Você está na página 1de 13

KIDD AND CARR: AUTOMATIC VOLTAGE AND SWITCH CONTROL.

285

THE APPLICATION OF AUTOMATIC VOLTAGE AND SWITCH CONTROL


TO ELECTRICAL DISTRIBUTION SYSTEMS.
By W. KIDD, Member, and J. L. CARR, B . S C , Associate Member.
{Paper first received 2nd June, 1933, and in final form 6th March, 1934; read before THE INSTITUTION 1th December, before the
NORTH-WESTERN CENTRE 1th November, before the MERSEY AND NORTH WALES (LIVERPOOL) CENTRE 20th November,
before the NORTH-EASTERN CENTRE 21th November, and before the WESTERN CENTRE 18th December, 1933; also before
the IRISH CENTRE 18th January, before the WEST WALES (SWANSEA) SUB-CENTRE 25th January, before the SCOTTISH
CENTRE IZth February, before the TEES-SIDE SUB-CENTRE IWI February, before the NORTH MIDLAND CENTRE 20th February,
and before the SOUTH MIDLAND CENTRE 26/A February, 1934.)

SUMMARY. are, in many instances, only commercially feasible by


this method.
During recent years, of the problems which have presented
themselves to engineers on electrical transmission and distri-Voltage control, which was usual in direct-current
bution systems, those of voltage and switch control have substations, is not possible without special equipment
probably been the most interesting. on alternating-current systems; consequently, although
Supply systems may be classified as either rural or urban;
trouble may not be serious in lightly loaded districts,
the latter type is that on which the experience and particulars
difficulties due to the inherent regulation of the system
for the preparation of this paper have been obtained. It isare accentuated where load development.is rapid.
believed that the city of Manchester is the first area to have
complete automatic voltage regulation, and also supervisory The economic benefits of a.c. distribution, together
control for its main substations. with its standardization nationally for all future develop-
Some particulars of the investigations made, equipment ment, have inaugurated an intensive programme of
installed, and results obtained, are given, together with achanging systems of supply from d.c. to a.c. distribution.
The electricity authority with which the authors are
brief outline of the growth of systems, and reasons why better
control of voltage is necessary. associated has adopted distributor networks as standard
It is claimed that, by a careful application of automatically-
for this type of supply.
controlled compensated voltage-regulators in main sub- The change from networks with large-section low-
stations, the voltage on distribution networks may be econo-
voltage feeders to distributor networks supplied from
mically maintained within the permissible limits of ± 4 per
high-voltage distribution substations is a logical step in
cent; and that, generally, the voltage variation at individual
services may be kept within 4 per cent overall. At the samethe process of evolution of electricity supply. Large
time, the fluctuations at the secondary terminals of high- stores, office blocks, and other buildings, each requiring
voltage power consumers' transformers may be maintained a considerable load, are in many instances supplied more
within the limits for low-voltage distribution. Abnormal satisfactorily at high voltage, thus relieving the distribu-
tion system of load and, in effect, increasing its capacity
cases will, however, occur and will require special treatment.
The limitation of voltage variation to such a small amount
for other smaller consumers. It is difficult, at this stage,
possesses definite technical, economic, and psychological to give a definite economic lower limit of load for supply
value; and available records over a short period suggest that
at high voltage which would be applicable to all systems,
it also results in increased sales of energy. but the authors are of the opinion that concentrated loads
The value of supervisory control is referred to, and one
system is described in some detail. exceeding 75 kW in amount in densely loaded areas
should generally be supplied direct from high-voltage
feeders.
It is unfortunate that, in such conversions, the low-
ELECTRICITY SUPPLY DEVELOPMENT.
voltage feeders are usually unsuitable for incorporation
Since the inception of public electricity supply, the in the later scheme; but the matter must be viewed
demand has increased with phenomenal rapidity. commercially.
In the post-war period, lighting and domestic-appli- In many instances an economic survey of several
ance connections have predominated. Owing to rapid alternatives • will result in the adoption of a plan for
house-building development, areas of supply have grown; distribution alterations which will show a cumulative
and although many of the new connections represent, saving after a short period.
in themselves, small increases in demand, distribution As an illustration of the alternative methods of feeding
problems have become more acute. The increasing use a district, Fig. 1 shows the original lay-out of the network
of high-efficiency lamps, electric cooking ranges, mains- in a rapidly-growing suburban area, with long d.c.
operated radio receivers, and other devices extremely feeders. During the conversion to a.c. distribution the
sensitive to voltage variation, has imposed special location of the feeding-points was modified; when the
requirements of voltage regulation; and the necessity for load increases, additional distribution substations are
a reduction of the amount of variation will increase as to be installed at approximately mid-positions between
special applications develop. those shown, and the networks are to be suitably
The flexibility and relatively low cost of alternating- divided.
". current supply are now fully appreciated, and extensions The problem of voltage regulation became acute,
of the area of supply into sparsely populated districts partly because of the increasing load density, but more
I.E.E. JOURNAL, VOL. 74, No. 448, APRIL, 1934. 19
286 KIDD AND CARR: THE APPLICATION OF AUTOMATIC VOLTAGE AND

