HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

HERRENKNECHT EPB SHIELD S-574


FOR HIGHWAY TUNNEL GALLERIA SPARVO.
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

PRODUCT PORTFOLIO OF HERRENKNECHT GROUP.


MECHANIZED TUNNELLING TECHNOLOGY.
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

STEEP TUNNELLING.

St. Petersburg

30° downhill

EPB Shield

Access metro station

Limmern

40° uphill

Gripper TBM

Hydropower
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

DIRECT PIPE®.

Rheindüker Worms | Germany

AVN1000C Pipe Thruster Customer:


Diameter: 1,326mm HK250/500PT Sonntag
Max. torque: 150kNm Pipeline diameter: 48“ Baugesellschaft
Tunnel length: 464m Max. pull / thrust force: 500 t mbH & Co. KG
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

VERTICAL SHAFT SINKING.

Naples

Shafts for Metro Linie 1

Diameter max. 9,000mm

10 Shafts
Inner diameter 4,500mm

Depths up to 45m
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

HERRENKNECHT EPB TECHNOLOGY.


SAFE MECHANIZED TUNNELLING IN SOFT GROUND.

Operational principle and face pressure control

1 Tunnel face 4 Pressure bulkhead 7 Erector


2 Cutting wheel 5 Thrust cylinders 8 Segment lining
3 Excavation chamber 6 Screw conveyor
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

S-574 GALLERIA SPARVO.


OVERVIEW.

Machine Type: EPB Shield Excavation diameter: 15.615 mm

Tot. length of machine: 130m Tot. installed power: 16.800 kW


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

2.700 TONS OF HIGHTECH.

Shield machine:
2.700t

Total weight
incl. backup
system:
4.500t
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

CUTTERHEAD DRIVE.

12 electric motors with


1.000 kW each

24 Hydraulic pumps able to


displace up to 26.820 l/min

50 hydraulic motors each with


a torque of 2.400 Nm

Main drive weight completely


assembled 400 tons

Max working pressure 320 bar


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

TORQUE.

Nominal torque: 94.800kNm Cutterhead power: 12.000kW

Max. torque: 125.000kNm Cutterhead rotation speed: 2,16 rpm


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

THRUST FORCE.

Normal operation: 315.000kN at 400bar

Max. thrust force: 400.000kN at 500bar

Advance speed 10 mm/min

Illustration to
be updated
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

CUTTERHEAD AND CUTTING TOOLS.

Designed and aranged for optimized excavation:


76 disc cutters, 216 cutting knifes, 24 buckets, 1 center knife
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

EXCAVATING AND LINING THE TUNNEL.

More than 957.000 m3 to be Ring division: 9+1 segments


excavated in total for two
Ring length: 2m
tunnel drives
2.500 rings
with a total weight of 390.000t
for 2 x 2.5km of tunnel
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

SCREW CONVEYOR.

Length: 22,7 m

Diameter: 1.600 mm

Installed power: 2.000 kW

Max. speed: 22.5 rpm


Max flow of excavated material: 1990 m³/h
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

TAILSKIN.

Double-shelled tailskin

3 lines of wire brushes + 1 line of spring steel plates

12 grout lines + 12 spare lines

19x3 grease lines


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

ROTARY UNIT

16 foam lines going to the cutting head

New high pressure cleaning system for the foam lines (4 lines)

2 Copy cutters at 180°

B.E.A.M. system
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

FIRE DAMP PROTECTION.

Double-shelled belt conveyor pipe, gas tight


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

FIRE DAMP PROTECTION.

Double-wall pressurized at 40 mbar


to avoid gas leakage from the pipe

CH4 sensors monitoring constantly the


presence of gas

“Flushing mode” to increase the


ventilation into the pipe

All the equipment in the pipe


Ex-proof, at least IM2 class
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

FIRE DAMP PROTECTION.

Void detection system in the excavation chamber


Radar System Viscosity Detector
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

FIRE DAMP PROTECTION.

Ventilation and gas monitoring systems accessible from the control


cabin

13 gas sensors distributed over shield, backup and excavation chamber


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

FIRE DAMP PROTECTION.

Redundant ventilation system (2 independent lines)


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

FIRE DAMP PROTECTION.

Essential services (lights, communications, ventilation, gas


monitoring system) IM2 Class

Separate 15 kV line to supply all the Ex-proof equipment on the TBM


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

THANK YOU FOR YOUR ATTENTION.