Escolar Documentos
Profissional Documentos
Cultura Documentos
Management Act:
an overview
16 September 2009
This briefing note has been prepared by the ILE Technical Committee for study and
application. The document reports on current knowledge and experience within the
specified field of light and lighting described and is intended to be used by the ILE
membership and other interested parties. This is a briefing note and is not of mandatory
status. The ILE should be consulted regarding possible subsequent amendments.
Any mention of organisations or products does not imply endorsement by the ILE. Whilst
every care has been taken in the compilation of any lists, at the time of going to press,
these may not be comprehensive.
Compliance with any recommendations does not itself confer immunity from legal
obligations.
2
The Traffic Management Act: an overview
The Traffic Management Act (TMA) was mentioned in the Queen’s speech in December
2003 and it received Royal Assent in July 2004. The overall emphasis of the TMA is to
help local authorities manage their road network effectively and cut out some of the
unnecessary disruption to road users.
The Traffic Management Act 2004 places a duty on local traffic authorities to:
Contents
1. Summary of the Act 4
3. Categories of works 7
7. Conclusion 11
3
Institution of Lighting Engineers– technical briefing note
wear a uniform
acquire land.
4
The Traffic Management Act: an overview
statutory undertakers’ street works and their own road works. Part 4 amends section 59 to
allow that duty to be extended to encompass the co-ordination of some other prescribed
temporary activities on the highway, for example the placing of skips and scaffolding.
The Act also amends the Highways Act 1980, most notably to provide for regulations to
apply ‘lane rental’ charges to skips, scaffolding, building materials and temporary
excavations that occupy the highway.
5
Institution of Lighting Engineers– technical briefing note
Section Description
48 Streets, street works undertakers
49 The street authority and other relevant authorities
50 Street works licences
52 Emergency works
53 The street works register
54 Advance notice of certain works
55 Notice of starting date of works
56 Power to give directions as to the timing of street works
56A Power to give directions as to the placing of apparatus
57 Notice of emergency works
58 Restriction on works following substantial road works
58A Restriction on works following substantial street works
59 General duty of the street authority to co-ordinate works
60 General duty of undertakers to co-operate
61 Protected streets
62 Supplementary provisions as to designation of protected streets
63 Streets with special engineering difficulties
64 Traffic sensitive streets
66 Avoidance of unnecessary delay or obstruction
70 Duty of the undertaker to reinstate
72 Powers of the street authority in relation to reinstatement
74 Charge for occupation of the highway where works are unreasonably prolonged
74A Charges for occupation of the highway
76 Liability for cost of temporary traffic regulation
81 Duty to maintain apparatus
83 Apparatus affected by highway, bridge or transport works
87 Prospectively maintainable highways
88 Bridges, bridge authorities and related matters
91 Transport authorities, transport undertakings and related matters
95 Offences
95A Fixed penalty notices
97 Service of notices and other documents
98 Reckoning periods
99 Arbitration
6
The Traffic Management Act: an overview
3. Categories of works
Minimum notice periods
Matrix of notice periods and response times
Notice period Validity period Response time
S 54 S s55/57 S54 Ss 55/57 S 54 Ss 55/57 S 74
Major 3 months 10 days 15 days 5 days 1 month 5 days 5 days
Standard n/a 10 days n/a 5 days n/a 5 days 5 days
Minor n/a 3 days n/a 2 days n/a 2 days 2 days
Immediate n/a 2 hours n/a n/a n/a Any time 2 days
after during works
Major works
Three months advance notice will be required if the duration is 11 days or over or if a
temporary traffic order is required. There is a requirement for increased planning and
advance notification and a 5-year ‘wish list’ programme to help with restriction
embargoes.
There is now a requirement for major works to be discussed much earlier that previously,
at 6 months prior to commencement rather than the previous 3 months. With better co-
ordination joint advertising will be possible for most traffic disruptive schemes.
Standard works
It is envisaged that the majority of works that were undertaken under the 7-days notice
period will now fall into the 3-months advance notice requirement. Standard works of
4 to 10 days duration requires a 10-days’ advance notice.
Minor works
The daily whereabouts notice has been scrapped and a 3-day advance notice is required
for 1 to 3 days works duration.
Immediate works
Emergency: works undertaken which are to prevent imminent danger to
people or property
7
Institution of Lighting Engineers– technical briefing note
Restrictions
Section 58 allows the Highway Authority (HA) to place the following maximum
restrictions:
all work that involves opening the carriageway or cycleway at traffic sensitive
times, including opening a chamber cover
all works that require any form of temporary traffic control as defined in the Code
of Practice for Safety at Street Works and Road Works
all works that reduce the number of lanes available on a carriageway of three or
more lanes
8
The Traffic Management Act: an overview
all works that require a temporary traffic restriction or the suspension of pedestrian
crossing facilities
all works that require the reduction in width of the existing carriageway of a traffic
sensitive street at a traffic sensitive time.
All works now have to be registered, including works for road purposes; maintenance and
improvement works to the road (including street lighting) itself carried out by, or on behalf
of, the HA. Section 53 of NRSWA requires an Authority to place information about its own
works on the street works register in similar timescales and protocols as a statutory
undertaker. Fines will be applicable for contraventions to permits for over-running works
or failure to have the necessary notice or permit in place when works commence. Fines
will be applied to all those working on the highway including the HA's own workforce such
as direct labour organisations, and although the HA cannot fine itself it will be required to
keep records of all incidents for comparison with other utilities.
Vandalism
These would either be emergency or urgent works requiring a notice within 2 hours of the
works commencing. However, the emphasis is about reasonableness: if the works are on
a traffic sensitive road then notices are required; if they are on a minor road then this
may not be necessary. In all cases, if excavations or barriers are necessary then notices
must be served or permits sought.
Electrical testing
9
Institution of Lighting Engineers– technical briefing note
Structural inspections
Structural testing
Painting
These are planned operations and being minor works require a 3-day notice. Daily
whereabouts notices are no longer valid so these works could be done as a rolling 3-day
programme requiring notices or permits.
These would be considered to be urgent works and, acting reasonably, 2-hour notices or
permits would probably not be required in many situations except on traffic sensitive
roads but would, of course, be needed where there is excavation or occupation of the
highway with barriers.
Attaching signs
These would be planned operations or minor works for which 3-day notices or permits
will be required.
Notices are required for these and the notice periods will be dependent on the period of
highway occupation. As a minimum a 7-day notice or permit is required.
10
The Traffic Management Act: an overview
7. Conclusion
The intention of the Traffic Management Act is to improve co-ordination between all those
occupying the highway that could lead to disruption to the travelling public. It is now a
duty for all those involved in these activities to talk to each other and discuss these
activities so they can be better planned and co-ordinated. This legislation requires the
highway authority to treat all those working on the highway the same way, whether they
be a statutory undertaker OR the highway authorities own workforce. The highway
authority must keep records of highway activities and for those that do not co-operate or
exceed their authorised highway occupation there will be penalties applied. Though the
highway authority cannot apply financial penalties on itself, it is required to keep records
on the performance of its own operations in order to achieve parity with utility
companies. These records, being open to public scrutiny, could adversely affect its local
and possible national Key Performance Indicators, its Comprehensive Performance
Assessment or its Comprehensive Area Assessment.
11
lightcast
briefings from the ILE technical committee
Regent House
Regent Place
Rugby
CV21 2PN