particularly because the variations possible with convert- when the consumer's load is sufficient to justify the
ing plant could no longer be achieved in substations with installation of local voltage regulators, as, for example,
plain transformers. in connection with bulk supplies.
Although it has been stated that in certain districts For low-voltage consumers, the supply voltage must
supplied by alternating current no voltage difficulty has be maintained within ± 4 per cent; such a variation is
been experienced, this must be due to variation of in the nature of a compromise and may be accepted
station busbar voltage, rendered possible either by as generally suitable. It should be noted, however, that
isolation or by relatively light loading, or by both. In this is the utmost variation permitted, and therefore
later stages of development, trouble will undoubtedly applies to the most abnormal cases met with in distribu-
be experienced unless comprehensive measures for tion. To keep within this limit, the average case must
dealing with this problem are adopted early. be catered for on a much narrower margin.
The present stage of development consists of the Unless distances are short, distributors can seldom
be loaded to the thermal limit because of voltage
limitations; therefore, full advantage must be taken of
the permissible drop. Consumers at the supply and
distant ends of a distributor should be supplied at 104 and
96 per cent of the declared voltage respectively, giving
the total allowed variation at the time of maximum load.
At other times the voltage at the supply end may vary
from 104 per cent to 96 per cent, provided that the
voltage at the remote end does not fall below 96 per cent.
To conform with these conditions, the closest regulation
will be attained by varying the distribution voltage at
the substation busbars between the limits of 100 and
104 per cent at no load and full load respectively.

SELECTION OF REGULATING POINT.


The ideal method of voltage control would be to
provide for constant voltage at each consumer's ter-
minals; financial considerations, however, preclude this.
An approximation would be to regulate at each
distribution station, but, whilst this method may be
essential in certain cases, e.g. where the local station is
supplied by long, overhead, secondary feeders having
poor regulation, the costs involved in altering existing
systems will prove a deterrent to adopting this method
as a general solution.
Apart from special cases requiring local regulation, it
appears that the most suitable regulating positions are
at the main substations. The principal regulating
Scale of feet points will therefore be relatively few in number, entailing
FIG. 1.—Plan showing rearrangement of low-voltage network comparatively low capital expenditure and also reduced
feeding-points. expense for supervision, adjustment, and general mainten-
Old d.c. feeding-points: A, B, C, D, E. ance. A careful examination of system characteristics
New a.c. substations: 1, 2, 3, 4. is desirable in order to decide whether this method will
prove reasonably satisfactory.
linking of local groups of supply undertakings and In the case dealt with by the authors there are 10
isolated stations by means of the national grid. The main substations, with an aggregate plant rating of
standard installation of voltage-regulating transformers 200 000 kVA. These supply 293 distribution and
at grid stations will permit of a certain measure of consumers' substations, of aggregate rating 227 360 kVA,
voltage variation to meet local conditions; but, with and also converting plant totalling 183 400 kW. Six
extensive local systems, this will be totally inadequate tap-changing transformers, 18 boosters, and 4 double
to meet distribution requirements. induction voltage-regulators, all automatically controlled,
have been installed in main substations. In the maj ority
PERMISSIBLE LIMITS OF VOLTAGE VARIATION. of the existing distribution substations there was not
enough space available for separate regulators.
In the case of a high-voltage consumer, it is prescribed
that the voltage must not exceed the declared value by
more than 12£ per cent. This refers, however, to the SYSTEM PARTICULARS.
primary supply; the voltage-drops in the transformer, In the area referred to in this paper, the extra-high-
and the local cable must also be taken into account. voltage system transfers large amounts of energy to
The total of these, variations is unreasonable for lighting main substations, where the voltage is reduced far*,"*
and cooking purposes,- and should only be permitted. secondary transmission. The original high-voltage sys- *
SWITCH CONTROL TO ELECTRICAL DISTRIBUTION SYSTEMS. 287

tern has become a secondary system, which is sectional- and reactance for the several system components under
ized around the main substations, and is augmented individual full-load conditions.
as found necessary for further developments. Fig. 2 It is apparent that, in the fully loaded state, the
shows the technical and geographical lay-out of the overall regulation may vary from 9-18 per cent at unity
primary system. The principal generating station is power factor to 15-6 per cent as a maximum. The
situated a considerable distance from the main load regulating devices should therefore be designed for the
centres, and the extra-high-voltage transmission system upper limit.
is operated in two main rings, apart from direct The relative effect of the several items depends to
feeders to other centres. The trunk feeders are normally a considerable extent on the power factor of the load,
loaded almost to full rating during times of maximum but for non-reactive loads that of the distribution net-
system load. Certain more-distant main substations work predominates. With reactive loads, the trans-
are fed from strategic points on the main rings through former regulation is most important.
relatively lightly-loaded feeders, so that the effective Regulating the voltage at the distribution-transformer
voltage-drops in the trunk feeders are not greatly secondary terminals between the limits of 100 and 104
dissimilar. per cent will, however, provide reasonably low variation
Transformers in the main substations may be operated on distribution networks, and only slightly coarser
regulation at power consumers' substations.
The effect due to variation of the length of secondary
feeder is not considerable. Taking four similar sub-
stations equally loaded and equidistant, supplied from
the same secondary feeder, the voltage-drops due to
length of cable will be in the proportion 4:7:9:10.

