Escolar Documentos
Profissional Documentos
Cultura Documentos
Headlines
Phase I baseline schedule approved; USACE reworking Phase II schedule to reflect Dec 2008 completion –
Baseline for 225 to be completed and final by 28 Sept 07 Deleted: 30
Received approval for the proposed expedited Real Estate Acquisition process. The Expedited process includes Deleted: <#>Held meeting with
Offering ROE-C to land owners along with a (b) payment for signing unopposed condemnation and Senior Management 10 Sept to go
condemnation of property if/when a property owner refuses to sell. Execution date of this process will begin after over final details in preparation for
(b) concludes the final communication is completed. Briefed the Hill today and hoping to start enacting briefing to S2 on Thursday 13 Sept¶
tomorrow.
225 project will work with OBP and COE to finalize Fence Lab fences design that will be used for Phase II
Performing site visits in Rio Grande Valley and remaining miles for Del Rio, Marfa and El Paso are scheduled for
the week of 17 Sept – Goal to finalize Phase 2 fence alignment by 30 Sept Site visit has identified a potential
problem with fence segment O-19 Which could result in segment being deleted from PF225
Scheduled NEPA kick-off meetings for all of the sectors which will occur in the month of Sept
USACE to update fence summary, including contingency miles, by next week ??
Three Fence Lab pedestrian fence designs selected ?? Deleted: <#>ROE for C authorized
and planned to be briefed to the Hill
next Tues.¶
Project Manager’s Assessment
Category Status Assessment Summary
Scope R Have identified 50+ contingency miles.
Need to complete official Gate Locations/Types, Access Roads, and Urban/Rural
demarcation lines in TX delineating land acquisition south of the fence along the river.
Decisions not yet final wrt fence alignment along levee in TX, will result in different
solutions due to varied field conditions/limitations & planned IBWC levee improvements –
currently conducting site assessments teaming w/ IBWC, USACE, OBP, CBP, SBI & DOI.
Budget Y (b) estimate (+20%/-5%); based on parametric estimate
Schedule Y Corps currently projecting Dec 08 based on CBP/SBI implementing required assumptions.
Technical Y Preparation of Phase 1 RFP documents on schedule; IBWC MOU needs to be
prepared/executed; Significant DoI coordination activities
Schedule Details
Key Milestone Baseline Current Estimate Status*
Identify contingency/buffer miles N/A 09/06/07 R
Complete PMP document N/A 9/14/07 Y
Delegation of Authority and Accompanying Support N/A 08/30/07 G
Agreement issued to USACE and accepted as written
Complete Phase 1 Preliminary Design/Contract Awards 12/02/07 10/01/07 G
Complete Phase 2 Preliminary Design/Contract Awards TBD TBD R
Complete Phase 1 Construction 08/31/07 03/01/08 G
Complete Phase 2 Construction 12/01/08 12/01/08 R
Complete Real Estate Phase 1 Acquisitions 11/27/07 11/27/07 G
Complete Real Estate Phase 2 Acquisitions 01/01/08 01/01/08 R
Complete Phase 1 NEPA Decision Documents 12/22/07 12/22/07 G
Complete Phase 2 NEPA Decision Documents 03/01/08 03/01/08 R
Project level gate reviews – Next Event/Milestone Only
- Approve Phase I baseline N/A 8/17/07 G
- Approve PMP N/A 09/14/07 Y
- Prepare/Approve Phase II and overall project baseline 09/30/07 Y
- Phase I construction breaks ground 10/25/07 09/01/07 G
FME004183breaks ground
- Phase II construction TBD TBD R
* Green = No Issues, No Help Needed, Yellow = Some Issues and Problems, No Help Needed, Red = Can’t or Probably Can’t Meet Promise, Need Help
2 – Timely ROEs and land acquisition (will require 8 – Public/environmental groups opposition
condemnations)
3 – Timely completion of NEPA decision documents (will 9 – Fence deployment in South Texas and portions
likely require a S1 waiver) of San Diego sector