Microtunnelling and Pipejacking


The Herrenknecht Range and Reference Projects
Presented by Ben Hayes

Herrenknecht AG 2013. - The Herrenknecht Company.


Herrenknecht.
Milestones of the company history.

Office and Complete Assembly Total output of


assembly plant product range in China 1.013 bn € 35 years
in Schwanau TBM (Guangzhou) 3,632 employees of Herrenknecht
1980 1999 2005 2008 2012

1977 1998 2002 2011 2014


Foundation of Conversion of Market leader in Final breakthrough at World‘s largest
Herrenknecht GmbH in AG mechanized tunnelling Gotthard Base Tunnel TBM for Hong
GmbH technology Kong, Ø 17.6m

Herrenknecht. Pioneering Underground Technologies


HERRENKNECHT
IN SCHWANAU

} Founded in 1977
} Conversion to Herrenknecht AG in 1998
} Today around 4,800 employees worldwide, 2,000 in Schwanau,
Herrenknecht.
around 200Pioneering
youngUnderground Technologies
people in training
Herrenknecht Group.
Company figures.
} Total output in million Euro } Sales in million Euro

Herrenknecht. Pioneering Underground Technologies


Herrenknecht Group.
Company figures.
} Employees* } Trainees

* Without trainees, including temporary staff

Herrenknecht. Pioneering Underground Technologies


Herrenknecht worldwide.
Subsidiaries and agents.

Russia
UK
Canada Germany Ukraine
Netherlands
Switzerland
USA France Italy
Spain Azerbaijan China
Iran
Mexico
Qatar UAE
Saudi Thailand
Venezuela Arabia
India
Panama Malaysia
Colombia Singapore

Brazil

Australia

Argentina
Chile
Subsidiary
Agent

Herrenknecht. Pioneering Underground Technologies


Herrenknecht Group.
Brands and business areas.

Corporate
Brand

Core
Markets

Core
Brands

Additional Equipment Additional Equipment Additional Equipment

Group
Brands

Services Services Services

Herrenknecht. Pioneering Underground Technologies


Herrenknecht Tunnelling.
Utility Tunnelling – Business Segments.

} Utility Tunnels & Shafts } Pipeline } Energy


} Machine range Ø < 4.2m.

Partial-face
AVN & AVND EPB Shield Gripper TBM Single Shield Double Shield
Excavation Machine

Auger Boring Machine HDD Rig Direct Pipe® VSM


Pipe Express®

Herrenknecht. Pioneering Underground Technologies


Pipe Jacking Jobsite.

Herrenknecht. Pioneering Underground Technologies


Basic Procedure of Pipe Jacking

Herrenknecht. Pioneering Underground Technologies


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Machine Types For Microtunnelling (Pipe Jacking)

Open Face Closed Face

MH AVN

TBM AVND

Guided
EPB
Auger

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Drive Length and Diameter


Machine Type Diameter Range Maximum Drive
Length
MH DN1700 – DN2500 800m
TBM > DN1200 200m
Guided Auger < DN1200 100m
AVN DN300 – DN800 150m
AVN DN800 – DN1200 200m
AVN DN1200 500m
AVN DN1500 800m
AVN DN1600 – DN3600 1000m +
EPB DN1500 – DN3600 800m

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Open Face Shield


Herrenknecht MH Series

Open Shield For Rock Open Shield For Soft Ground

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

The Open Face Shield Machine


Herrenknecht MH Series

ü û
nRelatively low cost nDifficult when significant
nEasy to operate water ingress present.

nEasy to maintain nDangerous in unstable


ground conditions.
nEasy initial set up
nRelatively slow excavation
process.
nDifficult to deal with mixed
ground conditions.

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Open Excavation System


Herrenknecht TBM Series

The Shield The Conveyor Hopper

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

The TBM Site Set Up

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

The Open Excavation System


Herrenknecht TBM Series

ü û
nRelatively low cost nCan only be used in dry
nSafe remote controlled ground conditions.
operation nAny running ground
nEasy initial set up due to conditions can prove
minimum back up equipment problematic.

nAble to cope with mixed nUse of skips is safety


ground conditions, including consideration.
very hard rock conditions.
nRapid excavation process

Herrenknecht AG 2013. - The Herrenknecht Company.


