Escolar Documentos
Profissional Documentos
Cultura Documentos
1 Scope............................................................. 2
2 Purpose.......................................................... 2
3 Abbreviation................................................... 2
4 References..................................................... 2
5 Inspection Procedure..................................... 2
6 Inspection's Reporting Methods..................... 5
1 Scope
1.1 This Inspection procedure describes how to inspect conduit and cable seals used
in hazardous locations and will include verification of suitable location use of
approved materials and a proper installation.
2 Purpose
The purpose of this procedure is to present all of the relevant information needed to
assure that seals are properly installed and to ensure that all inspections are done
uniformly.
3 Abbreviation
4 References
NEC Article 500 through 504
SAEP-1150 Inspection Coverage on Projects
SAES-B-068 Electrical Area Classification
SAES-J-902 Electrical Systems for Instrumentation
SAES-P-104 Wiring Methods and Materials
DC-950043 Electrical Connections for Field Mounted
Instruments
5 Inspection Procedure
Seals are made mandatory by the National Electric Code (NEC), Article 501-5. The
following step-by-step instructions provide direction for the proper inspection of most
conduit seals. Special applications not covered should be reviewed with CSD prior to
installation.
Page 2 of 5
Document Responsibility: Inspection Engineering Standards Committee 15-SAIP-50
Issue Date: 18 April 2009 Inspection Procedure
Next Planned Update: 18 April 2014 for Conduit and Cable Seals
5.1 Incorrect design and installation of hazardous area seals are the most prevalent
problems electrical inspection encounters in the field. Specifically problems in
conduit/cable seal installations are:
5.2 The major purposes of conduit and cable seals are as follows:
2) Prevent the passage of gases or vapors through the cable core and cable
interstices on multi-conductor cables.
5.3 Preparation
5.3.2 Identify any situations where it is not possible to go strictly by the NEC
or applicable SAES and make a decision on possible trade off's for these
situations based on experience and/or conferences with CSD. Waivers
may be required.
Page 3 of 5
Document Responsibility: Inspection Engineering Standards Committee 15-SAIP-50
Issue Date: 18 April 2009 Inspection Procedure
Next Planned Update: 18 April 2014 for Conduit and Cable Seals
5.3.4 Determine the type of marking system that will be used for the
inspection, i.e., tags, paint, etc., (experience has proven that it is better to
make these inspections by area rather than by system, if possible. This
eliminates a great deal of confusion. This is not always possible).
5.4.1 The first inspection should be made after all seal-off devices have been
installed and dammed but before the compound is poured.
2) Determine that the dam has been properly installed. This includes
determining that the lower end is dammed for vertical seals and
both ends are dammed for horizontal seals.
3) In the case of the cable seal (See 5.1 for cable seal definition) make
sure that the conductors have been properly separated so that the
compound will flow between them. Metal tools should not be used
for this purpose as the cable could be damaged.
4) Assure that the conductors are not against the wall of the seal.
5) Assure that a full five threads of the conduit have been engaged by
the seal off device.
6) Assure that the cable sheath is brought high enough so that it will
end inside the compound.
5.5.1 The second inspection should include witnessing the proper mixture of
the compound and pouring it.
Page 4 of 5
Document Responsibility: Inspection Engineering Standards Committee 15-SAIP-50
Issue Date: 18 April 2009 Inspection Procedure
Next Planned Update: 18 April 2014 for Conduit and Cable Seals
Commentary Note:
Use cold and pure water for mixing the compound, unless if it is specified
otherwise in the manufacturer catalog.
5.5.2 The compound should only be poured once, i.e., a second pour after the
first has hardened would probably leave a void.
5.5.3 In the case of a drain seal, make certain that the rubber drain hole was
properly placed during pour and hardening.
5.5.6 The pouring plug should be left off for at least 24 hours to allow for
proper drying and curing. Unless if it is specified to be closed by the
manufacturer. For example, Crouse-Hinds require closing the seal
fitting's plug immediately after pouring.
Revision Summary
18 April 2009 Editorial revision to change the primary contact.
Revised the “Next Planned Update”.
Page 5 of 5