Escolar Documentos
Profissional Documentos
Cultura Documentos
INSPECTION LOCATION:
J-NEAK GLOBAL SERVICES
CROSS RIVER STATE NIGERIA PROPOSED REDEEMED
CHRISTIAN CHURCH OF GOD (R.C.C.G). MISSION HOUSE
CONSTRUCTION SITE.
WRITTEN BY
NEBOSH IGC DELEGATE:
AKPAKPAN, NSIKAK EYO
STUDENT NO: 00435766
SUMMITED TO:
NEBOSH TRAINING SERVICE PROVIDER
NOVELLE INNOVATION CENTER.
RIVERS STATE, NIGERIA.
TABLE OF CONTENTS
1.1 Introduction - - - - - 1
1.4 Conclusions - - - -- 9
1.5 Recommendations - - - - - 10 - 12
Declaration
1.1 Introduction
This inspection was carried out at a construction site operated by J-Neak Global
services, a large indigenous construction company/ maintenance agent in Nigeria.
They are undertaking a refurbishment project to a large storey building that has now
being redesigned as a Redeemed Christian church of God (RCCG) Mission House for
the provincial level. The site consists of the main building with a courtyard area at its
back, a car park slot, gate house, a comparatively large yard area adjacent to its
north facing elevation and a minor highway to the south facing elevation the building
entrance. The east facing elevation adjoin the fence of a private house entrance
while the west facing elevations adjoins a public footpaths, an installed jetty to NNPC
(Nigeria National petroleum cooperation) deport oil pipelines for vessel. The yard is a
busy area, in that it is used to receive deliveries, accommodate store plants and
machinery. J-Neak global services project and site management team have a metal
storage unit on site, well equipped welfare facilities for both workers, contractors
and subcontractors. The work environment has been maintained such that it is clean
and in a safe condition as ILO C120, 1964 Article 7; All premises used by workers and
the equipment of such premise , shall be properly maintained and kept clean.
At the time of my visit (according to the site signing-in log) there were 25
operatives on the project working for 4 different subcontractors. There are currently
a number of activities being carried out including Mechanical and Electrical
installation, scaffolding installation, Steel work and the roof spray painting, Ground
works and Demolition, but clearly the nature of the project means that there are
ongoing changes in the nature and scope of the works and a high degree of
complexity was seen.
1.2 Executive Summary
Having completed the inspection and after discussions with the J-Neak Global
services management team it was evident that although there were a number of
issues in terms of health and safety, some more significant than others, the issues
could all be resolved given time, effort and adequate resource. J-Neak Global
services manages the Work Environment and Facilities Code of Practice 2011, 1.3
Maintaining the work environment and facilities, Floors and other surfaces are
designed, installed, and maintained to allow work to be carried out without risk to
health and safety. Doing this would certainly increase compliance with current
legislation and crucially protect the workforce from harm in what is a complex and
potentially dangerous work environment. It was also clear that J-Neak Global
Services take a conscientious and proactive approach to health and safety matters
and are acutely aware of how exposed they might be if they do not work to
continuously improve standards with regards to site safety and welfare. Health and
safety at construction sites deals with both physical and psychological well-being of
workers on construction sites and other persons whose health is likely to be
adversely affected by construction activities. The principal contractor has managed
the risks to health and safety associated with the storage, movement, and disposal of
construction materials and waste at the workplace. Work Health and Safety
Regulation 2011 s.315
J-Neak Global Services didn’t Set up a scaffold on level, compacted soil at a safe
distance from exposed pipelines before job execution hereby endangers ILO
Recommendation R171. (1985). B11A; Health assessment of workers before their
assignment to specific tasks which may involve danger to their health or that of
others. A proper scaffold must have guardrails on all platforms, have platforms that
are fully installed, and have all required components installed (base plates, mudsills,
braces, coupling devices, etc.).
The recommendation results set out, coupled with robust monitoring systems and a
proactive supervisory approach will address the issues in the report and set a
benchmark for future performance and continuous improvement, hopefully creating
a more positive atmosphere and culture on the site.