TABLE 1.

Voltage-drop percentage
Component
Resistance Reactance Impedance

33-kV feeder 1-43 117


Main transformer 0-70 4-80
6 • 6-kV secondary feeder 214 0-98
Distribution transformer 0-96 4-11

Total to this point .. 5-23 1106 12-23

Distributor, to constant-
voltage point 3-95 1-55
Scale of miles
FIG. 2.—Manchester area and 33-kV transmission lines. Total 918 12-61 15-60
Substations •
Generating stations •

in parallel, but normally supply independent secondary In no case will the drop deviate by more than 0-43 of
systems, in order to localize the extent of possible that calculated for the mean length, i.e. by more than
disturbances and to facilitate voltage regulation. 0-9 per cent. This is only 10 per cent of the total
Each secondary feeder supplies on the average four voltage variation to be compensated for, and is therefore
distribution or consumers' substations, except in the relatively unimportant. It can, moreover, be allowed
case of large converting and transforming substations, for in the majority of cases by slight adjustment of the
to which independent secondary feeders may be neces- basic voltage, i.e. by altering the distribution-trans-
sary. Facilities are provided for emergency supply former tapping so that the no-load voltage deviates
from alternative feeders. slightly from the declared value. In such cases the range
The distribution networks are normally isolated, with of local variation may exceed the ideal of 4 per cent
provision for the transfer of distributors to neighbouring whilst still remaining within the limits of 104 per cent
networks when required. Small local networks are and 96 per cent.
frequently built up around consumers' substations until The foregoing consideration shows clearly that, in
they are, sufficiently*, developed. to necessitate- separate many cases, extremely close voltage regulation on
distribution substations. distribution networks is attainable by the provision of
The average length of the main transmission lines is automatic voltage regulators at main substations, pro-
13 000 yards, of the secondary feeders to distribution vided that the regulators are suitably adjusted to give
substations 2 000 yards, and of main distributors 600 a voltage increasing in a predetermined manner with the
yards. • • . £ > * loaid, so as to compensate for the inherent?regulation of
-' Table 1 shows the approximate percentage resistance' the" system. '' »'
288 KIDD AND CARR: THE APPLICATION OF AUTOMATIC VOLTAGE AND

TYPICAL APPLICATIONS. early autumn on the secondary sides of the transformers


Where the main substation supplies one class of in an industrial area: (a) at the main substation, prior to
load, as, for example, (i) residential load, or (ii) indus- regulating; (b) at the main substation, after regulating;

c (a)
f-
0)
/ sC-' 7S'
co (b) '"

i.O U \i; ,]„;


Midnight Noon Midnig-ht
FIG. 3.—Voltage chart for industrial area in early autumn. Records taken on secondary side of transformers.
[a) Main substation, before regulating.
[b) Main substation, after regulating.
Distribution substation, after regulating.

(a)

N A <
J

Midnig-ht
FIG. 4.—^Voltage chart for industrial-area network supplied by distribution transformer C (Fig. 3).
Records taken about 225 yards from transformer.
a) Midwinter, before regulating.
b) Autumn, before regulating.
Autumn, after regulating.

(a)
™ 4
§ v '—.
.2 0

'Midnight Noon Midnight


FIG. 5.—Voltage chart for industrial-area remote distribution substation supplied from the main
substation of Fig. 3. Records taken on secondary side of transformer.
| ) Midwinter, before regulating.
6) Autumn, after regulating.
c) Midwinter, after regulating.

trial day load, with local street and shop lighting (c) at a distribution transformer, after regulating [same
at night, t&e regulating programme may be easily day as (6) ]. The direction of variations in (b) is almost th€
determined. tFfg1. 3 shows the voltage conditions in reverse of those in (a), and corresponds to load chatflge'lf'
SWITCH CONTROL TO ELECTRICAL DISTRIBUTION SYSTEMS. 289
The conditions on the distribution network supplied substation supplying a residential and suburban shopping
by the transformer referred to in Fig. 3(c) are shown district.
in Fig. 4: (a) during midwinter, before regulating; Where a mixed load is supplied, a careful survey of
(b) during autumn, before regulating; (c) during autumn, day and evening load conditions, including power factor,
after regulating. is necessary. By suitably adjusting the resistance and
The conditions on the low-voltage busbars at a more reactance components of the compensator, approxi-
distant distribution substation in the same area are mately constant-voltage conditions may be achieved in

'Midnight Noon Midnight


FIG. 6.—Voltage chart for residential area with large omnibus garage. Records taken on secondary
side of transformer, in November, after regulating.
(a)
a) Main substation.
(6)
6) Distribution substation (residential).
(c) Distribution substation (residential and shopping).'

shown in Fig. 5: (a) during midwinter, before regulating; the residential areas, with coarser regulation at power
(b) during autumn, after regulating; (c) during mid- consumers' substations.
winter, after regulating. The reduction of the amount It may be of interest to consider, in detail, the voltage-
of voltage variation is clearly shown by comparing drops in a particular area where a number of distribution
curves (a) and (c). substations supply (i) a residential district in an early
For a mainly residential area, the voltage variation stage of development, (ii) traction, (iii) industrial power,
during the latter part of November, after the installation and (iv) a local distributing authority with a mixed

259yards "f" 971yardi 1 10 11


2150 yards 1068 yards T "

1955yards

1714 yards.
1600yardl
2100yards

6186 yards

FIG. 7.—Diagram showing substations and secondary feeders in a mixed-load area.


