Você está na página 1de 2

Sheet1

CEMENT CONSUMPTION
S ITEM ITEM CONSUMPTION KG/CuM BAG WEIGHT
1
NO B-01 A
NO PCC M5 C 140 50
2 B-02A PCC M10C 228 50
3 B-02C PCC M15C 288 50
4 RCC M15C BELOW GL 288 50
5 RCC M15C ABOVE GL 288 50
6 RCC M20C BELOW GL 360 50
7 RCC M20C ABOVE GL 330 50
8 RCCM25C ABOVE GL 390 50
9 HRC M30 BELOW GL 518 50
10 HRC M30 ABOVE GL 518 50
11 PRECAST M20C 350 50
12 GROUTING M20C 429 50
13 GROUTING M25C 570.6 50
14 HOLLOW BLOCK WORK B GL 185 50
15 HOLLOW BLOCK WORK A GL 185 50
16 BRICK WORK 78 50
17 HALF BRICK WORK 10.6 KG/SqM 50
18 RRM A GL 102 50
20 PLASTERING 10 THK 4.6 KG/SqM 50
19 RRM B GL 102 50
20 PLASTERING 15 THK 6.5 KG/SqM 50
21 PLASTERING 20 THK 8.6 KG/SqM 50
22 NEAT CEMENT FINISHING 2.3 KG/SqM 50
23 IPS FLOORING 16 KG/SqM 50
24 IRONITE 9.75 KG/SqM 50
25 P/L CERAMIC TILES 12.16 KG/SqM 50
26 TAPECRETING 0.73 KG/SqM 50
27 SOLID BLOCK WORK A GL 293 KG/CuM 50
28 CURB STONE 3.2 KG/M 50
29 NON-SHRINK GROUT 2000 KG/CuM
30 BB WATER PROOFING 20 KG/SqM

Page 1
Sheet1

CONSUMPTION BAGS/ CuM


2.8
4.56
5.76
5.76
5.76
7.2
6.6
7.8
10.36
10.36
7
8.58
11.412
3.7
3.7
1.56
0.212
2.04
0.092
2.04
0.13
0.172
0.046
0.32
0.195
0.2432
0.0146
5.86
0.064

Page 2