1.3 Main findings of the inspection
As a company J-Neak Global services are performing well despite in the construction
sector over the past few years, but in this year they have secured much larger and
considerably more complex projects and the infrastructure of the business appears
to be struggling to keep up with this level of expansion. As a result it would appear
that the management of health and safety has been compromised and my visit has
shown that a number of hazards are present and that the management systems in
place are not currently robust enough. The main areas of concern are as follows:
(b) Recorded the significant findings of that risk assessment as soon as is practicable
after the risk assessment is made; and
Recognised, certificated The cost of the course together This is a high 1 month from date
training to be provided for site with temporary replacement for priority of report
workers example banksmen/ the operatives concerned
yard operative(s) and masons. should be less than #500,000
Pedestrian segregation to The main costs here will be This action is a 1 week from date
be put in place using labour and coupled with the very high priority as of report
physical barriers, hire or purchase of barriers, and it is required for
appropriate signage and cost of paint and signage should compliance and
floor marking be around #200,000 there is significant
risk if no action
A more effective system This can cost only but hiring of This is a high
for monitoring and competent firm for health and priority because it
supervising activities and safety briefings, inductions and is a way to raise
a more robust workplace more toolbox meeting and standards and then 1 day from date of
inspection programme programs on monthly basis. maintain and report.
required further develop
them. Without this
there will be a
continued decline
Procurement of good scaffolds The cost of ladder is #80,000
and ladders for suitability
At most 5 pieces of good
purpose, Every ladder must be 1 week - 1 month
ladders should cost # 400,000 This action is a
secured and safely positioned at from the date of
very high priority
the correct angle. Before a ladder A good scaffolding companies report
is used, it must be inspected for takes #150,000 for a good
damaged parts, including hinges, tubular scaffold with handrail,
rungs or steps, side rails, and foot panel and standard
feet. Side rails should extend at installation in calabar where the
least 900 mm (3 ft) above the site is located.
landing and be secured at the
top.
Sheet number 1 of 10
Place inspected: J-Neak Global Services (Nigeria Limited) Date of inspection 17/05/2018
1. Fall from Height (Physical Hazards) I. Adjust Equipment to suit worker. Immediately (1 day)
Falls from height can result to death L. Creation/Construction of fall arresting 3 weeks – 4 weeks
or injury that may cause disorder platform & installation of hand rails on
scaffolds (edge protection)
2. Risk of Trip due to the unsheeted I. Erect warning sign and barrier off Immediately (2-10min)
brittle roof which the work is done around area affected.
15m above the floor and the
spraying machine platform.
L. Repair/Resurface footpath
1 month
3. Slips (risk) on paint spillage found on I. Resurface footpath by quick cleanup. 2 days
scaffold top panel
4. Risk of fire outbreak due to the I. Isolate all ignition processes around. 7 days
inflammable chemical composition of
marine paint used for the top roof
spray on already installed aluminium
L. Erect suitable fire alarms to detect 4 months
sheets.
oxygen (atmospheric rich zone and
depletion)
GC3 – THE HEALTH AND Candidate’s observation
Place inspected J-Neak Global Services (Nigeria Limited) __ Date of inspection 17 /05 / 2018
5. Risk of tripping due to damaged I. Sand filling of the affected area 1 day
concrete floor at the main entrance
of the building.
8. The risk of Electric shock due to the I. The use of marking and caution band 1 – 2 days
exposed damaged cable. for restriction at affected area.
This can cause death or fatal injuries L. Placement of Protection guard rails to
avoid contact with electrical lines and 1 month
replacement of damage cables.
GC3 – THE HEALTH AND Candidate’s observation sheet
Place inspected J-Neak Global Services (Nigeria Limited) Date of inspection 18 /05 / 2018
10. Risk of having fall of object from the I. Barricades the working Area 1 day
workers above.
Risk of working with powered I. Restricting access to the area 2 days (immediately)
equipment that are not properly
grounded (earth).
12.Pressurized containers (spray I. Cordon off the area and put up 1 – 7 days
machine cylinder). Danger or it should be removed.
