Escolar Documentos
Profissional Documentos
Cultura Documentos
ABSTRACT
This research describes about voltage analysis and power relation of electrical power system . This relation is
depicted in the P-V and Q-V curve method . These two methods determine steady-state loadability limits which are
related to voltage stability, that occurs on 150 KV Sumbagteng interconnected power system (system consists of
Sumbar , Riau , and Jambi subsistem) 150 kV system. This system has peak load with power flow a total installed
capacity of 515,47 MW and 237,7 MVAR at 19.00 WIB, on the 26th December of 2005.
The Influence of various increase loading that resulted from transformation of active power loading, to strain
stability line through P-V and Q-V curve, visible at condition of total loading ( MW) and ( MVAR), the results strain
that there are many voltage buses have pass critical point of normally voltage. From the result of simulation at
condition of influence of increase till 12.6% condition from peak load causes Garuda Sakti bus has critical voltage
135.17 kV with total active power system 580,42 MW and reactive 269.29 MVAR, and caused all buses at Riau
subsystem have strain collapse that is residing in under voltage ridge nominal stress ( < 10 % V nom).
1. Introduction
Voltage stability is a real important problem in 2. Voltage stability
electric power system that having long transmission Voltage stability refers to the ability of power system
passage with big encumbering capacities, so that this to maintain stedy voltage at all buses in the system after
thing can cause instability of strain at the electric power being subjected to a disturbance from a given initial
system and in the end can cause the happening of strain operating condition. It depends on the ability to
shoot [1]. maintain/restore equilibrium between load demand and
The voltage stability study may be limited to identify load supply from the power system. Ins stability that may
areas prone to voltage instability and to obtain result occurs in the from of a progressive fall or rise of
information regarding how system voltage stability can voltage some buses. A possible outcome of voltage
be improved most effectively. The main goal of voltage instability is loss of load in an area, or tripping of
stability analysis is to find Point of Collapse (PoC). transmission lines and other elements by their protective
Operation near the voltage stability limits is impractical system leading to cascade outgas.
and a sufficient power margin is needed. Practically, the
idea of P-V and Q-V curves is used to determine the 2.1. P-V curves
maximal reactive margin at load buses to avoid voltage P-V curve are useful for conceptual analysis of
collapse [2]. voltage stability and for study of radial system. The
This relation is depicted in the form of P-V and Q-V method is also used for large meshed net works where P is
curve method . This methods applied to know the the total load in area and V is the voltage at a critical or
condition of total power that strain experiences collapse. representative bus. P can also be the power transfer across
Electric power system application to electric power a transmission interface or interconnection . Voltage at
system at Sumbagteng (Sumatera Center) 150 kV system, several busses can be plotted.
that has peak load with power flow at 19.00 WIB, on 26 For conceptual analysis, P-V curve are convenient
December 2005 with active power 515.47 MW and when load characteristics as a function of voltage are
reactive 237.70 MVAR. System consists of Sumbar analyzed. For example a resistive load can be plotted with
subsystem, Riau subsystem, and Jambi subsystem. P load =V2/R. [1. 3].
This research methodologies done through
simulation of EDSA (Electrical Distribution
Transmission System Analysis) programming. Simulation
done with light load, peak load, payload increases 5%,
12.6%, condition from peak load and contingency system
.
*Asnal Effendi. E-mail: asnal_itp@yahoo.com
145
145
of this simulation that is with increase of payload
Voltag
140
until 12,6% from peak load/burden, bus GRDSK
Vo
140
experiences critical voltage 135.17 kV with
135
135
system active power total 269.29 MVAR.
3. Then at condition of system experiences trouble
130
130
in the form of trouble contingency that is broken
100
100 200
200 300
300 400
400 500
500 600
600 700
700 it one of passage which is in the form of radial
dP(MW)
dP(MW)atatbus
busGRDSK
GRDSK that is at bus Ombilin and Kiliran Jao happened
at the time of peak load system, seen that power
Fig. 3. P-V curve at bus GRDSK (Garuda Sakti) with channeled has exceeded performance the
Critical point voltage 135.17 KV , of totally passage, so that this thing causes imbalance strain
payload is 580.42 MW and in the end causes system towards at condition
Result of analysis through curve P-V like shows at, blackout.
Fig. 3 that critical voltage 135.17 kV for bus GRDSK
happened at system total payload Sumbagteng 580.42 References
MW, with increase of payload 12.6% from peak load. [1]. Taylor, W. Carson.1994. “ Power System Voltage Stability”.
This thing shows performance ridge of system in McGraw-Hill. New York.
[2]. Sobierajski, Bertssh. 2001. “Using Bus Impedance and Bus P-Q
channeling active power to bus GRDSK. Curve for Voltage Stability Control”. IEEE Transaction on Power
System, 0-7803-7285-9. pp. 79-84
[3]. Kundur, P. 1994. “Power System Stability and Control”. McGraw-
155
155 Hill, Inc. New York.
[4]. Gupta, B.R.2004. “Power System Analysis and Design, Third
150
150
Edition”. Wheeler Publishing. S,CHAND end Company LTD, Ram
Nagar. New Delhi
[5]. Chowdhury.H.Badrul. 2000. “Voltage Stability Analysis : V-Q
(kV)
Voltage(kV)
145
145
Peower Flow Simulation Versus Dynamic Simulation”. IEEE
Voltage
4. Conclusions
1. From result of visible P-V cooling curve that
influence increase of active power payload (
MW) what results the happening of voltage drop
of towards voltage instability . From result of
this simulation that is with increase of payload
until 12,6% from peak load/burden, bus GRDSK
AGAM
BNKNG
LBALG SNKR
DUMAI
K BBATU
BTSKR DURI
PIP
INDRG OMBILIN
P LIMO
AURDURI BANGKO
Fig. A1. The Implementation power system application to electric power system at
Sumbagteng (Sumatera Center) 150 kV system