GUIDED AUGER BORING

Microtunneling / Guided auger boring

Microtunneling
Auger rigs with pilot

STRONG PARTNERS FOR SMALL DIAMETERS


GUIDED AUGER BORING

BM 150D piloting

STRONG PARTNERS FOR SMALL DIAMETERS


GUIDED AUGER BORING

First extension with casings

STRONG PARTNERS FOR SMALL DIAMETERS


GUIDED AUGER BORING

Jacking of product pipes

STRONG PARTNERS FOR SMALL DIAMETERS


GUIDED AUGER BORING

Alternative: Second extension

STRONG PARTNERS FOR SMALL DIAMETERS


GUIDED AUGER BORING
The Open Face Shield Machine
Guided Auger Systems

ü û
nLow investment nVery limited ground water.
nEasy to operate nLimited ground conditions,
nEasy to maintain displaceable soils only.

nEasy initial set up


nQuick and accurate
installation.

STRONG PARTNERS FOR SMALL DIAMETERS


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Closed Face Slurry System


Herrenknecht AVN Series

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

AVN General Arrangement

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

AVN Excavation Process

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

SPECIAL PIPE JACKING EQUIPMENT FEATURES TO ENSURE SUCCESS


Slurry & Hydro Shields Equipped with Cone Crusher

n Powerful cone crusher capable of crushing rocks to a pumpable size


n Reduced wear & tear on the cutting wheel
n Increased safety and higher production rates can be achieved
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

SPECIAL PIPE JACKING EQUIPMENT FEATURES TO ENSURE SUCCESS


Advanced Slurry Control in Excavation Chamber

n Via remote control the operator can select which slurry nozzles to use
depending on the soil conditions
n Increased safety and higher production rates can be achieved
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

SPECIAL PIPE JACKING EQUIPMENT FEATURES TO ENSURE SUCCESS


Medium and High Pressure Slurry Nozzles

n Additional medium pressure nozzles (up to 16 bar) and high pressure


nozzles (up to 300 bar) for increased advances rates in cohesive soil
conditions
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Closed Face Slurry System


Herrenknecht AVN Series

ü û
nSafe remote controlled nMore components for initial
operation set up
nFully closed continuous nSlurry management
excavation system. No skips.
nHigher maintenance in
nCan operate when ground abrasive ground conditions
water is present
nCan operate in all geologies
nLarger diameters can offer
compressed air working for
maintenance

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Closed Face Slurry System with


Compressed Air Face Support
Herrenknecht AVND Series

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

AVND General Arrangement

‘ Bubble Chamber’

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

AVND Excavation Process

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Closed Face Slurry System


Herrenknecht AVND Series

ü û
nSafe remote controlled nMore components for initial
operation set up
nFully closed continuous nSlurry management
excavation system. No skips.
nHigher maintenance in
nCan operate when ground abrasive ground conditions
water is present
nCan operate in all geologies
nAdded safety when
tunnelling under sensitive
areas.

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Closed Face Earth Pressure Balance


System
Herrenknecht EPB Series

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

EPB General Arrangement

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

EPB Excavation Process

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Application area of EPB technology.

Particle Size Distribution


Sieve Size
Silt Sand Gravel
Clay Fine Medium Coarse Fine Medium Coarse Fine Medium Coarse
100

90

80
Percentage Passing

70

60

50

40

30

20

10

0
0,001 0,002 0,006 0,02 0,06 0,2 0,6 2,0 6,0 20.0 60,0

Particle size in mm
Normally work without foam additives
Only possible with foam additives
Only possible with foam additives / no groundwater presence
Herrenknecht AG 2013. - The Herrenknecht Company.
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Closed Face Earth Pressure Balance


System
Herrenknecht EPB Series
ü û
nSafe remote controlled nUnable to operate
operation effectively in non cohesive
soil conditions
nNo slurry management
required nMaterial disposal can be
problematic
nCan operate when ground
water is present nUse of skips is safety
consideration.
nMost effective excavation
method in cohesive soils.
Clay.
nAdded safety when
tunnelling under sensitive
areas.

