25.October.2007
Hidetoshi Tanaka
KOBE STEEL, LTD.
Contents
FASTMET Process
FASTMELT Process
ITmk3 Process
CO2 Reduction by using New Iron-making
processes
Conclusion
1
Necessity of New Ironmaking Processes
Air Blower
Briquette
Mixer Machine
OR
ID Fan
Heat Bag Filter
Exchanger
Fuel
Discharger
Burner
OR
2
The image of Steel Dust recycling in
FASTMET Process
Zinc
Sale to
Alkali Zinc
Arsenic producer
Material Dust Lead
Nippon Steel
HIROHATA No1 & No2
190,000t/y Steelmaking dust
Start-up : March 2000 and Feb, 2005
Asia-Pacific Partnership on Clean Development and Climate
4th Steel Workshop, Wollongong Australia
3
Hot Metal Production
by FASTMELT® Process
FASTMELT Process
4
Typical FASTMELT Molten Iron Chemistry
Temperature Fe C Si S P
1,450-1,550 deg.C 96-98% 2.0-4.0% 0.1-0.6% <0.05% <0.04%
What is ITmk3 ?
Iron-making Technology Mark Three
Mark
One:
BF-
BF-BOF
system
Mark Two:
Natural
Gas-
Gas-
based DR
5
ITmk3 Process
High Grade Pure Iron Nuggets Metallic Iron 96-97%
Carbon 2.5-3.0%
¾ by using fine ore and coal Sulfur 0.05-0.07%
Size 5-25mm
¾ by separation of metal and slag
¾ with fast reduction and melting
rate (8 to 12 min.)
¾ at relatively lower temperature
(1350 to 1450℃)
Metal
Slag
Dense metallic Molten slag separated
iron shell from metal
6
Asia-Pacific Partnership on Clean Development and Climate
4th Steel Workshop, Wollongong Australia
Slag
7
ITmk3 process flow
Kakogawa Mesabi
Bench Scale Plant Pilot Demonstration Plant
RHF outer dia. : 4.0m RHF outer dia.: 13.5m
Capacity: 0.4t-iron/h Capacity: 25,000t-iron/y
8
Product Pile of Iron Nugget
9
CO2 reduction by using FASTMET
Mine Location Consuming Location
Iron Sinter
Ore Plant Sinter Hot Metal
TFe:56%
Mill Waste CO2 Redction
HBI Production ▲0.2 t-CO2/t-HBI I
from Mill Waste HBI
TFe:58% BF
MFe:50%
HBI Production FASTMET Hot Metal
in Mine Location
20.00
15.00
10.00
5.00
0.00
Large BF Mini BF FASTMELT ITmk3
(3Mt) (0.5Mt) (0.5M) (0.5M)
-5.00
10
CO2 reduction by using FASTMELT/ITmk3
in Japan
3,000
CO2 Emission (kg-CO2/thm)
2,500
CO2 Reduction
2,000
▲1t-CO2/thm
1,500
1,000
500
0
Large BF Mini BF FASTMELT ITmk3
(3Mt) (0.5Mt) (0.5M) (0.5M)
Conclusion
¾With growing concerns on the conservation of
resources and the environment, the new ironmaking
processes are receiving more and more attention.
¾Kobe/Midrex has jointly developed new ironmaking
processes such as FASTMET and ITmk3, which can
reduce CO2 emission as compared with the BF.
¾We will continue to develop and supply coal-based DR
processes and plants. In doing so, we aim to contribute
to both growing the ironmaking industry and improving
the global environment.
11