Distribution transformers 6 600/400 volts (see Tables 2 and 3 referring to substations 1 to 9).

of automatic control, is shown in Fig. 6. The area residential and industrial load. The diagrammatic
serves also a large omnibus garage with considerable lay-out and feeder lengths are shown in Fig. 7. The
night heating-load, which is switched off at 2.30 a.m. effective voltage-drops for day load-conditions are given
The figure shows conditions: (a) at the main substation on in Table 2, and for evening load-conditions in Table 3.
the secondary side of the transformer, which is lightly For stations Nos. 2 to 5, distributor voltage-drops up
loaded; (b) at the low-voltage busbars in a distribution to 4 per cent may be allowed for, according to loading,
substation supplying a partially-developed residential as previously described.
district; (c) at the low-voltage busbars in a distribution The voltage conditions, after commissioning the
290 KIDD AND CARR: THE APPLICATION OF AUTOMATIC VOLTAGE AND

TABLE 2.

Section Voltage-drop percentage (day)

Trunk feeder 112


Main transformer 2-21

Total 3-33
Substation No. 1 2 3 4 5 6 7 8 9

Load Traction Resi- Resi- Resi- Resi- Institu- Textile Power Bulk
dential dential dential dential tional institute
Secondary feeders 0-92 0-17 1-24 0-75 0-75 0-04 1-61 1-94 2-32
Transformer 0-43 0-29 006 Neg. Neg. 1-00 2-69

Total secondary 0-92 0-60 1-53 0-81 0-75 0-04 2-51 4-63 —

Distributor — To be added — — — —

automatic regulators, and during the same day in tion network is shown in Fig. 10, (a) for an autumn
winter, are shown in Fig. 8:—(a) At the main substation day, before regulating; (b) for an autumn day, after
on the secondary side of the transformer; (b) at the low- regulating.
voltage busbars in a distribution substation (No. 2, In this area, therefore, despite considerable differences
Fig. 7) supplying residential load; (c) at the low-voltage in the lengths of secondary feeders, the variations of
busbars in a remote distribution substation (No. 11, voltage on the load sides of the distribution trans-

Midnight Noon Midnight


FIG. 8.—Voltage chart for the area of Fig. 7. Winter, after regulating, Records taken on
secondary side of transformer; all on same day.
o) Main substation.
b) Distribution substation No. 2.
c) Distribution substation No. 11.

Fig. 7) supplying a residential area composed of small formers do not show wide discrepancies, and conse-
houses. quently close regulation has been obtained at the low-
The conditions for other days in autumn are shown in voltage consumers' terminals in all parts of the district.
Fig. 9:—(a) At the main.substation, on the secondary The variation at the low-voltage terminals of high-
side of the transformer; (6) at the iow-voltage busbars voltage consumers' substations is rather greater than
in a power consumer's substation (No. 8, Fig. 7); (c) as that of the residential consumers, but it is within the
for (b), but before regulating. low-voltage distribution limit, and therefore very much
The voltage variation at a residential consumer's less than that permitted by the regulations for supply
premises remotely situated* on a neighbouring distribu- at high voltage.
SWITCH CONTROL TO ELECTRICAL DISTRIBUTION SYSTEMS. 291

TABLE 3.

Section Voltage-drop percentage (evening)

Trunk feeder 111


Main transformer 1-17

Total 2-28

Substation No. 1 2 3 4 5 6 7 8 9

Load Traction Resi- Resi- Resi- Resi- Institu- Textile Power Bulk
dential dential dential dential tional institute
Secondary feeders 0-58 0-26 0-94 0-60 . 0-60 0-06 117 1-36 1-58
Transformer 0-69 0-37 0-60 Neg. 1-32 0-79 1-53

Total secondary 0-58 0-95 1-31 1-20 0-60 1-38 1-96 2-89 —

Distributor — To be added — — — —

Midnight Noon Midnight


Voltage chart for the area of Fig. 7. Records taken on secondary side of transformer, in autumn.
Main substation, after regulating.
Power-consumer substation No. 8, after regulating.
Power-consumer substation No. 8, before regulating.

Midnight Noon Midnight


FIG. 10.—Voltage chart for residential consumer on remote part of network, supplied from
substation No. 2 (Fig. 7). Records taken in autumn.
Before regulating.
- After regulating (same dav as for Fig. 9).
292 KIDD AND CARR: THE APPLICATION OF AUTOMATIC VOLTAGE AND
EFFECTS OF VOLTAGE VARIATION. The variations shown are not so great as may be
As the distribution-substation output voltage is to be expected in certain other districts: an estimate of
increased by 4 per cent, and in addition the distribution system-loss change derived from these values is there-
transformer voltage-drop may vary from 1 per cent to fore on a conservative basis. The values are for
4 per cent according to local conditions, the high-voltage intermediate periods, and are therefore assumed to be
supply to transformers may require increasing by 8 per typical of the annual result.