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Hybrid Systems

‘ EPB Screw ‘Fire Box’ and slurry


Conveyor’ by-pass
arrangement

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Fire Box and Slurry By-Pass System

Mode Change
Cylinder

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Cutting Wheels
Rock

Mixed Ground

Soft Ground

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Machine Choice Table

Rock Head

Mixed Head

Soft Ground
Head

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Limitations of Microtunnelling/Pipejacking
Europipe: 3.8m diameter.
2,535m total drive length. Sea Outfall.

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Diameter

Herrenknecht Standard Range


Largest Diameter
Extended AVND3000AB

Pipe Dimensions
3.6m ID
4.2m OD
3.0m Long

Approx. Weight
30 Metric Tons

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

WAN CHAI EAST AND NORTH POINT SEWERAGE TRUNK SEWERS.

CONTRACT NO. DC/2000/11.

Location: Hongkong

Client: DSD Drainage Services


Department

Customer: Fine Projects Ltd.

Geology: Hard Rock (max. 250MPa)

Machine: AVN 600|1200|1800

Tunnel length ID 600: 58m

Tunnel length ID 1200: 769m

Tunnel length ID 1800: 1750m


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

WAN CHAI EAST AND NORTH POINT SEWERAGE TRUNK SEWERS.

CONTRACT NO. DC/2000/11. ID1800mm DRIVES.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

WAN CHAI EAST AND NORTH POINT SEWERAGE TRUNK SEWERS.

JOBSITE IMPRESSIONS.

Breakthrough AVN 600


tunnel face in hard rock
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

WAN CHAI EAST AND NORTH POINT SEWERAGE TRUNK SEWERS.

JOBSITE IMPRESSIONS.

Machine handling and jobsite installation in dense city area


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

HYDRO POWER PLANT (HEPP) PROJECT IN AUSTRIA.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

HYDRO POWER PLANT (HEPP) PROJECT IN AUSTRIA.

PRESSURE WATER TUNNEL MAERZENBACH.

M-974M | HEPP Zillertal | Austria

AVN 1600 TB | OD 1970


Pipe: ID 1500 | Length: 4m
Geology: rock, chist,
quartz, approx. 170 MPA
Tunnel Length: 863m
Contractor: Mauracher Bau
GmbH
Launch of machine
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

HYDRO POWER PLANT (HEPP) PROJECT IN AUSTRIA.

PRESSURE WATER TUNNEL MAERZENBACH.


Altitude difference:
99.24m
Slope: 11,6 %
radius: 1.032m
5 interjacking
stations installed
OLC: Online Load
Control System
installed to prevent
local pipe overloads,
to build a high-
quality tunnel
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

HYDRO POWER PLANT (HEPP) PROJECT IN AUSTRIA.

INSTALLATION OF THE DISTANCE SENSORS .


Sensor 1/2: in jacking pipe no. 3
Sensor 3/4: in jacking pipe no. 30
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

HYDRO POWER PLANT (HEPP) PROJECT IN AUSTRIA.

INSTALLATION OF THE DISTANCE SENSORS .


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

HYDRO POWER PLANT (HEPP) PROJECT IN AUSTRIA.

RECOVERY OF THE MACHINE.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

AP LEI CHAU CABLE TUNNEL | THROUGH HARD ROCK | HONG KONG.

Location: Hongkong

Machine: AVN 1800 TB | OD 2150

Pipe: ID 1800 OD 2120

Tunnel length: 2 x 420m

Max. torque: 473kNm

Geology: ignimbrit, welded tuff

Compressive strength: max 411Mpa

Tensile strength: max 19.8Mpa

Chechar index: 5.6

Contractors: Fine Projects Ltd.,


China Complant
Development Ltd
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

AP LEI CHAU CABLE TUNNEL | THROUGH HARD ROCK | HONG KONG.

Facing tough hard rock conditions.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

AP LEI CHAU CABLE TUNNEL | THROUGH HARD ROCK | HONG KONG.

Hard rock cutterhead.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

AP LEI CHAU CABLE TUNNEL | THROUGH HARD ROCK | HONG KONG.

Tool replacement.
Tunnel face at 74m.
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

AP LEI CHAU CABLE TUNNEL | THROUGH HARD ROCK | HONG KONG.