Sheet number 4 of 10
Place inspected J-Neak Global Services (Nigeria Limited) Date of inspection 18 /05 / 2018
14. Poor Manual Handling I. Avoid, minimize or reduce load weight. Immediately
So far as it is reasonably practicable.
15. Scaffold install without guard rails & I. The use of PPE e.g Hard hat/safety 1 day
toe boards. boots and restriction to affected zone.
7 days
16. Risk of having silica dust in I. The use of competent person with PPE 1 day
demolition processes. used for dusty task.
17.Risk of releasing toxic solvent, I. The use of competent person with PPE 3 days
gases, fumes during paint spraying used for dusty task.
and the use of adhesive or thinner.
18. The risk of Asbestos due to I. The use of glove bag techniques and 1 day
demolition of fire resistant walls. thorough cleaning of the affected
area.
This can result to asbestosis diffuse
fibrosis of the lung or mesothelioma L. The removal of the materials by a 2 months
(cancer of the lining of the chest competent person before demolition
and abdomen) continues.
GC3 – THE HEALTH AND Candidate’s observation sheet
Place inspected J-Neak Global Services (Nigeria Limited) Date of inspection 19 /05 / 2018
The risk of carpal tunnel syndrome I. Top exposure to unfit portable devices Immediately
due to usage of portable hand tools
e.g drilling machine (A long term
exposure)
L. Regular maintenance of machine to 1 – 3 weeks
This can result to permanent avoid whole body vibration hazards
damage to nerves and loss of the and the procurement of up to date
sense of touch and dexterity. machines.
20. Hot work e.g welding activities in I. The use of PPE and a competent 1 – 3 days
the site. person.
21. Risk of delayed first aid treatment I. Supervision, Training and proper 1 – 3 hours
due to oil (pipeline) contamination instruction at intervals.
in drinking facilities .
L. Provision of First Aid unit at close
This can cause occupation health range and water filtration 3 months
illness (disease) & death. equipments.
22. Risk of ankle sprain due to poor I. Install make foot part panel. 1 week
posture while spraying the roof.
L. Move more excessive material away
This can result to disorder, fall and from access.
even death. 3 months
23. The risk of fire outbreak from I. Apply yellow/red paint markings/ 1 day
exposed oil pipeline due to missing caution.
warning signage.
Place inspected J-Neak Global Services (Nigeria Limited) Date of inspection 19 /05 / 2018
24. Risk of vehicle over speeding and I. Inform workers at site and contractors 1 day (immediately)
causing road traffic accidents due to speed limit on a minor highway.
poor signage at bend corners.
25. The risk of slip due to the sloppy I. Barrier off around affected area and 2 – 4 days
landing outside the work area by increase warning signs.
the west towards the entrance.
L. Monitoring and maintain the site
This can lead to injuries, death. condition of all footpaths on site Quarterly
during inspection.
26. The risk of Cement dust (chemical) I. The use of suppression techniques. 3 weeks
can lead to occupational asthma,
dermatitis.
L. Installation of LEV (Local Exhaust 3 months
Ventilation) and dust lamps or
monitors.
28. Risk of Eye and face injury due to I. Used of visor should be enforced. Immediately
operators and tillers not wearing
visor provided.
L. Training on use of PPE for all site 3 weeks
workers.
GC3 – The Health and Safety Practical Application
I declare that the work submitted for this practical application assessment ie. the completed observation sheets and the
report to management, is my own work. I recognise that contravention of this statement constitutes malpractice and may
result in my being subject to the penalties set out in the NEBOSH Malpractice policy.
Signature
Date 19/05/2018
I declare that the work marked is identical to that received from the candidate. I recognise that contravention of this
statement constitutes malpractice and may result in my being subject to the penalties set out in the NEBOSH Malpractice
policy.
Signature _______________________________
Date _______________________________
I declare that I have marked this work and am both qualified and approved by NEBOSH to do so. I recognise that
contravention of this statement constitutes malpractice and may result in my being subject to the penalties set out in the
NEBOSH Malpractice policy.
Signature _______________________________
Date _______________________________
NB: This declaration must be completed in full, submitted and retained with the candidate’s
script. If this declaration is not submitted the candidate’s result may be declared void.