150

/ \

130 y
t
./.**•——«-\. \ '
£ 120 A
\
.. ^ / \
110
\ J

^ ^

.' >^.
100
Midnight Noon Midnight
FIG. 11. —Distribution-transformer excitation variation before provision of automatic voltage regulation.
Reactive kVA.
Excitation loss.
Secondary volts.

cent. Distribution transformers should therefore be so For an installed rating of distribution transformer
designed that, at the upper limit of voltage, the magnetic amounting to 205 410 kVA, and taking an average
flux density is reasonably low; otherwise there is some excitation loss of 0-36 per cent, the decreased energy
danger of undesirable effects due to increased magnetizing loss, due to automatic regulating, amounts to 421 058
current. kWh per annum. In addition to this, a definite saving
The augmented lagging reactive kVA tends to increase is made in secondary transmission and distribution losses
the inherent regulation of the system, and so requires by operating at increased voltage during times of heavy

Noon Midnight
FIG. 12.—Distribution-transformer excitation variation after provision of automatic voltage regulation.
Reactive kVA.
- Excitation loss
Secondary volts.

more compensation; to some extent the effect is cumula- load. No attempt has so far been made to compute this
tive. Losses also increase, and finally the danger of additional saving.
giving rise to harmonics becomes more pronounced. Considering the effect on energy consumption, the
In order to estimate approximately the extent of these
effects, voltage records for one main substation have TABLE 4.
been plotted (Fig. 11) for an autumn weekday before
regulating and (Fig. 12) for a spring weekday after Average percentage
excitation values
regulating. The values have been expressed as a per- Item
centage of the rated voltage of distribution transformers: Before regulating After regulating
the corresponding values of reactive kVA and excita-
tion loss have been computed on a similar basis. Derived
average values over the 24 hours are shown in Table 4. Secondary voltage 104-3 101 6
The decrease in excitation loss is therefore 6-5 per Reactive kVA 120-7 106 3
cent of the loss at rated voltage: for week-ends and Excitation loss 1100 103 5
holidays the difference is greater.
SWITCH CONTROL TO ELECTRICAL DISTRIBUTION SYSTEMS. 293
provision of maximum voltage at times of maximum no harm in the event of an operation not being com-
load will result in the use of more energy at such times. pleted. In cases where this is not economically feasible,
In a recent American survey* it was computed that the the period of time between failure of operation and
overall increase in consumption due to giving normal damage to apparatus should not be less than 30 minutes.
voltage at all times would amount to little more than An automatic device should be fitted to give warning
1 per cent for the particular system considered. The in the control room. The operating staff can then deal
effect on revenue may, however, be appreciably greater
than this. The survey considered distributor drop only. Reactor Load
Resistor
Owing to the short period of operation, and to varying
trade conditions, representative particulars of augmented r-TJULP-T—* Load
consumption cannot be given, but there are indications
of appreciable increase.
The increase in revenue and the saving on distribution
expenditure will, in most cases, justify the installation
of automatic voltage-regulating equipment, which will
give better service to the public and will remove a cause Tapped Tapped
for complaint. winding (6) winding1
(a)
VOLTAGE-VARIATION EQUIPMENT. FIG. 13.—Tap-changers.
fa) Resistor method.
Types. (6) Reactor method.
The principal advantages of a.c. distribution in com-
parison with d.c. distribution systems are the lower with the matter, and, by transferring the load to other
capital cost and the smaller amount of attendance plant, ensure continuity of supply to consumers.
necessary. The question of stability of equipment during short-
Manual control of voltage, either direct or remote, circuit conditions is extremely important, and it should
would necessitate the uneconomic employment of addi- be noted that onerous conditions are not restricted to
tional labour, and the regulation so obtained would not large plant.
be entirely satisfactory. It therefore follows that the
control of voltage variation should be automatic. The Adaptation to Existing Plant.
following devices are available for this purpose: tap- The diagrams of three schemes for controlling the
changing transformers; booster transformers with tap- voltage variation of existing transformers are shown in
changers; induction regulators (including moving-coil Figs. 14, 15, and 16. Each arrangement consists of a
regulators). Each type will give satisfactory service, double-wound booster transformer with its secondary
and has its own particular field of application. winding connected in series with the main transformer.
For the addition of facilities for controlling voltage A regulating auto-transformer has automatically-
variation to existing plain transformers, the choice controlled tap-changing gear and the winding is con-
between tap-changing boosters and induction regulators nected in series with the primary winding of the booster,
depends upon local considerations and cost. If, for thus affording an easily controlled means of varying the
example, phase displacement is not permissible on amount of boost voltage.
account of parallel-operation requirements, then, if In the scheme shown in Fig. 14, one set of ends of the
induction regulators are installed, the double type booster primary-windings are connected to the middle
(i.e. two in series, the second to correct the phase dis- taps, so that the boost may be either positive or negative.
placement of the first) will have to be used, and the cost In Fig. 14 the regulating transformers are connected
will be substantially higher than for a tap-changing between phases and neutral, whilst in Fig. 16 they are
booster. between phases. The arrangement shown in Fig. 16
has been adopted for some of the larger transformers in
Tap-changers. preference to that shown in Fig. 15, on account of cost
Voltage variation by means of tap-changers necessi- only. The combination of regulating transformer and
tates voltage-steps, which should be small enough to switchgear is less expensive, mainly because the trans-
avoid causing any perceptible flicker of light. After former is about half the size of that required for the
careful consideration it has been decided that steps of arrangement shown in Fig. 15, in which each half-winding
1*5 per cent are reasonable, and this value has been must give full boost.
adopted as a standard.
Several arrangements of tap-changers are in use; the Automatic Control.
diagrams of connections of two types of equipments are A scheme for automatic control is shown in Fig. 17.
shown in Fig. 13. The principles embodied in this system are similar to
An advantage claimed for the resistor method is that those of many other arrangements in use. The diagram
the circuit to be broken is non-inductive, and there is has, as far as possible, been made " single-line "; wiring
therefore less wear of switch contacts; also that the for the " lower voltage " operation, and also a consider-
ciaorrent is interrupted during the first half-cycle, whereas able number of details, have been omitted. A v&tiasge
ike period is usually greater with the reactor method. relay (1) is fed from a voltage transformer eorJfle'<£ted;
Tap-changing equipments should be designed to take to tile outgoing circuit. As- the voltage" applied to the
* Electrical World, 1932, vol. 100, p. 858.
relay either rises above or falls below a,
294 KIDD AND CARR: THE APPLICATION OF AUTOMATIC VOLTAGE AND

