CHHATTISGARH STATE ELECTRICITY BOARD

FIELD TRAINING ASSESMENT REPORT

Name of the Trainee Shri : YOGESHWAR KUMAR


Branch : CIVIL ENGINEERING
Report No. :- : 01, (Period from 11.07.2019 to 15.07.2019)

Extra ordinary leave availed of any from : ___________________________________________

During the fortnight : Joining Duty of 11.07.2019, visited the 220 and 132 KV S/S
Bhilai-3, B.Q. preparation work for dismateling of old RCC
Brief mentioned of work : overhead water tank, site visit to Dhamdha and Bemetra
132/33 KV S/S.
Attended during the fortnight

1. Work grading A+ A B C D

2. Punctuality Never late Normally Punctual Fairly Punctual

Irregular Very Poor

3. Attitude Towards Outstanding Very Good Good Fair Poor


(a) Initiative

(b) Interest

(c) Willingness/
Enthusiasm

(d) Supervisory/
(Guide)

(e) Relation with/


other Employees

Enclosed: Work Diary __________________________________________________________


Ref. No. ___________ Dt. _____________ Ref. No. ____________ Dt. _______________
From to
Office in charge EE/SE/CE

(Signature & Seal) Countersigned & Submitted


(Signature & Seal)
-------------------------------------------------------------------------------------------------------------------------------
(i) Please tick (√) inside the relevant block of each item.
(ii) For S. No. 1: This is to be recorded by the Officer-in-Charge only.
(iii) For S. No. 2&3: Left side of the block is meant for the OIC and the right side for the controlling
office.
Fortnightly Report for Period from 11.07.2019 to 15.07.2019

Report No. :- 01
Sl. Date Particulars Remarks
No.
1 11.07.2019 Today at forenoon, I join my duty as Assistant
Engineer civil (T) at the O/o Executive Engineer (Civil)
Civil, Trans. Division, CSPTCL, Bhilai.
After joining E.E. Sir has show us the 220 KV sub-
station Bhilai-3, He also show the different
components like Transformer, Lightning Arrester,
Circuit Breaker, Pin Isolator, Gantry, Bus etc. at the
220 KV sub-station Bhilai-3.
2 12.07.2019 Visit the 132 KV sub-station Bhilai-3 and see the
components of the sub-station. We also visit the 33 KV
sub-station Bhilai-3 and see the components like
Capacitor bay etc.
Visit the colony premises of Bhilai-3 Bijali Nagar and
see the various public and residential building like
school building, quarters, rest house and overhead
water tanks for water supply system.
E.E. sir has instructed for preparation of Bill of
Quantity for dismantling of old RCC overhead water
tank at Bijali Nagar Colony Bhilai-3.
3 13.07.2019 Visit of C.E. (Civil) and S.E. (Civil) to Dhamdha and
Bemetara 132/33 KV Sub-Station. We visit Dhamdha
where control room extension work is in completion
stage.
Then we visit the Bemetara Sub-Station and see the
bay extension work where civil work is completed and
EHT work is running. (Second Saturday)
4 14.07.2019 Sunday
5 15.07.2019 As per instruction of E.E. Civil, I get the drawing of old
RCC overhead water tank of 50,000.00 Gallon capacity
and find the detailed dimensions as Dia, height,
thickness etc. of the tank.
PWD SOR-2015 for building work is studied and bill of
quantity is prepared and submitted to E.E. sir for
check.
E.E. sir instructed for preparation of bill of quantity for
providing and fixing sign board at various proposed
sub-station under Bhilai civil division as 1.
Khairagarh, 2. Indamar, 3. Amleshwar, 4. Temri, 5.
Betar, 6. Semariya (Litiya), and 7. Baijalpur.

YOGESHWAR KUMAR
Assistant Engineer Civil (Trainee)
O/o Executive Engineer (Civil)
Transmission Dn. Bhilai-3