DATE:
ICS-ONGC- INSP/91/Inspection/Survey/5483223/20191119 19/11/2019
Mehsana
CUSTOMER NAME : ONGC - TPI - MEHSANA (2018-21)
CONSULTANT/EPC CONTRACTOR NAME : Hal Offshore Limited
MANUFACTURER/SUPPLIER NAME : Hal Offshore Limited
PROJECT/VENDOR P.O. NO. : P O No DLH/OES/MM/RVMP-MHN/X11JC16001/2017 dated
17/05/2017
ITEM/MATERIALS : Sobhasan Site Close Drain Pit & Instrument Rack Room
BATCH NO./ Sr. No. : -
QUANTITY : Sobhasan Site Close Drain Pit Bottom Raft Reinforcement Fixing Work
Under Progress And 0.954 M3 M15 PCC Work For Instrument Rack
Room Plinth Beam Done.
SPECIFICATIONS/DRAWINGS : Relevent Clause Of Specification-P6EC-STD-CI-S-1010 & Relevent
Drawing Of 1702-741-CI-D-1020, Rev-B1 , 1702-741-CI-D-1040 REV-
B2
IR
CODES/STANDARDS : IS.383 & 456 And M-30 Concrete Mix Design Report No.MAPTCEL/17-
18/02404 Dated.30-08-2018
DATE(S) OF INSPECTION : 19/11/2019 INSPECTION TYPE Stage
The undersigned Surveyor working under general terms and conditions of International Certification Services, did visit at
Hal Offshore Limited for Inspection of the above.
FINDINGS / OBSERVATIONS:
A) Visual: (Annexure A)
T
(1) Reinforcement Cutting And Bending Work And PCC Grade Varify And Found Satisfactory As Per Drawing
AF
a) Any other:
(1) OK
B) Dimensional: (Annexure B)
(1) Dimension Of Reinforcement Cutting And Bending Work And Dimension Of PCC Verified As Per Drawing And Found
R
Satisfactory
H) Other: (Annexure H)
Reinforcement Work Witnessed Random Satisfactory At 4 RVMP Site Survey Done At Mehsana ONGC Site.
I) Deviation, if any: (Annexure I)
Nil
J) Identification / reference marking : (Annexure J)
Nil
ANNEXURES :Attached Inspection Visit :NA
IR
T
AF
R
D