figure, the relay makes contact at either K or Kl, and drop. A current transformer C.T.5 feeds an auxiliary
initiates the tap-changer operation in the direction to transformer A.C.T., the secondary of which supplies in
adjust the voltage in the outgoing circuit. The voltage series a variable resistor (3) and a variable reactor (4) in
at which the relay operates can be adjusted within the compensator. By suitable and independent adjust-
certain limits by means of the variable resistor (2). ment of (3) and (4) the voltage-drop across the coin-
Booster
Main transformer
secondary transformer

Load

Auto star
regulator transformer
with tap-chang-er
and resistor

FIG. 14.—Booster with resistor tap-changer.

Main transformer Booster


secondary transformer
fflfflorrntm .

Load

Regulator transformer,
tap-changer, and
reactor

FIG. 15.—Booster with reactor tap-changer.


Main transformer
secondary

•• Load

flJfiTI WT\ WT\ Booster


L_ J | transform

Regulator transformer
and tap-changer

FIG. 16.—Booster with tap-changer.

Constant voltage, however, is not wanted at the bination may be made directly proportional to, and of
beginning of the outgoing circuit. The desideratum is the same phase as, that in the main outgoing circuit.
to maintain the consumer's service voltage within the The compensator is connected in series with the
statutory limits of variation. This can only be done secondary of the voltage transformer (17), so that the
by compensating for both cable and transformer voltage- voltage applied to the relay (1) is exactly, proportional
SWITCH CONTROL TO ELECTRICAL DISTRIBUTION SYSTEMS. 295
to the desired voltage at the service terminals, where If the incoming high-voltage supply fails, means are
consequently the required voltage will be maintained provided to prevent the equipment operating itself into
irrespective of load variation and power factor. Alter- the highest boost position. A no-voltage relay (16) is fed
natively, the voltage can be arranged to vary within from the voltage transformer (17), and opens the relay-
certain limits at a selected point on the system. equipment circuit if the high-voltage supply fails. The
Change of load will result in a change of impressed tap-changer may, however, still be remote electrically-
voltage, via the voltage and current transformers and controlled by using the push-button switches (18) on
also the compensating device, on the relay coil (1), the control panel. Devices are included to ensure that
which will cause contact to be made at either K or K l the tap-changer can only move one step for each operation
(Fig. 17). A circuit is then completed from phase R, of the push-button.
via contact (13), travel limit switch (14), time-delay relay It is obviously undesirable to have the equipment
coil (6), no-volt relay contact (16), overload relay contact continually operating due to momentary fluctuations of
(10), and motor overload relay contact (9), to phase W. voltage, and too-frequent operation has been a cause
After the expiration of the time-delay period, relay (6) of trouble on some early-designed equipments. After
operates and completes the following circuit: phase R, examination of voltage records on the unregulated
contacts (13) and (14), coil of relay (7), contacts (6), system, it was decided to specify the installation of
(16), (10), and (9), to phase W. This causes relay (7) to adjustable time-delay devices (6) having a range of
operate and complete a circuit from phase R, motor 0-90 sec. Tap-change counters are also fitted to enable
overload relay coil (9), contacts (7), (14), and (13), to the a record of the number of operations to be kept.
motor. The motor starts and rotates the flywheel up
Voltage Regulators on Low-voltage Distribution Systems.
CT.15, CT.5 In some exceptional cases it may be found necessary
Load to install automatic control equipment on the low-voltage
distribution system. Various types of apparatus suitable
VT.17 for this purpose have been designed and are commer-
cially available.

SUPERVISORY CONTROL.