Interjacking station with cylinders fitted.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

SPECIAL PIPE JACKING EQUIPMENT FEATURES TO ENSURE SUCCESS


Advanced Interjack Stations

Cylinder Support Ring

Stroke Sensor

Reusable Adjustable Seal Ring

Thrust Cylinders

n Bolted multiple-section-design for easy disassembling after completion


of the tunnel and easy reuse for next tunnel
n Increased safety due to reduction of possible leakage using the special
adjustable seal
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

AP LEI CHAU CABLE TUNNEL | THROUGH HARD ROCK | HONG KONG.


Reference Project: Christchurch Ocean Outfall.
Sewage outfall tunnel in New Zealand.
} M-1124M, AVND 1800, OD 2145
} Outfall length: 875m (2 more drives: 610m + 830m)
} Geology: sand, silt
} Contractor: McConnell Dowell Construction NZ Pty Ltd.
} Longest Pipe jacking project in Australasia: 875m

Herrenknecht. Pioneering Underground Technologies


Reference Project: Sochi, Russia.
Two pipe jacked outfalls in the Black Sea.
} M-1103M, AVND 2000, OD 2525.
} 2 Sewage tunnels installed under the Black Sea, 1,411m + 2,014m.
} 2,014m = Long distance record in ID 2000.
} Performance: 2,014m tunnel installed in 100 days.
} First Sea Outfall in Russia.

Herrenknecht. Pioneering Underground Technologies


Reference Project: Oran, Algeria.
Magtaa Desalination Plant.
} M-1469M + M-1471M, 2x AVND2500, OD3025
} 3 x 1.280m Intake, 1 x 1.210m Outlet

} Geology: sand, clay, marl


} Groundwater pressure: 2bar
} Best performance: 36m in 24h

Herrenknecht. Pioneering Underground Technologies


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Scale (km)

0 5 10

38,7 km
32 Herrenknecht
Tunnelling Machines
in Bangkok

11,8 km 6,8 km

41,9 km 17,8 km

21,6 km
12,4 km 8,8 km
Over 100 km of pipejacking
completed for BMA
5,5 km 4,6 km

BMA Project Overview


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Micro Tunnelling – Bangkok - Thailand


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

PIPEJACKING –EPB2600AE
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

PIPEJACKING – EPB1400AE – EPB2400AE

n Location: Bangkok
n Project: 230KV
underground
lines from
Lardprao to
Vibhavadi
substations.
n Machine: EPB2600
n Outer diameter: 3,060mm
n Max. torque: 1,375kNm
n Total tunnel length: 7,600m
n Minimum drive: 500m
n Min. Curve radius: 400m
n Geology: Silt, sand, clay
n Contractor: Metropolitan
Electricity
Authority (MEA)
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

PIPEJACKING –EPB2600AE
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

PIPEJACKING –EPB2600AE – DRIVE SHAFT


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

PIPEJACKING –EPB2600AE – DOUBLE PIPE INSTALLATION


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

PIPEJACKING –EPB2600AE – PROGRESS CHART

439m 419m 365m 420m 426m

MH09 MH10 MH11 MH12 MH13 MH14

Total Drive Length 2,069m


Total Number of Days Production 84 days
Average Production 25m/day
Peak Production 30m/day
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Cable Tunnel Korea

n Machine: AVND 2400


n Location: South Korea
n Outer diameter: 3,060mm
n Max. torque: 620kNm
n Total tunnel length: 800m
n Shaft depth: 50m
n 5 curve drives: r=200-250m
n Geology: rock (up to 150 Mpa)
n Contractor: Tuksu Engineering &
Construction Ltd.

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Alignment

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Pipeline Section

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

45m Deep Drive Shaft

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Short Pipe to Reduce the Deflection

Page 80
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Pipe Joint Deflection

Page 81
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Finished Curved Tunnel

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Summary of Factors When Considering


Microtunnelling Project

1. Ground Conditions.
Good soil investigation is paramount to correct machine choice.
2. Alignment
Be aware of possibilities regarding curves and long drives.
3. Machine Choice
Following analysis of above factors choose the correct machine.

Herrenknecht AG 2013. - The Herrenknecht Company.


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

Breakthrough

Herrenknecht AG 2013. - The Herrenknecht Company.