589MT erected upto 01/08.
(Upto 04/08) 3. Boiler erection started on17.10.07.
Type of fuel :Coal 4. Boiler drum lifting is now expected
in 05/08.
Financial closure : Achieved on 3/06
Equity : GO Maharashtra Rs218 TG
Crs.Loan : PFC Rs. 830Crs. 1. Supply of TG materials started at site.

Date of Main Plant Order : M/S BHEL on 31.08.06 (BTG


+Electrical)
Sl. Capacity Commissioning Schedule Critical
No. PROJECT DETAILS (MW) Original Actual(A) / As Broad Status Areas
now Expected
Syn. COD Syn. COD
2. Paras TPS Expansion Availability
(Distt. Akola) 250 1. Consultant appointed on 12.09.06. of high boom
MSPGCL 2. All required clearances are available. crane(350T).
3. Financial closure achieved on 7.02.06.
4. The order for Civil Foundation is
placed on M/s Pratibha, Kolhapur on
Uni-2 250 06/09 08/09 06/09 08/09 10.4.07.
5. Orders of BOP packages are in
Date of TEC : Not Required progress.
Date of Approval by State : 12.05.06 Boiler
Govt. 1. MSPGCL have handed over Boiler
Est.Proj. cost. : 122400 Lakhs front to BHEL on 25.8.07.
Exp. Upto 03/08 : Rs.20412Lakhs 2. Out of total 16661MT Boiler & ESP
Exp. During 08-09 : Rs. - Lakhs material 10290MT received at site and
1000MT erected upto 01/08.
(Upto 04/08) 3. Boiler erection started on 14.9.07.
Type of fuel : Coal 4. Boiler drum lifting is now expected in
04/08.
Financial closure : Achieved in 3/06
Equity : GO Maharashtra Rs245 crs.
Loan : PFC Rs. 888Crs.
Date of Main Plant Order : M/S BHEL on 31.08.06 (BTG
+Electrical)

3. Khaperkheda TPS 1. Consultant appointed on 15.12.05. Boiler


Expansion Project 500 2. All required clearances are available. erection not
(Distt. Nagpur) 3. Financial closure achieved on yet started for
MSPGCL 26.05.06. want of
4. Design & Engg. is in progress. sequential
Unit - 1 500 03/10 06/10 03/10 06/10 5. Orders for all BOPs on EPC basis material.
placed on M/s BGR on 03.07.07.
Date of TEC : Not Required 6. Civil works in Boiler & ESP area are
Date of Approval by State : 12.05.06 in progress.
Govt. 7. 3039MT Boiler & ESP material
Est.Proj. cost. : 217000 Lakhs received at site upto 01/08.

Exp. Upto 03/08 : Rs.15072 Lakhs


Exp. During 08-09 : Rs. - Lakhs
(Upto 04/08)
Type of fuel :Coal
Financial closure : Achieved on 26.05.06
Equity : GO Maharashtra Rs434 crs
Loan : PFC Rs. 1753Crs..
Date of Main Plant Order : M/S BHEL on 23.01.07
(BTG +Electrical)
Sl. Capacity Commissioning Schedule Critical
No. PROJECT DETAILS (MW) Original Actual(A) / As Broad Status Areas
now Expected
Syn. COD Syn. COD
4. Bhusawal TPS 1000 1. Consultant appointed on 01.04.06.
Expansion Project 2. All required clearances are available.
(Distt. Bhusawal) 3. Financial closure achieved on 27.07.06.
MSPGCL 4. Design & Engg. is in progress.
Uni-1 500 05/10 08/10 05/10 08/10 5. Orders for all BOPs on EPC basis are
placed on M/s TPL on 05.11.07.
Uni-2 500 09/10 12/10 09/10 12/10 6. Preliminary work for land development
is in progress.
7. Supply for construction work is in
Date of TEC : Not Required progress.
Date of Approval by State : 12.05.06 8. Civil works in Boiler area started.
Govt. 9. 3200MT Boiler & ESP material
Est.Proj. cost. : 412400 Lakhs supplied at site upto 02/08.
Exp. Upto 03/08 : Rs. 19645 Lakhs
Exp. During 08-9 : Rs - Lakhs
(Upto 04/08)
Type of fuel :Coal
Financial closure : Achieved on 27.07.06
Equity : GO Maharashtra Rs825
crs. Loan : PFC Rs. 3693Crs.
Date of Main Plant Order : M/S BHEL on 23.01.07
(BTG +Electrical)
PRIVATE SECTOR
1. TrombayTPS Extension 250 1. All required clearances are available.
(Distt. Mumbai) 2. Zero date of the project is 5th June06.
TPCL 3. Chimney shell completed upto 220
metre.
4. Work on all the BOPs is progressing
Unit - 8 250 08/08 10/08 08/08 10/08 as per schedule.
Boiler
Date of TEC : Not Required 1. Out of total 10900MT boiler material
Date of Approval by State : N.A. 6027MT received & 2550MT erected
Govt. upto 8/07.
Original Est. cost. : Rs. 99000 lakhs 2. Boiler erection started on 01.01.07.
Latest Cost : Rs.106600 Lakhs 3. Boiler Drum lifted on 14.6.07.
Exp. Upto 03/07 : Rs. 9900 Lakhs 4. Boiler HT completed in 02/08.
5. Boiler Light Up is expected in 06/08.
Budget Estimate 07-08 : N.A.
TG
Exp. During 07-08 : Rs.48700 Lakhs.
1. Condenser erection started in 9/07.
(Upto 01/08) 2. TG erection started in 9/07.
Type of fuel : Imported Coal (very low 3. TG Box Up is expected in 06/08
Sulphur & Ash content)
Financial closure : 27.9.06
Date of Main Plant Order : M/S BHEL on 05.06.06 (EPC
Basis)
Sl. Capacity Commissioning Schedule Critical
No. PROJECT DETAILS (MW) Original Actual(A) / As Broad Status Areas
now Expected
Syn. COD Syn. COD
1. JSW Energy( Ratnagiri) 1200 1. All required clearances are available.
Limited, TPP at Jaigad 2. Zero date of the project is 10.05.07.
(Distt. Ratnagiri) 3. Order for Chimney & NDCT already
JSW Energy( Ratnagiri) placed.
Limited 4. Order placement for other BOPs is in
progress.
Unit - 1 300 06/10 08/10 06/10 08/10 5. Mega Power status is yet to be
Unit - 2 300 09/10 11/10 09/10 11/10 received.
Unit - 3 300 12/10 02/11 12/10 02/11 6. Excavation for chimney # 1&2 is in
Unit - 4 300 03/11 05/11 03/11 05/11 progress.
7. Civil works started in IDCT.
Date of TEC : Not Required 8. Structural fabrication is in progress.
Date of Approval by State : N.A. 9. Site Grading 95000 cubic metre out of
Govt. 224000 cubic metres completed.
Original Est. cost. : Rs- 450000 Lakhs 10. Work on chimney is in progress.
11. Boiler & TG foundations are in
Latest Cost : Rs. 450000 Lakhs progress.
Exp. Upto 03/07 : Rs. Nil
Exp. During 07-08 : Rs. 41800 Lakhs.
(Upto 01/08)
Type of fuel : Imported Coal (very low
Sulphur & Ash content)
Financial closure : Achieved on 02.08.07
Date of Main Plant Order : M/sShanghai Electric Power
Generation Company, China on
10.05.07 (BTG) under –ICB route

III PROJECTS WHERE CONSTRUCTION IS YET TO START


Nil