General Considerations.
The small number of circuit breakers and the infre-
quency of switch operation in the distribution substations
render it unnecessary to provide either attendance or
remote control.
A.C.T. The main substations, which contain switchgear for a
larger number of feeders and deal with the supply for
PhaseR comparatively large areas, present a different case; here
FIG. 17.—Automatic control of voltage. it is desirable that facilities should exist for:—
Closed for automatic control. (1) More frequent operation of switchgear.
Closed for manual control.
(2) Immediate notice of circuit-breaker operation by
to a speed which causes the centrifugal switch (11) to protective gear; also of transient earth faults.
close and allow current to flow through contactor (3) Quick resumption of supply after a failure.
coil (12); this causes two contacts of (13) to open, thus (4) Obtaining records of feeder loads and voltage.
disconnecting the motor and relay equipment from the It is uneconomical, and bad psychologically, to have
supply. attendants in transformer substations where there is
Simultaneously, mechanical connection is made, by only a small amount of work to be done.
means of a centrifugal clutch, between the flywheel shaft Experience indicates that the installation of super-
and the tap-changer gear. Failure of the motor supply visory control gear is the best solution; further, it enables
does not interrupt an operation after commencement of the control of the system to be centralized.
movement of the contacts. Several types of supervisory gear, using either
After the tap-changer has completed one sequence of synchronously-rotated apparatus or equipment for
operations, the flywheel shaft and motor are disconnected transmitting electrical impulses over telephone lines, are
from the changer gear. Overrunning of the gear is available; impulsing may be done either by voice-
prevented by limit switches (14). frequency current or by direct current. The last-named
Each change of tap is automatically shown on the tap- type of gear has been installed on the system dealt with
position indicator. in this paper in main substations which contain a total
The booster should not operate during periods of of 125 circuit breakers. At present there are two control
short-circuit on the outgoing circuit, otherwise abnormal centres, but ultimately there will be only one.
stresses would occur in the equipment. Two instanta- Two types of equipment are in use; the control panels
neous overload relays (10) are fed from separate current- are similar, the difference being mainly in the impulsing
transformers (15), and in the event of short-circuit arrangements. In one type, magnetic ratchet multi-
disconnect the supply from the relay equipment. point rotary switches and relays are used. A full
296 KIDD AND CARR: THE APPLICATION OF AUTOMATIC VOLTAGE AND

description of these has already been published. The direction, and, if everything is in order, the lighting of
following particulars relate to the second type, which is a white lamp adjacent to the key indicates that the
shown diagrammatically in Fig. 18. master control-button should now be pressed to operate
the breaker. The illumination of the associated coloured
Duty. lamps is automatically altered to correspond with the
The supervisory gear enables the substations to be new state of the breaker. The key on the diagram is
remotely controlled and fulfils the following require- then restored to normal.
ments. (1) Two control switches must be moved before A breaker, when opened automatically by the protec-
any circuit-breaker operation can be completed, and an tive gear, alters the coloured lamps to correspond, and
intermediate signal is to be automatically given if the attracts the engineer's attention to the board by an
circuit has been correctly selected. (2) Automatic audible signal and to the particular breaker by flashing
warning of any change of state of all circuit breakers. its coloured lamps. These signals are stopped by
(3) Automatic and continuous indication of the state of operation of the reset key.
all circuit breakers. (4) Automatic warning of current- After the switchgear has been out of commission, the
flow through the neutral earthing resistance, even when indicators and switchgear are brought into correct
the current is insufficient to operate the neutral circuit relationship again by the operation of the check key,

Meter iCheckind. ?.'^7r" I link


circuit 5 l lnc ?ication| ,- , .
circuit • circuit I circuit I circuit
. .,

J Ammeter. 12. S/S alarm buzzers.


2. Voltmeter. Control 13. C/S fuse alarm
8. Lamps. lamps.
4. Selector key.
station 14. C/S switch alarm
6. Alarm bell. lamps.
6. Red lamps. 15. Master operating
7. Green lamps. button.
8. Reply lamps 16. Code receiver.
9. S/S fuse alarm 17. Code sender.
lamps. 18. O.C.B. operating
10. S/S alarm reset key. circuit.
11. Impulse lamps. 19. O.C.B. auxiliary
contacts.
20. Earth-fault alarm.
21. Meter transformers.
22. Reset key.
S. Supervisory gear.

i Substation

FIG. 18.—Supervisory control circuits.

breaker. (5) Automatic warning when any supervisory- which causes each breaker to send its indication code,
gear fuse blows. (6) The indication of voltage and and sets the coloured lamps to correspond.
current measurements must be continuous for as long The equipment in each substation is divided into
a period as the operator wishes. groups, according to voltage, for checking, and each
The indicators for isolating switches shown in Fig. 18 group has its own check key.
are hand-operated. All supervisory circuits are electric-
ally separate from the circuit-breaker solenoid circuits, General Principles.
and batteries are used for supplying current to the Each operation is performed by the transmission over
supervisory switch circuits. The network a.c. supply telephone wires of an allocated code of electrical impulses
is employed for the indicating lamps, but an automatic which are made by connecting a battery to the line and
change-over switch is provided, so that the battery may interrupting it at a predetermined frequency. Each
be used for the indicators when the network supply is code is composed of 4 digits, and each digit consists of
not available. Existing telephone conductors are used from 1 to 8 impulses, transmitted at a uniform speed.
for connection between substations. The sum of the impulses for the 4 digits in each code
is 16 (for different installations other numbers may be
Operation. more suitable).
The equipment on the control board consists of a The receiving circuits are arranged to be ineffective
diagram of connections of each substation, with keys and if the total of the impulses received for any code is
coloured lamps to show the state (open or closed) of the different from 16. Thus, for any code to be received
circuit breakers. When it is desired to operate a wrongly and yet to be effective, any error in counting
breaker, the appropriate key is moved in the required the impulses for one digit must be accompanied by an
SWITCH CONTROL TO ELECTRICAL DISTRIBUTION SYSTEMS. 297

equal and opposite error in counting for another digit— Thus a number of independent circuits require the
an exceptionally remote possibility. control of the sender, and a link circuit is provided to.
The route for each intended operation is automatically ensure that, if a number of breakers operate simultane-
established, and the setting checked; then by means of ously, they shall engage the sender one at a time. For
the reply code a lamp is lighted on the control panel. this purpose a sequence switch is used as a " searcher "
The-master control-button, common to all main circuits switch. Each breaker has a relay coupling-circuit, and
on the board, can only cause the main contactor to is associated with one position of the " searcher " switch.
operate and complete the operation when this lamp is The relay coupling-circuit drives the switch round to
alight. the corresponding position, where the switch starts the
The selecting mechanism at the substation then sender, at the same time marking the required shading
returns to normal and permits the circuit-breaker segments. When the code has gone, the " searcher "
indication to be transmitted from the breaker auxiliary switch resets the coupling circuit and is driven home.
contacts to the control panel. This, being independent If a number of coupling circuits are operated, the
of the previous operation, is an important check. " searcher " switch will visit each in turn, and all the
codes will be sent one at a time.
Code Sending. The same device is used on the control keys, where the
A motor-driven, multi-circuit sequence switch is used " searcher " switch, in addition, provides means either
to send the codes, for which purpose it makes one for checking the selection indication codes or for routing
complete revolution. There are 16 impulses in each the meter pilot to the required instruments.
code, and the 3 inter-digital pauses are each equal to the
duration of 6 impulses, giving the time of an extra 18 Metering.
impulses. The switch is fitted with a cam giving 34 A separate pair of telephone wires is used (in the most
interruptions (or impulses) and 24 shading segments, recent installation only one pair of wires is employed for
each covering 6 of these impulses. The first segment both operation and metering) to connect an instrument
covers impulses 2-7, the second 3-8, and so on, and all on the control board to an instrument transformer in
are electrically connected to the interrupter cam. Thus, the controlled station.
when the battery is connected to the interrupter cam Since the line has an appreciable resistance, it is
and to a chosen three of the shading segments, a 4-digit necessary to employ metering currents of the order of
code of 16 impulses will be obtained from the common 100 milliamperes, and therefore to provide each circuit
connection to the cams, the impulses being due to the with an auxiliary instrument transformer.
interrupter cam and the inter-digital pauses to the The operation of the meter request-key selects the
shading segments in parallel with the interrupter cam. appropriate indicating instrument, and sets the routing
Code Receiving. to the required transformer as for a circuit-breaker
control, and the master operating-button makes the
The codes are counted by a train of relays which final connection.
mark out the digit on a routing sequence switch, causing Circuit-breaker control and indication operations may
the switch to be driven as many positions from its normal proceed whilst the meter is indicating.
position as there are impulses in the digit. Three The auxiliary current-transformers are connected in
routing switches are set by the first three digits of a code, series with the 5-ampere metering circuits, and are short-
and, in addition, a totalling switch is set according to circuited when not in use for remote metering because
the impulses received in all three digits. The fourth considerable impedance in their secondary circuits affects
digit checks the total, because each counting relay is the reading of instruments connected in their primary
associated with one position of the totalling switch, and circuits. With the secondary on open circuit a dangerous
only if the counting relays and totalling switch correspond voltage would occur across the secondary terminals; and,
is the code effective. to guard against this effect arising accidentally, each
The routing is effected by interconnection between the current transformer has a neon lamp connected across
routing switches, by which a single wire going to the first its secondary terminals. During a reading, the secondary
switch is connected to one of the total number of wires voltage is less than that necessary to start the neon
connecting the third switch to the control or indicating discharge, and the lamp imposes no shunt on the
circuits. At the control switch the routing is immedi- metering circuit. On open circuit the voltage rises until
ately effective and sets one of the lamp-indicating relays, the lamp discharge takes place, and then the burden of
but at the distant station the routing established connects the lamp prevents any further increase.
a master contactor to a particular operating solenoid.
The routing switches here also mark shading segments ACKNOWLEDGMENTS.
on the sender, and cause a code depending on then-
setting to be transmitted. This code informs the The authors wish to thank Mr. H. C. Lamb, chief
operator of correct selection, and allows operation of the engineer and manager, for his permission to give par-
master contactor to complete the circuit. ticulars of the Manchester Corporation electric supply
A further switch is used to perform inter-digital system; also the Automatic Electric Co., Ltd., the
switching and timing, thus eliminating relays. English Electric Co., Ltd., Ferranti, Ltd., the Fuller
Electrical and Manufacturing Co., Ltd., the Metro-
Link Circuits. politan- Vickers Electrical Co., Ltd., and Standard
Indications of whether circuit breakers are open or Telephones and Cables, Ltd., for information regarding
closed are given by sending a code for each position. their equipment.

Você também pode gostar